5s - Rapid_improve

download 5s - Rapid_improve

of 20

Transcript of 5s - Rapid_improve

  • 7/30/2019 5s - Rapid_improve

    1/20

    Puget Sound Naval ShipyardCircuit Breaker Repair Shop

    Rapid Improvement Workshop

    October 29 to

    November 2, 2001

    Before Situation Measures

    Key Measures

    Usable Floor Space 1,710 Square Feet

    Mechanic Walking Distance 12,552 ft (2.4 Miles)

    Lead Time Average is 175 days

    Dissatisfied Customers

    Frustrated Mechanics

    High Overtime rate

    Status of WIP not readily available

  • 7/30/2019 5s - Rapid_improve

    2/20

    Monday, October 29

    Team Introductions 8 Person Team

    Representatives from Production, Engineering, Supply, Business Office

    Lean Manufacturing Training Introduction

    Waste Elimination Concepts

    Visual Management Concepts

    5-S Process

    Approach to Lean Workshop

    Identify Specific Goals

    Waste Walk Identified 30 items

    Circuit Breaker Repair Shop R.I.W. Team

    Dwight Otis - Team Leader Sr. Process Manager

    Grant Clark - Co-Leader SY Process Improvement Division

    Evan DeWan Shop 11 General Foreman

    Jim Doyle Engineering Technician

    Bob McDonald Business Agent

    Dr. Chris Murphy Surgeon (Mechanic) Rick Tift Material Manager

    John Von Rotz Shop 51 Foreman

    Kurt Knoth Sr. Lean Consultant Optiprise, Inc.

  • 7/30/2019 5s - Rapid_improve

    3/20

    Summary of Tools Used

    Waste Walk 5-S

    Visual Management

    Brainstorming

    Value Stream Mapping

    Just Do It

    Specific Goals of Workshop

    Improve Safety

    Improve 5S Identified 80 tagged items

    Goal is to Address 40 items

    Reduce Mechanic Walk Distance by 90%

    Improve Lead Time by 40%

    Improve floor space utilization

    Reduce part travel distance by 50%

    Provide Visual Controls

  • 7/30/2019 5s - Rapid_improve

    4/20

    Tuesday, October 30

    Data Gathering

    Existing Flow (floor space, part travel, walk distance)

    5-S Survey

    Began Discussion of New Flow for Area

    Began 5-S (Tagging for Sort)

    Tagged 80 items for sort

    Began removal of unnecessary items

    Before Layout

  • 7/30/2019 5s - Rapid_improve

    5/20

    BreakerFlow Diagram

    Spaghetti Diagram

    12,552 ft

  • 7/30/2019 5s - Rapid_improve

    6/20

    Before Situation

    Before Situation

  • 7/30/2019 5s - Rapid_improve

    7/20

    Before Situation

    Before Situation

  • 7/30/2019 5s - Rapid_improve

    8/20

    Wednesday, October 31

    Continued 5-S Removed Tagged Items

    ) Disposed of Obsolete Materials and Equipment

    Cleaned Floor and Began Straightening

    New Layout Cleaned Floor

    Moved workbenches

    Moved storage bins

    Value Stream Map Created current Value Stream Map

    Management Presentation Presented Plan of Action

    Layout AfterU P

    S h i p / R e c M a n

    T e s t B e n c h ( T B )

    P o w e r P a n e l ( P P )

    P P

    P P

    P P

    P P

    T e s t S t a n d

    ( T S )

    T S

    WorkBench(WB)

    P a r t s

    V i c e

    W B

    F i l e s

    T e s t A d a p t e r s

    WIP/AW

    PS t a t u s B o a r dP a r t s

    P a r t s

    WorkBench

    T S

    T S

    T E

    T e s t

    E q u i p ( T / E )

    T / E

    T / E

    T / E

    F i r e E x .

    C r a n e

    C r a n e

    C r a n e

    T / E

    C o a t R a c k

    I n c o m i n g W o r k

    S t o r a g e

    S t o r a g e

    Storage

    M i c r o w a v e

    T a b l e

    F r i d g e

    P a l le t

    P a l le t

    P a l le tP a l le t

    P a l le t

    P a l le t

    E q u i pE q u i pE q u i pE q u i p

    H a z m a t L o c k e r

    V a c u u m

    I N / O U T

  • 7/30/2019 5s - Rapid_improve

    9/20

    In-Process Picture

    In-Process Picture

  • 7/30/2019 5s - Rapid_improve

    10/20

    In-Process Pictures

    Customer

    50 Breakers / Yr

    RFI

    Inventory

    Repair Lead

    Time= 155days

    Value Added

    Time= 84.5 hrs

    Takt Time = 1 Week

    Circuit Breaker Repair "Simplified" Value Stream Map - Current

    Time = 1 hr

    139 Inspect

    Time = 1 hr

    Pack / Ship

    Time = 16 hrs

    Appendix B

    Time = 2 hrs

    Appendix A

    Time = 1 hr

    Ship to Shop

    Time = 2 hrs

    Rec/ Inspect

    Supplier

    (Customer)

    34.5 Hrs 2 Days 16 Hrs 1 Hr 1 Hr 2 Hr

    2 Days2 Days3 Days2 Days10 to 100 days

    Time = 2 hrs

    Packaging

    Time = 2 hr

    Shop Inspect

    Time = 2 days

    Reliability

    Time = 34.5 hrs

    Repair

    Time = 8 hrs

    Order Parts

    Waiting for Parts

    Time = 1hr

    RIDL

    This loop happens up to

    9 times per Breaker

    Waiting for Paperwork

    2 to 15 Days3 Days

    2 Hrs

    W

    ait

    Wait

    Wait

    Wait

    Wait

    Wait

    Wait

    Wait

    Wait

    Wait

    Wait

    8 Hrs

    Up t o 30 Days

    2 Hr

    Waiting for Tech. Code

    Waiting for Shop

    Value Stream Map - Existing

  • 7/30/2019 5s - Rapid_improve

    11/20

    Thursday, November 1

    Continued 5-S Continued the Disposal of Obsolete Materials and Equipment

    Created Storage Areas

    Labeled Everything That Didnt Move!

    New Layout Established Aisle ways and Work Areas

    Completed WIP Storage Racks

    Moved Storage Bins

    Completed Visual Management Board

    Value Stream Map Created To-Be Value Stream Map

    Management Presentation Prepared for Friday Morning Report Out

    Before Picture After Picture

  • 7/30/2019 5s - Rapid_improve

    12/20

    After Picture

    After Picture

  • 7/30/2019 5s - Rapid_improve

    13/20

    Before Picture After Picture

    Before Picture After PictureHow are we doing?

    Status

    Color In Stock list

    Cos

    Status is Color-Coded:

    Red = Stopped

    Green = Working

  • 7/30/2019 5s - Rapid_improve

    14/20

    After Picture

    After Picture

  • 7/30/2019 5s - Rapid_improve

    15/20

    After Breaker Flow

    Total Travel Before: 513Ft.

    Total Travel After: 410Ft.

    Goal Reduction: 50%Actual Reduction: 20%

    After Mechanic Walking

    Total Travel Before: 12,552Ft.

    Total Travel After: 2,385Ft.

    Goal Reduction: 90%

    Actual Reduction: 81%

  • 7/30/2019 5s - Rapid_improve

    16/20

    Status Board

    5S

    Status is Color-Coded:

    Red = Stopped

    Green = Working

    Cost

    In-Stock

    Customer

    50 Breakers / Yr

    RFI

    Inventory

    Repair Lead

    Time= 8.5 days

    Value Added

    Time= 57.5 hrs

    Takt Time = 1 Week

    Circuit Breaker Repair "Simplified" Value Stream Map - Future State

    Make "Dirty 30"

    Parts Avaiilable to

    Mechanic

    Time = 1 hr

    139 Inspect

    Time = 1 hr

    Pack / Ship

    Time = 16 hrs

    Appendix B

    Time = 34.5 hrs

    Repair

    Time = 4 hrs

    Appendix A

    Time = 1 hr

    Ship to Shop

    Time = 2 hrs

    Rec / Inspect

    Supplier

    (Customer)

    3 Hrs 4 Hrs 34.5 Hrs 16 Hrs 1 Hr 1 Hr 2 Hr

    1 Hr1 Hr1 Hr1 Hr1 Hr1 Hr

    Time = 2 hrs

    Packaging

    Change Sign-Off

    Proceedures

    Change in RIDL

    Documentation

    Procedure

  • 7/30/2019 5s - Rapid_improve

    17/20

    30 Day Homework ListProblem / Improvement Target Completion

    Opportunity (Solution) Date Date

    Circuit Breaker Crates are stored in area that could be

    utilized for other storage. Code 500 store crates in Bldg. 856 11/2/2001 10/31/2001

    Phone is away from mechanic work area. Move or relocate phone 11/9/2001

    Numerous Vidmar's used for storage Consolidate Vidmar's 11/9/2001

    "Strategic Assets" of Material i n Vidmars Indoctrinate material into Supply System 11/09/01

    Project Target Motors being worked in same area Revi ew work in area/move mot or work to new l oc at ion. 10/ 31/ 01 10/ 31/ 01

    "Waiting" Breakers are stored in work/test area

    Design/build storage rack for breakers waiting on

    material/technical resolution 11/01/01 10/31/01

    Storage room (front entrance) being utilized as a

    lunchroom facility. Modi fy arangement /propos e move to another area 12/ 07/ 01

    Movement of breakers from 856 to 427 utilizing single

    crate is cumbersome.

    Propose a design that allows shipment of mulitple breakers

    in a one box. 12/07/01

    Identifying status of work Develop visual management board 11/01/01 11/01/01

    Storage of miscellaneous parts of "waiting" breakers Develop/utilize method to store and identify parts 11/01/01 11/01/01

    AC Test Machine broken Rem oved from room . One t es t m ac hi ne handl es work load . 10/ 31/ 01 1 0/ 31/ 01

    Common "shop store" material is not close to

    mechanic (30 Most Wanted list)

    Work with Vendor/supply to provide the material to

    mechanic 12/07/01

    Storage of tooling/ma terial i s stored in vario us spotsin room Design new floor arrangement 10/31/01 10/31/01

    Flam locker not located close to work Review location/add new flam locker 12/07/01

    Mechanic travel time/distance to Bldg. 856 numerous

    times (RIDL processing, Official Copy)

    Developed method to document RIDL and return officials to

    Code 139 for certification 11/02/01 11/01/01

    Comments

    Add phone line -in progress

    Shop 51 Action: Consolidate vidmars

    Shop 51/Code 500: Turn material into supply

    Shop 51 Action: Determine suitable replacement

    Shop 51/Code 2330: Review/design

    Code 500: May need outside help

    Shop 51: Perform Cost Analysis for adding locker

    30 Day Homework List (Continued)

    16 Getting approval to complete all testing Simplify process with Code 2330 12/07/01

    17 Assign a cost to "waiting". Reduce Lead Time . Analyze all improvements 12/07/01

    18 Who controls "status" Cog GF coordinate and update visual management board 11/01/01 11/02/01

    19 Central vacuum cleaner doesnot work Put in repair ticket 12/07/01

    20 All workersin bldg not aware of changes Present process to entire shop 11/09/01

    21 Mechanic tooling not well organized Use 5S process to improve performance 12/07/01

    22 Wood shelf on new storage area breaks down Get different material to use for shelving 12/07/01

    23 Need to keep room in present condition Develop 5S audit sheet 11/01/01 11/01/01

    24 Room reorganized with temp marking Paint permanent lines 12/07/01

    25 Amount of breakers allowed in facility (20 limit)

    Review improvements to work area to see if limit c an be

    raised 12/07/01

    Code 2330 action: May need outside help

    Shop 51 action: Review work in progress

    Shop 51 action

    Shop 51 action

    Shop 51 action

    Shop 51 action

    Shop 51 action

    Shop 51 action

  • 7/30/2019 5s - Rapid_improve

    18/20

    Results Safety

    Reduced Clutter

    Removed Shock Hazard (Broken Test Equipment)

    Improved 5S

    Identified 80 tagged items

    Completed 65 items

    Reduced Mechanic Walk Distance by 81%

    Lead Time Will be Reduced by 90+%

    Improved Floor Space Utilization by 20%

    Reduced Part Travel Distance by 20%

    Provide Visual Controls

    There is a place for everything and everything is in its place

    Results

    Improved Customer Satisfaction

    Employee Ownership

    Reduced Overtime

    Increasing Breaker Output Better Organization of Work area

    Better Working Conditions for Mechanics

  • 7/30/2019 5s - Rapid_improve

    19/20

    Value Added Time (Days) 10.5 10.5

    Wait Time (NVA) 144.5 80*

    Repair Lead Time = 155 days 93 days*

    Useable Floor Space (SF) 1,710 2,052

    Walking Travel Distance (Feet) 12,552 2,385

    Part Travel Distance (Feet) 513 410

    * Calculated from breaker deliveries since 11-16-01

    Original State Current State

    Results

    Value Added Time (Days) 10.5 10.5 0%

    Wait Time (NVA) 144.5 1 99%

    Repair Lead Time = 155 days 8.5 days 90+%

    Useable Floor Space (SF) 1,710 2,052 20%

    Walking Travel Distance (Feet) 12,552 2,385 81%Part Travel Distance (Feet) 513 410 20%

    Safety

    Improved 5S

    Provide Visual Controls

    Current State Future State

    Potential

    Improvement

    Results

  • 7/30/2019 5s - Rapid_improve

    20/20

    The Dream Team

    Questions