5.Energy Audit of CW System.ppt

download 5.Energy Audit of  CW System.ppt

of 39

Transcript of 5.Energy Audit of CW System.ppt

  • 7/28/2019 5.Energy Audit of CW System.ppt

    1/39

    ENERGY AUDIT OF CONDENSER AND

    CONDENSER COOLING WATER

    SYSTEM

    Presented ByM.V.Pande

    Dy.Director

    NPTI, Nagpur

  • 7/28/2019 5.Energy Audit of CW System.ppt

    2/39

    Background

    Condenser:The condenser is the most important component of the turbine cycle that

    affects the turbine heat rate. The function of the condenser is to

    condense exhaust steam from the steam turbine by rejecting the heat of

    evaporation to the cooling water passing through the condenser.

    Generally, twin shell- double pass- surface type condensers areemployed for higher capacity units

    CW Pump

    Hot Water

    Condenser

    Cooled

    Water

    Cooling

    Tower AirAir

    Make-up

    Water

    Hot

    Water

  • 7/28/2019 5.Energy Audit of CW System.ppt

    3/39

    Background

    Cooling towers:

    Different types of

    cooling towers are

    used in the power

    plants depending upon

    the location, size,

    infrastructure andwater resources etc.

    Close cycle wet

    cooling systems:

    -Induced draft

    -Forced draft

    - Natural draftcooling

    towers

  • 7/28/2019 5.Energy Audit of CW System.ppt

    4/39

    Background

    Cooling water pumps:

    Circulating water pumps supply cooling water at therequired flow rate and pressure to the power plant

    condenser and the plant auxiliary cooling water heat

    exchangers. These pumps are required to operate

    economically and reliably over the life of the plant.

    For once through systems, vertical wet pit pumps are in

    common usage.

    For re-circulating cooling systems, vertical wet pit and

    horizontal dry pit are used about equally, with occasional

    use of vertical dry pit pumps.

  • 7/28/2019 5.Energy Audit of CW System.ppt

    5/39

    Specifications of Typical Cooling Water Pump

  • 7/28/2019 5.Energy Audit of CW System.ppt

    6/39

    Steps Involved in Energy Audit

    The major energy consuming equipments in the CW

    systems are:

    Cooling towers and fans

    Cooling water pumps

    Make up water pumps

    Condensers

    The steps involved in conducting energy audit of cooling

    water and cooling tower are:

    Data collection Observations and Analysis

    Exploration for energy conservation measures

    Report preparation

  • 7/28/2019 5.Energy Audit of CW System.ppt

    7/39

    Data Collection

    Specifications of cooling towers:

  • 7/28/2019 5.Energy Audit of CW System.ppt

    8/39

    Data Collection

    Specifications of cooling towers- contd:

  • 7/28/2019 5.Energy Audit of CW System.ppt

    9/39

    Specification of water pumps and motors:

    Specification of water pumps and motors

  • 7/28/2019 5.Energy Audit of CW System.ppt

    10/39

    Specification of water pumps and motors- contd:

    Data Collection

    Rated kW of the pump

  • 7/28/2019 5.Energy Audit of CW System.ppt

    11/39

    Data Collection- Other Information

    Performance characteristics of all pumps and motors

    Compile design, P. G. Test, previous best and last energy

    audit value with respect to cooling tower and cooling water

    system along with the condensers

    If the pumps are operated in parallel then it is advised to

    collect the performance curve for the parallel operation

    Schematic diagram of Water pumping network (which

    depict the source, pumps in operation & stand by, line sizes

    and users)

    Water and pressure equipments at the users as per the

    design requirements

    Brief description of the system with the key specifications in

    which pumps are used (for example, if pumps are used for

    supplying water to condenser, then add a brief write up

    about the cooling water system)

  • 7/28/2019 5.Energy Audit of CW System.ppt

    12/39

    Data Collection- Condenser Specifications

    Heat load considered for design

    Design inlet cooling water temperature/ Design TTD

    Cleanliness factor/ Cooling water temperature raise

    Condenser back pressure

    Cooling water flow/ Cooling water side pressure drop

    No of cooling water pass/ Total heat transfer area

    No. of tubes - Condensing zone - Air cooling zone

    Tube dimensions: - Tube OD x thickness - Length of

    tube

    Tube material: - Condensing zone - Air cooling zone

    Water box design pressure

  • 7/28/2019 5.Energy Audit of CW System.ppt

    13/39

    Instruments Required

    Power Analyzer: Used for measuring electricalparameters of motors such as kW, kVA, pf, V, A andHz

    Temperature Indicator & Probe

    Pressure Gauge: To measure operating pressureand pressure drop in the system

    Stroboscope: To measure the speed of the drivenequipment and motor

    Ultra sonic flow meter or online flow meter

    Sling hygrometer or digital hygrometer Anemometer

    In addition to the above calibrated online instrumentscan be used

    PH meter

  • 7/28/2019 5.Energy Audit of CW System.ppt

    14/39

    Measurements & Observation Energy consumption pattern of pumps and cooling tower

    fans

    Motor electrical parameters (kW, kVA, Pf, A, V, Hz, THD)for pumps and cooling tower fans

    Pump operating parameters to be measured/monitored foreach pump are: - Discharge, - Head (suction & discharge) -

    Valve position Temperature - Load variation, Powerparameters of pumps - Pumps operating hours andoperating schedule

    Pressure drop in the system (between discharge and userpoint)

    Pressure drop and temperatures across the users (heatexchangers, condensers, etc)

    Cooling water flow rate to users - Pump /Motor speed

    Actual pressure at the user end

    User area pressure of operation and requirement

  • 7/28/2019 5.Energy Audit of CW System.ppt

    15/39

    Measurements & Observation

    Cooling tower parameters to be monitored

    Inlet temperature

    Outlet temperature

    Dry bulb temperature

    Wet bulb temperature or relative humidity

    Water flow to cooling towerAir flow rate of cooling tower

    Range, oC

    L/G ratio

    Approach, oC

    Fan speed, rpm

    Fan power consumption (kW/cell)

  • 7/28/2019 5.Energy Audit of CW System.ppt

    16/39

    Observations and Analysis

    System familiarization and operational details

    Energy consumption Pattern

    The energy consumption of cooling water : kWh/day and

    associated system

    Total auxiliary power consumption : kWh/Day

    O ti Effi i d P f

  • 7/28/2019 5.Energy Audit of CW System.ppt

    17/39

    Operating Efficiency and Performance

    Evaluation of the Pumps

    Water flow rate and pressure of pumps / headers

    Velocity in the main headers and pumps and major lines (to

    verify adequacy of line sizes)

    Power consumption of pumps (for estimating the operating

    efficiency of the pumps) Monitor present flow control system and frequency of

    control valve variation if any (for application of variable

    speed drives)

    Fill up the following data sheet for every pump forcomparison with the design / PG test values

    Operating Efficiency and Performance

  • 7/28/2019 5.Energy Audit of CW System.ppt

    18/39

    Operating Efficiency and Performance

    Evaluation of the Pumps

    Operating Efficiency and Performance

  • 7/28/2019 5.Energy Audit of CW System.ppt

    19/39

    Operating Efficiency and Performance

    Evaluation of the Pumps

  • 7/28/2019 5.Energy Audit of CW System.ppt

    20/39

    Investigations & Recommendations Compare the actual values with the design / performance

    test values if any deviation is found, investigate for the

    contributing factors and arrive at appropriate suggestions The investigations for abnormality are to be carried out for

    problems. Enlist scope of improvement with extensivephysical checks / observations.

    Based on the actual operating parameters, enlistrecommendations for action to be taken for improvement, ifapplicable such as

    Replacement of pumps/ Impeller replacement/ trimming

    Variable speed drive application, etc

    Compare the specific energy consumption with similar typeof pumps and latest energy efficient pumps

    Cost analysis with savings potential for taking improvementmeasures.

  • 7/28/2019 5.Energy Audit of CW System.ppt

    21/39

    Flow Distribution

    Measure the flow at the individual pump discharge side,

    main header, at the users (for the major and large users) along with the

    pressure and

    velocity. Depict these values in schematic diagram

    Ensure Line adequacy by measuring the velocity in themajor pipe lines

    Pressure drop in the distribution network

    Specific water flow rate

  • 7/28/2019 5.Energy Audit of CW System.ppt

    22/39

    CONDENSERS

  • 7/28/2019 5.Energy Audit of CW System.ppt

    23/39

    Performance of Condensers

    Parameters for condenser performance

  • 7/28/2019 5.Energy Audit of CW System.ppt

    24/39

    Performance of Condensers

    Parameters for condenser performance- contd

  • 7/28/2019 5.Energy Audit of CW System.ppt

    25/39

    Performance of Condensers

    The following needs to be computed:

    1. Condenser heat load = Q x T x Cp

    Parameter Details Unit

    Q Water flow rate Kg/h

    T Average CW temperature rise oC

    Cp Specific heat kcal/kg oC

    2. Calculated condenser vacuum =

    Atmospheric pressure Condenser back-pressure

    3. Deviation in condenser vacuum =Expected condenser vacuum - Measured condenser vacuum

    4. Condenser TTD =Saturation temperature Cooling water outlet temperature

  • 7/28/2019 5.Energy Audit of CW System.ppt

    26/39

    Performance of Condensers

    5. Condenser Effectiveness =

    Rise in cooling water temperature

    Saturation temperature - Cooling water inlet temperature

    6. Condenser heat duty in kcal/h =

    Heat added by main steam + heat added by reheater + heat

    added by SH attemperation + heat added by RHattemperation + heat added by BFP - 860 x (Pgen + Pgen

    losses + heat loss due to radiation)

    7. Condenser tube velocity (m/s) =

    Cooling water flow rate (m3/h) x 106

    3600 x tube area (mm2) x ( no. of tubes per pass - no. of

    tubes plugged per pass )

  • 7/28/2019 5.Energy Audit of CW System.ppt

    27/39

    Performance of Condensers

    8. Determination of actual LMTD

    Tsat - ToutLn

    LMTD =

    Tout - Tin

    Tsat -Tin

    9. LMTD expected = LMTD test x ft x fw x fq

    (Saturation Temperature during test LMTD during test

    Saturation Temperature design LMTD design)ft=

    0.25

    fw = Tube velocity during test Tube velocity design( )0.50

    fq = Condenser design duty

    Condenser duty during test( )

    fw: correction forwater flow rate

    fq: correction for

    cooling water heat load

    ft: Correction for cooling water inlet temperature

  • 7/28/2019 5.Energy Audit of CW System.ppt

    28/39

    Observations During Condenser Energy Audit Tubes in operation Vs total installed

    Cleaning system operation

    Filtering system for cooling water Regular monitoring system for performance

    Comparison of LMTD, TTD, heat load, condenser vacuum, flow,temperatures, pressures with design / PG test- arriving the factorscausing deviation

    Modifications carried out in the recent past Cooling water flow

    Pressure drop on water side and choking

    Affect of present performance of cooling tower

    Accurate metering of vacuum

    Absolute back pressure deviation from expected value Sub cooling of air steam mixture and condensate

    Circulation water temperature raise

    Effectiveness of cleaning the tubes

    Circulating water velocity in tubes

  • 7/28/2019 5.Energy Audit of CW System.ppt

    29/39

    COOLING TOWERS

  • 7/28/2019 5.Energy Audit of CW System.ppt

    30/39

    Performance of Cooling Towers

  • 7/28/2019 5.Energy Audit of CW System.ppt

    31/39

    Performance of Cooling TowersWhile conducting the cooling tower, visual observations

    need to be made with respect to:

    Adequate water level in the trough Cross flow air from other cooling towers (which are under

    maintenance)

    Nozzle condition and operation

    Fill condition Change of blade angles during change of seasons

    The CT airflow shall be measured using an anemometerand compared with calculated airflow derived from fan

    characteristic curves of CT fans with actual powermeasurements.

    Calculate range, approach, L/G (Liquid to gas) ratio andeffectiveness for design and operating conditions for eachtower

  • 7/28/2019 5.Energy Audit of CW System.ppt

    32/39

    Performance of Cooling Towers

    1. C.T. Range = Water inlet temperature Water outlet temp.

    2. C.T. Approach = Water outlet temperature Wet bulb temp.

    3. Effectiveness % = Range x 100( range + approach )

    Fan actual airflow (Nm3) / cell =

    Fan rated airflow (Nm3) / h x ( Fan input kW actual )

    ( Fan input rated )

    1/3

    1/3

    4.

    5. Air mass flow / cell = flow x density of air

  • 7/28/2019 5.Energy Audit of CW System.ppt

    33/39

    Performance of Cooling Towers

    5. Evaporation losses =CW flow (m3/ h) x CT range in 0C

    675

    6. Makeup water consumption = Evaporation losses(COC 1)

    The above readings may be taken on daily basis for three

    days on different atmospheric conditions say during mid

    summer, winter & monsoon period. Once in the mid day and

    once in the mid night time and a record duly maintained.

    Collect unit load (MW), frequency, and condenser vacuum

    condition while taking the cooling tower measurement

  • 7/28/2019 5.Energy Audit of CW System.ppt

    34/39

    Performance of Cooling Towers

    Power consumption of CT fans

    Exploration of Energy Conservation Possibilities:

    Condenser Possibility of Improvement in condenser vacuum

    Turbine heat rate Reduction possibilities

    Improving the effectiveness of condenser and TTD Cooling water flow adequacy and flow optimization

    Air ingress

    Increasing the TTD of the condenser

  • 7/28/2019 5.Energy Audit of CW System.ppt

    35/39

    Exploration of Energy Conservation Possibilities

    Water pumping and cooling tower

    Improvement of systems and drives Use of energy efficient pumps Correcting inaccuracies of the Pump sizing / Trimming of impellers Use of high efficiency motors

    Integration of variable speed drives into pumps: The integration ofadjustable speed drives (VFD) into compressors could lead toenergy efficiency improvements, depending on load characteristics

    High Performance Lubricants: The low temperature fluidity and hightemperature stability of high performance lubricants can increaseenergy efficiency by reducing frictional losses

    Improvements in condenser performance Improvement in cooling tower performance Application potential for energy efficient fans for cooling tower fans Measuring and tracking system performance

  • 7/28/2019 5.Energy Audit of CW System.ppt

    36/39

    Exploration of Energy Conservation Possibilities

    Measuring water use and energy consumption is essentialin determining whether changes in maintenance practices

    or investment in equipment could be cost effective

    In this case it is advised to monitor the water flow rate andcondenser parameters, cooling tower parameters

    periodically i.e. at least once in a three months and energyconsumption on daily basis. This will help in identifying the -

    - Deviations in water flow rates

    - Heat duty of condenser and cooling towers

    - Measures to up keep the performance

  • 7/28/2019 5.Energy Audit of CW System.ppt

    37/39

    Exploration of Energy Conservation Possibilities

    System Effect Factors

    Equipment cannot perform at its optimum capacity if fans,

    pumps, and blowers have poor inlet and outlet conditions

    Correction of system effect factors (SEFs) can have asignificant effect on performance and energy savings

    Elimination of cavitation: Flow, pressure, and efficiency arereduced in pumps operating under cavitation. Performance

    can be restored to manufacturers specifications through

    modifications. This usually involves inlet alterations and

    may involve elevation of a supply tank

    f C

  • 7/28/2019 5.Energy Audit of CW System.ppt

    38/39

    Exploration of Energy Conservation Possibilities

    Internal Running Clearances: The internal runningclearances between rotating and non-rotating elements

    strongly influence the turbo machine's ability to meet ratedperformance. Proper set-up reduces the amount of leakage

    (re-circulation) from the discharge to the suction side of the

    impeller

    Reducing work load of pumping: Reducing of obstructionsin the suction / delivery pipes thereby reduction in frictional

    losses. This includes removal of unnecessary valves of the

    system due to changes. Even system and layout changes

    may help in this including increased pipe diameter.Replacement of components deteriorated due to wear and

    tear during operation, modifications in piping system

  • 7/28/2019 5.Energy Audit of CW System.ppt

    39/39