-57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The...

80
- 57 - 4.0 ALTERNATIVE DESIGNS 4.1 Roadway Cross Section 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed a lane width of 3.65 m (12'), For heavily travelled roadways the City has typically used a lane width of 3.65 m, (12 ft. -eg. Dougall Avenue, Huron Church Road and Howard Avenue) and has recently completed planning studies which have used a pavement width of 3.65 m. However, taking into account construction and property costs and the possible reduction or elimination of Provincial subsidy for roadway construction, a reduced lane width was considered. Ministry of Transportation of Ontario and Transportation Association of Canada design standards indicate that a 3.5 m lane width Is satisfactory for a multi-lane divided urban roadway with a design speed less than 80 km/hr. which is the case for Tecumseh Road East. The use of 3.5 m lanes would reduce construction cost by less than 2%. Because a reduced lane width could negatively affect capacity and accidents and to maintain consistency with current projects, the 3.65 m lane width was adopted. Design standards suggest that left turn lanes of 3 m are adequate when the width of the median gutter is taken into account. However, because most Intersections will have a number of turning trucks, the left turn lane width was set at 3.25 m for planning purposes. Similarly, where right turn lanes are Indicated by high turning volumes, a width of 3.25 m was used. As noted In Section 3.6.8 , Lauzon Road from Clalrvlew to Hawthorn is parallelled by a designated future secondary blkeway. The City's Official Plan requires that arterial road upgrading projects examine the effectiveness of providing additional pavement to accommodate the City's plans for providing bicycle facilities. Accordingly, the curb lane width proposed for Lauzon Road Includes a 1.5 m bikelane and 3.65 m vehicle lane. The bike lane Is measured to the face of curb. CO~Blft~G OGIM!III

Transcript of -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The...

Page 1: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 57 -

4.0 ALTERNATIVE DESIGNS

4.1 Roadway Cross Section

4.1.1 Travelled Pavement

The roadway capacity analysis carried out In the Traffic Analysis and Planning Report

assumed a lane width of 3.65 m (12'), For heavily travelled roadways the City has typically

used a lane width of 3.65 m, (12 ft. -eg. Dougall Avenue, Huron Church Road and Howard

Avenue) and has recently completed planning studies which have used a pavement width

of 3.65 m. However, taking into account construction and property costs and the possible

reduction or elimination of Provincial subsidy for roadway construction, a reduced lane

width was considered.

Ministry of Transportation of Ontario and Transportation Association of Canada design

standards indicate that a 3.5 m lane width Is satisfactory for a multi-lane divided urban

roadway with a design speed less than 80 km/hr. which is the case for Tecumseh Road

East. The use of 3.5 m lanes would reduce construction cost by less than 2%. Because a

reduced lane width could negatively affect capacity and accidents and to maintain

consistency with current projects, the 3.65 m lane width was adopted.

Design standards suggest that left turn lanes of 3 m are adequate when the width of the

median gutter is taken into account. However, because most Intersections will have a

number of turning trucks, the left turn lane width was set at 3.25 m for planning purposes.

Similarly, where right turn lanes are Indicated by high turning volumes, a width of 3.25 m

was used.

As noted In Section 3.6.8 , Lauzon Road from Clalrvlew to Hawthorn is parallelled by a

designated future secondary blkeway. The City's Official Plan requires that arterial road

upgrading projects examine the effectiveness of providing additional pavement to

accommodate the City's plans for providing bicycle facilities. Accordingly, the curb lane

width proposed for Lauzon Road Includes a 1.5 m bikelane and 3.65 m vehicle lane. The

bike lane Is measured to the face of curb.

CO~Blft~G OGIM!III

Page 2: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 58 -

4.1.2 Medians

A key component of the recommended solution is the inclusion of a raised median. There

are several factors involved In selecting the width for the raised median:

minimum width produces minimum cost

adequate space as refuge area for pedestrians caught at the end of a walk

cycle (particularly those using wheelchairs or motorized buggies)

offset to traffic signal poles from the curb line

continuity of through lanes

Taking Into account the above factors, the offset to traffic signal poles dictates a minimum

raised median width of 2.Sm (edge of pavement to edge of pavement and assuming a

0.45 m gutter pan). This width would provide a l .6m refuge area which is considered

sufficient.

The 2.Sm raised median In Intersection areas plus the 3.25m left turn lane creates a median

area (space between through lanes) of 5.75m. In a typical mid-block areas where no left

turn lanes are required, the median area could be reduced to 2.Sm (2m would be the

minimum because there are no signal pole hazards). This would result in a horizontal

deflection of about l .6m (3.25m left turn lane width split equally on each direction). This

deflection of traffic would have a negative affect on traffic capacity and safety but

maintaining the 5.75 median area would add extra construction cost. Therefore, to

maintain capacity and safety it was agreed to maintain a wide median area but to

reduce the mid-block median area width to Sm. The result will be a 0.375m deflection

which Is considered acceptable.

On other roadways In the Improvement Corridor, raised medians are required only In

intersection areas.

In addition to median width, median type was examined. Four median types were

compared:

wide median with a 560 mm high barrier curb

concrete median barrier with flush shoulders

Page 3: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 59 -

concrete median barrier with mountable curbs at edge of pavement

wide median with 250 mm high barrier curb.

The details of the comparison of these alternatives are Included In Appendix C.

For cost and safety reasons, the wide median 250 mm high was selected as the preferred

alternative. Its accident reduction potential Is good, although less than the concrete

median barrier, and Is easier to design and build because severe height transitions are not

required.

4.1.3 Boulevard

The width of the boulevard Is based on accommodating sidewalks and Illumination poles

as well as providing distance between the sidewalk and roadway for comfortable

pedestrian use. A reasonable boulevard for a major arterial would be 4.0 m as shown on

Figure 4.1. Depending on the right-of-way adopted and difficulties in obtaining property,

the boulevard width could vary slightly.

4.1.4 Typical Cross Sections

4.1.4. l Tecumseh Road East

Figure 4.2 shows the cross section elements for Tecumseh Rd. E. as previously adopted,

including 3.65m travelled lanes and a Sm wide raised median. As called for in the Official

Plan, 36m was adopted for planning purposes as the basic right-of-way ( Class I Arterial).

The resulting boulevard Is 4. l 75m, with the extra width allocated for utilities behind the

sidewalk.

4.1.4.2 Jefferson Boulevard

As shown on Figure 4.2, the cross section elements for Jefferson Blvd. will generally fit on

the existing 26.2m (86 ft.) right-of-way. Included is a 4m TWLTL which Is slightly wider than

the adjacent through lanes to provide a higher comfort level for motorists using the turning

lane and lower the probability of Improper use affecting through lanes. Additional right-of­

way width Is required for the channelized intersection at Tecumseh Rd. E.

eo~UUIII(; [~~!1'1111

Page 4: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 60 -

4.1.4.3 Lauzon Road

Figure 4.2 shows 3.65m inside through lanes and 4.7m curb lanes on Lauzon Rd. The 4.7m

curb lane accommodates a l.5m dedicated bikelane. A 3.65 m TWLTL was Included.

Generally, this section will flt on the existing 26.2 m (86') right-of-way.

These cross sections have been used In the development of alternative designs in the

following sections.

4.1.5 Planning Criteria

The following criteria were used In the development of alternative alignments and designs;:

l .Road Classification - Tecumseh Rd. E. Jefferson Blvd. Lauzon Rd.

2. Speed - design

- posted

3. Basic Number of Lanes - Tecumseh Rd. E. - Jefferson Blvd. - Lauzon Road

4. Through Lane Width

5. Auxiliary Lane Width

6. Medians

7. Sidewalks

Tecumseh Rd. E.

Jefferson Blvd. Lauzon Rd.

8. Minimum Horizontal Curvature

9. Boulevard Width (typical distance edge of pavement to front of sidewalk)

l 0. Basic Right-of-Way Width Roadway

L~~ CO~Hll!Nl. lNGINl!II

Urban Arterial Divided Urban Arterial Undivided Urban Arterial Undivided

70 km/hr.

60 km/hr.

3 (each direction 2 (each direction) 2 ( each direction) 3.65m

3.25m

2.5 m raised (min) 5.0 m raised (max) 4m (TWLTL) 3.65m (TWLTL)

1.5 (min)

190 m (@6% super elevation)

Tecumseh Rd.E. l .5m Jefferson Blvd. l .2m Lauzon Rd. - .65m

Tecumseh Rd. E. Jefferson Blvd. Lauzon Rd.

- 36m - 26.2 (existing) - 26.2 (existing)

(

Page 5: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 61 -

4.2 Alternative Alignments

4.2.1 Evaluation Methodology

A major part of Phase 3 of the Class E.A. process Involves the development and evaluation

of alternative designs based on the recommended solution. In this study, the main

problem was Identified as Insufficient traffic capacity in the existing roadway corridors. The

solution identified in Phase 2 (widening of existing roadways) can be accommodated

generally within the existing corridors. Alternative designs which implement the widening

solution in the existing corridors are very concentrated and the differences between the

alternatives relative to their traffic operation effectiveness, construction cost and

adherence to deslreable design standards was considered negligible. For example, where

raised medians are called for in the recommended solution, travel patterns to existing

businesses will be affected; however, these effects are deemed to be comparable to all

alternative designs, ie. their differences are negligible. Similarly, the opportunity to provide

effective areas to turn around, necessitated by the raised median, are deemed equal to

all alternatives.

The main area where design alternatives differ is their impacts on abutting properties.

Because the operational characteristics of the design alternatives are considered

comparable, to establish the relative property impacts, only alternative alignments

incorporating the typical right-of-way requirements were developed. The following criteria

were adopted for comparing alternative alignments and a brief description of each

follows:

number of properties affected

area of property required for right-of-way

estimated property costs

number of businesses affected

estimated number of buyouts

potential effects on business viability

COIISVlllllG IIIGlll!IIS

Page 6: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 62 -

Number of Properties Affected

This Involves a count of all existing residential and business properties where negotiations

will be required to purchase property for right-of-way requirements. It is an Indication of

the general property effects of each alternative alignment.

Area of Property Required

This criteria Is Included for situations where a small number of properties are significantly

affected. The total area required could be higher for a smaller number of properties

impacted. The measurement Is based on a calculation of the area required as shown on

Figures 4.4A-F.

Estimated Property Cost

This comparison criteria reflects the extent to which alternative alignments affect land or

business operations of varying value. Typical unit costs for various land classifications were

provided by the Property Department and applied to the area calculations. This

measurement includes any buyout cost or business viability allowance. The estimates are

presented as low, moderate, or high according to the following definition;

low < $100,000

moderate $100,000 - $250,000

high > $250,000

Number of Businesses Affected

This Is an Indication of the general economic effects when, for example, alternative

alignments affect existing business versus residential properties where redevelopment Is

planned. Vacant businesses were not counted.

Estimated Buyouts

Where properties appear to be Impacted in a major way, estimates were made as to

whether continued use of the remaining property was possible. If not, they were Identified

C011Hl1111G INGIMUIS

(

Page 7: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 63 -

as a "buyout" and a cost estimate was included to buy the total property, whether

business or residence. The tables Include a count of the locations and the estimated cost

is Included under the criterion Estimated Property Cost.

Business Viability Impacts

Where businesses, In particular, appeared to be Impacted such that continued profitable

operation might be affected, a viability Impact was Identified. An example would be

reduction of parking which might limit customers. Similar to "Estlmtated Buyouts", locations

of viability Impacts were counted. Costs are Included under the Estimated Property Cost

item.

Other Criteria

For some evaluations, additional criteria were used such as "alignment compatibility with

existing roadways". However, they are used only where appropriate and are considered

self-explanatory.

4.2.2 Jefferson Boulevard

The traffic flow analysis at the Tecumseh Rd. E. - Jefferson Blvd. Intersection, using Passer

213, was adjusted several times to approach optimum levels of service on the critical traffic

movements. The resulting lane configuration Is as follows:

left turn lane on both north and south legs

2 through lanes north bound (outside lane dropped north of Diamonds)

l through lane south bound

north bound right turn lane

south bound right turn lane

The existing conditions In the area of this Intersection are shown on Figure 4.3. The right-of­

way on the north side of Tecumseh Road E. is 20 m while on the south side, it Is 26.2 m.

13 Passer 2 Is a computer analysis tool used by Traffic Engineering Department to establish timing tor a group of traffic signals.

eo~~nllMG EMGIIIIEIS

Page 8: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 64 -

The 6.2 m difference In right-of-way width is split approximately equally on both sides and (

the alignment Is straight.

Figure 4.3 shows 3 Intersection quadrants occupied by businesses:

northwest - Sotos Submarine, Onyx Engineering, Adaptable Software and Tally Ho

Distributing

northeast - Diamonds, Sassy Scissors, Attard Clothing

southeast - Valiant Tool and Machine Inc.

The southwest corner Is vacant and Is zoned commercial (previously occupied by Esso gas

station). North of the commercial development on the north side are residences. Offsets

from the right-of-way to houses on the west side are in the order of 5.5 m while on the

east side, houses are set back about 1 Om.

On the northeast side, a laneway has been incorporated Into Diamonds parking area.

Slightly further north on the west side, a laneway serves the rear of the businesses on

Tecumseh Road E. just west of Jefferson Blvd.

The alignment concepts examined for Jefferson Blvd. At Tecumseh Road E. were:

Alternative 1

Alternative 2

Alternative 3

use centreline of existing right-of-way

hold the west right-of-way and widen to the east

hold the east right-of-way and widen to the west

For either Alternative 1 or 2, which require widening to the east, Diamonds would be

affected to the extent that a costly buyout Is required. For Alternative l, Sotos would be

affected as well. Since Alternative 1 affects both sides and there are no offsetting

benefits, It was abandoned and only Alternatives 2 and 3 were analyzed. Therefore, one

side or the other is affected, not both.

Figure 4.3 shows the alignments for Alternative 2 and Alternative 3 respectively.

Operationally, the two alignments are comparable and the only reasonable comparison

criteria are property Impacts.

eo~UtTtNG INGUIUI

Page 9: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

TABLE4.1 TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION· JEFFERSON BOULEVARD

EVALUATION CRITERIA ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES AFFECTED 9 11

AREA OF PROPERTY REQUIRED (sq.m.) 866 677

ESTIMATED PROPERTY COST HIGH HIGH

NUMBER OF BUSINESSES AFFECTED 3 2

ESTIMATED BUY-OUTS 3 0

BUSINESS VIABILITY IMPACTS 0 2

SUMMARY - major impacts result from - property impacts considered

closeness of Diamonds to the lower

existing R.O.W.

- higher property cost

Page 10: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

The following criteria were used:

number of properties affected

number of businesses affected

number of buyouts

area of property required

property cost

- 65 -

Table 4.1 summarizes the evaluation of alternatives relative to the evaluation criteria. As

shown, the overall property impacts of Alternative 3 are lower and it was Identified as the

recommended alternative by th_e Project Team.

4.2.3 Tecumseh Road East Alignment

4.2.3.1 Corridor Review

Prior to proceeding with development of alternative alignments, It Is appropriate to

examine the existing right-of-way. Figure 3.6 shows the approximate right-of-way widths

at spot locations along the Corridor. Examination of the various right-of-way widths and

where they occur help in the development of design alternatives. For example, from Rose

City Ford to Lauzon Parkway much of the right-of-way on the south side has been already

widened consistent with an overall 36 m right-of-way. Slmllarly on the north side, although

not as extensive, widenlngs have occurred to create the full 36 m. Between Lauzon

Parkway and Lauzon Road, the right-of-way has been widened, primarily to the north, to

about 34 m to accommodate a continuous left turn lane. The remainder of the right-of­

way to the east City Limits reflects a basic 30 m (100') right-of-way.

The existing and future land use pattern in the Improvement Corridor shows differing

characteristics for different sections which are factors in developing and evaluating

alignments. The existing development pattern on the south side of the Corridor is

consistent with the City's Official Plan and little or no change from existing is anticipated.

The exceptions are the areas either side of Little River and from Robinet Lane easterly

where the existing land use and designations are expected to change. In contrast on the

north side, where the land use designation is industrial, considerable change is expected

within the 20 year study period.

CQH!Ut!IKG n(.IHII!

(

Page 11: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 66 -

Because of the differing characteristics, the Improvement Corridor was broken Into 6

sections, as shown on Figure 3.6 and on Figures 4.4A-F, to facilitate evaluation of

alternatives for Tecumseh Rd. E. The sections and their main characteristics are

summarized below.

Section Main Characteristics

- 24 m right-of-way

- development mature both sides

2 - mqture commercial development south side

- Industrial redevelopment expected on north side

- allowance for 36 m right-of-way already made for majority

of south side

3 - 34 m right-of-way

- mature commercial development on south side

- shopping centre occupies most of north side

4 - 30 m right-of-way

- mature development on north side

- redevelopment pending on south side

- shopping centre occupies about l /3 of north side

5 - 30 m right-of-way

- mature residential area on south side

- redevelopment expected on north side

6. - 30 m right-of-way

- existing business on both sides and redevelopment expected

CO~IHIHG IMQl~HII

Page 12: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 67 -

4.2.3.2 Alignment Alternatives

Three basic approaches to implementing the widening of Tecumseh Road E. to 6 lanes

considered:

Alternative l. Centre of the existing road (approximately centre of right-of-way).

Alternative 2. Hold the south right-of-way limit and widen only to the north.

Alternative 3. Hold the north right-of-way limit and widen only to the south.

Centreline alignments were developed and the necessary right-of-way identified according

to the typical cross section. The edges of pavement and intersection designs were not

developed on each alternative as there was no evaluation factor requiring that level of

detail.

Alternative l

Figures 4.4 A-F show the alignment concept developed for Alternative l. it generally

coincides with the existing roadway centreline which Is basically centred In the right-of-way

except for the widened areas noted previously. The right-of-way was offset 18 m either

side of centreline consistent with the typical section for Tecumseh Rd. E. The alignment

Is a best fit of the alignment controls.

Alternative 2

Figures 4.4 A-F show the alignment concept developed for Alternative 2. Because of the

variations in the south right-of-way, It was necessary to select control points for the

alignment. Controls at the east limit of Rose City Ford and at Swiss Chalet take advantage

of the earlier widening in this area to accommodate a 36 m right-of-way. Between Lauzon

Parkway and Lauzon Road, the general south limit controlled the centreline. Maintaining

the concept at the Jefferson intersection Involves a considerable shift to the north and a

reverse curve system opposite Rose City Ford to connect the alignments. East of Lauzon

Road, the control points are set according to the south right-of-way tangents. Alternative

2 requires a set of reverse curves at both ends to match to existing pavements.

I

Page 13: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 68 -

I Alternative 3

Figures 4.4 A-F show Alternative 3 developed similar to Alternative 2 based on a set of

control points using the north right-of-way limits. The alignment Is a best fit on the control

points and like Alternative 2, reverse curves are required at each end to match existing

pavements.

4.2.3.3 Evaluation of Alternative Alignments

The following tables show the evaluation on a section by section basis.

Review of the evaluation tables shows that, generally, the differences between alternatives

are small. However, a recommended alternative for certain section was reasonably clear

and following those selections compatibility with the already preferred sections In some

cases, became a deciding factor.

Section I

In a previous section of the report, Alternative 3 was Identified as the preferred alternative

for Jefferson Blvd. at Tecumseh Rd. E. That concept Involves maintaining the east property

line of Jefferson Blvd. and widening to the west. As shown In Table 4.2A, In Section l,

concentration of property Impacts along with those resulting from Jefferson Blvd. and

compatibility with the existing alignment to the west were deemed Important factors.

Although Alternative 2 has greater concentration of property Impacts in the northwest

quadrant, It also severely Impacts the northwest quadrant resulting in concerns for business

viability. Alternative I concentrates property Impacts, matches the existing roadway

alignment to the west, and was Identified as the recommended alternative.

Section 3

Before reviewing Section 2, Section 3 was examined, Table 4.28 shows that Alternative 2

causes less overall property Impact and therefore was Identified as the recommended

alternative.

eQNUtl!NG l~Gl~IUI

Page 14: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

TABLE4.2A TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION -TECUMSEH ROAD EAST

SECTION 1 EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES CHANGE EXPECTED -(1) - -AFFECTED NO CHANGE 13 8 5

AREA OF PROPERTY CHANGE EXPECTED -- -- -

REQUIRED NO CHANGE 3054 3111 3071

ESTIMATED PROPERTY CHANGE EXPEQTED - -- -COST (2) NO CHANGE HIGH HIGH HIGH

ESTIMATED BUY-OUTS CHANGE EXPECTED - - -NO CHANGE 3 5 4

NUMBER OF BUSINESSES CHANGE EXPECTED ... - -AFFECTED NO CHANGE 30 22 8

BUSINESS OPERATION CHANGE EXPECTED - - -IMPACTS NO CHANGE 6 10 2

ALIGNMENT COMPATIBILITY - good, matches existing - poor, requires 6m. shift to - poor, requires Gm shift to

WITH EXISTING PAVEMENT south north

COMPATIBILITY WITH JEFFERSON BLVD. - preferred Jefferson Blvd. - preferred Jefferson Blvd. - preferred Jefferson Blvd. ! alignment impacts alignment impacts alignment impacts

heavily in the northwest heavily in the northwest heavily in the northwest

quadrant - this alternative quadrant - this alternative quadrant - this alternative

consolidates impacts in also impacts heavily on also im.pacts heavily on

northwest quadrant and the northeast quadrant the south side and also

adds impacts in the north· thereby spreading out spreads out impacts

east quadrant impacts and creating via·

bility concerns

SUMMARY - aggregates property - more buy-outs and via- - more buy-outs

impacts - good match to biHty impacts - short taper - have major impact in north-

existing alignment to west to reduce impacts west of west quadrant from Jefferson

Balfour may have negative regardless

affect on traffic operation - short taper to reduce impacts

lo ' "'~.~ _,, Jl. west of Balfour may have negative affect on traffic operation

(1) No change in land use expected on either side.

(2) $152, 700 $325,000 - land acquisition cost and additional buyout or viability costs respectively

Page 15: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TABLE4.2B TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION· TECUMSEH ROAD EAST

SECTION 3 EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES CHANGE EXPECTED -(1) - -AFFECTED NO CHANGE 14 4 10

AREA OF PROPERTY CHANGE EXPECTED - - --REQUIRED NO CHANGE 1188 1154 1189

ESTIMATED PROPERTY CHANGE EXPECTED - ·- ---COST NO CHANGE LOW LOW LOW

ESTIMATED BUY·OUTS CHANGE EXPECTED - - ·-NO CHANGE 0 0 0

NUMBER OF BUSINESSES CHANGE EXPECTED - - -AFFECTED NO CHANGE 15 4 11

BUSINESS OPERATION CHANGE EXPECTED -- - -IMPACTS NO CHANGE 0 0 0

SUMMARY • least overall property

impact and those impacts

on outer fringe of large

parking area ,~ (1) No change in land use expected on either side.

Page 16: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

TABLE4.2C TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION -TECUMSEH ROAD EAST

SECTION 2 EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES CHANGE EXPECTEO 16 (1) 16 0

AFFECTEO NO CHANGE 3 3 7 (2)

AREA OF PROPERlY CHANGE EXPECTED 2076 2671 0

REQUIRED NO CHANGE 866 525 3550

ESTIMATED PROPERlY CHANGE EXPECTED MODERATE MODERATE LOW

COST NO CHANGE LOW LOW MODERATE

ESTIMATED BUY·OUTS CHANGE EXPECTED 0 0 0

NO CHANGE 0 0 0

NUMBER OF BUSINESSES CHANGE EXPECTED 6 6 0

AFFECTED NO CHANGE 3 3 8 (3)

BUSINESS OPERATION CHANGE EXPECTED 0 1 0

IMPACTS NO CHANGE 0 0 0

SUMMARY - more Impact In stable - least impact In stable - highest impact in stable

area area area

- 2m shift to north required - best match with Alt 2 In

lo match Alt 2 in Section 3 Section 3 - worst match with Alt 2 In

- best match with Alt 1 In Section 3

Section 1

~:. ti I!! .

Page 17: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TABLE 4.20 TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION -TECUMSEH ROAD EAST

SECTION 4 EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES CHANGE EXPECTED 9 (1) 0 9

AFFECTED NO CHANGE 13 13 0

AREA OF PROPERTY CHANGE EXPECTED 1677 0 3946

REQUIRED NO CHANGE 2417 3755 0

ESTIMATED PROPERTY CHANGE EXPECTED LOW $0 LOW

COST NO CHANGE LOW LOW $0

ESTIMATED BUY-OUTS CHANGE EXPECTED 0 0 0

NO CHANGE 0 1 0

NUMBER OF BUSINESSES CHANGE EXPECTED 0 0 3

AFFECTED NO CHANGE 8 5 0

BUSINESS OPERATION CHANGE EXPECTED 0 0 0

IMPACTS NO CHANGE 0 0 0

SUMMARY - less Impact in stable - most impact in stable - feast Impact In stable

area area area

- affects lagoon on north - would require construe- - aviods lagoon on north

side but less than Alt 2 lion In area of lagoon side

- requires widening of - requires widening of - good alignment for

bridge on both sides bridge on both sides bridge, widen only on

south slde

Page 18: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

,'

{

TABLE 4.2E TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION· TECUMSEH ROAD EAST

SECTION 5 EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3

NUMBER OF PROPERTIES CHANGE EXPECTED 21 21 0

AFFECTED NO CHANGE 45 0 69

AREA OF PROPERTY CHANGE EXPECTED 3349 5224 0

REQUIRED NO CHANGE 1320 0 5007

ESTIMATED PROPERTY CHANGE EXPECTED LOW LOW $0

COST NO CHANGE LOW $0 MODERATE

ESTIMATED BUY-OUTS CHANGE EXPECTED 0 1 0

NO CHANGE 0 0 0

NUMBER OF BUSINESSES CHANGE EXPECTED 13 13 0

AFFECTED NO CHANGE 4 0 5

BUSINESS OPERATION CHANGE EXPECTED 0 0 0

IMPACTS NO CHANGE 0 0 0

SUMMARY - some Impacts to stable - least impact to stabte - most Impacts In stable

area area area

- pavement closer to - pavement furthest away - pavement closest to

Forest Glade residences from residences in Forest Glade residences

Forest Glade

lfit§f!i~-

Page 19: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TABLE 4.2F TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL ROAD

ALIGNMENT EVALUATION· TECUMSEH ROAD EAST

SECTION 6 .

EVALUATION CRITERIA ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3 NUMBER OF PROPERTIES CHANGE EXPECTED 28 18 12

AFFECTED NO CHANGE - (1) - -AREA OF PROPERTY CHANGE EXPECTED 3085 3088 2879

REQUIRED NO CHANGE - - -ESTIMATED PROPERTY CHANGE EXPECTED LOW MODERATE LOW

COST NO CHANGE -· -· ...

ESTIMATED BUY-OUTS CHANGE EXPECTED 0 1 0

NO CHANGE -· -· -· NUMBER OF BUSINESSES CHANGE EXPECTED 16 12 4

AFFECTED NO CHANGE - - -BUSINESS OPERATION CHANGE EXPECTED 0 1 0

IMPACTS NO CHANGE -· - -ALIGNMENT COMPATIBILITY - matches existing - requires 3m. shift to - requires 3m. shift north

WITH EXISTING PAVEMENT soulh to match existing to match existing

SUMMARY - highest property impact - more property impacts - feast overall impacts

- partially overlaps Sm - Sm easement In addition - overlaps easement on

easement on south side to right-of-way south side

- longer transition

required ,_,

Page 20: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 69 -

Section 2

Section 2 was examined with respect to Identification of compatibilities with Alternative l

In Section l and Alternative 2 in Section 3 (see Table 4.2c). Alternative 2 had marginally

less impact in the stable area and matches the adjacent preferred alternatives best.

Alternative 2 was Identified as recommended.

Section 4

In Section 4, the area of stable development switches to the north side. East and west of

Little River on the south side, re,development is expected.

Table 4.2D indicates Alternative 3 as the recommended alternative because of Its lower

property impacts In the stable development area and compatibility with the alignment for

the Little River bridge widening. The ultimate transition with Alternative 2 in Section 3 will

further reduce Impacts In the southeast quadrant of the Tecumseh Rd. E. - Lauzon Rd.

Intersection.

Section 5

In Section 5, Impacts to the established Forest Glade community were deemed negative.

Because Alternative 2 has the lowest property Impacts In the stable area and Its pavement

would be furthest from the outdoor living area of existing Forest Glade residences backing

onto Tecumseh Rd. E., It was recommended. (See Table 4.2E).

Section 6

In Section 6, redevelopment is expected on both sides of the Improvement Corridor. Table

4.2F Indicates overall property impacts to be less for Alternative 3 and it was identified as

the recommended alignment.

4.2.4 Lauzon Road

The future traffic volumes for the Lauzon Road intersection at Tecumseh Road E. require

a basic intersection for a 4 lane roadway - 4 lanes through and a left turn storage lane

on both north and south legs. Although there Is an existing separate right turn lane for

(()N!HIII/G 11/Glij[IH

Page 21: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 70 -

south bound turns, because the Lauzon Parkway extension Is assumed to be in place, right

turning traffic Is reduced and therefore a separate lane is not required.

Similar to Jefferson Blvd. the right-of-way width varies - on the north it Is 26.2 m while on

the south It Is 20 m. The additional width on the north side occurs mainly on the east side.

A detailed analysis of alignment options was not carried out for Lauzon Road. With the

property control on the west and the acute angle Intersection In the southeast quadrant,

It was agreed that the alignment should be based on the existing parking arrangement

in the southeast quadrant.

The typical cross-section for Lauzon Rd. calls for a 26 m right-of-way width (wider at

Intersections). This generally fits on the existing right-of-way north of Tecumseh Rd. E.

however, additional property on the east side south of Tecumseh Road E. Will be required.

4.2.5 Other North/South Intersecting Roads

The existing alignments for the remaining north/south roads Intersecting Tecumseh Rd. E.

such as Roseville Garden Drive, East Park Centre, Lauzon Parkway, Annie Street/Tecumseh

Mall, Forest Glade Drive, Robinet Lane and Banwell Road, were generally maintained.

Widening on the existing alignments was deemed appropriate.

4.3 Alternative Crossings of Little River

As noted previously, a 6 m easement paralleling the east side of Little River has been

allocated for the future extension of the Ganatchio Trail (primary recreatlonway).

However, because an at grade crossing of Tecumseh Road East at Little River would

represent a serious conflict between pedestrians and vehicles, the currently planned

extension of the Ganatchlo Trail parallels the south side of the CNR easterly and then

southerly to the Forest Glade Drive intersection. At the outset of the study, It was deemed

appropriate to consider the Incorporation of future recreationway plans In any

improvements to be carried out for Tecumseh Road East.

The existing roadway bridge over Little River Is located in Section 4 as defined for the

evaluation of Tecumseh Road East alignments. The preferred roadway alignment In

ial)­b.._~·1l CONl!(IIIIG UGINEII!

Page 22: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 71 -

Section 4 was Identified as Alternative 3 - widen to the south. That alignment is consistent (

with a bridge alignment based on widening only on the south side. This Is the preferred

bridge alignment because the widening would be added to the newest section of the

existing bridge and traffic disruption would be required only on one side. Also most of the

utility crossings are located on the north side. Therefore, widening of the existing bridge on

both sides was not evaluated.

The north section of the existing bridge Is about 46 years old and the south section Is

about 30 years old. The latest structural adequacy review of the bridge indicates a high

rating (structure is in good condition) and nothing but minor maintenance Is scheduled for

the near future.

Three alternatives for the roadway crossing of Little River and the recreationway crossing

of Tecumseh Road East were considered:

Alternative l - Widen the existing bridge on the south side to accommodate 6 lanes on

Tecumseh Road East and construct recreationway overpass.

Alternative 2 • Reconstruct the existing bridge about l m higher and l m. longer to

accommodate 6 lanes and a recreatlonway underneath.

Alternative 3 • Widen the existing bridge as in Alternative l and provide a separate tunnel

to take the recreatlonway under Tecumseh Road East just east of Little River.

Figure 4.5A shows Alternative l which includes the minimum requirements to widen the

existing structure to provide for 6 lanes together with an overpass to accommodate the

future recreationway extension. About 8.5m of new bridge would be required on the south

side of the existing roadway bridge. The key structure component is the box girder

supports for the riding surface which allows quicker construction and less work in the water.

This bridge widening accommodates the 1: 100 year storm elevation (177 .Sm) as defined

in ERCA's 1985 flood line mapping of Little River. Standard provision was Included In the

estimated cost for minimizing sedimentation of Little River.

The overpass structure consists of a double "T" beam providing a clear span over the future

roadway and concrete approach ramps at appropriate grades for wheelchair users.

!~~ CO~SUHING IWGl~IIU

Page 23: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 72 -

Alternative 2, as shown on Figure 4.58, Involves the complete replacement of the existing

bridge according to a raised roadway profile which accommodates the recreatlonway

under the structure. The structure substantially exceeds the flood requirements. The

recreatlonway elevation under the bridge was assumed at a level of 400 mm above the

highest lake level or 176.5 m and clearance of 2.5m to the underside of the structure was

assumed. The l m thick structure requires a raising of the roadway profile grade about

l m above the existing road profile.

Alternative 3, shown on Figure 4.5C, Includes the widening of the existing bridge similar to

Alternative l, plus the construction of a concrete box culvert to accommodate the

extension of the recreationway along Little River. The approach ramp slopes

accommodate wheelchair use. Estimated costs Include provision for Illumination and water

level sensors to signal the backup of storm flows In Little River and consequently to the box

culvert.

Late in this study, the planners for the East Riverside Planning District concurred with the

concept of a roadway link on the extreme east side of the district. The traffic analysis for

this study also assumed that an easterly link would be required. This has led to the need

to Investigate a 4th alternative which would be for the Ganatchio Trail to follow the east

link (also known as Scarsdale Road), to a crossing of Tecumseh Road at a signalized

intersection. This alternative will be evaluated further.

The alternatives were compared according to the following factors:

Natural Environment

Work In Channel Area - The extent of excavation work required In the invert area or

on the side slopes of the channel will have the potential to increase sedimentation. A

measure of this Impact Is indicated subjectively In the evaluation table.

Social Environment

Property impacts - A measure of Impacts to adjacent properties was provided In the

form of a subjective description.

CONSltllNG !MGl~l!II

Page 24: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 73 -

Personal safety - Safety Is an Issue onto itself, but also any alternative perceived to be ;

unsafe will discourage use, thereby reducing the pedestrian and recreational benefits.

These advantages or disadvantages were Identified.

Construction Flexibility - The flexibility to advance the construction of the recreationway

grade separation, In the event that special recreatlonway funding becomes available, was

considered an advantage.

Construction Cost - The cost of alternatives was estimated. Higher cost without higher

benefits Is undesirable.

Utility Impacts - While general utility relocation will be required for the overall project, any

additional utility relocation was considered a disadvantage.

Compatibility with Roadway - Features of bridge alternatives which generate spin-off

effects on the adjacent roadway were Identified.

Structure Life - A subjective Indication of long term consequences of widening rather

than replacing the existing road bridge was provided.

Table 4.3 shows the measurements of the comparison criteria for the three alternatives.

Alternative 3 was abandoned for safety reasons. Alternative 2 requires the demolition of

a structure which currently has a very good rating. Alternative I Is the safest, has good

construction flexibility and was Identified as the recommended alternative.

4.4 Recommended Alignments

In the preceding sections, the recommended alignments were Identified as follows:

Jefferson Blvd. Alternative 3

Tecumseh Rd. E.

Section 1

Section 2

Section 3

Section 4

Section 5

Section 6

Alternative 1

Alternative 2

Alternative 2

Alternative 3

Alternative 2

Alternative 3

(OMIUll!IIG i~Gl~l!IS

Page 25: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 74 -

The evaluation leading to selection of preferred alignments In some cases also Identified

offset distances between respective alternative alignments. As required, transition

alignments have been added to the composite alignment where the recommended

alignments are offset between evaluation sections eg. Section 3 (Alignment 2) and Section

4 (Alignment 3). Most of the transitions occur at deflections in the existing right-of-way and

the appearance of a parallel Jog in the alignment will not be evident.

The recommended centreline alignments for all roadways based on the preceding

selections Is shown on Figures 4.6A-K, along with the preliminary property requirements.

4.5 Development of Recommended Design

4.5. l Basic Lane Requirements

To solve the capacity problem, Tecumseh Rd. E. requires 3 through lanes in each direction

while both Jefferson Blvd. and Lauzon Rd. require 2 through Janes in the north/south

direction. Although the northerly extension of Lauzon Parkway Is not part of this study, a

stub which matches the lane configuration on the south side has been Included. The

remaining north/south roads Intersecting with Tecumseh Rd. E. require only one through

lane In each direction.

4.5.2 Auxiliary Lanes

Auxiliary traffic Janes have been added to improve traffic flow. Figure 4. 7 shows the

schematic arrangement of the auxiliary traffic lanes provided at each Intersection together

with the through lanes.

Storage lengths for left turn lanes were estimated In the Traffic Analysis and Planning

Report as follows:

Page 26: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

Page 27: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

COMPARISON CRITERIA

NATURAL ENVIRONMENT

- grading work. In the channel area

SOCIAL ENVIRONMENT

- property impacts

- personal safety

CONSTRUCTION FLEXIBILITY

COMPATIBILITY WITH ROADWAY

UTILITY IMPACTS

COST

STRUCTURE LIFE

SUMMARY

NOTES:

TABLE4.3 EVALUATION OF LITTLE RIVER CROSSINGS

TECUMSEH ROAD EAST CLASS ENVIROMENTAL ASSESSMENT JEFFERSON BLVD TO BANWELL ROAD

ALTERNATIVE 1 ALTERNATIVE 2 ALTERNATIVE 3 WIDEN EXISTING BRIDGE (8.6m) RECONSTRUCT EXISTING WIDEN EXISTING BRIDGE (6.5m)

AND CONSTRUCT OVERPASS BRIDGE ON RAISED PROFILE AND CONSTRUCT TUNNEL

- road bridge widening affects - most grading required In channel - road bridge widening affects channel bottom and side slopes and along side slopes channel bottom and side slopes

- minor localized excavation for - substantial excavation for box structure culvert, approach ramps, and

storm outlet

- minor property Impacts during - no impact - property required from Top Hat construction and possibly some reduction of

- additional easement required tin parking during construction south side - additional easement required on

south side

- good, recreationway grade - poor, safety compromised - poor, 35m tunnel where separation in full public view because portion of recrealionway recreationway users out of

out of public view public view and in an enclosed area

- good, overpass could proceed - poor, recreationway underpass - good, tunnel could proceed at before road bridge should provfded with road bridge any time that funding is available funding become available

-good - fair, requires raising of adjacent - good roadway profile by about 1m with associated approach grade slopes

- minor relocation required for - all relocations part of roadway - large diameter watermain, gas, north abutment construction bell would need to be lowered

- aerial hydro needs relocation, -1520mm storm outlet needs

probably put underground as relocation part of relocation required

for roadway

,., ,., $570,000 $671,000 $573,000

- north side of brigde may need - combined solution for 60-100 - north side of brigde may need

replacement in 20-50 years and years replacement in 20-50 years but

work may be hampered by should not affect tunnel

location of overpass north abutment

- good consrtuct!on flexibility - highest cost and highest - good consrtuction flex!b!lity -safest alternative environmental Impacts on - least safe alternative

Little River

~~J:t•J~ - safety compromised

(1} Estimated cost includes Illumination and water level warning system.

COMPARISON CRITERIA

NATURAL ENVIRONMENT

- grading work. in the channel area

SOCIAL ENVIRONMENT

• property Impacts

- personal safety

CONSTRUCTION

FLEXIBILITY

COMPATIBILITY WITH ROADWAY

UTILITY IMPACTS

COST

STRUCTURE LIFE

SUMMARY

Page 28: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed
Page 29: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 75 -

Left Turn Storage Length

Intersection Northbound Southbound Eastbound Westbound (m) (m) (m) (m)

Tecumseh Rd. E./Jefferson Blvd. 60 90 60 120

Tecumseh Rd. E./Rosevllle Garden Drive 45 3514 35 45

Tecumseh Rd. E./East Park Centre Drive 68 35 45 50

Tecumseh Rd. E./Lauzon Parkway 75 60 120 135

Tecumseh Rd. E./Annle St./ Tecumseh Mall 35 35 68 35

Tecumseh Rd. E./Lauzon Rd. 45 68 60 75

Left Turn Storage Length

Intersection Northbound Southbound Eastbound Westbound (m) (m) (ml (m)

Tecumseh Rd. E./Proposed New Road 60 8015 35

Tecumseh Rd. E./Forest Glade Dr. 150 35 35

Tecumseh Rd. E./Clover St. 35 8015

Tecumseh Rd. E./Robinet Lane 35 35 35

Tecumseh Rd. E./Banwell Rd. 90 35 100 45

Jefferson Blvd/Rose Ave. 35 35 35 35

Lauzon Rd./Tecumseh-Eastown Mall 35 35 35 35

" 35 m. used as a minimum

" Third entrance (Clover St.) added for access to East Riverside Planning District. Turning traffic and storage length spill equally between Clover SI. and proposed new road (Scarsdale).

C0~5~l!lijG UIGINl!U

Page 30: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 76 -

In cases where back-to-back storage lanes overlap, available storage length was

allocated on a pro-rated basis.

4.5.3 Recommended Roadway Design

The evaluation of alternative alignments was based on the conclusion that the roadway

elements necessary to solve the identified problems produced the same engineering

Impacts regardless of which alignment was used. Property impacts resulting from widening

of the right-of-way to 36 m on Tecumseh Rd. E. varied according to alignment location

and alternative alignments were evaluated only on the basis of property Impacts. it

follows directly that there is only one roadway design. It Involves the development of the

necessary roadway design elements such as through lanes, raised medians, turning lanes,

sidewalks, etc., on the preferred alignment and is referred to hereafter as the

recommended design. Figure 4.8A-J shows the recommended design.

4.6 Future Access From/To Tecumseh Rd. E.

It is important to understand the function of Tecumseh Rd. E. relative to continuing local

development and the resulting Increase In traffic flow. There Is a continuum of roadway

function which ranges from providing access to abutting property exclusively (eg. cui-de­

sac street) to providing movement of traffic (eg. controlled access freeway)16•

Most roads perform a dual function of both access and traffic movement. Tecumseh Rd.

E. is a major arterial which, except for the section between Roseville Garden Drive and

Lauzon Parkway, provides full access to adjacent property but is also currently required to

handle a substantial traffic flow. Unfortunately, a roadway cannot maximize access and

traffic movement at the same time and therefore a compromise between the two

functions Is required.

The traffic analysis carried out for this study indicates the local and regional growth will

result In a doubling of traffic on the roads in the Improvement Corridor. New commercial

developments will attract additional traffic and new residential developments will produce

16 'One Suburban County''s Policy for Selecting Median Treatments for Arterials. Bretherton, W. N .. Womble, J. E .. Parsonson, P.S .. Black, G .. ITE Compendium, Technical Papers.'

ltl3~ COll5il!lijG 1)1(;.IR(lll

(

Page 31: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 77 -

developments will attract additional traffic and new residential developments will produce

additional traffic both of which wlll need to be distributed to a large extent by Tecumseh

Rd. E. and intersecting roads. Improvements must be made to handle this traffic safely,

otherwise undesirable diversion of traffic to other roadways will occur, but probably not

before an increase in severity and duration of traffic congestion In the Improvement

Corridor. Figure 4.8 shows the recommended design to handle the traffic flow safely as

the first priority but maintain access as high as possible.

The existing median between Roseville Garden Drive and Lauzon Parkway represents a

case study for why a raised median is an essential design element in the solution of the

identified problems. Along that stretch of roadway, access to 24 businesses is

concentrated at 4 entrances, 2 of which currently allow only right-In and right-out turns.

An important aspect of this arrangement is the intra-parcel access between the East Park

Centre and Parkway Mall.

Figure 3.78 shows that 3 lanes can handle the future traffic flows effectively (V /C < 1.0)

and Figure 3.6 (a) and (b) show that accident rates are much lower because of the

control of left turns at mid-block locations. This limited access concept should be used for

future developments adjacent to Tecumseh Rd. E. and can be implemented effectively

by maintaining the "divided" roadway classification (UAD - urban arterial divided).

A raised median will have at least a short term effect on access patterns used by

customers of the mid-block businesses. The locations where full access was changed to

right-in and right-out Is shown In Figure 4.8.

All existing public roadways intersecting Tecumseh Rd. E. are provided with left turn storage

areas and channelization as required.

4.7 Residual Environmental Impacts and Mitigation Measures

Typically, a recommended design wlll not be able to avoid all potential impacts. The

residual impacts of the recommended design, which represent both advantages and

disadvantages, are summarized in Table 4.4. Where an Impact represents a disadvantage,

measures have been identified which will mitigate the Impact. In some cases, eg. erosion

control, widely adopted construction measures to mitigate Impacts have been developed

i~~ CO~Ulll/lG !NGllll!H

Page 32: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 78 -

and will be reviewed with the appropriate agencies prior to construction. The impacts

included in Table 4.4 have been numbered and are shown on Figure 4.8A-K to Indicate

typical locations where the Impact occurs.

Where a median eliminates left ·turn access to businesses, alternative access Is available

within a short distance by making U-turns at signalized intersections. The traffic signal

turning analysis Indicates that basically ail signals will need opposing advanced left turn

arrows which provide a break in the through traffic to allow the U-turn opportunity. None

of the prohibitions on U-turns In the Highway Traffic Act (Sec. 143) apply to the

recommended design. The City's current Traffic Bylaw (Part IV, Article 7) would not

prohibit U-turns at the median openings proposed.

To demonstrate future access patterns with the raised median In place, the following trips

to various destinations have been routed and shown on Figure 4.8 (numbering sequence

repeated on Figure 4.8.). Although several opportunities exist for provision of intra-parcel

access only those that appear to exist now were used in this examination.

l. West bound motorist heading for Tim Hortons.

2. West bound motorist heading to Shell Gas Bar/Car Wash.

3. West bound motorist heading for McDonalds.

4. West bound motorist heading for State Farm insurance.

5. East bound motorist heading for the Floor Store.

6. East bound motorist heading for the Serbian Centre.

7. East bound motorist heading for Windsor Honda.

8. East bound motorist heading for Anderson's Nursery.

9. East bound motorist heading for Canadian Carpet.

l 0. East bound motorist heading for the Cooperators.

11. Dontrans tractor trailers exiting site and heading east bound.

The geometrics for the above considered only automobiles and single-axle delivery trucks

(see Figure 4.9). Larger semi-tractor trailers would not be able to make the 180 degree

turnaround movements shown. However, it is anticipated that most of those trips would

involve longer distances and an alternative route could be used.

CONHlltNG ING!NIIII

(

Page 33: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

CATEGORY

NATURAL

Vegetation Removal

TABLE 4.4

RESIDUAL IMPACTS TECUMSEH ROAD EAST CLASS EA

JEFFERSON BLVD. TO BANWELL RD.

IMPACT MITIGATING MEASURE

1. removal of random indMdual tress required by wklenlr,g - relocate if feasible or replace

2. landscape areas removed by wklenlng - landscaping redesigned and reconstructed

Erosion I Sedimentation 3. excavation and grading work in and around the Little River channel will - minimize area and time erodab/e so!ls are exposed

SOCIAL

Property

Business

Recreation

Land Use

INFRASTRUCTURE

ROADWAYS

Level Of Service

New Development

Accklents

Pedestrians

Transit

Access

UTILITIES

Water

Hydro

Gas

Bell

Cable

Sewers

increase sedimentation

4. property acqulstion reqired from abutting land owners for widening of the - fair market value, based on market appraisals, paid for any right-of-way land required

5. some businesses cannot continue because Impacted directly

6. some businesses indirectly impacted, eg. loss of parking spaces

7. overpass linkage across Tecumseh Rd. E. provides for greater safety an useability of linear park system

a. setting of roadivay access policy provides for future growth without need to address transJ)0,'1atlon problems al a stage where options may be limit

a. acceptable level of traffic service provided to the end of 20 yr. planning period

9. suitable access to new development areas provided, consistent with roadway access policy

10. preferred design wm result In significant reduction in aecklenls

11. sidewalks provided throughout project

12. existing bus bays maintained and additional bays provided as requested Transit ~ndsor

13. In areas where raised median Introduced, left turns In and out of abutting property removed

14. may be isolated areas where roadway widening requires watermain relocation

15. relocation of some hydro distribution !Ines and arumlnation systems w.11 be required

16. may be some localized re!ocaUon of gas marns required

17. may be some localized relocation of telephone ducts reqlred

1a. may be some relocal!on of TV cable systems

19. storm sewer in!els and laterals will require reconsrtuctlon

20. sanitary sewer construction in new development areas may be advanced

- businesses purchased based on fair market value

- payment made in addition to land purchase cost

- u-tums possible at Intersection openings because of 6 lane cross section on Tecumseh Rd. E. - also have poss!bllityto provide alternative access from the rear of some of the affected properties

- a new Jocation and cost sharing agreement will be negotiated with VvlJC for any pafant requiring relocation

- a new locatlon and cost sharing agreementwm be negotiated with 'A'l.JC for any palant requiring relocallon

- a new loca.Uon will be negotiated with Union Gas for any plant impacted by the preferred design

- a n,m locatlon will be negotiated with Bell Canada for any plant impacted by the preferred design

- a new locallon will be negotiated with Shaw communications for any plant impacted by the preferred design

- this will be done by public works with the roadway widening if schedules permit

- any consrtuct!on of new sanitary sewers or seNices wm be done at the same time as the roadivay widening, schedules permitting, to avoid traffic disruption and impacts on the roadway structure

Page 34: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

Page 35: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 79 -

4.8 Public and Agency Review

As shown on Figure 1.1, a second opportunity Is afforded the public and external agencies

to review the work carried out to develop and evaluate the alternative design concepts

selected to implement the recommended solution.

A notice in the Windsor Star on May 25, 1996 announced the date, time and location of

the second mandatory public input opportunity. The potentially affected public were

notified of the Public Information Centre as follows:

Date: Thursday, June 13, 1996

Time: 3:00 P.m. to 8:00 p.m.

Location: Serbian Centre

6770 Tecumseh Road East

Windsor, Ontario

Copies of the notice and sample letters are Included In Appendix "A".

4.8.1 Agency Input

A copy of the draft ESR was circulated to potentially affected or interested external

agencies. The following table Identifies those receiving draft reports and summarizes the

responses. Those agencies providing comment which required clarification, received follow­

up letters providing appropriate adddltional Information.

CO~IU\l!~G l~G!~!!ll

Page 36: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 80 -

TABLE 4.5

EXTERNAL INVOLVEMENT

AGENCY CONTACT REPLY COMMENTS

l . Windsor Police Service Barry Horrobin Yes - agree with rec-Director Planning ommended option and Physical - warrant for signals Resources at east end should

be monitored

2. Ministry of Natural Resources Fred Johnson No Acting Area Planner Chatham Area Office

3. Ministry of Municipal Affairs Dan Hammond Yes No Comment

4. Ministry of Transportation Peter Ginn No

5. Essex Region Conservation Stan Taylor Yes Need fill permit Authority Water Erosion control

Management needed Supervisor

6. Windsor Separate School James Molnar No Board W. M. Lozinski

Supt. of Education

7. Windsor Board of Education Stephen Payne No Board Mr. A. Cook

Plant Manager

8. Transit Windsor Bob Goody Yes

9. Windsor Architectural Sharon Amlin No Conservation Advisory Committee

10. Ministry of the Environment J. Drummond, No and Energy P.Eng.

Manager, Windsor District Office

11. Ministry of the Environment Donna Watson No and Energy Southwestern Regional Office Technical Support Section

Page 37: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 81 -

CONTACT REPLY COMMENTS

12. Windsor-Essex County Paul Bondy Yes Comments relate Development Commission Commissioner to Lauzon Pkwy.

extension

13. Little River Enhancement Mr. I. Naisbitt Yes Protect quality in Group Little River

Agree with Alt. No. 1 for pedestrian overpass at Little River

14. CN Rail Line Operations Ms. Karen Fraser No

15. Town of Tecumseh Mr. L. A. Lessard No Administrator

16. Windsor Bicycling Ms. Sharon Amlin No Committee Secretary

17. Windsor Utilities Commission Mr. Kent Edwards No

18. Union Gas Ms. Karen Hockin No

19. Bell Canada Mr. Keith Lumsden No

20. Shaw Cable Mr. Esa Wilander No

21. Essex County Field Mr. T. Hurst No Naturalists

22. Citizens Environmental Mr. Rick Coronado No Alliance

23. Windsor Air Quality Ms. Kimberly Telega No Committee

24. Township of Sandwich Mr. Gerald Sykes No South Clerk-Administrator

25. Windsor Fire Department Chief David Fields Yes Concerned about water supply Response times with raised median

Page 38: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 82 -

4.8.2 Public Input

Over 900 notices were malled (or faxed) to abutting property owners and those expressing

a direct interest. Forty-eight individuals are Identified on the sign-In sheets as having

attended the Public Information Centre. After recording their attendance, visitor were

provided with a handout which provided a brief synopsis of the progress of the project to

date. A comment sheet was attached to the handout (copies Included in Appendix A).

In addition to draft copies of the ESR, the following textual and graphic information was

provided on display boards:

The Problem Definition

Schematic of the Class EA Process

Why we carry out Class EA's

Principles followed in a Class EA

Schedules (levels of activity) Involved In a Class EA

Detailed flow chart of the Class EA process

The Study Area

Aerial photo of the Study Area

Plan of existing roadway showing existing and future

and current accident analysis

Schematic cross sections of alternative solutions

Chart showing evaluation of alternative solutions

The Preferred Solution

Alternative design concept sketches and evaluation

charts

Typical roadway cross sections

The Preferred Design

Text

Graphic

Text

Text

Text

Graphic

Graphic

Graphic

Graphic

Graphic

Text

Text

Text

Graphic

Graphic

The following Individuals representing the Project Team were available to provide

information and receive public comment:

Mr. Tedd Szalay, P.Eng. - City of Windsor, Public Works Department

Mr Glen Adams, P.Eng. - City of Windsor, Public Works Department

Mr. Lorne Meloche, P.Eng. - City of Windsor, Public Works Department

Mr. Vince Francescutti, P.Eng. - City of Windsor, Public Works Department

C0HIHIIN$ lNGlUlfS

Page 39: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

(

- 83 -

Mr. Mark Winterton, P.Eng. - City of Windsor, Public Works Department,

Development Division

Mr. Mike Palanacki, P.Eng. - City of Windsor, Traffic Engineering Department

Mr. Wes Hicks, P.Eng. - City of Windsor, Traffic Engineering Department

Mr. Doug Caruso - City of Windsor, Planning Department

Ms. Faye Langmaid, - City of Windsor, Parks and Recreation Department

Mr. Mike Stamp - City of Windsor, Property Department

Mr. Ted Fearnley, P.Eng. - E. Fearnley Ltd., Transportation Consultant

Mr. Barry Sherwood, P.Eng. - LaFontalne Cowie Buratto and Associates Ltd.

Fourteen comment sheets wer~ received relative to the second opportunity for public

participation. In addition, there were several requests for Information or clarification on

the effects the recommended design would have on abutting properties. The individuals

responding were as follows:

NAME REPRESENTING ADDRESS

RESIDENTS

Mrs. Charles Stevenson Resident 9664 Melville Drive

Sharon and Don Turner Resident 10192 Shenandoah Cres.

Donald Fraysure Scarsdale Residents 9565 Tecumseh Rd. E. Association

R. Dean Resident 7040 Tecumseh Rd. E.

Audrey West Resident 2085 Jefferson Blvd.

Biii Prestanski Resident Shenandoah Cres.

James Thrasher Resident 2191 Jefferson Blvd.

BUSINESS

Dino Dilaudo Red Lobster 6575 Tecumseh Rd. E.

Pat Horwood Sr. Commercial Lessor 6033-6045 Tecumseh Rd. E.

Mohammed Abdel-Nab! Chrysler Canada 10940(+/-) Tecumseh Rd. E.

Chris Minielly Wal-Mart Eastown Mall

eo~IV!ll~G l~Glkllll

Page 40: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 84 -

NAME REPRESENTING ADDRESS

Jim Mantua Brewer's Retail 2451 Jefferson Blvd.

Joseph lossifidls Sofos Submarine 6082 Tecumseh Rd. E.

Keith Spence Project Planning FCS 8150 Tecumseh Rd. E. representing Canadian Tire

Joseph Mikhail Tecumseh Commercial Centre 7610 Tecumseh Rd. E.

Rocco Lucente A. A. Boscariol and Associates 10574 Tecumseh Rd. E. representing Messrs. Shaloub and Malette

Rocco Lucente A. A. Boscariol and Associates 11655 (+/-) Tecumseh Rd. E. representing Mr. Docherty

Robert K. Goody Transit Windsor 3700 E. C. Row

John Bonvlvere TRANS-PLAN representing Shell 7555 Tecumseh Rd. E. & Canada Forest Glade

Drive/Tecumseh Rd. E.

Peter Draglcevic Used Car Dealership 6642 Tecumseh Rd. E.

Ed Drouillard Mark's TV 11400 Tecumseh Rd. E.

Simeon Draklch Top Hat East 9250 Tecumseh Rd. E.

Chris Woodall Gus Revenberg 10150 Tecumseh Rd. E.

Norman Shewchuk Anderson Nursery 9666 Tecumseh Rd. E.

John Jedllnski Wilson, Walker, Hochberg, 9420 Tecumesh Rd. E. Slopen representing Big D Bingo Emporium East

Piero Venditti Garden Homes representing 11729 Tecumseh Rd. E. Loeb

G. Gouin Commercial Developer 10530 Tecumseh Rd. E.

Responses were reviewed in detail and specific comment categories identified. A

summary of the public responses Is Included In Appendix A. Some responses Included

several comment categories.

CO!HHIIMG IXGIIU!U

(

Page 41: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 85 -

Eleven of 35 comments were from residents fronting or backing onto Tecumseh Road E.

These comments dealt mainly with direct property Impacts during construction such as

effect on driveways, fences and trees. These Individuals were Informed that reinstatements

to properties will be made during construction such that the end result is equal to or better

than the previous conditions. Where trees cannot be relocated, new trees will be planted

In appropriate locations relative to the new roadway.

One resident expressed concern regarding the high existing traffic noise and Increased

noise resulting from future traffic. The MTO/MOEE protocol Agreement for noise evaluations

was briefly explained and the estimated 3.7 dbA maximum future Increase In noise was

identified at the specific location. It was noted that a 5 dbA Increase in noise Is required

before noise mitigation Is deemed warranted In the Protocol Agreement.

The responses from businesses In the Corridor were mainly focused on the restriction of left

turns to and from the properties abutting Tecumseh Road E. where a raised median Is

proposed. These concerns were acknowledged and the alternatives noted:

- turnarounds at signalized Intersections and

- intra-parcel access arranged between private property owners.

At the extreme west limit of the project, concern was expressed regarding leasing of

commercial properties, which have been Identified for acquisition, In the short term. In

that case, an Interim construction stage was identified to eliminate the uncertainty for

possible lessees.

The need for service roads was identified by some business operators. Service roads would

essentially be the same as intra-parcel access. The Individuals were informed that the City

Is Interested In facilitating appropriate Intra-parcel accesses, but because they would be

located on private property, the City cannot force their Implementation. Many of the

business operators were amenable to that suggestion.

The comments regarding negative effects on business through loss of traffic were

addressed. The Project Team's position that locations such as Red Lobster and the Top

Hat East are planned destinations for most patrons was noted. Therefore, If safe alternative

access is provided, customers will generally maintain their current purchasing levels but

Page 42: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

- 86 -

using a different travel pattern. It was pointed out at the Public Information Centre and

In letters of acknowledgement that a 6-lane roadway carrying the expected traffic without

left turn control by a raised median may induce customers to shop elsewhere.

4. 9 Preferred Design

The Tecumseh Road E. corridor requires a widening of the current 4 lanes to 6 lanes to

accommodate anticipated daily traffic In the range of 21,000 to 30,000 vehicles. Given

the current development pattern along Tecumseh Road E., a raised median Is required to

handle this traffic flow safely.

The range of roadway functions was discussed earlier and It was noted that as the need

to handle higher traffic volumes arises, the ability to provide unrestricted access to

adjacent properties diminishes. The recommended design will accommodate the

anticipated traffic as safely as possible while maintaining reasonable access. However,

there will be unmitigated access effects. Based on the number of responses, those are

expected to be minimal compared to the need for safe handling of the traffic flow.

Therefore, the recommended design as shown on Figures 4.S(a)-(k) was selected as the

Preferred Design.

eo~HtllNG l~GINIIII

(

Page 43: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

=- --..;:;;;:,-

4.0 m ,, . ' .

1.0 m . , . 1.5 m 1.5 m ~ . ' "' (MIN.)

.

* .

TYPICAL BOULEVARD

* - SIDEWALK MAY BE WIDER IN HEAVILY lRA VELLED PEDESTRIAN AREAS

SCALE 1:100

FIGURE 4.1

Page 44: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

3: 0

"' ... 0 .... 'i :::;

4.55 m

1.5m 1.Sm

·1 rT'rP)

-3: ci "" ~ .... 'i ::I

4.175 m

n -

o. Sm

36.0 m IBASIC)

3.65 m 3.65 m 3.65 m S.O m 3.65 m 3.65 m

C/L I i -

36.0 m

3.65 m 3.65 m 3.65 m S.75 m 3.65 m 3.65 m

2.5 m.s 3.25 m

17~ LEFT r~ ........

TYPICAL 8·LANE DIVIDED CROSS·SECTION

(lECUMSEH ROAD EAST - .EFFERSON BOULEVARD TO BANWEU. ROAD) SCALE 1:250

26.2 m (EXISTING)

F: 5.15 m l

3.65 m

3.65 m

TYPICAL 4·LANE WITH TWO-WAY LEFT TURN LANE (LAUZON RO. - TECUMSEH RO. E. TO c.N.R.)

3.8 m

SCALE 1:250

LAUZON ROAD OESIQIATED AS SECOHOARY BIKEWAY (INCUJDES AU.OWANCE FOR 1.5 m EXCl..USI\IE BIKE LANE)

26.2 m (EXlSllNG)

3.65 m 3.65 m 4.0 mm 3.65 m 3.65 m 3.8 m

- -

4.55 m

r, .....

-

4.175 m

r, ......

0.675 m

1.5m {l'Vd.ll) 1.Sm 0.5 m

l ., C/L

r I i - .......

TYPICAL 4•LANE WITH TWO-WAY LEFT TURN LANE (.&FERSlM Bl.VO. - lECUMSEH RO. E. TO ROSE\'lll.E GARDEN ~ )

SCALE 1:250

l

3: 0

"' l3 .... 'i ::i

3: 0

"' l3 .... Sl ::I

FIGURE· 4.2

Page 45: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

I I I I I I I I

I I I I I I I I

~!~. I I l""'I ' I

I I I I I I

I I I AREA m 569 mZ

I AREA - 207 m•!

I AREA m 143 mZ

1---- C/1- OF ROAfJWAY AT C/1- OF RIGHT-Of-WAY

TECUMSEH ROAD EAST CLASS ENVIRONMENT Al ASSESSMENT

JEFFERSON Bl VD. TO BANWELL RD.

ALIGNMENT NO. 2

ALIGNMENT NO. 3

UISlllTIH tUIIHU

ALTERNATIVE ALIGNMENT JEFFERSON BOULEVARD

0 50 METRES

SCALE : 1: 2000 FIGURE 4.3

Page 46: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TECUMSEH ROAD_ EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

SECTION 1

UUIUIIC (UUUU

t

-------------------------------

LEGEND EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

I AREA - e22 m1 I ALIGNMENT NO. 1

I AREA • 1009 m1 I ALIGNMENT NO. 3

0 ALTERNATIVE r""\--_;,- DESIGN CONCEPTS

=, 1::21JOO FIGURE 4.4(al

Page 47: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

I AREA = 1514 m• I

\ \ \

• . • e .._.._.,_ _______ _

ffi~~~~~~~~~~~~~~~~~~

ROSC CITY fDRO 0CAL£R j AREA • 59J m2

II r c:::J

ROS( CITY FCRO VSW CAR

ROSf C1 TY ffiRO OfAl.£R ! AREA • 247 m•

c:::J

'I r ROS£ ON fORO USED CJ.R

ROSE CITY FOll1) DUJ.£R

I I

\

I I

\

I I

\

--D

~

~

ri ~ g ! 0

r1 ~ g ! 0

I AREA = 2240 m• I EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

I AR£A - 429 m•

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON Bl VD. TO BANWELL RD.

I AREA - 133 ~ I SECTION 2

\ I I

toUtlrtU UIIIHU

t

=========='='='="='=====---~-~-=ac:a==============~:"=::::=:='==:":'::~==-~=-=_=_=_=_=_=_~_~--=>===

i AREA • 432 m•

. '

= :r= rr

. . . .

• • •

\\ ALIGNM NT NO. 1

• • •

\\ ALIGN

\ ~·=~·, ~

I AREA= 228 ~ \t PElRO-c>NADA \ SERVICE: STATION I I

\\ Al TERNA TIVE i AREA= 1310 m• l ~ DESIGN CONCEPTS

ALIGNMENT NO. 3 SCPJ.E ' 1,2000 FIGURE 4.4lbl

Page 48: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

I AREA = 1514 m• I

\ \ \

• . • e .._.._.,_ _______ _

ffi~~~~~~~~~~~~~~~~~~

ROSC CITY fDRO 0CAL£R j AREA • 59J m2

II r c:::J

ROS( CITY FCRO VSW CAR

ROSf C1 TY ffiRO OfAl.£R ! AREA • 247 m•

c:::J

'I r ROS£ ON fORO USED CJ.R

ROSE CITY FOll1) DUJ.£R

I I

\

I I

\

I I

\

--D

~

~

ri ~ g ! 0

r1 ~ g ! 0

I AREA = 2240 m• I EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

I AR£A - 429 m•

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON Bl VD. TO BANWELL RD.

I AREA - 133 ~ I SECTION 2

\ I I

toUtlrtU UIIIHU

t

=========='='='="='=====---~-~-=ac:a==============~:"=::::=:='==:":'::~==-~=-=_=_=_=_=_=_~_~--=>===

i AREA • 432 m•

. '

= :r= rr

. . . .

• • •

\\ ALIGNM NT NO. 1

• • •

\\ ALIGN

\ ~·=~·, ~

I AREA= 228 ~ \t PElRO-c>NADA \ SERVICE: STATION I I

\\ Al TERNA TIVE i AREA= 1310 m• l ~ DESIGN CONCEPTS

ALIGNMENT NO. 3 SCPJ.E ' 1,2000 FIGURE 4.4lbl

Page 49: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

'

CAPTAINS HOME OECORATtlC

CJ.B.C. SHC.PPERS DRUG MART

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

SECTION 3

KMART ZDllRS \ "\\ Cll.~lCII. WA.L-MA.Rr /;£>,""'

.I ~I<) si.,p,,,,.,Al<Kt:r

\

I ""!Pi.-,nc

~ Q.

lCSo

--Cl==-----------------------------------------. ----

\~ I NfE.A .. 111M mt I CAPTAINS HOWE MARKS WORK

OECORATNO .....

.-. ..... .....

CJ.B.C.

NO. 1

ICMAAT m..u:RS \ "\\ I \ I

KMART m.uRS

n

-----------------------------------------------------._

0

LEGEND EXISTING RIGHT-OF-WAY PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED ALIGNMENT NO. 3 r---~ SCAU: : 1:2000

Q.

Q.

ALTERNATIVE DESIGN CONCEPTS

FIGURE 4.4[cl

Page 50: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

lAREA•!ISm2 li~©lUJlMl~~IMJ Wd@~[Q) ~~~ii i 16

•A\ ........ JI. ""'"""""""' """"'''"'- . \ ""'""

!~---I "'=,." I

""""" ~ 0·

fl ,,

\ c:::J I \ ...,.., I

\ ~ \ .... , ....

I NfEA - 913 m•

I AREA• 1905 m2

I _...::._-----------------------------------------------1 - ---- - __;__ - --:- ---+--,--

AREA• 9 m2

I NfEA • 890 ml

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

SECTION 4

ALIGNMENT NO. 1

Cl ,c 0 a:

Cl ,c 0 a:

I AREA• 1001 m2

t

t - - -----------------------

COIUllUe EHllt([RS

\ c:::J I I

------------ - - --=-----· ~ - - - - - - - -----,- - - "-'rt'--. ---=---

\ B·W

--

\ -· \~ \

--, . \ I I

\ I cJ h

· __ . i t -,---..,.-----,,---.::µ,.,..,....--. ~

______ 5___ ------------------------- -,.-----;-=

I AREA • 1796 m2

\ c:::J \ t,I\J'l·f \ ~·

LEGEND ( REVISED DEC. 15/97 )

EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

I \ I ,1

'

ALIGNMENT NO. 2

I AREA• 1836 m2

ALIGNMENT NO. 3

SCALE : 1: 2000

......

-· .-

ALTERNATIVE DESIGN CONCEPTS

FIGURE 4.4ldl

Page 51: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

lAREA•!ISm2 li~©lUJlMl~~IMJ Wd@~[Q) ~~~ii i 16

•A\ ........ JI. ""'"""""""' """"'''"'- . \ ""'""

!~---I "'=,." I

""""" ~ 0·

fl ,,

\ c:::J I \ ...,.., I

\ ~ \ .... , ....

I NfEA - 913 m•

I AREA• 1905 m2

I _...::._-----------------------------------------------1 - ---- - __;__ - --:- ---+--,--

AREA• 9 m2

I NfEA • 890 ml

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

SECTION 4

ALIGNMENT NO. 1

Cl ,c 0 a:

Cl ,c 0 a:

I AREA• 1001 m2

t

t - - -----------------------

COIUllUe EHllt([RS

\ c:::J I I

------------ - - --=-----· ~ - - - - - - - -----,- - - "-'rt'--. ---=---

\ B·W

--

\ -· \~ \

--, . \ I I

\ I cJ h

· __ . i t -,---..,.-----,,---.::µ,.,..,....--. ~

______ 5___ ------------------------- -,.-----;-=

I AREA • 1796 m2

\ c:::J \ t,I\J'l·f \ ~·

LEGEND ( REVISED DEC. 15/97 )

EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

I \ I ,1

'

ALIGNMENT NO. 2

I AREA• 1836 m2

ALIGNMENT NO. 3

SCALE : 1: 2000

......

-· .-

ALTERNATIVE DESIGN CONCEPTS

FIGURE 4.4ldl

Page 52: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

1-· ~- ... I

LEGEND ( RE\1SED DEC. 15/97 )

EXISTING RIGHT-OF-WAY

PROPOSED RIGHT-OF-WAY

~ PROPERTY TO BE ACQUIRED

\

\\

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

SECTION 5

ALIGNMENT NO. 1

itl:31! CiUUTIH [HIIEUS

-----.-------...,. :

~-:-.,1,i\-~ ~ -- ------1 \ \ \ 1 I i ! ! '! ·a1 ------,r----..-. -·g. · l. I I· I I I I . .. J \ \ \ \ b i l ci ./.. __ 1 cr.Vl I )J .> l"i

ir-.-t.-Jt::',JJ,-J-~rrnnrliJ t:j..£c-Pn L ~ \ \ \ .---ii . ,- /f,r... \ ~

ALIGNMENT NO. 2

°""'""" ALTERNATIVE ALIGNMENT NO. 3 i-..--

1 DESIGN CONCEPTS

FIGURE 4.4[el SCALE : 1:2000

Page 53: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

SECTION 6

tOISUlrlH U~11££1S

Page 54: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

'

I

I I

I ! ----- H.w.L 1n.30

SITE: PLAN SCAU: 1:1000

n 11 II

NEW l!RIDGE

,--L-...i-, I - I

----- W,L 1nlAQ

I I r~-------------------------------------------------------- -r-------------L-i I I I

L----------------------------------------------------------....1...---------------J SECTION A-A

SClil I: 200

I

I I I

I I ,--L--'-, '----.J

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

w.L 1711.40

SECTION 8-8 SC..U:1:200

I

I I

I I r-L-...J.., L---..1

OWN LINK · FENCE ENQ..CSJRE

( BE't'ONO )

BRIDGE ELEVA TlON OF SECTTON THRU PEDESTRIAN OVERPASS

L---------------------------------...J I I I I I I

,--.a.--'-, L----..1

LITTLE RIVER CROSSING ALTERNATIVES

ALTERNATIVE NO. 1 WIDEN EXISTING BRIDGE AND

CONSTRUCT PEDESTRIAN OVERPASS

FIGURE 4.51al

Page 55: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

SIT£ PLAN SCAI£ 1:1000

IEW Cf\.

2.000 m

K.w.L 1n.ll0

------ W.L 178.50 ( taar LNCE L.E\e. )

'B'

3.MO m 3.MO m

I .

1-------------------------------------------------....CO::~W:::. l-----------------------------------------..1 SECTION A-A

'B'

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

fl l:·::>~r:·:1 ,.,.

-...::::=:::::.:W.::.L 1:75.:i40 · .. ·. ;. • • t ~

_____ ..._ ____ -4

I

,.L-----------J, L----. ... ______ J

NOTE: 11-1£ EAST .fBJllEMT IIAS IIEDI OFFSET N'PROX. 3m l<WAY FRDII 11-1£ Rl\tll TO MJ.1111 Fa! THE P£DESIRIAN UNDEIIPJ.SS le RI.IIPINO.

SECTION B-B 5CALE 1:200

NEW RAISED BRIDGE ELEVA nON WITH PEDESTRIAN UNDERPASS

12:1 SLClPE .

LITTLE RIVER CROSSING ALTERNATIVES

ALTERNATIVE NO. 2 NEW STRUCTURE RAISED TO

ACCOMMODATE PEDESTRIAN UNDERPASS

FIGURE 4.51bl

Page 56: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

SITE: PLAN SCALE 1:1000

r 5.143 m

r 12.400 m

r 12.400 m

r 4.7211 m

-- ------,------T- --,-- ~------~----- I ----~------t------,--=~~T--==::;==---:;: -- ,-----,----1----,----,---,---,---"' ,- ---F===-.- I ,- I I I I I I I I I I I l I l I I I I I I I I I I

: I I I : : : : I I I I l I I I I l I I I I I I I I I I I ...J- aL.. I . J.-----1----J.---L---~----L..---1--L--..l----'------- ----.... --- ..A.,,,, __. ___ __._._ _ _....._ _ _........ ____ ... _c_ ... _ __.. _____ ~ __________ ...._ ----- '·----- --- - -

CONCH![ P6lES1RIAH --SECTION A-A

SECTION THRU PR£CAST CUL V£RT

1

TECUMSEH ROAD . EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

ElCIS11IIO IIRIOOE TO BE 'MllEIE)

------ 11.WL 177,JO

------ w.t. 175.40

BOX SEC11CN

SECTION B-8 SCALE 1: 200

SOUTH OR NORTH ELEVATION

12

LITTLE RIVER CROSSING ALTERNATIVES

ALTERNATIVE NO. 3 WIDEN EXISTING BRIDGE AND

CONSTRUCT TUNNEL PEDESTRIAN UNDERPASS

FIGURE 4.51cJ

Page 57: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

T£CVMS£H LAUNOROMA.i

AREA = 1122 m2

____ ,.. -----

if (g ©lUJlMJ~(g(K] 'ii c:, #.\ [L O@!Nl ~ ~!NJ 1F 'ii

\ i---1

= 628 m 2

CALIFORNIA AUTO CLINIC

AREA

\

VALIANT MACHINE AND TOOL INC,

AREA = 617 m2

= 487 m 2

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

UNHltlMC UCll[IU

\ I I

ROSE CITY FORD USED CAR

AREA 552 m2

ROSE CITY FORD DEALER

•PREFERRED ALIGNMENT' 0 25 METRES r-.-.-, FIGURE 4.61al SCALE : 1:1000

Page 58: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

MUN, I 6424

0

" c, "

j AREA = 115 m 21

ROSE CJTY FD::.:D

AREA = 883 m2

\ I \ I I I I I I

1AUN, #

\ MUN. U

0 \ 6570

D I

\

~ '- _,) ___ ...ii __ _

\ SLEEP

CLEARANCE CENTRE

\ MUN, # \ 6700

D TO SERBIAN COMMUNITY CENlRE

* zzzz'.7j~~:7Y:3:'.:79-:o=~~('.?2".2'2tz?.7.7-2Z7-ZZZ!.Z:~0".2::2:.z7-7-:7.:

0

Z7~,,,..z.·..,...,.......---i~-

\ I I

\ \

I I

\

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

AREA = 391 m 2

\ I I

1,<UtL i

CIIISHIIHC IHIUIU

\

---------------------------------------------------,--- ~~~:;;~~~~~=~==~~~~IOI -~---------------l~ ;:; ----·~- ---

I I

\ I I

\

I I

I I

VAcANr I I I I

' I

n~ Li I I

0 REO LOBSTER

RESTAURANT

0 ~ D

11M

HORTON

OONUTS

d ~

E

--,,- - --- - ---- - ~J- -:!!':$. o ••

e "'• •• "' -- --- :;9"~~ -··~

c?

0 c?

G EAST PARK CENTRE

1PREFERRED ALIGNMENT' 0 25 METRES ~-.-,

SCALE : 1: 1000 FIGURE 4.61bl

Page 59: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

\ t

\

AREA = 39 m2

>,\UN. # 1'126

\l I I

1-,-,-1,.4...,-t-- - - - -- - ~ d --

G o O G " e "'

c:, b\lLU~Wl~~Wlif' ~

\ I AREA = 226 m2 \ I

\ I

\ I

\ I

\ I

\ ~···· I

\ I I

\ I I

B ' '

PETRO-CANADA

SER\f!CE STATION

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

c:,

'S K"""1

~\U I I

CAPTAINS HDME

DECORATING

UUllfllC lKCIUIU

AREA = 518 m2

··~·--------------. ---------------r--~~~--------------------------------------------------

___ ..,-------4: \

\ I \ I

ti.b.TION;,..\.. \ \ ,-RUST \ \

\ I ______ J \

---, -- \ \ I I \ I \ \ \

1,ULI< \ 1,/•RN

\ I \ \ \ I I \ \ \ \ I I I I

I I

\ I I

\

I I

\ I I

~

0

,1•f:IG1'1

~,.1ec1£~- ---­

--; QR\\l(R \1€}\\Clt r,1Ct

l)C£t6£ O

,,_;,.1.11NGO

c1>f£

AREA = 14 m2

•PREFERRED ALIGNMENT' 25 METRES

SCALE : 1:1000 FIGURE 4.61cl

Page 60: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

MARKS WORK

YIEAR

CJ.B.C. SHOPPERS DRUG MART

AREA 775 m2 TECUMSEH MALL

ZElliRS

KMART

,_ ,_

I I

\ I I

\

I AREA = 749 m2

D ______,____ __ L _ -- --- --- --- --

ESSO GAS STATION

TIM HORTONS

TIGER EXPRESS CONVENIENCE

---

AREA 975 m2

lcao

0

_..-,\\o\8 \ l---l flll"· J \ 5065 I eo5' \ ,1u1'1. ,j/ I

B025 I I

\ \ \ I I \

\ \ I

I

\ \ \

I I

\

- --

I J

I MUN.#

\ 8151

\

\

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

HISlllll~ IKCIKHRS

I

I I

I

·, I I

AREA = 1174 m2

-~~-------,.

I I I I I I I I I I

I I I I I I I

I

~

•PREFERRED ALIGNMENT' o 25 METRES

~-~ FIGURE 4.61dl SCALE : 1: 1000

Page 61: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

ir~©lUJ~~[glMJ t=:::J-------------------- ~~©"iiD@WI ~ c:, ~rr:,o@WJ~~Wl"ii ~

j AREA = 1113 m2

AREA = 129 m2 \ \ \

.-·

----

I AREA = 1317 m2

/ ( REV1SEO DEC. 15/97 )

LEGEND

-- EXISTING PROPERTY LINE

· - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

--------

~~<C"iiO@WI @ c:,

~rr:,a@wi~~wi"ii ~

PAPA JOHN

CENTRE

-------------~

Ltl:311 UUUlTIU £UIIHU

'PREFERRED ALIGNMENT' 0 25 METRES

r""w,•J-i SCALE : 1:1000 FIGURE 4.61eJ

Page 62: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

---------------------

"10' I d i p

\ x I x I

x \

\

~

( REVlSED DEC. 15/97 J

LEGEND

-- EXISTING PROPERTY LINE

- · - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

FRANCOS PIZZA

9940

0

COUN"TRY STYLE

DDNLITS

FOREST GLADE CINEMA

FOREST

GLADE

HIROPRACTIC

I AREA = 2545 m2

SHELL STATION

WINDSOR

M A Z D A

MUN. 10080

0 • LS

.ts • LS

+

•LS .ts

--------------

0

0 [] PETRO CANADA

STATION

0 ~

.ts GUS REVENBERG

PARKING LOT 0

TECUMSEH ROAD EAST LtBII CLASS ENVIRONMENT AL ASSESSMENT """"" '""""

JEFFERSON BLVD. TO BANWELL RD.

MUN. 10280

.ts ,LS

CANADIAN CARPET CHRYSLER

CANADA LlD,

--------------------------------

-------------- ---------------------

•PREFERRED ALIGNMENT'

SCALE : 1: 1000 FIGURE 4.61fl

Page 63: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

\ \

CHRYSLER CANADA LID.

I AREA = 5BB m2 I

\ \ \

WiNDSOR JEEP EAGLE

-----------------------------------------------------

oo g T I " x

. I

"l +

( RE'1SEO DEC. 15/97 )

LEGEND

-- EXISTING PROPERTY LINE

- · - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

10660

WINDSOR

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

I AREA = 602 m2

D +

COISHllH (HIUtlS

'PREFERRED ALIGNMENT' 0 25 METRES

~-~ SCALE : 1: 1000 FIGURE 4.6[gl ,

Page 64: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

tUSUlTIU UCIIE(I!

r----- $~©iFD@[M ~ c

~O:.O@!Nl~~!NliF ~

---r-::::>!-=--i--------------------- $~©iFO@!NI ® c:, ~O:.a@!Nl~~rMiF $ ----------------------r:::::::>r:::::::=-1

I AREA = 429 m2

\ ~

110D3 \

I AREA = 113 m2

( REV1SED DEC. 15/97 )

LEGEND

-- EXISTING PROPERTY LINE

- • - • - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

I AREA = 1290 m2

CO-OPERATORS L&AAUTO

11210 & 11236

----

c;:::::> c;::::;

---VISUAL CONCEPT \

DESIGNS

\ \ \ \ \ \ \

--l--.\.;..._-A_\ _ \_ ---- - - --...1

G)

~~ ~l! 0 ,o\_t;, \ 'JI!

~~ n= \

\oi \

0£ \

~~ \ ~

'PREFERRED ALIGNMENT' 0 25 ME1RES r-.,-..-,

SCALE : 1:1000 FIGURE 4.61hl

Page 65: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

---

. \

---

\ \

11646

PERCIBALLI

POOLS

---

11646

J

----

\ I AREA = 1285 m 2

( REVISED OEC. 15/97 )

LEGEND

-- EXISTING PROPERTY LINE

- • - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

11702

L J

\ \

\ \ \

\

11744

TECUMSEH

SERVICE

CENTRE

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

-------------- -----...--\ - - - -

\

LOEB SUPER MARKET (VENOITII)

U11Stl111t IIIUIHU

'PREFERRED ALIGNMENT' 0 25 METRES

FIGURE 4.6111 ~-..-, SCALE : 1:1000

Page 66: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

I

I I

I

-- - ----

f 2D17

' I UN' I ' 200fl

I I

I

I I

ll ~. \'-'" 1~ I

,,I - _1....... ~\~

I

ANDRE CLOTHING

SASSYS SC!SSO'<S

I

I_U lttt~i{------

I I I

I I I • I

VAUANT MACHINE AND TOOL !NC.

--------------------------------_,!! __ _

---~rt~~~-1 __ -ci --:r~-- --4---, -.....-,...__..'-,-,'1 ~~-~:= .. ~· .. =······

I I

"' ;, !#

i !# ~

I I

CALIFORNIA AUTO CUNIC

COPE CONSTRUCTION

WORLD V.1DE BEDROOMS

PAQUETTE WINDOWS

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

RUSSELL OFFICE

l'ilNKS SUNOCOC

SUPPL y HUCKER'S

p=--'E'3"-r---1 FLOORING

s 0 s

w > <I: Ill VJ 0 a:

CITY OF Y.1NDSOR DAYCARE

'PREFERRED ALIGNMENT' 0 25 METRES

•• I 11111..., SCALE ; 1;1000 FIGURE 4.61jl

Page 67: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

BURGER KING

I AREA = 703 m 21 I CAR WASH

D :::::::., ~- tER EXPRESS I ONVENIENCE

r----

iECUMSEH MALL

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEf FER SON Bl VD. TO BANWELL RD.

n MUN.# u 8025

-----

ASPHALT

I- 0

I DORCHESTER I APARTMENTS

m I

----

•PREFERRED ALIGNMENT' 0 25 METRES

FIGURE 4.6[kJ

Page 68: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

t ROSE cir ..fY" AVENUE

~ i

TECUMSEH cir

TECUMSEH S

TECUMSEH

* ut.mul'E WHDI L,<UZCfl PARXVIAY IS EX1EIICED

===-===-~

,£}>-c::=-

===-~

~~t zO oo:: "':!: o::~ ~::, wo ..., CJ

! -= t if ROAD EAST

1~ -=::2S

t -==-I -==-i 'lf ROAD EAST

i ~l w --'z ~~~ We,::-"'<o:: ~c.,O

,~ ~ t -==--==-if ROAD EAST

i ~~

w t;~g:~ i:St~12 c..,O

1~ ~ t -==-! -==-

lECUMSEH cir if ROAD EAST.

===- i c::=- ~t ~

w \!,I:,

~~ <<

I -= lECUMSEH s--+-..(F"

===- i

; ~~~ Oo N< ~~ --'

t ROAD EAST

,~ = t TECUMSEH ,£}>- -f-- ..fY" ROAD EAST

===- i

; J~ I-

~ ~~ o::d_ 0 0:: ... 0

I = t lECUMSEH --f- 'lf ROAD EAST

lEa.JMSEH

===- i ===- ~ ~ ~

,£}>-

===-===-~

1-W w ~z CJ< 0...1 0::

,~~

i

~~~ ~~ zo <O:: CD

,~~ !

~

t -==--==-if ROAD EAST

~ t TECUMSEH ,£}>- - if EAST OWN

MAU. ~ i

~~~ MAU.

z ~~ ~o --' 0:

SCHEMA TIC INTERSECTION CONFIGURATION

FIGURE 4.7

Page 69: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

--------

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

I I

~ l I

~

\ --L--- __ __

L ___ ::

CAUFORNIA AUTO CLINIC

\ I I

\ I I

\ I I

AJAX BUILDING SUPPLIES \

I I

\ I I I

I

\ [;) I

/I

VALIANT MACHINE AND TOOL INC.

\

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

GREEN FOREST LUMBER

\ \ ~-----•---~ I I I I

I \ \ I '\

POSSIBLE FUTURE

EXTENSION

I \ \ MVN, R , \ \ \ \ \ Cj\1\,1\

\ \ \ \\ \ 'I I \ \ \ \ \I \ \ I

\ \ I \ l \ \ \

I 'i I\\\ '

\

I ~ \! * \ \ \

/ \ I ', \ I.) I ' / \/ ', \ ' ._ __ _

ROSE CITY FORD USED CAR

ROSE cnY FORD DEALER

1RECOMMENDED DESIGN' 0 25 METRES

SCALE : 1: 1000 FIGURE 4.Slal

Page 70: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

\ MUN. i \

C,424 \

D \ CAR

G e e

---

I

VACANT I

\ I I

\ ROS?. C' T't rORD

\ I \

MU~· I

\ MUN. G

0 6570

\ D I

\, \ \ ,,

\ \

~ ri ~ ~ 9 ~ 0

~ 0

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

\ \ \

I I

\

~ D TIM

HORTON

DONUTS

RED LOBSTER

RESTAURII.NT

a ~ ~

0

\ POSSIBLE FUTURE

EXTENSION

SLEEP

CLEARANCE CENTRE

0

MUN. # \ 6700

D

* *

TO SERBIAN COMMUNITY CENTRE

10RONiO ,uR\1\IUR(

[O

CJ

CJ

\ \ \ I

\ I

\ \ ,,\l>' # \ I

\Q\ I I\ \ \ ) I

' ___ _/

EAST PARK CENTRE

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

CIMHlflU fHIIHU

\ POSSIBLE FUTURE

EXTENSION \ I

\

•RECOMMENDED DESIGN'

0 25 METRES

SCALE : 1: 1000 FIGURE 4.Slbl

Page 71: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

\ I

\ M\JH. f

·11,& r-.... \ \

------~ t::1 --

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

-~--· _.., \ I I \ \

""Tlot'>-l \ \ -ntusi I i

\ \ ____ ..J \

-------~ I \ I I I I I \

eu'-"' \ e"Rl'I

I \ I \ I I I \ \ \ \ \ \ \ I

\ PETRO-CANADA

SERVlCE STATION

I I

\ I I

\

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

0

~1GH•

~";01£\\S ----

-;;;;~\< ~\-1\Cl ff\CE ucu,sE o

n.>-'l\\'lGO

CAPTAINS HOME

DECORATING

'RECOMMENDED DESIGN'

25 ME1RES

SCALE : 1:1000 FIGURE 4.Slcl

Page 72: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

MARKS 'NOOK

'N(AR

C.I.B.C.

ZELLEF~5

SHOPPERS DRUG MART

TE:GUMSEH MALL

·o

\

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

KMART

\

ESSO GAS STATION

TIM HORTONS

TIGER EXPRESS CONVENIENCE I CAR WASH I

----

Lceo

I

_....-,\\cJ\9 \ \_-_..) µ\JI<· # \ 3()65 I

e,Q5\ \ M\Jt<. # I

so25 1 1

\ \ I I

~ \ ASPI-IAL1

I I

,--:) \

---

I 1

I MUN. #

\ 8151

I I

\

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

I I

-' --·---L_.-1.,,,L_ ----------,.

I I

I

I

SIT[ PLAN APP CANADIAN Ti LICA TION BY

IRE PENO/NG

I I I I I I I

CHHlrtH lUIUUS

,RECOMMENDED DESIGN'

0 25 METRES

SCALE: 1:1000 FIGURE 4.8(dJ

Page 73: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

/

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

( REVlSED DEC. 15/97 )

LEGEND

-- EXISTING PROPERTY LINE

- · - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

FUTURE EXTENSION TO EAST RIVERSIDE PLANNING DISTRICT

\

POSSIBLE FUTURE EXTENSION

OF SCARSDALE ROAD

-0

1 ~

Ci)

~ FIRESIDE INN ~

tC\

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

APARTMENT

PAPA JOHN

CENTRE

'RECOMMENDED DESIGN' 0 25 MElRES

FIGURE 4.Slel r-.,•-t, SCALE : 1: 1000

Page 74: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

0

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

FRANCOS PIZZA

9940

COUNTRY smE

DONUTS

FOREST GLADE CINEMA

0

"

0 SHELL

STATION

\

WiNOSOR

MA Z DA

MUN. 10080

0

,LS

PETRO CANADA

STATION

,LS GUS REVENBERG

PARK!NG LOT 0

,LS

TECUMSEH ROAD EAST liBI! CLASS ENVIRONMENT Al ASSESSMENT ................ ...

JEFFERSON Bl VD. TO BANWELL RD.

MUN. 10280

HUNT

WINDOWS

CAAADIAN

CARPET

1RECOMMENDED DESIGN'

0 25 METRES

SCALE : 1:1000 FIGURE 4.81fl

Page 75: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

\ A;.:MCORP ?-21 LTD.

\ \ \

CHRYSLER CANADA LTD. \

LEFT nJRN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

TYPICAL LOCATION OF IMPACT

( REVISED DEC. 15/97 )

LEGEND

EXISTING PROPERTY LINE

- - - FX!ST!NG EAS:::MtNT UNE

---------- NcW PROPCRTY UN[

FUTURE EXTENSION TO EAST RIVERSIDE PLANNING DISTRICT

10660

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

;

' 07 I

~ ].----'-----,0 j~~[SJLJ, ol~ / 1 · ; I

•RECOMMENDED DESIGN'

0 25 METRES

r'!,.·.18i FIGURE 4.Slgl SCALE : 1: 1000

Page 76: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

POSSIBLE FUTURE ACCESS TO INDUSTRIAL AREA

,. " \ .,, \ " .£ \

i\ •<" \. ~ /'

/+ \ ~\ +

'/ ", t"'" \ ~ .<\

~\ 11\

\

\ \ \

\ \

\

LEFT TURN IN AND OUT PROHIBITED (NUMBER CORRESPONDS TO TABLE 4.4)

&TYP TYPICAL LOCATION OF IMPACT

CO-OPERATORS L&AAUTO

LEGEND

( REVISED DEC. 15/97 )

-- EXISTING PROPERTY LINE

- · - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

DONUT 11302

VISUAL CONCEPT

DESIGNS

TECUMSEH ROAD EAST CLASS ENVIRONMENTAL ASSESSMENT

JEFFERSON BL VD. TO BANWELL RD.

\

\

\

\\ FUTURE EXTENSION \ TO BANWELL ROAD

\ \ \

\ \ \ \ \ \ \ \\ \ I \\ \

0 25 MElRES

CQUUlftH fMl:llHU

FIGURE 4.Slhl ~-...-, SCALE : 1:1000

Page 77: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

11646

·-·-\ \ \ \

\ \ \

( REVISED DEC. 15/97 )

\ LEGEND

EXISTING PROPERTY LINE

- · - · - · - EXISTING EASEMENT LINE

---------- NEW PROPERTY LINE

\

11744

TECUMSEH

SERYlCE

TECUMSEH ROAD EAST II CLASS ENVIRONMENT AL ASSESSMENT ,mm .. , "'"""

JEFFERSON BLVD. TO BANWELL RD.

- - ----:

·-·-·- ,· ·-·-\

LOES SUPER MARKET (VENDITTI)

'RECOMMENDED DESIGN'

0 25 MElRES

r-.•J-i SCALE : 1:1000 FIGURE 4.8111

Page 78: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

,.. !

,

I I ,~g

"' ANDRE

'"' CLOTHING

"' E SASSY'S ,: SCISSORS

I &a , .. I

trk';j· ~

s "

L!i'.cl' 4' :, "'~ ) ...

5 II.I 0 ,-o/ ..

i I ,

\ < Q;, 0

I • ~- .,.o,--r I - r

.- -

I {'.

I

I , I "', I I

2009 I I I

I '_Li' I

I I I

VAUANT MACHINE AND TOOL INC.

CALIFORNIA A\JTO CLINIC

COPE WORLD W\OE CONSl'RUCTlON ElEDROOMS

Zc

~6 -~ "w eU

" ~" w

;!:~(..) " oO ~ >w

o<z 0 oO zw- " Oa

" r Zo w Oo

" DI Oo We

PAOUEnE WINDOWS

m . 0

"u ~" "" <oo ww rn <

a 8 0

~ " " < 0

TECUMSEH ROAD EAST LeBl!I CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

1un,,,o umu ..

il <"< i:j~g:c; -· ", <C D> eO Ow !e

ill ...lz :::! ill >O ill a: (/) cc Oc, a:

LI.I Cl)

0 a:

\\lNKS SUNOCOC

'RECOMMENDED DESIGN'

0 25 METRES r--•,,/"11 FIGURE 4.8ljl SCALE: 1:1000

Page 79: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

EAST0\11'< MALL

I

TECUMSEH MALL

I ""~~

D 1::£, ~- t.ER EXPRESS I ON\/ENIENCE

TECUMSEH ROAD EAST CLASS ENVIRONMENT Al ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

n MUN. H u 8025

-----

BANK OF ~ONTREAL ASPHALT

0 .... LI.I

--+-- LI.I a:

It­u, c Q z c ...I 0 >

UUIHIU tllltHUS

----

I DORCHESTER I APARThlENTS

fil I

,RECOMMENDED DESIGN'

0 25 METRES ~-.-, FIGURE 4.81kl SCALE : 1: 1000

Page 80: -57 - 4.0 ALTERNATIVE DESIGNS Roadway Cross Section 4.1.1 ... · 4.1.1 Travelled Pavement The roadway capacity analysis carried out In the Traffic Analysis and Planning Report assumed

co (\j

TECUMSEH ROAD EAST CLASS ENVIRONMENT AL ASSESSMENT

JEFFERSON BLVD. TO BANWELL RD.

TYPICAL TURNAROUND MOVEMENT FROM LEFT TURN STORAGE LANE

0 25 MElRES

'11'1!CUH81!1Hl ROAD EAST ( PROPOSED )

\\ ;, PASSENGER CAR

Leading Outside Tire Radius = 7.50 m *

inECUHSEIHI ROAD UST ( PROPOSED )

-

SINGLE UNIT TRUCK Leading Outside Tire Radius = 7.50 m *

* MINIMUM RADIUS= 6.0 m

LtBII (l)IHlflJC. {HIIUtS

t

r--•J1 SCA!..£ : 1: 1000

FIGURE 4.9