56561935 Program Narrative Report 24 March 2011

download 56561935 Program Narrative Report 24 March 2011

of 17

Transcript of 56561935 Program Narrative Report 24 March 2011

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    1/17

    Mumbai

    International

    Airport

    Phase

    II

    &

    IIISubcontract# T2/22.10A&B Supply and Installation of AcousticMetal & Gypsum

    False Ceiling.

    SubcontractorDetailedProgramNarrative

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    2/17

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    3/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    1. Introduction.

    The intent of this narrative report is to present a description of how the Subcontractor

    has formulated his detailed program of work. This narrative when read in conjunction

    with the detailed program shall explain the sequence, logic and planning methodology

    utilized by the Subcontractor when constructed his baseline program.

    The Subcontractor has used a licensed Primavera Project Planner P3.1 Version to

    develop this program and all the related manpower calculations and histograms and

    resources.

    1.1. Contents

    This program narrative consists of the following detailed Sections:

    Contractual Compliance.

    Project Phasing Layout and Building Numbering.

    Program Structure and logic.

    Program Constraints Definitions.

    Resources Loading.

    3

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    4/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    2. Contractual Compliance

    This program has been developed based on the correspondences received from the

    Contractor which are related to the accessibility to site constraints, also it defines clearly

    the contractual milestones specified for the project completion and trials. Also it is to be

    noted that all the contractually specified durations have been taken into consideration in

    this program.

    Moreover the sequence and breakdown structure has been also developed based on

    the instructions received from the Contractors planning department.

    4

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    5/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    3. Project Phasing Layout and Building Numbering.

    The below schematic Diagram shows the airport phasing according to the priorities

    defined by the Contractor.

    The entire Subcontractors scope of work includes the areas defined as Phase II.

    Each Phase of the above phases has been internally divided into areas in which each

    area has been later divided into floors/levels as per the following schematic diagram.

    5

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    6/17

    Lindner llmmInteriors MumbaiInternationalAirportPhase IISubcontract-# T2/22.10A&B Supply and Installation ofAcousticMetal&

    Gypsum False Ceiling

    Subcontractor Detailed Program Narrative Reportand Methodology

    10

    8

    5

    33A

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    7/17

    ---------1( 4 )--------

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    8/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    4. Program Structure and Logic.

    The program has been divided in addition to the previous two classifications to three

    general global levels, under each level there are different types of classifications

    according to the discipline or the physical sequence needed as per the following chart:

    Accordingly, the program Layout has been organized using the above different levels of

    organization and the activities have been Identified in the same manner as per the

    following table.

    This structure is also matching with the general structure specified by the Contractor

    and sent to the Subcontractor via e-mail sent on 9 th March 2011.

    8

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    9/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    Activity IDs and coding system

    PRIMAVERA PROJECT PLANNER

    Date 09MAR11 -----ACTIVITY CODES DICTIONARY----- Page 1

    MIA1 - Mumbai Intl Airport- Ceiling package

    ---------------------------------------------------------------------

    CODE VALUE TITLE SEQUENCE

    --------------------------------------------------------------------------------

    Activity Codes:MATR Material Code

    0 Substructure

    1 CLG01

    2 CLG02

    3 CLG03

    4 CLG04

    5 CLG05

    6 CLG06

    7 MP04

    Activity ID Codes:TYPE Work Type

    MI Project Milestone Dates 1

    GN Pre-Construction Stage 2

    CN Construction Stage 3

    DIVI Division

    ENG Engineering Work 1

    FMI Finish Milestones 1

    PRO Production and Delivery 2

    P02 Phase II 3

    P03 Phase III 4

    DISE Dscepline04 Area 4 1

    3A Area 3A and Ramp Portion 1

    4A Area 4A 1

    LD LD Completion Dates 1

    RM Raw Material Procurement and Preparation 1

    SW Shop Drawings 1

    03 Area 3 2

    9

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    10/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    11 Area 11 2FA Factory Production 2

    SA Material & Samples 2

    10

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    11/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    05 Area 5 3

    1A Area 11A 3

    DE Delivery to site 3

    07 Area 7 4

    7A Area 7A 4

    09 Area 9 6

    10 Area 10 6

    9A Area 9A 6

    08 Area 8 (Statue Area) 7

    FLOR floor1F 1st Level 1

    P2 Phase II Finish dates 1

    SU LD Submission 1

    2F 2nd Level 2

    AP Client Approval 2

    M0 Mockups 2

    P3 Phase III Finish dates 2

    3F 3rd Level 3

    4F 4th Level 4

    11

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    12/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    4. Subcontractors Sequence of Work and program constraint definition.

    The priority for each building/Area has been defined previously by the Contractor as per

    the following graph.

    75

    5 57

    4 6

    4

    13

    1

    2 7

    The above priority has been incorporated into the program based on the accessibility to

    site.

    12

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    13/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    The Accessibility to site also has been provided to the Subcontractor from theContractor via an email sent on 7 th march 2011, where there is clear identification for

    the Access for each individual building and individual level.

    13

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    14/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    The access dates shows in some buildings that the Subcontractor, will be having

    access to the same level twice as per the restriction due to the existence of the statue.

    It is to be noted that this access in order to be beneficial for the Subcontractor and to

    help better progress on site, the access shall be preceding by the completion of all the

    following activities to avoid any interruption or disruption of the Subcontractors work:

    I. Completion of All Duct works.

    II. Completion of Cable trays.

    III. Completion of Conduits.

    IV. Completion of Drainage Pipe works.V. Completion of Fire Protection Works.

    VI. Completion of Plumbing Works.

    VII. Completion of all any other Mechanical/ Electrical works.

    The Subcontractor will not proceed with installation of sub frames or paneling until

    access document is officially signed off as being complete, by all responsible interfacing

    or preceding Subcontract Trades.

    The construction activities have been developed starting from the access date

    milestone that has been constrained with an early start constraint as specified by the

    Contractor followed by all the subsequent activities.

    As per the project specifications and the suppliers specification with reference to DIN

    EN 13964, the installation of any acoustical panels will require a controlled environment

    in terms of Temperature as well as the Humidity, this will require the Contractor to give

    the Subcontractor the access associated with a closed envelop and supplied with a wild

    air in order to control the Temperature and the Humidity.

    Therefore, the Contractor is required to provide a schedule of the faade works

    completion dates along with the wild air required for the installation process and this will

    be again incorporated in the program.

    The regimen of access controls to a great extent the peaks of the Manpower needed as

    the access to the all buildings will be mostly given to each bundle of buildings in one

    time span, this controls the existence of the Subcontractors manpower and creates

    peaks and dips in the manpower histogram.

    All the subsequent activities are linked to this start milestone as well as to the related

    activity that has direct physical relation with this activity. Also all the construction14

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    15/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    activities have predecessor activity related to the design, production, and delivery to

    15

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    16/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    site, this have controlled the closure of all open ends and ensures proper critical path

    development.

    The program has included some control activities that could be the driving factor to

    proceed with the next step, in all cases these driving activities are related or should be

    given by the Contractor to allow the Subcontractor to proceed forward. One of these

    critical control activities is the receipt of the chandleries locations and hanging point that

    will be affecting the commencement of design of the Subcontractors substructure and

    bridging drawings and accordingly will affect the production of the substructure and

    panel materials.

    At the end of each phase, there is a particular section defining the finish milestone dates

    for that particular phase as well as the project opening and trials.

    16

  • 7/29/2019 56561935 Program Narrative Report 24 March 2011

    17/17

    Mumbai International Airport

    Phase IISubcontract# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum

    False CeilingSubcontractor Detailed Program Narrative Report and Methodology

    5. Subcontractors Material quantity and manpower

    Loading

    In order for better monitoring and controlling over the project, the program has been

    fully loaded with the material quantity. This will help the Subcontractor to clearly

    determine the required material from each type of the ceiling material for a certain

    period, and to help the control over the inventory.

    The Manpower histograms also help the Control over the required number of Manpower

    per month or even per week. This will provide a clear image about the peaks that need

    special measurements.