5 Year Capital Replacement Program -...

124
5 Year Capital Replacement Program FY2019 DRAFT

Transcript of 5 Year Capital Replacement Program -...

5 Year Capital Replacement Program

FY2019

DRAFT

 

 

Five Year Capital Replacement Program 

FY2019 

  

BOARD OF DIRECTORS 

Justin McCusker President 

 

Saundra F. Jacobs Vice President 

 

Betty H. Olson, Ph. D. Director

Charley Wilson Director 

 

Charles T. Gibson Director 

    

Overview  

The Santa Margarita Water District’s (District) Five Year Capital Replacement Program (CRP) is a 

projection of the District’s capital funding requirements for planned capital replacement 

projects from Fiscal Year 2019 through Fiscal Year 2023.  

This planning document outlines the proposed projects for the next five years and provides an 

overview of the upcoming replacements throughout the domestic water, recycled water, and 

wastewater systems. The project costs provided are planning estimates and are to be reviewed 

each year to confirm applicability. This document is not a cashflow projection but a listing of 

proposed projects.  

The CRP is just one component of the Capital Improvement Program (CIP). Each of these 

components provides a specific function to the overall CIP.  

 

Capital Replacement Program The District must continue to reinvest in its infrastructure to maintain its high level of service to 

its customers. Due to the age of the District and the timing of its development phases, much of 

the District’s linear infrastructure (pipelines) are in the middle of its life‐cycle. In time, the need 

for pipeline replacements will increase. However, mechanical and electrical equipment, as seen 

with the Chiquita Wastewater Treatment Plant, must be upgraded over time as infrastructure 

wears and to address regulatory requirements. The District also has an obligation to contribute 

a proportional share to the upgrade of regional or shared facilities.  

Capital Improvement Program (CIP)

Capital Replacement Program (CRP)

Development Reliability

These projects are typically greater than $50,000 and are required to maintain the level of 

service that SMWD expects. They have historically been funded through rates with sometimes 

with the usage of reserves. New approaches to funding the proposed CRP are being developed 

and will be produced in a subsequent document.  

Development Projects The District expands system capacity and extends infrastructure to serve new development as it 

occurs. These projects are identified based on projected growth rates by geographic area. 

These projects are undertaken specifically to serve new development rather than to benefit 

existing customers, and costs are funded by local community facility districts or developers.  

Reliability Projects Reliability projects enhance the District water supply portfolio to decrease reliance on imported 

water and provide a sustainable source of supply in case of emergencies. These projects are 

also necessary to meet the District’s stated objectives to fully recycle all wastewater by 2019 

and achieve 30 percent local water supply by 2030. Recycled water and other local non‐

domestic projects provide a direct and indirect benefit to the District’s water customers by 

lowering potable water use for irrigation, thus freeing potable water capacity for other users, as 

well as by decreasing long‐term imported water costs and providing a drought resistant water 

source. All of these possibilities have the ability to continue to move the District towards 

greater water independence. Below is a short list of projects under consideration that the 

District is working on as part of Reliability Projects: 

‐ Expansion of 3AWRP 

‐ Oso Creek Barrier treatment 

‐ Recycled water conversions  

‐ Recycled water conveyance projects 

‐ San Juan Watershed Project 

‐ Alternative local water supplies 

‐ Talega / City of San Clemente 

wastewater diversions 

Since these projects are designed to support the strategic goals of the District, there are options 

on the financing and timing of these projects.  

 

   

Overview  

The project listings within this workbook are shown with their estimated costs associated with 

the beginning of the project. For instance, a project that starts in 2020 and goes until 2023 will 

show the entire project in 2020 with no costs spread over 2021, 2022, and 2023. The rationale 

behind this is that funds must be available for a project at its inception, not its conclusion. 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

01 ‐ Domestic Water System 1,865,000$     1,652,200$     1,927,000$  1,096,400$  2,728,400$  820,700$     

02 ‐ Recycled Water System 50,000$           470,000$        560,000$      1,170,000$  850,000$      703,400$     

03 ‐ Wastewater System 1,477,500$     6,595,000$     705,000$      1,365,000$  1,210,000$  1,260,000$ 

04 ‐ Chiquita Water Reclamation Plant 2,710,000$     3,963,300$     65,800$        780,000$      450,000$      1,905,000$ 

05 ‐ Oso Creek Water Reclamation Plant 500,000$        750,000$        54,800$       

06 ‐ 3A Water Reclamation Plant 7,805,000$     10,749,000$  400,000$      650,000$      700,000$      600,000$     

07 ‐ Outside Agency Capital 2,639,000$     5,036,413$     2,193,523$  4,255,963$  2,189,612$  1,375,416$ 

08 ‐ Overhead 170,000$        995,000$        150,000$     

Grand Total 17,216,500$  30,210,913$  6,056,123$  9,317,363$  8,128,012$  6,664,516$ 

01 ‐ Domestic Water Projects Projects associated with the repair, maintenance, and improvement of the domestic water system. 

 

 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

Altisima Z5 PS ‐ Upgrade jockey pump 85,000$          

AMP Z1 PS ‐ Investigate/Repair subsidence 150,000$     

AMP Z1 PS ‐ Rehab 4 pumps 87,000$       

Antonio Z3 PS ‐ Replace MCC on Pumps 5+6  330,000$       

Antonio Z3 PS ‐ Replace switchgear and MCCs on Pumps 1‐4 725,000$       

Aurora Z2 PRS ‐ Install SCADA monitoring 50,000$          

Domestic Water ‐ Cathodic Protection 600,000$     

Domestic Water ‐ Placeholder 500,000$      500,000$      500,000$     

Domestic Water ‐ Remote monitoring of cathodic protection 300,000$     

Domestic Water ‐ Replace 40' of pipeline in RSM 80,000$          

Domestic Water ‐ SCADA Phase III 300,000$       

Domestic Water ‐ SCADA Replacements 142,200$        200,000$      171,400$      128,400$      95,700$       

Domestic Water ‐ Valve Replacement Program 225,000$        225,000$      225,000$      225,000$      225,000$     

Empresa Z3 PRS ‐ Install SCADA monitoring 50,000$          

Estado Z4 Res. ‐ Install res. management system 660,000$       

Florecer Z1 PRS ‐ Install SCADA monitoring 50,000$          

Foothill Z4 PS ‐ Upgrade switchgear 250,000$     

Island Pasture Z3 Reservoir ‐ Install CP array 105,000$       

Lakeside PS ‐ Engine overhaul 500,000$     

Lakeside PS ‐ Replace soft starts 55,000$       

MNWD Intertie @ Via Noveno/Los Alisos ‐ Rehab intertie 65,000$          

Plano Z4 Reservoir ‐ Resurface exterior 775,000$     

San Fernando Z1 PRS ‐ Install SCADA monitoring 50,000$          

South County Pipeline ‐ Inspect pipe wall thickness 200,000$     

Talega Z1 Res. ‐ Install res. management system 550,000$       

Trabuco Ridge Z4 Res. ‐ Install  res. management system 660,000$     

Via Noveno Z2 PRS ‐ Install SCADA Monitoring 50,000$          

Grand Total 1,865,000$     1,652,200$     1,927,000$  1,096,400$  2,728,400$  820,700$     

CAMP #: STAT‐04.01.19002 

Project Name: Altisima Z5 PS ‐ Upgrade jockey pump 

Project Location: Altisima Z5 Pump Station 

Total Budget: $85,000  

Project Date: 2019 ‐ 2019 

Background: Altisima Pump Station was constructed when the distribution system in the area was a 

closed loop system with less customers and no reservoir serving the local area. Once the area became 

more populated, Rancho Trabuco Reservoir was constructed in 1991 and the system became an open 

loop system which changed the flow pattern seen at Altisima Pump Station. 

Justification: The pump scheduled to be upgraded is known as a jockey pump. Essentially it's a smaller 

pump that prevents larger pumps from repeatedly cycling on and off during periods of low demand. 

Ongoing flow analysis has determined that replacing the jockey pump with a low‐capacity pump will 

provide the District more redundancy in it's Zone 5 distribution network.  

 

 

CAMP #: STAT‐04.08.20002 

Project Name: AMP Z1 PS ‐ Investigate/Repair subsidence 

Project Location: AMP Z1 Pump Station 

Total Budget: $150,000  

Project Date: 2020 ‐ 2020 

Background: The AMP Z1 Pump Station is utilized to get water in/out of R‐6 Emergency Reservoir and 

provide backup pumping for the Allen McCullough pipeline which accounts for approximately 30% of the 

District's potable water demand. A recent inspection of the facility resulted in subsidence issues that 

require investigation. 

Justification: Staff estimated $150,000 in costs for the investigation of the subsidence and to perform 

some minimal repair work to prevent the issue from becoming worse. 

 

CAMP #: STAT‐04.01.20001 

Project Name: AMP Z1 PS ‐ Rehab 4 pumps 

Project Location: AMP Z1 Pump Station 

Total Budget: $87,000  

Project Date: 2020 ‐ 2022 

Background: The AMP Z1 Pump Station is utilized to get water in/out of R‐6 Emergency Reservoir and 

provide backup pumping for the Allen McCullough pipeline which accounts for approximately 30% of the 

District's domestic water demand. 

Justification: Of the nine total pumps, five have already been refurbished. The remaining four pumps 

need to be refurbished in order to ensure that this station remains online. 

 

CAMP #: STAT‐04.06.19001 

Project Name: Antonio Z3 PS ‐ Replace MCC on Pumps 5+6  

Project Location: Antonio Z3 Pump Station 

Total Budget: $330,000  

Project Date: 2019 ‐ 2019 

Background: The motor control center (MCC) on pumps are responsible for controlling the pump 

operation such as turning on/off. Pumps 5 + 6 were installed in the early 2000's. Parts for the existing 

MCC are no longer supported. 

Justification: The MCC for pumps 5 + 6 have exceeded their service life and are due for replacement. 

 

 

CAMP #: STAT‐04.06.19002 

Project Name: Antonio Z3 PS ‐ Replace switchgear and MCCs on Pumps 1‐4 

Project Location: Antonio Z3 Pump Station 

Total Budget: $725,000  

Project Date: 2019 ‐ 2019 

Background: The switchgear and motor control centers (MCC) on pumps 1 ‐4 are responsible for 

controlling the pump operation such as turning on/off. Pumps 1 ‐ 4 were installed in the early 1990's. 

Parts for the existing MCC are no longer supported. 

Justification: The switchgear and MCC for pumps 1 ‐ 4 have exceeded their service life and are due for 

replacement. Faults in the relays have led to false alarms and unnecessary overtime. 

 

CAMP #: PRS‐06.01.18002 

Project Name: Aurora Z2 PRS ‐ Install SCADA monitoring 

Project Location: Aurora Z2 PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Aurora Zone 2 pressure reducing station is located west of the intersection of Alicia and 

Marguerite in Mission Viejo. The PRS allows for domestic water from the higher zone 3 system to feed 

the lower pressure zone 2 system. This allows for greater reliability for the District domestic water 

supply. 

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

 

CAMP #: PIPE‐07.05.21001 

Project Name: Domestic Water ‐ Placeholder 

Project Location: Domestic Water System 

Annual Budget: $500,000  

Justification: The domestic water system spans more than 630+ miles of pipelines, 400 million gallons of 

storage, and more than 20 pump stations. Projects within the CRP are specified as much as possible but 

history has shown that budgeting $500,000 to $1 million as a placeholder is a prudent measure.  

 

 

 

 

 

CAMP #: PIPE‐07.01.19001 

Project Name: Domestic Water ‐ Replace 40' of pipeline in RSM 

Project Location: Domestic Water System 

Total Budget: $80,000  

Project Date: 2019 ‐ 2019 

Background: The Alicia Transmission Main is located near the intersection of Alicia Parkway and Santa 

Margarita Parkway which is responsible for conveying potable water throughout western Rancho Santa 

Margarita. Sometime after it was installed in 1987, the pipe was jostled which caused the interior lining 

to become unseated.  

Justification: Without the mortar lining protecting the pipe, a stretch of pipeline located on Santa Clara 

in Rancho Santa Margarita has developed several leaks. Replacing 40 linear feet of this pipeline will 

reduce the frequency of leaks on this stretch. 

 

CAMP #: OH‐08.06.18001 

Project Name: Domestic Water ‐ SCADA Phase III 

Project Location: Domestic Water System 

Total Budget: $300,000  

Project Date: 2018 ‐ 2020 

Background: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the domestic water, recycled water, wastewater, and treatment plant. Over the past few 

decades, the District has developed a private network that allows District facilities to easily and securely 

communicate with each other.  

Justification: This project proposes to add the remainder of facilities onto the SMWD network. This 

allows employees to remotely control and monitor the entire system at a glance. Phase III is in the final 

stages of adding facilities to the network so that they can communicate with each other.  

 

CAMP #: STAT‐04.08.19003 

Project Name: Domestic Water ‐ SCADA Replacements 

Project Location: Domestic Water System 

Annual Budget: 2019: $142,200  

    2020: $200,000 

2021: $171,400 

2022: $128,400 

2023: $95,700 

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the domestic water system. The SCADA system has been configured to control various 

equipment and monitor the entire domestic water distribution system. 

 

CAMP #: PIPE‐07.06.19001 

Project Name: Domestic Water ‐ Valve Replacement Program 

Project Location: Domestic Water System 

Annual Budget: $225,000  

Justification: As part of the Capital Repair & Replacement budget, the District sets aside $225,000 each 

fiscal year for work to be conducted on the domestic and/or recycled valves within the distribution 

system. Currently, the District has approximately 21,000 domestic valves and 8,000 recycled valves to 

maintain.  

 

 

 

CAMP #: PRS‐06.01.18003 

Project Name: Empresa Z3 PRS ‐ Install SCADA monitoring 

Project Location: Empresa Z3 PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Empresa Zone 3 pressure reducing station is located south of the intersection of Banderas 

and Empresa in Rancho Santa Margarita. The PRS allows for domestic water from the higher zone 4 

system to feed the lower pressure zone 3 system. This allows for greater reliability for the District 

domestic water supply. 

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

CAMP #: RES‐05.03.18001 

Project Name: Estado Z4 Reservoir ‐ Install reservoir management system 

Project Location: Estado Z4 Reservoir 

Total Budget: $660,000  

Project Date: 2018 ‐ 2019 

Background: In certain areas of the District, there have been significant changes in domestic water 

demands due to recycled water conversions, low flow appliances, and other water saving measures. As a 

result of these changes, certain reservoirs have a difficult time maintaining a chloramine residual that 

the District is comfortable with. Staff has investigated several different approaches to remedy this issue 

and has selected reservoir management systems to be the best solution for a few reservoirs. 

Justification: The District has been piloting a chloramination system at Estado Reservoir since Fall 2016. 

Since then, the District has been able to keep a consistent chlorine residual within the tank and has seen 

a benefit to downstream reservoirs as well.  

 

CAMP #: PRS‐06.01.18001 

Project Name: Florecer Z1 PRS ‐ Install SCADA monitoring 

Project Location: Florecer Z1 PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Florecer Zone 1 pressure reducing station is located north of the intersection of La Paz and 

Marguerite in Mission Viejo. The PRS allows for domestic water from the higher zone 2 system to feed 

the lower pressure zone 1 system. This allows for greater reliability for the District domestic water 

supply. 

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

CAMP #: STAT‐04.06.20001 

Project Name: Foothill Z4 PS ‐ Upgrade switchgear 

Project Location: Foothill Z4 Pump Station 

Total Budget: $250,000  

Project Date: 2020 ‐ 2020 

Background: The Foothill Z4 Pump Station is responsible for bringing domestic water to the higher 

elevations of Rancho Santa Margarita and surrounding areas.  

Justification: The control systems in place at Foothill Z4 Pump Station are scheduled for replacement. 

This includes the controls for the motors as well as the electric infrastructure.  

 

CAMP #: RES‐05.02.19001 

Project Name: Island Pasture Z3 Reservoir ‐ Install CP array 

Project Location: Island Pasture Z3 Reservoir 

Total Budget: $105,000  

Project Date: 2018 ‐ 2019 

Background: The Island Pasture Zone 3 Reservoir is a domestic water reservoir located in Rancho Santa 

Margarita. The internal lining has seen some mild corrosion and is scheduled to be relined.  

Justification: The District investigated the level of corrosion at Island Pasture and found that instead of 

relining the tank, the installation of a cathodic protection array within the tank would extend the life of 

the lining for an additional ten years. This array would be hung within the reservoir so that the sacrificial 

anodes would corrode rather than the interior of the tank walls.  

 

CAMP #: STAT‐04.03.19001 

Project Name: Lakeside PS ‐ Replace soft starts 

Project Location: Lakeside PS 

Total Budget: $55,000  

Project Date: 2020 ‐ 2020 

Background: The Lakeside Pump Station is responsible for bringing in more than 30% of the District's 

domestic water into eastern Mission Viejo. The station utilizes a combination of natural gas and 

electrical engines to power the pumps. 

Justification: In order to reduce the mechanical stress on the motors, devices called soft starts are 

installed on the motors. These devices temporarily reduce the load on the power train during the start 

up of the motor. One of the soft starts at Lakeside Pump Station has begun having issues due to its age 

and needs to be replaced. 

 

 

CAMP #: PIPE‐07.04.19001 

Project Name: MNWD Intertie @ Via Noveno/Los Alisos ‐ Rehab intertie 

Project Location: MNWD Intertie @ Via Noveno/Los Alisos 

Total Budget: $65,000  

Project Date: 2019 ‐ 2019 

Background: The District maintains several interties with neighboring agencies that allow for increased 

reliability in emergencies. Since most of these interties are only used in case of an emergency, they are 

not regularly utilized. Due to these interties being located underground, debris and runoff can fill these 

vaults and lead to increased risk of corrosion. 

Justification: In order to ensure that these interties will function as needed in times of emergency, the 

intertie needs to be kept in working order. A recent inspection of this vault indicated that this meter is 

no longer accurate and should be replaced along with a rehabilitation of its surrounding fittings. In 

addition to rehabilitating this intertie, it will also be added to the SCADA system so that a manual read 

isn't required every month. 

 

CAMP #: RES‐05.01.22001 

Project Name: Plano Z4 Reservoir ‐ Resurface exterior 

Project Location: Plano Z4 Reservoirs 

Total Budget: $775,000  

Project Date: 2022 ‐ 2022 

Background: The Plano Zone 4 tanks are located in northern Rancho Santa Margarita and can hold more 

than 12 million gallons of domestic water. The tanks typically require exterior coating work between 12 

to 15 years to control corrosion and maintain the appearance of the tanks.  

Justification: The District utilized Michael Baker International to perform an exterior coating inspection 

on all of the District's above ground tanks. One of the tanks at Plano Reservoir was found to have 

multiple layers of paint which made it impractical to just clean and coat. This tank requires all the paint 

to be removed so that the bare metal is exposed and then have a new coat reapplied.  

 

 

CAMP #: PRS‐06.01.18004 

Project Name: San Fernando Z1 PRS ‐ Install SCADA monitoring 

Project Location: San Fernando Z1 PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Aurora Zone 2 pressure reducing station is located east of the intersection of Jeronimo and 

Marguerite in Mission Viejo. The PRS allows for domestic water from the higher zone 2 system to feed 

the lower pressure zone 1 system. This allows for greater reliability for the District domestic water 

supply. 

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

CAMP #: PIPE‐07.01.20001 

Project Name: South County Pipeline ‐ Inspect pipe wall thickness 

Project Location: South County Pipeline 

Total Budget: $200,000  

Project Date: 2021 ‐ 2021 

Background: The 24 mile South County Pipeline was built in 1993 in order to bring domestic water into 

the Southern Orange County area from the Allen‐McColloch Pipeline. Since its construction, the pipeline 

has been opened several times for new construction with no signs of corrosion or deterioration.  

In 2011, the Upper Chiquita Reservoir was constructed and tied into the South County Pipeline. This tie‐

in was constructed in the middle of the pipeline and resulted in no pipe defects detected. 

In 2016, the Baker Water Treatment Plant Tie‐In and Service Connection 6 (SC‐6) Tie‐In were 

constructed and tied into the South County Pipeline. The Baker tie‐in was constructed in the upper 

portion of the pipeline while the SC‐6 tie‐in was constructed in the lower portion of the pipeline and 

both resulted in no pipe defects 

detected. 

Justification: Given the current 

condition of the pipe, staff 

believes that the inspection of the 

South County Pipeline can be 

deferred and re‐evaluated in 

2023. The pipeline is 25 years old 

as of 2018 and the deferral would 

push the inspection to 30 years 

since construction. As of 

November 2017, there has been 

development planned on/around 

the pipeline which would further 

add to the justification of 

inspection. 

 

 

CAMP #: RES‐05.03.18002 

Project Name: Talega Z1 Reservoir ‐ Install reservoir management system 

Project Location: Talega Z1 Reservoir 

Total Budget: $550,000  

Project Date: 2018 ‐ 2019 

Background: In certain areas of the District, there have been significant changes in domestic water 

demands due to recycled water conversions, low flow appliances, and other water saving measures. As a 

result of these changes, certain reservoirs have a difficult time maintaining a chloramine residual that 

the District is comfortable with. Staff has investigated several different approaches to remedy this issue 

and has selected reservoir management systems to be the best solution for a few reservoirs. 

Justification: The District has been piloting a chloramination system at Talega Z2 Reservoir since Fall 

2016. Since then, the District has been able to keep a consistent chlorine residual within the tank and 

has seen a benefit to downstream reservoirs as well. 

 

CAMP #: RES‐05.03.20001 

Project Name: Trabuco Ridge Z4 Reservoir ‐ Install reservoir management system 

Project Location: Trabuco Ridge Z4 Reservoir 

Total Budget: $660,000  

Project Date: 2020 ‐ 2020 

Background: In certain areas of the District, there have been significant changes in domestic water 

demands due to recycled water conversions, low flow appliances, and other water saving measures. As a 

result of these changes, certain reservoirs have a difficult time maintaining a chloramine residual that 

the District is comfortable with. Staff has investigated several different approaches to remedy this issue 

and has selected reservoir management systems to be the best solution for a few reservoirs. 

Justification: The District has been piloting a chloramination systems since Fall 2016. Since then, the 

District has been able to keep a consistent chlorine residual within the tank and has seen a benefit 

to downstream reservoirs as well. 

 

CAMP #: PRS‐06.01.18007 

Project Name: Via Noveno Z2 PRS ‐ Install SCADA Monitoring 

Project Location: Via Noveno Z2 PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Via Noveno Zone 2 pressure reducing station is located at the intersection of Los Alisos and 

Via Noveno in Mission Viejo. The PRS allows for domestic water from the higher zone 3 system to feed 

the lower pressure zone 2 system. This allows for greater reliability for the District domestic water 

supply. 

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

02 ‐ Recycled Water Projects Projects associated with the repair, maintenance, and improvement of the recycled water system. 

 

 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

Canyon Crest ZE PS ‐ Replace controls 50,000$          

Eastbrook ZD PS ‐ Upgrade control valve 50,000$       

La Paz ZB PS ‐ Replace SCADA equipment 300,000$       

Lake Mission Viejo APW ‐ Replace membranes 670,000$     

Portola ZB Reservoir ‐ Install electrical infrastructure 60,000$          

Portola ZB Reservoir ‐ Install water quality aeration fountain 60,000$          

Recycled Water ‐ Cathodic Protection 300,000$     

Recycled Water ‐ Placeholder 500,000$      500,000$      500,000$     

Recycled Water ‐ SCADA Replacements 50,000$        153,400$     

Talega ZB PS ‐ Upgrade valves 65,000$       

Upper Oso ZC Reservoir ‐ Reasphalt dam 180,000$     

Upper Oso ZC Reservoir ‐ Upgrade I/O valves and install meter 315,000$     

Vault D Minus PRS ‐ Install SCADA Monitoring 50,000$          

Grand Total 50,000$           470,000$        560,000$      1,170,000$  850,000$      703,400$     

CAMP #: STAT‐04.06.22001 

Project Name: Canyon Crest ZE PS ‐ Replace controls 

Project Location: Canyon Crest ZE PS 

Total Budget: $50,000  

Project Date: 2019 ‐ 2022 

Background: Canyon Crest ZE PS feeds the Canyon Crest neighborhood with recycled water.  

Justification: The controls used to operate the facility are in need of replacement. The motor control, 

control valves, meter interface, and programming needs to be updated to new standards. 

 

CAMP #: STAT‐04.02.23001 

Project Name: Eastbrook ZD PS ‐ Upgrade control valve 

Project Location: Eastbrook ZD PS 

Total Budget: $50,000  

Project Date: 2023 ‐ 2023 

Background: When Eastbrook Pump Station was built in 1986, it served a closed system which meant 

that there was no reservoir in the pressure zone. As the area became more developed, Trabuco Hills 

Reservoir was built in 1995. This changed the typical hydraulics seen at Eastbook PS but the station 

could still operate.  

Justification: The control valves are reaching the end of their useful service life. Rather than replacing 

them, they will be replaced with check valves instead. The maintenance on check valves is expected to 

be significantly less than the existing valves. 

 

CAMP #: STAT‐04.08.19002 

Project Name: La Paz ZB PS ‐ Replace SCADA equipment 

Project Location: La Paz ZB Pump Station 

Total Budget: $300,000  

Project Date: 2019 ‐ 2019 

Background: MNWD installed the existing equipment in the 1990s. At the time, MNWD was able to 

install a temporary motor control and communications. This project will upgrade the SCADA equipment 

to meet current SMWD standards, including integration into SMWD's SCADA network. 

Justification: The La Paz Pump Station is on the SMWD Oso WRP property and is critical in the 

conveyance of recycled water into the service area and Upper Oso Reservoir. The pump station is 

operated and maintained by SMWD staff. Monitoring through SMWD SCADA will provide SMWD staff 

with real time operations information and alarms. 

 

CAMP #: LMVAPW‐03.06.21002 

Project Name: Lake Mission Viejo APW ‐ Replace membranes 

Project Location: Lake Mission Viejo APW 

Total Budget: $670,000  

Project Date: 2021 ‐ 2021 

Background: As part of the advanced treatment that water undergoes at the Lake Mission Viejo 

Advanced Purified Water Treatment Facility (APW), recycled water is passed through a series of 

membrane filters. While these membranes are regularly cleaned, over time the pore sizes are reduced 

and the throughput decreases and treatment efficiency is reduced. 

Justification: The capacity of the membranes for the filtration process is reduced at the end of the 

service life. Replacement of the membranes is required to maintain the treatment capacity and avoid 

higher operating costs. 

 

CAMP #: RES‐05.03.19001 

Project Name: Portola ZB Reservoir ‐ Install electrical infrastructure 

Project Location: Portola ZB Reservoir 

Total Budget: $60,000  

Project Date: 2019 ‐ 2019 

Background: The Portola ZB Reservoir is located in north Coto de Caza and stores recycled water for the 

area. Currently, the reservoir has limited electrical connectivity due to the historical power demands of 

the facility. 

Justification: The Portola ZB Reservoir was historically fed by domestic water. However, the 

Gobernadora Multipurpose Basin and the Los Patrones highline have changed that in recent years. Now 

that the reservoir is receiving urban runoff as well as recycled water, there is potential that the reservoir 

will require water quality monitoring that will require additional power. 

 

CAMP #: RES‐05.03.19002 

Project Name: Portola ZB Reservoir ‐ Install water quality aeration fountain 

Project Location: Portola ZB Reservoir 

Total Budget: $60,000  

Project Date: 2019 ‐ 2019 

Background: Portola ZB Reservoir is a recycled reservoir located in Northern Coto de Caza utilized for 

storing water for irrigation. Historically, it was filled with domestic water but the construction of the 

Gobernadora Multipurpose Basin and the Los Patrones highline has allowed recycled water to be 

utilized to fill the reservoir.  

Justification: Due to the higher organics present in recycled water, the District must combat algae 

development and odors from developing. Current methods of remediation include flushing the lake with 

drinking water as well as dosing with chemicals. The proposed aeration fountains should reduce the 

necessity for these measures and potentially remove them completely.  

 

CAMP #: PIPE‐07.05.21002 

Project Name: Recycled Water ‐ Placeholder  

Project Location: Recycled Water System 

Annual Budget: $500,000  

Justification: The recycled water system spans more than 130+ miles of pipelines, 1.5 billion gallons of 

storage, and 14 pump stations. Projects within the CRP are specified as much as possible, but history has 

shown that budgeting $500,000 to $1 million as a placeholder is a prudent measure. 

 

CAMP #: OH‐08.06‐23001 

Project Name: Recycled Water ‐ SCADA Replacements 

Project Location: Recycled Water System 

Total Budget: 2022: $50,000 

           2023: $153,400  

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the recycled water system. The SCADA system has been configured to control various 

equipment and monitor the entire recycled water distribution system. 

 

CAMP #: STAT‐04.02.20001 

Project Name: Talega ZB PS ‐ Upgrade valves 

Project Location: Talega ZB PS 

Total Budget: $65,000  

Project Date: 2020 ‐ 2020 

Background: Talega Zone B Pump Station is responsible for ensuring that the higher elevation areas in 

the Talega area receive recycled water. Currently, the valves that control this flow are older style ball 

valves.  

Justification: The proposed project would replace the ball valves with KTORK valves which is the 

District's new standard. This type of valve is more efficient which lowers the power cost of the station. 

Additionally, the District has seen less valve failure and less corrosion with these new valves. 

 

CAMP #: RES‐05.01.20001 

Project Name: Upper Oso ZC Reservoir ‐ Reasphalt dam 

Project Location: Upper Oso ZC Reservoir 

Total Budget: $180,000  

Project Date: 2020 ‐ 2020 

Background: The Upper Oso Reservoir is actually a large earthen dam holding 5,000 (1.6 billion gallons) 

acre feet of recycled water. The dam face and top of the dam is covered in asphalt to prevent erosion 

and reduce wear and tear.  

Justification: It's been 20+ years since the reservoir has had the asphalt replaced. Sun exposure and 

erosion lead to cracks and fissures in the dam face. These fissures allow for water to enter and weeds to 

grow. This can cause a potential dam safety issue which must be addressed. 

 

CAMP #: RES‐04.02.20001 

Project Name: Upper Oso ZC Reservoir ‐ Upgrade I/O valves and install meter 

Project Location: Upper Oso ZC Reservoir 

Total Budget: $315,000  

Project Date: 2020 ‐ 2020 

Background: The inlet/outlet (I/O) valves are what control the flow of recycled water in/out of the 

Upper Oso Reservoir. The 5,000 acre foot (1.6 billion gallons) reservoir is shared with Moulton Niguel 

Water District for seasonal storage of recycled water. 

Justification: Since the construction of the dam in the late 1970s, there have been no major upgrade to 

the I/O valves. The proposed project would upgrade the valves to provide a better user interface and 

allow operators to see the position of the valves. In addition, there is no meter at the reservoir site that 

records water coming in/out. The addition of a meter would allow the District to maintain better 

accuracy of its recycled water supply. 

 

CAMP #: PRS‐06.01.18006 

Project Name: Vault D Minus PRS ‐ Install SCADA Monitoring 

Project Location: Vault D Minus PRS 

Total Budget: $50,000  

Project Date: 2018 ‐ 2019 

Background: Vault D Minus pressure reducing station is located of the intersection of Jeronimo and 

Olympiad in Mission Viejo. The PRS allows for recycled water from the higher zone D system to feed the 

lower pressure zone D Minus system.  

Justification: Currently, these PRS stations are not electronically monitored. If a problem were to arise, 

the District would find out about it when customers called in with water outages. The proposed project 

would allow for the District to monitor the status of the PRS remotely and alarm operators whenever an 

issue arose.  

 

03 ‐ Wastewater Projects Projects associated with the repair, maintenance, and improvement of the wastewater system.  

 

 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

Boy Scout LS ‐ Install packaged lift station 250,000$       

Coto LS ‐ Install emergency bypass 332,500$       

Coto LS ‐ Install emergency storage basin 1,500,000$    

Coto LS ‐ Install odor control 525,000$       

Coto LS ‐ Install overhead hoist 230,000$     

Coto LS ‐ Replace surge tank 370,000$       

Horno LS ‐ Install odor control 390,000$     

Horno LS ‐ Replace pumps 4,000,000$    

Ladera LS ‐ Install odor control 225,000$     

Meadow Ridge LS ‐ Install emergency storage 50,000$       

Ortega LS ‐ Install overhead hoist 230,000$     

Plano LS ‐ Install odor control 400,000$       

Plano LS ‐ Install overhead hoist 230,000$     

Plano LS ‐ Replace generator control panel 85,000$          

South Ranch LS ‐ Install overhead hoist 230,000$     

South Ranch LS ‐ Install surge tank and redesign pumps 360,000$       

Talega LS ‐ Upgrade pumps 175,000$     

Trabuco LS ‐ Install overhead hoist 230,000$     

Wastewater ‐ Placeholder 500,000$      500,000$      500,000$     

Wastewater ‐ SCADA Replacements 50,000$       

Wastewater ‐ Various Sewer Repairs 250,000$      250,000$      250,000$      250,000$     

Grand Total 1,477,500$     6,595,000$     705,000$      1,365,000$  1,210,000$  1,260,000$ 

CAMP #: STAT‐04.01.18001 

Project Name: Boy Scout LS ‐ Install packaged lift station 

Project Location: Boy Scout Camp LS 

Total Budget: $250,000  

Project Date: 2018 ‐ 2019 

Background: Until recently, the wastewater collection system did not reach to the Boy Scout 

campground located at Upper Oso Reservoir. However, recent development surrounding the site has 

provided the opportunity to work with the Boy Scouts to develop a plan to install a packaged lift station 

and force main to allow for the campground to be connected to the District's wastewater collection 

system.  

Justification: The lift station and force main will allow the campground to build shower facilities which 

will allow longer outings at the campground.  

 

CAMP #: PIPE‐07.05.18001 

Project Name: Coto LS ‐ Install emergency bypass 

Project Location: Coto LS 

Total Budget: $332,500  

Project Date: 2018 ‐ 2019 

Background: The Coto Lift Station is located in southern Coto de Caza and collects wastewater from 

Coto de Caza and Wagon Wheel before pumping it to the Chiquita Water Reclamation Plant.  

Justification: Typically, the force main carries over 1 million gallons per day underneath Coto de Caza 

Drive. If the force main were to have a break, it would close down Coto de Caza Drive and potentially 

spill into the creek. By installing bypass structures, the District would be able to bypass the force main 

completely and allow for the scheduling of inspection and repair, if needed, that would not greatly 

disturb the community or risk a larger spill. 

 

CAMP #: STAT‐04.08.19001 

Project Name: Coto LS ‐ Install emergency storage basin 

Project Location: Coto LS 

Total Budget: $1,500,000  

Project Date: 2019 ‐ 2019 

Background: Coto Lift Station conveys flow from Coto de Caza to the gravity sewer system that flows to 

Chiquita Water Reclamation Plant. The facility is not equipped with emergency storage. Industry and 

District standards are to provide emergency storage at lift stations in the event of equipment failure, 

and to facilitate certain maintenance such as force main work that requires station shut‐down for short 

periods. 

Justification: In FY17, the District narrowly avoided a sewer spill at Coto LS due to the lack of emergency 

storage. If the District had arrived 5 minutes later, it would have been too late. Emergency storage 

greatly reduces the risk of sewage spills under certain equipment failure conditions. 

 

CAMP #: STAT‐04.07.18001 

Project Name: Coto LS ‐ Install odor control 

Project Location: Coto LS 

Total Budget: $525,000  

Project Date: 2018 ‐ 2019 

Background: Coto Lift Station is located adjacent to Coto de Caza Drive and is in close proximity to 

neighboring homes. The District has been investigating different odor control technologies at the station 

and have concluded that a biological odor scrubber followed by carbon media would be the best 

solution. 

Justification: In the past several years, the District has received odor complaints in the area and 

measured elevated numbers of odor‐related chemical compounds. Implementation of odor control is 

consistent with the District Strategic Plan to reduce odor complaints. the proposed system is 

recommended based on life cycle analysis and non‐monetary considerations. 

 

CAMP #: STAT‐04.05.22001 

Project Name: Coto LS ‐ Install overhead hoist 

Project Location: Coto LS 

Total Budget: $230,000  

Project Date: 2020 ‐ 2020 

Background: The District's current specification for lift stations calls for an overhead hoist to be installed 

to facilitate the movement of pumps in/out of the station. Several lift stations built before this standard 

do not have these hoists which makes removing and installing pumps after maintenance increasingly 

difficult. 

Justification: While District crane trucks can move pumps vertically out of a station, they cannot move 

them horizontally through a lift station. An a‐frame device must be used and maneuvered through the 

tight spaces which makes movement within a station very difficult. Overhead hoists allow for 2 axes 

(up/down/left/right) of travel while crane trucks can only move in one dimension (up/down). Typical 

maintenance requires pumps to undergo maintenance every 5 years. In addition, these installations lead 

to a significant decrease in the risk of injuries and equipment damage. 

 

CAMP #: STAT‐04.09.18001 

Project Name: Coto LS ‐ Replace surge tank 

Project Location: Coto LS 

Total Budget: $370,000  

Project Date: 2018 ‐ 2019 

Background: Surge tanks are installed in order to be able to accommodate pressure surges that happen 

within the pipeline. This allows for a pressure buffer while upstream pumps shut on/off. During force 

main break in 2017, the District had the surge tank analyzed and found that the walls were too thin to 

be effective.  

Justification: The surge tank wall thickness analysis showed both tanks at Coto LS needed to be 

replaced. If not replaced, there is a potential the existing surge tanks will eventually fail and cause a 

sewer spill. 

 

CAMP #: STAT‐04.01.19001 

Project Name: Horno LS ‐ Replace pumps 

Project Location: Horno LS 

Total Budget: $4,000,000  

Project Date: 2019 ‐ 2021 

Background: Horno Lift Station is one of the District's largest lift stations and faces moving 

approximately 50 million gallons of wastewater up and over the Ladera Ranch community towards 

Chiquita Water Reclamation Plant. The station was designed with four sets of two 150 horsepower 

pumps that are run in series to produce enough discharge pressure to pump the wastewater.  

Justification: The proposed project is to replace the existing pumps with newer higher head pumps. The 

existing pump setup has led to excessive wear, overheating, and frequent outages. A single pump of the 

new type will output sufficient flow and pressure to replace the output of four existing pumps. In order 

to provide redundancy, three of the newer style pumps would be installed.  

The new pumps would require significant modification to the electrical equipment, piping, structural 

openings for pump removal, and possibly generator capacity 

 

CAMP #: STAT‐04.08.20001 

Project Name: Meadow Ridge LS ‐ Install emergency storage 

Project Location: Meadow Ridge LS 

Total Budget: $50,000  

Project Date: 2020 ‐ 2020 

Background: Meadow Ridge Lift Station is responsible for conveying wastewater flow from the Meadow 

Ridge neighborhood to the gravity sewer system that currently flows to IRWD's Los Alisos Water 

Reclamation Plant. The facility is not equipped with emergency storage. Industry and District standards 

are to provide emergency storage at lift stations in the event of equipment failure, and to facilitate 

certain maintenance such as force main work that requires station shut‐down for short periods. 

Justification: Meadow Ridge Lift Station is one of the furthest stations from District Headquarters where 

emergency equipment is stored. If an emergency would occur, it would take at least 20 minutes to reach 

the site. Emergency storage greatly reduces the risk of sewage spills under certain equipment failure 

conditions. 

 

CAMP #: STAT‐04.05.23001 

Project Name: Ortega LS ‐ Install overhead hoist 

Project Location: Ortega LS 

Total Budget: $230,000  

Project Date: 2023 ‐ 2023 

Background: The District's current specification for lift stations calls for an overhead hoist to be installed 

to facilitate the movement of pumps in/out of the station. Several lift stations built before this standard 

do not have these hoists which makes removing and installing pumps after maintenance increasingly 

difficult. 

Justification: While District crane trucks can move pumps vertically out of a station, they cannot move 

them horizontally through a lift station. An a‐frame device must be used and maneuvered through the 

tight spaces which makes movement within a station very difficult. Overhead hoists allow for 2 axes 

(up/down/left/right) of travel while crane trucks can only move in one dimension (up/down). Typical 

maintenance requires pumps to undergo maintenance every 5 years. In addition, these installations lead 

to a significant decrease in the risk of injuries and equipment damage. 

 

CAMP #: STAT‐04.07.19003 

Project Name: Plano LS ‐ Install odor control 

Project Location: Plano LS 

Total Budget: $400,000  

Project Date: 2019 ‐ 2019 

Background: Plano Lift Station is one of the largest lift stations in the District's wastewater system. It's 

responsible for moving over 65 million gallons of wastewater from Rancho Santa Margarita and eastern 

Mission Viejo every month.  

Justification: The sewer pipeline entering Plano Lift Station has a low slope which leads to longer 

detention times in the early morning which has caused complaints by the surrounding residents. The 

proposed project would install an odor scrubber system selected based on life cycle analysis and other 

considerations. Ongoing operating costs are estimated to be $60,000 per year and would cover power, 

media, and labor.  

 

CAMP #: STAT‐04.05.22003 

Project Name: Plano LS ‐ Install overhead hoist 

Project Location: Plano LS 

Total Budget: $230,000  

Project Date: 2022 ‐ 2022 

Background: The District's current specification for lift stations calls for an overhead hoist to be installed 

to facilitate the movement of pumps in/out of the station. Several lift stations built before this standard 

do not have these hoists which makes removing and installing pumps after maintenance difficult. 

Justification: While District crane trucks can move pumps vertically out of a station, they cannot move 

them horizontally through a lift station. An a‐frame device must be used and maneuvered through the 

tight spaces which makes movement within a station very difficult. Overhead hoists allow for 2 axes 

(up/down/left/right) of travel while crane trucks can only move in one dimension (up/down). Typical 

maintenance requires pumps to undergo maintenance every 5 years. In addition, these installations lead 

to a significant decrease in the risk of injuries and equipment damage. 

 

CAMP #: STAT‐04.04.19001 

Project Name: Plano LS ‐ Replace generator control panel 

Project Location: Plano LS 

Total Budget: $85,000  

Project Date: 2019 ‐ 2019 

Background: Plano Lift Station is one of the largest lift stations in the District's wastewater system. It's 

responsible for moving over 65 million gallons of wastewater every month. Due to the previous 

modifications made at Plano Lift Station, the existing generator cannot run all pumps at the same time. 

If power was lost during a high flow period, the risk for a sewer spill would be extremely high. The 

proposed project would replace the generator and electrical panel.  

Justification: Replacing the generator control will allow the generator to run all the pumps at the same 

time, in the event of a power loss. This ability decreases the potential for a sewage spill.  

 

CAMP #: STAT‐04.05.23002 

Project Name: South Ranch LS ‐ Install overhead hoist 

Project Location: South Ranch LS 

Total Budget: $230,000  

Project Date: 2023 ‐ 2023 

Background: The District's current specification for lift stations calls for an overhead hoist to be installed 

to facilitate the movement of pumps in/out of the station. Several lift stations built before this standard 

do not have these hoists which makes removing and installing pumps after maintenance increasingly 

difficult. 

Justification: While District crane trucks can move pumps vertically out of a station, they cannot move 

them horizontally through a lift station. An a‐frame device must be used and maneuvered through the 

tight spaces which makes movement within a station very difficult. Overhead hoists allow for 2 axes 

(up/down/left/right) of travel while crane trucks can only move in one dimension (up/down). Typical 

maintenance requires pumps to undergo maintenance every 5 years. In addition, these installations lead 

to a significant decrease in the risk of injuries and equipment damage. 

 

CAMP #: STAT‐04.09.19001 

Project Name: South Ranch LS ‐ Install surge tank and redesign pumps 

Project Location: South Ranch LS 

Total Budget: $360,000  

Project Date: 2019 ‐ 2019 

Background: When South Ranch Lift Station was designed, its pumps were built utilizing a flywheel 

configuration. A flywheel is a protection against pressure surges that utilizes a large wheel to mitigate 

any damages. 

Justification: The District wants to move away from the flywheel technology and standardize its surge 

protection by utilizing surge tanks. Since South Ranch Lift Station was not built with this type of surge 

protection in mind, the existing pumps will need to be replaced as well as adding a surge tank.   

 

CAMP #: STAT‐04.01.20002 

Project Name: Talega LS ‐ Upgrade pumps 

Project Location: Talega LS 

Total Budget: $175,000  

Project Date: 2020 ‐ 2020 

Background:    

Talega Lift Station is responsible for moving more than 600 thousand gallons of wastewater a day. This 

wastewater is pumped towards Chiquita Water Reclamation Plant where it is treated and results in 

recycled water.  

Due to the high head conditions at the station when being designed, the best available technology was 

to a dual pumping operation. New pump technology allows for a more reliable single pump operation.  

Justification:  

The current dual pump operation is unreliable due to its vulnerability to becoming misaligned which 

leads to increased wear and tear and clogging. Conversion to a single pump operation will reduce this 

and lead to a longer and more reliable service life. 

 

CAMP #: STAT‐04.05.22002 

Project Name: Trabuco LS ‐ Install overhead hoist 

Project Location: Trabuco LS 

Total Budget: $230,000  

Project Date: 2022 ‐ 2022 

Background: The District's current specification for lift stations calls for an overhead hoist to be installed 

to facilitate the movement of pumps in/out of the station. Several lift stations built before this standard 

do not have these hoists which makes removing and installing pumps after maintenance increasingly 

difficult. 

Justification: While District crane trucks can move pumps vertically out of a station, they cannot move 

them horizontally through a lift station. An a‐frame device must be used and maneuvered through the 

tight spaces which makes movement within a station very difficult. Overhead hoists allow for 2 axes 

(up/down/left/right) of travel while crane trucks can only move in one dimension (up/down). Typical 

maintenance requires pumps to undergo maintenance every 5 years. In addition, these installations lead 

to a significant decrease in the risk of injuries and equipment damage. 

 

CAMP #: PIPE‐07.05.21003 

Project Name: Wastewater – Placeholder 

Project Location: Wastewater System 

Annual Budget: $500,000  

Justification: The wastewater collections system spans more than 630+ miles of pipelines and more than 

20 lift stations. Projects within the CRP are specified as much as possible, but history has shown that 

budgeting $500,000 to $1 million as a placeholder is a prudent measure. 

 

 

 

 

CAMP #: STAT‐03.02.23001 

Project Name: Wastewater ‐ SCADA Replacements 

Project Location: Wastewater System 

Total Budget: $50,000  

Project Date: 2023 ‐ 2023 

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the wastewater system. The SCADA system has been configured to control various equipment 

and monitor the entire wastewater collection system. 

 

 

 

 

 

CAMP #: PIPE‐07.03.19001 

Project Name: Wastewater ‐ Various Sewer Repairs  

Project Location: Wastewater System 

Annual Budget: $250,000  

Background: As part of the Capital Repair & Replacement budget, the District sets aside $250,000 each 

fiscal year for work to be conducted on the wastewater system. Typically these funds are utilized on 

manhole rehabilitation and/or pipe relining. 

Justification: As the manhole liners degrade, the exposed concrete behind them is exposed to 

concentrated amounts of H2S gas which is present in sewer lines. This leads to accelerated corrosion 

that can destabilize the manhole structure. In addition, pieces of the liner which break off can quickly 

lead to sewer blockages and eventual sewer spills.  

 

 

 

04 ‐ Chiquita Water Reclamation Plant Projects Projects associated with the repair, maintenance, and improvement of the Chiquita Water Reclamation 

Plant. These costs represent 100% of the total cost, not SMWD’s share. 

 

 

 

 

 

 

 

 

 

 

Column1 Ongoing 2019 2020 2021 2022 2023

CWRP ‐ Clean digesters 130,000$        130,000$     

CWRP ‐ Install additional digester chopper pump 60,000$          

CWRP ‐ Install air compressors 75,000$          

CWRP ‐ Perform electrical study 60,000$          

CWRP ‐ Refurbish microturbines 250,000$     

CWRP ‐ Rehab CWRP structures 200,000$        200,000$     

CWRP ‐ Rehab digested sludge holding tank 350,000$       

CWRP ‐ Rehab Phase III Influent Lift Station pumps 750,000$       

CWRP ‐ Repair gas sphere 175,000$       

CWRP ‐ Replace aeration diffusers 100,000$     

CWRP ‐ Replace centrifugal blower 300,000$     

CWRP ‐ Replace dewatering conveyer 900,000$       

CWRP ‐ Replace digester area hot water piping 400,000$       

CWRP ‐ Replace digester recirculation pumps 200,000$     

CWRP ‐ Replace ferric chloride tank in digester area 75,000$       

CWRP ‐ Replace filtrate pumps 150,000$       

CWRP ‐ Replace hypochlorite tanks 150,000$     

CWRP ‐ Replace Influent Lift Station generator 450,000$       

CWRP ‐ Replace original electrical equipment 800,000$       

CWRP ‐ Replace polymer blender 60,000$          

CWRP ‐ Replace RAS/WAS pumps 300,000$     

CWRP ‐ Replace scum pumps 130,000$     

CWRP ‐ Replace sludge feed pump 80,000$          

CWRP ‐ Replace sludge pumps at primary clarifier 150,000$       

CWRP ‐ Replace temporary force main 350,000$       

CWRP ‐ Replace tertiary filter cloths 50,000$       

CWRP ‐ Replace tertiary filters backwash pumps 60,000$       

CWRP ‐ SCADA Replacements 133,300$        65,800$       

CWRP ‐ Upgrade controls at Influent Lift Station 850,000$       

CWRP ‐ Upgrade electrical equipment 1,190,000$ 

CWRP ‐ Upgrade security 250,000$       

CWRP‐Replace digester gas piping 300,000$       

Grand Total 2,710,000$     3,963,300$     65,800$        780,000$      450,000$      1,905,000$ 

CAMP #: CWRP‐03.03.18001 

Project Name: CWRP ‐ Perform electrical study 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $60,000  

Project Date: 2018 ‐ 2019 

Background: The electrical demands for CWRP have changed drastically in the last 30 years. Increased 

flows from new developments have increased the power demands while alternative power supplies 

such as solar panels have reduced the power demand.  

Justification: Due to the changes in power demands, the proposed study will analyze these demands 

and provide analysis on what power needs the treatment plant will require in the future. The results of 

this study will be utilized in other electrical CIP projects at the plant. 

 

CAMP #: CWRP‐02.04.21001 

Project Name: CWRP ‐ Refurbish microturbines 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $250,000  

Project Date: 2021 ‐ 2021 

Background: Historically, excess methane produced in the digesters was burned off to atmosphere. 

However in the early 2000s, the District installed a microturbine system that burns excess methane and 

converts it into usable electricity. Typically, these microturbines offset approximately 15% of the plant 

power demands and saved $10,000 per month in power savings. 

Justification: Previously, the District was able to locate microturbine parts at a discount due to locating 

other agencies selling the parts at a loss due to their inability to get their systems to work. However, in 

the past few years, there are fewer opportunities to purchase minimally used parts and the District 

anticipates having to get parts at list price moving forward. 

 

CAMP #: CWRP‐03.05.19001 

Project Name: CWRP ‐ Rehab CWRP structures 

Project Location: Chiquita Water Reclamation Plant 

Annual Budget: 2019: $200,000  

           2023: $200,000 

Background: The first buildings at Chiquita Water Reclamation Plant were built in 1986 with additional 

buildings constructed with each expansion. 

Justification: Due to the extremely corrosive nature of wastewater treatment, many of the structures at 

CWRP require structural rehabilitations. The proposed project would reroof the main building and 

laboratory in 2019, and the digester area and warehouse in 2023. 

 

CAMP #: CWRP‐02.02.18001 

Project Name: CWRP ‐ Rehab digested sludge holding tank 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $350,000  

Project Date: 2018 ‐ 2019 

Background: The Sludge Holding Tank was constructed in 1986 and it has had no major refurbishment. It 

has been entered and cleaned twice. This units is in need of the same work scope that the Phase I sludge 

thickener of its equal size received in 2014. The units main drive unit has 30‐years of continuous 24‐hour 

operation. 

Justification: The sludge holding tank drive is at the end of its service life, with eminant failure if not 

replaced. If the tank fails, the sludge dewatering operation will be impacted. 

 

CAMP #: CWRP‐01.01.19002 

Project Name: CWRP ‐ Rehab Phase III Influent Lift Station pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $750,000  

Project Date: 2019 ‐ 2020 

Background: The Phase III expansion of CWRP occurred during the early 2000s in order to accommodate 

the increased flow from the Talega and Ladera communities.  

Justification: The proposed project will rehabilitate these pumps in order to extend their service life.  

 

 

CAMP #: CWRP‐02.04.19001 

Project Name: CWRP ‐ Repair gas sphere 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $175,000  

Project Date: 2019 ‐ 2019 

Background: The gas sphere at CWRP is where excess methane gas is collected from the digester 

process. The gas is later used at the boilers to generate heat or at the microturbines to generate 

electricity.  

Justification: The gas sphere is scheduled for repairs. The proposed project would have a full inspection 

performed and repair recommendations would be followed. 

 

CAMP #: CWRP‐01.04.21001 

Project Name: CWRP ‐ Replace aeration diffusers 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $100,000  

Project Date: 2021 ‐ 2021 

Background: As part of the secondary treatment process, air bubbles are introduced into the aeration 

basin through air diffusers. The air supports the biological activity that treats the process flow. Microbes 

feed on the organic material in the primary effluent introduced into the process.  

Justification: Openings in the air diffuser membrane face gradually expand over time, which results in 

larger air bubbles, reducing the efficiency of the treatment process. Replacing the air diffusers will 

reduce power costs in the aeration process.  

 

CAMP #: CWRP‐01.03.18001 

Project Name: CWRP ‐ Replace digester area hot water piping 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $400,000  

Project Date: 2018 ‐ 2019 

Background: Anaerobic digesters treat solids produced at Chiquita Water Reclamation Plant. Primary 

and waste activated sludge enters the digesters where microbes consume the remaining organic matter 

similar to the bacteria in a human stomach. In order for this process to work effectively, the digesters 

must remain within a specific heat range to accommodate the microbes. A heat exchanger transfers 

heat from hot water produced at the boilers to sludge circulated in the digesters.  

Justification: The hot water pipeline in the digester area has reached the end of its service life and 

requires replacement. The pipeline has had to have numerous repairs and has damaged other pipelines 

in the common pipe trench due to the high heat of the water.  

 

 

CAMP #: CWRP‐01.04.23001 

Project Name: CWRP ‐ Replace digester recirculation pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $200,000  

Project Date: 2023 ‐ 2023 

Background: Digesters require mixing to maintain solids in suspension. The digester recirculation pumps 

are at the end of their service life and require replacement 

Justification: Digester recirculation pumps are critical in the operation of the digester. If the pumps 

break down, the digester will not operate effectively, reducing gas production and the dewaterability of 

the treated sludge. 

 

CAMP #: CWRP‐02.02.23001 

Project Name: CWRP ‐ Replace ferric chloride tank in digester area 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $75,000  

Project Date: 2023 ‐ 2023 

Background: The CWRP utilizes ferric chloride in its biosolids handling to reduce the hydrogen sulfide 

(H2S) gas produced through the digestion process.  

Justification: The storage tank for the ferric chloride has surpassed its service life and needs to be 

replaced. 

 

 

 

CAMP #: CWRP‐02.01.19001 

Project Name: CWRP ‐ Replace filtrate pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $150,000  

Project Date: 2019 ‐ 2019 

Background: As part of the solids handling process at CWRP, screw presses utilize centrifugal force in 

order to remove as much liquid as possible from the biosolids. This liquid is called filtrate and is stored 

before being pumped back into the beginning of the treatment process.  

Justification: The pumps that move filtrate back into the treatment process have reached the end of 

their service life are scheduled to be replaced. The filtrate pumps are required to operate the 

dewatering process. 

 

CAMP #: CWRP‐01.06.22001 

Project Name: CWRP ‐ Replace hypochlorite tanks 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $150,000  

Project Date: 2022 ‐ 2022 

Background: The hypochlorite storage tanks at Chiquita Water Reclamation Plant are utilized to store 

the chlorine that is utilized in the chlorine contact basin. This allows for the recycled water to carry a 

chlorine residual within the recycled distribution system.  

Justification: The existing tanks have reached the end of their useful service life and require 

replacement. Leaking hypochlorite poses a safety and regulatory risk. 

 

CAMP #: CWRP‐03.03.19001 

Project Name: CWRP ‐ Replace Influent Lift Station generator 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $450,000  

Project Date: 2018 ‐ 2020 

Background: The generator for the Influent Lift Station (ILS) at Chiquita Water Reclamation Plant is the 

same generator originally installed in the 1980s. Since then, there have been changes in the flow seen at 

the ILS which has changed the electrical demands of the generator.  

Justification: The generator at the ILS requires an analysis to determine if it will work effectively with 

the modified influent pump station equipment. Based on the results of the analysis, the generator may 

need to be replaced or supplemented with an additional unit. 

 

CAMP #: CWRP‐03.03.19002 

Project Name: CWRP ‐ Replace original electrical equipment 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $800,000  

Project Date: 2019 ‐ 2020 

Background: The first phase of the Chiquita Water Reclamation Plant was built in the 1980s. The 

electrical components in order to support the preliminary, primary, secondary, and tertiary treatment 

processes have been in place since then. 

Justification: The electrical equipment has become obsolete and spare parts are no longer available.  

 

 

 

 

CAMP #: CWRP ‐ 01.04.21001 

Project Name: CWRP ‐ Replace RAS/WAS pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $300,000  

Project Date: 2021 ‐ 2021 

Background: As part of the secondary treatment process, activated sludge is utilized as part of the 

biological treatment that wastewater undergoes. Wastewater enters the aeration basin where bacteria 

digests the organics within the wastewater. Return activated sludge (RAS) is returned to the beginning 

of the process to re‐seed the wastewater entering into the tank. Waste activated sludge (WAS) is excess 

sludge that is removed from the treatment process. 

Justification: The RAS/WAS pumps have reached the end of their service life and need to be replaced.  

 

CAMP #: CWRP‐01.04.21002 

Project Name: CWRP ‐ Replace scum pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $130,000  

Project Date: 2021 ‐ 2021 

Background: As part of the primary treatment process, wastewater enters the primary clarifier where 

heavier components sink to the bottom and lighter components float to the top. These clarifiers have a 

skimmer that collects all of the scum floating on the top. Scum pumps convey the floatables to the 

digester process for further processing.  

Justification: The scum pumps at CWRP which allow for this process to occur have reached the end of 

their service life and need to be replaced. 

 

CAMP #: CWRP‐02.03.19001 

Project Name: CWRP ‐ Replace sludge feed pump 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $80,000  

Project Date: 2019 ‐ 2019 

Background: As part of the solids handling process at CWRP, the solids are pumped from the holding 

tank through a grinder and then onto the screw press where excess water is removed. The grinder 

reduces the larger clumps of solids to protect the screw press from excessive wear and tear. 

Justification: The sludge feed pump has reached the end of its service life and needs to be replaced. 

 

CAMP #: CWRP‐01.03.21001 

Project Name: CWRP ‐ Replace sludge pumps at primary clarifier 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $150,000  

Project Date: 2019 ‐ 2019 

Background: The primary clarifier is part of the primary treatment process at CWRP. The clarifier 

removes suspended solids that have settled to the bottom of the tank. These solids are then pumped to 

the digesters in the secondary treatment process to be utilized as a food source for the microbes.  

Justification: The sludge pump at primary clarifier #2 has reached the end of its service life. 

 

 

CAMP #: CWRP‐01.01.19001 

Project Name: CWRP ‐ Replace temporary force main 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $350,000  

Project Date: 2018 ‐ 2020 

Background: In 2014, the force main at the CWRP Influent Lift Station (ILS) suffered a break. While the 

force main was broken, wastewater continued to flow into CWRP which required the District to install 

available pipe that did not have the preferred pipe lining. Due to the anticipated refurbishment in FY18, 

a temporary force main was installed which allowed the plant to return into service quickly. The 

temporary force main was left in place in case it is needed before a secondary force main can be 

installed in a more permanent, buried configuration.  

Justification: This project will construct a secondary force main which will allow the primary force main 

to be installed with the preferred pipe material and lining. This layout will allow for each force main to 

be taken offline for maintenance and inspection which will further increase the anticipated lifespan of 

the pipeline and reduce potential for a spill.  

 

 

CAMP #: CWRP‐01.05.23002 

Project Name: CWRP ‐ Replace tertiary filter cloths 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $50,000  

Project Date: 2023 ‐ 2023 

Background: Tertiary filtration is the final treatment process at the CWRP, before treated effluent is 

disinfected and conveyed to the recycled water distribution system. These filters use a cloth barrier to 

remove residual particulate matter and reduce the turbidity of the process flow. 

Justification: The tertiary filter clothes at CWRP have reached the end of their service life and need to be 

replaced. 

 

 

CAMP #: CWRP‐01.05.23001 

Project Name: CWRP ‐ Replace tertiary filters backwash pumps 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $60,000  

Project Date: 2023 ‐ 2023 

Background: As part of the tertiary treatment process at CWRP, treated wastewater goes through 

tertiary filters in order to remove particulate. These filters undergo a backwash in order to remove the 

collected particulate and keep the filters efficient. 

Justification: The tertiary filter backwash pumps at CWRP have reached the end of their useful service 

life and require replacement.  

 

 

CAMP #: CWRP‐03.02.19001 

Project Name: CWRP ‐ SCADA Replacements 

Project Location: Chiquita Water Reclamation Plant 

Annual Budget: 2019: $133,300  

                    2020: $65,800 

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the CWRP. The SCADA system has been configured to control various equipment and monitor 

the entire treatment process. 

 

CAMP #: CWRP‐01.01.19003 

Project Name: CWRP ‐ Upgrade controls at Influent Lift Station 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $850,000  

Project Date: 2018 ‐ 2020 

Background: The controls for the Influent Lift Station at Chiquita Water Reclamation Plant are the 

original controls installed in 1986. Since then, there have been significant technological upgrades made 

that render the existing controls obsolete. 

Justification: This project will replace all the controls in the Influent Lift Station with an upgraded system 

compatible with the plant‐wide control system. This will allow for much better control of the various 

pumps and monitoring systems within the Influent Lift Station.  

 

CAMP #: CWRP‐03.06.18001 

Project Name: CWRP ‐ Upgrade security 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $250,000  

Project Date: 2018 ‐ 2019 

Background: Since CWRP was built in the 1980s through recent years, the site did not have close 

residential neighbors. With the development of Esencia, residential neighborhoods are in close 

proximity to the plant, increasing the potential for trespessing.  

Justification: In order to protect the District from the potential liability of trespassers, the proposed 

project would install security cameras around the CWRP perimeter and in key process locations. 

 

 

CAMP #: CWRP‐01.03.19001 

Project Name: CWRP‐Replace digester gas piping 

Project Location: Chiquita Water Reclamation Plant 

Total Budget: $300,000  

Project Date: 2019 ‐ 2019 

Background: The anaerobic digesters produce methane gas. The methane gas is typically used in the 

microturbines (which convert it to electricity), to the boilers (where they convert it into heat for the 

digesters). As a backup, the gas can be conveyed to the flare (where it is burned off). The gas piping has 

reached the end of its service life and requires replacement. 

Justification: This proposed project will replace the piping with non‐metallic piping. The new piping will 

provide reliable conveyance of digester gas to the various processes for use or flaring. 

 

05 ‐ Oso Creek Water Reclamation Plant Projects Projects associated with the repair, maintenance, and improvement of the Oso Creek Water Reclamation 

Plant. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

OCWRP ‐ Replace inf. screens and install washer/compactor $500,000

OCWRP ‐ Replace tertiary filters $750,000

OCWRP ‐ SCADA Replacements $54,800

CAMP #: OCWRP‐01.01.18001 

Project Name: OCWRP ‐ Replace influent screens and install washer/compactor 

Project Location: Oso Creek Water Reclamation Plant 

Total Budget: $500,000  

Project Date: 2018 ‐ 2019 

Background: The rotary screens at the Oso Water Reclamation Plant serve to remove large debris (rags, 

toilet paper, etc.) before it flows into the activated sludge process. The screenings are discharged back 

into the downstream sewer for removal and disposal at JB Latham or the 3AWRP. 

Justification: The current rotary screens were originally installed around 1977 

when the plant was constructed. While the existing screens have been repaired many times, they have 

reached the end of their useful service life. This project will replace the two existing rotary screens with 

newer screens. In addition, a washer/compactor will be installed which will clean the screenings and 

convey them to a bin for disposal rather than discharging it back into the downstream sewer. 

 

CAMP #: OCWRP‐01.05.19001 

Project Name: OCWRP ‐ Replace tertiary filters 

Project Location: Oso Creek Water Reclamation Plant 

Total Budget: $750,000  

Project Date: 2019 ‐ 2019 

Background: The tertiary filters are a part of the tertiary treatment process which provides extra 

filtration as treated secondary water becomes tertiary treated recycled water.  

Justification: The tertiary filters at OCWRP have reached the end of their useful service life and are 

scheduled for replacement. The existing filters at OCWRP are sand filters which are an older technology. 

The District has tested out fuzzy filters at the 3AWRP and recommend upgrading to this type of filter as 

part of this project. 

 

CAMP #: OCWRP‐03.02.20001 

Project Name: OCWRP ‐ SCADA Replacements 

Project Location: Oso Creek Water Reclamation Plant 

Total Budget: $54,800  

Project Date: 2020 ‐ 2020 

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the CWRP. The SCADA system has been configured to control various equipment and monitor 

the entire treatment process. 

 

06 ‐ 3A Water Reclamation Plant Projects Projects associated with the repair, maintenance, and improvement of the 3A Water Reclamation Plant. 

These costs represent 100% of the total cost, not SMWD’s share. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

3AWRP ‐ Centrifuge maintenance $100,000 $100,000

3AWRP ‐ Convert EQ basin to secondary clarifier $834,000

3AWRP ‐ Install backup power $1,079,000

3AWRP ‐ Install chemically enchanced primary treatment $777,000

3AWRP ‐ Investigate/Repair subsidence $5,000,000

3AWRP ‐ Modify access in influent screening area $216,000

3AWRP ‐ Rebuild 4 RAS pumps $70,000

3AWRP ‐ Rehab air gap facilities $100,000

3AWRP ‐ Rehab digesters $2,400,000

3AWRP ‐ Rehab primary clarifier #4 $300,000

3AWRP ‐ Repairs/Replacements $250,000 $250,000 $250,000 $250,000 $250,000

3AWRP ‐ Replace aeration blowers $3,954,000

3AWRP ‐ Replace boiler burner $360,000

3AWRP ‐ Replace digester sludge heater pump $50,000

3AWRP ‐ Replace electrical instrumentation $360,000

3AWRP ‐ Replace feed grinders for centrifuge $60,000

3AWRP ‐ Replace odor control equipment $250,000

3AWRP ‐ Replace odor control media $100,000 $100,000

3AWRP ‐ Replace solids thickening process $1,750,000

3AWRP ‐ Resurface roads $300,000

3AWRP ‐ SCADA Replacements $215,000 $75,000 $150,000

3AWRP ‐ Upgrade primary/secondary water facilities $504,000

Grand Total $7,805,000 $10,749,000 $400,000 $650,000 $700,000 $600,000

CAMP #: 3AWRP‐01.04.19001 

Project Name: 3AWRP ‐ Convert EQ basin to secondary clarifier 

Project Location: 3A Water Reclamation Plant 

Total Budget: $834,000  

Project Date: 2019 ‐ 2020 

Background: The 3AWRP has been adapted as the wastewater flows in Mission Viejo have changed. The 

initial design of the plant built an additional secondary clarifier that was eventually deemed unnecessary 

and was turned into an equalization basin.  

Justification: Just as 3AWRP has adapted before, the changing profile of wastewater has required 

3AWRP to adapt again. In the last several years the increased focus on water conservation has resulted 

in wastewater coming into 3AWRP with significantly higher biological oxygen demand (BOD) and total 

suspended solids (TSS) levels. This is attributed to significantly less water being utilized within the home 

such as toilets, showers, and washing machines which concentrates the BOD and TSS within the 

wastewater. The proposed project would convert the equalization basin back to a secondary clarifier 

which would allow 3AWRP to treat the volume of wastewater it is currently rated to treat.  

 

CAMP #: 3AWRP‐03.03.19001 

Project Name: 3AWRP ‐ Install backup power 

Project Location: 3A Water Reclamation Plant 

Total Budget: $1,079,000  

Project Date: 2019 ‐ 2019 

Background: The wastewater treatment process requires power to maintain treatment. The 3AWRP was 

designed as a "skimming plant" and is configured so wastewater can be diverted into the 3A WRP or 

conveyed downstream where JB Latham capacity is available for treatment. During an extended power 

outage, wastewater is diverted because the 3A plant is not equipped with backup power.  

Justification: As the District relies more on 3AWRP for recycled water production, it is imperative that 

the plant is able to stay online. The installation of backup power will reduce the potential of lost 

recycled water production and process upsets due to a power outage.  

 

CAMP #: 3AWRP‐01.03.19001 

Project Name: 3AWRP ‐ Install chemically enchanced primary treatment 

Project Location: 3A Water Reclamation Plant 

Total Budget: $777,000  

Project Date: 2019 ‐ 2019 

Background: The primary treatment process of a wastewater treatment plant typically relies on 

sedimentation. Heavier solids sink to the bottom of a tank while water flows onto the next process.  

Justification: Chemically enhanced primary treatment (CEPT) removes more inorganic solids in the 

primary process than traditional primary treatment, thus reducing the load on the downstream 

secondary process. The usage of CEPT will provide a more stable operation with increased plant capacity 

without the construction of additional aeration basins.  

 

CAMP #: 3AWRP‐03.02.20002 

Project Name: 3AWRP ‐ Investigate/Repair subsidence 

Project Location: 3A Water Reclamation Plant 

Total Budget: $5,000,000  

Project Date: 2019 ‐ 2022 

Background: Extensive soil subsidence is apparent and has caused damage to piping, electrical duct 

banks and structures throughout the 3A plant.  

Justification: The proposed project would research the subsidence issue and develop plans to rectify 

and/or mitigate this issue. This project will reduce the potential for ongoing facility damage and outages 

caused by subsidence. 

 

CAMP #: 3AWRP‐01.01.18001 

Project Name: 3AWRP ‐ Modify access in influent screening area 

Project Location: 3A Water Reclamation Plant 

Total Budget: $216,000  

Project Date: 2018 ‐ 2019 

Background: The influent screening area is where large debris/rags are removed from the wastewater 

before it enters the primary treatment process. Staff needs access to this area to remove accumulated 

grit and foam. If not maintained regularly, this accumulation causes excessive pump wear and a high risk 

of the pumps or piping clogging. 

Justification: The current setup at the 3AWRP influent screening area has poor access for staff to access 

the screens. The wetwell is over 20 feet deep and cannot be access by the District's vacuum trucks. The 

proposed modification will create openings of adequate size and location to allow for staff and 

equipment access. 

 

CAMP #: 3AWRP‐03.02.19003 

Project Name: 3AWRP ‐ Rehab air gap facilities 

Project Location: 3A Water Reclamation Plant 

Total Budget: $100,000  

Project Date: 2019 ‐ 2019 

Background: An air gap is required as domestic water enters the water reclamation plant for use in on‐

site plumbing, eye washes and safety showers. The existing air gap, tank and associated facilities are at 

the end of their service life.  

Justification: The existing air gap structure at 3AWRP has reached the end of its useful service life and 

needs to be replaced. Clean water from a well‐maintained facility is needed for bathrooms, drinking 

water, eye wash stations, etc.  

 

CAMP #: 3AWRP‐02.02.18001 

Project Name: 3AWRP ‐ Rehab digesters 

Project Location: 3A Water Reclamation Plant 

Total Budget: $2,400,000  

Project Date: 2018 ‐ 2019 

Background: The digesters are part of the solids treatment process at 3AWRP. Primary and waste 

actived sludge is conveyed to the digesters where bacteria digests the biological content which makes it 

easier to dewater and produced digester gas. Industry standards dictate that two operating digester 

tanks are required to provide redundancy.  

Justification: While 3AWRP has two digesters, Digester #2 has remained offline due to maintenance 

issues. In order for 3AWRP to expand to handle 5 million gallons per day, both digesters need to be 

operating. The proposed project will return Digester #2 to working order while cleaning Digester #1 as 

well.  

 

CAMP #: 3AWRP‐01.03.18001 

Project Name: 3AWRP ‐ Rehab primary clarifier #4 

Project Location: 3A Water Reclamation Plant 

Total Budget: $300,000  

Project Date: 2018 ‐ 2019 

Background: 3AWRP has four primary clarifiers which are where the inorganic solids settle for removal 

from the process.  This sludge settles to the bottom of the tank and scum floats to the top for removal. 

Forward flow passes into the final chamber where clarified flow passes through weirs and into troughs 

where it is conveyed to the secondary activated sludge process. 

Justification: Primary clarifier #4 troughs and weirs have reached the end of their service life. Primary 

clarifiers #1 ‐ #3 were rehabilitated under a SOCWA project in FY 2015. The proposed project would 

replace the existing metal launders with fiberglass launders which will last longer since they are more 

resistant to corrosion.  

 

CAMP #: 3AWRP‐03.06.19001 

Project Name: 3AWRP ‐ Repairs/Replacements  

Project Location: 3A Water Reclamation Plant 

Annual Budget: 2019 – 2020: $250,000  

    2021 – 2023: $400,000 

Justification: The District earmarks $250,000 for miscellaneous repairs/replacements that occur but are 

not specifically identified. This fund is typically utilized for equipment that breaks or if regulatory 

requirements change.This amount is increasing in 2021 due to anticipated expansion. 

 

CAMP #: 3AWRP‐01.04.18001 

Project Name: 3AWRP ‐ Replace aeration blowers 

Project Location: 3A Water Reclamation Plant 

Total Budget: $3,954,000  

Project Date: 2018 ‐ 2019 

Background: Aeration blower provide air which is introduced into the aeration basins through air 

diffusers. The air is required to maintain the biological treatment. The existing blowers are at the end of 

their service life. Newer more efficient blowers are available which will reduce power costs. The existing 

ceramic type diffusers are also at the end of service life. Newer, more efficient membrane diffusers are 

proposed to replace the existing diffusers. 

Justification: The aeration diffusers and the blowers which circulate the air have reached the end of 

their service life and need to be replaced. Newer, more efficient, diffusers and blowers will increase the 

capacity and improve the operational flexibility and performance of the plant. 

 

CAMP #: 3AWRP‐02.04.18001 

Project Name: 3AWRP ‐ Replace boiler burner 

Project Location: 3A Water Reclamation Plant 

Total Budget: $360,000  

Project Date: 2018 ‐ 2019 

Background: The boiler utilizes a blend of gas that is produced from the digester process and natural 

gas. The boiler heats water, which is used in heat exchangers to heat sludge circulated through the 

digester to maintain the required temperature.  

Justification: The burner components of the boiler are no longer in compliance with air quality 

regulations and need to be replaced. 

 

CAMP #: 3AWRP‐03.02.18002 

Project Name: 3AWRP ‐ Replace electrical instrumentation 

Project Location: 3A Water Reclamation Plant 

Total Budget: $360,000  

Project Date: 2018 ‐ 2019 

Background: Existing electrical and controls equipment was installed approximately 30 years ago. The 

equipment manufacturer for the existing equipment is no longer providing parts and materials which 

makes finding replacement parts extremely difficult and costly. This project will replace PLC's, electrical 

gear and instrumentation with equipment that meets SMWD standards and can be fully integrated into 

control systems. 

Justification: The equipment manufacturer for the existing equipment is no longer providing parts and 

materials which makes finding replacement parts extremely difficult and costly.  

 

CAMP #: 3AWRP‐03.01.20001 

Project Name: 3AWRP ‐ Replace odor control equipment 

Project Location: 3A Water Reclamation Plant 

Total Budget: $250,000  

Project Date: 2021 ‐ 2021 

Background: The primary treatment process odor control equipment at 3AWRP has been in service 

since 1987. The odor control consists of a biological scrubber followed by a carbon adsorber. This 

equipment treats foul air from the headworks, sludge dewatering and primary processes. The biological 

scrubber requires condition assessment and rehabilitation as needed. 

Justification: This proposed project will replace necessary components and also rehabilitate existing 

odor control to extend its service life where applicable. Odor control must be maintained in accordance 

with the AQMD permit. 

 

CAMP #: 3AWRP‐02.03.19001 

Project Name: 3AWRP ‐ Replace solids thickening process 

Project Location: 3A Water Reclamation Plant 

Total Budget: $1,750,000  

Project Date: 2019 ‐ 2020 

Background: As part of the dewatering process at 3AWRP, a dissolved air floatation (DAF) thickening is 

utilized. This process creates a blanket of bubbles that adhere to solids which float to the surface. This 

thickened sludge is removed and conveyed to the digester for treatment. 

Justification: The 3AWRP has two DAF units. However, due to soil subsidence, one of the units cannot 

operate properly. This proposed project would replace one (or both) of the DAF units with mechanical 

thickeners. This different type of thickener is a more efficient alternative to DAF thickening. This project 

will also reconfigure the dewatering area to allow for larger dewatered sludge bins which will allow for 

fewer disposal trips and reduce the solids handling cost at the treatment plant.  

 

CAMP #: 3AWRP‐03.01.22001 

Project Name: 3AWRP ‐ Resurface roads 

Project Location: 3A Water Reclamation Plant 

Total Budget: $300,000  

Project Date: 2022 ‐ 2022 

Background: Due to the size and layout of 3AWRP, there is a network of roads throughout the plant 

which allow operators to transit.  

Justification: The roads at 3AWRP have reached a point where they need to be refurbished in order to 

avoid a costlier replacement. The proposed project would reasphalt the roads to extend their service 

life. 

 

CAMP #: 3AWRP‐03.02.18001 

Project Name: 3AWRP ‐ SCADA Replacements 

Project Location: 3A Water Reclamation Plant 

Annual Budget: Ongoing: $215,000  

    2019: $75,000 

    2020: $150,000 

Justification: The District relies on its supervisory control and data acquisition (SCADA) systems to 

operate the 3AWRP. The SCADA system has been configured to control various equipment and monitor 

the entire treatment process.  

 

CAMP #: 3AWRP‐03.02.19001 

Project Name: 3AWRP ‐ Upgrade primary/secondary water facilities 

Project Location: 3A Water Reclamation Plant 

Total Budget: $504,000  

Project Date: 2019 ‐ 2019 

Background: Once wastewater completes the secondary treatment process, it is ready to be discharged 

to the ocean. However, the 3AWRP currently utilizes this secondary treated water for washing down the 

plant as well as supplementing the treatment process where additional water is necessary.  

Justification: The secondary treated water is acceptable for the odor scrubber, recycled water served by 

Moulton Niguel Water District is available in the area and would provide a better resource to utilize 

instead of treated secondary water.  

 

07 ‐ Outside Capital Projects Projects where other agencies are heading the efforts such as the J.B Latham Treatment Plant (SOCWA), 

the Baker Water Treatment Plant (IRWD), and other projects. These costs represent SMWD’s share of the 

project, not the total cost. 

 

 

 

   

Column1 Ongoing 2019 2020 2021 2022 2023

CalTrans ‐ Relocate pipeline near I5 and Aliso Creek $1,639,000

CalTrans ‐ Relocate pipeline near I5 and Oso Creek $300,000

IRWD ‐ Baker Water Treatment Plant Upgrades $50,000

LBCWD ‐ Replace meter at CM‐12 $250,000

MNWD ‐ ETM Outfall Valves $225,000

MNWD ‐ ETM Replacement ‐ Avenida de a Vista $100,000

MNWD ‐ ETM Replacement ‐ Camino Capistrano $1,750,000

MNWD ‐ Install recycled pipeline casing under I5 and Oso Creek $550,000

OC Public Works ‐ Relocate pipeline near Tesoro HS $1,000,000

SOCWA ‐ Repairs/Replacements $3,886,413 $2,193,523 $2,505,963 $1,964,612 $1,275,416

Grand Total $2,639,000 $5,036,413 $2,193,523 $4,255,963 $2,189,612 $1,375,416

CAMP #: IRWD‐08.06.19001 

Project Name: IRWD ‐ Baker Water Treatment Plant Upgrades 

Project Location: Baker Water Treatment Plant 

Total Budget: $50,000  

Project Date: 2019 ‐ 2019 

Background: The Baker Water Treatment Plant went online in January 2017 and provides increased 

water supply reliability to South Orange County by increasing local treatment capability from multiple 

water supply sources, including imported untreated water from the Metropolitan Water District of 

Southern California (MWD) through the Santiago Lateral and local surface water from Irvine Lake.  

Justification: After the first year of operation, the operators at Baker Water Treatment Plant have 

identified several capital improvements that would increase the efficiency of the plant.  

     ‐ Programming changes  

     ‐ Modifications to Clean In Place process 

     ‐ Piping modifications 

 

CAMP #: LBCWD‐07.04.19002 

Project Name: LBCWD ‐ Replace meter at CM‐12 

Project Location: CM‐12 Intertie with LBCWD 

Total Budget: $250,000  

Project Date: 2019 ‐ 2019 

Background: While this connection represents less than 5% of the District's domestic water supply, the 

connection (CM‐12) is kept open to maintain a reliable backup in case of an emergency. When this 

connection was installed, higher demands for Southern Orange County were expected. However, the 

construction of the South County Pipeline and the development of recycled infrastructure has led to 

significantly less flow than this meter was designed to handle.  

Justification: Due to conservation measures, the flows through CM‐12 began to dip under the minimum 

flow level for the meter. While the meter can record up to 40 cfs, it can only accurately record volumes 

higher than 10 cfs. If the meter is showing flow at 7 cfs, the agencies must pay as if the connection is 

flowing at 10 cfs. This lead to the participating agencies paying for water that they were not receiving. In 

order to prevent these penalties from occurring again, a new meter that can handle lower flows will be 

installed. 

 

 

CAMP #: MNWD‐07.03.19001 

Project Name: MNWD ‐ ETM Outfall Valves 

Project Location: Meadow Ridge LS 

Total Budget: $225,000  

Project Date: 2022 ‐ 2022 

Background: The Effluent Transmission Main (ETM) was originally constructed in 1978 as a pressure 

main to supply water from wells located in San Juan Capistrano to Lake Mission Viejo. Moulton Niguel 

Water District (MNWD) purchased half of the “Lakefill Line” or ETM and converted the pipeline from a 

pressure force main to a gravity pipeline to discharge 3A WRP treated effluent to the Chiquita Land 

Outfall. The ETM is over 35,000 feet in length and travels through various terrains and city jurisdictions. 

SMWD also utilizes the ETM for emergency 

disposal of Oso Creek stream flow if 

SMWD’s Oso Creek Barrier facility is not in 

service. In accordance with a permit issued 

by the San Diego Regional Water Quality 

Control Board, Oso Creek Barrier low flows 

can be bypassed upstream of Oso Parkway 

into the ETM for transfer to SMWD’s 

Chiquita Land Outfall pipeline near Dana 

Point. 

Justification: Since the pipeline was 

repurposed from its original purpose of 

feeding Lake Mission Viejo, there is an 

insufficient amount of isolation valves 

along a five mile stretch. If there was a 

failure along this reach, the line would 

discharge secondary effluent into the 

creeks. The installation of additional 

isolation valves will reduce the exposure of 

a potential spill. The total cost of this 

project is $450k with SMWD's share to cost 

$225k.  

 

CAMP #: MNWD‐07.01.23001 

Project Name: MNWD ‐ ETM Replacement ‐ Avenida de a Vista 

Project Location: MNWD ‐ Effluent Transmission Main 

Total Budget: 100000 

Project Date: 2023 ‐ 2023 

Background: The Effluent Transmission Main (ETM) was originally constructed in 1978 as a pressure 

main to supply water from wells located in San Juan Capistrano to Lake Mission Viejo. Moulton Niguel 

Water District (MNWD) purchased half of the Lakefill Line or ETM and converted the pipeline from a 

pressure force main to a gravity pipeline to discharge 3A WRP treated effluent to the Chiquita Land 

Outfall. The ETM is over 35,000 feet in length and travels through various terrains and city jurisdictions. 

SMWD also utilizes the ETM for emergency disposal of Oso Creek stream flow if SMWD’s Oso Creek 

Barrier facility is not in service. In accordance with a permit issued by the San Diego Regional Water 

Quality Control Board, Oso Creek Barrier low flows can be bypassed upstream of Oso Parkway into the 

ETM for transfer to SMWD’s Chiquita Land Outfall pipeline near Dana Point. 

Justification: The existing alignment of the ETM in this area is located in an embankment along an 

unprotected bank of Trabuco Creek and is at risk of failure due to erosion of the creek bank. This 

proposed project will abandon the existing strecth of ETM pipeline and construct a replacement pipeline 

in Avenida de la Vista. The total cost of this project is $2.475 million with SMWD's share to cost $1.2 

million ($100k in 23, $1.1 mil in 24).  

 

CAMP #: MNWD‐07.01.21001 

Project Name: MNWD ‐ ETM Replacement ‐ Camino Capistrano 

Project Location: MNWD ‐ Effluent Transmission Main 

Total Budget: 1750000 

Project Date: 2021 ‐ 2022 

Background: The Effluent Transmission Main (ETM) was originally constructed in 1978 as a pressure 

main to supply water from wells located in San Juan Capistrano to Lake Mission Viejo. Moulton Niguel 

Water District (MNWD) purchased half of the Lakefill Line or ETM and converted the pipeline from a 

pressure force main to a gravity pipeline to discharge 3A WRP treated effluent to the Chiquita Land 

Outfall. The ETM is over 35,000 feet in length and travels through various terrains and city jurisdictions. 

SMWD also utilizes the ETM for emergency disposal of Oso Creek stream flow if SMWD’s Oso Creek 

Barrier facility is not in service. In accordance with a permit issued by the San Diego Regional Water 

Quality Control Board, Oso Creek Barrier low flows can be bypassed upstream of Oso Parkway into the 

ETM for transfer to SMWD’s Chiquita Land Outfall pipeline near Dana Point. 

Justification: The existing pipeline is approaching the end of its useful service life. Replacement of the 

existing strecth of 20‐inch pipeline will increase hydraulic capacity and improve operation of the 

pipeline. The total cost of this project is $3.5 million with SMWD's share to cost $1.75 million ($150k in 

21, $1.6 mil in 22).  

 

CAMP #: OCPW‐07.01.18001 

Project Name: OC Public Works ‐ Relocate pipeline near Tesoro HS 

Project Location: OCPW ‐ 241 at Oso Parkway 

Total Budget: $1,000,000  

Project Date: 2018 ‐ 2020 

Background: In order to connect Los Patrones Parkway to State Route 241, the stretch of Oso Parkway 

that is in the way is being converted to a bridge. Currently, the District has 16" and a 24" water pipelines 

that is responsible for supplying southern Coto de Caza with domestic water. 

Justification: Since the District does not have an easement for this stretch, it's up to the District to pay 

for this relocation. 

 

CAMP #: SOCWA‐03.06.19001 

Project Name: SOCWA ‐ Repairs/Replacements for FY19 

Project Location: SOCWA 

Annual Budget: 2019: $3,886,413  

    2020: $2,193,523 

2021: $2,505,963 

2022: $1,964,612 

2023: $1,275,416 

Background: South Orange County Wastewater Authority (SOCWA) is a Joint Powers Authority made up 

of ten member agencies in order to operate three treatment plants and two ocean outfalls, in addition 

to multiple programs to meet the needs of its member agencies and the requirements of the Clean 

Water Act and applicable National Pollutant Discharge Elimination System (NPDES) permits. 

Justification: When SMWD has more flow than it's treatment plants can handle, wastewater flows are 

sent to SOCWA's Jay B. Latham Plant for treatment. Latham and the District's treatment plants utilize 

the San Juan Creek Ocean Outfall to discharge treated secondary water into the ocean for disposal. In 

addition to paying a portion of the operating and maintenance costs, the District pays a proportion of 

the capital cost for these facilities as well. 

 

08 ‐ Overhead Projects Projects associated with the repair, maintenance, and improvement of the Administration Building, 

Warehouse, and Operations Overhead. 

 

 

 

 

 

 

 

Column1 Ongoing 2019 2020 2021 2022 2023

Headquarters ‐ Install pallet racks $170,000

Headquarters ‐ Modifications to Ready Room $345,000

Headquarters ‐ Rehab demonstration garden $150,000

Headquarters ‐ Rehab exterior of buildings $150,000

Headquarters ‐ Replace furniture/workspaces $500,000

Grand Total $170,000 $995,000 $150,000

CAMP #: OH‐08.01.18001 

Project Name: Headquarters ‐ Install pallet racks 

Project Location: District Headquarters 

Total Budget: $170,000  

Project Date: 2018 ‐ 2020 

Background: The District has fully utilized the available horizontal space in the warehouse area and 

behind it. In an effort to more efficiently utilize this space, the District is working on installing pallets 

racks that will allow for vertical storage as well.  

Justification: By building the pallet racks, it will allow the District to continue to maintain an inventory 

which will allow for timely service as well as quick emergency repairs.  

 

CAMP #: OH‐08.01.19001 

Project Name: Headquarters ‐ Modifications to Ready Room 

Project Location: District Headquarters 

Total Budget: $345,000  

Project Date: 2019 ‐ 2019 

Background: Since the District moved to the current headquarters in 1994, service connections have 

doubled, and the employee count has risen as well. The Ready Room is located adjacent to the 

warehouse and is where all Operations Field Crews meet in the morning to coordinate their daily duties. 

In addition, it's also where the locker room facilities are located for employees to shower after their 

work day. 

Justification: The proposed modifications are to redesign the locker room facilities to alleviate the 

crowding issues that occur as well as redesign the Ready Room area to better allow for multiple crews to 

utilize it at the same time. 

 

CAMP #: OH‐08.06.19003 

Project Name: Headquarters ‐ Rehab demonstration garden 

Project Location: District Headquarters 

Total Budget: $150,000  

Project Date: 2019 ‐ 2019 

Background: The District has maintained a water conservation demonstration garden behind the office 

since the early 1990’s.  Its purpose is to provide a public space for the education and inspiration of low 

water‐use landscaping.  The physical appearance of the garden, due to both age and maintenance, no 

longer supports its intended purpose of enjoying and inspiring low water‐use landscaping. 

As part of the Operating budget, the District budgets each fiscal year for a landscape maintenance 

contract to take care of landscaping at District facilities.  The demonstration garden is but part of this 

larger contract and has suffered from a lack of maintenance.  

Justification: Since installation in the early 1990’s, the demonstration garden’s aesthetics and irrigation 

system has degraded and needs rehabilitation.  In its present state, the garden does not support the 

District’s water efficiency programs that promote beautiful and functional low water‐use landscapes.  A 

new garden design and installation will support District water efficiency programs while rehabilitating 

aging facility infrastructure related to the adjacent trellis and outdoor patio.  A separate contract to 

maintain the garden will ensure the right level of attention and care is provided to this asset.  

 

CAMP #: OH‐08.06.19002 

Project Name: Headquarters ‐ Replace furniture/workspaces 

Project Location: District Headquarters 

Total Budget: $500,000  

Project Date: 2019 ‐ 2019 

Background: The office furniture and modular furniture (such as cubicles and wall dividers) at the 

Administration building have been in service since the early 1990's.  

After 25+ years, the useful life of the furniture has been exceeded. Additional modular pieces are 

unavailable for order which limits the District's ability to replace and modify its existing layout.  

Justification: The District is looking to replace the modular furniture for approximately 20,000 square 

feet which represents the entirety of the Administration Building except for areas occupied by tenants. 

The typical workspace has dramatically changed since the existing furniture was installed. The existing 

furniture was designed around a 20th Century workflow while the current workflow is drastically 

different. Work stations no longer need to accommodate for several file cabinets and large computers. 

However, additional meeting space for coordination and training is becoming increasingly sparse. 

Preliminary estimates range from $15 ‐ $22 per square foot for the design and replacement of modular 

furniture and office furniture.