COMMISSIONING /RETRO-COMMISSIONING &ENERGY AUDITS
PERCEPTION vs. REALITY
J. Woody Thompson, PE, CxA, CEM, REP, CPMP,CBCP, LEED AP
-
8/9/2019 5 Commissioning
2/35
Session Learning Objectives:
Commissioning (Cx) & Retro-Commissioning (RCx)What it IS & IS NOT
Objectives & Benefits
Systems, Providers, & References
Cx & RCx ProcessCx & LEED
Energy Audits / Surveys
Process & Benefits
-
8/9/2019 5 Commissioning
3/35
The Commissioning Process
The Commissioning Process is aquality-focused processforenhancing the delivery of a project byverifying and documenting that thefacility and all of its systems andassemblies are planned, designed,
installed, tested, operated, andmaintained to meet the OwnersProject Requirements.-- ASHRAE Guideline 0-2013: TheCommissioning Process
-
8/9/2019 5 Commissioning
4/35
What is Cx? RCx? ReCx?
Commissioningis performed specifically to ensure thatthe finished facility operates in accordance with the ownersdocumented project requirements (OPR) and theconstruction documents (BOD).
Retro-Commissioningis the commissioning processas applied to an existing facility that has never beencommissioned. Focus is on building performance and how toimprove utility/energy consumption.
Re-Commissioningis the commissioning process asapplied to an existing building that had been commissionedbut no longer meets owners current operational need.
http://www.nottinghamshire.gov.uk/youthzone/youthzone-getactive/cpd-thinking.gif -
8/9/2019 5 Commissioning
5/35
More Definitions
Commissioning Authority / Agent Helps Commissioning Team Implement Cx Process
Leads, Plans, Schedules, & Coordinates Cx Team
Hired by Owner (Ideally)
Commissioning Team
Owner, DoR, GC & Subs, CxA & Specialists
All Stakeholders that Implement Commissioning Process
http://www.nottinghamshire.gov.uk/youthzone/youthzone-getactive/cpd-thinking.gif -
8/9/2019 5 Commissioning
6/35
Still More Definitions
Owners Project Requirements (OPR) Written document of project requirements. (NOT the RFP)
Details how project will be used and operated.
Basis of Design (BoD)
Record of how the OPR is met in design.
Concepts, Calculations, Decisions, and Product Selections
Commissioning Plan
Documents Requirements of Commissioning Process Outlines Organization, Schedule, & Resources
http://www.nottinghamshire.gov.uk/youthzone/youthzone-getactive/cpd-thinking.gif -
8/9/2019 5 Commissioning
7/35
Even More Definitions
Commissioning Report Records the Activities & Results of the Cx Process
Developed from Final Commissioning Plan
Systems Manual
Composite Document
Design & Construction, O&M, Cx, Training, Maintenance, etc.
Issues & Resolutions Log
Ongoing Record of Problems/Concerns & Resolutions
Maintained Throughout Life of Project
http://www.nottinghamshire.gov.uk/youthzone/youthzone-getactive/cpd-thinking.gif -
8/9/2019 5 Commissioning
8/35
Enough Definitions
Monitor Based Commissioning Ongoing Building Energy System Monitoring
Provides Substantial, Persistent, Energy Savings
On-Going / Persistent Commissioning
Post Warranty Continuation of Cx Process
Improves Performance as Building Evolves
Positive Feedback Commissioning
Monitors Critical Aspects of Building Performance
Predictor of Operational Failure: Safety, Comfort, Efficiency
http://www.nottinghamshire.gov.uk/youthzone/youthzone-getactive/cpd-thinking.gif -
8/9/2019 5 Commissioning
9/35
What Cx / RCx IS NOT!
Construction Administration / Quality Control
Bunch of Tests at the end of Construction
Maintenance Contract
Energy Audit / Study
HVAC Test and Balance
http://www.istockphoto.com/file_thumbview_approve/9206198/2/istockphoto_9206198-do-not-symbol.jpghttp://www.istockphoto.com/file_thumbview_approve/9206198/2/istockphoto_9206198-do-not-symbol.jpg -
8/9/2019 5 Commissioning
10/35
Objectives of Cx / RCx
Implement Quality-Verification Practices for Design & Construction Owners Project Requirements (OPR) are Being Met By the Basis of
Design (BOD) & Construction
Provide Documentation & Tools to Improve Quality of Deliverables
Verify Coordination Between Owner, Designers, and Builders
Verify and Document that Building & Integrated Systems PerformProperly
Verify that O&M Staff are Trained
ENSURING THE OWNER GETS
WHAT THEY PAID FOR!
http://www.google.com/imgres?imgurl=http://have-a-nice-day.org/happy/images/Smiley%20Face%20(flat).jpg&imgrefurl=http://have-a-nice-day.org/happy/Smiley%20Face%20(flat).html&usg=__dH_gzL1igNesYgGInsPaOT9WDlw=&h=1800&w=1800&sz=143&hl=en&start=11&zoom=1&itbs=1&tbnid=NcreDsGXlmu9OM:&tbnh=150&tbnw=150&prev=/images?q=smiley+face&hl=en&rls=com.microsoft:*&biw=1280&bih=846&tbm=isch&ei=mtUhTpqfHYTZgQfK8cW-Cwhttp://ian.umces.edu/imagelibrary/albums/userpics/12789/normal_ian-symbol-positive.png -
8/9/2019 5 Commissioning
11/35
Benefits of Cx / RCx
Higher Quality Product that Leads to Better Owner, A/E &Contractor Reputations
Confident O&M Staff inMaintaining Facility
Budget Savings in Capital & Operations
Healthy Building which Improves Occupant Productivity
Less Conflicts / Litigation
http://www.google.com/imgres?imgurl=http://info.instantis.com/Portals/37019/images/resource%20management%20benefits.jpg&imgrefurl=http://info.instantis.com/enterprise-ppm-blog/bid/55468/Resource-Management-Maturity-Model-Benefits&usg=__VBYV1_lepPXCBJUMEOhJbF1Do0A=&h=346&w=347&sz=54&hl=en&start=4&zoom=1&itbs=1&tbnid=qAde4yUSfUqvvM:&tbnh=120&tbnw=120&prev=/images?q=benefits&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=4tUhTrHsGsTdgQeAls2-Cw -
8/9/2019 5 Commissioning
12/35
Cx / RCx Systems
HVAC system and associated controls Electrical lighting and power
Plumbing systems
Building envelope
Renewable energy systems
Refrigeration systems
Industrial process system
Life safety & fire protection systems Security systems
JUST ABOUT ANYTHING!
http://www.google.com/imgres?imgurl=http://thejourneyofbuildingourfamily.files.wordpress.com/2011/05/certified-stamp.gif&imgrefurl=http://thejourneyofbuildingourfamily.wordpress.com/tag/licensing/&usg=__VUBhBmdz71EyyeVu-Eq11DJZu7U=&h=3750&w=5000&sz=612&hl=en&start=4&zoom=1&itbs=1&tbnid=KxN4sWDxgc6znM:&tbnh=113&tbnw=150&prev=/images?q=certified&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=QdYhToHlEMTbgQfUuuG-Cw -
8/9/2019 5 Commissioning
13/35
What is a CertifiedCx / RCx Provider?
Certified Building Commissioning Professional (CBCP) -AEE
Commissioning Process Management Professional
(CPMP) - ASHRAE Commissioning Authority (CxA) ACG
Certified Commissioning Provider (CCP) BCA
Commissioning Accredited Professional (CxAP)
University of Wisconsin Madison Qualified Commissioning Administrator (QCA) NEBB
Certified Commissioning Supervisor (CCS) - TABB
http://www.google.com/imgres?imgurl=http://thejourneyofbuildingourfamily.files.wordpress.com/2011/05/certified-stamp.gif&imgrefurl=http://thejourneyofbuildingourfamily.wordpress.com/tag/licensing/&usg=__VUBhBmdz71EyyeVu-Eq11DJZu7U=&h=3750&w=5000&sz=612&hl=en&start=4&zoom=1&itbs=1&tbnid=KxN4sWDxgc6znM:&tbnh=113&tbnw=150&prev=/images?q=certified&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=QdYhToHlEMTbgQfUuuG-Cw -
8/9/2019 5 Commissioning
14/35
Qualified Cx / RCx Provider Attributes
Ability to Work with Multi-Disciplined Team
Good Communicator / Diplomat
Organized
Ample Field Experience
Understanding of the A/E and Contractor Requirements
Ability to Define Optimal Operating Procedures for
Building Systems
http://www.google.com/imgres?imgurl=http://www.healthcarereformmagazine.com/upload/articles/pursuing-the-promise-of-care-coordination-with-qualified-credentialed-professionals.jpg&imgrefurl=http://www.healthcarereformmagazine.com/article/pursuing-the-promise-of-care-coordination-with-qualified-credentialed-professionals.html&usg=__tK4foHpd4LR5EWLNiH_I0y3rIXc=&h=336&w=344&sz=21&hl=en&start=17&zoom=1&itbs=1&tbnid=RlENpVIKr0m3tM:&tbnh=117&tbnw=120&prev=/images?q=qualified+professional&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=gtYhTuuKDMeRgQeBr9W-Cw -
8/9/2019 5 Commissioning
15/35
Cx / RCx References
ASHRAE Guideline 0-2013 (replaced 0-2005)
ASHRAE Guideline 1.1-2007 (replaced 1-1996)
ASHRAE Standard 202-2013
ACG Commissioning Guideline
NEBB Procedural Standards for Building Systems
Commissioning
SMACNA HVAC Commissioning Guideline
Portland Energy Conservation, Inc. (PECI)
*NUMEROUS OTHERS!
http://www.google.com/imgres?imgurl=http://www.oralchelation.net/images/bs00554_.jpg&imgrefurl=http://www.oralchelation.net/&usg=__i1SURKymED8cV4q5S3UjIflYdkw=&h=364&w=417&sz=16&hl=en&start=18&zoom=1&itbs=1&tbnid=h6wghqRLs3CxEM:&tbnh=109&tbnw=125&prev=/images?q=references&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=ydYhTqmsI83pgAfl1sy-Cw -
8/9/2019 5 Commissioning
16/35
The Commissioning (Cx) Process
The commissioning process involves activities that areintegrated into every phase of the project . . .
NOT CONSTRUCTION ADMINISTRATION!
NOT JUST TESTING AT THE END!
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
17/35
Commissioning: Program Phase
Define Project Scope
Identify Owners Project Requirements
Develop Budget for Commissioning
Establish Commissioning Plan
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
18/35
Commissioning: Design Phase
Verify Basis of Design With Owners ProjectRequirements
Review Design Documents for Completeness andLong-term System Integrity/Maintenance
Create Checklists and CommissioningRequirements
Define Training Requirements
Update Commissioning Plan
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
19/35
Commissioning: Construction Phase
Update Commissioning Plan
Verify Submittals With Design Documents
Develop Detailed Test Procedures and Data Forms
Verify That Systems Comply With DesignDocuments
Develop Systems Manual for Operation andMaintenance
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
20/35
Commissioning: Acceptance Phase
Manage Functional Performance Testing
Verify Training of Operations & Maintenance(O&M) Personnel
Maintain Issue Logs
Convene Lessons Learned Workshop
Deliver System Manual
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
21/35
Commissioning: Warranty Phase
Verify Seasonal Testing of Facility Systems
Verify Continuing O&M Personnel Training
Conduct Periodic Performance Evaluations ofSystems & Assemblies
Deliver Final Systems Manual
PROGRAM DESIGN CONSTRUCTION ACCEPTANCE WARRANTY
-
8/9/2019 5 Commissioning
22/35
The Retro-Commissioning (RCx) Process
The retro-commissioning process involves activities that areintegrated into every phase of the project . . .
NOT A MAINTENANCE CONTRACT!
NOT JUST AN ENERGY STUDY!
PRE-PLANNING PLANNING INVESTIGATION IMPLEMENT HAND-OFF
-
8/9/2019 5 Commissioning
23/35
Retro-Commissioning:Pre-Planning Phase
Identify Possible Candidate Buildings
Collect Utility Data & Evaluate
Generate Energy Star Portfolio Manager Energy Performance
Rating
Select Candidate Building(s)
Define Project Goals & Objectives (OPR)
PRE-PLANNING PLANNING INVESTIGATION IMPLEMENT HAND-OFF
http://www.google.com/imgres?imgurl=http://patentlawcenter.pli.edu/wp-content/uploads/2010/10/man-question-mark.jpg&imgrefurl=http://patentlawcenter.pli.edu/2010/10/04/what-is-prior-art/man-question-mark/&usg=__MElEOct9NZOVrrgiC7WNXtzT07w=&h=359&w=286&sz=11&hl=en&start=9&zoom=1&itbs=1&tbnid=RtcmX_DtJpu3_M:&tbnh=121&tbnw=96&prev=/images?q=question+mark&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=Z9chTuXWFYuugQeWkry-Cw -
8/9/2019 5 Commissioning
24/35
Retro-Commissioning: Planning Phase
Perform Facility Interviews & Walk-through
Confirm Project Goals & Objectives (OPR)
Submit Draft RCx Plan for Owner Review
Submit Final RCx Plan
PRE-PLANNING PLANNING INVESTIGATION IMPLMENT HAND-OFF
http://www.google.com/imgres?imgurl=http://www.mdp.state.md.us/images/OurWork/planning-1.jpg&imgrefurl=http://www.mdp.state.md.us/OurWork/localplanning.shtml&usg=__iPZqWdKSVqEQDancq853Wg1x5NQ=&h=348&w=577&sz=44&hl=en&start=2&zoom=1&itbs=1&tbnid=Q_td-1ppMbR03M:&tbnh=81&tbnw=134&prev=/images?q=planning&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=EdchTpnKJtG_gQfFgcm-Cw -
8/9/2019 5 Commissioning
25/35
Retro-Commissioning:Investigation Phase
RCx Plan Presented to Key Facility Staff
Conduct In-Depth Building Investigation
Submit Findings Log & Energy Savings Calculations to Owner
Owner Selects Energy Conservation Measures to Implement
Submit Final RCx Investigation Report w/ Recommended
Implementation Measures
PRE-PLANNING PLANNING INVESTIGATION IMPLEMENT HAND-OFF
http://www.google.com/imgres?imgurl=http://www.lawyerbrooks.com/investigation.jpg&imgrefurl=http://www.lawyerbrooks.com/investigation.html&usg=__Pp2Cy-lxlm8ptBHAwJT2mOwMBAc=&h=370&w=600&sz=49&hl=en&start=1&zoom=1&itbs=1&tbnid=e0lrk2cl3HaqiM:&tbnh=83&tbnw=135&prev=/images?q=investigation&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=o9chTryPOs3TgQewiMi-Cw -
8/9/2019 5 Commissioning
26/35
Retro-Commissioning:Implementation Phase
Submit Implementation Plan (similar to Cx Plan)
Energy Conservation Measures & Improvements are Made
Verify Pre-Functional Performance Testing
Conduct Functional Performance Testing
PRE-PLANNING PLANNING INVESTIGATION IMPLEMENT HAND-OFF
http://www.google.com/imgres?imgurl=http://campaigns.realpage.com/realworld/files/2011/04/implementation.jpg&imgrefurl=http://campaigns.realpage.com/realworld/keys-to-a-successful-implementation/&usg=__jevWiIehW0_W3RNF6KBHCp7OBC8=&h=314&w=467&sz=13&hl=en&start=2&zoom=1&itbs=1&tbnid=3jzVF1yp5Hiy-M:&tbnh=86&tbnw=128&prev=/images?q=implementation&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=49chTp2BKY7UgAeFt8G-Cw -
8/9/2019 5 Commissioning
27/35
Retro-Commissioning: Hand-Off Phase
Verify Seasonal Testing of Facility Systems
Verify O&M Personnel Training
Conduct Lessons Learned Workshop
Conduct Periodic Performance Evaluations of Systems &
Assemblies
Deliver Final Retro-Commissioning Report (Systems Manual)
PRE-PLANNING PLANNING INVESTIGATION IMPLEMENT HAND-OFF
http://www.google.com/imgres?imgurl=http://1.bp.blogspot.com/-Kw-JZ_En1AY/TdwOQmZM0aI/AAAAAAAAAJ8/N2yu9ZB88XY/s1600/handoff.jpg&imgrefurl=http://trishaleaver.blogspot.com/2011/05/hand-off.html&usg=__5P8JSwCODAupUX0SV0FLu_ZNtfM=&h=254&w=469&sz=24&hl=en&start=1&zoom=1&itbs=1&tbnid=du8bzMzM2Hh4lM:&tbnh=69&tbnw=128&prev=/images?q=hand-off&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=GNghTqSyM4zpgAfcg8y-Cw -
8/9/2019 5 Commissioning
28/35
LEED v4 Fundamental Commissioning EA PreReq Fundamental Commissioning and Verification
Systems Commissioned: HVAC&R & Associated Controls Plumbing: Domestic Hot Water &
Associated Controls Interior & Exterior Lighting Controls Electrical Service & Distribution Renewable Energy Systems Option: Envelope, Life Safety, Comm/Data,
Fire Protection/Alarm, Process Equipment
Review OPR, BoD & Design / Verify Agreement Write Cx Specs Develop & Implement Cx Plan Verify Pre-Functional & Functional Performance Tests Issue Final Report / Systems Manual
-
8/9/2019 5 Commissioning
29/35
-
8/9/2019 5 Commissioning
30/35
What is an EnergyAudit / Survey?
It serves the purpose of identifying where a building or plantfacility uses energy and highlights energy conservationopportunities (ECOs). Albert Thumann
Detailed examination and analysis of how a facility usesenergy.
Identifies what the facility pays for that energy.
Recommends a program for changes in operational practices
and / or energy consuming equipment.
http://www.google.com/imgres?imgurl=http://trustedhi.com/sitebuildercontent/sitebuilderpictures/webassets/EnergyAudit.jpg&imgrefurl=http://trustedhi.com/catalog/i50.html&usg=__RkICJdX_bkE5y31C1ZwyftpjQ04=&h=915&w=800&sz=41&hl=en&start=6&zoom=1&itbs=1&tbnid=4NQot6_-JflDZM:&tbnh=147&tbnw=129&prev=/images?q=energy+audit&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=ZNghTp2NM8PZgQe_mMW-Cw -
8/9/2019 5 Commissioning
31/35
-
8/9/2019 5 Commissioning
32/35
ASHRAE Energy Audits
Level 1 : Lowest Cost Preliminary Opportunity Assessment(POA) Walk through site visit
Review of Energy Bills (consumption, costs, rate structure)
Report includes list of Low cost / No cost Opportunities
Level 2 : includes Level 1, plus Energy use breakdown by system and energy source O& M practices , Constraints, Economic criteria
List of ECMs recommended for further detailed quantification and analysis
Level 3 : (Investment grade) Detailed site visit, system performance data gathering
Level 2 list of ECMs are evaluated in detail. Current costs, potential savings,paybacks
High level of confidence in economics and schedule of each ECM
-
8/9/2019 5 Commissioning
33/35
Energy Audit Overall Benefits
Planning Tool to Develop Future Capital InvestmentBudget
Prioritize Which Facilities Need The Most Attention:Finding the ENERGY PIGS!
Identify the Immediate Impact on Facility O&M Budget The FIRST Step in the Retro-Commissioning Process!
http://www.google.com/imgres?imgurl=http://twincitiesrealestate.housingstorm.com/files/2010/09/home-energy-audit.jpg&imgrefurl=http://twincitiesrealestate.housingstorm.com/2010/09/energy-audits-%E2%80%93-the-costs-and-benefits/&usg=__GsJUW9tXCosjqQF_jMqJdvwTpFk=&h=237&w=255&sz=34&hl=en&start=5&zoom=1&itbs=1&tbnid=OLHA_rZ9x9WI5M:&tbnh=103&tbnw=111&prev=/images?q=energy+audit+benefits&hl=en&rls=com.microsoft:*&biw=1259&bih=842&tbm=isch&ei=ydghTtXRHo6tgQemstG-Cw -
8/9/2019 5 Commissioning
34/35
Audits vs. Retro-CommissioningSimilar but NOT the Same
Audits - Often Performed in Older Facilities Investigate what's there. Determine how it is performing. Determine
if it can be improved economically (Energy & Maintenance Savingsoffset capital investment ECMs / ECOs)
Product is an Implementation Document Similar to RCx Plan.
RCx Performed on Existing Buildings, relativelynew or old
Goal Make facility perform As Owner Intended. Ownerscontractor/ maintenance staff usually performs corrective action.
Product - Properly operating building, with documentation provingsame. Some investment might be necessary.
QUESTIONS?
http://www.jrdkirk.com/wp-content/uploads/2010/10/NotEqual.jpghttp://www.jrdkirk.com/wp-content/uploads/2010/10/NotEqual.jpg -
8/9/2019 5 Commissioning
35/35
QUESTIONS?