BULAN-C WELLHEAD PLATFORM Fabrication, Hook-up, and Commissioning 1 Fabrication, Hook-up, and Commissioning

Transcript of 4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14

BULAN-C WELLHEAD PLATFORMFabrication, Hook-up, and Commissioning

1

Fabrication, Hook-up, and Commissioning

PROJECT INFORMATIONPROJECT INFORMATION

BACKGROUND

General

• Contract No. 3000000580

• Provision of Fabrication, Offshore Transportation and Installation, and

Hook-up, and Commissioning Services for Bulan-C Wellhead Platform

Scope of Work

3

• Engineering, procurement, and construction

• Hook-up and commissioning of new BLC (4-legged, 15 slots)

• Riser Tie-in and SDV Installation at CKR

• Modification of existing CKP telecomm & control systems

• Purging and packing of new 24-inch subsea pipeline, BLC to CKR

BACKGROUND

Duration and Milestones : June 2013 to October 2014

• Contract award 07 - Jun - 2013

• Jacket MCD 12 - Jul – 2014

4

• Jacket Sail-away 08 - Aug – 2014

• Topsides MCD 13 - Aug – 2014

• Topsides Sail-away 22 - Aug – 2014

• Offshore MCD 25 - Oct - 2014

WORK LOCATIONS / FIELD MAP

5

CAKERAWALA FACILITIES

BLC

6

ORGANIZATION CHART

7

KEY DATES

Activity Description From To

1 Risk Assessment 6-Aug-14 -

2 IPOP/Flawless Workshop 7-Aug-14 -

3 Mobilize AWB from SIN to SKL 31-Aug-14 6-Sep-14

4 Pre-mob briefing for TNS Crew at BPK 6-Sep-14 6-Sep-14

5 Pre-mob briefing for Marine Crew at SKL 7-Sep-14 7-Sep-14

8

5 Pre-mob briefing for Marine Crew at SKL 7-Sep-14 7-Sep-14

6 D & A Test for all Personnel at SKL 7-Sep-14 7-Sep-14

7 Construction spread loading at SKL 7-Sep-14 8-Sep-14

8 Mobilize AWB to JDA 8-Sep-14 10-Sep-14

9 Meeting with OIM/OPNS 10-Sep-14 10-Sep-14

10 Anchor handling at BLC 10-Sep-14 12-Sep-14

KEY DATES

Activity Description From To

14 Brownfield - HUC work at CKP 15-Sep-14 29-Sep-14

15 Post HUC work & Platform hand-over 29-Sep-14 4-Oct-14

11 Gangway Installation 13-Sep-14 -

12 Greenfield - HUC work at BLC 14-Sep-14 4-Oct-14

13 Brownfield - HUC work at CKR 15-Sep-14 2-Oct-14

9

15 Post HUC work & Platform hand-over 29-Sep-14 4-Oct-14

16 Retrieve anchors and demobilize to SKL/Sin 5-Oct-14

GREENFIELD SCOPE OF WORKGREENFIELD SCOPE OF WORKBLC Hook-up and Commissioning

BLC HOOK-UP & COMMISSIONING

Structural

• Install shipped-loose section of downcomer pipes

• Re-instate of staircase at SDV Deck to Sea Deck

• Grind smooth 4 nos. lifting padeyes @ main deck

• Blasting & painting works (carry over from T &I)

Mechanical / Piping

• Tie-in riser of new 24-inch BLC to CKR pipeline

11

• Install new 24-inch riser valve

• Hook-up shipped-loose piping at Cellar Deck, at and below Pump

Access Deck, and Boat Landing (approx. 53 joints)

• Install and commission Open Drain Pump at Sea Deck

• Install remaining fire & safety equipment

• System reinstatement leak testing (10 test packs)

• Commission utility systems

• Pipeline purging and nitrogen packing/preservation

BLC HOOK-UP & COMMISSIONING

Electrical

• Install solar arrays at Main Deck

• Install 5 nos. lighting fixtures at Sea Deck

• Re-instate 4 nos. Flood light & 2 no. Emergency light remove due to

obstruction during jacket transportation

• Commission power generation, small power & lighting systems

Instrument

12

• Install telecomm antenna and associated accessories

• Tie-in fusible plug and ESD system devices

• Commission control and shutdown systems including helideck lighting

• Establish voice/data communication with CKP

BROWNFIELD SCOPE OF WORKBROWNFIELD SCOPE OF WORKCKR Riser Tie-In

Riser Tie-in at CKR (SIMOPS mode)

Structural

• To complete installation of ESDV Access Platform

• Install handrails and gratings

Mechanical / Piping

• Install 24” topside spool at CKR Cellar Deck

• Install 24” topside riser of pipeline from BLC

• Install shutdown valve XV -0908

14

• Install shutdown valve XV -0908

• Re-instatement test of 24” bend spool after hydrotesting

• N2 service leak testing of 24” topside piping

Instrument

• Install tubing & terminate control cable for XV -0908

• Install and commission Gas Detector GDT / GDR -9706A

• Testing of XV -0908

BROWNFIELD SCOPE OF WORKModification of CKP TelecommunicationModification of CKP Telecommunication

and Control Systems

CKP COMM/CONTROL SYS MODIFICATION

Telecommunication

• Install telecom antenna CKQ – ANT - 9027

• Upgrade existing telecommunication system

• Cabling works including new MCT installation

• Establish voice/data communication between CKP and BLC

Control / Shutdown / Monitoring Systems

• Upgrade DCS (distributed control system)

16

• Upgrade DCS (distributed control system)

• Upgrade SDS (shutdown system)

• Upgrade WGFM (wet gas flow metering system)

• Upgrade SDM (sand detection & monitoring system)

Electrical

• Install wireless broadband indoor unit & switch device server for BLC at

Communication Room

• Install gateway and CCTV decoder for BLC at Control Room

SCHEDULE OF WORKSSCHEDULE OF WORKS

OVERALL SCHEDULE

18

BLC HUC SCHEDULE

19

CKR BROWNFIELD SCHEDULE

20

CKP & CKQ SYSTEM MODIFICATION SCHEDULE

21

MANPOWER OVERALL LOADING

22

Overall 252 pax

MANPOWER DIRECT LOADING

23

Overall 91 pax

MANHOUR ESTIMATE

Manning Levels Per Platform

• BLC - 75 men working day shift

• CKR - 45 men day shift

• CKP - 10 men working day shift

Estimated Man-Hours

• CARIGALI HESS : 3,780

24

• CARIGALI HESS : 3,780

• TNS Indirect : 14,040

• TNS Direct : 32,760

• Vendor reps & specialist services : 4,620

• Marine crew & catering : 30,240

• Total estimated man-hours : 85,440

WORKS EXECUTION STRATEGYWORKS EXECUTION STRATEGY

WORKS EXECUTION STRATEGY

Personnel Accommodation and Movement

• AWB moored at BLC

• Daily crews inter-rig to CKR and CKP via dedicated Crew Boat

• CKP - 10 men working

• CKR - 45 men working

26

• 5 Pax Package Vendors (Instrument & Controls) accomodated at CKQ

CKR Hot Work

• SIMOPS hot work inside safe house habitat SHH’s

• 2 hot work location at any given time

WORKS EXECUTION STRATEGY

Material Handling @ BLC

• BLC Platform crane for materials from BLC Main Deck to Cellar Deck

Lay Down Area

• BLC Platform crane to lift gangway during installation

• Piping and Structural materials will be transferred from Cellar Deck lay

down area to final position by manual handling

Material Handling @ CKR

27

Material Handling @ CKR

• CKR Platform crane for materials & equipment from AHTS to CKR

Cellar Deck lay down area.

• Piping and Structural materials will be transferred from lay down area to

final position by manual handling using lifting aids

• All lifting equipment and gears shall comply with LMS Rev. 2

requirements (6 weeks Schedule and cost impact if to comply with LMS

Rev.3)

WORKS EXECUTION STRATEGY

MAJOR INSTALLATION WORKS FOR EXECUTIONMAJOR INSTALLATION WORKS FOR EXECUTION

� Gangway Installation at BLC (Post IPOP : AWB on heading

to SW)

� Shutdown Valve & Actuator Installation @ BLC Deck

� 24” Pipe Spool Installation@ CKR Cellar Deck

28

� Shutdown Valve & Actuator Installation at CKR SDV Deck

MARINE SPREADMARINE SPREAD

ACCOMODATION WORK BARGE

AWB Swiber Victorious

• 300-men capacity

• 8-point mooring system

• 1,200 m2 clear deck space

• 300 MT SWL crane at 11m

radius

• crane limited to 1.5m swell, 20

30

• crane limited to 1.5m swell, 20

knot winds, 2o roll

• gangway limited to 1.5m swell,

20 knot winds

• 2,043 m3 fuel storage, 544 days

at 80%

• 2 x 50 MT water making capacity

• Helideck for Sikorsky 71

SUPPORT VESSELS

AHT/S VOS Hyperion

• 5,150 BHP main engines

• 67 MT bollard pull

• 13 knots maximum speed

• built in 2010

• anchor handling & supply runs

31

AHT No. 2 Swissco Sapphire

• 5,150 BHP main engines

• 60 MT bollard pull

• 12 knots maximum speed

• built in 2007

• anchor handling & towing

SUPPORT VESSELS

Crew Boat TMS 7

• 3 x 1.350HP main engines

• 23 knots max/cruising speed

• 90 passengers

• 67 m2 clear deck space, 2MT/m2 deck

loading

32

loading

• built in 2010

ANCHOR PATTERNS

33

ANCHOR PATTERNS

34

BLC PIPING: Utility Piping

35

BLC PIPING: Pipeline Riser Spools

36

BLC PIPING: Utility Piping

37

BLC PIPING: Utility Piping

38

BLC PIPING: Utility Piping

39

Install solar arrays at Main Deck

Install solar arrays at Main Deck

40

Install solar arrays at Main Deck

41

Install lighting fixtures at Sea Deck

42

Install lighting fixtures

43

Install telecomm antenna and associated accessories

Telecomm antenna and associated accessories

44

Tie-in fusible plug and ESD system devices

45

Modify ESDV Access Platform

46

GANGWAY INSTALLATION @ BLC

47

GANGWAY INSTALLATION @ BLC

91

GANGWAY INSTALLATION @ BLC

92

GANGWAY INSTALLATION @ BLC

50

GANGWAY INSTALLATION @ BLC

51

SDV & Actuator Installation @ BLC

52

SDV & Actuator Installation @ BLC

53

SDV & Actuator Installation @ BLC

54

SDV & Actuator Installation @ BLC

55

CKP – Telecoms Upgrade

56

CKP – Telecoms Upgrade

57

CKP – Telecoms Upgrade

58

CKP – Telecoms Upgrade

59

New MCT Location at TER

CKP DCS & SDS Upgrade

60

CKP DCS & SDS Upgrade

61

CKP DCS & SDS Upgrade

62

CKP DCS & SDS Upgrade

63

CKP DCS & SDS Upgrade

64

CKP DCS & SDS Upgrade

65

CKP DCS & SDS Upgrade

66

24” Pipe Spool Handling Method @ CKR

67

24” Pipe Spool Handling Method @ CKR

68

24” Pipe Spool Handling Method @ CKR

69

STEP 3

24” Pipe Spool Handling Method @ CKR

70

24” Pipe Spool Handling Method @ CKR

71

24” Pipe Spool Handling Method @ CKR

72

24” Pipe Spool Handling Method @ CKR

73

24” Pipe Spool Handling Method @ CKR

74

24” Pipe Spool Handling Method @ CKR

75

24” Pipe Spool Handling Method @ CKR

76

SDV / Actuator Handling Method @ CKR

77

SDV / Actuator Handling Method @ CKR

78

SDV / Actuator Handling Method @ CKR

79

SDV / Actuator Handling Method @ CKR

80

SDV / Actuator Handling Method @ CKR

81

SDV / Actuator Handling Method @ CKR

82

SDV / Actuator Handling Method @ CKR

83

SDV / Actuator Handling Method @ CKR

84

SDV / Actuator Handling Method @ CKR

85

SDV / Actuator Handling Method @ CKR

86

SDV / Actuator Handling Method @ CKR

87

SDV / Actuator Handling Method @ CKR

88

SDV / Actuator Handling Method @ CKR

89

SDV / Actuator Handling Method @ CKR

90

Install shipped-loose section of downcomer pipes

Downcomer pipes

91

Re-instate staircase at SDV Deck to Sea Deck

Staircase at SDV Deck to Sea Deck

92

Lowering of staircase at SDV Deck to Sea Deck

Staircase at SDV Deck to Sea Deck

93

BLC PIPING: Utility Piping

94

BLC PIPING: Pipeline Riser Spools

95

BLC PIPING: Utility Piping

96

CKR Riser Tie-in & SDV Installation Scope

97