48434-003: Visakhapatnam-Chennai Industrial Corridor ...

149
Semi-Annual Environmental Monitoring Report Project number: 48434-003 Period: July - December 2018 Submission Date: March 2019 IND: Vishakhapatnam Chennai Industrial Corridor Development Program Project 1 This report was prepared by Project Management Unit of Visakhapatnam Chennai Industrial Corridor for the Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Transcript of 48434-003: Visakhapatnam-Chennai Industrial Corridor ...

Semi-Annual Environmental Monitoring Report

Project number: 48434-003

Period: July - December 2018

Submission Date: March 2019

IND: Vishakhapatnam Chennai Industrial Corridor Development Program – Project 1

This report was prepared by Project Management Unit of Visakhapatnam Chennai Industrial Corridor for the Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Semi-annual Environmental Monitoring Report Project Number 48434 July-December 2018

India: Visakhapatnam - Chennai Industrial Corridor (July-December 2018) – Tranche - 1

Prepared by the Project Management Unit of Visakhapatnam-Chennai Industrial

Corridor for the Asian Development Bank.

Contents ABBREVIATIONS 4

1 Introduction 6

2 Project Description and Objectiies 6

3 Eniironmental category as per ADB Safeguard Policy Statement, 2009 7

4 Eniironmental category of each subproject as per national laws and

regulations 7

5 Project Safeguards Team 8

6 Implementaiton progress 8

7 Oierall project and sub-project implemetnation progress 9

8 Compliance Status with NationallStatelLocal Statutory Eniironmental Requirements 12

9 Compliance Status with Eniironmental Loan Coienants 13

10 Legislatiie Framewor6 15

11 Application of eniironmental legislation and its permissions 17

12 Compliance Status with Site Specifc Eniironmental Management Plan 22

13 Summary of Eniironmental Monitoring Actiiities 26

14 Conclusion and Recommendation 74

Appendices 75

A. Copy of Eniironmental Clearance of Industrial Par6 at Atiaram 76

B. Eniironmental Clearance of MPSEZ 85

C. Public Consultation 111

1 Public Communication Actiiities 111

1.1 Actiiities in October month 2018 111 1.1.1 Awareness programme on wor6site safety 111 1.1.2 Meeting with women group members 112 1.1.3 Interaction with Students on Road Safety 113

D. Appendix – Eniironmental Monitoring Results 115

ABBREVIATIONS

ADB - Asia Developme t Ba k AMTZ - A dnhra Pradnesh Mednitech Zo e APIIC - A dnhra Pradnesh I dnustrial I frastructure Corporato APRDC -- A dnhra Pradnesh Roadn Developme t Corporato AP-TRANSCO -- Tra smissio Corporato of A dnhra Pradnesh -- Limitedn APSEB A dnhra Pradnesh State Electricity Boardn -- BGL - Below Grou dn Level

BOD - Biological Oxyge Dema dn BIS - Bureau of I dnia Sta dnardn CPCB - Ce tral Polluto Co trol Boardn DO - Dissolvedn Oxyge DoE - Departme t of E viro me t DISCOM - Distributo Compa y

PMC - Project Ma ageme t Co sulta t EA - Execut g Age cy EIA - E viro me tal Impact Assessme t EMP - E viro me tal Ma ageme t Pla EMoP - E viro me tal Mo itori g Pla ESO - E viro me tal a dn Safety Ofcer GoAP - Gover me t of A dnhra Pradnesh

GoI - Gover me t of I dnia

GVMC - Greater Vishakhapat am Mu icipal Corporato

IEE - I ital E viro me tal Exami ato IMD - I dnia Meteorological Departme t IS - I dnia Sta dnardn MFF - Mult Tra che Fi a cial Facility MoEF - Mi istry of E viro me t a dn Forests MSL - Mea Sea Level MW - Mega Watt NSDP - Net State Domestc Prodnuct NGO - No - Gover me t Orga izato NH - Nato al Highway NOx - Oxidnes of Nitroge PMSC - Project Ma ageme t a dn Supervisio Co sulta t RF - Reserve Forest ROW - Right of Way SO - Safeguardns Ofcer SPCB - State Polluto Co trol Boardn

SPM - Suspe dnedn Partculate Matter

SO2 - Sulphur Dioxidne

SSI - Small Scale I dnustries

SPCB - State Polluto Co trol Boardn

TA - Tech ical Assista ce

TDS - Total Dissolvedn Solidns

TSS - Total Suspe dnedn Solidn

1 Introduction 1. The project-1 under the Vishakhapatnam – Chennai Industrial corridor has been

initiated under the ADB guidelines.

2 Project Description and Objectives 2. The proposed Visakhapatnam–Chennai Industrial Corridor Development Program

(VCICDP) will complement the ongoing efforts of the Government of Andhra Pradesh

(GoAP) to enhance industrial growth and create high-quality jobs. The VCICDP

comprises: (i) a proposed Multi-Tranche financing facility (MFF), (ii) a proposed policy-

based loan (PBL), and (iii) a proposed administration of a grant to be provided by the

Urban Climate Change Resilience Trust Fund2 (UCCRTF) under the Urban Financing

Partnership Facility. The VCICDP will support policy reforms and institutional

development in the state; and priority infrastructure investments in the Visakhapatnam–

Chennai Industrial Corridor (VCIC).

Impact, outcome and outputs 3. The impact of the VCICDP will be an increased contribution of the manufacturing

sector to the state’s GDP, trade, and employment. The outcome will be enhanced

growth and competitiveness of the VCIC. The VCICDP will have three outputs as

follows. The PBL will support output 1, and the MFF and the Grant will support outputs

2 and 3.

Output 1: Corridor management strengthened and ease of doing business improved.

Output 2: Visakhapatnam–Chennai Industrial Corridor infrastructure strengthened and

more resilient. This will include the development of (i) internal roads, water supply,

drainage, logistics, and industrial effluent treatment in selected industrial clusters; (ii)

roads for connectivity between industrial nodes, ports, and urban areas, and road

safety measures; (iii) power transmission and distribution system in the industrial

corridor; and (iv) smart cities planning with climate change resilience and continuous

water supply in Visakhapatnam.

Output 3: Institutional capacities, human resources, and program management

strengthened.

4. The VCIC is proposed as a node centric development platform with four nodes: (i) Visakhapatnam node, (ii) Kakinada node, (iii) Amaravati region node, and (iv)

Yerpedu–Srikalahasti node. Some of the critical industrial sectors shortlisted for

achieving the targeted outcomes are textiles, food processing, metallurgy, chemicals

and petrochemicals, electronics, pharmaceuticals, and automobiles. In the future, it is

expected to have sectors such as medical equipment, plastics, organic chemicals,

aerospace, and information technology or information technology-enabled services.

The VCIC is well poised to connect to global production networks of southeast and east

Asia.

5. APIIC has prioritized two nodes, Visakhapatnam and Yerpedu–Srikalahasti, for

initial investments.

3 Environmental category as per ADB Safeguard Policy Statement, 2009 6. ADB requires the consideration of environmental issues in all aspects of ADB’s

operations, and the requirements for environmental assessment are described in ADB

SPS, 2009. This states that ADB requires environmental assessment of all ADB

investments.

4 Environmental category of each subproject as per national laws and regulations

7. The nature of the environmental assessment required for a project depends on the

significance of its environmental impacts, which are related to the type and location of

the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and

the availability of cost-effective mitigation measures. Projects are screened for their

expected environmental impacts, and are assigned to one of the following four

categories:

Category A 8. A proposed project is classified as category A if it is likely to have significant adverse

environmental impacts that are irreversible, diverse, or unprecedented. These

impacts may affect an area larger than the sites or facilities subject to physical works.

An environmental impact assessment is required.

Category B. 9. A proposed project is classified as category B if its potential adverse environmental

impacts are less adverse than those of category A projects. These impacts are site-

specific, few if any of them are irreversible, and in most cases mitigation measures can

be designed more readily than for category A projects. An initial environmental

examination is required.

Category C 10. A proposed project is classified as category C if it is likely to have minimal or no

adverse environmental impacts. No environmental assessment is required although

environmental implications need to be reviewed.

Category FI 11. A proposed project is classified as category FI if it involves investment of ADB

funds to or through a FI

12. The Project-1 under the VICICDP is categorized as Category B.

5 Project Safeguards Team Table 1: Project Safeguards Team

PIU/PMU

Designation Name of Contact Details

Officer

PMU - VCICDP Environmental Recruitment in

Safeguards officer process

APIIC Environmental Officer Mr. Suresh Babu [email protected]

Naidupeta +917075920060

Environmental Officer Mr. Kompala Ravi [email protected]

Visakhapatnam +919705428890

APRDC Environmental Ms. V. Sowjanya [email protected]

Safeguards Officer +918008887713

APTRANSCO Environmental Mr. B. +91-8332983756

Safeguards Officer Purushotham GVMC Dy. Executive Mr. B. Maheswar +91-9912255228 Engineer, Environmental & Social Safeguards

Officer Source: PMU Email

6

7

Implementation progress Overall project and sub-project implemetnation progress

13. Description of subprojects (package-wise) and status of implementation

(preliminary, detailed design, on-going construction, completed, and/or O&M stage).

Table 2: Subprojects (package-wise) and status of implementation

Package Components/ Status of Contrac If On-going

Number List of Works Implementat t Status Construction

ion

%Financ Expected

ial Completi

Progres on Date

s

APIIC

VCICDP- Construction of Contracted M/s 1.06% 30.06.201

APIIC/01 1MLD Common awarded on Ramky 9

Effluent 27 June 2018 Enviro

Treatment Engineer

(CETP) plant at s Limited

Naidupeta Agreeme

Industrial nt

cluster Executed

.

27.06.18

VCICDP- Augmenting Contracted M/s SRR 37.95% 31.03.2019

APIIC/03 utility services for awarded on 30 Projects

Naidupeta June 2018

Industrial cluster.

[SWD, power,

internal road and

one stop Centre.

VCICDP- Providing 21 Contracted Awarded 33.24% 31.03.2019

APIIC/04 MLD bulk water awarded 05 Mobilizatio

facility and March 2018 n

summer storage Advance:

in Naidupeta Rs.7.40Cr

Industrial cluster. s.

APRDC VCICDP- Upgrading & Contracted Contract 1% 12.02.2021 APRDC/01 Rehabilitation of awarded on 13 awarded

‘Samarlkota to August 2018 Rajanagaram’ Section of ‘Kakinada – Rajanagaram’ Road to ‘2 Lane Dual Carriageway

Standard’ VCICDP- Greenfield NA IFB: NA APRDC/04 approach road to Preparation of 30.07.201

Nakapalli Cluster DPR 8 VCICDP- Widening of road NA IFB: NA NA APRDC/05 (single lane to 2 Preparation of 30.07.201

lane) from DPR 8 Neleballi to Routhusuramala and formation of new two-lane road from Srikalahasti Yerpedu (south block to Pallamala on Kalahasti Tada

Road ) VCICDP- Widening of road NA IFB: NA NA APRDC/06 (single lane to 2 Preparation of 30.07.201

lane) from DPR 8 Thimmaji Kandriga to NH-5 (AH-45) near Pandlur Railway gate for 6.1Km length (without

RoB) GVMC

VCICDP- Distribution Work in Awarded 13.7% 31.12.2019 GVMC/02 Network progress on 14 Mobilizatio

improvements for March 2018 n

NRW reduction Advance: and 24x7 supply Rs.33.67C

in GVMC area rs.

VCICDP- Water shed Final DPR and IFB 0% UCCRTF/04 development and Bid Document prepared

Rejuvenation of submitted to as per

Mudasarlova ADB ADB lake. 23.05.2018 guidelines submitted to ADB on 14.06.201

8 VCICDP- Developing a Bids were 0% UCCRTF/05 3MW Solar opened on

Energy Park at 05.04.201 Mudasarlova/ 8.

Meghadri Gedda 13 proposals were received. Replies to comments on Technical Evaluation report submitted

to ADB VCICDP- Converting 3 Revised IFB 0% UCCRTF/06 streets into non- concept note, prepared

vehicular zone RFP and Cost as per Estimates were ADB submitted to guidelines ADB on submitted 14.06.2018 to ADB on 14.06.201

8

APTRANCO

VCICDP- Augmenting Contract Awarded 4.24% 31.12.2019 APTransco/0 power Awarded on 5 on 1 distribution June 2018 05.06.201

capacity for 8 meeting Industry demand at Kapuleppada, Ozone Valley, Nakkapalle/ Chandanada and Achutapuram

locations. VCICDP- Augmenting Contract Awarded. 3.82% 31.12.201 APTransco/0 power Awarded on Mobilizati 9 3 distribution 27 February on

capacity for 2018 Advance: meeting Rs.9.69C Industry rs. demand at Rachagunneri, Naidupeta and Yerpedu

locations. Source: Mo thly Progress Report

8 Compliance Status with National/State/Local Statutory Environmental Requirements

Table 3: Compliance Status of legislative requirements

Package Subproje Statutor Status Validity Actio Specific

No. ct Name y of if n Conditions

Environ Compl obtaine Requi that will

mental iance d red require

Require c environmenta

ments l monitoring

as per

Environment

Clearance,

Consent/Per

mit to

Establish d

VCICDP/API Constructi Environm Complie Valid No

IC/01 on of ental d (one-time action

CETP at Clearance clearance) Compliance

Naidupeta

report attached

Consent Complie Valid for No in annexure

to d period of action

Establish 7 years

and from the

approval date of

of SPCB issue

VCICDP/API Augment Environm Complie Valid No

IC/03 ation of ental d (one-time action

Utilities Clearance clearance) actin Compliance

report attached

Consent Complie Valid for No in annexure

to d period of action

Establish 7 years actin

from the

date of

issue

VCICDP/API Bulk water Environm Complie Valid No

IC/04 supply and ental d (one-time action

summer Clearance clearance) actin Compliance

storage

report attached

Consent Complie Valid for No in annexure

to d period of action

Establish 7 years actin

from the

date of

issue

Source: Copy of E viro me tal Cleara ce a dn CFE

9 Compliance Status with Environmental Loan Covenants

Table 4: Loan Covenancts

No. (List Covenant Status of Compliance schedule and

paragraph number of Loan

Agreement) Environment Schedule 5 of Loan Agreement

6 The Borrower shall ensure, or cause, the EA to ensure, that the preparation, design, construction, implementation, operation, and decommissioning of project facilities comply with (i) All applicable laws and regulation of borrower and the state relating to environment, health and safety (ii) The ADB’s Environmental safeguards; and (iii) All measures and requirement set forth in EARF , the IEEs and respective EMP and any corrective and preventive actions set forth in the safeguards monitoring report

Complied The applicable laws and regulations of Government of India, Government of Andhra Pradesh and local regulation have been reviewed and incorporated in the IEE and DDR. The IEE and its EMP have been prepared based on ADB’s Safeguards Policy Statement, 2009, All measures set forth in the EARF and IEEs have been included in the contract of the works and awareness training and workshops have been organized for the compliance. Regular monitoring mechanism has been established as per the EARF and IEE.

Human and Financial Resources to Implement Safeguards Requirements

9a

9b

10

The Borrower shall make Complied

available, or cause the EA to Budgetary provision has been made in

make available, all necessary the respective IEE and EMP.

budgetary and human

resources to fully implement the

EMP required.

The EA shall designate at least Complied

one expert each to supervision An environmental officer has been

implementation of the EMPs designated in each PIU for

and RPs, if any supervision of implementation

environmental safeguards measures

in each package. PMSC

environmental specialist is also

responsible providing all support to

contractor and PIU to implement the

environmental safeguards measures

The Borrower shall ensure, or Complied

cause the EA to ensure, that all The IEEs and its EMPs have been

bidding documents, and made part of the contract and it has

contracts for works contain been suitably referred in the

provision that require contractor conditions of the contract.

to : The IEE includes environmental

a. Comply with measure and

management and monitoring budget.

requirement relevant to

contractor set forth in the

IEEs , the respective EMPs,

and the respective RPs, in

particular no demolishing or

relocating private assets

before ensuring asset owner

has received compensation

and resettlement assistance

and any corrective and

preventive actions set out in

Safeguards Monitoring

Report

b. Make available budget for all

such environmental and

social measures;

c. Provide EA with written

notice of any unanticipated

environmental resettlement

or indigenous people risks if

any , or impacts that arise

during construction ,

implementation or operation

of the Project that were not

considered in the respective

IEE , the respective EMP,

and the respective RP.

d. Adequately record the

condition of roads,

agricultural land and other

infrastructure prior to starting

to transport materials and

constructions; and

e. Fully reinstate pathways,

other local infrastructure, and

agricultural land to atleast

their pre-project condition

upon the completion of

construction.

11 The Borrower shall do, or cause Complied

the EA to do the following: The semiannual safeguards

a. Submit semi-annual

monitoring report is being prepared

safeguards monitoring report

and submitted on time.

to ADB and disclosure

relevant information from

such report to affected

person promptly upon

submission ;

b. If any unanticipated

environmental and or social

risks and impacts arise due

to construction, implementation or operation of the project that were not considered in the respective IEE, the respective EMP and the respective RP, promptly form ADB of occurrence of such risks or impacts, with detailed description of the event and propose corrective action plan;

c. No later than award of related works contract , engage qualified experienced external expert(s) under the selection process and terms of reference acceptable to ADB, to verify information produced through the project monitoring process, and facilitate the carrying out of any verification activities by such external expert; and

d. Report any breach of compliance with the measures and requirements set forth in the respective EMP and the respective RP, promptly after aware of the breach.

10 Legislative Framework

Table 5: List of Legislative Requirements

S. No.

Legal Requirements/ Compliance

Environmental Regulations

1 The Environment EIA Notification 2009 and CRZ Notification 2011 require

(Protection) Act, 1986 clearance under this notification condition to its

(amended in 1991) application.

2 The Environment

(Protection) Rules, 1986 3 The Air (Prevention This deals with emission of pollutants defined in Air Act,

&Control of Pollution) 1981 and Environmental Protection Act 1986. Air Act Act,1981 1981 mandates to obtain Consent to Establish and Consent to Operate for the industries defined under this ACT by the State Pollution Control Board.

4 The Water (Prevention & This deals with discharge of pollutants defined in Water Control of Pollution) Act, Act, 1974 and Environmental Protection Act 1986. Water

1974 Act 1981 mandates to obtain Consent to Establish and Consent to Operate for the industries defined under this ACT by the State Pollution Control Board.

5 The Noise Pollution The Noise Pollution Rule 2000 regulates noise generation (Regulation & Control) from various activities and project. Rules, 2000

7 The Pesticides The Pesticides Management Act, 2008 regulates the use Management Act, 2008 of pesticides in the plantation and various activities.

8 The Forest Forest Conservation Act has been enacted for (Conservation) Act, 1980 conservation of forest and it mandates permission and (amended in 1988) clearance in case Forest Conservation Act is intervened.

9 Hazardous and Other The Hazardous and Other Waste Rules, 2016 regulates Waste (Management and the use, transport, handling, storage and disposal of Transboundary hazardous material. It mandates permission and Movement) Rules, 2016 authorisation from pollution control Board in case this rule is applicable.

10 Solid Waste Management Solid Waste management Rule regulates the disposal and Rules, 2015 treatment of solid waste.

Social Aspect 1 The Bonded Labour The child labour and bonded labour is prohibited through

System (Abolition) Act, this Act. 1976

2 The Child Labour

(Prohibition and

Regulation) Act, 1986

3 The Minimum Wages Act, The Minimum Wages Act regulates and mandates 1948 and rules made minimum wages defined by the state government to be thereunder implemented.

4 The Contract Labour The facilities like canteen, rest room, first aid facilities, (Regulation and Abolition) payment of wages and other amenities have to be Act, 1970 provided under this Act.

5 The Workmen’s All contractors have to be comply the Workmen Compensation Act, 1923 Compensation Act 1923.

6 The Equal Remuneration The Equal Remuneration Rules, 1976 prevent any Rules, 1976 discrimination in payment among women and men employees.

8 The Maternity Benefits Maternity benefits have been defined under this Act and Act, 1961 requires to be complied.

9 The Trade Union Act, For the common facilities and bargain for labour are 1926 provided in in this act.

10 The Employees Provident For the welfare and future security of the employees this Funds and Miscellaneous act has been formulated Provisions Act, 1952

11 The Sexual Harassment This Act controls the sexual harassment at work place. of Women at Workplace (Prevention, Prohibition

and Redressal) Act, 2013 Source: <I sert Notes or Source>

11 Application of environmental legislation and its permissions

The e viro me tal permissio s or o-objecto or lice ces requiredn u dner gover me t of I dnia a dn gover me t of A dnhra Pradnesh are explai edn below. The

permissio a dn are dnef edn i two categories amely

Coneiton preceeence – the co dnito precedne ce makes it ma dnatory to acquire the permissio or lice se or o-objecto s

Coneiton occurrence – the co dnito occurre ce makes the it ma dnatory to acquire whe the co dnito requires to acquire the certfcate or it is ma dnatory for the

partcular actvity

Sub-project No No Sub-project No No Sub-project No No

APIIC/01 1 APRDC/05 6 UCCRTF/01 11

APIIC/03 2 APRDC/06 7 APTRANSCO/01 12

APIIC/04 3 GVMC/02 8 APTra sco/03 13

APRDC/01 4 UCCRTF/01 9

APRDC/04 5 UCCRTF/01 10

No.

Legislation

Requirements for the Project

Applicability 1

2 3 4 5 6 7 8 9 1 1 1

1

0 1 2 3

1 National Environment Policy Project should adhere to the NEP The policy governing the √ √ √ √ √ √ √ √ √ √ √ √ √

(NEP), 2006 principle of: enhancing and environmental rules and

conservation of environmental legislations and is

resources and abatement of applicable to all the

pollution subprojects.

2 EIA Notification, 2006 Environmental clearances (EC) The Industrial Parks

mentioned earlier in

Naidupet Industrial zone

have been granted

Environmental

Clearance by the MoEF

3 Water (Prevention and ● Consent for establishment (CFE) Applicability of Law √ √ √ √ √ √ √ √ √ √ √ √ √

Control of Pollution) Act, and consent for operation (CFO)

Error! No text of specifee sttye in eocument.BS1192Error! No text of specifee sttye in eocument.384028384028Error! No text of specifee sttye in eocument.0101Error! No text of specifee sttye in eocument.00Error! No text of

specifee sttye in eocument.3 September 20183 September 2018 Error! No text of specifee sttye in eocument.Docume t1

1974 amended 1988 and its from APPCB CFE

Rules, 1975 ● Compliance to conditions and

CFO

disposal standards stipulated in

the CFE and CFO

4 Air (Prevention and Control CFE and CFO from APPCB Applicability of Law

of Pollution) Act, 1981, as applicable Compliance to

amended 1987 and its conditions and emissions standards

CFE

Rules, 1982 stipulated in the CFE and CFO.

CFE and CFO: (i) diesel generators; CFO

(ii) hot mix plants; and (iii) vehicles

emitting air pollutants.

5 Environmental (Protection) Solid waste and sludge generated As Applicable to √ √ √ √ √ √ √ √ √ √ √ √ √

Act, 1986 amended 1991 at proposed facilities shall be proposed subproject

and the following disposed in accordance with the components.

rules/notifications: MSWM Rules.

Environment ● Compliance with noise standards

(Protection) Rules, 1986 ● Compliance to environmental

including amendments

standards (discharge of effluents)

● Municipal Solid Wastes

● Restriction of activities (including

(Management and

construction, tree cutting, etc.) in

Handling) Rules, 2000

the notified zones. There are no

● Noise Pollution eco sensitive zones in or near the

(Regulation and Control) subproject locations.

Rules, 2000 ● Applies to protected wetlands

● Environmental Standards (Ramsar sites, wetlands in eco

of sensitive areas and UNESCO

Central Pollution Control heritage sites & in high altitudes,

Board (CPCB) and wetlands notified by

Government of India) - Prohibits/

● Notification of Eco

regulates activities within and

Sensitive Zones

near the wetlands. None of the

● Wetland (Conservation

subproject locations has

and Management) Rules, protected wetlands.

2010 ● Rules defines and classifies

● Hazardous Waste hazardous waste provides

(Management, Handling procedures for handling

and hazardous waste.

Transboundary Movement) ● Requires Pollution Control

Rules, 2009 Board’s consent for handling

hazardous waste.

Procedure for storage of Hazardous

wastes and provides procedures for

recycling, reprocessing or reuse,

important and export of hazardous

waste.

6 Contract Labour ● Department of Labour, GoAP as ● Applicable to all √ √ √ √ √ √ √ √ √ √ √ √ √

(Regulation and principle employer. construction/civil

Abolition) Act, 1970; ● Contractor shall register with works.

● The Inter-State Migrant Labour Department, GoAP if ● APIICs to obtain

Workmen (Regulation of inter-state migrant workmen are Certificate of

Employment and engaged. Registration.

● Conditions of Service) ● Adequate and appropriate ● Contractors to obtain

Act, 1979 amenities and facilities shall be license from

provided to workers including designated labour officer

housing, medical aid, travelling

expenses from home and back,

etc.,

7 The Building and Other ● Cess should be paid at rate not Applicable to any √ √ √ √ √ √ √ √ √ √ √ √ √

Construction Workers exceeding 2% of the cost building or other

(Regulation of Employment of construction as may be notified construction work and

and Conditions of ● The employer is required to employ 10 or more

Service) Act, 1996 and the workers

provide safety measures at the

Cess building or construction work and

Act of 1996 other welfare measures, such as

canteens, first-aid facilities,

ambulance, housing

accommodation for workers near

the workplace etc.

● The employer has to obtain a

registration certificate from the

Registering Officer.

8 The Child Labour No child below 14 years No child below 14 years √ √ √ √ √ √ √ √ √ √ √ √ √

(Prohibition and Regulation) of age will be employed or of age will be employed

Act, 1986 permitted to work in all the or permitted to work in

subprojects. all the subprojects.

9 Minimum Wages Act, 1948 All construction workers Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

should be paid not less than the

prescribed minimum wage

10 Workmen Compensation Compensation for workers in Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

Act, 1923 case of injury by accident

11 Equal Remuneration Act, Equal wages for work of Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

1979 equal nature to male and female

workers

12 AP State Environment ● Follows the National Environment Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

Policy Policy, 2006

● Project implementation should

adhere to the policy aims

13 The Motor Vehicles Act, Standards for vehicular pollution Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

1988 and prevention control. The

Pollution under control √ √ √ √ √ √ √ √ √ √ √ √ √

authority also checks emission

certificate

standards of Registered vehicles,

collects road taxes, and issues

licenses.

● In August 1997, the Pollution

under Control Certificate

(PUC) program was launched in an

attempt to crackdown on the

vehicular emissions in the States.

All the vehicles that will be used in

construction of the subprojects will

have to comply with the PUC norms

set down under this act.

14 Coastal Regulation Zone The main objectives of the Coastal Naidupeta Industrial

(CRZ) Regulation Zone Estate does not attract

Notification 6th January Notification, 2011 are: requirements under CRZ

2011 to ensure livelihood security to the

Central fishing communities and other local

Government have declared communities living in the coastal

the coastal stretches of areas;

seas, bays, estuaries, to conserve and protect coastal

creeks, rivers and back stretches and;

waters which are influenced to promote development in a

by tidal action (in the

sustainable manner based on

landward side) up to 500m

Scientific principles, taking into

from the High Tide Line

account the dangers of natural

(HTL) and the land between

hazards in the coastal areas and

the Low Tide Line (LTL) &

sea level rise due to global

High Tide Line (HTL) as

warming.

“Coastal Regulation Zone”

(CRZ), as per the provisions

of the CRZ Notification 6th

January 2011.

15 Minor Mineral and For opening new quarries. Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

concession Rules Regulate use of minor minerals like

stone, soil, river sand etc.

16 The Mining Act (1952) The mining act has been notified for Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

safe and sound mining activity.

The construction of road

subprojects will require aggregates.

These will be procured through

mining from

riverbeds and quarries

17 Notification for use of fly The MoEF had issued in 2009 a Applicable

ash from thermal power notification that all brick units within

plants within 100km radius of thermal power .

100km reaches of the plants were required to use fly ash

project. for making bricks as well as using it

for construction activities like

building or roads.

18 Public Liability and Protection from Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

Insurance Act 1991 hazardous materials and

accident.

19 National Environment Grievances process and how they Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

Appellate Authority Act will be dealt with.

(NEAA) 1997

20 Explosive Act 1984 - For Safe transportation, storage and Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

transporting and storing use of explosive material.

diesel, bitumen etc.

21 The Factories Act, 1948 - The Act lays down the procedure Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

The Andhra Pradesh for approval of plans before setting

Factory Rules up a factory, health and safety

provisions, welfare provisions,

working hours and rendering

information-regarding accidents or

dangerous occurrences to

designated authorities.

22 Chemical Accidents The Rules provide for mandatory Applicable √ √ √ √ √ √ √ √ √ √ √ √ √

(Emergency Planning, preparation of On-Site Emergency

Preparedness and Plans by the industry and Off-Site

Response) Rules, 1996. Plans by the district collector and

the constitution of four tier crisis

groups at the center, district, and

local levels for the management of

chemical disaster.

23 Permission for extraction of Extraction of groundwater. Applicable to √ √ √ √ √ √ √ √ √ √ √ √ √

ground water for use in road rehabilitation and

construction activities from improvement of water

State Ground Water Board. supply. To be obtained

prior to initiation of any

work involving

abstraction of

groundwater

24 Permission for use of water

for construction purpose from irrigation department

Use of surface water Applicable. To be √ √ √ √ √ √ √ √ √ √ √ √ √ for obtained prior to

construction initiation of any work involving use of surface

water for construction

12 Compliance Status with Site Specific Environmental Management Plan

Table 6: Package-wise Status of IEEs

Package Components Design Final IEE based on Detailed Design Site- Remarks Number Status specific

EMP (Yes/No) Not yet due Submitted Disclosed on Final IEE (detailed to ADB project website provided design not yet (Provide (Provide Link) to completed) Date of Contractor Submission /s

) (Yes/No) VCICD/ Construction Construction Not yet due Draft IEEs No No Draft IEE APIIC/01 of 1MLD design to be as designed http://www.apiic.in/ is part of Common prepared not yet wp- the Effluent after site completed content/uploads/20 contract Treatment survey and 16/04/20160314_Dr (CETP) plant investigation aft-IEE-

at Naidupeta by the Naidupeta_Econom Industrial contractor. ic_Zone_Subproject

cluster _IEE_final.formatte d.pdf

VCICDP- Augmenting Designs are Yes Draft IEE It will be No IEE is part APIIC/03 utility services complete along http://www.apiic.in/w shared with of the for Naidupeta with progress contractor

Industrial of work p- after contract cluster. [SWD, content/uploads/201 approval power, internal 7/02/IEE-Naidupeta- road and one Cluster.pdf

stop Centre. VCICDP- Providing 21 Designs are Yes Draft IEE It will No IEE is part APIIC/04 MLD bulk water complete along http://www.apiic.in/w shared with of the

facility and with progress p- contractor contract summer of work content/uploads/201 after storage in 7/02/IEE-Naidupeta- approval Naidupeta Cluster.pdf Industrial

cluster. VCICDP- Upgrading & Design not yet No Draft IEE Yes In progress as IEE is part APRDC/ Rehabilitation completed http://aprdc.ap.gov.in the design is of the 01 of ‘Samarlkota /Documents/DISCLO being done contract

to SURES/ENVIRONM Rajanagaram’ ENT/FinalDraft_EA_ Section of VCIC_Samalkot- ‘Kakinada – Rajanagram- Rajanagaram’ March2016.pdf Road to ‘2 Lane Dual Carriageway

Standard’ VCICDP- Greenfield Under Review No Disclosure after Yes Bidding IEE is part APRDC/ approach road of PMSC/PMU approval document is of the bid 04 to Nakapalli being documents

Cluster finalized VCICDP- Widening of Under Review No Disclosure after Yes In progress as IEE is part APRDC/ road (single of PMSC/PMU approval the design is of the bid 05 lane to 2 lane) being done documents

from Neleballi to Routhusuramal a and formation

of new two lane road from Srikalahasti Yerpedu (south block to Pallamala on Kalahasti Tada

Road ) VCICDP- Widening of Under Review No Disclosure after Yes In progress as IEE is part APRDC/ road (single of PMSC/PMU approval the design is of the bid 06 lane to 2 lane) being done documents

from Thimmaji Kandriga to NH-5 (AH-45) near Pandlur Railway gate for 6.1Km length (without

RoB) VCICDP- Distribution Site not yet No Draft IEE Awaited In progress as IEE is part GVMC/0 Network final https://gvmc.gov.in/g this is being of the 2 improvements vmc/images/IEE.pdf prepared by contract

for NRW contractor reduction and 24x7 supply in

GVMC area Water shed Not yet No Yes Yes Bidding IEE is part development submitted by document is of the bid and the consultant being documents Rejuvenation of finalised Mudasarlova

lake. Developing a Not yet No Yes Yes Bidding IEE is part 3MW Solar submitted by document is of the bid Energy Park at the consultant being documents Mudasarlova/ finalized

Meghadri Gedda Converting 3 Environmental Yes Bidding IEE is part streets into Social Due document is of the bid non-vehicular Diligence Done being documents zone finalized

VCICDP- Augmenting Prepared Detailed No Draft IEE No It is being IEE is part APTrans power Design not yet http://www.aptransco prepared by of the co/01 distribution final .gov.in/transco/docs/ contractor contract

capacity for whatsnew1/draft- meeting iee.pdf Industry demand at Kapuleppada, Ozone Valley, Nakkapalle/ Chandanada and Achutapuram

locations. VCICDP- Augmenting Prepared Detailed design No Draft IEE No It is being IEE is part APTrans power not yet final http://www.aptransco prepared by of the co/03 distribution .gov.in/transco/docs/ contractor contract

capacity for whatsnew1/draft- meeting iee.pdf Industry demand at Rachagunneri, Naidupeta and Yerpedu

locations.

13 Site Specific Environmental Management Plan and Its Monitoring Report

Table 7: VCIDP/APIIC/03 Augmentation of Utilities

Impacts (List Mitigation Paramete Location Responsi Monitorin Responsibl Date of Compliance

from IEE) Measures (List rs ble for g Method e for Monitorin Status

from IEE) Monitored mitigation Monitoring g

Design Phase / Pre-construction Stage

Undertake all Necessary Environmen Naidupeta EC Documents APIIC/ PMU/ 9-11 July Complied

necessary tal industrial compliance check PMSC 2018

planning and

requirements Clearance cluster is 24-25

coordination with

to obtain No public is responsibilit October

concerned

EIA approval affected in y of APIIC 2018

authorities

for this 29-30

Naidupeta Prior notice to and package November

industrial consultation with 2018

estate concerned

including the authority, public to

proposed be affected so as

subprojects to ensure that

work does not get

affected.

The Contractor Letters and Office of the Contractor Document APIIC/ PMU/ 9-11 July Being complied

physical contractor

check PMSC 2018

will complete the

progress

24-25

following activities

no later than 30 October

days upon 2018

issuance of Notice 29-30

to Proceed November

Submit 2018

appointment letter

and resume of the

Contractor’s

Environmental

Officer

(EO) to SC/APIIC EO will engage CSC-Environment Specialist and to a meeting to discuss in detail the EMP, seek clarification and recommend corresponding revisions if necessary. 3.) EO will request CSC-ES copy of monthly monitoring formats and establish deadlines for submission. 4.) EO will submit for CSC-ES approval an action plan to secure all permits and approvals needed to be secured during construction stage which include but not limited to: i) disposal of hazardous waste (e.g. sludge, toxic untreated wastewater), ii) temporary storage location, iii) water use, and iv) ditch that will be managed for the

period of construction and after construction such ditches will be filled and restored to original condition.

Construction Stage The proposed

construction

works related

to internal

roads, water

supply, power

transmission

and distribution

lines, etc.

Dust during

earth works or from

spoil dumps.

Air pollution during

construction

activities needs to

follow all

requirements

relating to

obtaining permits

and maintaining

emission

requirements as

per the statutory

norms. Regular sprinkling

of water, as

necessary. Maintaining

adequate moisture

at surface of any

earthwork layer

completed or non-

completed unless

and until base

course is applied,

to avoid dust

emission.

Monitoring Sub project Contractor Laboratory APIIC/ PMU/ 9-11 July Being Complied of Ambient Location testing PMSC 2018

Air Quality 24-25 October

2018 29-30 November

2018 Visual

verification

of dust

generation

Vehicles and

Construction

machinery

Protection devices (ear plugs or ear muffs) will be provided to the workers operating near high noise generating machines. Construction equipment and machinery should be fitted with silencers and maintained properly. Source-control

through proper

maintenance of

all equipment. Use of properly

designed engine

enclosures and

intake silencers. Noise measurements should be carried out along the road to ensure the effectiveness of mitigation measures.

Availability Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied and use of construction inspection PMSC 2018

PPE site 24-25 October

2018 29-30 November

2018

Vehicles and

equipment used

should confirm to

the prescribed

noise pollution

norms.

Spillage from Providing Site Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied

plant and impervious condition construction inspection PMSC 2018

equipment at platform and oil site 24-25

construction and grease trap October

camp for collection of 2018

spillage from 29-30

construction

November

equipment

2018

vehicle.

Domestic solid Collecting kitchen Waste Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied

waste and generation construction

inspection PMSC 2018

waste at separate

liquid waste

site

24-25

bins and disposing

generated at of in a pit at October

camp designated area/s 2018

Collecting plastics 29-30

November

in separate bins

2018

and disposing in

deep trench at

designated area/s

covering with soil.

Collecting cottons,

clothes etc. at

separate bins and

burning in a pit

(with sand bed)

maintenance

platform

Collection oil and

lubes drips in

container during

repairing

construction

equipment

vehicles

Providing

impervious

platform and

collection tank for

spillage of liquid

fuel and lubes at

storage area

Construction • Water PPE, Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied

camp supply, sanitation, Sanitation, construction inspection PMSC 2018

drainage and Facility at site 24-25

medical health labour October

facilities at

camp 2018

campsite

29-30

• Providing

November

and using PPEs •

2018

Using

working reverse

horn for all

construction

equipment and

vehicles

Construction • Providing Safety Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied

sites adequate light at measures construction inspection PMSC 2018

construction zone site 24-25

if working during October

night time is

permitted by the 2018

Engineer 29-30

• Conductin

November

g induction and

2018

periodic training

for all workers and

supervisors

Potential safety Provide fence or Safety Project Contractor Site APIIC/ PMU/ 9-11 July Being Complied

risks to barricade (as measures constructio inspection PMSC 2018

community. appropriate), n site 24-25

sufficient lights, October

2018

clear warning

29-30

signs and danger

November

signals, and take

2018

all precautions

identified in the

community and

safety plan

Assign security

personnel to

prevent accidents,

trespassing, and

pilferage.

Contractor(s) to

direct drivers to

strictly follow road

regulations

Source: <I sert Notes or Source>

Table 8: VCIDP/APIIC04/ 21 MLD Bulk Water Supply

Impacts (List Mitigation Parame Location Responsi Monitorin Responsibl Date of Compliance from IEE) Measures (List ters ble for g Method e for Monitorin Status

from IEE) Monitor mitigation Monitoring g

ed Construction Stage

Exhaust To reduce Ambient Near Contractor Laboratory APIIC/ PMU/ Visual Being complied

emissions impacts from Air Construction test PMSC monitoring

from exhausts, Quality site by the

vehicles emission control Monitorin PMSC

Windblown norms shall be g specialist

dust during enforced/adhered. on following

material All the vehicles dates 9-11

movement and construction July 2018

Fugitive machinery shall 24-25

dust during be periodically October

material checked to 2018

unloading ensure 29-30

Dust

compliance to the

November

suspension emission 2018

during site standards

preparation Construction

, equipment and

constructio transport vehicles

n and shall be

trenching periodically

Emissions washed to

from DG remove

sets accumulated dirt

Providing

adequately sized

construction yard

for storage of

construction

materials,

equipment tools,

earthmoving

equipment, etc.

Provide

enclosures on all

sides of

construction site

Water sprinkling

shall be carried

out to suppress

fugitive dust in the

project site

Environmental

awareness

program shall be

provided to the

personnel

involved in

developmental

works

Use of tarpaulin

covers and speed

regulations for

vehicles engaged in

transportation

Noise Noise levels shall Ambient Near Contractor Laboratory Contractor Monitoring Being complied

be

mai tai edn Noise Construction test

during the

/Vibration from

below thresholdn Level site constructio

following

levels stpulatedn by Monitorin n period is

activities

Ce tral Polluto g being done.

Vehicles

Co trol Boardn

transportin (CPCB) tme to tme

g Procureme t of

constructio

machi ery/co stru

n material

cto equipme t i

Diesel run

accordna ce with

engines of

specifcato s

constructio

n

machinery Drilling/Pile

driving

activities

co formi g to source oise levels less tha 75 dnB (A) Well-mai tai edn co

structo equipme t,

which meets the

regulatory sta dnardns for

source oise levels,

shall be usedn A y equipme t emit g

high oise, wherever

possible, shall be

orie tedn so that the

oise is dnirectedn

away from se sitve

receptors Noise atte uato

shall be practsedn for oisy equipme t by employi g suitable tech iques such as acoustc co trols, i sulato a dn vibrato dnampers

High oise ge erat g actvites such as pili g a dn dnrilli g shall be schednuledn i dnay tme

Personnel

exposed to noise

levels beyond

threshold limits

shall be provided

with PPE.

Disturbance to The drains Drains Near Contractor Visual APIIC/ PMU/ 9-11 July Being complied

Natural passing through will be Construction inspection PMSC 2018

Drainage the area shall be construct site and record 24-25

pattern rerouted as per ed first checking October

Impact to the drain rerouting then 2018

plan existing

29-30

natural flow of

Adequate storm drains

runoff due to November

water drainage will be

2018

blockage and

system shall be closed

change of provided. and

drainage The storm water diverted

course system need to to new

be properly drains

connected to the

natural drainage

system of the

area

Drainage system

shall be provided at

construction yard.

Measures shall be

taken to prevent

silting of natural

drainage due to

runoff from

construction areas

Vegetation and Commencement No of Near Contractor Visual APIIC/ PMU/ 9-11 July Being complied

Strain on of greenbelt trees to Construction inspection PMSC 2018

existing development be cut. site and 24-25

infrastructure during October

Loss of construction 2018

vegetato phase especially 29-30

in terms of

a dn strai nursery November

o exist g development and 2018

i frastructur identification of

indigenous

e.

species

Temporary workers

camp with self-

sufficient

infrastructure

facilities.

Table 9: VCICDP/APIIC/01 - Construction of CETP

Impacts (List Mitigation Paramete Location Responsi Monitorin Responsibl Date of Compliance

from IEE) Measures (List rs ble for g Method e for Monitorin Status

from IEE) Monitored mitigation Monitoring g

Design Phase / Pre-construction Stage

EIA Approval • Necessary Environmen All project APIIC Document APIIC/ PMU/ 9-11 July Complied.

planning and tal site check PMSC 2018

Coordination clearance 24-25

with concerned has been October

authorities obtained for 2018

• Prior notice to the 29-30

and consultation November

with concerned 2018

authority, public to

be affected so as

to ensure that

work does not get

affected.

Contractor The Contractor The All project APIIC Document APIIC/ PMU/ 9-11 July Complied.

Preparatory will complete the identified site check PMSC 2018

Works following items are 24-25

activities no later being October

than 30 days prepared. 2018

upon issuance of 29-30

Notice to

November

Proceed

2018

1.)Submit

appointment

letter and

resume of the

Contractor’s

Environmental

Officer (EO) to

SC/APIIC

2.) EO will engage CSC - Environment Special is and to a meeting to discuss in detail the EMP, seek clarification and recommend corresponding revisions if necessary 3.) EO will request CSC-ES copy of monthly monitoring formats and establish deadlines for submission. 4.)EO will submit

for CSC- ES approval an action plan to secure all permits and approvals needed to be secured during construction stage which include but not limited to: i) Agreement with TSDF for transport, storage and disposal of hazardous

waste (e.g. sludge, toxic untreated wastewater), ii) temporary storage location, iii) water use, and iv) emission and fitness compliance of all vehicles to be used for hazardous waste transfer to CETPs.

CONSTRUCTION PHASE

Air Pollution • Maintaining Air quality All places of Contractor Laboratory APIIC/ PMU/ PMSC

adequate monitoring construction testing and PMSC environmen

moisture at is being site and air visual tal

surface of any done the quality inspection specialist

earth work layer contractor monitoring conducted

completed or construction is site visit on

non-completed

stage following

unless and until

date s 9-11

base course is

July 2018

applied, to avoid

24-25

dust emission.

October

• Stock piling spoil

2018

at designated

29-30

areas and at

least 5m away November

from traffic lane. 2018

Sprinkling of It will be

water as done during

necessary the

construction

stage

Water Storage of It will be Pollution construction done during

material and the excavated soil construction above high flood stage

level

•Strictly avoiding It will be cleaning/washing done during of construction the vehicle in any construction

water body stage • Proper It will be planning of site done during clearing and the grubbing so as construction not to keep the stage cleared site before working

for long duration. • Providing temporary side drains, catch water bank or drains, sedimentation basin, as necessary to avoid or minimize erosion and prevent sedimentation to receiving water

bodies Groundwater •All waste water It will be pollution will be diverted to done during

a ditch that will the

be managed for construction

the period of stage

construction and

after construction

such ditches will

be filled and

restored to

original

condition.

Providing septic It will be

done during

tanks for

the

treating

sewage from construction

toilets before stage

discharging

through soak

pits

• Decanting

and or controlled

disposal of oil

and grease as

collected at

collection tanks

of maintenance

yard and

chemical storage

areas

Noise Pollution • Protection It will be

and Vibration devices (ear done during

plugs or the

earmuffs) will construction

be provided to stage

the workers

operating in

the vicinity of

high noise

generating

machines.

• Construction equipment and machinery should be fitted with silencers and maintained

properly. • Source-control through proper maintenance of

all equipment. • Use of properly designed engine enclosures and

intake silencers. • Noise measurements should be carried out along the road to ensure the effectiveness of mitigation

measures. • Vehicles and equipment used should confirm to the prescribed noise pollution

norms.

Land Pollution • Providing It will be impervious done during platform and the oil and grease construction

trap for stage

collection of

spillage from

construction

equipment

vehicle

maintenance

platform

• Collection oil

and lubes

drips in

container

during

repairing

construction

equipment

vehicles

• Providing

impervious

platform and

collection tank

for spillage of

liquid fuel and

lubes at

storage area

Collecting It will be

done during

kitchen waste

the

at separate

bins and construction

disposing of in stage

a pit at

designated

area/s

• Collecting

plastics in

separate bins

and disposing

in deep trench

at designated

area/s

covering with

soil

• Collecting

cottons,

clothes etc. at

separate in

sand burning

in a pit(with

sand bed)

Occupationa • Water It will be

l health and done during

supply,

safety of the

sanitation,

workers drainage and construction

medical health stage

facilities at

campsite

• Providing

and using

PPEs

• Using

working

reverse horn

for all

construction

equipment

and vehicles

Accidents •Providing It will be

and safety done during

adequate light

the

at construction

zone if construction

working during stage

night time is

permitted by

the Engineer

•Conducting

induction and periodic training for all

workers and supervisors

Table 10: APTRANCO03/ Rachagunneri-Yerpedu

Impacts (List Mitigation Paramete Location Responsi Monitorin Responsibl Date of Compliance

from IEE) Measures (List rs ble for g Method e for Monitorin Status

from IEE) Monitored mitigation Monitoring g

Design Phase / Pre-construction Stage

• Loss of • Use of criteria for Loss of Rachgunner Contractor/ Document APTRANSCO 9-11 July complied

agricultural site selection agricultural ia and APTRANSC inspection, PMU 2018

land and which include land has Yerpudu O site PMSC 30

crops environmental been substation verification November

• Loss of factors to compensat locations and 2018

habitat and minimize ed as per consultation

vegetation potential impacts the with project

clearing • Use of prevailing affected

• Land checklist/questio land persons

acquisition nnaire in acquisition

Increase in soil evaluating act.

substation sites The land

erosion and

which aim at

acquired is

impact to soil

avoidance of

not

productivity

land acquisition

cultivable.

and

• Physical

Loss of Rachgunner Contractor/ Document APTRANSCO 9-11 July complied

environmental

displacement impacts agricultural ia and APTRANSC inspection, PMU 2018

of people • Substations are land has Yerpudu O site PMSC 30

and all on been substation verification November

structures •

government land compensat locations and 2018

• Economic No land ed as per consultation

loss to acquisition the with project

people required but prevailing affected

• Disturbance transfers of land persons

and ownership from acquisition

inconvenienc the act.

e to people APIIC to AP-

The land

due to traffic,

acquired is

increased

TRANSCO is

not

noise and required cultivable.

dust levels,

• Transmission

vibration

line will not

Interference to

traverse forest,

existing utilities

sanctuary, or

• Interferen

APTRANSCO 9-11 July

protected areas

ce to local

Use of non PCB 1 PMU 2018

drainage PMSC 30

Water quality based oil for November

impacts due to transformers 2018

erosion and/or

sedimentation

• Increase No impact Rachgunner Contractor/ Document APTRANSCO 9-11 July Being complied dust and recipient ia and APTRANSC inspection, PMU 2018

noise near the Yerpudu O site PMSC 30 levels, project site. substation verification November

and Moreover locations and 2018 vibration the consultation

Emissions from monitoring with project heavy of noise affected equipment level will be persons machinery and conducted. construction

vehicles

Construction Stage Awareness of Conduct briefing of Awareness Rachgunner Contractor/ Document APTRANSCO 9-11 July Being complied

workers on the session ia and APTRANSC inspection, PMU 2018

Contractor(s) on

environmental EMP, records conducted Yerpudu O site PMSC 30

requirements management, and by the substation verification November

and their reporting contractor locations and 2018

responsibility • Identify critical and consultation

with project

Understanding areas to be

affected

of monitored and

persons

Contractor(s) the required

of their mitigation

1 Polychloro Biphe yls

responsibility in measures implementing • Create the EMP awareness of sexually-

transmitted diseases such as HIV/AIDs • Conduct training/drills on emergency

preparedness

Encourage workers to conduct exercises every day prior to start of work to

keep fit • Avoid effects • Temporary No such Thought out contractor Visual APTRANSCO 9-11 July Being Complied of pedestrian and circumstanc the project inspection PMU 2018

Contractor(s) traffic es site and PMSC 30 unplanned management plan verification November activities of 2018

documents Smooth work Community and Documents Office of the contractor Visual APTRANSCO 9-11 July Being Complied implementation safety plan of site contractor inspection PMU 2018

specific and PMSC 30 environmen verification November

tal of 2018 manageme documents

nt plan Spoils disposal Documents Office of the contractor Visual APTRANSCO 9-11 July Being Complied plan of site contractor inspection PMU 2018

specific and PMSC 30 environmen verification November

tal of 2018

manageme documents

nt plan

Noise and dust Documents Office of the contractor Visual APTRANSCO 9-11 July Being Complied

control plan of site contractor inspection PMU 2018

specific and PMSC 30

environmen verification November

tal of 2018

manageme documents

nt plan

Drainage and Documents Office of the contractor Visual APTRANSCO 9-11 July Being Complied

storm water of site contractor inspection PMU 2018

management plan specific and PMSC 30

environmen verification November

tal of 2018

manageme documents

nt plan

• Materials Documents Office of the contractor Visual APTRANSCO 9-11 July Being Complied

management of site contractor inspection PMU 2018

plan specific and PMSC 30

• Construction environmen verification November

waste tal of 2018

management manageme documents

plan nt plan

• Conflict Contractor(s) The Construction Contractor Site APTRANSCO 9-11 July Being complied

due to will be contractor and labour inspection PMU 2018

potential encouraged to will arrange camp site PMSC 30

workers’ use local labor labors. The November

migration for manual work contract will 2018

• Lack of and eligible keep their

local local workforce labors in

support to labour

for clerical and

the project camp. The

office jobs

• Dispute labour

over camp has

been paced

transparen

away from

cy of

the

hiring

community

and sharing

of facility of

community

has been

avoided by

placing the

• Dismantlin • Construction No All project Contractor Visual APTRANSCO 9-11 July

g of management dismantling sites inspection PMU 2018

structure(s) plan of existing PMSC 30

and will be strictly substation November

equipment

implemented

2018

from

• Use of proper

existing

substations safety

• Dismantled clothes/equipm

equipment ent in

dismantling

may be

structure(s)

suspected

and equipment

or

potentially-

PCB

contaminat

ed

Potential safety • Provide fence Full At Contractor Visual APTRANSCO 9-11 July Being complied

risks to or barricade (as boundary Rachgunner inspection PMU 2018

community appropriate), wall is i substatin PMSC 30

sufficient lights, being and November

clear warning constructed Yerpedu 2018

signs and substation

danger signals,

and take all

precautions

identified in the

community and

safety plan

• Assign security

personnel to prevent accidents, trespassing, and pilferage • Contractor(s) to direct drivers to strictly follow road regulations

Interference • Danger Measures At the road Contractor Visual APTRANSCO 9-11 July Will be complied. with road and will be crossings inspection PMU 2018

crossings clearly adopted PMSC 30 visible during road November warning crossing 2018

signs will be posted at designate d sites • Scaffoldin gs will be placed over road crossing points • Constructi on vehicles to strictly follow road regulation s • Implemen t temporary pedestria

n and traffic managem ent plan

Potential • Provide sanitary Facilities to Labour Contractor Visual APTRANSCO 9-11 July Being complied health and facilities and be camp at inspection PMU 2018 safety risks to wash areas provided in Rachgunner PMSC 30 workers • Provide safe the labour i and November

drinking water camp Yerpedu 2018

and garbage bins • Enforce good housekeeping at all times • Provide workers with hard hat, safety shoes and belts • Coordinate with nearest hospital

for

arrangements in case of accidents • Assign nurse or medical staff to make weekly rounds at substation

sites • Set up first aid

treatment within construction sites and field office

• Observance and compliance with relevant safety measures required by law and best engineering practices • Provide communication devices to designated workers

• Erosion and • Only minimal localized vegetation will

flooding be cleared since most of the substation sites are on grassland.

Landscaping/re planting of trees at subsstations will be done after completion of construction

works • Compensation Compensati Locations Contractor/ Visual APTRANSCO 9-11 July Being complied. for temporary on for where APTRANSC inspection PMU 2018 damages to temporary stringing of O and PMSC 30

crops/plants crop loss wire will document November along the ROW will be take place. verification

and substations • Cut trees owned

by the government will be sold and revenue turned over to Revenue Authority Debris/dismantle d structures/equip

ment will be disposed of in

designated landfill and/or

controlled

dumpsites • Usable scrap

materials from dismantling will be

stored in

warehouses of

AP-TRANSCO

• Erosion-control measures will be provided (as needed)

• Implement

spoils disposal

plan and

construction

compensat 2018 ory as per the entitlement

framework

57

waste

management

plan

• Generation • Avoidance Facilities at Labour Contractor Site APTRANSCO 9-11 July Being complied

of sewage of labour camps inspection PMU 2018

from waterways camp like PMSC 30

construction in site water November

workers selection supply, 2018

• Localized • Provide toilets and

flooding sanitary medical

• Increase facilities to facility

turbidity in workers

surface and safe

water near drinking

water.

construction

• Constructio

sites

n works will

be done

during

summer in

areas

potential for

erosion and

localized

flooding

• Implement

drainage

and storm

water

manageme

nt plan

• Waterways

were

avoided in

selecting

subproject

sites

• Heavy

equipment and construction vehicles may increase vehicular emissions

• Transport of construction materials to construction s sites may increase dust level

• Earthmovin

g works,

excavations ,

and opened

land areas

for

substations

and towers

may

increase

dust levels • Increase in

noise level and vibration from excavation and heavy equipment and

• Construction Safety and All locations Contractor Site APTRANSCO 9-11 July Being complied vehicles will be security at of inspection PMU 2018 maintained to construction construction PMSC 30

minimize site and and November vehicular construction construction 2018

emissions camp camp site • Enclose

construction sites temporarily to contain dust dispersion

• Temporary storage / Warehouse for construction materials onsite will be provided to reduce trips of material delivery

• Contractor(s) will be required to maintain construction vehicles and heavy equipment machineries regularly to reduce emissions

• Opened land areas or sources of dust will be sprayed with water (as

construction needed)

vehicles

• Transport of

dust generating

materials will be

covered

• Observance of

low speed by

vehicles to

reduce noise

• Noise-

generating

works will be

done between

7AM and 7PM

done at daytime

as

required by

APPCB

Table 11: APTRANCO04/ Visakhapatnam

Impacts (List Mitigation Paramete Location Responsi Monitorin Responsibl Date of Compliance

from IEE) Measures (List rs ble for g Method e for Monitorin Status

from IEE) Monitored mitigation Monitoring g

Design Phase / Pre-construction Stage

• Loss of • Use of criteria for Loss of Brandis Contractor/ Document APTRANSCO 12-13 July complied

agricultural site selection agricultural substation APTRANSC inspection, PMU 2018

land and which include land has locations O site PMSC 20-21

crops environmental been verification September

• Loss of factors to compensat and 2018

habitat and minimize ed as per consultation

vegetation potential impacts the with project

clearing • Use of prevailing affected

• Land checklist/questio land persons

acquisition nnaire in acquisition

Increase in soil evaluating act.

substation sites The land

erosion and

which aim at

acquired is

impact to soil

avoidance of

not

productivity

land acquisition

cultivable.

and

• Physical

Loss of Brandis Contractor/ Document APTRANSCO 12-13 July complied

environmental

displacement impacts agricultural substation APTRANSC inspection, PMU 2018

of people • Substations are land has locations O site PMSC 20-21

and all on been verification September

structures •

government land compensat and 2018

• Economic No land ed as per consultation

loss to acquisition the with project

people required but prevailing affected

• Disturbance transfers of land persons

and ownership from acquisition

inconvenienc the act.

e to people APIIC to AP-

The land

due to traffic,

acquired is

increased

TRANSCO is

not

noise and required cultivable.

dust levels,

• Transmission

vibration

line will not

Interference to

traverse forest,

existing utilities

sanctuary, or

• Interferen

protected areas

ce to local

Use of non PCB 2

drainage

Water quality based oil for

impacts due to transformers

erosion and/or

sedimentation • Increase No impact Brandis Contractor/ Document APTRANSCO 12-13 July Being complied

dust and recipient substation APTRANSC inspection, PMU 2018

noise near the locations O site PMSC 20-21

levels, project site. verification September

and Moreover and 2018

vibration the consultation

Emissions from monitoring with project

heavy of noise affected

equipment level will be persons

machinery and conducted.

construction

vehicles

Construction Stage

Awareness of Conduct briefing of Awareness Brandis Contractor/ Document APTRANSCO 12-13 July Being complied

workers on the session substation APTRANSC inspection, PMU 2018

Contractor(s) on

environmental EMP, records conducted locations O site PMSC 20-21

requirements management, and by the verification September

and their reporting contractor and 2018

responsibility • Identify critical and consultation

with project

Understanding areas to be

affected

of monitored and

persons

Contractor(s) the required

of their mitigation

2 Polychloro Biphe yls

responsibility in measures implementing • Create the EMP awareness of sexually-

transmitted diseases such as HIV/AIDs • Conduct training/drills on emergency

preparedness

Encourage workers to conduct exercises every day prior to start of work to

keep fit • Avoid effects • Temporary No such Thought out contractor Visual APTRANSCO 12-13 July Being Complied of pedestrian and circumstanc the project inspection PMU 2018

Contractor(s) traffic es site and PMSC 20-21 unplanned management plan verification September activities of 2018

documents Smooth work Community and Documents Office of the contractor Visual APTRANSCO 12-13 July Being Complied implementation safety plan of site contractor inspection PMU 2018

specific and PMSC 20-21 environmen verification September

tal of 2018 manageme documents

nt plan Spoils disposal Documents Office of the contractor Visual APTRANSCO 12-13 July Being Complied plan of site contractor inspection PMU 2018

specific and PMSC 20-21 environmen verification September

tal of 2018

manageme documents

nt plan

Noise and dust Documents Office of the contractor Visual APTRANSCO 12-13 July Being Complied

control plan of site contractor inspection PMU 2018

specific and PMSC 20-21

environmen verification September

tal of 2018

manageme documents

nt plan

Drainage and Documents Office of the contractor Visual APTRANSCO 12-13 July Being Complied

storm water of site contractor inspection PMU 2018

management plan specific and PMSC 20-21

environmen verification September

tal of 2018

manageme documents

nt plan

• Materials Documents Office of the contractor Visual APTRANSCO 12-13 July Being Complied

management of site contractor inspection PMU 2018

plan specific and PMSC 20-21

• Construction environmen verification September

waste tal of 2018

management manageme documents

plan nt plan

• Conflict Contractor(s) The Construction Contractor Site APTRANSCO 12-13 July Being complied

due to will be contractor and labour inspection PMU 2018

potential encouraged to will arrange camp site PMSC 20-21

workers’ use local labor labors. The September

migration for manual work contract will 2018

• Lack of and eligible keep their

local local workforce labors in

support to labour

for clerical and

the project camp. The

office jobs

• Dispute labour

over camp has

been paced

transparen

away from

cy of

the

hiring

community

and sharing

of facility of

community

has been

avoided by

placing the

• Dismantlin • Construction No NA NA NA APTRANSCO 12-13 July

g of management dismantling PMU 2018

structure(s) plan of existing PMSC 20-21

and will be strictly substation September

equipment

implemented

2018

from

• Use of proper

existing

substations safety

• Dismantled clothes/equipm

equipment ent in

dismantling

may be

structure(s)

suspected

and equipment

or

potentially-

PCB

contaminat

ed

Potential safety • Provide fence Full Brandis Contractor Visual APTRANSCO 12-13 July Being complied

risks to or barricade (as boundary Substation inspection 2018

community appropriate), wall is 20-21

sufficient lights, being September

clear warning constructed 2018

signs and

danger signals,

and take all

precautions

identified in the

community and

safety plan

• Assign security

personnel to prevent accidents, trespassing, and pilferage • Contractor(s) to direct drivers to strictly follow road regulations

Interference • Danger Measures At the road Contractor Visual APTRANSCO 12-13 July Will be complied. with road and will be crossings inspection PMU 2018

crossings clearly adopted PMSC 20-21 visible during road September warning crossing 2018

signs will be posted at designate d sites • Scaffoldin gs will be placed over road crossing points • Constructi on vehicles to strictly follow road regulation s • Implemen t temporary pedestria

n and

traffic

managem

ent plan

Potential • Provide sanitary Facilities to Labour Contractor Visual APTRANSCO 12-13 July Being complied

health and facilities and be camp inspection PMU 2018

safety risks to •

wash areas provided in PMSC 20-21

workers Provide safe the labour September

drinking water camp 2018

and garbage

bins

• Enforce good

housekeeping

at all times

• Provide workers

with hard hat,

safety shoes

and belts

• Coordinate with

nearest hospital

for

arrangements

in case of

accidents

• Assign nurse or

medical staff to

make weekly

rounds at

substation

sites • Set up first aid

treatment within construction sites and field office

• Observance and compliance with relevant safety measures required by law and best engineering practices • Provide communication devices to designated workers

• Erosion and • Only minimal localized vegetation will

flooding be cleared since most of the substation sites are on grassland.

Landscaping/re planting of trees at subsstations will be done after completion of construction

works • Compensation Compensati Locations Contractor/ Visual APTRANSCO 12-13 July Being complied. for temporary on for where APTRANSC inspection PMU 2018

damages to temporary stringing of O and PMSC 20-21 crops/plants crop loss wire will document September

along the ROW will be take place. verification

and substations • Cut trees owned

by the government will be sold and revenue turned over to Revenue Authority Debris/dismantle

d structures/equip

ment will be disposed of in designated landfill and/or

controlled

dumpsites • Usable scrap

materials from dismantling will be

stored in

warehouses of

AP-TRANSCO

• Erosion-control measures will be provided (as needed)

• Implement

spoils disposal

plan and

construction

compensat 2018 ory as per the entitlement

framework

waste

management

plan

• Generation • Avoidance Facilities at Labour Contractor Site APTRANSCO 12-13 July Being complied

of sewage of labour camps inspection PMU 2018

from waterways camp like PMSC 20-21

construction in site water September

workers selection supply, 2018

• Localized • Provide toilets and

flooding sanitary medical

• Increase facilities to facility

turbidity in workers

surface and safe

water near drinking

water.

construction

• Constructio

sites

n works will

be done

during

summer in

areas

potential for

erosion and

localized

flooding

• Implement

drainage

and storm

water

manageme

nt plan

• Waterways

were

avoided in

selecting

subproject

sites

• Heavy

equipment and construction vehicles may increase vehicular emissions

• Transport of construction materials to construction s sites may increase dust level

• Earthmovin

g works,

excavations ,

and opened

land areas

for

substations

and towers

may

increase

dust levels • Increase in

noise level and vibration from excavation and heavy equipment and

• Construction Safety and All locations Contractor Site APTRANSCO 12-13 July Being complied vehicles will be security at of inspection PMU 2018 maintained to construction construction PMSC 20-21

minimize site and and September vehicular construction construction 2018

emissions camp camp site • Enclose

construction sites temporarily to contain dust dispersion

• Temporary storage / Warehouse for construction materials onsite will be provided to reduce trips of material delivery

• Contractor(s) will be required to maintain construction vehicles and heavy equipment machineries regularly to reduce emissions

• Opened land areas or sources of dust will be sprayed with water (as

construction needed)

vehicles

• Transport of

dust generating

materials will be

covered

• Observance of

low speed by

vehicles to

reduce noise

• Noise-

generating

works will be

done between

7AM and 7PM

done at daytime

as

required by

APPCB

Table 12: GVMC/ 24X7 Water Supply

Impacts (List Mitigation Paramete Location Responsi Monitorin Responsibl Date of Compliance

from IEE) Measures (List rs ble for g Method e for Monitorin Status

from IEE) Monitored mitigation Monitoring g

Design Phase / Pre-construction Stage

Utilities (i) Identify and Utility All along the Contractor Verification GVMC 12-13 July Being complied

Telephone include shifting is road of PMU 201821-22

lines, locations and being done documents PMSC September

electric operators of after and site 2018

poles and these utilities in permission verification

wires, water the detailed of the

lines within design concerned

proposed documents to department.

project area prevent

unnecessary

disruption of

services during

construction

phase; and (ii)

Require

construction

contractors to

prepare a

contingency

plan to include

actions to be

done in case of

unintentional

interruption of

services. (iii)

Require

contractors to

prepare spoils

management

plan and traffic

management

plan

Social and Consult No NA NA NA GVMC 12-13 July

Cultural Archaeological archeologic PMU 201821-22

Resources Survey of India al site PMSC September

Ground

(ASI) or intervention 2018

disturbance concerned involved in

can dept. of Andhra the project.

uncover Govt. to obtain

and an expert

damage assessment of

archaeologi the

cal and archaeological

historical potential of the

remains site; Consider

alternatives if

the site is found

to be of

medium or high

risk; (iii)

Develop a

protocol for use

by the

construction

contractors in

conducting any

excavation

work, to ensure

that any chance

finds are

recognized, and

measures are

taken to ensure

they are

protected and

conserved.

Constructio Prioritize areas n work within or camps, hot nearest mix plants, possible vacant stockpile space in the areas, project location; storage If it is deemed areas, and necessary to disposal locate

areas. elsewhere, Disruption consider sites to traffic that will not flow and promote sensitive instability and receptors result in destruction of property, vegetation, irrigation, and drinking water supply systems; Do not consider residential areas; Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. For excess spoil disposal, ensure (a) site shall be

All facilities Labour Contractor Visual GVMC 12-13 July Being complied

for labors camp inspection PMU 201821-22

like drinking PMSC September

water, 2018

sanitation,

solid waste

disposal

facility, cot

and medical

facility

selected

preferably from

barren, infertile

lands. In case

agricultural land

needs to be

selected,

written consent

from

landowners (not

lessees) will be

obtained; (b)

debris disposal

site shall be at

least 200 m

away from

surface water

bodies; (c) no

residential

areas shall be

located within

50 m downwind

side of the site;

and (d) site is

minimum 250 m

away from

sensitive

locations like

settlements,

ponds/lakes or

other water

bodies.

Sources of Prioritize sites Licenses Project Contractor Visual GVMC 12-13 July Being complied

Materials already and permits construction inspection PMU 201821-22

Extraction permitted by and royalty camps and PMSC September

the authorized paid office 2018

of materials

agency; If other receipt.

can disrupt

sites are

natural land necessary,

contours inform

and construction

vegetation contractor that

resulting in it is their

accelerated responsibility to

erosion, verify the

disturbance suitability of all

in natural material

drainage sources and to

patterns, obtain the

ponding approval of

and water PMU and If

logging, additional

and water quarries

pollution. required after

construction is

started, inform

construction

contractor to

obtain a written

approval from

PIU

Structural The design All structure Drawings Contractor Visual GVMC 12-13 July Being complied

and seismic shall shall be and designs inspection PMU 201821-22

stability of incorporate reviewed by of p PMSC September

storage seismicity of the government 2018

reservoirs place and all recognized

(OHTs or other safety institutions.

GLSRs) is factors. All care

to be shall be taken

ensured for to ensure a

the safety safe and

of people structurally

working in sound

and living construction.

around

these

structures.

The failure of

the storage

structures

ca be

catastrophic.

Consents, Obtain all Records Office of Contractor Visual GVMC 12-13 July Being complied

permits, necessary and contractor inspection PMU 201821-22

clearances, consents, Documents PMSC September

NOCs, etc. permits, 2018

Failure to clearance,

obtain NOCs, etc.

necessary prior to start of

consents, civil works.

permits, Acknowledge in

NOCs, etc writing and

can result provide report

to design on compliance

revisions all obtained

and/or consents,

stoppage of permits,

works clearance,

NOCs, etc.

Include in

detailed design

drawings and

documents all

conditions and

provisions if

necessary

Asbestos Obtain details The older Project area Contractor No GVMC 12-13 July Being complied

Cement from of the asbestos and GVMC monitoring PMU 201821-22

Pipes nature and pipes are required PMSC September

Health risk location of all not 2018

due to water supply removed

exposure to infrastructure while laying

asbestos Develop an AC of new materials pipe protocol pipelines.

Require all The personnel proposed (including pipelines manual laying does laborers) to not include undergo the training as per asbestos AC pipe pipelines.

protocol Construction Stage

Utilities (i) Identify and Telephone include lines, locations and electric operators of poles and these utilities in wires, water the detailed lines within design proposed documents to project area prevent unnecessary disruption of services during construction phase; and (ii) Require construction contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services. (iii)

Document Along the Contractor Visual GVMC 12-13 July Being complied verification, pipelines inspection PMU 201821-22 Verification and road. PMSC September

of other 2018 utilities and services of community which would be impacted by the utilities

shifting.

Require

contractors to

prepare spoils

management

plan and traffic

management

plan

Social and Consult No such All along the Contractor Visual GVMC 12-13 July Being complied

Cultural Archaeological impacts project inspection PMU 201821-22

Resources Survey of India involved. PMSC September

Ground (ASI) or

2018

disturbance concerned

can dept. of Andhra

uncover Govt. to obtain

and an expert

damage assessment of

archaeologi the

cal and archaeological

historical potential of the

remains site; Consider

alternatives if

the site is found

to be of

medium or high

risk; (iii)

Develop a

protocol for use

by the

construction

contractors in

conducting any

excavation

work, to ensure

that any chance

finds are

recognized, and

measures are

taken to ensure

they are

protected and

conserved.

Constructio Prioritize areas All items Location of Contractor Visual GVMC 12-13 July Being complied

n work within or listed in construction inspection PMU 201821-22

camps, hot nearest mitigation camp and PMSC September

mix plants, possible vacant measures locations of 2018

stockpile space in the allied

areas, project location; facilities.

storage If it is deemed

areas, and necessary to

disposal locate

areas. elsewhere,

Disruption consider sites

to traffic that will not

flow and promote

sensitive instability and

receptors result in

destruction of

property,

vegetation,

irrigation, and

drinking water

supply systems;

Do not consider

residential

areas;

Take extreme

care in

selecting sites

to avoid direct

disposal to

water body

which will

inconvenience

the community.

For excess

spoil disposal, ensure (a) site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water

bodies. Sources of Prioritize sites Licenses, All project Contractor Visual GVMC 12-13 July Being complied Materials already permit and facilities and inspection PMU 201821-22

permitted by third party allied September

Extraction the authorized certification facilities PMSC 2018

of materials agency; If other of the allied

can disrupt sites are facilities

natural land necessary,

contours inform

and construction

vegetation contractor that

resulting in it is their

accelerated responsibility to

erosion, verify the

disturbance suitability of all

in natural material

drainage sources and to

patterns, obtain the

ponding approval of

and water PMU and If

logging, additional

and water quarries

pollution. required after

construction is

started, inform

construction

contractor to

obtain a written

approval from

PIU

Structural The design A third party All Contractor Visual GVMC 12-13 July Being complied

and seismic shall vetting of structures inspection PMU 201821-22

stability of incorporate structure involved in PMSC September

storage seismicity of the design is the project 2018

reservoirs place and all done by

(OHTs or other safety civil

GLSRs) is factors. All care department

to be shall be taken of Andhra

ensured for to ensure a University.

the safety safe and Based on

of people structurally this vetting

working in sound GVMC

and living construction. approves

around the design

these and

structures. construction

The failure of to proceed.

the storage

structures

ca be

catastrophic.

Consents, Obtain all Availability Availability Contractor Visual GVMC 12-13 July Being complied

permits, necessary of permits of inspection PMU 201821-22

clearances, consents, and documents PMSC September

NOCs, etc. permits, clearance in the office 2018

Failure to clearance, for the of contractor

obtain NOCs, etc. project in and PIUs

necessary prior to start of the office of

consents, civil works. contractor

permits, Acknowledge in and project

NOCs, etc writing and implementa

can result provide report tion unit.

to design on compliance

revisions all obtained

and/or consents,

stoppage of permits,

works clearance,

NOCs, etc.

Include in

detailed design

drawings and

documents all

conditions and

provisions if

necessary

14 Conclusion and Recommendation

Table 22: Corrective Action Plan

Sr Unanticipated impacts Action Required Responsibil Target Indicator of

. or Observations ity Date Compliance

N

o.

1 Orga isato a dn Recruitme t of PMU By March Recruitment

i sttuto capacity

e viro me tal ofcer 2019 of

i PMU environmenta

l officer

2 Capacity of co tractor Providne roles a dn Contractor 31 March Confirmation

to impleme t

respo sibility of 2019 from

e viro me tal contractor

e viro me tal

e gi eer of co tractor with name

safeguardns and details of

the

environmenta

l engineer

3 E viro me tal Recordns Co tractor/ PIU a dn Contractor/ 31 March Contractor to

PMSC to establish PIUs / PMU 2019 provide copy

recordn of and PMSC of

e viro me tal compliances

complia ces i the like permits,

ofce NoC and

clearances

4 Fi al IEE submissio of APTRANSCO to f alise APTRANSC 3o APTRANSCO

APTRANSCO/01

the locato of O January to confirm the

Kappulupadna 2019 location and

substato locato boundary of

APTRANSCO

substation.

Appeneices A. Copy of Environmental Clearance of Industrial Park at Attivaram 71 B. Environmental Clearance of MPSEZ 80 C. Public Consultation 106

File No.INC02/10/2019-PMU-VCIC

A. Copy of Environmental Clearance of

Industrial Park at Attivaram

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

B. Environmental Clearance of MPSEZ Source: <I sert Notes or Source>

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

C. Public Consultation

1 Public Communication Activities

The civil works at GVMC startedn o 14th March 2018 with the sig i g of agreeme t with the

co tractor. It was pla edn to dnemo strate the project i o e dnistrict meteri g area (DMA).

i.e. Block 10 a dn the works are expectedn to complete by November 2018.

14.1 Activities in October month 2018 14.1.1 Awareness programme on worksite safety

Date of programme: 03.10.2018 Partcipa ts : Workers a dn Fieldn Staf of Co tractor (NCC) Purpose of the meet g:

To i form the workers about the project

To i form about dniscomforts the residne ts may face dnuri g executo of the work.

To i form the workers to take up safety protectve measures

To recordn a y grieva ces with regardn to worksite Methodn

Presentation on the project and safety protective

measures Discussion on the issues No. of partcipa ts: 41

A meet g with workers of Nagarju a Co structo Compa y (NCC) was co dnuctedn at

Madnhavdnhara. The meet g was atte dnedn by staf from PMSC a dn Co tractor.

Proceedni gs of the meet g

Mr.D.A. Sa thosh, Public Commu icato Specialist, PMSC prese tedn dnetails of the project,

its compo e ts a dn 24 x 7 water supply project dnetails. Mr. Ve katesh, E gi eer, NCC explai edn about the works a dn dniscomforts residne ts may

face dnuri g the executo of works. Mr. Muthyalu, Safety Ofcer, NCC explai edn about the worksite safety. (Note A exedn)

File No.INC02/10/2019-PMU-VCIC

NCC workers explai edn about worksite safety measures at Madnhavdnhara, GVMC

14.1.2 Meeting with women group members

Date of Programme : 03.10.2018

Partcipa ts : Wome group members of Madnhavdnhara (Block 10)

Purpose of the meeting:

To i form the wome about progress of the project

To i form about temporary impacts a dn dniscomforts

To providne adnva ce commu icato about works

Methodn

Focussed Group Discussions

Structured meetings and presentations No. of partcipa ts: 23 A meet g with wome members of Madnhavdnhara area of the GVMC was co dnuctedn with

the support of Ms. Jyots a, Wome Leadner. She mobilizedn other wome for the meet g. The

meet g was heldn at Shivalayam (Temple), where e ough space was available for co dnuct g

the meet g. The meet g was atte dnedn by staf from PMSC a dn Co tractor. Proceedni gs of the meet g Mr.D.A. Sa thosh, Public Commu icato Specialist, PMSC prese tedn dnetails of the project, its compo e ts a dn 24 x 7 water supply project dnetails. Mr. Ve katesh, E gi eer, NCC explai edn about the works a dn dniscomforts residne ts may

face dnuri g the executo of works. Wome expressedn the followi g dnuri g the meet g.

Residne ts of the Madnhavdnhara are joyful about the 24 x 7 water supply work. Wome are happier because, it lesse s their workloadn of bri gi g a dn savi g water.

They feel that as the water is available throughout the dnay, they ca take up better

jobs.

File No.INC02/10/2019-PMU-VCIC

Colo y residne ts dnidn ot face a y major issue with regardns to dniscomfort or safety.

The commu icatedn that the dniggi g, layi g pipes a dn closi g the tre ches hadn take

o ly 3 dnays periodn. Wome , se ior citze a dn childnre dnidn ot face a y

i co ve ie ce dnuri g executo of works. O e dnay, whe it rai edn, all the roadns have

become skidndny dnue to mudn.

However, it was taki g lo g tme for BSNL a dn Cable operator to restore

Wome i formedn that ma y of the householdn have i vestedn more tha Rs.75,000

for dnrilli g of borewells a dn pipeli e co ecto s. They fear that, the i vestme t

may go waste o ce they get 24 x 7 water.

The GVMC is alreadny collect g water tax of Rs.100 per six mo ths. Wome dnema dn that, GVMC shouldn ot collect both water tax as well meteredn bill.

The wome complai that, the mu icipal water they get is pollutedn a dn u clea . They

sufer from ma y dniseases dnue to usi g pollutedn water.

Interaction with women group members at Madhavdhara, GVMC on 03.10.2018

14.1.3 Interaction with Students on Road Safety

Date of Programme: 04.10.2018 Partcipa ts : Studne ts at Machavadnhara

Purpose of the meeting:

To i form the studne ts about the project a dn its progress

To i form about temporary impacts a dn dniscomforts

To se sitze o roadn safety a dn precauto s to be take at project sites Methodn

Presentation and discussion. No. of partcipa ts: 45

File No.INC02/10/2019-PMU-VCIC

A i teractve meet g with meet g with studne ts of Hebro School, Madnhavdnhara was

co dnuctedn o 04.10.2018.

Proceedni gs of the meet g

Mr.D.A. Sa thosh, Public Commu icato Specialist, PMSC prese tedn dnetails of the project,

its compo e ts a dn 24 x 7 water supply project dnetails.

Mr. Ve katesh, E gi eer, NCC explai edn about the works, dniscomforts, roadn safety to the

studne ts.

Studne ts expressedn the followi g dnuri g the meet g.

Studne ts were ot aware about the 24 x 7 project. They were happy that they get

water throughout the dnay. They saidn, bri gi g water is the mai respo sibility the

mother. Now, they feel, the project will lesse their others’ burd e .

The studne ts explai edn that they face lot of dnifculty comi g to school dnue to heavy trafc a dn polluto .

Sig boardns at worksites helpi g them to be cautous. Also, they otcedn, security

perso s dnivert g the vehicle ridners to be cautous at some sites.

They wa tedn the school to dno such se sitzato programmes regularly.

Prese tato a dn dniscussio o 24 x 7 water supply project a dn roadn safety for Studne ts at

Madnhavdnhara, GVMC

File No.INC02/10/2019-PMU-VCIC

D. Appendix – Environmental Monitoring

Results

APIIC- 03

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

APIIC04

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

File No.INC02/10/2019-PMU-VCIC

VCICDP_2nd SEMR july-dec 2018 log sheet.docx

1

SOUTH ASIA REGIONAL DEPARTMENT SAUW Semi-Environmental Monitoring Report Log Sheet

Project title: Visakhapatnam Chennai Industrial Corridor Development Program (VCICDP) – Project 1

Loan Number: Project Number: 48434

Overall Project and Objectives

Approved Categorization

Category A Category C

Category B ✓ FI

Loan Effectivity Date: Frequency of Reporting

Project Officer Project Analyst

Reporting Year 2018 Coverage Period

✓ July to December

Dates PMU submission to ADB 3 March 2019 ADB comment submission to PMU

18 March 2019

Item Findings in the SEMR Comments Action/s Required Response by PMU

A. Project Safeguards Team (check loan agreement and PAM requirements)

PMU1 PMU has appointed a safeguards officer currently looking at both environmental and social safeguards.

PMU to confirm if a separate environment officer is being appointed.

Provide timelines for such appointment.

PIU2 PIU has appointed Environmental officers,

The details and co-ordinates for the PIU designated environment officers are included in the SEMR.

Nil

Consultants PMSC Environmental Specialist has been mobilized.

The co-ordinates are included in the SEMR

Nil

Others (e.g. auditor, external monitoring team, etc)

Not applicable as there is no requirement of external monitoring for Category B projects.

NA Nil

B. Overall Project and Subproject Description (summarize number and type of packages)3

Number of Packages with civil works (check if consistent with latest procurement plan)

11 packages with Civil works VCICDP-APIIC/03 VCICDP-APIIC/04

A brief summary of key environmental issue associated with the civil

To be included in next SEMR

1 PMU – project management unit 2 PIU – project implementation unit 3 DB/DBO – design-build or design, build, and operate or where contractor will finalize the detailed engineering design; civil works contract – enough details of the package is known and used as basis for bid/contract’s Technical Specification

Item Findings in the SEMR Comments Action/s Required Response by PMU VCICDP-APRDC/01 VCICDP-APRDC/04 VCICDP-APRDC/05 VCICDP-APRDC/06 VCICDP-GVMC/02 VCICDP-APTransco/01 VCICDP-APTransco/03 VCICDP-GVMC/02 UCCRTF/ 05

works for each package may be included.

Number of DB/DBO packages and status (see footnote 3)

2 Packages of DBO VCICDP-APIIC/01 UCCRTF/ 06

Please elaborate requirements for design approvals if any.

To be included in next SEMR.

Number of civil works packages and status (see footnote 3)

4 packages under construction VCICDP-APIIC/03 VCICDP-APIIC/04 VCICDP-APTransco/01 VCICDP-APTransco/03

Packages awarded but construction not started VCICDP-APIIC/01 VCICDP-APRDC/01

Rest of the packages are under bidding process

Status of works included in the SEMR.

Nil

IEEs cleared for awarded packages?

Yes Updated IEEs uploaded at ADB website

To be uploaded at project websites

Safeguard documents disclosed on project website?

Yes Complied Nil

SEMR information on package-wise implementation phase (bidding, on-going, construction, completed, under operation, others)

Yes Included in SEMR Nil

C. Status of compliance with statutory clearances (check IEE for the complete list, summarize the findings for each package – obtained/under application and if obtained, specify validity period)

Environmental Clearance (EC) EC obtained for VCICDP-APIIC/01 VCICDP-APIIC/03 VCICDP-APIIC/04

Included in the SEMR Nil

Forest Clearance Not application to any sub-project

Not applicable Tree cutting permit will be obtained as required.

To include tree cutting permit for APRDC/01.

No Objection Certificate/Letter Noc Obtained for VCICDP-APIIC/01 VCICDP-APIIC/03 VCICDP-APIIC/04

Included in SEMR Nil

Site location clearance Yes Included in SEMR Nil

Permit/Consent to Construct (or equivalent)

Yes Included in SEMR Nil

Item Findings in the SEMR Comments Action/s Required Response by PMU

Permit/Consent to Operate (or equivalent)

This will be applied as applicable.

To be included as and when required

To be included as and when required

Road-cutting permit Not applicable to any sub-project under implementation presently.

To be included as and when required

To be included as and when required

Utilities shifting permit Utility shifting is not required for the present projects under construction. For other project utility shifting permission will be obtained from the relevant department and it will reported in next SEMR.

To be included as and when required

To be included as and when required

Tree-cutting permit Tree cutting permission will be obtained for VCICDP-APRDC/01 before construction and reported in next SEMR.

To be included To be included

Others (specify)

D. Status of Compliance with loan covenants (verify items in SEMR with project loan agreement)

Procurement of goods, works and consulting services (Schedule 4, Item 7)

Complied Provided in SEMR

Safeguards environment (Schedule 5, Item 5)

Complied Provided in SEMR

Human and financial resources to implement safeguards requirements (Schedule 5, Item 9)

Complied Provided in SEMR

Safeguards-related provisions in bidding documents and works contracts (Schedule 5, Item 10)

Complied Provided in SEMR

Safeguards monitoring and reporting (Schedule 5, Item 11)

Complied Provided in SEMR

Prohibited list of investments (Schedule 5, Item 12)

Complied Provided in SEMR

Labor standards, health and safety (Schedule 5, Item 13)

Complied Provided in SEMR

E. Contractors Compliance with Environmental Safeguards Requirements

Appointment of Environment, Health and Safety (HSE) and/or nodal person

Complied Details to be included in the SEMR

To be provided in next SEMR

-

Submission of site-specific EMPs Complied - -

Item Findings in the SEMR Comments Action/s Required Response by PMU

Submission of SEMP implementation report (specify in comments frequency – daily, weekly, monthly or quarterly basis)

Complied monthly Included in SEMR Details on implementation status may be provided in next SEMR

-

Site verification by PMU, PIU, or consultants (verification report should be attached to the SEMR)

Complied Verification done, and photographs of site verification will be included.

Photographs to be included in SEMR

To be included in SEMR -

SEMR compliance matrix on mitigation measures implementation (matrixes are based on approved SEMPs)

Included and complied Provided in SEMR Nil

Other information - -

F. Environmental Monitoring based on EMP

Rationale

Parameters to be monitored are commensurate to the impacts, mitigation measures, and project/subproject/package

Complied Test results / Provided in SEMR

Sampling locations identified and appropriate

Complied Provided in SEMR

Sampling frequency identified and appropriate

Complied Provided in SEMR

Sampling collection and analysis are in accordance with internationally-accepted practices

Complied Provided in SEMR

Standards and performance indicators are compliant with ADB SPS requirements4 (provide justification if less stringent standards are used)

Complied Provided in SEMR

G. Environmental monitoring results (narrative based on presented results)

Visual inspection (refer to EMP tables in the IEE where visual inspections are required to determine if there are environmental impacts)

Air quality results In compliance with regulatory standards

Included in SEMR

4 ADB SPS (Appendix 1 para 33) requires projects to apply pollution prevention and control technologies and practices consistent with international good practices as reflected in internationally recognized standards such as the World Bank Group’s Environmental, Health and Safety Guidelines (https://www.ifc.org/ehsguidelines). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When host country regulations differ from these levels and measures, the borrower/client will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the borrower/client will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented ADB SPS.

Item Findings in the SEMR Comments Action/s Required Response by PMU

Water quality results In compliance with regulatory standards

Included in SEMR

Noise level results In compliance with regulatory standards

Included in SEMR

Others

H. Consultations and/or FGDs during the reporting period

Number

Reason/s for consultations/FGDs 3 FGD conducted Photographs to be provided To be provided

Number of participants No of participants 41,23 and 45

Included Nil

Number of female participants Segregated data not reported

Female/Male segregated data to be provided

To be provided

I. Trainings, Workshops, Seminars during the reporting period

Number SEMR report conducting awareness training for contractors and PIUs

Details / Photographs provided

Nil

Topics Provided Sample training material / presentation slides may be included as Annex

Number of participants Provided Nil

Number of female participants To be provided To be included in next SEMR

J. Grievance Redress Mechanism

GRM per PAM or IEE/EARF established

Yes No reported grievances

GRM notified via publication or notice boards

Yes No reported grievances

GRM members identified Yes No reported grievances

GRM members have capacity to address project-related complaints (detailed information on capacity development of GRM members such as trainings, workshops, briefings, etc should be attached in the SEMR)

Yes No reported grievances

Number of meetings conducted (attach minutes of the meeting)

K. Complaints Received (detailed information on nature of complaints, summary and status of resolution)

Number of complaints Nil Not reported for this period.

Nature (provide summary of issues/concerns)

Nil Not reported for this period

Status of resolution NA NA

L. Summary of Issues and Corrective Actions

Major issues/concerns (specify) NA NA

Item Findings in the SEMR Comments Action/s Required Response by PMU

Corrective Action to be implemented, timeline, responsible person/s, and budget are clearly specified

NA NA

M. Status of Corrective Action Plan from Previous Reporting Period (list all and provide status)

Nil

N. Appendixes

Photos Photographs will be provided

Photographs To be provided To be included

Summary of consultations Provided

Copies of environmental clearances and permits

Provided in the SEMR Included as Annex in SEMR Nil

Site EMPs Provided Included in SEMR Nil

Checklists Provided Included in SEMR Nil

Others

O. Review and clearance for disclosure

Reference

Name Date

Reviewed by ANIK AJMERA 18 March 2019

Noted by

Response to ADB comments by:

Status/Remarks 1. Recorded as submitted

2. Send comments to PMU for response to comments