48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates...

38
Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 48373-007 October 2019 Part B: Annexures Period: October 2018 – December 2018 IND: Bihar New Ganga Bridge Project Submitted by Bihar State Road Development Corporation Limited, Patna

Transcript of 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates...

Page 1: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 48373-007 October 2019 Part B: Annexures Period: October 2018 – December 2018

IND: Bihar New Ganga Bridge Project Submitted by Bihar State Road Development Corporation Limited, Patna

Page 2: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

107

Page 3: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

108

APPENDIX 4: ENVIRONMENT MONITORING REPORT

Page 4: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

109

Page 5: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

110

Page 6: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

111

Page 7: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

112

Page 8: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

113

Page 9: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

114

Page 10: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

115

APPENDIX 5: CONSENT TO ESTABLISH FOR BATCHING PLANT

Page 11: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

116

Page 12: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

117

Page 13: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

118

Page 14: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

119

Page 15: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

120

Page 16: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

121

APPENDIX 6: CONSENT TO OPERATE FOR BATCHING PLANT

Page 17: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

122

Page 18: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

123

Page 19: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

124

Page 20: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

125

Page 21: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

126

Page 22: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

127

APPENDIX 7: LIST OF SICK PATIENT DURING THE PERIOD OCTOBER-DECEMBER 2018

Raghopur Sl. No. Date Workman name Age Company Name Designation Illness Details

1. 01.10.18 Santosh KumarYadav 23 R.S.B.Ent. Helper Loose motion

2. 05.10.18 Mithlesh Sharma 34 R.R.B.Engg. Fitter Abdominal Pain with Acidity

3. 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder

4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

5. 20.10.18 Ramchandra 32 Bhangal const. Crane Operator Fever & Loose motion

6. 29.10.18 Shiv NathChamar 35 Daewoo-L&T JV Carpenter Indigestion & vomiting

7. 31.10.18 Ravi Kumar 25 Mark Facility Supervisor Gastroenteritis

8. 01.11.18 Jun Bahadur pun 38 Daewoo-L&T JV Forman Rhinitis with Throat Infection

9. 03.11.18 Sanjay Kumar 51 Daewoo-L&T JV Sr.Forman Fever& Cough

10. 09.11.18 Panne Saran Diwedi 27 Daewoo-L&T JV Civil Forman Cough & Cold

11. 15.11.18 Sanjay vishwakarma 22 Javed Akhtar Fitter Abdominal Pain

12. 21.11.18 Ashish Das Gupta 42 Daewoo-L&T JV Engineer Fever

13. 24.11.18 Ramchandra 32 Bhangal Const. Crane Operator Cough & cold

14. 27.11.18 Pravin Kumar 23 MaaLaxmiEngg. Helper Loose motion

15. 28.11.18 Prakash Kumar 24 Daewoo-L&T JV Steel Fitter Cold & Cough

16. 30.11.18 Shah Alam 31 Bhangal Const. Crane Operator Fever with cough

17. 01.12.18 Deepak KumarJha 32 Tara chand Crane Operator Abdominal pain

18. 05.12.18 Ramesh sah 32 Sunny Const. Fitter Constipation

19. 11.12.18 Md.Iftekhar khan 36 Arvind kumar Helper Fever & Cold

20. 19.12.18 ShastriMahto 41 Manoj Enterprises Helper Cough

21. 22.12.18 AkleshKumarPandey 22 RajmataEnterprises Helper Fever with bodyache

22. 27.12.18 K.C.Pandey 48 Daewoo-L&T JV Scaffolder inspector Cough & Cold

Page 23: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

128

Zero Point & Sabalpur

S. No. Date Workman Name Age Company Name Designation Illness Details

1. 06.09.2018 Md. DaudIbrahid 30 RSB Enterprises Helper Headache

2. 16.09.2018 Ranish Kumar 22 V S Engineering Helper Cough

3. 22.09.2018 Nirpendra Kumar Singh 26 RSB Enterprises Supervisor Fever

4. 29.09.2018 Guddu Kumar 24 SANTOSH KUMAR Helper Fever

5. 30.09.2018 Santosh Kumar 23 RBS Enterprises Helper Headache

6. 05.10.2018 Alok Singh 36 ADWIK Security Guard Fever

7. 09.10.2018 Sailesh Singh 19 L&TNAPS Driller Cough

8. 13.10.2018 Saroj Kumar 35 V S ENGG Carpenter Bodyache

9. 22.10.2018 Manish Pandey 19 L&TNAPS Security Guard Dysentery

10. 27.10.2018 Sunil Singh 40 ADWIK Carpenter Bodyache

11. 02.11.2018 Manish Kumar Jha 20 L&T Security Guard Abdominal Pain

12. 08.11.2018 Vishwajeet 27 ADWIK Sweeper Cough

13. 18.11.2018 PremRanjan Kumar 43 JAI KISHORE Helper Fever

14. 22.11.2018 BabuPaswan 30 RSB ENT Helper Fever

15. 27.11.2018 Binay Singh 39 ADWIK Carpenter Cough

16. 01.12.2018 Pappu Kumar 20 L&TNAPS Store Asst. Fever

17. 05.12.2018 Santosh Kumar 32 RSW Helper Fever

18. 09.12.2018 Sunil Kumar 20 RSW QA/QC Asst. Cough

19. 12.12.2018 Dharmendra Kumar 48 RSW Trailer Driver Fever

20. 18.12.18 Munna Kumar 26 SAI CONST Engg. Bodyache

21. 25.12.2018 PintuManjhi 31 L&T Cook Helper Dysentery

22. 31.12.2018 Arun Mandal 50 WELL SERVE Helper Bodyache

Page 24: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

129

APPENDIX 8: TREE CUTTING PERMISSION FOR SABALPUR & RAGHOPUR

Page 25: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

130

Page 26: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

131

Page 27: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

132

Page 28: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

133

Page 29: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

134

APPENDIX 9: CGWA APPLICATION FOR GROUND WATER WITHDRAWL

Page 30: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

135

Page 31: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

136

APPENDIX 10: STP (Sewage Treatment Plant)

MBBR PROCESS; MOVING BED BIO REACTOR PROCESS

1. Collection Tank: The Raw sewerage is collected here and then goes to the MBBR tank for further processing. 2. The MBBR Tanks: These are also called aeration tanks and diffused air through blowers is given in the tank. We also put Fab media in these tanks so these tanks are also called FAB tanks. The blowers provide the oxygen in the water which helps in creating bacterial which keeps consuming the human waste. The FAB media works has a home for the bacteria where they stay and keep increasing day by day. 3. Settling tanks: This is called the tube settler tank. When partially clear water from the Fab tanks enter the tank which has a funnel type shape the remaining sludge (Most of the sludge is eaten by bacteria in MBBBR tanks) is settled in the bottom and taken to the sludge holding tank with the help of sludge holding pump .The pure water on the top of the settling tank is automatically transferred to the clear water tank of filter feed tank. 4. Tertiary unit: The water from the clear water tank is further taken to Multi Grade filter and activated carbon filter. The Multi grade filter which consists layers of Pebbles, gravels and silex sand polisheds the water and does not allow the suspended matter to go further. The Multi grade filter is operated through a multiport valve or Butter fly valves which backwashed and rinse the suspended matter trapped in the Multi grade filter. The water then goes through the Activated carbon filter which reduces the bad smell of the water .It also reduces the COD(chemical oxygen demand) of the water. 5. Treated water tank: The treated water tank is the collection tank for the treated water. It is taken for reuse or safe disposal of this water. 6. Filter Press or Sludge De-Watering System: The sludge collected in the sludge holding tank is taken to the filter press. It is a hand hydraulic system where the sludge is squeezed to the level that it is completely dry. The filter press converts it in cake shape. These cakes are natural fertilizers and can be used for horticulture purpose.

Note: Currently STP (capacity-87 KLD) at Zero Point and Raghopur(capacity 273 KLD) are in functional stage.

Page 32: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

137

APPENDIX 11: ENVIRONMENTAL CLEARANCE FROM SEIAA, BIHAR

Page 33: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

138

Summary of Projects:-

Name of Project

Green Field Six Lane Extradoses Cable Bridge over river Ganga near KachhiDargah in District Patna on NH-30 near Bidupur in District Vasihali on NH- 103 (Bihar). Length of the project 22.76 Km. includes 9.76 km. long main bridge.

S. No in the Schedule 8 (b)

Project Cost $832 million

Location The proposed bridge across Ganga river froDeedarganj on NH-30 to chakSikandar in Vaisahli district on NH-103, consisting of six lane bridge structures of the 9.760 Km, approach viaduct and roads of 1.5 km from South and 8.5 Km from Noth, tolling and serving faculties, and windering 3 Kilometer of NH-103. The proposed location of the bridge is about 10 Km downstream of existing Mahatama Gandhi Setu in Patna. Start Location: Sabalpur (near KacchiDargah) Latitude:- 250 34’ 02.24” N Longitude:- 850 15’ 07.86” E

End location: Sarmastpur (near Bidupur), Latitude:- 250 41’ 17.82” N

Longitude:- 850 22’ 49.65” N

Plot/Survey/Khasra No.

Sl. No. Village Name Thana No.

1. Sabalpur 44

2. NasirpurTajpur 40

3. Rustampur 394

4. HimmatpurDiara 393

5. JamalpurChak Shankar Ganga Prasad Diyara

345

6. JafrabadDih 342

7. Saifabad 347

8. Karampur 364

9. JahangirpurFuli 381

10. Madhurpur 374

11. SadullahpurChakFarid 375

12. BishnupurKishundas @ MajlispurChakGangadhar

379

13. Chak Said Ali@ Darwa 376

14. BishnupurKishundas @ Majlispur 377

15. Mathura SultanpurPachkatiya 423

16. DilwarpurGowardhan 424

17. Kanpur Pakri 429

Page 34: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

139

18. Kalyanpur 434

19. BishnupurBishunath @ Teliya 268

20. Samastipur 269

Village The proposed road bridge traverses along 20 villages of the Patna and Vaishali District.

District Patna and Vaishali

State Bihar

Nearest Railway Station, airport along with distance in Kms

Nearest Railway Station:- Patna Saheb- approx. 5 Km (From Start location) Nearest Airport:- Patna – 16.50 Kms (From Start location)

Name of Applicant Bihar State Road Development Corporation Ltd.

Registered Address Central Mechanical Workshop Campus, Near Patna Airport, Patna- 800 014

1. SPECIFIC CONDITIONS:-

I. Construction Phase

(i) All necessary clearance as applicable to the project shall be obtained from the

concerned authorities before initiating the project.

(ii) Necessary mitigative measure against adverse impact to the water bodies that

are to be affected shall be provided.

(iii) There shall be no disposal of solid and liquid wastes into the water body. The

solid waste shall be properly collected, segregated and disposal as per the

provision of Solid Waste (Management and Handling) Rules, 2000.

(iv) Installation and operation of DG set, if any shall comply with the guidelines of

CPCB.

(v) Provision shall be made for the housing of construction labour with all necessary

infrastructure and facilities such mobile toilets, mobile STP, safe drinking water,

medical health care, etc. The housing may be in the form of temporary structures

to be removed after the completion of the Project.

(vi) All the top soil evacuated during construction activities should be stored for use

in horizontal/landscape development within the project site.

(vii) Disposal of muck during construction phase should not be created any adverse

effort on river and the neighbour communities and the disposal off taking the

necessary precautions for general safety and health aspects of people, only in

approved sites with the approval of competent authority.

(viii) Vehicles hired for bringing construction material to the site should be in good

condition and should have a pollution check certificate and should conform to

the applicable air and noise emission standards and should be operated only

during non-peak hours.

(ix) Under the provisions of Environment (Protection) Act, 1986, legal action shall

be initiated against the project proponent if it was found that construction of the

project has been started without obtaining environmental clearance.

(x) Necessary permission for tree felling, if any, from the concerned department

shall be obtained before commencement of the project work and copies of the

same shall be submitted to this Office Minimum of three times the number of

trees to be cut shall be planted. It shall be ensured that the trees planted as a part

Page 35: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

140

of the afforestation shall be looked after by the proponent. Tree plantation shall

be of the same species/local species and survival shall be monitored

Transplantation of trees shall be carried out wherever possible.

(xi) During construction phase noise pollution should be minimized in the river for

the safety of the Gangetic dolphins because they are very sensitive to noise

pollution

(xii) On both flanks of the bridge fencing at suitable height by proper mesh should be

provided so that garbage and other unwanted materials are not thrown in the

Ganges.

(xiii) Number of pillars should be minimum so as to minimise siltation in Ganga,

ofcourse without compromising with structural design.

II. Operation Phase.

(i) Noise barriers shall be provided at appropriate locations particularly in the areas

where the alignment passes through inhabited areas so as to ensure that the noise

levels do not exceed the prescribed standards.

2. General Conditions:

(i) In the event of any change in the project profile, a fresh reference shall be made

to SEIAA, Bihar.

(ii) SEIAA reserves the right to revoke this clearance, if any, of the conditions

stipulated are not complied with to the satisfaction of SEIAA.

(iii) SEIAA may stipulate any additional conditions subsequently, if deemed

necessary, for environmental protection, which shall be complied with.

(iv) Full support should be extended to the officers of Bihar State Pollution Control

Board by the project proponents during their inspection for monitoring purposes.

(v) All other statutory clearances shall be obtained, as applicable by project

proponents from the respective competent authorities.

(vi) The project Proponent should advertise in at least two Newspapers widely

circulated in the region, one of shall be in the vernacular language informing that

the project has been accorded Environmental Clearance and copies of clearance

letter are available with the Bihar State Pollution Control Board.

The Project proponent shall also submit six monthly reports on the status of compliance of the stipulated condition including results of monitored data (both in hard copies as well as the stipulated condition including results of monitored data(both in hard copies as well as by e-mail) to SEIAA, Bihar and regional office, Ranchi.

Page 36: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

141

APPENDIX 12: BOCW REGISTRATION

Page 37: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

142

APPENDIX 13: LABOUR LISCENCE FROM GOVERNMENT OF BIHAR

Page 38: 48373-007: Bihar New Ganga Bridge Project€¦ · 06.10.18 Hari Kishor Yadav 33 Tiwari Associates Fitter Frozen Shoulder 4. 13.10.18 SonuKumar 20 Spark vidyut R.O.Operator Pherengitis

Environmental Monitoring Report (October-December 2018)

143