    WORK STUDY

  • 8/11/2019 47 52 Work Study

    2/24

    Definition

    Work study is a generic term for those techniques

    which are used in the examination of human work

    in all its contexts, and which lead systematically to

    the investigation of all the factors which affect theefficiency and economy of the situation being

    reviewed, in order to effect improvement.

    Work study assumes that there is only one best

    way to accomplish a task.

  • 8/11/2019 47 52 Work Study

    3/24

    Work study is used to associate two sets of

    techniques:

    1. Method study

    2. Work measurement

    (Work measurement is also known as time study)

  • 8/11/2019 47 52 Work Study

    4/24

    Method study

    It is concerned with the way in which work

    is done.

    It is used to simplify the way to accomplish

    a work and to improve the method of

    production.

    It results in a more effective use of

    material, plant, equipment and manpower.

  • 8/11/2019 47 52 Work Study

    5/24

    Work measurement

    Work measurement is concerned with the

    value or work content of the task itself. It is

    used to determine how long it should take

    to carry out the job.

    It provides a yardstick for human effort.

  • 8/11/2019 47 52 Work Study

    6/24

  • 8/11/2019 47 52 Work Study

    7/24

    Steps in work study

    Work study consists of an eight step process.These are:

    Step 1: Identify and select the job or process to

    be studied.Step 2: Use direct observation for recording

    everything that happens, using the most

    effective recording techniques. Ensurethat the date are in the most convenient

    form for further analysis.

  • 8/11/2019 47 52 Work Study

    8/24

    Step 3: Data and facts obtained in the previous

    step are to be examined and analysed.

    Step 4:Develop the most economical methodunder prevailing circumstances.

    Step 5:Measure the quality of work involved in

    the method defined by usingappropriate methods of measurement.

    Calculate standard time for doing it by

    adding rest allowance. Thus, determinethe work content.

  • 8/11/2019 47 52 Work Study

    9/24

    Step 6:Define the best method and related

    time.

    Step 7:Install the new method and trainpersonnel so that it conforms to the

    agreed standard practices.

    Step 8:Maintain the standard practice by aproper control mechanism.

    KeywordSelect-Record-Examine-Develop-Evaluate-Define-install-Maintain

  • 8/11/2019 47 52 Work Study

    10/24

    Recording methods

    1. Flow type diagram

    2. Multiple Activity chart

    3. Process chart4. SIMO (Simultaneous Motion Chart)

    5. Memo motion

    6. Cycle graphic

  • 8/11/2019 47 52 Work Study

    11/24

    Flow type diagram

    These diagrams are the pictorial representation of the flow of

    material in the factory while different sequence of operation,

    transportation, inspection, delay and storage takes place.

    There are three types of flow diagram

    i. Flow diagram

    ii. String diagramiii. Travel chart

  • 8/11/2019 47 52 Work Study

    12/24

    12

    Flow diagram

    It is a floor-planshowing the path of travel of the

    operator or the material, through the plant.

    It also indicates the direction of travel by means

    of arrows, drawn on the diagram.

  • 8/11/2019 47 52 Work Study

    13/24

  • 8/11/2019 47 52 Work Study

    14/24

    14

    String diagram

    It is a scale plan or model on which a thread or

    string is used to trace and measure the path of

    workers/ materials during a specified sequence ofevents.

    Length of the thread/string measures the distancemoved.

  • 8/11/2019 47 52 Work Study

    15/24

  • 8/11/2019 47 52 Work Study

    16/24

    16

    Travel chart

    It is a tabular record of quantitative data about movement

    of workers/materials/equipment between any number of

    places over a given period of time

    It gives the details of volumetric data during travel between

    work area.

  • 8/11/2019 47 52 Work Study

    17/24

  • 8/11/2019 47 52 Work Study

    18/24

    18

    The outline flow process chart

    It uses two symbols:

    &

    It provides an overall picture of the process / job / task.

    Primarily it is used to show the sequence of operations &

    inspections for a manufacturing or an assembly kind ofjobs.

  • 8/11/2019 47 52 Work Study

    19/24

  • 8/11/2019 47 52 Work Study

    20/24

    Flow process chart

    It helps in setting out the sequence of the flow

    of a product or a procedure by recording all

    events under review using appropriate

    process chart symbols. It covers symbols foroperations, inspection, storage, delay and

    transportation.

  • 8/11/2019 47 52 Work Study

    21/24

    21

    Process chart symbolsASME has recommended FIVE standard symbols to be used on

    Process Charts, given below:

    1. OPERATION

    2. INSPECTION

    3. TRANSPORTATION

    4. DELAY

    5. STORAGE

  • 8/11/2019 47 52 Work Study