46-08436

32
06/14/22 1 46-08436

description

46-08436. April 5, 2010 Upper Big Branch Mine Disaster – Ongoing January 18, 2011 Update. Status of Underground Investigation Interviews Conducted MSHA Personnel Involved Events Leading Up to Explosion Shift Prior to Explosion April 5, 2010: Longwall – Day Shift - PowerPoint PPT Presentation

Transcript of 46-08436

Page 1: 46-08436

04/20/23 1

46-08436

Page 2: 46-08436

04/20/23 2

April 5, 2010 Upper Big Branch Mine Disaster – Ongoing

January 18, 2011 Update

• Status of Underground Investigation• Interviews Conducted• MSHA Personnel Involved• Events Leading Up to Explosion• Shift Prior to Explosion• April 5, 2010: Longwall – Day Shift• Location of Deployed SCSR Units• Ventilation Issues• Fuel• Possible Ignition Sources

Page 3: 46-08436

04/20/23 3

Status of Underground Investigation

• Accident Investigation began April 12, 2010.– Underground Investigation began June 25,

2010.• Nearing Completion• Recent Delays

– Pumping Water from TG 22 and HG 22– Establishing Water to the Shearer

Page 4: 46-08436

04/20/23 4

Interviews Conducted

• 261 Individuals have been interviewed as of January 18, 2011

• 18 Individuals exercised their 5th Amendment Rights

• The investigation team is continuing interviews

Page 5: 46-08436

04/20/23 5

MSHA Personnel Involved

– 105 MSHA Investigation Personnel have been utilized during the on-site investigation Type and Number of Teams Utilized

– 10 Mine Dust Survey Teams– 7 Mapping Teams– 3 Electrical Teams– 1 Ventilation Team– 1 Geology Team– 1 Flames and Forces Team– 1 Evidence Collection Team– Inspection Activities Team

– An additional 45 Technical Support Personnel were utilized to perform testing and other technical activities

– Also 25 EFS, 7 SM, and 9 EPD Personnel were utilized to guard the three portals during the investigation

Page 6: 46-08436

04/20/23 6

Events Leading Up to Explosion

Page 7: 46-08436

04/20/23 7

1 North Development

• As per the mine map, originally developed as Room and Pillar entries

• Converted to L/W Panel

• 1 North HG Developed ground controls issues

Page 8: 46-08436

04/20/23 8

Easter Weekend

• C/M miner sections did not produce coal on Easter weekend

• Longwall produced coal on Saturday (4/3/10)

• Entire Mine idle on Sunday (4/4/10)

Page 9: 46-08436

04/20/23 9

Shift Prior to Explosion

Page 10: 46-08436

04/20/23 10

4-5-2010 L/W 3rd Shift (Midnight Shift)

• Maintenance Shift Only (No Production)

• Various items remain under investigation

Page 11: 46-08436

04/20/23 11

April 5, 2010Longwall - Day Shift

Page 12: 46-08436

04/20/23 12

UBB Longwall Day Shift Summary

• First Call Out at 7:30 a.m.– Longwall ran until 11:00 a.m. and had made 2 passes– Longwall was down from approximately 11:00 a.m. to

as late as 2:15 p.m. – Longwall may have been tested following repairs

between 1:30 p.m. and 2:00 p.m. A total of 2.2 passes was reported.

• Shearer was down due to Lost B-Lock on Ranging Arm– B-Lock is the retainer for the hinge pin that holds the ranging

arm in place

• Call Out at 2:30 p.m.– Shearer at Shield 115 going toward tailgate

• The Pre-shift Report was called out at 2:40 p.m.

Page 13: 46-08436

04/20/23 13

Location of Deployed SCSR Units

Page 14: 46-08436

04/20/23 14

Page 15: 46-08436

04/20/23 15

Ventilation Issues

Page 16: 46-08436

04/20/23 16

UBB Ventilation Issues

•The official 75.1200 map identified by company was not up to date.

•During the mapping portion of the investigation, stopping remnants were identified and plotted on a map.

Page 17: 46-08436

04/20/23 17

Page 18: 46-08436

04/20/23 18

BeltEllis #4Ellis #5North No.4North No.5North No.6North No.7LongwallTG No.1TG No.2HG22

LEGEND: Belt needs to be rockdusted Rockdust applied to some part of belt

4/1/10 4/1/10 4/2/10 4/2/10 4/2/10 4/3/10 4/3/10 4/3/10 4/4/10 4/4/10 4/4/10 4/5/10 4/5/101st 2nd 3rd 1st 2nd 3rd 1st 2nd 3rd 1st 2nd 3rd 1st

Day Eve Mid Day Eve Mid Day Eve Mid Day Eve Mid DayElectrical No Exam No Exam ElectricalElectrical No Exam No Exam ElectricalElectrical No Exam No Exam ElectricalElectrical No Exam No Exam ElectricalElectrical No Exam No Exam ElectricalElectrical No Exam No Exam ElectricalElectrical No Exam No Exam Idle

Idle Idle Idle No Exam No Exam IdleIdle Idle Idle No Exam No Exam Idle

Electrical No Exam No Exam Idle No Exam

To Date, Belt Examination Records Indicate

Page 19: 46-08436

04/20/23 19

Fuel

Page 20: 46-08436

04/20/23 20

Methane

• Based on the analysis of the evidence collected thus far, it appears that a low Volume of Methane and/or Methane from Natural Gas provided the fuel for the initial ignition on or near the face on the tailgate side of the longwall.– No evidence to date of flame on the tailgate

end of the longwall face– No evidence to date of coking on the tailgate

end of the longwall face

Page 21: 46-08436

04/20/23 21

To date the analysis of the evidence shows that a small Methane/Methane from Natural

Gas Ignition transitioned into a Massive Coal Dust Explosion

Page 22: 46-08436

04/20/23 22

Fac

e

Post Explosion Dust Sampling Results

Page 23: 46-08436

04/20/23 23

Possible Ignition Sources

Page 24: 46-08436

04/20/23 24

Status of Electrical Testing

• All electrical components have been tested and checked for possible ignition sources.

• At this time no electrical ignition sources have been identified.

Page 25: 46-08436

04/20/23 25

Testing of Handheld Methane Detectors

Page 26: 46-08436

04/20/23 26

Introduction to the Solaris Handheld Multi-Gas Detector

• Handheld detectors were in use that recorded data.  These were the MSA Solaris Multigas Detectors.  These devices included:– a combustible gas sensor (used to detect methane), – an oxygen sensor,– a carbon monoxide sensor, and, in some cases,– an nitrogen dioxide sensor..

• A total of 3 Solaris Handheld Detectors recorded similar data– One detector was found on the longwall face– One detector was approximately 3600 feet from the longwall

(Near Mother Drive)– One detector was approximately 6000 feet from the longwall

(Near Mantrip at Crosscut 68)

Page 27: 46-08436

04/20/23 27

Testing of Solaris Handheld Methane Detectors

• The ‘Combustible Gas Sensor’ in the Solaris will respond to methane and other combustible gases.

• Once the instrument detects any combustible gas mixture equivalent to 5% of methane, the power to this sensor shuts down and the data latches at 5%.– Byproduct gases of an explosion such as Ethylene,

Acetylene, Carbon Monoxide and Hydrogen can appear on these instruments as Methane.

Page 28: 46-08436

04/20/23 28

Potential Frictional Ignition Sources

• Longwall Shearer– Worn Bits– Missing Water Sprays

• Other Ignition Possibilities

Page 29: 46-08436

04/20/23 29

Video of Tailgate Drum as it was found with 4 visible sprays missing.

(Click on Picture to Start Video Clip)

Water Pressure on Shearer is 150 PSI.

Page 30: 46-08436

04/20/23 30

Page 31: 46-08436

04/20/23 31(Click on Picture to Start Video Clip)

Page 32: 46-08436

04/20/23 32

Investigation On-Going

• Additional Investigation Activities to be Completed– Interviews– Remove HG 22 Mantrip– Verify Facts of Findings during UG

Investigation– Longwall Face will also be revisited for

various purposes