Pipe pile works (Yongnam) SC-02~100 and SC173~ SC121 at reached toe level. SW01~0115 Reached toe level. SW116 ~138, and SC101 SC120 are in progress UT test for pipe joint welding works at pipe piles T227/465, T227/466, T227/467, T227/468 done. Welding and gas cutting for pipe piles. Visual inspection for pipe pile interlock length for SW-113A completed.
Silo tank base slab - (RYOBI KISO)
Witnessed for laying of BRC & concrete casting done @ GL 4 to 5. Total vol. 35m3 with Grade 30 & concrete thickness is 300mm (10m width X 10m length).