44259126 ms-project-presentation

20
Presented by Ajai Govind G (191065) Ankita Sehjpal (191076) Khem Singh Chauhan (1910

Transcript of 44259126 ms-project-presentation

Page 1: 44259126 ms-project-presentation

Presented byAjai Govind G (191065)Ankita Sehjpal (191076)Khem Singh Chauhan (191090)

Page 2: 44259126 ms-project-presentation

Microsoft Project is a project management software program developed and sold by Microsoft

Designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads.

The application creates critical path schedules, and critical chain which can be visualized in a Gantt chart.

Available currently in two editions, Standard and Professional.

MS Project's proprietary file format is *.mpp.

INTRODUCTION

Page 3: 44259126 ms-project-presentation

HISTORY Initially proposed by Microsoft's Manager of Product

Development, Alan M. Boyd as an internal tool to help manage the huge number of software projects that were in development at any time inside the company.

The first commercial version of Project was released for DOS in 1984. Subsequent DOS versions: V2 (1985), V3 (1986) and V4 (1986)

First Windows version-1990

Macintosh version -1991

Subsequent versions-V3 (1992), V4 (1993), 1995, 1998, 2000, 2002, 2003, 2007 and 2010.

Page 4: 44259126 ms-project-presentation

GanttProject

Genius Inside

LiquidPlanner

MicroPlanner X-Pert

NavalPlan

COMPETITORS OpenProj

Open Workbench

Primavera (software)

Project.net

Basecamp (software)

Page 5: 44259126 ms-project-presentation

List each task necessary to complete a project in the order they should be performed.

Assign start and finish dates to tasks or let the program set them for you by you specifying the duration of the task.

Display the tasks graphically over a time line to get an overall view of the project.

Assign workers, contractors, and other resources to tasks and print their schedules.

Compute the hours and cost necessary to complete a task or the entire project.

Monitor a project’s progress and compare it to your original estimate.

Analyze such items as cost, hours, slack time, resource allocation, etc. using tables and graphs

PURPOSE

Page 6: 44259126 ms-project-presentation

Planning a Project

Define Goals

Develop Tasks

Establish Timeframes

Resource Availability

Organize

Page 7: 44259126 ms-project-presentation

Define the ProjectBuild the Plan

Set a start dateEnter tasks/durationsAssign resourcesLink tasksFine tune the plan

Track and ManageSet a baselineEnter actualsAdjust plan

Close Project

USING MS PROJECT

Page 8: 44259126 ms-project-presentation

The objective of the project should be defined by the

person/group that is going to manage the project.

Tasks, start times, and deadlines should be clearly

established.

DEFINING THE PROJECT

Page 9: 44259126 ms-project-presentation

BUILD THE PLAN

Page 10: 44259126 ms-project-presentation

1. Set up Project Defaults: Set working order. (Schedule from Start Date forward or Finish Date backwards) Set a start or finish date. Select/create the project calendar to use. (Controls working days and hours)

2. Enter tasks: In chronological order, enter the tasks necessary to complete the project. Set the task’s duration. When appropriate, set a task’s Start / Finish date.

3. Set Task Sequencing: Link tasks that must be completed sequentially. Do not link tasks that can be completed simultaneously.

4. Create a Resource List: Create a list of contractors, laborers, equipment rental, fees, etc. and their

corresponding rates. Set working hours for each resource.

5. Assign Resources to Tasks

6. Analyze/Reevaluate/Adjust Project

7. Document Task Progress

PURPOSE

Page 11: 44259126 ms-project-presentation
Page 12: 44259126 ms-project-presentation

SCHEDULING A TASKWhen tasks must either end on a specific date or begin on a specific

date, you can create constraints.

Page 13: 44259126 ms-project-presentation

RESOURCE MANAGEMENT

Page 14: 44259126 ms-project-presentation
Page 15: 44259126 ms-project-presentation

TRACK AND MANAGE THE PROJECT

As the project proceeds, you may wish to record its progress, noting any deviations from your planned schedule.

A baseline is a snapshot of you project before actual work begins and changes are made to the schedule.

The baseline includes task start and finish dates, resources, and costs.

Compare the actual project to the baseline.

CREATING A BASELINE

Page 16: 44259126 ms-project-presentation

The sequence of activities which have no float or slack is called the critical path.

Slack = Late Start – Early Start OR Late Finish - Early Finish

i.e. A critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project.

Any delay of an activity on the critical path directly impacts the planned project completion date.

A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path.

CRITICAL PATH

Page 17: 44259126 ms-project-presentation

When we say that an activity will take a certain number of days or weeks, what we really mean is this activity normally takes this many days or weeks. We could make it take less time, but to do so would cost more money.

Crashing is a process of expediting project schedule by compressing the total project duration.

TIME-COST TRADE-OFFS: CRASHING

• The key is to attain maximum decrease in schedule time with minimum cost.

• More resources are needed to speed-up a part of a project

• Depends on what slack is available in a non-critical activity

Page 18: 44259126 ms-project-presentation

The key to project crashing is attaining maximum reduction in schedule time with minimum cost. Quite simply, the time to stop crashing is when it no longer becomes cost effective. A simple guideline is:

Crash only activities that are critical.

Crash from the least expensive to most expensive.

Crash an activity only until:

It reaches its maximum time reduction.

It causes another path to also become critical.

It becomes more expensive to crash than not to crash.

WHEN NOT TO CRASH

Page 19: 44259126 ms-project-presentation

Identify the critical path and the corresponding tasks.

Export the work package tasks (ID and Task Name fields), the original duration (Duration field), and the original cost (Cost field) from your MS Project schedule, and open that file in Excel.

You must calculate the potential crash duration for each critical path task and the cost to crash each task.

On the Excel worksheet, add a column to calculate crash reduction, which is how many weeks you can crash each task. Crash reduction is simply the original duration minus the crash duration.

Add another column to calculate the crash cost per week, which is the crash cost divided by the crash reduction value.

CREATING A CRASH TABLE

Page 20: 44259126 ms-project-presentation