41220-013: Integrated Natural Resources and Environmental ......EHSM Environmental Health and Safety...
Transcript of 41220-013: Integrated Natural Resources and Environmental ......EHSM Environmental Health and Safety...
Initial Environmental Examination
January 2019
PHI: Integrated Natural Resources and Environmental Management ProjectRehabilitation of Ilaya to Datag Access Road in
Inabanga, Bohol
Prepared by Municipality of Inabanga, Province of Bohol for the Asian Development Bank.
II
CURRENCY EQUIVALENTS (as of 03 December 2018 Year)
The date of the currency equivalents must be within 2 months from the date on the cover. Currency unit – peso (PhP)
PhP 1.00 = $ 0.019052 $1.00 = PhP 52.4864
ABBREVIATIONS
ADB Asian Development Bank BDC Barangay Development Council BUB Bottom-Up Budgeting CNC Certificate of Non-Coverage CSC Construction Supervision Consultant CSO Civil Society Organization DED Detail Engineering Design DENR Department of Environment and Natural Resources DILG Department of Interior and Local Government DSWD Department of Social Welfare and Development ECA Environmentally Critical Area ECC Environmental Compliance Certificate ECP Environmentally Critical Project EHSM Environmental Health and Safety Manager EIA Environmental Impact Assessment EIS Environmental Impact Statement EMB ESS
Environmental Management Bureau Environmental Safeguards Specialist
GAD Gender and Development IEE Initial Environmental Examination INREMP Integrated Natural Resources and Environment Management Project IP Indigenous People IROW Infrastructure Right of Way LGU Local Government Unit LPRAT Local Poverty Reduction Action Team MDC Municipal Development Council NAAQ National Ambient Air Quality Guidelines NCB National Competitive Bidding NECA Non-Environmental Critical Area NECP Non-Environmental Critical Project NPCO National Project Coordinating Office NRIMP National Road Improvement and Management Program NRM Natural Resources Management OMC Overhead, Contingencies and Miscellaneous and Contractor’s PAGASA Philippine Atmospheric Geophysical and Astronomical Services
Administration PDR Project Description Report PMIC Project Management Implementation Consultant PPMO Provincial Project Management Offices PMO Project Management Office PMU Project Management Unit
iii
POs Peoples’ Organizations PSA Philippine Statistics Authority RC Reinforced Concrete RCPC Reinforced Concrete Pipe Culvert RPCO Regional Project Coordinating Offices REA Rapid Environmental Assessment ROW Right of Way SB Sangguniang Bayan SBD Standard Bidding Document SPMU Sub-Project Management Unit SPS SSS
Safeguard Policy Statement Social Safeguards Specialist
TA Technical Assistance TOR Terms of Reference
iv
WEIGHTS AND MEASURES
˚C – degree centigradeha – hectarekm – kilometerm – meter
m asl – meter above sea levelmm – millimeter
mg/L – milligram per litermg/Nm3 – milligram per normal cubic meter
ppt – parts per thousandμg/Nm3 – microgram per normal cubic meter
µS/cm – microSiemens/cm% – percent
NOTE
In this report, "$" refers to United States dollars.
This initial environmental examination is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,
and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgment as to the legal or other status
of any territory or area.
v
TABLE OF CONTENTS
I. EXECUTIVE SUMMARY .................................................................................................... 1 II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK ............................................... 2 A. Environmental Clearance Requirements ........................................................................... 2
1. Government Environmental Laws, Regulations and Guidelines ................................... 2 2. ADB Environmental Assessment Requirements ............................................................ 5
III. DESCRIPTION OF THE PROJECT ................................................................................... 6 A. Overview ............................................................................................................................. 6 B. Project Location .................................................................................................................. 6 C. Project Rationale ................................................................................................................ 7 D. Project Development Plan .................................................................................................. 8
1. Project Components ....................................................................................................... 8 2. Description of the Project Phases .................................................................................. 8
E. Manpower Requirements ................................................................................................... 9 F. Project Cost ...................................................................................................................... 10 G. Project Duration and Schedule ........................................................................................ 11 IV. DESCRIPTION OF THE ENVIRONMENT ....................................................................... 12 A. Elevation and Slope .......................................................................................................... 12 B. Geology............................................................................................................................. 14 C. Soils .................................................................................................................................. 14 D. Water Quality .................................................................................................................... 16 E. Land Classification ........................................................................................................... 16 F. Land Cover and Land Use ............................................................................................... 17 G. Climate .............................................................................................................................. 18
1. Baseline Climate ........................................................................................................... 18 2. Climate Scenario for Bohol in 2020 and 2050.............................................................. 19
H. Hydrology .......................................................................................................................... 21 I. Natural Hazards ................................................................................................................ 21 J. Biological Environment ..................................................................................................... 22
1. Flora .............................................................................................................................. 22 2. Fauna ............................................................................................................................ 23
K. Socio-Economic Conditions ............................................................................................. 24 1. Population ..................................................................................................................... 24 2. Water Supply................................................................................................................. 24 3. Indigenous Peoples and People’s Organization .......................................................... 24 4. Education ...................................................................................................................... 24 5. Health and Sanitation ................................................................................................... 25 6. Housing ......................................................................................................................... 25 7. Electricity ....................................................................................................................... 25 8. Communication ............................................................................................................. 25 9. Income and Expenditure ............................................................................................... 25 10. Tourism ...................................................................................................................... 25 11. Commerce and Industry ............................................................................................ 26 12. Road and Transportation .......................................................................................... 26
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ............ 27 A. Pre-Construction ............................................................................................................... 29
1. Confirmation of no required resettlement, relocations, and compensation ................. 29 2. Identification and prioritization of road section where re-gravelling will be done ........ 29 3. Preparation of detailed engineering designs and programs of work ........................... 29 4. Recruitment of workers ................................................................................................. 30
B. Construction ...................................................................................................................... 30 1. Construction materials acquisition, transport access, and storage system ................. 30
vi
2. Clearing and removal of obstructions ........................................................................... 30 3. Soil erosion ................................................................................................................... 30 4. Ground surface leveling and gravelling of existing road .............................................. 31 5. Civil works (Concrete Pavement) ................................................................................. 31 6. Implementation of noise and dust control measure ..................................................... 31 7. Dust and noise from borrow pits ................................................................................... 32 8. Implementation of spoil management and control measure ........................................ 32 9. Solid and liquid construction waste management system ........................................... 32 10. Water quality ............................................................................................................. 32 11. Construction drainage system .................................................................................. 33 12. Workers health, safety and hygiene ......................................................................... 33 13. Traffic safety and management ................................................................................ 34 14. Ecological environment (Flora and Fauna) ............................................................... 34 15. Damaged to properties .............................................................................................. 34 16. Concrete washout ..................................................................................................... 34 17. Use of Hazardous Substances ................................................................................. 35 18. Public safety .............................................................................................................. 35
C. Operation and Maintenance (O&M) Phase ...................................................................... 35 1. Operation of upgraded access road ............................................................................. 35
VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION ................... 36 A. Stakeholder Consultations ............................................................................................... 36 B. Information Disclosure ...................................................................................................... 39 VII. GRIEVANCE REDRESS MECHANISM ........................................................................... 39 VIII. ENVIRONMENTAL MANAGEMENT PLAN ..................................................................... 41 A. Implementation Arrangements ......................................................................................... 41 B. Environmental Mitigation .................................................................................................. 43 C. Environmental Monitoring ................................................................................................. 56 IX. CONCLUSION AND RECOMMENDATIONS .................................................................. 59 A. Conclusion ........................................................................................................................ 59 B. Recommendations ............................................................................................................ 60 APPENDICES .......................................................................................................................... 62
vii
LIST OF FIGURES
Figure 1: Location of the Proposed Rehabilitation of the Access Road ................................... 7
Figure 2: Location Map of the Inabanga Watershed ............................................................... 13
Figure 3: Elevation and Slope Range Distribution of the Proposed Road Rehabilitation ...... 13
Figure 4: Geology Map of the Inabanga Watershed ............................................................... 15
Figure 5: Soil Map of the Entire Inabanga Watershed ............................................................ 15
Figure 6: Land Classification Map of the Influenced area ....................................................... 17
Figure 7: Monthly Rainfall and Temperature Conditions in Inabanga, Bohol ......................... 19
Figure 8: Projected monthly rainfall change under Medium-range Emission Scenario (A1B) in
Tagbilaran City, Bohol .............................................................................................. 20
Figure 9: Projected Change in Monthly Average Mean Temperature (°C) under Medium-
range Emission Scenario (A1B) Tagbilaran City, Bohol .......................................... 21
Figure 10: Distribution of Watersheds in Bohol Province ...................................................... 22
Figure 11: Road network in Inabanga, Bohol .......................................................................... 26
LIST OF TABLES
Table 1: Summary List of ECP Types and ECA Categories ..................................................... 3
Table 2: EIS and IEE Requirements for Road and Bridge Projects ......................................... 4
Table 3. Breakdown of cost estimates for the road rehabilitation project .............................. 11
Table 4: Implementation Schedule ......................................................................................... 12
Table 5: Common Recorded Birds in Inabanga Watershed ................................................... 23
Table 6. Potential environmental impacts of the proposed rehabilitation sub-project. ........... 27
Table 7. Results of the stakeholder’s consultations at Brgy. Ilaya, Inabanga Bohol .............. 37
Table 8. Responsibilities for EMP Implementation. ................................................................ 42
Table 9. Environmental Impact Mitigation Plan ....................................................................... 43
Table 10.Environmental Monitoring Plan ................................................................................ 57
viii
LIST OF APPENDICES
Appendix 1. Photographs of the Proposed Road Rehabilitation Subproject .......................... 63
Appendix 2. Stakeholder Views of the Road Rehabilitation in Ilaya ....................................... 64
Appendix 3. Brgy. Ilaya Minutes; Endorsement; Attendance; Photo Documentation ............ 68
Appendix 4. PO Resolution Endorsing the Sub-project .......................................................... 81
Appendix 5. Grievance Intake Form ........................................................................................ 89
1
I. EXECUTIVE SUMMARY
1. This Initial Environmental Examination (IEE) has been prepared for the Rehabilitation of
Access Road in Brgy. Ilaya in Inabanga, Bohol. This Sub-project is the rehabilitation of the
existing access road with an estimated length of 2.552 km. It is located within the alienable
and disposable area of the barangay leading to the NRM site of INREMP. It is seen to directly
benefit the students and the farmers in the influenced area. Major components of the sub-
projects are the provisions of the following: 2.552 km - including improvements to 234 m
existing concrete pavement, slope protection, line canal, pipe culvert and rehabilitation of
existing pipe culverts.
2. The objective of the Rehabilitation of Ilaya to Datag Access Road is to uplift the quality
of life of the people thru the provision of all-year-round easy access thereby improving the
delivery of basic services, increasing economic opportunities and conditions. The proposed
access road will support the NRM project activities of the constituents.
3. The Sub-project has been categorized by ADB as Category B and this IEE was
prepared consistent with the environmental assessment requirements of ADB’s Safeguard
Policy Statement of 2009. The IEE was carried out through screening and analysis of various
environmental parameters, field investigations, stakeholder consultations, and review of other
road project reports in the Philippines. The IEE covers the general environmental profile of
Inabanga’s rural infrastructure sub-project and includes an assessment of the potential
environmental impacts during different sub-project phases and formulation of corresponding
mitigation measures. The IEE was prepared by the LGU of Inabanga in cooperation with
RPCO, PMU, WMCO and POs.
4. The estimated total sub-project cost is Php 19,620,000.00. Majority of the project cost
will come from the DENR - INREMP and LGU, with a cost sharing of 80% and 20%,
respectively. It is assumed that the benefits of the sub-project will be in terms of economic
gains from the sub-project, reduction in fare, travel time, and cost of transporting agricultural
produce.
5. The sub-project is located within the alienable and disposable area of the barangay
leading to the NRM site of INREMP. This is compliant to the INREMP technical bulletin No. 1-
2 April 04 2017 that allows access road in A&D leading to NRM sites.
6. The IEE, based on the screening of baseline environment and review of proposed civil
works, has not identified any major environmental concerns due to proposed rehabilitation
given that all the proposed civil works are only asset preservation of existing roadway and are
located within existing right of way. There will only be localized short-term impacts during
construction activities due to the implementation of civil works that will be addressed in the
detailed design and through implementation of the mitigation and monitoring measures
specified in the environmental management plan.
2
7. The IEE process included stakeholder participation and consultation to help LGUs
achieve public acceptance of the sub-project. A series of consultations with barangay Ilaya
and the local government of Inabanga confirmed that the rehabilitation of the access road is
essential for economic development.
8. A grievance redress mechanism will be established by the LGU prior to
commencement of site works to ensure that complaints of affected persons and other
stakeholders regarding the project’s environmental performance will be addressed promptly.
9. The IEE includes an environmental management plan which details the mitigation
measures, environmental monitoring activities, institutional responsibilities, and environmental
management capacity building. The LGU, through its Municipal Planning and Development
Coordinator and the Municipal Engineer, will ensure that relevant EMP provisions are included
in bid and contract documents for detailed design, project supervision, and civil works. During
construction, they will closely conduct monitoring of the contractor’s environmental
performance and over-all EMP implementation. A semi-annual monitoring report to be
consolidated by the NPCO will be submitted to ADB for clearance and disclosure.
10. The major positive impact of the project will be economic gains and better accessibility.
The sub-project will directly benefit people located within the barangay providing improved
access and economic development. The sub-project would also improve the environment in
terms of reduced soil erosion and landslides through slope stabilization measures and
construction of retaining structures. Dust generation from the damaged roads, health risks to
the roadside communities, and damage to the biological environment will be reduced by
pavement improvement and soil erosion control measures.
11. This Sub-project will have an overall beneficial impact and will have minor negative
impacts that will be carefully monitored and adequately mitigated through implementation of
the EMP.
II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK
A. Environmental Clearance Requirements
1. Government Environmental Laws, Regulations and Guidelines
12. According to the EMB Memorandum Circular 005 - 2014, the environmental category
of a project is decided based on the type of the project (whether it falls into ‘Environmental
Critical Project’, ECP type), location of the project (whether it falls into ‘Environmental Critical
Areas’, ECA category), and size of the project. A summary list of ECPs and ECA categories
are presented in Table 1.
3
Table 1: Summary List of ECP Types and ECA Categories
A. List of ECPs
As declared by Proclamation No. 2146 (1981)
1. Heavy Industries – Non-ferrous Metal Industries, Iron and Steel Mills, Petroleum and Petro-
chemical Industries including Oil and Gas, Smelting Plants
2. Resource Extractive Industries – Major Mining and Quarrying Projects, Forestry Projects
(logging, major wood processing projects, introduction of fauna (exotic animals) in public and
private forests, forest occupancy, extraction of mangrove products, grazing), Fishery Projects
(dikes for/ and fishpond development projects)
3. Infrastructure Projects – Major Dams, Major Power Plants (fossil-fueled, nuclear fueled,
hydroelectric or geothermal), Major Reclamation Projects, Major Roads and Bridges
As declared by Proclamation No. 803 (1996)
4. All golf course projects
B. List of ECA Categories - As declared by Proclamation No. 2146 (1981)
1. All areas declared by law as national parks, watershed reserves, wildlife preserves, sanctuaries
2. Areas set aside as aesthetic potential tourist spots
3. Areas which constitute the habitat of any endangered or threatened species of Philippine wildlife
(flora and fauna)
4. Areas of unique historic, archaeological, or scientific interests
5. Areas which are traditionally occupied by cultural communities or tribes
6. Areas frequently visited and/or hard-hit by natural calamities (geologic hazards, floods, typhoons,
volcanic activity, etc.)
7. Areas with critical slopes
8. Areas classified as prime agricultural lands
9. Recharged areas of aquifers
10. Water bodies characterized by one or any combination of the following conditions: tapped for
domestic purposes; within the controlled and/or protected areas declared by appropriate
authorities; which support wildlife and fishery activities
11. Mangrove areas characterized by one or any combination of the following conditions: with
primary pristine and dense young growth; adjoining mouth of major river systems; near or
adjacent to traditional productive fry or fishing grounds; areas which act as natural buffers
against shore erosion, strong winds and storm floods; areas on which people are dependent for
their livelihood.
12. Coral reefs characterized by one or any combination of the following conditions: With 50% and
above live coralline cover; Spawning and nursery grounds for fish; Act as natural breakwater of
coastlines
4
13. Based on their type, size and location, the projects have been classified into 3 major
groups:
• Group I (ECPs): ECPs in either ECAs or NECAs – Environmentally Critical Projects
in either Environmentally Critical Areas or Non-Environmentally Critical Areas. These
projects require the proponent to submit ‘Environmental Impact Statement’ report to
secure ‘Environmental Compliance Certificate’ from DENR’s Environment
Management Bureau (EMB). Table 2 gives the size of the road and bridge projects
that fall in to Group 1.
• Group II (NECPs): NECPS in ECAs – Non- Environmentally Critical Projects in
Environmentally Critical Areas. These projects require proponent to submit either
‘Initial Environmental Examination’ Report or ‘Project Description Report ‘based on
the size of the project (see Table 2) to secure either ECC or ‘Certificate of Non
Coverage’.
• Group III (Non Covered Projects): NECPs in NECS – Non- Environmentally Critical
Projects in Non- Environmentally Critical Areas. PDR required to be submitted for
Enhancement Mitigation Projects for confirmation of benign nature of proposed
activity, and CNC is required to be secured. All other projects shall be at the option of
the proponent to prepare a PDR as a basis for CNC, should the proponent opt to
secure one.
Table 2: EIS and IEE Requirements for Road and Bridge Projects
Project Type Project size parameter
EIA Report Type Required/Decision Document
Group I Group II
Environmental Impact
Statement (EIS)/ ECC
Initial Environmental Examination (IEE Report (IEER) or IEE Checklist
(IECC)/ ECC
Project Description Report (PDR)/ CNC
Bridges and viaducts new construction
Length >= 10 km >=80m but <=10 km Regardless of length for foot bridges; < 80m for other bridges
Roads, new construction and widening (including RO- RO facilities)
Length with no critical slope or Length with critical slope
>= 20km or
>=10km
>= 2 km but <20km or
>=2km but <10km
< 2 km
Tunnels and sub-grade roads and railways
Length >=10 km < 1 km
14. This sub-project is an improvement of existing barangay road which falls under the
group of Non-ECP. Given that the sub-project is a rehabilitation of access road with no more
than 50% increase in capacity, the Inabanga LGU is now concurrently processing its
application for IEE checklist. Environmental consideration of the proposed project will be
5
incorporated in an Environmental Management Plan where possible adverse impacts will be
identified including the corresponding mitigating measures and following the DENR.
2. ADB Environmental Assessment Requirements
15. According to ADB guidelines, the process of determining a project’s environment
category is to prepare a Rapid Environmental Assessment screening checklist, taking into
account the type, size, and location of the proposed project. Based on ADB’s Safeguard Policy
Statement 2009 (SPS 2009), a project is classified as one of the four (4) environmental
categories (A, B, C or FI) as follows:
• Category A: Projects with potential for significant adverse environmental impacts that
are irreversible, diverse or unprecedented. These impacts may affect an area larger
than the sites or facilities subject to physical works. An environmental impact
assessment is required.
• Category B: Projects judged to have some adverse environmental impacts, but of
lesser degree and/or significance than those for category A projects. Impacts are site-
specific, few if any of them are irreversible, and in most cases mitigation measures can
be designed more readily than for Category A projects. An initial environmental
examination (IEE) is required.
• Category C: Projects likely to have minimal or no adverse environmental impacts. No
environmental assessment is required although environmental implications are still
reviewed.
• Category FI: Projects are classified as category FI if they involve investment of funds
to or through a financial intermediary. Where the FI’s investment have minimal or no
adverse environmental risks. The FI project will be treated as Category C. All other FI’s
must establish and maintain an environmental and social management system and
must comply with the environmental safeguards requirements specified in SPS 2009
if the FI’s sub-projects have the potential for significant adverse environmental impacts.
16. According to Philippine environmental guidelines, the project or sub-project can be
considered whether under Group II or III, while ADB has categorized the Project as
environment Category B. Hence, this IEE has been prepared to meet the requirements of both
ADB and the government. Upon ADB’s receipt of the final IEE from the proponent, this will be
publicly disclosed through posting on ADB’s website.
6
III. DESCRIPTION OF THE PROJECT
A. Overview
17. The general objective of the Rehabilitation of Ilaya to Datag Access Road is to uplift
the quality of life of the people thru the provision of all-year-round easy access thereby
improving the prompt delivery of basic services, increasing economic opportunities and
conditions. The proposed access road will support the national resources management project
activities of the constituents.
18. To ensure the access of communities to basic social services delivery, repair and
maintenance of roads, spillways and drainage systems are among the infrastructure concerns
identified by the community and specifically expressed in their Annual Investment Plan for
specific funding assistance by the local government unit.
B. Project Location
19. Inabanga is a coastal municipality situated at the northwestern part of Bohol
approximately seventy-two (72) kilometers from Tagbilaran City, the provincial capital of
Bohol. It can be reached in 1.5 hours by land through all-weather roads. It is bounded by:
Northeast: Buenavista; Southeast: Danao; South: Clarin; and Southwest: Sagbayan. The
municipality is located at the mouth of the Inabanga River, the largest river in Bohol. The
distance from Poblacion to Barangay Ilaya influence area is 11 kilometers.
20. The Municipality of Inabanga is part of the Inabanga Sub-Watershed of the Wahig-
Inabanga River Basin, Province of Bohol, Region 7 (Central Visayas Region). One of the
current major problems of the municipality is the bad condition of several barangay roads.
21. The proposed road infrastructure (RI) sub-project is located in barangay Ilaya. The
sub-project is located within the alienable and disposable area of the barangay leading to the
NRM site of INREMP (Figure 1 and Appendix No. 1). Major components of the sub-projects
are the provisions of the following: 2.552 km - including improvements to 234 m existing
concrete pavement, slope protection, line canal, pipe culvert, and rehabilitation of existing pipe
culverts.
22. Based on the environmental characterization of the project site done during the field
reconnaissance survey, the project is not located in an environmentally critical area and the
field data were supplemented with secondary information gathered from the DENR Regional
Office and CENRO and other relevant data such as watershed management plan,
environmental reports, and feasibility studies undertaken by national and local agencies.
7
Figure 1: Location of the Proposed Rehabilitation of the Access Road
C. Project Rationale
23. The Rehabilitation of Access Road in Brgy. Ilaya is located within the A&D area. Most
of the beneficiaries are farmers who rely heavily on agricultural products as their main source
of income, safe and lower costs in transporting and hauling their harvests are among the prime
needs that ought to be addressed as early as possible.
24. The main livelihood of the community within the influenced barangay is farming.
However, these activities are very much affected by the poor condition of the road. During
rainy season, the road becomes muddy and hardly passable and dusty during summer. Based
on the data above, health is another issue and they need access to more additional health
services. The transport condition also makes the fare rates high in which people tend to get
their basic needs from unscrupulous businessmen engaged in trading or middlemen in the
area. Also, the quality of farm produce transported to the main market will lessen if the road is
rough. The lack of access also deprives them of the ability to take advantage of job
opportunities.
25. During a series of consultations with the municipal and barangay officials, the major
problem identified by the community was the poor access to road. Because of this, the farmers
are forced to sell their agricultural products to traders who go into the area and buy their
products at a very low price. The traders tell the farmers that revenues would be lower due to
transportation cost and hauling if they sell them to the market.
8
26. There will be many opportunities that this rehabilitated access road will bring. Foremost
of which will be the additional income of the farmers and the people due to the enhancement
of their farming systems and maximization utilization of the area. Other factors that would
contribute to income or savings generation are the following: reduction of time in transporting
their produce and finished products, increase of enrollees in Ilaya Elementary School,
decrease of maternal and infant mortality rate due to the increase of frequency of health
personnel going to the area, and the decrease of transportation fare rates due to the reduction
of vehicular operating cost. Other potential livelihoods that will emerge are backyard poultry
and/or piggery, commercial high value crops, and eco-tourism development and other related
activities.
27. Employment during the construction will be made available to the local residents in
accordance with their skills and capabilities in support of the Gender and Development
program of the government; labor, skilled and unskilled, will be from the barangay. Women
will also be employed. It may address some of the poverty situation as it decreases costs and
prices and enhances trade and employment opportunities. Transportation indirectly alleviates
poverty since the lack of access deprives them of the ability to take advantage of job
opportunities and even of very basic social services. Reliable access to schools and health
services for the poor contributes directly to their accumulation of human capital which is a key
factor in poverty alleviation in as much as jobs and basic social services are relatively highly
valued by the poor.
D. Project Development Plan
1. Project Components
28. The scope of works for the sub-project is composed of 2.552 km including
improvements to 234 m existing concrete pavement, slope protection, line canal, pipe culvert
and rehabilitation of existing pipe culverts.
29. The total project cost is Php 19,620,000.00 considering all the sub-project components
which include the indirect cost and taxes aside from the direct cost
(material+labor+equipment).
30. The direct cost has the amount of PhP 15,206,319.43. The overhead, contingencies
and miscellaneous (OCM) and Contractor’s Profit will be the same percentage 8% of the direct
cost. Taxes will be in the fixed ratio of 12% as required by the government.
2. Description of the Project Phases
a. Pre-Construction Phase/Pre-Development Phase
31. The pre-construction phase involves the social preparation (to include organizational
strengthening, planning, identification and prioritization of community needs) of the community
9
for the entry of the project to the site, conduction of pre-engineering activities covering detailed
survey works to determine alignment of roads and canal systems, preparation of the detailed
engineering plans and programs of work, recruitment of work force and initial sourcing and
procurement of construction materials. These activities will be conducted by the proponent
technical staff, partner line agencies, NGO service providers, community beneficiaries
especially the Peoples’ organizations, and contractors.
b. Construction/Development Phase
32. The construction phase involves the mobilization of construction equipment,
construction workers and materials to the specific project site after which the longer period of
actual construction work will commence. The construction phase will end with the
demobilization of construction equipment, workers and other construction paraphernalia from
the construction site. Majority of these activities will be undertaken by the contractor and
community residents under the close supervision of the Sub-Project Management Unit.
c. Operation Phase and Maintenance Phase
33. The operation and maintenance phase involves the actual maintenance of the
rehabilitated access road during its expected economic life. This will involve the designation
of a spoil storage area at least 25 meters away from water bodies for proper disposal of
excavated materials, wet areas of dust sources along vehicle route, and regular removal of
debris, logs and other materials along drainage canals.
d. Abandonment Phase
34. This phase is included in the project demobilization. The proponent does not intend to
abandon any facilities and unserviceable equipment used during construction. The project will
not be abandoned in disorderly condition but instead restored for functional use. Following the
completion of the construction, the proponent will dismantle temporary shelters and the
construction yard including unserviceable vehicles and equipment.
35. Wastes arising from the abandonment are expected to be minimal. These wastes could
include small volumes of left-over sand and gravel, re-bars and other steel materials (i.e., nails
and welding roads) and lumber.
E. Manpower Requirements
36. Construction activities will require hiring of manpower. It is assumed that some skilled,
semi-skilled and unskilled manpower will be available in the area. Skilled manpower not
available in the locality may be sourced from other nearby localities. Technical manpower will
be a complementation of specialists to be provided by locally known engineering firms.
10
37. During the construction phase, a workforce consisting of contractual and regular
laborers will be employed to carry out the construction of the proposed project.
38. The contractor shall employ qualified and sufficient staff to carry out inspections,
testing and monitoring for the project.
F. Project Cost
39. The sub-project cost has an estimated total amount of Php 19,620,000.00 considering
all the sub-project components which include the indirect cost and taxes aside from the direct
cost (material+labor+equipment).
40. Following the agreed financing mix of the sub-project, 80% of the total sub-project cost
as presented will be covered by the project and the remaining 20% will be borne by the LGU
proponent (Inabanga, Bohol) as equity counterpart which will be appropriated by the
Sangguniang Bayan (SB) from the local development fund.
41. The breakdown of cost estimates is presented in Table 3.
42. Aside from the equity counterpart provided by the LGU for the sub-project, they also
allocated some amount intended for the preparation of the project such as seminars,
preparation of feasibility study (or sub-project proposal document) and detailed engineering,
survey of the project site and some evaluation by the personnel from different sectors who are
involved in the implementation of the sub-project.
43. Asian Development Bank and other foreign funding institutions together with the DENR
will provide the budget needed for capacity development trainings. It will enhance the skills of
the proponent and POs as well as provide additional learnings on the guidelines and best
practices on Infrastructure project implementation.
11
Table 3. Breakdown of cost estimates for the road rehabilitation project
G. Project Duration and Schedule
44. After the provision of technical assistance provided by the National Project
Coordinating Office (NPCO), the LGU-SPMU will finalize the “full blown” proposal or the Sub-
project Proposal Document (SPD). The completed SPD was submitted to NPCO for review
and concurrence. When found substantial enough, it was endorsed to the PPMC for the
request of approval. During these stages, the DED was simultaneously prepared by the LGU
Engineering Unit and was completed at the time of the approval by the PPMC. The DED shall
then be translated into a Bidding Document once the SPD is approved by the council.
Procurement period should take three (3) months to comply with the ADB Procurement
Guidelines. Construction as indicated in the prepared Bar Chart of Construction Schedule will
take eleven months assuming that there will be no delay. The 340 construction calendar days
may start on middle of April 2019 and should end on mid of February 2020. After the target
completion of construction works, the LGU will prepare the completion documents and the
turn-over ceremonies shall also take place at the same time. Finally, maintenance and
sustainability activities will be performed on April 2020 which will include the adaptation of the
required MOA for maintenance of the facility and sustainability training which will be provided
by the NPCO. See the table below for the illustration of the indicative implementation schedule.
12
Table 4: Implementation Schedule
Sub-project
Milestones
2018 2019 2020
J F M A M J J A S O N D J F M A M J J A S O N D J F M A
SPD Preparation
Review of SPD
SPD Approval
DED Preparation
Procurement Stage
Construction Stage
Completion and
Turn-over
O & M Activity
IV. DESCRIPTION OF THE ENVIRONMENT
45. Wahig -Inabanga River Basin is the largest watershed in Bohol. It is composed
of four major watershed components, namely; Wahig-Pamacsalan, Danao, Dagohoy
and Inabanga covering an area of about 62,795.74 hectares. Most of the land areas
are classified as alienable and disposable lands.
46. Inabanga watershed is located at the northern part of the province of Bohol (Figure 2).
It is one of the watersheds of Wahig-Inabanga River Basin. It has a total area of 14,111
hectares covering the municipalities of Inabanga, Sagbayan, Danao, Dagohoy and Carmen
which expands to 59 barangays. Out of the five municipalities, the municipality of Inabanga
has the biggest area covering 38 barangays and occupied 58% of the total area of the whole
Inabanga watershed. Having this extent, the watershed is second to Dagohoy watershed in
terms of area. The headwaters of Inabanga Watershed emanate from Wahig and Pamacsalan
rivers flowing through the three watersheds. It traverses 6 municipalities namely: Sierra
Bullones, Pilar, Dagohoy, San Miguel, Danao and Inabanga.
A. Elevation and Slope
47. Inabanga watershed has an elevation that ranges from 0 to 400 meters above sea
level. Highest elevation is observed in the municipality of Dagohoy and Carmen where the
elevation ranges from 300 to 400 meters above sea level. It has a slope that varies from level
to gently sloping, undulating, moderately steep to very steep and hilly.
48. The influence area has an elevation ranging from of 40 to180 meters above sea level
and a very minimal number of big trucks (especially diesel powered) goes into this barangay.
However, the proposed subproject has an elevation ranging from 48 to 157 m asl with an
average slope of 9.3% (Figure 3).
13
Figure 2: Location Map of the Inabanga Watershed
Figure 3: Elevation and Slope Range Distribution of the Proposed Road Rehabilitation
14
B. Geology
49. Geological composition of Inabanga Watershed includes Maribojoc limestone,
undifferentiated andesite and basalt lava flows, alluvium, and Carmen formation
50. The following are the description of the geologic formation in Inabanga Watershed:
Undifferentiated Andesite, basalt lava flows. Undifferentiated Andesite is closely
related and or similar to Ubay Volcanics (BOHOL).. Ubay Volcanic is a thick extensive,
basaltic to Andesite flows mostly sheared, interbedded and/or intercalated in places
with clastic rocks. Fissured basalt normally has high permeability and good
groundwater development potential.
Carmen Formation. The Carmen Formation is distributed mainly in the eastern part
of Bohol occupying 30 to 40 percent of the total island area. This low dipping thick
sedimentary sequence is essentially composed of shale, sandstone, slabby to massive
limestone, conglomerate, siltstone, marl and some Tuffaceous and siliceous facies.
The conglomerate of this formation occurs around Dimiao, the southern coast and
along Tanguhay River. This formation has a low groundwater potential which primarily
provides water for Level 1 systems.
Maribojoc Limestone. The Maribojoc Limestone is found extensively in the western
part of Bohol. It is mainly massive or lagoonal limestone and creamy to brownish
yellow. It is also coralline, porous and in some places marly or agglomeratic. The rock
resembles the Carcar Formation of Cebu. Bedding planes are generally flat though
poorly bedded. It is more likely that it was formed either after the deposition of the
Sierra Bullones Limestone during Late Miocene, or after the Jagna Andesite activity
(Sajona et al. 1986).
Talibon Diorite. Talibon Diorite consists of quartz, feldspar and biotite intruded into
the metasedimentary and metavolcanic rocks producing hydrothermal alteration along
the contacts. These rocks have poor groundwater potential; however, water for
domestic use in rural areas can be obtained from weathered zone thru dug wells.
C. Soils
51. Inabanga watershed has seven types of soil namely Bantog clay, Batuan Faraon
complex, Bolinao clay, Calape clay loam, Hydrosol, Inabanga clay and Ubay clay (Annex B
Table 13 and Figure 4). Among these types, Batuan Faraon clay has the largest area
comprising 6,384 hectares or 45% of the total area of the watershed, followed by Inabanga
clay with 2,772 hectares. On the other hand, the Hydrosol type of soil comprises 246 hectares
and 12 hectares unclassified.
15
Figure 4: Geology Map of the Inabanga Watershed
Figure 5: Soil Map of the Entire Inabanga Watershed
16
D. Water Quality
52. The Inabanga Watershed was classified as Class D water. A ‘Class D’ classified water
ways is intended for navigation. The classification also takes into consideration the component
of water quality management since the application of effluent standards is dependent on this
classification.
53. The collection of water samples was made on October 28, 2014. The standard
procedures in the conduct of water quality monitoring (i.e., field sampling, transport,
preservation, analysis and sample chain custody) were strictly followed. The samples were
properly preserved before and during the transport to the TECHNOLAB Analytical Group, Inc.
Laboratory in Cebu City. The analysis was undertaken following the prescribed method of
analysis (Standard Methods for Examination of Water and Wastewater). Physical and
chemical parameters as indicators of water quality include, among others, the following: pH,
temperature, conductivity (us/cm), COD, Ca (mg/L), Nitrate - N (mg/L), Phosphate (mg/L), total
microbiological analysis, total coliform (MPN/100 mL), and fecal coliform (MPN/100 mL). As a
result, the water quality characteristics of the Inabanga Watershed are described based on
guidelines indicated in DAO No. 8 Series of 2016 as follows:
• The Inabanga Watershed mean temperature is 27°C which indicates that the water in
the watershed is within the normal range for surface water.
• Average pH value is 8.08 taken from different monitoring points showing that the water
quality of Inabanga watershed conformed to the standard set by DENR.
• The result of conductivity in Inabanga watershed has an average value of 0.49 µS/cm,
which means minimum concentration of electrolyte ions has low conductivity.
• The average salinity is 2.32 ppt which indicates that the water in the watershed has
low salinity.
• Total Dissolved Solids show low levels of dissolved solids compared to the standard
set by DENR which is 1000 mg/L. This result is in conformity with the prescribed
standard of DENR.
• The result of the Chemical Oxygen Demand in Inabanga Watershed has the average
value of 18 mg/L. The DENR does not have a guideline value for chemical oxygen
demand.
• The water in the watershed has a low value of Calcium (Ca, mg/L).
• The watershed has a low value of Nitrate-N.
• The Inabanga Watershed is below the set standard for total phosphate.
• The Inabanga Watershed has a value of 0.01 to 0.02 phosphates which is below the
set standard.
• Amount of Nitrate average is 0.47 which indicate that the water in the watershed has
a low value of Nitrate-N.
• Fecal coliform in Inabanga watershed from existing monitoring stations has a value of
4.8x102 Most Probable Number (MPN) in station 1, 1.1x102 MPN in station 2, 1.6x104
MPN in station 3, 9.2x103 in station 4, and 1.6x104 MPN in station 5.
E. Land Classification
54. Based on the records from the Department of Environment and Natural Resources,
the Municipality of Inabanga has a total land area of 13,868 hectares or it is about 3.18% of
17
the area of Bohol province. Roughly eighty-eight percent or 12,170 hectares is alienable and
disposable lands and twelve percent or 1,698 hectares is timberland or forestlands. It is
composed of fifty (50) barangays, twelve (12) of which are coastal, thirty-six (36) are inland
and two (2) are island barangays with a total population of 51,070 and 10,197 households.
55. Of the total hectares of 850 hectares covered by barangay Ilaya, more than 30% of
grassland and 26% is used for agricultural purposes. Other land uses include agroforestry,
tree plantation and other special uses.
56. The sub-project is located within the alienable and disposable area of the barangay
leading to the NRM site of INREMP. This is compliant of the INREMP Technical Bulletin No.
1-2 April 04 2017 that allows access road in A&D leading to NRM sites.
Figure 6: Land Classification Map of the Influenced area
F. Land Cover and Land Use
57. There are areas in the municipality which are covered by Proclamation No. 468 as
amended to Presidential Proclamation 223 “Wahig Inabanga River Watershed Forest
Reserve”. Among the barangays affected are Baguhan, Ilaya, Datag, Riverside, Sua, San
Jose, Cagawasan, Tungod, Ondol, Bugang, Lawis and Sto. Niño. Considering that the
municipality is dominated by rivers and mangrove areas, it is very important that easements
and buffer zones shall be provided along its river banks, mangrove and forest development
shall be enhanced so that human settlements shall be protected. Also, soil erosion should be
prevented in which it might cause floods and siltation in the coastal zone
18
58. The topography of the influenced area is characterized by level plains on the northern
portion which gently undulate to hills and mountains on the southern part. Of the total area of
850 hectares covered by barangay Ilaya, more than 30% is grassland and 26% is used for
agricultural purposes. Other land uses include agroforestry, tree plantation, and other special
uses.
59. There are only two (2) households living in makeshift houses in the barangay. Of
which, one (1) household is located in the project influence area. The distance of this single
household is more than 10 meters from the side of the road. In general, most of the houses in
the barangay are made of light construction materials for its wall and 50% have strong roofing
system.
60. Although the project will traverse into production areas, no trees, crops and other
assets encroachment at the easement and right of way of the road. The proposed road access
rehabilitation will not cause adverse impact on the environment.
G. Climate
1. Baseline Climate
61. Based on Modified Corona’s Classification System, the area has a Type IV climate
which is characterized by more or less evenly distributed rainfall throughout the year (Agpaoa
et al. 1975). The climate is influenced by southwest originating monsoons, and is relatively dry
from March to May. The wet season is from June to December.
a. Rainfall
62. The observed mean monthly rainfall based on 2018 records ranges from 60 mm to 204
mm. The driest months are March to May ranging from 60 mm to 83 mm, while the wettest
months are June to December with rainfalls ranging from 149 mm to 204 mm. The annual
rainfall around the proposed subproject is 1,736 mm. Other details are shown in Figure 7.
b. Temperature
63. The monthly maximum air temperatures range from 30.1 ˚C to 32.8 ˚C based on year
2018 recorded temperatures. The annual average temperature is 27.7 ˚C - indicative of a fairly
uniform temperature throughout the year. In Inabanga, the air temperature can be considered
low due to the mountains, the alignment of the area, and the prevailing winds that tend to
reduce the movement of warm air from the sea which promotes outflow from the area.
19
Figure 7: Monthly Rainfall and Temperature Conditions in Inabanga, Bohol
2. Climate Scenario for Bohol in 2020 and 2050
64. The projected future changes in temperature and rainfall in 2020 and 2050 were
developed based on the data prepared by the PAGASA using the PRECIS model. In that
assessment, the medium-range scenarios are within a planning horizon of up to 2050. Outputs
of the model under the A1B and A2 scenarios will only diverge after 2050 due to the long
lifetimes of the greenhouse gases. The outputs of the model run for the observed monthly
changes, and changes in the monthly rainfall both in 2020 and 2050 were based on climate
scenarios.
a. Rainfall
65. Figure 8 presents the projected change in monthly average rainfall (mm) under the
medium-range emission scenario (A1B) in 2020 and 2050. Projected change anomalies were
20
estimated as the difference from current or future periodic monthly average precipitation to the
observed baseline period (1971-2000) monthly average precipitation values. The A1B
scenario showed an overall increasing trend in the monthly precipitation particularly in June
and December while consistently decreasing trend was noted during the months of January
to April. In particular, the monthly precipitation fluctuated from month to month. However, the
most distinct changes were predicted to be in the 2050s period where the month of October
indicated a potential increase of approximately 44 percent from the baseline precipitation
period while noticeably decreased for the duration of January to April (up to -42%). The
variability of the amount of precipitation is mainly attributed to the shorter dry-spell length
during dry seasons. In effect, the dry season tends to become drier while the wet season
becomes wetter.
Figure 8: Projected monthly rainfall change under Medium-range Emission Scenario
(A1B) in Tagbilaran City, Bohol
b. Temperature
66. The projected change anomalies of mean temperature in the future estimated an
increase of +0.8 °C (the present condition) up to +2.4 °C by the end of 2050s. The results
revealed differences in temperature changes that are larger from the 2050s period. The
increase in local-mean temperatures is between +0.8 to +1.2 °C in 2050s.
67. For temperature, Figures 9 shows the projected mean temperature scenarios based
on the Tagbilaran weather station in the area.
21
Figure 9: Projected Change in Monthly Average Mean Temperature (°C) under
Medium-range Emission Scenario (A1B) Tagbilaran City, Bohol
H. Hydrology
68. Only one body of water is within the influence area which is called Wahig-Inabanga
River. Based on the available data, Inabanga River is the longest in terms of length with 17
municipalities as tributaries (Figure 10).
I. Natural Hazards
69. There were only five (5) typhoons/tropical storms that almost or directly crossed the
path across the province since 1991. The latest two of which are tropical storms Seniang and
Queenie (international names Jangmi and Sinlaku, respectively) both occurred in 2014 and
are most remembered due the extent of additional damage inflicted on the province after the
devastating earthquake of 2013. Nevertheless, stronger typhoons affected the province and
the five municipalities even if these were not within the vicinity of the province. These are
typhoons/tropical storms either crossing from the Samar area and directly hitting Cebu and
the western provinces or were over the northern Mindanao area, thereby affecting Bohol. Most
notable of these are typhoon Nona (Melor, 2015), super typhoons Yolanda (Haiyan, 2013) and
Pablo (Bopha, 2012), severe tropical storms Sendong (Washi, 2011) and Frank (Fengshen,
2008). Around 75% of these typhoons, especially the most devastating ones occurred in the
last quarter of the year, notably November and December.
22
Figure 10: Distribution of Watersheds in Bohol Province
J. Biological Environment
1. Flora
70. The province of Bohol has an estimated remaining forest cover of 9 % of its total land
area. Natural forests in the province are still evident. However, flora of the families
Dipterocarpaceae, Fabaceae (Leguminosae) and Verbenaceae are becoming very rare. This
is exemplified by the short supply of Bohol’s molave or “tugas”. It is alarming that there are
young people who have never seen premium hardwood species that were previously
abundant.
71. The inventories on the diversity of plant species focused on the five vegetative cover
types of the watershed. Results of the inventory revealed that the watershed is low in plant
diversity. This is shown in the general list where there are 63 tree species belonging to 56
genera in 28 families; 5 species of palms in 4 genera; 3 species of shrubs in 3 genera and 3
families; 15 species of herbs belonging to13 genera in 7 families; 6 species of succulents and
woody vines belonging to 6 genera and 4 families; 12 species of ferns belonging to 8 genera
and 7 families; and 12 species of grasses belonging to 12 genera and 2 families
23
72. The common reforestation species used in the province are Yemane (Gmelina
arborea), Large-eaf Mahogany (Swietenia macrophylla), Small-leaf mahogany (Swietenia
microphylla), Teak (Tectona grandis), Auri (Acacia auricularformis) and Eucalypts (Eucalyptus
spp).
73. Overall, there are no trees and crops at the easement and right of way on the proposed
road rehabilitation project. It must also be noted that there are no endangered and critically
endangered species of flora in the project area and even within its impact zone based on the
validation report conducted by the LGU and the DENR on March 24, 2017.
2. Fauna
74. The floral resources of Inabanga Watershed were determined through primary and
secondary data collection. The data of the Bohol Island State University (BISU) Rapid
Biodiversity Assessment (RBA) Report (2013) was used to describe the faunal resources of
the watershed. Accordingly, wildlife was surveyed using the line transect method. A kilometer-
long transect lines were established traversing to known habitats of wildlife. Latitude/longitude
coordinates were taken using a Global Positioning System (GPS) device at the starting point
of each transect. Only bird species noticed were recorded together with its number, mode of
observation and distance from the observation point. The top three (3) significant bird species
encountered during the conduct of resource basic inventory rank accordingly were Whiskered
Treeswift (Hemiprocnecomate comata), Large-billed crow (Corvus macrorhynchos), and
Amethyst Brown Dove (Phapitreron amethystine). This faunal species belongs to 18 genera
and 16 families. The conservation status of these species is mostly least concern which means
that the population is stable and/or increasing.
Table 5: Common Recorded Birds in Inabanga Watershed
Family Name Scientific Name Common Name No. of
Individuals Conservation
Status*
Alcedinidae Alcedo argentata Silvery Kingfisher 3 Near Threatened
Alcedinidae Halcyon chloris White-collared Kingfisher 10 Least Concern
Columbidae Phapitreron leucotis White-eared Brown Dove 12 Least Concern
Laniidae Lanius cristatus Brown Shrike 18 Least Concern
Nectariniidae Nectarinia jugularis Olive-backed Sunbird 13 Least Concern
Pycnonotidae Pycnontus goiavier Yellow-vented bulbul 10 Least Concern
Pycnonotidae Hypsipetes philippinus
Philippine Bulbul 8 Least Concern
Turdidae Capsychus saularis OrientalMagpie Robin 3 Least Concern
*Based on the IUCN Red List of Threatened Species (2016).
24
K. Socio-Economic Conditions
1. Population
75. Based on the regular monitoring of RHU in 2017 data, the barangay has a population
of 469 which is equivalent to 0.0091% of the total population of the municipality. It has a
computed growth rate of 1.54%.
76. Based on the Rural Health Unit Survey conducted in year 2017, the barangay has a
total population of 469 and the total land area of the barangay is 850.96 hectares. Based on
these data, the computed population density for 2017 is 0.55 persons per hectare. This density
is expected to increase from 0.58 to 0.62 persons per hectare for 2019 and 2023 respectively.
77. Based on RHU data, the influence area has a total household of 90 and a total
population of 469 people. The total number of males is 251 and females is 218.
2. Water Supply
78. Main source of potable water is groundwater with L1 facilities – 489 water wells; L2
systems in Brgy. Poblacion and L3 systems serving 22 barangays. When it comes to access
of safe drinking water, 27% or 25 out of the 90 households reported that their source of drinking
water is unsafe. Most households in the barangay are still drinking water from dug wells. The
survey results are reflective to the fact that most people nowadays are drinking water coming
from water refilling station. The designated barangay sanitary aide as well as the barangay
officials in close coordination with the Municipal Health Office are constantly monitoring all the
sources of potable drinking water by conducting sampling and testing to prevent diseases
outbreak in the whole municipality.
3. Indigenous Peoples and People’s Organization
79 There are no indigenous people in the community of the proposed sub-project.
4. Education
80. There is low percentage of literacy in the barangay. Children aging 10 years old and
above are considered. Among all seven puroks, Purok 7 has the highest percentage of
illiterates. In the influence area, there is one primary and one elementary school that will
directly benefit from the proposed project.
25
5. Health and Sanitation
81. Malnutrition is still present among children 0-5 years old despite the intensive
campaign by the local authorities to eradicate the problem. Based on the regular evaluation of
the Municipal Rural Health Unit, there are 5 households in influenced area with no access to
sanitary toilets. In Sitio Tuko 5, 5.55% of the total households in the purok are without sanitary
toilet facility. The barangay nutrition council is looking for solution to resolve this issue.
6. Housing
82. There are only two (2) households living in makeshift houses in the barangay of which
one household located in the project influence area. Most of the houses in the barangay are
made of light construction materials for its wall and 50% have strong roofing system.
7. Electricity
83. The required electric power for the influence area is provided by Bohol Electric
Cooperative (BOHECO) - a non-stock non-profit organization. With the full cooperation of the
barangay and municipal officials, 100% of the puroks or households had been reached by
BOHECO’s services or energized by the electric power.
8. Communication
84. The main communication in the barangay is through cellular phone. Almost all
residents own cellphone units. The traditional way of sending message via telegram and other
means thru postal services had been gradually abolished. Email and other form of sending
messages like in the social media are now the present means.
9. Income and Expenditure
85. The barangay has real property taxes, local source from different taxes and Internal
Revenue Allotment (IRA) from national government as the three(3) main sources of income.
The barangay is very dependent on its IRA. The barangay has not received its share of real
property taxes from the use of the timberland areas since the Forest Land Use Plan has yet
to start the survey and delineation process.
10. Tourism
86. The town of Inabanga is blessed with natural attractions with rolling terrain, hills and
mountains. Also, Inabanga River (the largest river of Bohol), Ilihan Falls and, the Macavan
Cave are within the town. Other attractive sights are the centuries old Inabanga Church which
is dedicated to Saint Paul and whose feast day falls on June 30. Getting its share of visitors is
the Inabanga Nature Park and Fishing Village. There are potential tourism areas in the
26
barangay such as nature of river However, no development along this line has been started
because of the huge capital needed to start these kind of business activities.
11. Commerce and Industry
87. Most of the commercial establishments in the barangay and in influence area are
engaged in agri-business related activities. Buy and sell (rice, corn, cassava, coconut), and
livestock trading are common in the barangay. Barangay folks are mostly engaged in raffia
and Amakan weaving. Others are engaged in trading, especially those located at the town
proper. Establishments available are bakeries, lending institutions, gasoline stations, stores
selling construction materials, and more.
88. The people of Inabanga are industrious. Many are engaged in fishing, mat weaving,
the making of nipa thatches and seafood preservation such as salted sisi, litub, tagimtim and
kaykay. The women folks are also adept at saguran weaving, the weaving of blankets and the
making of hats, bags and baskets. 100% of the population from 15 years old and above are
employed members of the labor force. The unemployed members of the labor force are maybe
those having disabilities. The labor force includes those currently working or actively seeking
for work.
12. Road and Transportation
89. The municipality has a total of 130.6 kilometers roads and 8 bridges that links all 50
barangays (Figure 11). The main mode of transportation to and from the influence area is by
means of motorcycles for hire or locally known as (habal-habal) only. There are some farmers
who use raft (balsa) to transport their farm products via in the river since there is no access
road going to their farms.
Figure 11: Road network in Inabanga, Bohol
27
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
90. The IEE, based on the screening of baseline environment and review of proposed civil
works, has not identified any major environmental concerns due to proposed rehabilitation of
the access road given that all the proposed civil works are only asset preservation of existing
roadway and are located within existing right of way.
91. There will only be localized short-term impacts during construction activities due to
implementation of civil works that will be addressed in the detailed design and through
implementation of the mitigation and monitoring measures specified in the environmental
management plan.
92. These construction related impacts can be mitigated by: 1) the contractors’ work
practices, especially those related to the systematized demolition procedure consistent with
approved standard safety requirements; 2) cooperation by the local authorities with the
contractor in terms of use of public space and utilities; 3) project management’s strict
enforcement of the correct construction practices and standards; 4) the incorporation of the
mitigation measures identified in the IEE into the bid documents and specifications; and 5)
close monitoring of the contractor’s implementation of the required mitigation measures.
93. The potential environmental impacts resulting from implementation of civil works are
expected to be minor and likely short-term since the improvement works will not involve
widening and alignment adjustments (Table 6). Detailed environmental mitigation measures
have been prepared for all the identified impacts and presented in the environmental
management plan under Chapter VIII.
Table 6. Potential environmental impacts of the proposed rehabilitation sub-project.
Potential Environmental Impacts or
Values the Sub-project construction
would likely create:
Provision on
concrete
pavement
Slope
protection
Line
canal
Provision of
pipe culvert
Rehabilitation
of pipe culvert
Land surface disturbance – surface
scrapping, top soil erosion, and
vegetative clearing
minor minor minor minor minor
Affects temporal water regime:
decrease water quantity and quality
and flow regularity or seasonality due
to altered drainage patterns, water way
configuration, sedimentation, turbidity,
as well as river flow diversion
minor minor minor minor minor
Altered or impaired hydrology of the
immediate area: increase peak and
flood flows and irregular streamflow
minor minor minor minor minor
Decrease in downstream natural
resources’ economic and social
values/uses
minor minor minor minor minor
28
Potential Environmental Impacts or
Values the Sub-project construction
would likely create:
Provision on
concrete
pavement
Slope
protection
Line
canal
Provision of
pipe culvert
Rehabilitation
of pipe culvert
Decrease site’s attraction in terms of
losing some geological or
geomorphological values, particularly
those of known local, national or
international nature conservation
importance
minor minor minor minor minor
Vegetation loss affecting rare species
habitats, particularly of known local,
national or international nature
conservation importance
none none none
none none
Adverse impact on local and transient
fauna species (those species whose
range may include the project site),
particularly those of known local,
national or international nature
conservation importance.
none none none
none none
Bio-invasion of new strain of pests,
weeds or rare diseases none none none
none none
Frequent incurrence and increased
intensity of grassfire none none none
none none
Contamination of the immediate and/or
broader environment cause by the
storage or use of chemicals needed for
the construction works
minor minor minor minor minor
Air particulate emissions which may
cause atmospheric / environmental
pollution impacting on human health
and livelihood at local or larger scale
during construction phase
moderate moderate moderate minor moderate
Excessive solid waste accumulation
during infrastructure construction minor minor minor minor minor
Increase in noise and/or vibration
during construction minor minor minor minor minor
Unnatural lighting effects that may
impact upon flora and fauna, or deplete
the sense of naturalness of the area
none none none none none
Natural landscape fragmentation and
discontinuity none none none none none
Adverse impact on land use and the
amenity values of adjacent or
downstream areas (including the
integrity of agricultural land, or other
industry that the local community may
depend on)
minor minor minor minor minor
Adverse impact on existing or potential
recreational value and quality of known
traditional experience associated to
site natural setting
minor minor minor minor minor
Adverse impact or alter on-sites’ visual
value and its surrounding area -from
different vantage points
minor minor minor minor minor
Rating: None= No adverse impact; Minor= slight negative impact and momentary; Moderate=severe negative
impact with duration more than a year or permanent with far reaching spatial range
29
94. During operation, the project is expected to benefit the environment and socio-
economic conditions of the sub-project areas through increased agricultural production,
increased tourism activities, improved access and economic development, reduced dust due
to asset preservation, improved road safety due to installation of safety signs, and others.
95. Environmental impacts and proposed mitigation measures during sub-project pre-
construction, construction and operation phases are described under Chapter VIII. Detailed
environmental mitigation measures have been prepared for all the identified impacts and
presented in the environmental management plan.
A. Pre-Construction
1. Confirmation of no required resettlement, relocations, and compensation
96. This will be undertaken prior to the commencement of any civil works. The proponent
shall conduct consultation meetings with directly affected barangays and concerned POs’, and
information awareness campaign regarding sub-project location.
2. Identification and prioritization of road section where re-gravelling will be
done
97. Identification and prioritization of road sections will be give information and
participation of the community, particularly women and marginalized sectors. A sub-project
site validation will be facilitated to ensure that the INREMP validation process on sub-project
implementation is being complied with and hold consultative meetings with balanced
representation of men and women and affected persons on the sub-project components and
management plan.
3. Preparation of detailed engineering designs and programs of work
98. The detailed engineering designs and programs of work for the sub-project will be
prepared by the LGU for the completion of the proposed upgraded access road. The detailed
designs shall include the identification of spill management prevention and emergency
response plans for all construction sites, locate aggregate borrow pits and rock supply areas
away from human settlements with fencing and access barriers, and specific plan to notify and
provide them schedule to minimize disruption to normal commercial and residential activities.
99. The LGU with assistance from TA-PMIC will ensure that relevant provisions of the EMP
in terms of implementation of environmental mitigation measures, monitoring activities,
supervision and reporting are included for civil works and construction supervision.
30
4. Recruitment of workers
100. One of the potential impacts of the sub-project will be employment of skilled local
workers and other unskilled jobs. A robust “local first” hiring policy will be designed and be
implemented in coordination with local officials and community leaders especially at the
barangay and municipal levels. The Contractor will be required to follow the “local first” hiring
policy.
B. Construction
1. Construction materials acquisition, transport access, and storage system
101. The contractors will source out construction materials under their own arrangements.
Uncontrolled sourcing of such materials could lead to environmental impacts such as the loss
of topsoil or the disfigurements of the landscape from borrow pits. Earthen embankments and
material stockpiles will be susceptible to erosion, particularly during the rains and re-
suspension of dust during the dry seasons, but will be addressed in the EMP.
102. Local roads will be damaged during transportation of borrow materials and by the
construction equipment. In order to reduce impact on all borrow sites, contractors will water
the local roads close to the settlements used by the borrow trucks. As much as possible,
contractors will not make use of productive agricultural land. In case this is unavoidable, the
contractor will obtain consent to use the land from owner with agreed rental and will restore
the site to its original condition after completion of civil works.
2. Clearing and removal of obstructions
103. The contractor will initiate clearing and removal of obstructions on the existing road
which would result to damage landscape. However, vegetation (mostly grasses) present in
the site are common and will recover after the construction. The contractor will not use or
permit the use of wood as a fuel for the execution of any part of the works, including but not
limited to the extent practicable shall ensure that fuels other than wood are used for cooking.
3. Soil erosion
104. Soil erosion and unstable side slopes susceptible to landslides are noticed along
subproject road. The impact of soil erosion and unstable side slope are increased run off and
sedimentation causing a greater flood hazard to the downstream, loss of topsoil affects the
growth of vegetation that causes ecological imbalances, and development of unsightly cuts
and fills that have been riddled by uncontrolled erosion and gullying. Construction activities
should be taken up only during dry season.
31
105. During operation, silt load in the river is expected to be minor due to slope protection
structures installed. The contractor will also be required to make additional measures to
minimize erosion and landslides during construction phase such as 1) minimize damage and
cutting of surrounding vegetation during slope formation, 2) prevent erosion and protect the
cut slope with temporary drainage as soon as practicable after cutting, and 3) If new erosion
occurs accidentally, back fill immediately to restore original contours.
4. Ground surface leveling and gravelling of existing road
106. During ground surface leveling and gravelling of existing road, the potential impacts
would be minor and short-termed to the terrestrial and aquatic resources as well as to the
quality of surface water in the river. The contractor is expected to do the following: 1) the
construction site should be located away from forested or plantation areas, 2) all construction
fluids such as oils, and fuels should be stored and handled away from forested and plantation
areas, 3) no waste of any kind is to be discarded on land or in forests/plantations, 4) erosion
channels must be built around aggregate stockpile areas to contain rain-induced erosion, 5)
earthworks should be conducted during dry periods, 6) no waste of any kind is to be thrown in
surface waters, 7) no washing or repair of machinery near surface waters, 8) pit latrines to be
located away from surface waters, 9) no unnecessary earthworks in or adjacent to water
courses, 10) no aggregate mining from rivers or lakes, and 11) minimize the use of heavy
equipment at steep slopes.
5. Civil works (Concrete Pavement)
107. Since the subproject will mainly involve concrete pavement (with no road widening and
realignments), main impacts on land during construction are from air pollution, land and water
contamination, and traffic and access problems. The contractor will apply stated mitigating
measures during concrete pavement and stone masonry activities such as 1) piling of
aggregates at sites should be used/or removed promptly, or covered and placed in non-traffic
areas, and 2) all spills should be cleaned immediately and handled as per hazardous waste
management plan, and according to government regulations.
6. Implementation of noise and dust control measure
108. During construction, air quality is likely to be degraded by exhaust emissions from the
operation of construction equipment, and dust generated from haul roads, unpaved roads,
exposed soils and material stockpiles.
109. To mitigate the declining air quality problem during construction, the following will be
implemented: 1) regularly apply wetting agents to exposed soil and construction roads, 2)
cover or keep moist all stockpiles of construction aggregates, and all truckloads of aggregates,
32
3) minimize the time for excavations and exposed soil are left open or exposed, 4) backfill
immediately after work is completed, 5) restrict working time between 7:00 am and 5:00 pm,
6) maintain equipment in proper working condition, 7) replace unnecessarily noisy vehicles
and machinery, 8) vehicles and machinery to be turned off when not in use, and 9) construct
temporary noise barriers around excessively noisy activity areas if possible.
7. Dust and noise from borrow pits
110. Noise and dust may be generated from borrow pits. The contractor will ensure the
following mitigating measures: 1) provision of noise control measures to comply with national
standards, watering of the earth roads close to the settlements, use covered truck, 2) secure
appropriate environmental permits, 3) the borrow and material dumping sites must be access
controlled to keep away unauthorized entry of people, grazing cattle and any other stray
animals, and 4) protective gear like ear plugs will be provided to operating personnel if they
are exposed to noise levels beyond threshold limits.
8. Implementation of spoil management and control measure
111. The contractor will ensure that there will be no contamination of land and surface
waters from excavated spoils, and construction wastes. The uncontaminated spoils will be
disposed of in municipal or provincial designated sites, which must never be in or adjacent
surface water. On the other hand, suspicious contaminated soil will be tested, and disposed
of in designated sites identified as per government regulations.
9. Solid and liquid construction waste management system
112. Solid and liquid construction wastes management system will be facilitated to avoid
contamination of land and surface water from the construction wastes. The management of
general solid and liquid wastes of construction will follow government regulations to include
covering, collecting, handling, transporting, recycling, and disposing waste created from
construction activities and the work force. A schedule of solid and liquid waste pickup and
disposal will be established and followed to ensure construction sites are as clean as possible.
All solid wastes will be separated and recyclables be donated to the barangay. There will be
no site-specific landfills established by the contractors. All solid waste will be collected and
removed from the work camps and disposed in local waste disposal sites.
10. Water quality
113. The subproject has potential impacts on water quality due to washing of equipment
(i.e. vehicles and concrete mixers), and leakage and spills from discharge from worker camps
33
to the water resources. To mitigate, there should be a 1) set up proper and adequate sanitary
facilities, 2) ensure strict observance of proper waste handling and disposal and proper
sanitation including by the contractors and its workers, 3) provide wastewater treatment facility
(e.g., septic tank), and 4) trucks and other vehicle maintenance should be strictly controlled to
prevent the discharge of waste into the river system. Wastewater from the construction works
containing high concentration of suspended solids should be treated through sedimentation
tanks. 5) The discharge of cement-laden water and slurry during concrete mixing may
contaminate water resources and damage productive land in the surrounding areas. To
mitigate possible effects of cement-laden water and slurry, the Contractor shall i) collect and
retain all the concrete washout water and solids in leak proof containers, so that this does not
reach the soil surface and then migrate to surface waters or into the ground water, ii) recycle
the collected concrete washout water and solids, and/or iii) use of a washout pit made with a
plastic lining that can be dug into the ground or built above grade.
11. Construction drainage system
114. The contractor shall construct drainage systems to facilitate drainage and rain water
natural channels. The contractor will also provide adequate short-term drainage away from
construction sites to prevent ponding and flooding.
12. Workers health, safety and hygiene
115. Construction sites are likely to have public health impacts. Contractors will ensure that
no untreated wastewater is discharged in the river and that no site-specific landfills will be
established at the construction camps. There will be a potential for diseases to be transmitted,
exacerbated by inadequate health and safety practices. The contractor will therefore be
required to recruit or designate a health and safety officer to address such concerns in the
work sites and liaise/work with the nearby communities.
116. Mitigation measures include: 1) proper fencing, protective barriers, and buffer zones
should be provided around all construction sites, 2) sufficient signage and information
disclosure, and supervisors and night guards should be placed, 3) worker and public safety
guidelines should be followed, 4) provide adequate sanitation and waste disposal at
construction sites, 5) the contractor will not hire children and pregnant women, 6) standing
water suitable for disease vector breeding should be filled in, 7) worker education and
awareness seminars for construction hazards should be given at the beginning of the
construction phase. A construction site safety program should be developed and distributed
to workers, 8) appropriate safety clothing, footwear, gloves, hard hats, eye protection and
other PPE should be mandatory for all construction workers, 9) adequate medical services
must be on site or nearby all construction site, 10) drinking water must be provided at all
construction sites, 11) sufficient lighting be used during necessary night work, and 12) all
construction sites should be examined daily to ensure unsafe conditions are removed.
34
13. Traffic safety and management
117. Throughout the construction period, the contractor should ensure that affected people
are provided adequate and safe access to properties (structures, land, etc.). During
construction, the contractor is responsible for ensuring that all construction vehicles observe
speed limits on the construction sites and to provide adequate signage, barriers, and flag
persons for traffic control. Sign postings such as ‘men working’, ‘Keep left/right’, ‘construction
ahead’, and ‘speed limit’, should be used for traffic management and road safety. As much as
possible, road works will be confined to one half of the road width at each section to provide
access to pedestrian and vehicles during construction works.
14. Ecological environment (Flora and Fauna)
118. Rehabilitation work will directly cause minor degradation of the local ecology through
the clearance of small areas of vegetation (mainly grasses) at major work sites. A short-term
impact on ecology along the rehabilitated road is likely to occur in worksites during the
construction period due to minor vegetation clearance (mainly grasses, not trees). Vegetative
cover stripped from the locations described above will be kept for slope protection.
119. Meanwhile, the potential impacts from construction worker camps are poaching of
edible animals and birds of the locality in spite of prohibitions. The contractors’ will be
responsible for providing adequate knowledge to the workers regarding the protection of
fauna. In short, all workers will be prohibited from hunting wild animals.
15. Damaged to properties
120. Another potential impact during construction is damaged to properties (structures,
irrigation, farmland) and access roads due to civil works, transport of materials and other
project-related activities. To address this impact, the contractor will immediately repair and/or
compensate for any damage that it causes to properties (houses, farmlands, aquaculture
ponds, irrigation canals, and others), community facilities such as water supply, power supply,
communication facilities and the like. Access roads used for transport of construction materials
and other construction-related activities will be maintained by the Contractor in at least in their
pre-project condition for the duration of construction.
16. Concrete washout
121. The discharge of cement-laden water and slurry during concrete mixing may
contaminate water resources and damage productive land in the surrounding areas. To
mitigate possible effects of cement-laden water and slurry, the Contractor shall 1) collect and
retain all the concrete washout water and solids in leak proof containers, so that this does not
reach the soil surface and then migrate to surface waters or into the ground water, 2) recycle
the collected concrete washout water and solids, and/or 3) use of a washout pit made with a
plastic lining that can be dug into the ground or built above grade.
35
17. Use of Hazardous Substances
122. Storage and use of fuel, lubricant and other toxic and hazardous chemicals will have
potential impacts on soil surface and groundwater contamination. To address this impact,
vehicle maintenance and refueling will be confined to areas in construction sites designed
(with concrete flooring, drainage leading to oil and water separator, etc.) to contain spilled
lubricants and fuels. Spill waste will be disposed to sites approved by the concerned
government agency and following national regulations. Adequate precaution will be taken to
prevent oil/lubricant/ hazardous substances contamination of channel beds. Spillage if any will
be immediately cleared with utmost caution to leave no traces. All areas intended for storage
of hazardous materials will be quarantined and provided with adequate facilities to combat
emergency situations such as fire, spills, etc. in compliance with all the applicable statutory
stipulation. The personnel in-charge of these sites will be properly trained and these areas
will be access controlled and entry will be allowed only under authorization. Hazardous wastes
will be collected, stored, transported and disposed consistent with national regulations to
ensure that these will not cause pollution of surrounding areas.
18. Public safety
123. `Some of the mitigation measures that should be implemented are as follows: To
mitigate this impact, the following should be addressed by the Contractor: 1) installation of
sturdy fencing around excavation areas and construction sites, 2) provision of proper signage
and lighting at night at the periphery of the construction site to warn and direct traffic and
pedestrians, 3) deployment of security personnel in hazardous areas to restrict public access,
4) imposition of speed limits for construction vehicles along residential areas and where there
are other sensitive receptors, and 5) orientation of drivers on safe driving practices to minimize
accidents and to prevent spill of hazardous substances and other construction materials during
transport.
C. Operation and Maintenance (O&M) Phase
1. Operation of upgraded access road
124. The rehabilitation of Rehabilitation of access road will have potentials impacts both
positive and negative to the area. The negative impacts will directly involve the increased risk
of accident or injury, air pollution and noise, and unplanned urbanization. However, the
positive impacts will mainly focus on increased delivery of agricultural products, provide
access to natural resources management project sites, and open for tourism businesses. To
mitigate these impacts, the LGU of San Miguel and other concerned agencies shall initiate
and implement the following: 1) set speed limit when passing through populated area, 2)
provide appropriate warning signs and lighting, 3) regular removal of debris, logs and other
36
materials along drainage canals to avoid clogging, 4) regular vegetation control along run-off
area to ensure free flow, 5) ensure that existing environmental management policies are
effectively implemented and proper coordination involves different agencies, 6) adherence to
land use and zoning regulations, and 7) promote tourism in the area through advertisement
from the local and nationwide venue.
VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION
A. Stakeholder Consultations
125. The IEE process included stakeholder participation and consultation to help LGUs
achieve public acceptance of the sub-project. Series of consultations with barangay Ilaya and
local government unit of Inabanga confirmed that the rehabilitation of the access road is
essential for economic development.
126. During these consultations on March 26, 2017 and June 8, 2017, the proponent with
technical assistance of consultant has made presentation of the sub-project describing the
objective of the consultations, project description, proposed civil works, and anticipated
environmental impacts and their mitigation measures. The consultations went very well and
effective and the discussions were documented. The results of the consultation were positive,
with local people considering that the road will bring significant economic benefits to the
barangays and increase trade flows (Table 7).
127. Concerns on the sub-project mainly revolved on its construction phase which can be
mitigated. There is no long term negative environmental impact assessed by the participants.
Majority of the respondents cited ease of transport as one of the direct benefits of the road;
majority of them as well are not anticipating any negative impact of the sub-project to the
environment, though one of the respondents mentioned that the road might be a corridor for
illegal loggers to access the forest land so he suggested an intensified barangay patrolling
during the operation phase of the access road.
128. The influence barangay conducted a barangay consultation where they discussed
priority projects of their barangay (Appendix No. 2). Consistent with the site validation result
conducted, the sub-project was assessed to unlikely cause significant adverse impact on the
environment; in fact, the sub-project is identified by the community members to improve the
status of the environment as it will serve as a corridor in mitigating forest fires in the area.
37
Table 7. Results of the stakeholder’s consultations at Brgy. Ilaya, Inabanga Bohol
Date of Consultations: March 26, 2017, June 8, 2017
Venue: Bgry. Ilaya, Inabanga, Bohol
Total number of participants: 15 and 90
Group represented: local residents, Parent-Teacher Association, ISFA of Inabanga Bohol Inc.
members, Barangay officials, MPDO, PPDO staff, Consultants
38
39
129. Barangay Ilaya endorsed the proposed road rehabilitation Access Road for inclusion
to INREMP rural infrastructure component (Appendix No. 3).
130. With the involvement of the LGU in the sub-project activities of INREMP particularly
in the implementation of rural infrastructure support facilities, they dedicated time and effort
in participating with orientation, consultation, planning and training activities (Appendix No.
4). Indeed, a municipal resolution was crafted affirming the interest of the local government
unit to apply, negotiate, avail financing grant from the INREMP of the DENR thru the municipal
development fund office, and undertake other acts necessary for the effective implementation
of the access road.
B. Information Disclosure
131. After study completion, the IEE documenting the mitigation measures and consultation
process will be submitted to ADB for posting on their website, DENR-FMB, the Municipality of
Inabanga, Bohol and the affected Barangay office, the Provincial Environmental and Natural
Resource Officer, and DENR regional office, which will make them available to the public.
More informal and vigorous level of disclosure and consultation will be done during
implementation through:
• The preparation and dissemination of a brochure in local languages, explaining the
affected peoples’ entitlements and the procedures for obtaining compensation for
temporary disturbances, trees, crops, and land for construction camps and recording
grievances; and
• Setting up a formal grievance redress committee with a representation from the
affected people. Field consultant in association with the Contractor will be responsible
for managing the effective grievance redress program.
VII. GRIEVANCE REDRESS MECHANISM
132. The Local Government Unit of Inabanga has properly conducted the consultations
with the different stakeholders of the sub-project site. However, it still has to make room for
possible issues, concerns, or grievances and disputes arising from the communities in relation
to the project implementation. Thus, it sets up a Grievance Redress Mechanism to provide a
venue for resolving grievances and disputes even at the lowest level. This will be done to
resolve disputes as early and as quickly as possible before it escalates to an unmanageable
level.
40
133. Since, the community consultations were conducted smoothly and no adverse or
violent reactions have been noted, there are only minor grievances that are anticipated which
may arise. These are listed below:
1) Road accessibility related grievances – This may include complaints from
communities using the roads under repair or construction due to temporary
obstruction, which may cause delay in travel time and other inconveniences of the
travelling public.
2) Construction related grievances – Community members specially those adjacent
lot owners may demand to be hired as part of the labor force in the project
construction/implementation. This may also include complaints of community
members regarding noise, drainage, and etc.
134. Since, the community consultations were conducted smoothly and no adverse or
violent reactions have been noted, there are only minor grievances that are anticipated which
may arise. These are listed below:
1) Road accessibility related grievances – This may include complaints from
communities using the roads under repair or construction due to temporary
obstruction, which may cause delay in travel time and other inconveniences of the
travelling public.
2) Construction related grievances – Community members may demand to be hired
as part of the labor force in the project construction/implementation. This may also
include complaints of community members regarding noise, drainage, and etc.
135. A subproject-specific grievance redress mechanism will be established at the PPCO
to receive, evaluate and facilitate the complaints/grievances of affected persons on the sub-
project’s environmental performance. This mechanism will be disclosed to the host
communities before start of civil works.
136. The grievance redress committee (GRC) will be chaired by the PPCO head. Members
will include the following: (i) designated GRM officer of PPCO, (ii) contractor’s highest official
at the site such as the Construction Manager or the Construction Superintendent; and (iii)
barangay chairperson. For the quick filing of complaints, the GRC will use the attached
grievance intake form (Appendix No. 5). The PPCO's GRM officer will be responsible for
registration of grievances and communication with the aggrieved party.
41
137. The steps to be followed in filing complaints and the procedures for redress are the
following:
(i) complainant will provide the background and file the complaint verbally or in
writing to the PPCO, and the PPCO's GRM officer will assist the complainant in
filling-up the grievance intake form;
(ii) within 2 working days, the GRM Officer, contractor’s representative, and
complainant will discuss if the complaint can be resolved without calling for a
GRC meeting;
(iii) within 3 days of lodging the complaint, the PPCO's GRM officer will provide the
complainant a written feedback on the process, steps and timeframe for resolving
the complaint.
(iv) if the complaint cannot be resolved, a GRC meeting with the complainant will be
called within 5 working days;
(v) the GRC will have 15 working days to resolve the complaint;
(vi) the complainant will receive feedback from the PPCO's GRM officer within 5
working days after the various steps of the GRM are completed; and
(vii) if unsatisfied with the decision, the existence of the GRC will not impede the
complainant's access to the Government's judicial, administrative remedies or
through concerned government agencies (e.g., Community Environment and
Natural Resources Office and Provincial Environment and Natural Resources
Office of DENR, Regional offices of the Environmental Management Bureau, etc.)
138. The GRC will receive, follow-up and prepare monthly reports regarding all complaints,
disputes and/or questions received about the Project and corresponding actions taken to
resolve the issues. These reports will be included in the semi-annual environmental
monitoring reports to be submitted to ADB.
VIII. ENVIRONMENTAL MANAGEMENT PLAN
A. Implementation Arrangements
139. Institutions responsible for executing and monitoring the implementation of the EMP are presented in Table 8.
42
Table 8. Responsibilities for EMP Implementation.
Agency Responsibilities
LGU of Inabanga, Bohol • Executing agency with overall responsibility for project construction and
operation
• Ensure that sufficient funds are available to properly implement the EMP
• Ensure that Project implementation complies with Government
environmental policies and regulations
• Ensure that the Project, regardless of financing source, complies with the
provisions of the EMP and ADB Safeguard Policy Statement 2009
• Obtain necessary environmental approval(s) from the Environmental
Management Bureau and/or other concerned government agencies prior to
commencement of civil works
• Ensure that tender and contract documents for design, supervision and civil
works include the relevant EMP requirements
• Establish an environmental grievance redress mechanism, as described in
the IEE, to receive and facilitate resolution of affected peoples' concerns
• Submit semi-annual monitoring reports on EMP implementation to ADB.
PPMO and WMPCO • Closely monitor contractor’s environmental performance and over-all
implementation of the EMP
• Prepare semi-annual environmental monitoring reports on status of EMP
implementation for submission to ADB
• Based on the results of EMP monitoring, identify environmental corrective
actions and prepare a corrective action plan, as necessary, for submission
to ADB
• Responsible for coordinating with EMB, Local Government Units (LGU),
and other concerned agencies related to environmental aspects for
maintaining project`s compliance with environmental permits.
TA - PMIC and NPCO • . Engage environment specialists who will undertake supervision and
monitoring of EMP implementation and contractor’s environmental
performance
• As part of day-to-day project supervision, closely supervise and monitor the
contractor’s implementation of mitigation measures specified in the EMP
• Assist PMU and WMPCO in preparing semi-annual environmental
monitoring reports on status of EMP implementation. Such report will
include results of ambient environmental monitoring to be conducted by the
contractors.
Contractors • Recruit qualified environmental and safety officer to ensure compliance with
environmental statutory requirements, contractual obligations and EMP
provisions
• Provide sufficient funding and human resources for proper and timely
implementation of required mitigation and monitoring measures in the EMP
43
Table 8. Responsibilities for EMP Implementation.
Agency Responsibilities
• Implement additional environmental mitigation measures, as necessary, to
avoid, minimize and/or compensate for adverse impacts due to
construction works and related activities performed by the contractor.
EMB - DENR • Review and approve environmental assessment reports required by the
Government
• Undertake monitoring of the project’s environmental performance based on
their mandate
ADB • Conduct periodic site visits to assess status of EMP implementation and
over-all environmental performance of the Project
• Review environmental monitoring reports submitted by the executing
agency to ensure that adverse impacts and risks are properly addressed
• Publicly disclose through posting on ADB’s website environmental
monitoring reports, corrective action plans, new or updated IEE (if any)
prepared by the executing agency during project implementation
B. Environmental Mitigation
140. Table 9 presents the environmental mitigation measures to address anticipated
adverse impacts of the Sub-project. The EMP also shows responsibilities for the
implementation of mitigation measures and corresponding supervision and monitoring.
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Pre-Construction Phase
Confirmation of no
required resettlement,
relocations, and
compensation
No negative
environmental
impacts
Conducted Consultation
meetings with barangay officials
and concerned POs’ officers and
members
Conducted information
awareness campaign regarding
subproject location
LGU of
Inabanga
WMPCO
PPMO
44
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Identification and
prioritization of road
section where re-
gravelling will be done
Lack of information
and/or low
participation of the
community,
particularly women
and marginalized
sectors
Subproject sites validation with
following conditions:
ensure that the INREMP
validation process on subproject
implementation is being complied
with
hold consultative meetings with
balanced representation of men
and women and affected persons
on the subproject components
and management plan
LGU of
Inabanga
WMPCO
PPMO
Preparation of detailed
engineering designs and
programs of work for the
subproject
Minimize negative
environmental
impacts
Work with LGU RI Engineer for the
completion of the proposed
upgraded access road detailed
designs and to ensure the following
measures are included:
identification of spill management
prevention and emergency
response plans for all
construction sites;
locate aggregate borrow pits and
rock supply areas away from
human settlements with fencing
and access barriers;
for local residents: include
specific plan to notify and provide
them schedule to minimize
disruption to normal commercial
and residential activities
LGU of
Inabanga
WMPCO
PPMO
Recruitment of workers Gender
discrimination and
tendency to recruit
outsiders
Hire local workers as much as
possible, and give equal privilege
for women to get involved in
selected tasks appropriate for
them
Contractor
LGU of
Inabanga
/
WMPCO
PPMO
Construction Phase
Construction materials
acquisition, transport
access, and storage
system
Pollution, injury,
interrupted usual
road use, disrupted
access, noise
Procure construction
materials from sources with
valid environmental
clearances, i.e. for sand,
gravel and timber from those
with valid DENR-MGB/EMB
permits.
All borrow pits and quarries
should be approved by
Municipal Engineering
Division.
Select pits and quarries in
areas with low gradient and as
close as possible to
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
45
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
construction the sites.
Required aggregate volumes
must be carefully calculated
prior to extraction to prevent
wastage.
Pits and quarries should not be
located near surface waters,
forested areas, critical habitat
for wildlife, or cultural objects
and landmarks.
If aggregate quarrying from
fluvial environments is required
small streams and rivers should
be used, and dry alluvial plains
preferred.
All topsoil and overburden
removed should be stockpiled
for later restoration.
All borrow pits and quarries
should have a fence perimeter
with signage to keep public
away.
After use pits and quarries
should be dewatered and
permanent fences installed with
signage to keep public out, and
restored as much as possible
using original overburden and
topsoil.
Unstable slope conditions
in/adjacent to the quarry or pit
caused by the extractions
should be rectified with tree
planting.
Define & schedule how
materials are extracted from
borrow pits and rock quarries,
transported, and handled &
stored at sites.
Define and schedule how
fabricated materials such as
steel, wood structures, and
scaffolding will be transported
and handled.
All aggregate loads on trucks
should be covered.
Clearing and removal of
obstructions
Damage landscape Restrict vegetation removal to
within RoWs.
In case, no trees will be removed
without prior approval of
Contractor LGU of
Inabanga
/
WMPCO
Part of the
contractor’
s contract
46
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
concerned government agency.
The contractor will not use or
permit the use of wood as a fuel
for the execution of any part of
the works, including but not
limited to the extent practicable
shall ensure that fuels other than
wood are used for cooking.
Within RoWs, minimize land
cover removals, and install
protective physical barriers
around trees.
All RoWs to be re-vegetated and
landscaped after construction
completed.
Consult PENRO/CENRO to
determine the most successful
restoration strategy and
techniques.
PPMO
Soil erosion High suspended
solid contents of
river,
sedimentation.
Berms, and plastic sheet
fencing should be placed
around all excavations and
earthwork areas.
Earthworks should be
conducted during dry periods.
Maintain a stockpile of topsoil
for immediate site restoration
following backfilling.
Protect exposed or cut slopes
with planted vegetation and
have a slope stabilization
protocol ready.
Re-vegetate all soil exposure
areas immediately after work is
completed.
minimize damage and cutting of
surrounding vegetation during
slope formation,
prevent erosion and protect the
cut slope with temporary
drainage as soon as practicable
after cutting, and
If new erosion occurs
accidentally, back fill
immediately to restore original
contours.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
47
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Ground surface leveling
and gravelling of
existing road
Degradation of
terrestrial and
aquatic resources,
and decreased
water quality
All construction sites should be
located away from forested or
plantation areas as much as
possible.
All construction fluids such as
oils, and fuels should be stored
and handled away from forested
and plantation areas.
No waste of any kind is to be
discarded on land or in
forests/plantations.
Erosion channels must be built
around aggregate stockpile areas
to contain rain-induced erosion.
Earthworks should be conducted
during dry periods.
All construction fluids such as
oils, and fuels should be stored
and handled with extra care away
from surface waters.
No waste of any kind is to be
thrown in surface waters.
No washing or repair of
machinery near surface waters.
Pit latrines to be located away
from surface waters.
No unnecessary earthworks in or
adjacent to water courses.
No aggregate mining from rivers
or lakes.
Minimize the use of heavy
equipment at steep slopes.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
Civil works (Concrete
Pavement)
Air pollution, land
and water
contamination, and
traffic & access
problems,
All construction sites should be
located away from forested or
plantation areas as much as
possible.
All construction fluids such as
oils, and fuels should be stored
and handled away from
forested and plantation areas.
No waste of any kind is to be
discarded on land or in
forests/plantations.
Protective berms, plastic sheet
fencing, or silt curtains should
be placed between all
earthworks and nearby surface
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
48
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
waters.
Erosion channels must be built
around aggregate stockpile
areas to contain rain-induced
erosion.
Earthworks should be
conducted during dry periods.
All construction fluids such as
oils, and fuels should be stored
and handled with extra care
away from surface waters.
No waste of any kind is to be
thrown in surface waters.
No washing or repair of
machinery near surface waters.
Pit latrines to be located away
from surface waters.
No unnecessary earthworks in
or adjacent to water courses.
No aggregate mining from
rivers or lakes.
Implementation of noise
and dust control
measure
Noise, Dust, Air
Pollution Regularly apply wetting agents
to exposed soil and
construction roads.
Cover or keep moist all
stockpiles of construction
aggregates, and all truckloads
of aggregates.
Minimize the time for
excavations and exposed soil
are left open or exposed.
Backfill immediately after work
is completed.
As much as possible, restrict
working time between 07:00
and 17:00, in particular,
activities such as pile driving,
etc.
Maintain equipment in proper
working condition
Replace unnecessarily noisy
vehicles and machinery.
Vehicles and machinery to be
turned off when not in use.
Construct temporary noise
barriers.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
49
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Dust and noise from
borrow pits
Noise, Dust provision of noise control
measures to comply with
national standards, watering of
the earth roads close to the
settlements, use covered truck,
secure appropriate
environmental permits,
the borrow and material
dumping sites must be access
controlled to keep away
unauthorized entry of people,
grazing cattle and any other
stray animals, and
protective gear like ear plugs
will be provided to operating
personnel if they are exposed to
noise levels beyond threshold
limits.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
Implementation of spoil
management and
control measure
Contamination of
land and surface
waters from
excavated spoil,
and construction
waste
Uncontaminated spoil to be
disposed of in government –
designated sites, which must
never be in or adjacent surface
waters. Designated sites must be
clearly marked and identified.
Spoil must not be disposed of on
sloped land, near cultural
property or values, ecologically
important areas, or on/near any
other socially or ecologically
sensitive feature.
Where possible spoil should be
used at other construction sites,
or disposed in spent quarries or
borrow pits.
A record of type, estimated
volume, and source of disposed
spoil must be recorded.
Uncontaminated spoil to be
disposed of in government –
designated sites, which must
never be in or adjacent surface
waters. Designated sites must be
clearly marked and identified.
Spoil must not be disposed of on
sloped land, near cultural
property or values, ecologically
important areas, or on/near any
other socially or ecologically
sensitive feature.
Where possible spoil should be
used at other construction sites,
or disposed in spent quarries or
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
50
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
borrow pits.
A record of type, estimated
volume, and source of disposed
spoil must be recorded.
Contaminated spoil disposal must
follow government regulations
including handling, transport,
treatment (if necessary), and
disposal.
Suspected contaminated soil
must be tested, and disposed of
in designated sites identified as
per government regulations.
Before treatment or disposal
contaminated spoil must be
covered with plastic and isolated
from all human activity.
Solid and liquid
construction waste
management system
Contamination of
land and surface
waters from
construction waste
Management of general solid and
liquid waste of construction will
follow government regulations to
include covering, collecting,
handling, transporting, recycling,
and disposing waste created from
construction activities and the
work force.
Disposal areas for solid and liquid
waste must be determined by the
government.
Disposal of waste should be
catalogued for type, estimated
weigh, and source.
Construction sites should have
large garbage bins.
A schedule of solid and liquid
waste pickup and disposal must
be established and followed that
ensures construction sites are as
clean as possible.
Solid waste should be separated
and recyclables be sold to buyers
in the community.
Hazardous Waste
Collection, storage, transport,
and disposal of hazardous waste
such as used oils, gasoline, paint,
and other toxics must follow
government regulations.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
51
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Wastes should be separated
(e.g., hydrocarbons, batteries,
paints, organic solvents)
Wastes must be stored above
ground in closed, well labeled,
ventilated plastic bins in good
condition, away from construction
activity areas, all surface water,
water supplies, and cultural and
ecological sensitive receptors.
All spills must be cleaned up
completely with all contaminated
soil removed and handled with by
contaminated spoil sub-plan.
Construction drainage
system
Loss of drainage
and rain water
natural channels
Provide adequate short-term
drainage away from construction
sites to prevent ponding and
flooding.
Prevent borrow pits and quarries
to be filled with water. Pump
periodically to infiltration areas or
nearby water courses.
Install temporary storm drains or
ditches for construction sites
Ensure connections among
surface waters (ponds, streams)
are maintained or enhanced to
sustain existing storm water
storage capacity.
Protect surface waters from silt
and eroded soil.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
Water quality Water and soil Set up proper and adequate
sanitary facilities,
Ensure strict observance of
proper waste handling and
disposal and proper sanitation
including by the contractors and
its workers,
Provide wastewater treatment
facility (e.g., septic tank), and
Trucks and other vehicle
maintenance should be strictly
controlled to prevent the
discharge of waste into the river
system. Wastewater from the
construction works containing
high concentration of suspended
solids should be treated through
sedimentation tanks.
The discharge of cement-laden
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
52
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
water and slurry during concrete
mixing may contaminate water
resources and damage
productive land in the
surrounding areas. To mitigate
possible effects of cement-laden
water and slurry, the Contractor
shall 1) collect and retain all the
concrete washout water and
solids in leak proof containers, so
that this does not reach the soil
surface and then migrate to
surface waters or into the ground
water, 2) recycle the collected
concrete washout water and
solids, and/or 3) use of a
washout pit made with a plastic
lining that can be dug into the
ground or built above grade.
Implement construction
drainage system
Loss of drainage
and rain water
natural channels
Provide adequate short-term
drainage away from construction
sites to prevent ponding and
flooding.
Prevent borrow pits and quarries
to be filled with water. Pump
periodically to infiltration areas or
nearby water courses.
Install temporary storm drains or
ditches for construction sites
Ensure connections among
surface waters (ponds, streams)
are maintained or enhanced to
sustain existing storm water
storage capacity.
Protect surface waters from silt
and eroded soil.
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
Workers health, safety
and hygiene
Land and people proper fencing, protective
barriers, and buffer zones should
be provided around all
construction sites,
sufficient signage and information
disclosure, and supervisors and
night guards should be placed,
worker and public safety
guidelines should be followed,
provide adequate sanitation and
waste disposal at construction
sites,
the contractor will not hire
children and pregnant women,
standing water suitable for
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
53
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
disease vector breeding should
be filled in,
worker education and awareness
seminars for construction
hazards should be given at the
beginning of the construction
phase. A construction site safety
program should be developed
and distributed to workers,
appropriate safety clothing,
footwear, gloves, hard hats, eye
protection and other PPE should
be mandatory for all construction
workers,
adequate medical services must
be on site or nearby all
construction site,
drinking water must be provided
at all construction sites,
sufficient lighting be used during
necessary night work, and
all construction sites should be
examined daily to ensure unsafe
conditions are removed.
Traffic safety and
management
Road accidents Throughout the construction period,
the contractor will ensure that
affected people are provided
adequate and safe access to
properties (structures, land, etc.). All
construction vehicles observe speed
limits on the construction sites and to
provide adequate signage, barriers,
and flag persons for traffic control.
Sign postings such as ‘men working’,
‘Keep left/right’, ‘construction ahead’,
and ‘speed limit’, should be used for
traffic management and road safety.
As much as possible, road works will
be confined to one half of the road
width at each section to provide
access to pedestrian and vehicles
during construction works.
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
Ecological environment
(Flora and Fauna)
Minor vegetation
loss
Construction vehicles will operate
within the corridor of impact to
avoid damaging soil and
vegetation.
Avoid soil compaction around
trees. Generally the rule will be to
avoid driving heavy equipment or
trucks anywhere into the 'drip-
line' of a tree.
In case, no trees will be removed
Contractor LGU of
Inabanga
/
WMPCO
PPMO
Part of the
contractor’
s contract
54
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
without prior approval of
concerned government agency.
The contractor will not use or
permit the use of wood as a fuel
for the execution of any part of
the works.
No work camps will be located in
ecologically sensitive sites such
as protected and conservation
areas, or densely vegetated site.
Workers shall be prohibited from
hunting/trapping wildlife.
Damaged to properties Land The contractor will immediately
repair and/or compensate for any
damage that it causes to properties
(houses, farmlands, aquaculture
ponds, irrigation canals, and others),
community facilities such as water
supply, power supply,
communication facilities and the like.
Access roads used for transport of
construction materials and other
construction-related activities will be
maintained by the Contractor in at
least in their pre-project condition for
the duration of construction.
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
Concrete washout Soil and water
contamination
The Contractor shall 1) collect and
retain all the concrete washout water
and solids in leak proof containers,
so that this does not reach the soil
surface and then migrate to surface
waters or into the ground water, 2)
recycle the collected concrete
washout water and solids, and/or 3)
use of a washout pit made with a
plastic lining that can be dug into the
ground or built above grade.
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
Use of Hazardous
Substances
People, land and
water
Vehicle maintenance and refueling
will be confined to areas in
construction sites designed (with
concrete flooring, drainage leading to
oil and water separator, etc.) to
contain spilled lubricants and fuels.
Spill waste will be disposed to sites
approved by the concerned
government agency and following
national regulations. Adequate
precaution will be taken to prevent
oil/lubricant/ hazardous substances
contamination of channel beds.
Spillage if any will be immediately
cleared with utmost caution to leave
no traces. All areas intended for
storage of hazardous materials will
be quarantined and provided with
Contractor SPMU
PPMO
Part of the
Contractor’
s contract
55
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
adequate facilities to combat
emergency situations such as fire,
spills, etc. in compliance with all the
applicable statutory stipulation. The
personnel in-charge of these sites
will be properly trained and these
areas will be access controlled and
entry will be allowed only under
authorization. Hazardous wastes will
be collected, stored, transported and
disposed consistent with national
regulations to ensure that these will
not cause pollution of surrounding
areas.
Public safety People installation of sturdy fencing
around excavation areas and
construction sites,
provision of proper signage and
lighting at night at the periphery
of the construction site to warn
and direct traffic and pedestrians,
deployment of security personnel
in hazardous areas to restrict
public access,
imposition of speed limits for
construction vehicles along
residential areas and where there
are other sensitive receptors, and
orientation of drivers on safe
driving practices to minimize
accidents and to prevent spill of
hazardous substances and other
construction materials during
transport.
Operation and Maintenance (O&M) Phase
56
Table 9. Environmental Impact Mitigation Plan
Project
Component/Activity
Potential
Environmental
Impacts
Mitigation Measures Institutional
Responsibilities
Cost
Estimates
Implementation Monitor
Operation of upgraded
access road
Increased risk of
accident or injury,
air pollution and
noise.
Obstruction of run-
off along drainage
canals causing run-
off overflow leading
to erosion of the
road
Exploitation of
natural resources
in the area
Unplanned
urbanization
Increased delivery
of agricultural
products
Tourism
Set speed limit when passing
through populated area
Provide appropriate warning signs
and lighting
Regular removal of debris, logs
and other materials along
drainage canals to avoid clogging
Regular vegetation control along
run-off area to ensure free flow
Ensure that existing
environmental management
policies are effectively
implemented and proper
coordination involves different
agencies.
Adherence to land use and
zoning regulations
Promote tourism in the area
through advertisement from the
local and nationwide venue.
LGU of
Inabanga
WMPCO
PPMO
DENR
Part of the
proponents
obligation
C. Environmental Monitoring
141. Table 10 presents the environmental monitoring activities to be undertaken during
various project phases. Monitoring of the contractor’s environmental performance in terms of
implementation of mitigation measures during construction phases shall be undertaken by the
community at the barangay level and SSE. The ESS shall be assisted by TA-PMIC in
preparing semi-annual environmental monitoring reports. Such reports will be submitted by
the proponent to ADB and will be publicly disclosed on ADB’s website. The monitoring reports
shall describe in detail the status of EMP implementation and compliance issues as well as
corrective actions, if any.
142. The ESS during project implementation will be required to organize a community level
environmental monitoring. Prior to commencement of site works, the ESS and SSS shall
undertake consultations with affected residents, barangay and/or officials to encourage them
to participate in the community level environmental monitoring program. The locals shall be
allowed to freely participate during the environmental monitoring to be conducted by the LGU
together with SSS and ESS. The SSE, ESS and WMPCO shall provide orientation on how to
undertake monitoring using the Environmental Monitoring Framework shown below:
57
COMMUNITY LEVEL CONSTRUCTION MONITORING FORM
Sub-project Name:
Location:
Reporting Period:
Impact/ Mitigation Measures Compliance Attained (Yes, No,
or Partial)
Comment on Reasons for Partial or Non-Compliance
1
2
3
N
Recommendation/s:
Signature:
Date:
Table 10.Environmental Monitoring Plan
Activities Location Means of
Monitoring
Frequency of
Monitoring
Responsible
Unit
Monitoring
Cost
Pre-
Construction
Completion of
the Sub-Project
Documents
Final location
of the sub-
project
Review of the SPD Prior to issuance of
NOL
SPMO,
WMPCO,
PPCO with
SSS and
ESS, ADB
INREMP
Project Cost
58
Completion of
detailed
engineering
design in
accordance with
EMP
requirements
Final location
of the sub-
project
Review of detailed
design
documentation
Prior to approval of
detailed design
SPMO,
WMPCO,
PPCO with
SSS and
ESS, ADB
INREMP
Project Cost
Completion of
social and
environmental
safeguards
Final location
of the sub-
project
Confirm IEE report
and disclosed to
the public
Prior to issuance of
NOL
SPMO,
WMPCO,
PPCO with
SSS and
ESS, ADB
INREMP
Project Cost
Establishment
of grievance
redress
mechanism
Final location
of the sub-
project
Confirm GRM is
established and
disclosed to the
public
Prior to start of site
works
SPMO,
WMPCO,
PPCO with
SSS and ESS
INREMP
Project Cost
Construction
Implementation
of construction
phase
environmental
mitigation
measures
specified in IEE
EMP
As indicated in
IEE EMP Table
23 for specific
mitigation
measures
(e.g., sub-
project road,
borrow sites,
construction/
workers’
camps, air and
noise, water
contamination
and others)
Site visit, ocular
inspections,
interviews with
local residents,
coordination with
concerned
barangay/s
Monthly and as part
of regular project
supervision
Random checks and
to validate complaints
SPMU,
WMPCO,
PPMO, NCIP
with SSS and
ESS
INREMP
Project Cost
143. The NPCO shall submit the following environmental report documentation to ADB:
Environmental Monitoring Reports: Semi-annual environmental monitoring
reports will be submitted by NPCO to ADB. The report, which will be prepared by
ESS with assistance for TA-PMIC, will provide the following information:
Background/Context of the monitoring report (adequate information on the
project, including physical implementation progress of project activities,
scope of monitoring report, reporting period, and the monitoring
requirements including frequency of submission as agreed upon);
Compliance with applicable government laws, regulations and
requirements;
Changes in project scope and adjusted safeguard measures, if applicable;
Monitoring parameters/indicators and methods based on the monitoring
plan/program in the EMP;
59
Monitoring results compared against the objectives of safeguards or
desired outcomes documented (e.g. environmental impacts avoided or
minimized, etc.);
If noncompliance or any major gaps identified, include a corrective action
plan;
Records on disclosure of monitoring information to affected communities;
Summary of environmental mitigations and compensation measures
implemented;
Identification of key issues, or complaints from affected people, or
recommendations for improvement;
Monitoring adjustment measures recommended based on monitoring
experience/trends and stakeholders response;
Information about actual institutional arrangement for implementing the
monitoring program/plan provided or adjusted, as may be required;
Proposed items of focus for the next report and due date.
Project Completion Report: One (1) year after completion of the construction, the
NPCO through its ESS shall submit a Project Completion Report which will include
the overall environmental performance of the Sub-project.
IX. CONCLUSION AND RECOMMENDATIONS
A. Conclusion
144. The present IEE reviewed the general environmental profile of the sub-project, and
screened them to assess potential impacts. The IEE results revealed that no major negative
environmental impacts are likely to occur due to the construction activities and normal
operations after the proposed rehabilitation. Implementation of appropriate mitigation
measures during construction and operation phases will minimize the minor negative impacts
of the project to acceptable levels. To ensure that these mitigation measures are implemented
and negative impacts avoided, the measures will be included in the civil works bid and contract
specifications of the Project.
145. Rural infrastructures like roads, arguably, are vital structures needed to spur economic
development in Inabanga, Bohol, with full potentials and opportunities owing to its varied
development zones and natural resources.
146. The rehabilitation of Ilaya to Datag road project shall be a crucial infrastructure for
uplifting the quality of life of the people by providing an all-year-round easy and affordable
access, improving the prompt delivery of basic services, increasing economic opportunities,
and supporting the NRM project activities of the constituents, thus supporting the developing
economy of Inabanga and cascading benefits to the entire province.
60
147. Hence, the project will have an overall beneficial impact and will have minor negative
impacts that will be carefully monitored and adequately mitigated through implementation of
the EMP.
148. The main goal of the project is to support the NRM activities of POs with the end goal
of providing an all-year-round easy and affordable access to the community thereby improving
the prompt delivery of basic services, increasing economic opportunities and conditions and
uplifting the quality of life of the inhabitants, especially the constituents.
149. The project will have a direct benefit on savings in transportation cost of agricultural
and non-agricultural products, savings of passenger transportation expense, and increase in
net value added from the agricultural production as more farmlands will be utilized due to
access to market and trade and the corollary increase in agricultural productivity growth,
because of the availability of appropriate technologies to farmers. In addition, indirect will also
be experienced especially people who are near the project site. Some of the indirect benefits
are creation of jobs in the influence areas and improve economic situation of the influence
barangays, good transportation for all women and children in going to public premises like
schools, market and hospitals, increase farm produce, and increase number of cultivated
lands near the road.
150. The performance indicators that the project will be effective to the influence areas are
on socioeconomic, agricultural and environmental specifically reduce transportation cost, high
agricultural traffic savings in transportation cost and high non-agricultural traffic savings in
transportation cost. Whereas, performance indicators that the project will be effective to the
NRM site will be increased production of farmlands, increase number of hectares cultivated
lands and easier access to transport inputs from market to farm
151. The Rehabilitation of the access road will boost the economic activities of the influence
area which is currently experiencing stagnation mainly due to inaccessibility. With the project,
socio-economic services will be easier not only for the public sector, but also to private and
semi-private providers. This will entice the community to gradually eliminate economic
activities in the forest protection zone, and instead, concentrating their activities in the forest
production zone of the WMA. In this way, the people will become the guardian of the natural
resources of the upper slopes of the WMA guaranteeing stable supply of water and other
natural resources in the lower portion of the watershed.
B. Recommendations
152. Regular monitoring by the LGU staff (engineering office) and the DENR to make sure
that the provisions in the contract are followed by the contractor;
61
153. Involvement of the PO/IP and barangay officials in monitoring and evaluation to make
sure that mitigating measures as stated in the EMP are implemented by the contractor;
154. Regular maintenance of the rehabilitated road in order to prolong its service to the
community;
155. The proposed road rehabilitation project will indeed enhance the economic
opportunities and environmental conditions of the influence barangays, thus deserves
support.
62
APPENDICES
63
Appendix 1. Photographs of the Proposed Road Rehabilitation Subproject
64
Appendix 2. Stakeholder Views of the Road Rehabilitation in Ilaya
65
66
Stakeholder Views of the Road Rehabilitation in Ilaya last March 26, 2017
67
68
Appendix 3. Brgy. Ilaya Minutes; Endorsement; Attendance; Photo Documentation
69
70
71
72
73
74
ISFA Minutes; Endorsement; Attendance; Photo Documentation
75
76
77
78
79
80
81
Appendix 4. PO Resolution Endorsing the Sub-project
82
83
84
85
86
87
88
89
Appendix 5. Grievance Intake Form
Name of Project, Subproject and Location
Project (indicate name of project) welcomes complaints, suggestions, comments and queries regarding the project implementation and its
stakeholders. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for
clarification and feedback.
Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing
"(CONFIDENTIAL)" above your name.
Thank you.
Contact Information
Name Gender □ Male
□ Female
Home Address
Age
Phone No.
City/Province Email
Complaint/Suggestion/Comment/Question Please provide the details (who, what, where and how) of your
grievance below:
90
How do you want us to reach you for feedback or update on your comment/grievance?
Portion to be filled in by PPCO staff (designated Grievance Redress Mechanism Officer):
Date received:
Received
through:
__ In person __ mail __ email __ fax __ phone __ sms
91
Name of staff
who received
comment/
complaint
Position of staff:
Type of
Grievance:
Remarks
Signature of
staff
Updates on the case:
Date: Update Updated by (Name, Signature and
Designation)
92