Page 1: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

400kV Underground Cable Construction

Tim Inglehearn

Page 2: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

2

Contents

� Underground cable components

� Access and preparation for construction

� Underground cable construction

� Reinstatement

� Inspection and maintenance

� Sealing end compounds

Page 3: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

3

Underground Cable Components

� 150mm diameter cables, made up of copper core, cross linked polyethylene insulation, seamless corrugated aluminium sheath and PVC outer sheath

� Max. 18 cables would be needed, laid in 6 x groups of 3

� Separation required to allow heat to dissipate

� Joints required every 500 – 800m (depends on cable manufacture)

� Sealing end compounds required at either end of underground section

Page 4: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

4

Access for Construction

� Approx. 65m wide working

area, protected by post and

wire fencing

� Temporary trackway provide

vehicle access along entire

route

� Vegetation clearance across

working area

� Drainage improvement works

� Temporary soil storage

Access, Working Areas and Ground Preparation

Page 5: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

5

Underground Cable Construction

� Excavators to clear working area, dig trenches and improve drainage

� Delivery of materials to site using 38 tonne lorries (cables on drums)

� Tractors and other smaller vehicles used to transport materials within cable route

� Backfill delivered to site and surplus spoil removed

Machinery Required

Page 6: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

6

Cable trenches and laying

� Excavation of 6 trenches within

working area

� Timber reinforcement to trench sides

� Cement Bound Sand bed

� Cables laid at a depth of 1.1m on

CBS bed and surrounded by an

additional CBS layer

� Concrete protective tiles

� Warning tapes

Underground Cable Construction

Page 7: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

7

Underground Cable Construction

Cable trenches and laying –example of section through a working area

Page 8: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

8

Underground Cable Construction

Cable jointing

� Joints required every 500 – 800m

depending on length of cables

� Joints are made in controlled clean

conditions

� Technically demanding and labour

intensive

� Copper conductors joined with a

compression ferrule

� Insulation hand wrapped

� Protected by glass fibre box filled

with resin or bitumen

Page 9: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

9

Reinstatement

� Reinstatement of soil above

cable trench and across

working area

� Temporary access tracks and

site fencing removed

� Care needs to be taken with

replacement of hedgerows and

fencing – restrictions apply

� Permanent tree loss over cable

swathe

Page 10: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

10

Inspection and Maintenance

� Inspection is carried out at a

min. every 3 years using test

equipment carried in vans

� Monitoring is carried out via fibre

optic cables installed with the

power cables

� Excavation required to carry out

cable repairs

� Cable replacement every 40

years (approx.)

Page 11: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

11

Sealing End Compounds

� SEC provides connection between overhead line and underground cables

� Area protected by 2.4m high pallisade fence with electrified fence inside

� Permanent vehicle access required

� Terminal overhead line tower with downleads

� Cable sealing ends emerge from ground

Page 12: 400kV Underground Cable Construction · Cable trenches and laying Excavation of 6 trenches within working area ... Underground Cable Construction Cable jointing Joints required every

12

Sealing End Compounds

2.4m palisade

fence with electrified fence above

Surge

arrestor

Downlead

from OHL tower

Cable sealing end

Insulated post

Height barrier