External Environmental Monitoring Report External Environmental Monitoring Report (July 2018 September 2019) February 2020 VIE: Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) Prepared by TPF Getinsa Euroestudios (Project Management Support Phase 2 Consultant) for Ha Noi People’s Committee and the Asian Development Bank.

Transcript of 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System...

Page 1: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

External Environmental Monitoring Report

External Environmental Monitoring Report (July 2018 – September 2019) February 2020

VIE: Ha Noi Metro Rail System Project

(Line 3: Nhon – Ha Noi Station Section)

Prepared by TPF Getinsa Euroestudios (Project Management Support Phase 2 Consultant) for Ha Noi People’s Committee and the Asian Development Bank.

Page 2: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

NOTE

In this report, “$” refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

Annual Report

External Report on Verification of Environmental Monitoring Information

Project Number: 40080-013 Loan Number: 2741-VIE Report Time: 06

Reporting Period: July 2018 to September 2019

Report Code: ERVEM_22.00

Ha Noi Metro Rail System Project (Line 3 Nhon-Ha Noi Station Section)

Hanoi, November 2019

Page 4: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

AMENDMENTS RECORD

Revision Date Amendment Description number

01 30/10/2019 Sixth version

Prepared by:

Date: / /2019 Checked by:

Bui Nguyen Pho External Environmental Specialist

José Carlos Pazos Riaño Team Leader

Page 5: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

TABLE OF CONTENT

EXECUTIVE SUMMARY ....................................................................................................... 1

A. Project Background and main features ........................................................................... 1 B. Methodology of the works .............................................................................................. 1 C. Main Findings and Recommendations ........................................................................... 2 D. Main issues detected in document and recommendations ............................................. 3 E. Conclusion and recommendations: ................................................................................ 6

1 INTRODUCTION ................................................................................................................ 7

1.1 Project background ....................................................................................................... 7 1.2 Objective and Purpose of the report ............................................................................. 7 1.3 Progress of Project Implementation .............................................................................. 7

2 ENVIRONMENTAL MANAGEMENT AND MONITORING FRAMEWORK ....................... 12

2.1 APPLICABLE POLICIES, LAWS, DECREES, REGULATIONS AND STANDARDS ... 12 2.1.1 Vietnam Environmental Laws, Regulations and Standards ..................................... 12 2.1.2 ADB Safeguard Policy and Environmental Safeguards ........................................... 13

2.2 Institutional arrangements for EMP Implementation and Monitoring ........................... 13

3 Methodology of Independent Environmental Verification Works ................................ 17

3.1 Desk review ................................................................................................................ 18 3.2 Site Inspection and Interviews with households along the Project ............................... 19 3.3 Constraints found during the Independent Environmental Auditing Works (IEAW) ...... 19

4 ASSESSMENT ON THE EMP IMPLEMENTATION AND MAIN FINDINGS ..................... 20

4.1 Environmental, health and safety officers and specialist mobilization ......................... 22 4.2 Results of Semi-annual environmental monitoring reports .......................................... 25 4.2.1 Semi-annual environmental monitoring reports ....................................................... 25 4.2.2 Construction Environmental Management Plans (CEMPs) ..................................... 25 4.2.3 Monthly Environmental monitoring report of the Contractors................................... 26 4.2.4 Environmental Effect Monitoring report of the Contractors ...................................... 26

4.3 Approved disposal locations ....................................................................................... 31 4.4 Concrete batching plants, approvals ........................................................................... 31 4.5 Grievance redress and status of complaints ............................................................... 31 4.5.1 Grievance Redress Mechanism .............................................................................. 31 4.5.2 Complaints received ............................................................................................... 31 4.5.3 Interview with affected people ................................................................................. 31

4.6 Tree Relocation .......................................................................................................... 32

5 COMPLIANCE WITH EMP. ENVIRONMENTAL MAIN FINDINGS ................................... 34

5.1 Air Quality Impacts:..................................................................................................... 34 5.2 Noise impact: .............................................................................................................. 35 5.3 Wastewater from concrete batch plants (CBP) ........................................................... 36 5.4 Potential contamination of groundwater due to spills of fuel and other hazardous substances. ...................................................................................................................... 36 5.5 Drainage obstruction/flooding: .................................................................................... 36 5.6 Generation of solid waste: .......................................................................................... 36 5.7 Damage to community facilities .................................................................................. 37 5.8 Land Subsidence ........................................................................................................ 37 5.9 Traffic build-up along access road to the depot ........................................................... 37 5.10 Traffic congestion and access problems ................................................................... 38 5.11 Hazards to health and safety of workers and the public due to construction works ... 40 5.12 Social conflicts due to presence of workers; ............................................................. 41 5.13 Spoils generation from pier excavation Works .......................................................... 41

Page 6: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

5.14 Sedimentation of Thu Le Lake and generation of sediment-laden wastewater from pier excavations ............................................................................................................... 42 5.15 Generation of solid wastes ........................................................................................ 42 5.16 Hazards to health and safety of workers and the public ............................................ 42 5.17 Potential damage to Undiscovered archaeological relics .......................................... 43 5.18 Potential damage to the Temple of Literature ........................................................... 44

6 CONCLUSION AND RECOMMENDATION ...................................................................... 44

APPENDICES...................................................................................................................... 46

Appendix 1: Interview questionnaire (from September - October 2019) ............................ 46 Appendix 2: Photos of site inspection ............................................................................... 47 Appendix 3: Photos of interviewed house (taken on 16th September - 16th October 2019)49 Appendix 4: Report to Donor on EHS for the meeting in April 2019 .................................. 50

Page 7: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

ABBREVIATIONS

ADB Asian Development Bank

AFD Agence Française de Development

CEMP Contractor Environmental Management Plan

CO Carbon Monoxide

CP Construction Package

CRB Citizen Reception Board (Ha Noi People’s Committee) DG Tresor Direction General du Tresor DAELIM DAELIM industrial Co., LTD - Contractor of Contract Package 01

DONRE Department of Natural Resources and Environment DOT Department of Transportation

EATC Environmental Analyzing and Technique Joint Stock Company

EIA Environmental Impact Assessment

EIB European Investment Bank

EMoP Environmental Monitoring Plan EMP Environmental Management Plan

GRM Grievance Redress Mechanism

HANCORP Hanoi Construction Corporation - Contractor of Contract Package 05

HPC Hanoi Peoples’ Committee

HSE Health, Safety and Environment HGU JV Hyundai Engineering & Construction Co., Ltd and GHELLA S.p.A.

– For Underground section & Stations – Contractor of Contract Package 03

IEAW Independent Environmental Auditing Works IEC Independent Environmental Consultant IEVR Independent Environmental Verification Report MONRE Ministry of Natural Resources and Environment MOU Memorandum of Understanding (ADB) MRB Hanoi Metropolitan Railway Management Board MRP Hanoi Metropolitan Railway Management Project, Nhon - Hanoi Railway

Station

NO2 nitrogen dioxide

PCR Physical Cultural Resources

PIC Project Implementation Consultant

PID1 Project implementation department 1

PMS2 Project Management Support, Phase 2 POSCO POSCO E&C Co., LTD - Contractor of Contract Package 02 PPE Personal Protective Equipment

QCVN Viet Nam National Environmental Standards

SEMR Semi-annual Environmental Monitoring Report

SO2 sulfur dioxide SPS Safeguard Policy Statement URENCO Urban Environmental Company

Page 8: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

LIST OF TABLES

Table 1. Main Scope of Packages ....................................................................................... 1

Table 2. Main issues identified in document and recommendations ............................... 4

Table 3. Work progress as of 30 September 2019 ............................................................. 8

Table 4. The Government Environmental Requirements and Compliance Levels ........ 12

Table 5. Document types, focused information and expected outputs .......................... 18

Table 6. List of Key personnel in charge on environmental and safety of Contractors 23

Table 7. The status of CEMP ............................................................................................. 25

Table 8. Summary of the environmental monitoring program of Contractors and

requirement of the report EIA 8/2013-ADB .............................................................. 26

Table 9. Environmental monitoring implemented by construction Contractors during

July 2018 – September 2019 .................................................................................... 28

Table 10. List of Disposal Areas ....................................................................................... 30

Table 11. Claims raised by the interviewed affected people on 10 September 2019 ..... 32

Table 12. Tree Relocation Status ...................................................................................... 33

Table 13. Tree relocation status ........................................................................................ 50

Table 14. Summary of actions’ status .............................................................................. 51

Table 15. HSE training courses ...................................................................................55

LIST OF FIGURES

Figure 1. The Project Map.................................................................................................. 11

Figure 2. Environmental and Safety management and monitoring structure ................ 14

Figure 3. Reporting Process chart .................................................................................... 15

Page 9: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

1

EXECUTIVE SUMMARY

A. Project Background and main features

1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass Transit Model in urban area of Hanoi. The Project comprises a 12.5 km long section that goes from Nhon along the National Road 32 and into the urban area of Hanoi. The elevated section has a total length of 8.5 km with 8 stations, whereas the underground section has a length of 4 km including 4 underground stations, plus a 500 m long transition section. 2. The Project is divided into nine construction packages (CP01 to CP09). The first five are mainly related to the execution of the civil works (CP01: Evaluated section- line; CP02: Evaluated stations; CP03: Underground section and its stations; CP04: Depot infrastructure; and CP05: Depot architectural works) and the other four (CP06 - CP09) cover the supply and installation of the power supply, tracks, rolling stock, equipment, etc. The Project is co-financed by loans of the French Treasury (DG Tresor), Asian Development Bank (ADB), the Agence Franҫaise de Development (AFD) and European Investment Bank (EIB). The counterpart is the Hanoi People’s Committee (HPC). 3. Here are summarized the main features of this project: The project includes 9 main civil works and system packages, as shown in Table 1. Some of them, CP01 to CP05 are construction units with clear environmental implications.

Table 1. Main Scope of Packages

Package Title Main Scope

CP01 Construction of Elevated section - Line

Viaduct, Bridges, Access ramp to depot, Above ground part of ramp to underground station

CP02 Construction of Elevated section - Stations

Structures, Architectural finishes Low voltage and plumbing

CP03 Construction of Underground section Tunnels and Stations

Structures, Architectural finishes Low voltage and plumbing

CP04 Construction of Depot Infrastructure

Depot infrastructure

CP05 Construction of Depot Architectural works

Construction of buildings and workshops

CP06

Rail systems 1: Rolling stock, Depot equipment, OCC/SCADA, signaling, communication, power supply

Design, supply and install: Rolling stock, Depot equipment, OCC/SCADA (includes BMS instations), signaling, communication, power supply (medium voltage 22kV and traction power)

CP07 Rail systems 2: Electrical and Mechanical (E&M)

Design, supply and install: E&M systems, Ventilation systems, Firefighting systems, Lifts and escalators, Dewatering

CP08 Rail systems 3: Track Works Design, supply and install: Rails for all the line and inside the Depot (includes 3rd rail)

CP09 Rail systems 4 Automatic Fare Collection (AFC)

Design, supply and install AFC system

B. Methodology of the works

4. The applied methodology for the independent verification tasks is an adequate sequence of activities, which follows and are in accordance with the objectives and specifications of ADB, mainly as follows:

Page 10: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

2

Analysis of the monthly reports prepared by Project Implementation Consultant (PIC). It was analyzed if these reports have any wrong assertion, any lack of information and if they match with the real situation observed on site.

Direct monitoring works on site and the assessment of the environmental protection measures currently implemented. As well, the assessment of the level of compliance with ADB Safeguard Policy Statement (SPS) 2009 and the common environmental expected sensibility.

5. The assessment may include some recommendations about measures to implement or to strength them.

Independent Environment Consultant (IEC) held interviews with affected local people, households, who have claimed because of any affection due to the construction works, as well as with the environmental and safety officers of Contractors and environmental specialist of the PIC.

Finally, some other important matters were analyzed, such as the general structure of the environmental management team in each involved organization or the established mechanism for grievance treatment and its operation.

C. Main Findings and Recommendations

6. During 15 September - 15 October 2019, the Independent Environmental Consultant (IEC) inspected along project, IEC met and worked wi - 41` th Hanoi Metropolitan Railway Management Board (MRB), the implementation agency of the Project, and Contractors. In general, all Contractors have complied with environmental protection measures defined in approved Contractor’s Environmental Management Plans (CEMPs), detail as following:

- Contractors maintain regular sanitation on and off the construction site relatively well. All materials are neatly arranged within the construction site. Machinery and tools are stored in a separate warehouse. Most contractors equip rubbish bins on site. All waste, including domestic and construction wastes, is collected in a large container and removed by a functional environmental unit. legal waste collection. Hazardous wastes such as oil, contaminated soil, rags / wipers, etc. are stored and treated and treated by an environmental company (contractors who signed a waste treatment contract ).The disposal areas of Contractors, namely Thap Boi field, Vinh Quynh landfill, Van Noi landfill, were approved by PIC, MRB and Hanoi People Committee. Details are listed in Table 10.

- All Contractors have rented local houses next to the construction sites for the worker camps. A number of contractors have installed a large container for the engineers working as well as the site office in some sections along the route, this container includes a toilet for engineers for normal use. The contractor has only a few places or areas where toilets are installed for workers. In other places / areas where toilets are not installed, workers must use toilets in their worker camps or sometimes they use a large can of water in construction sites and move it out. site and clean it every day

- Contractors POSCO and DAELIM established programs called Green Saturday. Every week, all workers and officers came to construction sites to collect waste. However, according to specification of the Project and approved CEMP, all the Contractors must conduct the training to enhance the environmental management capacity but all of them did not do it.

- Contractors are fully equipped with personal protective equipment (PPE) for on-site workers such as helmets, safety shoes, gloves and reflective jackets. Workers working in confined spaces such as building septic tanks are provided with ventilation. However, workers working in high noise area / equipment are not equipped with ear protection.

Page 11: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

3

- At present, construction activities do not generate much dust. Not many unsuitable materials have been moved out of the site, so the number of dump trucks has dropped significantly. Traffic on the roads around the project is very crowded, so it is very noisy and dusty. Contractors have never sprayed water to minimize dust on existing roads, they only irrigate in the field areas, although CEMP requires contractors to spray water on existing roads to minimize dust during dry days.

- Contractors set up hard barriers and fence along the Project’s alignment to separate the construction areas and existing roads, public areas to ensure safety. After construction activities in each section were finished, Contractors immediately dismantled these barriers to return space for traffic.

- Each Contractor has one Health, Safety and Environment (HSE) team which include the key personnel listed in Table 6. Some contractor, they do not have environmental qualification or Environment Manager

- Since July 2018 to September 2019, no labor deadly accident or serious injury case, no environmental risk; but there are some accidents happened during project`s construction time.

- However, IEC detected some HSE issues which need to be improved:

✓ Some excavated material still exists on construction sites. ✓ No toilet for the workers in almost section along route. ✓ No watering to minimize dust in existing roads. ✓ The workers working in the high noise areas/equipment were not equipped with

ear protection equipment.

7. By interviewing with some households along the alignment, conducted on 26 July 2019, IEC summary some complaint of the local people to the construction activities of the Project. Interviewees said that since the Project work, this location was easy flooding and the flooded time was extended more. Sometime when it was heavy rain these households were flooded. 8. So far, activities under the Project has impacts on income of some business households adjacent to Kim Ma, Tran Hung Dao, Cat Linh streets because traffic space has been narrowed down due to the Project, so traffic is inconvenient, leading to fewer consumers.

D. Main issues detected in document and recommendations

9. The following table summarizes the main issues and findings of the independent environment verification, including the corresponding recommendations to solve gaps and to improve the environmental protection tasks during the construction period.

Page 12: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

4

Table 2. Main issues identified in document and recommendations

Issue Finding Recommendation Responsibility

Mobilization of

Health, Safety and Environment (HSE) specialist, Safety manager, Environmental manager

Generally satisfactory

HSE specialist of PIC was mobilized and in charge of checking the Contractors’ compliance with CEMP. But in fact, the safety issues were focus much more than environmental issues.

Many environment issues were not reported.

In addition to health and safety issues, HSE specialist of PIC should report in detail the environmental issues in their Monthly Process Report.

The personnel in charge of environment issues of PIC/MRB should reinforcement to inspect, supervise the Contractor compliance with environmental mitigation measures.

PIC, MRB

Most of contractors had HSE Manager or Safety Manager but did not have environmental qualification

The Contractor should mobilize officers who have environmental qualification for environmental control and management.

Timeline requirement: 20th february, 2020

CP01, CP03,

CP05

MRB does not have officer in charge of environmental issues since 2018 up to now. There is no specialist conducted regular site inspections, the review of environmental reports prepared by contractors, PIC and other all tasks related to environmental and safety issues.

MRB should assign an office to manage all related environmental and safety issues before 20th february, 2020

MRB

Semi-annual environment monitoring report (SEMR)

Generally satisfactory

SEMR (July – December) and SEMR (Jan-Jun 2019): SEMRs reflected the general information about all parties in compliance Environmental requirement of Project such as dust control plan, noise control plan, spoils disposal, fuel management, traffic management, health and safety control plan and emergency response plan, etc.

All information was stated concise and complete all necessary information of project

MRB. PMS2

Environmental monthly report

Not satisfactory

The Contractors and PIC do not have separated Environmental monthly report. All health, environment, safety and issues were included like an item in the Monthly Process Report of them.

Contractors of CP01, CP02, CP03 and CP05 conduct the

The Contractors and PIC should have a report for Environmental implementation according to approved CEMP and requirement of project. Unless the

MRB, PIC,

Contractors

Page 13: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

5

Issue Finding Recommendation Responsibility

environmental effects monitoring during the period, complying with the statement in approved CEMPs; however, the monitoring frequency of once every six months is not appropriate.

EMR of packages in this period includes:

• CP-01: July 2018.

• CP-03: July 2018, October 2018, January 2019, May 2019 and July 2019.

CP-05: there is no EMR from July 2018 - December

Contractor and PIC should report all related environmental problems more detail in the Monthly Process Report.

Timeline requirement: 20th february, 2020

Disposal areas Generally satisfactory

All four Contractors submitted the list of disposal areas to the PIC for approval and the following disposals were approved by PIC, MRB and Hanoi People Committee for each Contractor:

- CP01: 2 landfill sites in Vinh Quynh and Dong Anh

- CP02: 2 landfill sites in Vinh Quynh and Dong Anh

- CP03: 2 landfill sites in Dong Anh

- CP05: HANCORP signed a contract with Hanoi URENCO to haul and dispose spoil during construction phase.

Contractors should summary the quantity of disposal every month and submit to the Consultant to ensure the dispose/spoil was discharge in correct and approved places.

Contractors

CEMP = Contractor Environmental Management Plan, HANCORP = Hanoi Construction Corporation, HSE = Health, Safety and Environment, PCR = physical cultural resources, SEMR = Semi-annual environment monitoring report, URENCO = Urban Environmental Company

Page 14: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

6

E. Conclusion and recommendations:

10. During the independent assessment, the consultant received enthusiastic support from stakeholders such as MRB, construction Contractors CP01, CP02, CP03 and CP05. But monthly environmental reports of all packages as well as monitoring reports of CP01, CP05 were not available for review. 11. In general, the SEMRs which were submitted to ADB by MRB in 2018 and 2019 were synthetic all data and closely monitor the Contractor's environmental compliance status. The information was collected from Monthly Progress Report of PIC and records of MRB each time visit sites. Therefore, the reports accurately reflect actual situation of environmental implementation of all Contractors in the reporting period. Since July 2018, the Contractors have stopped to submit monthly Environmental Monitoring Report and semi-annual environmental quality monitoring reports to PIC. The PIC should have an environmental officer to review, follow it. 12. However, after careful research all related documents such as EIA, CEMPs, Specifications and reviewed the report that was submitted by the PIC combine with checking in site, interview the local people next to project, the IEC identify some HSE incompliance as detail: 13. The traffic is maintained in good condition with security fence and lighting, signboard system surrounding construction areas. There is no construction material or waste due to construction activities detected surrounding construction sites so that affect the traffic safety along the route. 14. Until 30 July 2019, along all the packages, 127 trees have been cut down while 395 trees have been relocated. The aftercare for relocated trees has been strictly complied with the approved method statement such as providing and maintaining appropriate watering and fertilizing activities to ensure their adaptation and growing as well as to minimize the death rate.

Page 15: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

7

1 INTRODUCTION

1.1 Project background

15. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass Transit Model in urban area of Hanoi. The Project comprises 12.4 km long section that goes from Nhon along the National Road 32 and into the urban area of Hanoi. The elevated section has a total length of 8.4 km with 8 stations, whereas the underground section has a length of 3.5 km including 4 underground stations, plus a 500 m long transition section. Error! Reference source not found. shows a general location map. 16. The Project is divided into nine construction packages (CP01 to CP09). The first five are mainly related to the execution of the civil works (CP01: Evaluated section- line; CP02: Evaluated stations; CP03: Underground section and stations; CP04: Depot infrastructure and CP05: Depot architectural works) and the other four (CP06 - CP09) cover the supply and installation of the power supply, tracks, rolling stock, equipment, etc. The Project is co-financed by loans of the French Treasury (DG Tresor), the Asian Development Bank (ADB), the Agence Franҫaise de Development (AFD) and the European Investment Bank EIB. The counterpart is the Hanoi People Committee (HPC). 17. Socially the Project will be a benefit to the population in the Project area. The population, located in the western area of Hanoi will, by using the metro, avoid traffic congestion and reduce traffic safety hazards (especially traffic accidents); reduce health-related problems (especially respiratory problems) due to air pollution and dust; and save time and benefit from a good transportation alternative to go to Hanoi Centre. 18. Beside the benefits, the Project also has potential negative impacts on the local environment during both construction and operation stages. The updated Environmental Impact Assessment (EIA) was cleared in 2013, which included the Environmental Management Plan (EMP). Five mobilized Contractors (CP-01, CP-02, CP-04, CP-05 and CP-03 mobilized in February 2017) were required to prepare Contractor’s EMP (CEMP) for detailing their mitigation action plans to address construction impacts specific to site conditions. The CEMPs of CP-01, CP-02, CP-03, CP-04 and CP-05 were approved prior to construction start.

1.2 Objective and Purpose of the report

19. As required by ADB’s Safeguard Policy Statement 2009 (SPS 2009), an external environmental monitoring expert must be mobilized when the Project has been classified as environment category A under ADB SPS 2009. Such expert shall undertake independent periodic reviews to verify the monitoring information submitted by MRB to ADB on the implementation of the environmental management plan (EMP). The external expert shall also assess if various EMP provisions are being implemented as required. This report is an external monitoring report from July 2018 to September 2019. 20. The report focuses on the assessment of EMP implementation, and finding good practices and constraints of the period from July 2018 to September 2019, with the aims at: i) Review and verify the accuracy, breadth, depth, and relevance of information provided by MRB to ADB with regard to EMP implementation; ii) Determine if EMP provisions (mitigation, monitoring, reporting, etc.) are being conducted in thorough and timely manner and in accordance with budget identified within the EMP; iii) Verification of monitoring information submitted by MRB to ADB shall be undertaken through review of environmental monitoring reports and other relevant documents, site visit and interviews with affected households, local officials and other stakeholders.

1.3 Progress of Project Implementation

21. Construction activities during the period and project’s progress by end of September 2019 are presented in the following table.

Page 16: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

8

Table 3. Work progress as of 30 September 2019 (%)

Pks Activities were carried out July 2018

Sep 2019

CP01

Starting date: 4th July 2014 ✓ These items are already completed: Pile, Pile cap, Pier, Pier cap, Bridge ✓ Superstructure (CIP Girder), Bridge Superstructure (Cantilever Segments),

Bridge ✓ Concrete Parapet (CIP Girder), Bridge Metal Parapet (FCM Bridge), Bridge ✓ Aluminum Cladding (FCM Bridge), Typical U Girder Production, Typical U

Girder ✓ Erection, Ramp Structures (Top Slab), Ramp Structures (Walls/Parapets),

Steel ✓ Handrail. All special bridges are completed ✓ Casting concrete 1st stage foundation for RIS at P341-P342 is completed.

Completed installation of aluminum cladding at 2RR Bridge. Pending works are as follows:

✓ construction of Road underneath Access bridge, to complete the drainage connection to city manhole, and relocation of noted obstructions. Site handover of viaduct to CP08

✓ Completion of MSE wall landscaping works. Completion of RIS foundation ✓ Road re-instatement, drainage works, and removal of temporary fence were

progressing at various locations

82.99 (%)

99.51 (%)

CP02

Starting date: 27th May 2014 ✓ Concourse level to Platform level structure 3909: Station 1 to 8 completed.

✓ Road reinstatement has completed at station 1, 2, 3, 4, 5, 6 & 7.

✓ Technical room at ground level (masonry): Completed at Station 1, 2, 3, 4, 5, 6&7,

and progressing at Station 8.

✓ Architecture work (masonry and screed at concourse level and platform level) is in

progress at Station 1, 2, 3, 4, 5, 6 7 & 8.

✓ Fabrication of Steel structure has started from 9th of October. PSC has to speed

✓ up the production and delivery of Main roof steel structures for Stations 1, 4 & 5.

✓ Installation of main roof at Station: Station 2, 3 & 6 - Erection of main roof structural

component was completed, on-going for final welding works. PSC has to finalize

construction documents for roof cover materials and to start installation of roof cover

promptly.

✓ Station 1, 4 & 5 - To accelerate fabrication, delivery and erection of main roof

Package CS1: Consulting Services for Project Management Support (Phase 2) under

Hanoi Metro Rail System Project (Line 3: Nhon – Hanoi Station Section)

✓ Ref: PMS2_MRB_SEMR_21.02_ver 01 Page 10 of 176

✓ Package / Contractor Construction activities structural components.

✓ Roof finishing works: Roof finishing preparation works started in Station 6.

✓ Access entrance construction: PSC has to accelerate submittal for technical design

change for S05, S06, S07 S08, construction documents for test pile, jet grouting pile

foundation, concrete & architectural drawing for upper structure, and to complete

trial pit for checking the underground obstruction for S02-S08.

✓ The Contractor has to follow-up/obtain for DOT‟s approval. ✓ Finalize HOTSA for site access to CP07 to start ECS & FFS works at Station 1 & 2,

and initiate HOTSA process for Station 3 & 4.

✓ Water pipeline and sanitary drainage pipe installation by CP02 are progressing at

Station 6.

✓ Cable tray installation by CP02 is progressing at Stations 6 & 1. Duct and FFS

installation by CP07 are progressing at Stations 6. Embedded items for walls by

CP06 are progressing at Stations 6

50.74 62.67

CP03

Starting date: 06th February 2017 ✓ At Station 10, trial fencing work started from 12/4/2018. The formal handing over to

contractor of Phase 1 (North Part) was completed. The site hand over at Small Kim

Ma Street was finalized.

✓ At Station 9 and Ramp E, trial fencing work started from 27/10/2018. The permanent

fencing already finished.

1.38 5.40

Page 17: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

9

Pks Activities were carried out July 2018

Sep 2019

✓ On 22 May 2019, HGU received the Emergency shaft from the Employer.

✓ At Station 12, trial fencing work started from 22/06/2019.

✓ The temporary site office almost completed but still not inspected.

✓ Fencing at Ramp Zone E and St.9 are completed in December 2018.

✓ Tree cutting and replanting activity: Trees at Ramp zone E&C, St.9 and St.11 are

done. At shaft and station 12 this work has a major delay.

✓ The Thu Le Detour road is partially performed up to subbase and one section was

handed over to CP1 on 15/6/2018. The area handed over back by CP01 by 10/8/2018

with 10 days delay.

✓ Ramp zone A+B: The pilot bored pile, bored pile at Ramp and its pile tests were

completed and accepted. D-wall started on 24/10/2018 and is currently done

✓ Ramp zone E: D-wall started on 22/12/2018 and is currently under progress.

✓ Station 9: D-wall started on 23/12/2018 and finished on 21/05/2019. Excavation of

top slab started from 20/05/2019 and already done without PIC‟s supervision for 7 segments.

✓ Station 10: D-wall of north side is completed. HGU start excavation from 19/04/2019

CP04 Starting date: 22nd september 2010 100 100

CP05

Building No. 1-2-14-31A:

✓ Brickwork: From the 1st floor to 5th floors 1st floor completed 95%. Areas not

completed are affected by the hoist.

✓ Internal plastering work: The 2nd /3rd/4th/5th floors completed 100%.

✓ External plastering work: Building No.1 completed 100%; Building No.2, 31

completed 95%; Building No.14 Completed 100%. The area affected by the hoist has

not finished yet.

✓ MEP work: Installation of electric conduits and water supply pipes: Completed 100%

at the 2nd/3rd/4th/5th floors & 60% on the 1st floor.

✓ Tiling work: Completed 100% for the 2nd, 3rd, 4th and 5th floor. The toilet area has

been completed 100% for the 2nd, 3rd, 4th, 5th floors and 50% for the 1st floor.

External wall tiling is completed 25% for the building No.1, 90% for the building

No.2-31, 0% for the building No.14.

✓ Waterproofing work: the toilet areas were completed and completed 100% for

✓ the 1st, 2nd, 3rd, 4th, 5th floors. Other areas, in progress.

Building No. 21A:

✓ Concrete for pile caps, cable trench, lean concrete for ground slab are completed

100%.

✓ Setting rebar, formwork for column is ongoing.

Building No. 21B, 22, 24:

✓ Lean concrete for piles caps is completed 36%.

✓ Cutting & treatment pile head is ongoing.

Building No. 23, 27:

✓ Concrete for pump pit is completed 100%.

✓ Lean concrete for pile caps & ground beam is completed 90%.

✓ Concrete for cable trench is completed 50%.

✓ Fabrication for rebar of ground beam, pile caps is ongoing and sand mix cement back

filling is ongoing.

Building No. 07:

✓ Welding work of steel frame, lining concrete for pump pit (axis G-K/4-6) Concrete

for pump pit (axis 4-5/H-I) completed at 100%.

✓ Filling sand and pile head chipping for foundation axis G-K/1-4 is on progress

Building 8,9,10,11:

✓ Pile caps, lean concrete of MBF axis 1-2, excavation work for slab, pump pit

✓ Axis D-G, plastering work for septic tank and welding work of main steel column in

Quang Minh factory have been completed at 100%.

✓ Concreting work for ditch and cable trough (axis 5-21/D-G) is completed 80%

✓ Concreting work for pump pit (axis 5-21/D-G) and for cable trench axis (20- 21/D-

G) is completed 90%

✓ Filling sand for foundation and ground slab (axis 5-14/D-G), rebar installation for

ground slab axis 14-21/D-G and 1-5/D-G, MEPF work for ground slab is on

51.44 55.22

Page 18: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

10

Pks Activities were carried out July 2018

Sep 2019

progress.

Building No. 04:

✓ Installation of traveling-crane steel beam, staircase, brickworks, internal and external

plastering works and the toilet areas for the 2nd floor have been completed.

Building No. 06:

✓ Steel structure installation, fabrication and installation of shutter frames and roof

metal sheet installation have been completed at 100%;

✓ Steel platform support (column and beam) has been installed about 70%.

Building No. 12:

✓ Pile cap has been completed at 100%

✓ Steel material delivery to manufactory is completed 60%.

Building No. 13:

✓ Plastering of external & internal wall and waterproofing for roof has been completed

100%.

✓ MEP work: PVC pipe installation for roof drainage system has been completed.

Building No. 20:

✓ Plastering of external & internal wall, PVC pipe installation for roof drainage

✓ system and waterproofing for roof have been completed 100%.

Building No. 15:

✓ MEP work: the installation of electric conduits and water supply pipes; brick &

plastering wall works and waterproofing for roof have been completed 100%.

✓ Tiling work: It has been completed 50%.

✓ Roof metal sheet installation has been completed at 95%.

Building No. 17-19:

✓ Brick and plastering works: external walls have been done at 99% and internal wall

have been completed at 100%, 1st floor and90%, 2nd floor.

✓ MEP work: the installation of electric conduits and water supply pipes (2nd floor)

and tiling work for slab and toilet are in progress.

✓ Concreting work in progress for bracing (1-21/A-D) 100% & stair 1, 2 has been

completed at 100%

✓ Metal sheet installation work has been done at 98%.

✓ Canopy installation is completed 90%

Building No. 28-29:

✓ Brick work & Installation of electric conduit and water supply pipes have been

completed at 100%

✓ Internal plastering work: Completed at 80%.

Building No. 31B:

✓ Brick works, external and internal plastering works, installation of electric conduits

and water supply pipes, roofing metal sheet work and tiling work for slab and toilet

have been completed at 100%.

CP06

Starting date: 16th october 2017 ✓ Thales have started the installation works in Station 6 for containment in Concourse

areas and embedded conduits for Access Control in “back of house” technical rooms. ✓ There are several on-going pre-HOTSA‟s being carried out for the remaining

✓ Thales technical rooms, PS room and UPS Battery room in Station 6. The final

HOTSA has been rejected by CP06.

✓ Preparation work for the two EVN cable routes, Cau Dien to Station 2 and My Dinh

to Station 5, have been reviewed by PIC and MRB and have also now been agreed

with Local Author

8.15 38.67

CP07

Starting date: 26th April 2016 ✓ Preparing escalator area at Station 6. The HOTSA

✓ for station 01 gridline (5-15) is signed. No HOTSA is signed for station 02.

✓ Installation and Construction activities. Contractor had continued the installation of

ECS duct system, firefighting pipes, clean agent pipes, fire alarm system, and

preparation for the Escalator installation in station 6

19.41 35.54

CP08 Starting date: 05th september 2017 ✓ The logistics for installation activities have started.

2.93 52.59

Page 19: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

11

Figure 1. The Project Map

Page 20: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

12

2 ENVIRONMENTAL MANAGEMENT AND MONITORING FRAMEWORK

2.1 APPLICABLE POLICIES, LAWS, DECREES, REGULATIONS AND STANDARDS

22. Here it’s included a list of laws, regulations and standards that need to be considered as guidelines during the implementation of the Project.

2.1.1 Vietnam Environmental Laws, Regulations and Standards

23. The status of compliance with Government environmental requirements are

presented in Table 4.

Table 4. The Government Environmental Requirements and Compliance Levels

Government Environmental requirements Compliance

levels

Law on Environmental Protection No. 55/2014/QH13 passed by the National Assembly on 23 June 2014 and took effect since 01 January 2015;

Compliance

Law No. 27/2001/QH10 on fire protection and prevention dated 29 June 2001 of the National Assembly;

Compliance

Decree No. 18/2015/ND-CP of 14 February 2015 of the Government on environmental protection planning, strategic environmental assessment, environmental impact assessment and environmental protection plans;

Compliance

Decree No.19/2015/ND-CP of 14 February 2015 of the Government detailing the implementation of several articles of the Law on Environmental Protection;

Compliance

Decree No. 83/2009/ND-CP of 15 October 2009 of the Government on amending and supplementing several articles of Decree No. 12/2009/ND-CP of the Government on management of investment projects on the construction of works;

Compliance

Circular No. 27/2015/TT-BTNMT of 29 May 2015 of the Ministry of Natural Resources and Environment on strategic environmental assessment, environmental impact assessment and environmental protection plans;

Compliance

Circular No. 22/2010/TT-BXD of 03 December 2010 of the Ministry of Construction on labor safety in work construction; Circular No. 36/2015/TT-BTNMT of 30 June 2015 on hazardous waste management;

Compliance

Circular No. 19/2011/TT - BYT of 06 June 2011 of the Ministry of Health guiding labor hygiene, laborers‟ health and occupational diseases;

Compliance

Circular No. 32/2015/TT-BGTVT dated 24 July 2015 of Ministry of Transport regarding Environmental Protection in Traffic infrastructure development.

Compliance

Circular No. 32/2013/TT-BTNMT of 25 October 2013 of the Ministry of Natural Resources and Environment on the issuance of national technical regulations on environment;

Compliance

Circular No. 10/2007/TT-BTNMT of 22 October 2007 on guiding quality assurance and control in environmental monitoring;

Compliance

Decision 869/QD-BTNMT dated 01/06/2007 and No.620/QD-BTNMT dated 30/03/2009 (supplement) of Ministry of Natural Resources and Environment (MONRE) on assessment of environmental impact of Hanoi Pilot Light Metro Line Project, section- Hanoi railway section;

Compliance

+ Water quality: - QCVN 08:2015/BTNMT - National technical regulation on surface water

quality.

Compliance

Page 21: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

13

Government Environmental requirements Compliance

levels

- QCVN 09:2015/BTNMT - National technical regulation on underground water quality.

+Air quality: - QCVN 05:2013/BTNMT – Air quality – National technical regulation on

ambient air quality. - QCVN 06:2009/BTNMT – Air quality – Permitted maximum concentration of

hazardous substances in ambient air. - TCVN 6438:2001 - Road traffic means - Permitted maximum level of exhaust

gas.

Compliance

+ Quality of soil and sediment: - QCVN 03:2015/BTNMT – Soil quality - National technical regulation on the

allowable limits of heavy metals in the soils. - QCVN 15:2008/BTNMT - Soil quality - National technical regulation on the

pesticide residues in the soils.

Compliance

+ Noise and vibration: - QCVN 26:2010/BTNMT - National technical regulation on noise. - TCVN 5948:1999 - Acoustic - Noise emitted by accelerating road vehicles -

Permitted maximum noise level. - QCVN 27:2010/BTNMT - National technical regulation on vibration.

Compliance

+ Water supply and drainage: - TCVN 7957:2008 - Drainage and sewerage - External Networks and Facilities

- Design Standard - TCXDVN 33:2006 - Water Supply - Distribution System and Facilities. Design

Standard. - QCVN40:2011/BTNMT: National technical regulation on Industrial

Wastewater.

Compliance

+ Labor safety and health: - Decision No. 3733/2002/QĐ-BYT dated 10 October 2002 on application of 21

standards on safety and health. - Law of Safety and Labor sanitation No. 84/2015/QH13 dated 25 June 2015 - Circular 04/2017/TT-BXD dated 30 March 2017 regulated to Safety labor

Management on construction.

Compliance

2.1.2 ADB Safeguard Policy and Environmental Safeguards

24. ADB Safeguard Policy Statement (2009) and environmental guidelines.

2.2 Institutional arrangements for EMP Implementation and Monitoring

25. The organizational structure for environment and safety management and monitoring is shown in Error! Reference source not found. and Error! Reference source not found.. 26. It must be mentioned that, as per Project Management Support contract with MRB, PMS2 oversees MRB reporting responsibilities. 27. MRB had assigned an experienced environmental officer to conduct environmental and safety issues monitoring and review the environmental report submitted by the Contractors and PIC since April 2017 to the end of 2017. However, nowadays and during all semester 2019, MRB has no specialist for any of both subjects.

Page 22: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

14

Ended Monitoring Activities

Figure 2. Environmental and Safety management and monitoring structure

Continuous Monitoring Activities Temporary Monitoring Activities

HPC ADB

DONRE MRB

PIC SYSTRA

PMS2

PID1

Contractors CP01, CP02, CP 03 and CP05

Weekly

Daily

Quarterly

Page 23: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

15

Figure 3. Reporting Process chart

The roles of organizations are described in detail in the following table:

Page 24: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

16

Page 25: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

17

3 Methodology of Independent Environmental Verification Works

28. The applied methodology for the independent verification tasks was an adequate sequence of activities, which follows and are in accordance with the objectives and specifications of ADB, mainly as follows:

Analysis of the reports prepared by PIC. It was analyzed if these reports have any wrong assertion, any lack of information and if they match with the real situation observed on site.

Direct monitoring works on site and the assessment of the environmental protection measures currently implemented. As well, the assessment of the level of compliance with ADB SPS 2009 and the common environmental sensibility expected.

The assessment may include some recommendations about measures to implement or to strength that protection.

IEC held interviews with affected local people, households, who have claimed because any affection due to the construction works, as well as with the environmental and safety officers of Contractors and environmental specialist of the PIC.

Page 26: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

18

Finally, some other important matters were analyzed, such as the general structure of the environmental management team in each involved organization or the established mechanism for grievance treatment and its operation.

3.1 Desk review

29. Available documents concerning environmental issues of this project were collected and reviewed to study pre-project environmental situation of the Project area and environmental management plans as well as project environmental measures implementation progress. Purpose of this activity was to understand the performance of a project/organization through its documentation, whether in written, electronic or photographic form.

Table 5. Document types, focused information and expected outputs

Information sources Document types and needed

information Expected results

MRB

Semi-annual environment monitoring reports

Understanding the performance of the EMP implementation Analysis of the responsibility of all relevant agencies in CEMP implementation

Understanding the performance of the mitigation measure taken place on the sites

Understanding any outstanding issues of CEMP implementation

Identify the effectiveness of the mitigation measures

Agreement letters on local facility usages, disposal sites, the borrow Areas.

The environmental clauses added in the civil work contracts, biding documents.

Any public consultation meetings organization during the construction phase

Contractors (CP01-DAELIM);

(CP02 Posco);

(CP03-HYUDAI and GELLA);

CP05HANCORP)

Monthly Environmental Monitoring Reports

Understanding on the performance of the mitigation measure taken place on the sites

PIC (Project Implementation

Consultant)- SYSTRA

Monthly Progress Reports

Understanding on project implementation progress

Understanding on the performance of the mitigation measure taken place on the sites

PMS2 Semi-annual report (July – December 2018)1

Understanding on project implementation progress

Understanding on the performance of the mitigation measure taken place on the sites

Public announcement

Vietnam Environmental Protection Law ADB

Understand about directions on Government of Viet Nam and ADB on

1 See footnote Error! Bookmark not defined..

Page 27: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

19

Information sources Document types and needed

information Expected results

Documents of

project

Website:

ADB

http://www.a db.org

Environmental Safeguard policies Project Administration Manual,

8/2015

Updated Environmental Impact

Assessment (8/2013)

environmental safeguard policies, Project loan covenants, Pre-project environmental situation of the Project area and EMP; the responsibility of all relevant agencies in EMP implementation

Understanding on the performance of the mitigation measure taken place on the sites (period: 2018-2019) Understanding any outstanding issues of CEMP implementation (period: 2018-2019)

Identify the effectiveness of the mitigation measures (period: 2018-2019)

30. The following documents were provided and reviewed: ✓ Semi-annual reports: Semi-annual report July to December 2018. Semi-

annual report January to June 2019. Construction environmental management plans (CEMPs): The CEMPs for Packages CP01, CP02, CP03 and CP05 were provided and reviewed.

✓ Contractors’ environmental monitoring reports: CP01: July in 2018. CP02: The contractor has not carried out the environmental monitoring work for noise and vibration, air quality and wastewater quality…. with frequency of twice a year as per stated in approved CEMP. CP03: Jul 2018, Oct 2018, January 2018, May 2019, July 2019, CP05: November 2018 and May 2019, For CP05, the contractor carries out the environmental monitoring work with frequency of once every six months for noise and vibration, air quality and surface water quality, meanwhile according to the approved CEMP.

✓ PIC - Systra Monthly progress reports: During this period, the monthly report including EHS issues were submitted to client and ADB.

✓ Other documents and reports: Contractors‟ disposal documents. Grievance Redress Mechanism documents. Tree relocation document.

3.2 Site Inspection and Interviews with households along the Project

31. The IEC interviewed households during the evaluation process. The focus of interviews was on the information disclosure, environmental issues, environmental restoration, participation, complaints and complaint address, etc. 32. The IEC observed the status of construction sites, ground clearance, etc. and took pictures during site visit. Pictures were used to understand the context in sites and could be used to compare with the pre-project phase and to assess environmental restoration of the Project.

3.3 Constraints found during the Independent Environmental Auditing Works (IEAW)

33. During the independent environmental verification, the IEC encountered some constraints that were conditionings for our performance such as:

Page 28: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

20

✓ The Contractor, PIC did not submit the HSE monthly report because for a long time they did not prepare it.

✓ Some information regarding training Safety, HIV/AIDS, environment data were request but it was not submitted. Environmental specialists were not mobilized in all Packages except CP02. Since 2018 the MRB did not have officer/environmental specialist to inspect site and review all environmental report prepared by Contractors, PIC and other tasks related to environmental and safety issues. In PIC office, there is an HSE specialist who takes responsibility in all health, safety and environment matters. However, for long and big project, this duty is too heavy therefore the specialist mostly has just focus on safety issues. One environment officer to support for him is necessary.

✓ IEC was mobilized but just after PMS2 began work.

4 ASSESSMENT ON THE EMP IMPLEMENTATION AND MAIN FINDINGS

The areas surrounding the project include community facilities and long-

standing historical and cultural facilities that may be affected around the project,

including:

Page 29: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

21

Cultural and historical facilities around the project include:

Page 30: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

22

During the implementation, the Project has applied environmental mitigation

measures under the EMP, so there are no complaints from these facilities.

4.1 Environmental, health and safety officers and specialist mobilization

34. In this period, the Contractors have established HSE management units in charge of environment and safety to ensure implementation of the CEMPs. Site inspections for safety issues are conducted daily by safety engineers of Contractors. The Contractors have always at least one safety engineer on site during construction time. All environmental and safety staff of Contractors have been trained on an HSE course and have certificates on occupational safety supervision, issued by authorized agencies. 35. Current specialists/officers in charge of environmental and safety issues for each Contractor who were approved by PIC and MRB are listed in Error! Reference source not found.. The key personnel mobilization in each contractor’s staff, regarding to Health, Safety and Environment (HSE) matters, is described as follows and summarized in table 6. This information was updated in the end of September 2019. 36. The contractors established HSE management units in charge of environment and safety to ensure implementation of the CEMP, in the first semester of 2018. Site inspections for safety issues are conducted daily by safety engineers of contractors; the contractors have always at least one safety engineer on site during construction time. All environmental and safety staff of contractors have been trained on HSE course and have certificates on labor safety supervision issued by authorized agencies such as Safety Training – Inspection – Environmental Survey JSC and Solution Safety and Health Co., Ltd.

Page 31: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

23

Table 6. List of Key personnel in charge on environmental and safety of Contractors

PACK. POSITION

CURRENT STATUS

REMARK

PROPOSE APPROVED MOBILIZED NAME

CP01

Environmental

Manager - - - -

Safety

Manager Yes Yes Yes

Vu Van Thuy

was replaced

by Nguyen

Khanh Toan

HSE Manager

CP02

Environmental

Manager Yes Yes Yes

Nghiem Xuan

Anh

Safety

Manager Yes Yes Yes

Nguyen Quoc

Tuan HSE Manager

CP03

Environmental

Manager - - Yes Tran Bien Gioi

Mobilized 2nd

quarter

Safety

Manager Yes Yes Yes Paul Evans.

HSE Manager.

Mobilized 1st quarter

CP05

Environmental

Manager - - - -

Safety

Manager Yes Yes Yes

Nguyen Thanh

Son HSE Manager

CP06

Environmental

Manager - - - - No construction

works. Activities are

developed in France Safety

Manager - - - -

CP07

Environmental

Manager - - - -

Safety

Manager Yes Yes Yes

Duong Quoc

Hung HSE Manager

CP08

Environmental

Manager -

Safety

Manager Yes Yes Yes Vu Van Thuy HSE Manager

Page 32: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

24

37. There is Environment Staff in MRB office (Mr Thien), but he need to have enough fully knowdlege on Environmental Management. PMS2 consultant has been mobilized since May 2018 while all 3 environment positions of Engineer have been mobilized in second half of June 2018. PIC has one (1) international HSE specialist. 38. Recommendation: To advanced environment control and management during the construction stage, the Contractors should promptly mobilize the Environment manager who has environmental background education and experience in the same position in the other projects. 39. In the table it may be observed that Packages CP02 and CP03 have mobilized one staff for environmental matters and one Safety Manager. Packages CP01, CP05, CP07 and CP08 keep mobilized in June 2019 a manager for the three subjects (Health, Safety and Environment). PMS2 considers that it’s enough, as CP01 is near completion, and other packages are developed also in well limited and restricted areas. As well, no significant environmental impacts have happened in these packages. Therefore, PMS2 considers that, according to the current progress of the works and the scale of the pending works, one HSE Manager for each of these packages can develops the supervision of the three matters. CP04 has already finished works and CP06 is mainly developing design works and activities, carried out in France, so currently no staff on site. Regarding CP03, it’s noted that the contractor mobilized a specialist for environmental matters during the second quarter 2019.

40. OTHER AGENCIES’ SPECIALISTS MOBILIZATION 41. Project Implementation Consultant - PIC has assigned one international HSE specialist, already mobilized when PMS2 started works in 2018, in charge of these three matters and for all packages under PIC supervision. However, in view of large and long construction site (about 12 km) and very strict requirements on safety, the specialist focused mainly on safety issues, with less attention to EMP compliance monitoring and reporting. In previous SEMRs, PMS2 recommended that PIC should mobilize a specific environmental specialist. 42. Regrettably, not only the recommendation was not assumed but also the HSE Manager was demobilized in February 2019. It means that during almost the whole semester, PIC had no specialized staff for any of these three subjects. PMS2 considers this fact not acceptable as Health-Safety and Environment are essential part of the implementation of a project during the construction phase. 43. Regarding this important non-compliance with PIC‟s responsibility, it has to be also pointed out that during the preparation of this report, August 2019, it was not informed the mobilization of a new HSE. 44. Ha Noi Metro Railway Board - MRB: since December 2017, MRB has no specialist for environment, health and safety issues, although there is one engineer in charge of the coordination with PMS2 for these subjects. PMS2 acts in fact as Client’s direct support, as requested by MRB, being in charge of environmental matters. 45. Project Management Support consultant, Phase 2 – PMS2 has mobilized full time a National Environmental Specialist by middle June 2018. Until September 2019, this specialist continues developing his duties. As well, the International Environmental Expert was mobilized to arrange and coordinate the works for a first period by end of June 2018 to prepare the SEMR No.1, second period by January 2019 and third period in August 2019. 46. The External Specialist was also mobilized on 16 September 2019 and prepared an Independent Environmental Verification Report (IEVR No.2) will be submitted and approved by MRB.

Page 33: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

25

4.2 Results of Semi-annual environmental monitoring reports

4.2.1 Semi-annual environmental monitoring reports

4.2.1.1 Semi-annual reports (July– December 2018 and January - June 2019)

47. During this period, PMS2 under MRB`s requirements had prepared 02 semi-annual environmental monitoring reports and submitted to ADB. These environment monitoring reports is in line with the Terms of Reference for the environmental consultant for the transition period. These report presents the results of the environmental management performance and internal monitoring activities. 48. The report covers the following:

- Status of compliance with ADB environmental loan covenants and with the environmental requirements of the Government of Viet Nam during the report period;

- Status of implementation of the environmental mitigation measures during the report period based on the EIA and CEMPs, including documentation of complaints received and corresponding action/resolution; and

49. Results of the environmental monitoring of air quality, noise, vibration and surface water quality conducted by the three Contractors.

4.2.1.2 Conclusion and recommendation:

50. Information in the semi-annual reports is based on monthly reports of construction Contractors, monthly reports of SYSTRA and MOU of ADB ‘s mission as well as environmental monitoring results provided by consultants and Contractors. Data appears to be correct and reliable. Assessment of compliance in the semi-annual report is based on: (1) Loan covenants, 2011; Updated Loan covenants, 2016; (2) Monthly Progress Reports; (3) Environmental Monitoring Reports; (4) The EIA report and (5) Site visits. The assessments are appropriate and dependable.

4.2.2 Construction Environmental Management Plans (CEMPs)

51. The EMP which is part of the EIA was included in the biding documents of five civil contractors (CP-01, CP-02, CP-03, CP-04 and CP-05). The CEMPs of CP-01, CP-02, CP-03, CP-04 and CP-05 were approved prior to construction start, as follows:

Table 7. The status of CEMP

Status CP01 CP02 CP03 CP04 CP05

Send PIC for review 06/092014 13/01/2014 20/02/2017 15/12/2013 21/02/2013

Issue No objection by PIC 10/09/2014 05/02/2014 08/05/2017 28/12/2013 07/03/2013

MRB Review and agree to submit CEMP to ADB for clearance and approval

4/6/2016 02/04/2014 28/07/2017 22/01/2014 08/04/2013

ADB’s receipt 1st review 2nd review 3rd review

20/10/2014 18/12/2014 23/01/2014 01/06/2016

03/04/2014 30/06/2014 15/10/2014 21/10/2014

28/07/2017 5/10/2017

19/01/2013 01/02/2013

08/04/2013

2 The contract of the environmental monitoring consultant (IDOM) ended in September 2015, and the new Project Management Consultant had been planned to be mobilized in the fourth quarter of 2017. During the period from November 2015 to June 2017 environmental monitoring activities of the Project have been conducted with the assistance of ADB.

Page 34: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

26

4th review 15/12/2016 15/12/2014

ADB’s approval Approved Approved Approved Approved Approved

52. Contractors for Packages CP-06 to CP-09, although they were not requested to prepare their specific CEMP, they need to implement main basic environmental protection measures, according to the approved EIA, Vietnamese regulations and ADB Policy.

4.2.3 Monthly Environmental monitoring report of the Contractors

53. There are no environmental monitoring reports of Contractors

4.2.4 Environmental Effect Monitoring report of the Contractors

54. In addition to the system of compliance monitoring through field surveys, the reports of environmental effect monitoring will be evidence for assessment of whether construction activities impact air, noise, vibration, surface water, etc. or not. Therefore, selection of monitoring parameters and locations is very important. The relationship between construction activities and receptors should be reflected. 55. At present, sampling locations in the periodical environmental reports already show relation between construction activities and sensitive receptors. Monitoring criteria are based on national technical regulation. As compared to earlier monitoring reports, future monitoring reports need to improve by adding assessment on monitoring results such as whether construction activities under the Project affect surrounding environment. The results confirmed that construction activities did not affect ambient environment. This content was reflected in some reports, but it is inadequate. Therefore, it is necessary to add findings of environmental monitoring results in future monitoring reports to define impacts caused by construction activities on the environmental quality. Error! Reference source not found. presents summary of environmental monitoring program through periods.

Table 8. Summary of the environmental monitoring program of Contractors and requirement of the report EIA 8/2013-ADB

Environmental components

According to EIA 8/2013-ADB Implemented by Contractor (by

June 2018) Ambient air quality

Location 11 13

Parameter HC, CO, SO2, NOx, dust and microclimate parameters

CO, SO2 and NO2 (PM10 is also monitored by CP03 Contractor)

Monitoring frequency Quarterly monitoring 2 months/1 time - 4 month/1 time

Noise

Location 11 13

Parameter Leq; Lmax; L50 Leq; Lmax; L50

Monitoring frequency 4 month/1 time (Quarterly) 2 months/1 time - 4 month/1 time

Vibration

Location 11 13

Parameter Velocity, acceleration and vibration frequency

Velocity, acceleration and vibration frequency

Monitoring frequency 4 month/1 time 2 months/1 time - 4 month/1 time

Surface water

Location Not required 6

Parameter pH, DO, Turbidity, Cr6+, Cr3+, TSS, NO2-, NO3-, NH4+, PO4

3-, total P, total N, Cl-, F-, COD, BOD5, Fe, Cu, Hg, Cd, Zn, Ni, As, Pb, Total phenol,

Page 35: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

27

Environmental components

According to EIA 8/2013-ADB Implemented by Contractor (by

June 2018) total oil and grease, coliform, E. Coli

Monitoring frequency 4 months/1 time

Groundwater

Location Selected water wells in the potential impact zone of tunneling works)

3

Parameter Heavy metals (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), SVOC, TPH and coliform

Cr, Fe, Mn, Se, Cu, Hg, Cd, Zn, As, Ni, Pb, Coliform, Hydrocarbon, sVOC, VOC

Monitoring frequency 4 months/1 time

56. Based on EIA, the PIC has responsibility in environmental monitoring during pre-construction and construction stage for depot, viaduct and tunnel components. But according to the contract between PIC and the Client they do not in charge to carry out the monitoring program. Instead of CENMA which had conducted this monitoring from 2012 to Feb 2015 and then from 2015 to June 2016, Contractors of CP01, CP02, CP03 and CP05 have been conducting the environmental quality monitoring. The environmental monitoring plan which was conducted by the Contractors from July 2018 to September 2019 are listed in the following table. 57. Quarterly Environmental Monitoring Reports have been prepared by PMS2: There are02 report (4th Quarter 2018, 1st quarter 2019….) 58. Monthly Environmental Monitoring Reports have been prepared and submitted to MRB: there are no monthly EMR submitted to MRB. 59. Reference with the proposal Environmental Monitoring Plan (EMoP) submitted to MRB in middle July 2018 for approval, EMoP was developed by PMS2 during the next 4 years. The plan was prepared mainly considering the specifications contained in the Terms of Reference of the support consultant’s contract and according to the current situation on site and the expected progress of the works.

Page 36: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

28

Table 9. Environmental monitoring implemented by construction Contractors during July 2018 – September 2019

No Status Contractors

CP01 CP02 CP03 CP05

1 Sub- Contractors EATC EATC EATC EATC

2 Ambient air quality

- Location 5 3 6 2

- Parameter CO, SO2, NO2, microclimate CO, SO2, NO2, TSP, PM10 PM10, NO2, SO2, CO, HC CO, SO2, NO2, and TSS, microclimate

- Sample location Pier 10, 100,180, 280 and 366 - Station 1 (Nhon) - Station 3 (Phu Dien Station) - Station 5 (Le Duc Tho Station)

- K1: Lane 555 Kim Ma street - K2: Lane 475 Kim Ma street - K3: Kim Ma Communal house - K4: 31A Cat

Linh street - K5: Temple of Literature - K6: Gate of heart hospital – Tran Hung Dao

street

- K1: at gate located at Residential area along Road No.70

- K2: Near Dormitory of HN Industry University

- Monitored time July No EMR July 2018, October 2018, January 2019, May 2019 and July 2019.

There is no EMR

3

Noise and vibration

- Location 5 3 6 2

- Parameter Leq, Lmax Leq Leq, Lmax

-

Sample location Pier 10, 100,

180, 280 and 366

-

- K1: Lane 555 Kim Ma street - K2: Lane 475 Kim Ma street - K3: Kim Ma Communal house - K4: 31A Cat Linh street - K5: Temple of Literature - K6: Gate of heart hospital – Tran Hung Dao

street

- K1: at gate located at Residential area along Road No.70

- K2: Near Dormitory of HN Industry University

- Monitored time July No EMR

July 2018, October 2018, January 2019, May 2019 and July 2019.

There is no EMR

4 Surface water quality

- Location 6 - - 2 1

-

Parameter

Temperature, pH, DO, turbidity, Cr6+, Cr3+, TSS, NO2-, NO3-, NH4+, total phosphorus, total Nitrogen, Cl-, F-, COD, BOD5, Fe, Cu, Hg, Cd, Zn, Ni, As, Pb, total phenol, Total oil

- -

Temperature, pH, DO, turbidity, Cr6+, Cr3+, TSS, NO2-, NO3-, NH4+, total phosphorus, total Nitrogen, Cl-, F-, COD, BOD5,

Page 37: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

29

No Status Contractors

CP01 CP02 CP03 CP05

and grease, Coliform, E. coli Fe, Cu, Hg, Cd, Zn, Ni, As, Pb, total phenol, Total oil and grease, Coliform, E. coli

-

Sample location

- NM1: at abutment No. 10 - MN2: Nhue River at Dien Bridge - NM3: Mai Dich Lake, opposite Mai Dich

cemetery - NM4: Mai Dich Lake near Mai Dich bridge - NM5: To Lich river near Cau Giay bridge - NM6: Thu Le Lake, opposite AIA building

near abutment No. 336

- - Pont in the Depot area.

- Monitored time July No EMR

July 2018, October 2018, January 2019, May 2019 and July 2019.

There is no EMR

5 Underground water

Location 2 - 3 -

Parameter

pH, CaCO3, Cr6+, TSS, NO2-, NO3-, NH4+, SO42-, Cl-, F-, COD, Fe, Mn, Cu, Hg, Cd, Zn, As, Pb, Se, CN-, Phenol, Coliform, E. Coli

- As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se, SVOC, VOC, Hydrocarbon, coliformes

Sample location

- NN1: Well of residential area near abutment No. 10

- NN2: Well at the shop of Da Minh Ngoc, Ho Tung Mau street

- NN3: Well at Salon Auto 370 Cau Giay Street

- - NG1: Ngoc Khanh carpark - NG2: 25 Giang Văn Minh street - NG3: Bich Cau Temple, Cat Linh

Monitored time July No EMR

July 2018, October 2018, January 2019, May 2019 and July 2019.

6 Wastewater quality

- Location - 8 3 -

- Parameter - SO42-, TSS, COD, BOD5, Zn,

Cr3+, oil and total coliform SO42-, TSS, COD, BOD5, Zn, Cr3+, oil and total coliform

-

- Sample location - All stations from station 1 to 8 - NM1: Thu Le lake - NM2: Giang Vo lake - NM3: Van Mieu lake

-

- Monitored time

July No EMR July 2018, October 2018, January 2019, May 2019 and July 2019.

There is no EMR

Note: EATC: Environmental Analyzing and Technique Joint Stock Company

Page 38: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

30

Table 10. List of Disposal Areas

SOIL DISPOSAL AREAS

Package/ SD No.

Location Approved Area (m2)

Approved Capacity

(m2)

Ownership3 Approval

Operation Name Contact Info

Local Authority4

PIC

CP01/SD1 Vien Noi, Van Noi

commune, Dong Anh district, Hanoi city

Vietnam Industry trade and services

Joint Stock Company (JSC)

Vien Noi, Van Noi commune, Dong Anh

district, Ha Noi City

12-Oct-2007

Yes Under operation

CP02/SD1 Thap Boi, Phung

town, Dan Phuong district, Hanoi city

10,300 50,000 Thanh Cong Co-

operative

145 Me Tri street, Thanh Xuan district,

Hanoi

24-Apr-2013

Yes Closed

CP02/SD2 Vinh Quynh disposal

area, Thanh Tri district, Hanoi city

304,500 (tons)

Environmental Technology and

Ecology JSC

24 Nhan Hoa street, Thanh Xuan district,

Hanoi

30-Aug-2012

Yes Closed

CP02/SD3 Van Noi commune, Dong Anh district,

Hanoi city 349,766

Hanoi construction and demolition waste

treatment and environmental

development JSC (CDWT&EDI., JSC)

Floor 1st, N03 building, South East Business

University Urban Area, Mai Dich Wards, Cau Giay district, Hanoi

27-Sep-2011

Yes

Under operation (CP02 has finished disposal at the end

of 2016)

CP03/SD1 Van Noi commune, Dong Anh district,

Hanoi city 349,766 CDWT&EDI., JSC SAA

27-Sep-2011

Yes Under operation

CP03/SD2 Nguyen Khe

commune, Dong Anh district, Hanoi city

1,399,819 CDWT&EDI., JSC SAA 27-Sep-

2011 Yes Under operation

CP05/SD1 Vinh Quynh disposal

area, Thanh Tri district, Hanoi city

304,500 (tons)

Environmental Technology and

Ecology JSC

24 Nhan Hoa street, Thanh Xuan district,

Hanoi

30-Aug-2012

Yes Closed

3 For a public land, indicate whether it is the property of the commune, district or city, etc. 4 Hanoi People Committee issued the approval, including any written agreement between the Contractor and the landowner.

Page 39: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

31

4.3 Approved disposal locations

60. Unsuitable material such as soil must be stored in bags or tanks before transport to the approved disposal places for all Contractors as requirement in Item Waste Management of its approved CEMP. All disposal places had to be permitted officially before Contractor could use them. CP05 urgently submit new disposal places for approval before using them. The currently approval situation of all disposal areas of all Contractors were listed in Error! Reference source not found..

4.4 Concrete batching plants, approvals

61. No concrete batching plant was installed at Project site. All concrete was purchased from Song Da Viet Duc Batch Plant, Xuan Mai Beam Production Factory and Factory No 5789 (789 Corporation).

4.5 Grievance redress and status of complaints

4.5.1 Grievance Redress Mechanism

62. In the draft of regulation about Coordinating among agencies in settling complaints of organizations and individuals related to the implementation of MRP, procedures for receiving and resolving claims related to the implementation of MRP are as followed:

a. Provisions on complaints b. First claim settlement procedure

Step 1. Receipting of complaint:

Step 2. Confirming the settlement of the complaint:

Step 3. Verifying the content of the complaint:

Step 4. Organizing dialogues:

Step 5. Issuing decision on complaint settlement:

c. Second claim settlement procedure

Step 1. Receipting of complaint:

Step 2. Confirming the settlement of the complaint:

Step 3. Verifying the complaint issue

Step 4. Organizing dialogues:

Step 5. Issuing decision on complaint settlement:

4.5.2 Complaints received

63. In March 2019, MRB received grievances on house cracking due vibration during carrying out construction work in this area, road no. 70, Tay Tuu ward, Bac Tu Liem district. The affected houses are vicinity of the construction site which include the houses of Nguyen Dang Chien, Dang Thi Doan Huong, Đinh Van Su, Dinh Van Vien, Pham Thi Duyen, Pham Quang Trung, Ta Xuan Luan, Bui Van Truong, Nguyen Khac Phuong. There are still 62 grievances of affected households relating in compensation policies, positions of land for compensation, unit price for compensation and policy of relocation in which 42 grievances in Depot & Access Line, 9 at Tay Tuu Road No 70 about cracks on houses, 10 from AHs and 1 from affected organization in Package CP03 (Underground Tunnel & Stations)

4.5.3 Interview with affected people

64. As a part of external monitoring, some representative households have been interviewed to record the local people’s opinions on project construction activities (please

Page 40: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

32

kindly refer to Appendix 1). Opinion of the local people has been transferred to MRB and related contractors to correct the defects.

Table 11. Claims raised by the interviewed affected people on 10 September 2019

Claim Location Remarks/ Action (to be) Taken - Reduce income. - Houses affected

by vibration from equipment

- Damaged the utilities (water pipeline, road, …).

- Traffic jam from Construction site arrangement.

- It’s very noisy at night.

- reduce income due to traffic jam and dirt.

- Construction waste was not removed.

-

Kim Ma, Ba Dinh district, Hanoi

- According to the current regulations, there is no mechanism to clarify and resolve the impact on income for the households whose land is not acquired for the project.

- Traffic hinder during the construction phase (even with no project) is unavoidable; however, the contractors are complying with the traffic management plans which were approved by Hanoi DOT.

- The contractor has checked and removed all the construction waste along the fence right after receiving the information. Daily checking is being implemented to ensure that the construction waste shall not be tracked onto public areas and managed in compliance with the mitigation measures in approved CEMP.

- The contractors are maintaining the housekeeping teams on sites to ensure that the sites are kept in the cleanliness and tidiness condition. During the interviews carried out by the independent expert with local people on site, it could not be corroborated the status of this claim and no further information was provided by PIC about it. So that, the IEVR can only suppose, but not assure according to the available provided information, that any corrective action was implemented.

- it’s dusty and very noisy.

- Construction activities hinder traffic

-

Tran Hung Dao street, Ba Dinh, Ha Noi

- it’s dusty, noisy and much construction waste.

- reduce income.

Cat Linh, Ba Dinh, Ha Noi

- it’s dusty, noisy at night.

- reduce income much, hard to business.

- Causing block drainage channel due to no drainage

Cat Linh street

4.6 Tree Relocation

65. Tree relocation/removal was implemented, according to Permit no. 63/GP-SXD and Permit no. 40/GP-SXD. The method to manage the trees was according to the method statement and properly carried out by specialists.

Page 41: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

33

66. Table 12 presents the tree relocation status by end of march and June 2019, it means, end of the period of reference of this report. This issue is being updated continuously in the reports prepared by PMS2.

Table 12. Tree Relocation Status

No. Concept Unit Quantity

CP02 CP03 Total

MARCH 2019

1

Total of relocated tree tree 61 156 217

Total number of trees growing

normally tree 52 143 195

Total number of trees no longer

able to grow (dried body, leaf

wilting)

tree 9 13 22

2 Total of removed tree tree 8 67 75

JUNE 2019

1

Total of relocated tree tree 61 161 222

Total number of trees growing

normally tree 51 148 199

Total number of trees no longer

able to grow (dried body, leaf

wilting)

tree 10 13 23

2 Total of removed tree tree 8 67 75

June 2019. Permit no. 63/GP-SXD dated 18 August 2016

1 Total of relocated tree tree 106

2 Total of removed tree tree 2

June 2019. Permit no. 40/GP-SXD dated 15 June 2017

1 Total of relocated tree tree 67

2 Total of removed tree tree 50

TOTAL JUNE 2019 tree

Page 42: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

34

1 Total of relocated tree tree 395

2 Total of removed tree tree 127

There are no any endangered species tree were cut/ relocated.

5 COMPLIANCE WITH EMP. ENVIRONMENTAL MAIN FINDINGS

67. In September 2019, the External Environmental Specialists of PMS2 analyzed the environmental situation on site from 2018 - 2019. PMS2 reviewed the documents and reports submitted by the PIC, that are the main source of information for MRB and, therefore, for PMS2. Some main results of this work and the compliances /non-compliances of Contractors are shown as following sentences:

5.1 Air Quality Impacts:

68. Propose measures according to EMP:

➢ Strictly implement approved Dust Control Plan

➢ Consider paving Road 70

➢ Position any stationary emission sources (e.g., portable diesel generators, compressors, etc.) as far as is practical from sensitive receptors;

➢ Use only vehicles and equipment that are registered and have necessary permits.

➢ Burning of wastes generated at the construction sites, work camps and other project-related activities shall be strictly prohibited.

➢ Construction equipment and vehicles shall be well-maintained and shall meet national QCVN emission standards.

➢ Specify the use of clean fuels such as ultra-low Sulphur diesel in dump trucks and other heavy-duty diesel vehicles and/or equipment, in conjunction with the use of particulate trap control devices, as well as catalytic converters, to avoid excessive diesel emissions.

➢ Keep stockpiles moist and cover vehicles with tarpaulin sheets or other suitable materials to minimize dust emission and prevent spillage of materials (e.g., soil, cement, stone, sand, aggregates, etc.).

➢ Provide temporary covers (e.g., tarpaulins, grass, etc.) on long term materials stockpiles.

➢ Concrete mixing areas at the Depot site shall be located at least 100 m from the nearest residential area.

➢ Clean road surfaces of debris/spills from construction equipment and vehicles.

➢ Install temporary fencing or barriers around particularly dusty activities in vicinity of sensitive receivers

➢ Ensure availability of water trucks on site and if the works surface and access roads near sensitive receptors (i.e., residential areas, roadside tea and food stalls, schools, hospitals and other sensitive receptors) are dry and dusty, spray water on the exposed surfaces to reduce dust emission.

➢ All construction equipment and machinery shall be fitted with emission control equipment in full compliance with the national (QCVN) and local regulations.

Page 43: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

35

➢ Fuel-efficient and well-maintained haulage trucks will be used to minimize exhaust emissions. Smoke belching vehicles and equipment shall not be allowed and shall be removed from the project.

➢ Impose speed limits on construction vehicles to minimize road dust in areas where sensitive receptors are located.

➢ Locations for stockpiling material at the depot area will be at least 100 m from the nearest residential sensitive receivers.

➢ Undertake immediate repairs of any malfunctioning construction vehicles and equipment.

➢ Discourage idling of engines. Provide prior notification to the community on schedule of construction activities. Implement 24-hour community complaints hotline

Compliance: Partially Complied With.

5.2 Noise impact:

EMP mitigations:

➢ Strictly implement of Noise Control Plan

➢ All construction equipment and vehicles shall be well maintained, regularly inspected for noise emissions, and shall be fitted with appropriate noise suppression equipment consistent with applicable national and local regulations.

➢ Use only vehicles and equipment that are registered and have necessary permits.

➢ No noisy construction-related activities (e.g., transport of materials along residential areas and other sensitive receptors, piling, etc.) will be carried out during the night. Such activities shall be restricted to daylight hours.

➢ Truck drivers and equipment operators shall minimize the use of horns.

➢ Impose speed limits on construction vehicles to minimize noise emission along areas where sensitive receptors are located (houses, schools, hospitals, etc.).

➢ Provide temporary noise barriers (3-5-meter-high barrier can reduce 5-10 dB(A), as necessary, if depot works will generate high noise levels that could disturb nearby households and other sensitive receptors.

➢ As much as possible, use quiet equipment and working method.

➢ Whenever possible, completely enclose noisy equipment which can reduce noise level by 15-25 dB(A), restrict use of noisy equipment (e.g.15 min for every consecutive 30 min period) and undertake sequential operation of equipment with objective to reduce noise generated;

➢ No noisy construction activities near schools during examination period.

➢ Avoid noisy construction activities in vicinity of sensitive receivers during nighttime or other sensitive periods (e.g. during school hours in vicinity of schools)

Compliance: Partially Complied With.

Page 44: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

36

5.3 Wastewater from concrete batch plants (CBP)

5.4 Potential contamination of groundwater due to spills of fuel and other hazardous substances.

➢ Strictly implement approved Spills Management Plan

➢ Store fuel and hazardous substances in paved areas with embankment. If spills or leaks do occur, undertake immediate clean up.

➢ Ensure availability of spill clean-up materials (e.g., absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored.

➢ Train relevant construction personnel in handling of fuels and spill control procedures.

➢ Ensure all storage containers are in good condition with proper labeling.

➢ Regularly check containers for leakage and undertake necessary repair or replacement.

➢ Store hazardous materials above flood level.

➢ Equipment maintenance areas shall be provided with drainage leading to an oil-water separator that will be regularly skimmed of oil and maintained to ensure efficiency. Discharge of oil contaminated water shall be prohibited.

➢ Store waste oil used lubricant and other hazardous wastes in tightly sealed containers to avoid contamination of soil and water resources.

➢ Transport and off-site disposal of such wastes shall be consistent with national and local regulations.

Compliance Assessment: Complied with.

5.5 Drainage obstruction/flooding:

Mitigation measures:

➢ Avoid placement of construction materials, waste storage areas or equipment in or near drainage channels surrounding the Depot.

➢ Prohibit disposal of waste materials to drainage channels.

➢ In case existing drainage ditch is filled-up as required for the construction works, provide alternative drainage for rainwater.

➢ Regularly inspect and maintain all drainage channels to keep these free of obstructions.

Compliance assessment: Complied with.

5.6 Generation of solid waste:

EMP measures:

➢ Provide garbage bins and facilities within the project site for temporary storage of construction waste and domestic solid waste.

➢ Separate solid waste into hazardous, non-hazardous and reusable waste streams and store temporarily on site in secure facilities with weatherproof

Page 45: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

37

flooring and roofing, security fencing and access control and drainage/ wastewater collection systems

➢ Ensure that wastes are not haphazardly dumped within the project site and adjacent areas

➢ Undertake regular collection and disposal of wastes to sites approved by local authorities.

Compliance assessment: Complied with.

5.7 Damage to community facilities

Mitigation measures:

➢ Access roads damaged during transport of construction materials and other project-related activities shall be reinstated upon completion of construction works.

➢ Immediately repair any damage caused by the Project to community facilities such as water supply, power supply, communication facilities and the like.

Compliance assessment: Partial complied with

The mitigation measures have not been implemented at station 8 (under CP02)

(observed on 19 Feb 2019) and in Pier 365 (under CP01) (observed on 09 May

2019)

The issue at Pier 365 has been corrected. At station 8, the solid waste has been

collected and removed by authorized company (URENCO) but it still need more

housekeeping activity

5.8 Land Subsidence

Mitigation measures: Depending on the results of the land subsidence monitoring conducted by the TBM contractor, suitable mitigation measures shall be developed and implemented by to avoid or minimize damage to properties.

Compliance assessment: Complied with.

5.9 Traffic build-up along access road to the depot

Mitigation measures:

➢ Post traffic advisory signs (to minimize traffic build-up) in coordination with local authorities

➢ Strictly implement approved Traffic Management Plan

➢ As much as possible, schedule delivery of construction materials and equipment during non-peak Regularly monitor traffic conditions along access roads to ensure that project vehicles are not causing congestion.

Compliance assessment: Complied with.

Page 46: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

38

5.10 Traffic congestion and access problems

The process of construction and transportation of raw materials, waste ... vehicles in service of construction using or circulating on the roads include: Inter - provincial road No.70, NR No32; Ho Tung Mau, Xuan Thuy, Kim Ma,Nui Truc, Giang Vo, Cat Linh, Quoc Tu Giam; 2nd, 3rd Ring Road, Lieu Giai, Nguyen Chi Thah and Ton Duc Thang Streets.

Page 47: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

39

Mitigation measures:

➢ Provide road signs indicating the lane is closed 500 m before the worksite.

➢ Strictly implement approved Traffic Management Plan

➢ Provide signs advising road users that construction is in progress and that the road narrows to one lane using cones.

➢ Employ flag persons to control traffic at the station sites for safety reasons when construction equipment is entering or leaving the work area. Lanes through the work site, created by rope or flagging, shall be developed to minimize risks and injuries from falling objects.

➢ As much as possible, lifting and placing of the pre-cast pier and viaduct sections will be done at night to minimize traffic congestion.

➢ Post traffic advisory signs (to minimize traffic build-up) in coordination with local authorities

➢ As much as possible, schedule delivery of construction materials and equipment as well as transport of spoils during non-peak hours.

Page 48: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

40

Avoid movements of noisy vehicles during night time in vicinity of sensitive receivers.

➢ Implement suitable safety measures to minimize risk of adverse interactions between construction works and traffic flows through provision of temporary signals or flag controls, adequate lighting, fencing, signage and road diversions.

➢ Ensure relocation of any affected public transport infrastructure (but stops, shelters etc) prior to commencement of works

➢ Provide advance notification to the community regarding changes to public transport facilities or routes

➢ Schedule construction works to minimize extent of activity along linear construction site at any one time

➢ Use traffic cones to direct traffic to move to the open lane. Provide sufficient lighting at night within and in the vicinity of construction sites. Regularly monitor traffic conditions along access roads to ensure that project vehicles are not causing congestion.

➢ Define and observe schedules for different types of construction traffic trips (e.g., transport of pre-cast sections, haulage of spoils, delivery of construction materials, etc.).

➢ Install temporary accesses to properties affected by disruption to their permanent accesses.

➢ Reinstate good quality permanent accesses following completion of construction.

➢ Comply with traffic regulations and avoid, where possible, roads with the highest traffic volumes, high density of sensitive receivers or capacity constraints are not used as access to and from the construction areas and spoils disposal sites.

During the implementation, the Project has applied environmental mitigation measures under the EMP, so there are no complaints from these roads and facilities on roads.

Compliance assessment: Complied with.

5.11 Hazards to health and safety of workers and the public due to construction works

EMP mitigation measures:

➢ Strictly implement approved Occupational and Community Health and Safety Plan, and approved Emergency Response Plan

➢ Appoint an environment, health and safety manager to look after implementation of required environmental mitigation measures, and to ensure that health and safety precautions are strictly implemented for the protection of workers and the general public in the vicinity of construction areas

➢ Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc., and prevention of HIV/AIDS and other related diseases

➢ Provide first aid facilities that are readily accessible by workers.

Page 49: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

41

➢ Provide firefighting equipment at the work areas, as appropriate, and at construction camps.

➢ Provide adequate drainage in workers camps to prevent water logging/accumulation of stagnant water and formation of breeding sites for mosquitoes.

➢ Provide adequate housing for all workers at the construction camps.

➢ Provide reliable supply of potable water

➢ Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers

➢ Establish clean canteen/rest area.

➢ Ensure proper collection and disposal of solid wastes within the construction camps consistent with local regulations.

➢ Provide fencing on all areas of excavation greater than 2 m deep.

➢ Provide appropriate personnel safety equipment such as safety boots, helmets, gloves, protective clothes, breathing mask, goggles, and ear protection

➢ Ensure reversing signals are installed on all construction vehicles.

➢ Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast sections, etc.) do not fall onto or hit construction workers.

➢ Implement fall prevention and protection measures whenever a worker is exposed to the hazard of falling more than two meters, falling into operating machinery or through an opening in a work surface. Based on a case-specific basis, fall prevention/protection measures may include installation of guardrails with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices such as full body harnesses, etc.

Compliance Assessment: Partially complied with

5.12 Social conflicts due to presence of workers;

Complied with (because there no worker camps are installed on site.

5.13 Spoils generation from pier excavation Works

➢ Strictly implement approved Spoils Disposal Plan

➢ Spoil disposal will only be to DONRE and DOC approved areas

➢ Trucks transporting spoils shall be tightly covered with tarpaulin or other suitable materials to minimize dust emission and spills.

➢ Wheel washing shall be undertaken to remove mud so as to ensure that access roads are kept clean.

➢ Road surfaces shall be regularly cleaned of spilled spoils

➢ Spoil disposal shall not cause sedimentation and obstruction of flow of watercourses, damage to agricultural land and densely vegetated areas.

Page 50: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

42

➢ The spoils disposal site shall be located at least 50 m from surface water courses and shall be protected from erosion by avoiding formation of steep slopes and grassing.

Compliance Assessment: Complied with.

5.14 Sedimentation of Thu Le Lake and generation of sediment-laden wastewater from pier excavations

➢ Immediately restore damaged rip-rap along Thu Le Lake to minimize erosion

➢ Undertake regular inspection and maintenance of erosion and sediment controls Prior to discharge, alkaline water from the casting yard shall be settled and neutralized,

➢ Installation of a sheet piled wall along Thu Le lake prior to filling.

➢ To prevent clogging of canals, sediment-laden water from excavation for pier placement shall be settled prior to discharge to the nearest storm drain.

➢ Sedimentation from filling materials behind the sheet piled wall shall be prevented from entering into Thu Le Lake by silt curtains anchored to the ends of the piled structure.

➢ Ensure that excavation spoils are not stockpiled or dumped near or into water courses

Compliance Assessment: Complied with.

5.15 Generation of solid wastes

➢ Provide garbage bins and facilities within the project site for temporary storage of

➢ construction waste and domestic solid waste.

➢ Separate solid waste into hazardous, non-hazardous and reusable waste streams and store temporarily on site in secure facilities with weatherproof flooring and roofing, security fencing and access control and drainage/ wastewater collection systems.

➢ Ensure that wastes are not haphazardly dumped within the project site and adjacent

➢ areas

➢ Undertake regular collection and disposal of wastes to sites approved by local authorities.

Compliance Assessment: Partial Complied with. (At station 8, the solid waste has been collected and removed by authorized company (URENCO), but it still needs more housekeeping activity)

5.16 Hazards to health and safety of workers and the public

➢ Strictly implement approved Occupational and Community Health and Safety Plan, and approved Emergency Response Plan

➢ Appoint an environment, health and safety manager to look after implementation of required environmental mitigation measures, and to

Page 51: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

43

➢ Conduct orientation for construction workers regarding health and safety measures, emergency response in case of accidents, fire, etc., and prevention of HIV/AIDS and other related diseases

➢ Provide first aid facilities that are readily accessible by workers.

➢ Provide firefighting equipment at the work areas, as appropriate, and at construction camps.

➢ Provide adequate drainage in workers camps to prevent water logging/accumulation of stagnant water and formation of breeding sites for mosquitoes.

➢ Provide adequate housing for all workers at the construction camps.

➢ Provide reliable supply of potable water.

➢ Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers

➢ Establish clean canteen/rest area. Ensure proper collection and disposal of solid wastes within the construction camps consistent with local regulations.

➢ Provide fencing on all areas of excavation greater than 2 m deep.

➢ Provide appropriate personnel safety equipment such as safety boots, helmets, gloves, protective clothes, breathing mask, goggles, and ear protection

➢ Ensure reversing signals are installed on all construction vehicles.

➢ Implement precautions to ensure that objects (e.g., equipment, tool, debris, pre-cast sections, etc.) do not fall onto or hit construction workers.

➢ Implement fall prevention and protection measures whenever a worker is exposed to the hazard of falling more than two meters, falling into operating machinery or through an opening in a work surface. Based on a case-specific basis, fall prevention/protection measures may include installation of guardrails with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices such as full body harnesses, etc.

Partially complied with (Except station 6, all the toilets for workers have been removed from construction site of elevated station (under CP02). Until the end of June 2019, there is no improvement)

5.17 Potential damage to Undiscovered archaeological relics

The following ‘chance-find’ principles will be implemented by the contractor throughout the construction works to account for any undiscovered items identified during construction works:

➢ If the site supervisor determines that the item is of potential significance, an officer from the Department of Culture and Information (DCI) will be invited to inspect the site and work will be stopped until DCI has responded to this invitation

➢ Work will not re-commence in this location until agreement has been reached between DCI and HRB as to any required mitigation measures, which may include excavation and recovery of the item

Page 52: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

44

➢ Should any potential items be located, the site supervisor will be immediately contacted and work will be temporarily stopped in that area

➢ Workers will be trained in the location of heritage zones within the construction area and in the identification of potential items of heritage significance

➢ A precautionary approach will adopted in the application of these procedures

Compliance Assessment: Complied with.

5.18 Potential damage to the Temple of Literature

➢ Establish a photographic record of the fence and gates, especially at ground level.

➢ To monitor settlement, install inclinometers along the fence, the gate and other structures closest to the flower garden. These inclinometers shall be left in place for 2 years after construction and regularly monitored.

➢ Install a vibration recording device and undertake continuous monitoring for the period when the TBM is traversing the Temple of Literature.

➢ Adjust tunneling speeds and periodicity should the vibration monitoring indicate excessive vibrations.

➢ Consult with managers of Temple of Literature and DCI prior to commencement of construction to inform them of construction schedule and activities and identify requirements for specific mitigation measures to minimize air, noise, or traffic impacts in addition to those already required in the EMP.

➢ Should the monitoring indicate that settlement has taken place based on photographic record, inclinometer reading and depending on the severity, the following remedial measures shall be applied, as appropriate: - Fill the garden area with soil and re-level the ground; - Re-install the fence and supports; - Jack-up the building(s) and rebuild the base with cement forms or engineered earth; - Repair cracks and re-plaster walls.

Compliance Assessment: No construction activities in the surrounding

6 CONCLUSION AND RECOMMENDATION

69. In general, the information submitted to ADB by MRB through SEMP reports in 2 years (2018 and 2019) accurately reflects the situation of CEMP implementation. The information in SEMP reports is collected from reports such as progress reports of SYSTRA and environmental monitoring reports, environmental incidents. Therefore, the reports accurately reflect information in the reporting period. However, to ensure better quality of SEMP reports, the SEMP reports could provide more information on the following. - Activities of training, environmental management capacity enhancement for Contractors

should be conducted and report by picture and minutes. - Tables including pictures and address of site present how key environmental issues

identified in the previous reporting period were solved or not, to ensure connectivity between the two reports and assessment of effectiveness of environmental mitigation measures implemented by Contractors.

- Landfill locations with updated capacity in the period should be considered and specifically mentioned in the semi-annual environmental report, especially in construction process of package CP03. Therefore, it is necessary to consider specific landfill locations,

Page 53: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

45

permits, maps, distance and routes of spoil transportation, companies in charge of hazardous waste transportation and disposal.

- PCR risk assessment under package CP03 should also be updated in the report. - For CP04: because the construction is completed, Thus, a post-construction report on

HSE is required. - To improve the Contractors‟ monthly environmental reports, the information on

construction activities within the month, mobilized equipment and human resources should be also updated. The compliance table should specifically show where and how the mitigation measures are carried out, and what corrective actions were or are needed to be implemented. Besides, appendices and minutes of spoil and waste transportation volume and distance, landfills should be updated in the reports.

70. There are some actions that Contractors have not complied with such as: Workers without PPEs have sometimes seen on construction sites; spoil on construction sites. 71. Construction sites are relatively clean and tidy. Mobile toilets are provided at each construction site by Contractors. Domestic waste and construction waste are classified. Construction waste is disposed in 03 permitted landfills including Thap Boi, Vinh Quynh and Van Noi. 72. The area of this project is very crowed (deports, stations…). Thus, even a small negative impact of the Project also affects the surrounding community. All contractors had to immediately mobilize environment manager positions to assure the environment issues. 73. Contractors need to prepare monthly environmental monitoring reports: The content regarding monitoring frequency should be reviewed. The relationship between construction activities and environmental quality during surveys should be also included in conclusions. It is necessary to clearly show causes, especially causes related to construction activities.

Page 54: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

46

APPENDICES

Appendix 1: Interview questionnaire (from September - October 2019)

Interviewed Person: Mr. Dung Add: 27D Cat Linh, Dong Da district, Hanoi. Dung Van’s shop Career: Grocer Claims: - Construction activities hinder traffic

- Reduce income due to traffic jam and dirt. Request from interviewed person: - Accelerate the construction work in order to minimize the traffic congestion. - Site arrangement need to study properly for public transportation.

Interviewed person: Vu Thi Hue Add: 32c Voi Phuc, Ngoc Khanh str, Cau Giay district, Hanoi Career: small business Claims: - it’s dusty and very noisy. - Construction activities hinder traffic

- reduce income. Request from interviewed person: no

Interviewed person: Mrs. Dung

Add: 96 Tran Dung Dao, Cua Nam district, Hanoi. Dung’s house. Career: Freelancer

Claims: - Construction activities hinder traffic

- reduce income.

Request from interviewed person:

- Accelerate the construction work to complete the project 20th february, 2020.

Interviewed person: Tran Thi Thanh Xuan

Add: 36 Cat Linh str, Cat Linh district, Hanoi. Baya’s furniture Company

Career: Business Staff of Company

Claims: - Causing block drainage channel due to no drainage

- reduce income much, hard to business.

Request from interviewed person:

- Accelerate the construction work to restore this area; the fence must be removed after finishing the construction work.

Interviewed person: Nguyen Thi Thanh Huong

Add: 478 Kim Ma str, Ba Dinh district, Hanoi. Tjhanh Xuan’s house/ shops. Career: business

Claims: - it’s dusty, very noisy at night due to construction activities and project’s vehicles and equipment.

- Construction wastewater affected on traffic, Risk of accident

- Construction activities hinder traffic

- Reduce income much because number of customers decreased.

Request from interviewed person: - Accelerate the construction work to restore this area and remove the fence.

Page 55: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

47

Appendix 2: Photos of site inspection

Concrete waste from Depot (20th

September 2019)

Waste at station - need to remove daily

(20th September 2019)

Plastic waste at station - need to

remove (21st September 2019)

Household waste at site (21st

September 2019)

Page 56: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

48

Waste of rock, peace of steal… (23rd

September 2019)

Waste soil at Station no 11 (23rd

September 2019)

Small road beside construction site on

25th September 2019

(S12 - Tran Hung Dao str)

Wastewater affected on traffic at S9on

25th September 2019 (Kim Ma str)

Page 57: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

49

Appendix 3: Photos of interviewed house (taken on 16th September - 16th October 2019)

Picture 1: 27D Cat Linh, Dong Da district, Hanoi. Dung Van’s shop, on 20th

september 2019

Picture 2: 96 Tran Dung Dao, Cua Nam district, Hanoi. Dung’s house, on 20th

september 2019

Picture 3: 36 Cat Linh str, Cat Linh district, Hanoi. Baya’s furniture Company, on 25th

september 2019

Picture 4: 478 Kim Ma str, Ba Dinh district, Hanoi. Tjhanh Xuan’s house/ shops, on

25th september 2019

Page 58: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

50

Appendix 4: Report to Donor on EHS for the meeting in April 2019

ENVIRONMENT, HEALTH, AND SAFETY

Environmental Management Arrangement (CP03 Contractor). For the CP03’s updated Environmental Management System (EMS), the MRB has some comments on this updated version and requested the contractor CP03 to supplement and modify information. The contractor CP03 is revising this EMS based on the comments of MRB. The report must be submitted to MRB by 16 September 2019 for review.

BCS. The report has been submitted to ADB on 23 May 2019; a meeting between the staffs of MRB, ADB and the contractor CP03 has been arranged in 28 May 2019 to discuss on this report. SONO was granted.

PCR risk assessment for Station 11. On 28 May 2019, ADB discussed with MRB’s staff and HGU’s engineers to clarify the requirement on PCR report; on 10 June 2019, ADB

issued a letter with a detail instruction and requirement for PCR report; On 05 July 2019,

MRB discussed with HGU’s engineer on the PCR report outline; The report outline has been submitted to ADB for consultation, and the PCR Risk Assessment and Management Plan is

under preparation by CP03. The draft of report shall be completed in the end of September

2019; relevant stakeholders and public consultation shall be implemented in October 2019

and the report shall be finalized and submitted to ADB in November 2019.

Temporary traffic management: TTMP for Station 12 has been approved on 14 June 2019 by Hanoi DOT and under implementation. TTMP for Station 11 shall be submitted to the Hanoi DOT to consider approving after finish construction of detour road in this area (expected in October 2019)

Tree relocation: Under the permission no. 22/GP-SXD dated 26 March 2019, the contractor has relocated 30 trees and removed 6 trees at Station 11. Under the permission no. 49/GP-SXD dated, at the Station 12 the contractor has relocated 27 trees, in which 3 Dalbergia Tonkinensis trees were handed over to Thong Nhat Park, and the contractor also removed 9 trees under this permission. Under permission 50/GP-SXD, the contractor has removed 8 trees at Station 12.

The status of tree relocation has been summarized as table below:

Table 13. Tree relocation status

No. Content Unit Quantity

1

Total of relocated tree tree 460

Total number of trees growing normally

tree 424

Total number of trees no longer able to grow (dried body, leaf wilting)

tree 36

2 Total of removed tree tree 142

Environmental Reporting. The last SEMR period from July to December 2018 has been submitted to ADB for review and approval on 15 May 2019. It’s also approved and disclosed on ADB’s website on that day.

Page 59: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

51

PMS2 has submitted to MRB a proposal for Monthly Environmental Monitoring Report (MEMR) templates which are separated for the Contractors and PICs. So far, PIC has not prepared a specific MEMR and its new HSE manager has been mobilized in full time since 9 September 2019.

Table 14. Summary of actions’ status

Issue Responsibility Deadline Status

Review CP03’s updated EMS and HSE corrective action report, clear the reports and submit to ADB

MRB 10 May 2019

MRB had reviewed the updated EMS and CEMP of CP03, however it is required to supplement the information in this updated version. CP03 is revising the CEMP based on the requirement of the MRB and it shall be submitted to MRB for review by 16 September 2019

Submit BCS report MRB 10 May 2019

The report has been submitted to ADB on 23 May 2018

PCR assessment i Prepare a draft

PCR risk assessment and management plan (including PCR mitigation measures and PCR monitoring plan) and submit to ADB

ii Hold consultation with Hanoi DCST, UNESCO Vietnam and the custodians of the Temple of Literature on the draft plan

iii Disseminate the information of the draft plan to the public

iv Finalize the plan by the reflecting the comments and opinions of the stakeholders and submit to ADB

CP03, MRB (i) 10 May 2019 (ii) (iii) 31 May 2019 (iv) 14 June 2019

- On 28 May 2019, ADB discussed with MRB’s staff and HGU’s engineers to clarify the requirement on PCR report

- On 10 June 2019, ADB issued a letter with a detail instruction and requirement for PRC report

- On 05 July 2019, MRB discussed with HGU’s engineer on the PRC report outline

- The report outline has been submitted to ADB for consultation, SONO was granted; and the PCR Risk Assessment and Management Plan is under preparation by CP03. The draft shall be completed in the end of September 2019 and relevant stakeholders and public consultation shall be implemented in October 2019 and the report shall be finalized and submitted to ADB in November 2019

Environmental Reporting i Submit revised

SEMR (cover

(i) MRB (assisted by PMS2) (ii) External

(i) 10 May 2019 (ii) 10 May 2019 (iii) From May 2019 (iv) 31 May 2019

(i) revised SEMR covers period from Jul to Dec 2018 has been submitted to ADB and it has been

Page 60: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

52

Issue Responsibility Deadline Status

period form Jul to Dec 2018)

ii Submit revised IEVR (covering the period from Mar 2017 to Jun 2018)

iii Prepare monthly environmental monitoring reports on EMP implementation for submission to MRB

iv Prepare a monthly environmental monitoring report template

monitoring consultant (PMS2) (iii) PIC (iv) MRB with PMS2, PIC and relevant contractors

approved by ADB, the SEMR covers period from Jan to Jun 2019 is under preparation of PMS2’s specialist and shall be submitted to MRB for review 20th february, 2020 (ii) updated IEVR, covers period from mar 2017 to Jun 2018, has been submitted to ADB on 26 August 2019 and it has been approved by ADB. IEVR, covers period from Jul 2018 to Jun 2019, shall be prepared whenever PMS2 mobilizes the external environmental expert. The proposal for this position has been submitted to MRB for approval. (iii) not yet. PIC has not mobilized its HSE manager. PIC has proposed a HSE manager for 2 months temporarily, MRB has agreed with this proposal on 08 Jul 2019 but PIC has not ever introduced these personnel to MRB although MRB has requested for mobilization status of this position (iv) the monthly environmental monitoring report template has been prepared by PMS2 and submitted to MRB for review (in August 2019)

MRB’s Institutional Arrangement i Discuss the

assignment of qualified and experienced environmental officer and occupational health and safety officer internally and with HPC

ii Approve the environmental training plan

MRB (i) (ii) 31 May 2019

(i) under discussion (ii) environmental training plan has been approved by MRB and implemented on 27 August 2019

Non-compliance of (i) (ii) CP05 (i) all the material

Page 61: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

53

Issue Responsibility Deadline Status

EMP identified during site visit (i) material (soil) stockpiles were left haphazardly dry and uncovered. Some of them were left for a long time enough for grasses to grow on them (ii) the construction site, access road, and the vicinity of the construction site were dusty with scattered sand and wind (iii) separate toilets were not provided for male and female workers at Station 6

(iii) CP02 stockpiles have been maintained the moist to minimize the spread of dust or cover with tarp/grass in case of long-term stockpile (ii) the contractor has installed the water supply with taps along the potential dusty areas such as access road and watering the surface to minimize the spread of dust with at least 2 times a day for normal days and 4 times a day for windy and dry days (iii) Mobile toilets have been provided and they are also separated for male and female workers at station 6

Page 62: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

54

Table 15. HSE training coures

Page 63: 40080-013: Ha Noi Metro Rail System Project (Line 3: Nhon ...€¦ · 1. Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) (the Project) is developing the Mass

55