WBM Roads Definition: The pavement base course made of crushed or broken aggregates mechanically interlocked by rolling and voids filled by screening and binding material with the assistance of water

Transcript of 4. wbm roads 10 sep

Page 1: 4. wbm roads 10 sep

WBM Roads

Definition: The pavement base course made ofcrushed or broken aggregates mechanicallyinterlocked by rolling and voids filled by screeningand binding material with the assistance of water

Page 2: 4. wbm roads 10 sep

Salient Features of WBM Roads

• WBM means Water Bound Macadam.

• The word Macadam comes from the name of Scottish Engineer John L. Macadam.

• Wearing surface is formed by cleaned, crushed aggregates which are spread and rolled by sprinkling water.

Page 3: 4. wbm roads 10 sep

Salient Features of WBM Roads

• Low cost

• Thickness range: 8cm to 30 cm

• Camber : 2.5% to 3% OR 1:36 to 1:48

• Surface is better than earthen road but rough as compared to bituminous or Concrete roads

• Can be used as Base Course for Bituminous or Concrete roads.

Page 4: 4. wbm roads 10 sep

Materials to be used in WBM roads

• Crushed trap rock – Most Suitable

• Crushed slag

• Burnt Brick bats

• Kankar Aggregate

• Laterite

• Screenings to be used as filler material

Page 5: 4. wbm roads 10 sep

IRC Recommendations for Course Aggregate Grading for WBM Roads

Grading No Size Range (mm) Sieve Size (mm) % Passing the sieve by weight

1

2

3

90 to 40

63-40

50-20

10080634020

8363504020

6350402010

10065-8525-600-150-5

10090-10030-700-150-5

10095-10035-700-100-5

Page 6: 4. wbm roads 10 sep

IRC Recommendations for Grading of Screenings

Classification Grading

Size of Screenings mm

Sieve sizemm

% by weight passing the sieve

A

B

12.5

10.0

12.510.04.750.15

10.04.750.15

10090-10010-30

0-8

10085-10010-30

Page 7: 4. wbm roads 10 sep

Construction Procedure of WBM Roads

• 1. Preparation of Sub Grade

• 2. Preparation of Base Course

• 3. Intermediate Layer

• 4. Wearing Surface

• 5. Shoulders

Sub Grade

Base Course

Intermediate Course

Wearing Course ShoulderShoulder

Page 8: 4. wbm roads 10 sep

Precautions in Rolling WBM Roads

• Roller to be used- 8-10 Tonnes

• Rolling should be done from edges to the centre

• The successive rolling strips should be overlapped

• Length of each rolling should be <=200m.

• Water should be sprinkled and not poured by buckets

• The rolling should be done for 80 passes or until the aggregates are broken.