4 – Storey Dormitory with Natural Light, Ventilation and Rainwater Cistern Project by
Transcript of 4 – Storey Dormitory with Natural Light, Ventilation and Rainwater Cistern Project by
4 – Storey Dormitory with Natural Light, Ventilation
and Rainwater Cistern
Project by:
ALMANDUS, Jhamina Zarrah J.
ICASIANO, John Matthew B.
VALENZUELA, Rafaela A.
Submitted to the School of Civil, Environmental and
Geological Engineering
(SCEGE)
In Partial Fulfillment of the Requirements for the
Degree of Bachelor of Science in Civil Engineering
Mapua Institute of Technology
Manila City
September 2014
TABLE OF CONTENTS
Chapter 1: Introduction
1.1 Problem Statement 1
1.2 Project Objective 2
1.3 Design Norms Considered 2
1.4 Major and Minor Areas 2
1.5 Project Beneficiary 3
1.6 Innovative Approach 3
1.7 Research Component 3
1.8 Design Component 4
1.9 Sustainable Development 4
Chapter 2: Environmental Examination Report
2.1 Project Description 5
2.1.1 Project Rationale 5
2.1.2 Project Location 5
2.1.3 Project Information 6
2.1.4 Description of Project Phases 6
2.1.5 Pre-Construction/Operational Phase 6
2.1.6 Construction Phase 7
2.1.7 Operational Phase 8
2.2 Description of Environmental Setting and Receiving Environment 8
2.2.1 Physical Environment 8
2.2.2 Biological Environment 8
2.2.3 Socio-Cultural, Economic and Environment 8
2.2.4 Future Environmental Conditions without the Project 8
2.3 Impact Assessment and Mitigation 9
2.3.1 Summary Matrix of Predicted Environmental
Issues/Impacts and their Level of Significance at
Various Stages of Development 9
2.3.2 Brief Discussion of Specific Significant Impacts
on the Physical and Biological Resources 9
2.3.3 Brief Discussion of Significant Socio-economic
Effects/Impacts of the Project 9
2.4 Environmental Management Plan
2.4.1 Summary Matrix of Proposed Mitigation and
Enhancement Measures, Estimated Cost and
Responsibilities 10
2.4.2 Brief Discussion of Mitigation and
Enhancement Measures 10
2.4.3 Monitoring Plan 11
2.4.4 Institutional Responsibilities and Agreements 11
2
Chapter 3: The Research Component
3.1 Abstract 12
3.2 Introduction 12
3.3 Review of Related Literature 12
3.3.1 Green Engineering 12-13
3.3.2 Green Building 13
3.3.3 Natural light and Ventilation 14
3.3.4 Rainwater Cistern 14-15
3.4 Methodology 15
3.4.1 Flow Chart 16
3.5 Results and Discussion 16
3.6 Conclusion and Recommendations 17
Chapter 4: Detailed Engineering Design
4.1 Loads and Codes 18
4.1.1 Introduction 18
4.1.2 References and Standards 18-19
4.1.3 Design Loads 19-22
4.1.4 Slab Design 22-25
4.4.4 Stair Design 25-29
4.2 Structural Engineering 30-38
4.3 Water Resources Engineering 39-44
4.4 Environmental Engineering 45-47
4.5 Plan Set 48-56
Chapter 5: Promotional Material 58
Chapter 6: Budget Estimation 59-65
Chapter 7: Project Schedule 66-75
Chapter 8: Conclusion and Summary 76
Chapter 9: Recommendation 77
Chapter 10: Acknowledgements 78
Chapter 11: References 79
Appendices
Appendix A: Article Type
Appendix B: Original Project Report Assessment Sheet by Panel Members
Appendix C: English Assessment and Evaluation Rubric
Appendix D: Accomplished Consultation Forms
Appendix E: Compilation of Assessment Forms
Appendix F: Drawing and Plans
Appendix G: Soil Report
Appendix H: Project Poster
Appendix I: Photocopy of Receipts
Appendix J: Other Required Forms
Appendix K: Student Reflections
List of Tables
Table 2.2 Summary Matrix of Predicted Environmental Issues/ 9
Impacts and their Level of Significance at Various
Stages of Development
Table 2.1 Summary Matrix of Proposed Mitigation and Enhancement 10
Measures, Estimated Cost and Responsibilities
Table 2.3 Monitoring Plan 11
Table 6.1 Preliminaries 59
Table 6.2 Site Works 60
Table 6.3 Formworks and Scaffoldings 60
Table 6.4 Steel Works 61
Table 6.5 Concrete Works 61
Table 6.6 Masonry Works 62
Table 6.7 Electrical Works 62
Table 6.8 Plumbing Works 63
Table 6.9 Specialty Works 63
Table 6.10 Project Costs 64
Table 6.11 Estimated Gross Income 64
Table 6.12 Estimated Expenses 64
List of Figures
Figure 3.1 Flow Chart 16
Figure 4.1 Footing Schedule 35
Figure 4.2 Slab Schedule 36
Figure 4.3 Beam Schedule 36
Figure 4.4 Beam Schedule 37
Figure 4.5 Column Schedule 38
Figure 4.6 Cistern Section Detail 42
Figure 4.7 Cistern Foundation Detail 43
Figure 4.8 Gutter Guards 44
Figure 4.9 GRID 1 from ETABS 48
Figure 4.10 GRID 2 from ETABS 49
Figure 4.11 GRID 3 from ETABS 50
Figure 4.12 GRID 4 from ETABS 51
Figure 4.13 3D View from ETABS 52
Figure 4.14 Sample Moment Diagram 53
Figure 4.15 Ground Floor Plan 54
Figure 4.16 2nd-4th Floor Plan 55
Figure 4.17 Room Plan 56
Figure 7.1 S curve 69
Figure 7.2 Gantt Chart 1 71
Figure 7.3 Gantt Chart 2 72
Figure 7.4 Gantt Chart 3 73
Figure 7.5 Gantt Chart 4 74
Figure 7.6 Gan
tt Chart 5 75
1
Chapter 1
Introduction
Civil Engineers believe that building structures are not limited for aesthetics. The
importance of satisfying standards which mostly conform to the economy and environment should
be considered in order to reach goals without sacrificing one from the other. The perfect concept
that can attest to this would be the technology behind green buildings. It has been around for
centuries which combines economic and environmental standards while providing aesthetics.
The focus on optimizing system efficiency is where today’s climate of sustainable design
is headed. For instance, high occupancy buildings such as office and dormitory premises have
issues in their heating, cooling and air conditioning systems which are well known energy
consumers. Energy efficiency measures are then proposed to reduce excess consumption.
Processes such as natural ventilation and cistern are key features that can help the industry in
building more refined building structures.
Natural ventilation is the process of supplying and removing air through an indoor space
without the use of a fan or other mechanical system. It uses outdoor air flow caused by pressure
differences between the building and its surrounding to provide ventilation and space cooling.
Significant energy savings are also achieved through the use of natural lighting and ventilation.
A cistern is a large vessel used to hold a reserve of water. It can either be above or below
ground, ranging in all sorts of size and shape with varying features. As mentioned, it acts like a
reservoir for rainwater used for cleaning, flushing and serves as tap water to households. If
intended to use for drinking, a filtration system must be added.
1.1 Problem Statement
One of the country’s top notching school, University of the Philippines (UP) in Diliman
has a total land area of 493 hectares (1,220 acres). Majority of the property has been utilized by
the university through building infrastructures and research facilities. Meanwhile, a remaining
portion of the land is forested, reserved for development and residential use or simply unoccupied.
Sustainable development can be divided into two categories; (1) social development and
poverty alleviation, and (2) natural resources and environment regeneration and protection.
With the continuous construction of various buildings within the vicinity, a proposed green
building/structure is the perfect solution to limited dormitory spaces of the university. Priority is
given to students from more distant homes and lower income bracket. The project will be located
within the UP campus. Adherence to the increasing awareness towards protecting the environment,
the structure will use natural ventilation and rainwater cistern. This way, the occupants will pay
less since electricity and water bills nowadays are very expensive.
2
1.2 Project Objective
The project aims to:
Provide students with the luxury of saving time and maximizing every opportunity
available
Lessen the utility cost of the occupants regarding the electricity and water bills
Design a cistern for storing rainwater which will provide sanitary water for the whole
dormitory. The cistern acts like a reservoir for rainwater.
1.3 Design Norms Considered
The group believes that being efficient, economical and sustainable are the most relevant
norms to base the design and construction of the structures for this study.
Considering the design norm of being efficient, the group will focus on the capabilities and
competence of the materials. This will be used in the structure since cleaning and treating water
through series of filters will take lesser time and effort compared to other complex and expensive
treating processes. At the same time, the group will be economical since it will focus on the least
possible cost of materials needed in the design process. Finally, the design will be sustainable by
using the principle of natural light and ventilation with cistern.
In addition, the design will be governed by the National Structural Codes of the Philippines
(NSCP) (2010, 6th Edition, Volume 2) for structural analysis and the Uniform Building Code
(UBC) (1997) for seismic analysis.
1.4 Major and Minor Areas of Civil Engineering
The major area of civil engineering in this project will be structural engineering. The focus
of the project is to design an eco-friendly dormitory for students. Considerations in designing it
thoroughly is very important to save building construction and operation costs.
Water resources engineering and environmental engineering are the minor areas of civil
engineering in this project. It will be provided through a cistern for storing rainwater to provide
sanitary for the whole dormitory. The cistern acts as a reservoir for rainwater. At the same time,
environmental engineering is concerned because we are using natural resources as a daily basis
while saving electricity and water.
3
1.5 Project Beneficiary
The direct beneficiary of this project is Architect Jun Chan of DPWH district office, owner
of the planned four storey dormitory.
The indirect beneficiary of this project will be the students of UP. Given that the number
of dormitory spaces are very limited, we reiterate that students who live distantly and those coming
from the lower income bracket are given top priority to avail of this service. UP plans to innovate
their dormitories by building and adding more in the succeeding years around the campus. If this
thesis project will be implemented, students and other immediate parties concerned will benefit
from it.
1.6 Innovative Approach
Innovative approach is accessible for this type of project. AutoCAD 2013 will be used to
design the structure while E-tabs are essential for the design and computation of loadings. Google
Sketch Up 8 on the other hand will conceptualize the project and become available in three
dimensional function. The researchers will provide an inverted roof design with openings from
frontal and posterior angles of the structure. It will provide ecological benefits. At the same time,
the green building will go with a rainwater cistern that will provide sufficient utility water for the
building.
1.7 Research Component
The researchers will pursue studying the effectiveness of green building concept in the
Philippines. The existing green engineering design systems or methods will be evaluated if they
are viable for the design of the proposed infrastructure.
The main research component of this project is to construct a dormitory with green features,
identifying proper placement of the building on site so that natural light and ventilation can be
achieved on the structure. A rainwater cistern installed at the side of the dormitory will be available
to serve as a water source for drinking and sanitary use.
The plan of the project is to provide students with the luxury of saving time and maximizing
every opportunity available for them. UP plans to innovate their dormitories by building and
adding more of its kind near the campus area.
4
1.8 Design Component
The design component will cover the design of the superstructure and substructure. It will
include the design of structural members which are the roof truss, slabs, column, beams and walls;
while the substructure is composed of the foundation. The project will follow the most economical
design which will be referred to the National Structural Code of the Philippines (NSCP) (2010).
Also, the design of a rainwater harvesting system will be provided.
Natural light & ventilation
Through openings on the front and the back of the structure, there are airways or
breezeways located on the left and right wing of every floor, free – flowing light
and air permeates around the structure.
Rainwater cistern
A cistern is purposed for storing rainwater to provide sanitary water for the whole
dormitory. The cistern acts like a reservoir for rainwater. This will be used for
cleaning, flushing and as tap water. If intended to use for drinking, a filtration
system must be added. The roof will be designed to be an inverted gable roof. This
will easily harvest rainwater leading to the underground cistern through pipes.
1.9 Sustainable Development
Rainwater cistern
o Stores water to provide drinking and sanitary for the dormitory
Partially open structure
o For natural light and ventilation - supplying and removing air through an indoor
space by natural means
5
Chapter 2
Environmental Examination Report
2.1 Project Description
This project proposal aims to design a four storey dormitory with natural light, ventilation
and rainwater cistern. A green building that reduces impact to the environment through
management of energy, air and water. This project strives to design an eco-friendly structure. This
project will benefit the students and/or employees of UP as it requires minimal cost compared to
others. The design will meet economical standards, continually benefiting all concerned consumers
in terms of drinking water and sanitary purposes.
2.1.1 Project Rationale
The idea of the project is to be a model construction. Sustainable design focusing on
optimizing system efficiency, partially involving structures for the flow of light and
ventilation based on the location’s basic wind speed. Rainwater cistern which is responsible
for storing rainwater throughout the whole building is designed based on the area of
catchment.
2.1.2 Project Location
The project will be implemented at Emilio Jacinto Street corner C.P. Garcia,
Quezon City, Philippines.
6
2.1.3 Project Information
The structure will have openings on the front and the back, there are airways or
breezeways located on the left and right side of every floor, through this free – flowing
light and air permeates around the structure.
A cistern is purposed for storing rainwater to provide sanitary water for the whole
dormitory. The cistern acts like a reservoir for rainwater. This will be used for cleaning,
flushing and as tap water. If intended to use for drinking, a filtration system must be added.
The roof will be designed to be an inverted gable roof. This will easily harvest rainwater
leading to the underground cistern through pipes.
2.1.4 Description of Project Phases
This project is to be done in four phases: (1) Pre-construction/operational phase is
the preparation before starting the construction of the building, (2) construction phase is
the actual construction of the building, (3) operational phase discusses the works done
within the construction period of the building, and (4) abandonment phase is the final
checking or assessment of the building.
2.1.5 Pre – Construction/Operational Phase
2.1.5.a Planning Stage
This part is used before actual construction starts. Visitation of the project location,
observation and inspection is done in this part. The engineers assess the given location to
come up with a design of a suitable structure.
2.1.5.b Preparation of Construction Documents
The construction documents are essential for engineers before executing the said
project. A building permit from the Quezon City Hall is the first important document, then
comes the bidders and their estimated price on the said project.
The bidding documents and the contract has the list of responsibilities on what the
contractor’s roles should be on the said project and so thus the owner. The documents are
then signed by both parties.
2.1.5.c Selection of Contractor
The contractor having the lowest price on their bid will be presented with the
project contract. The price of the winning contractor should not go beyond the price limit
given by the owner.
7
2.1.5.d Construction Planning
The construction planning consist of site investigation, site management, obtaining
permits, scheduling, excavation planning, estimating, value engineering and quality
control.
2.1.5.e Surveying and Staking
Before anything else, the lot must first be surveyed to know the restrictions and the
terrestrial distances. When staking out is done, mark the limits or periphery of the lot.
2.1.6 Construction Phase
2.1.6.a Clearing and Grubbing
This phase includes the removal/clearance of trees, slumps, roots, logs, rubbish and
other objectionable matter.
2.1.6.b Excavation
This phase pertains to the excavation and cut/fill of land.
2.1.6.c Building Structure
This phase will be the construction of foundation footings, columns, beams, slabs,
walls, roof truss, up to the method finishing.
2.1.6.d Water and Sewer Lines
This phase pertains to the installation of water and sewer lines.
2.1.6.e Rainwater Cistern
This phase includes the following processes:
Installation of water harvesters and pipes
Construction of rainwater cistern
2.1.6.f Power Distribution System
This phase will be managed by MERALCO
8
2.1.7 Operational Phase
During this period, the contractor is in charge for corrections of any identified
defects. Liability period within twelve months is applied to the completed structure.
2.2 Description of Environmental Setting and Receiving Environment
2.2.1 Physical Environment
The project is resided in one of the main roads of Quezon City. Sunlight is strongly
present in the area. The site has establishments in front of it which makes it an ideal place
to construct a dormitory.
2.2.2 Biological Environment
The environment is an open place. No existing structure on its vicinity so it is a
good area to incorporate natural lighting and ventilation.
2.2.3 Socio-Cultural, Economic and Environment
The project location is a university community which means that the vicinity
consists mostly of students or employees in nearby establishments. The area is not that big
and plenty of establishments are located around it.
2.2.4 Future Environmental Conditions without the Project
There will be a nominal effect on future environmental conditions without the
project. It will create job opportunities for the residents and will ease student’s adjustment
to college life, providing them with maximum opportunities to interact with their fellow
students, and to put them close to the school buildings and libraries.
9
2.3 Impact Assessment and Mitigation
2.3.1 Summary Matrix of Predicted Environmental Issues/Impacts and their Level
of Significance at Various Stages of Development
STAGE ENVIRONMENTAL
ISSUE/IMPACT
LEVEL OF
SIGNIFICANCE
Pre - Construction Noise
Air
Traffic / Passage
Mass Population
Moderate
Low Moderate
Low Moderate
High Impact
Construction Noise
Air
Traffic / Passage
Mass Population
Low Moderate
Low Moderate
Moderate
High Impact
Table 2.1 Summary Matrix of Predicted Environmental Issues/Impacts and their Level of
Significance at Various Stages of Development
2.3.2 Brief Discussion of Specific Significant Impacts on the Physical and Biological
Resources
2.3.2.a Air
There will be an effect on the air quality by the vehicles passing through.
2.3.2.b Noise The project will have effect on noise pollution by the machines that will
be using.
2.3.2.c Traffic / Passage
There will have no effect on the traffic or passage because of the
location is huge and the machines will be placed not on the road.
2.3.3 Brief Discussion of Significant Socio Effects/Impacts of the Project
Since the project is a residential building therefore it can also be a source of
business which promotes employment opportunities, there will be an increase in the
revenue.
10
2.4 Environmental Management Plan
2.4.1 Summary Matrix of Proposed Mitigation and Enhancement Measures,
Estimated Cost and Responsibilities
Impacts Mitigation Responsibilities
Noise Transportation of
machineries to check
on noise & vibration
Contractor
Air Dust Control (Net
and water sprinklers
will be provided);
Mask for laborers;
Regular maintenance
of heavy equipment;
Distribute system of
Deliveries;
Contractor
Mass Population Guarantee safety of
the project to avoid
accidents to people
Contractor
Table 2.2 Summary Matrix of Proposed Mitigation and Enhancement Measures,
Estimated Cost and Responsibilities
2.4.2 Brief Discussion of Mitigation and Enhancement Measures
First, the noise is measured during construction. The use of equipment/machineries
can create noise commotion to other establishments. Therefore, the equipment/machineries
must be carefully selected and prepared accordingly.
Second, the air is measured in the construction. Since the project location is a busy
road, many commuters will be affected. The construction of the project must avoid dust
control, providing net and water sprinklers.
Lastly, mass population that refer to the people coming in and out of the area. We
have to control the crowd for us to not have a problem on overcrowding the premises.
11
2.4.3 Monitoring Plan
Table 2.3 Monitoring Plan
2.4.4 Institutional Responsibilities and Agreements
The researchers considered the environmental effects of the project, as well
as the structural codes to be followed. Once it thus comply with the requirements of the
Engineering Office of the Quezon City Municipal, in the case of building an establishment
in the area.
ENVIRONMENTAL
PROBLEMS MITIGATION MONITORING
WORKER’S SAFETY
Execution of
personal protective
equipment;
Providing Gadgets;
Readiness of First
Aid
Daily
NOISE Proper scheduling of
construction Daily
DUST
Net and water
sprinklers will be
provided
Daily
TRAFFIC No Weekly
12
Chapter 3
Research Component
3.1 Abstract
This Proposed 4 storey dormitory is for the occupancy of students in the UP campus. The
structure design will feature green engineering. It will be provided with natural light, ventilation
and rainwater cistern. This proposed project strives to design an eco-friendly structure.
3.2 Introduction
Natural ventilation is becoming a gradually important design strategy for many buildings.
With careful design, such buildings can be inexpensive both to construct and to operate than more
heavily serviced equivalents. Many occupants prefer natural light and ventilation. Both of which
are structures of well-designed eco-friendly buildings. Low construction, running costs and a high
level of occupant satisfaction are key requirements for efficient buildings.
Natural rainfall can provide some of the cleanest occurring water that is accessible
anywhere. The most sustainable development to contribute is to provide a rainwater cistern that
can be used for storing rainwater. Through this technology, it can provide sanitary water for the whole structure.
This project aims to denote building structures considering not just aesthetics. It will satisfy
different standards compatible to the economy and the environment.
3.3 Review of Related Literature
3.3.1 Green Engineering
Green engineering is the design, commercialization, and use of processes and
products, which are feasible and economical while minimizing:
1. Generation of pollution at the source
2. Risk to human health and the environment
Green engineering embraces the concept that decisions to protect human health and
the environment can have the greatest impact and cost effectiveness when applied early to
the design and development phase of a process or product.
Principles of Green Engineering
1. Engineer processes and products holistically, use systems analysis, and integrate
environmental impact assessment tools.
2. Conserve and improve natural ecosystems while protecting human health and well-
being.
3. Use life-cycle thinking in all engineering activities.
13
4. Ensure that all material and energy inputs and outputs are as inherently safe and
benign as possible.
5. Minimize depletion of natural resources.
6. Strive to prevent waste.
7. Develop and apply engineering solutions, while being cognizant of local
geography, aspirations, and cultures.
8. Create engineering solutions beyond current or dominant technologies; improve,
innovate, and invent (technologies) to achieve sustainability.
9. Actively engage communities and stakeholders in development of engineering
solutions.
3.3.2 Green Building
Green building is an approach towards a buildings’ design, construction and
operation that conserves resources while it protects human health. Green buildings use less
energy, consume fewer natural resources such as water and forest products, and omit
pollutants into the environment. Because they are designed to make use of natural light and
good ventilation, green buildings provide a healthier indoor environment for their
occupants. Studies show that students in green buildings learn better and workers in green
buildings are more productive.
Green building brings together a vast array of practices, techniques, and skills to
reduce and ultimately eliminate the impacts of buildings on the environment and human
health. It often emphasizes taking advantage of renewable resources, e.g., using sunlight
through passive solar, active solar, and photovoltaic equipment, and using plants and trees
through green roofs, rain gardens, and reduction of rainwater run-off. Many other
techniques are used such as the use of low-impact building materials or using packed gravel
or permeable concrete instead of conventional concrete or asphalt to enhance
replenishment of ground water.
Sustainable or green building design and construction is the opportunity to use our
resources more efficiently, while creating healthier and more energy-efficient homes.
Although there is no magic formula, success comes in the form of leaving a lighter footprint
on the environment through conservation of resources. At the same time, balancing energy-
efficient, cost-effective, low-maintenance products for our construction needs. In other
words, green building design involves finding the delicate balance between homebuilding
and the sustainable environment.
14
3.3.3 Natural Light and Ventilation
Natural ventilation is the process of supplying and removing air through an indoor
space without the use of a fan or other mechanical system. It uses outdoor air flow caused
by pressure differences between the building and its surrounding to provide ventilation and
space cooling. Significant energy savings are also achieved through the use of natural
lighting and ventilation. The use of natural ventilation is definitely an advantage with the
raising concerns regarding the cost and environmental impact of energy use.
Natural ventilation can reduce building construction and operation costs. At the
same time it can reduce the energy consumption for air-conditioning and circulating fans.
An additional bonus is that no noisy fan will be of your concern.
Advantages of Natural Ventilation
o A fresh air supply for workers - proven to increase productivity & reduce staff
sickness
o Naturally ventilated - reduce your energy costs and carbon footprint without the
need for mechanical ventilation
o Night time purge of stale air - creating a fresh working environment for the staff
the following morning
o Better control of building temperature and CO² levels
o Free cooling
3.3.4 Rainwater Cistern
Rainwater harvesting is the accumulation and deposition of rainwater for reuse
before it reaches the aquifer. Uses include water for garden, water for livestock, water
for irrigation, etc. In many places, the water collected is just redirected to a deep pit with
percolation. The harvested water can be used for drinking water. If the storage is a tank,
that can be accessed and cleaned when needed.
Rainwater harvesting provides an independent water supply during regional water
restrictions and in developed countries is often used to supplement the main supply.
Rainwater harvesting provides water when there is drought. Rainwater harvesting prevents
flooding of low lying areas. Rainwater harvesting replenishes the ground water table and
enables our dug wells and bore wells to yield in a sustained manner. It helps in the
availability of clean water by reducing the salinity and the presence of iron salts.
Where there is no surface water, or where groundwater is deep or inaccessible due
to hard ground conditions, or where it is too salty, acidic or otherwise unpleasant or unfit
to drink, another source must be sought. In areas which have regular rainfall, the most
appropriate alternative is the collection of rainwater called ‘rainwater harvesting’. Falling
rain can provide some of the cleanest naturally occurring water that is available anywhere.
This is not surprising, as it is a result of a natural distillation process that is at risk only
from airborne particles and from man-made pollution caused by the smoke and ash of fires
and industrial processes, particularly those which burn fossil fuels.
15
Most modern technologies for obtaining drinking water are related to the
exploitation of surface water from rivers, streams and lakes, and groundwater from wells
and boreholes. However, these sources account for only 40% of total precipitation.
It is evident, therefore, that there is considerable scope for the collection of
rainwater when it falls, before huge losses occur due to evaporation and transpiration and
before it becomes contaminated by natural means or man-made activities.
The term ‘rainwater harvesting’ usually mean ‘the immediate collection of
rainwater running off surfaces upon which it has fallen directly’. This definition excludes
run-off from land watersheds into streams, rivers, lakes, etc. Water Aid is concerned
primarily with the provision of clean drinking water; therefore the rainwater harvesting
projects which it supports are mainly those where rainwater is collected from roofs, and
only to a lesser extent where it is collected from small ground or rock catchments.
Advantages of rainwater harvesting:
o Relatively cheap materials can be used for construction of containers and collecting
surfaces.
o Construction methods are relatively straightforward.
o Low maintenance costs and requirements.
o Collected rainwater can be consumed without treatment providing a clean
collecting surface has been used.
o Provides a supply of safe water close to homes, schools or clinics, encourages
increased consumption, reduces the time women and children spend collecting
water, reduces back strain or injuries from carrying heavy water containers.
3.4 Methodology
o Research for new possible innovation for building design.
o Consultation of the beneficiary for the expectation and needs of the project.
o Suggestion of possible green engineering features for the project.
o Preparation of the architectural plans of the structure.
o Application of the building codes and provisions with respect to NSCP 2010
manual.
o Utilization of computer software/s to be used in designing the project.
16
3.4.1 Flow Chart
Figure 3.1
3.5 Results and Discussion
After comprehensive study on green buildings, the researchers found out that it can really
contribute remarkable improvements to air, light quality and visual enhancement. Coupling the
green building with rainwater cistern will increase the structures use and efficiency.
According to the study, green building is an approach to building design, construction and
operations that protects resources while it protects human health. Green buildings use less energy,
consume less natural resources and secrete less pollutants into the environment. Because they are
designed to make use of natural light and good ventilation, green buildings provide a healthier
indoor environment for their occupants. Studies show that green buildings are more conducive for
students to learn and workers in green buildings are more productive.
Additional for the green building is the rainwater cistern that will be used to store and filter
the rain water. It can be used for sanitary and drinking purposes.
GREEN ENGINEERING
Location AnalysisSustainability of
Green Engineering
STRUCTURAL DESIGN
Application of innovative design &
materialsCost Estimation
4 STOREY BUILDING
Innovative Construction
MaterialsMaterial Resources
17
3.6 Conclusion and Recommendations
This study can contribute tremendous improvements to air and light quality and visual
enhancement. The researchers coupled the green building with a rainwater cistern.
The structure is built up of reinforced concrete since we considered it as a conventional
structural design. The greatest challenge of our project is its location, Emilio Jacinto Street corner
C.P. Garcia, Quezon City because it stands in one of the busiest streets of Quezon City.
The cistern will also act as a reservoir for the whole building for sanitary purposes. But the
main challenge is filtering the water coming from the cistern making it potable for drinking to the
tenants of the building. The building will have an inverted gable roof for catchment of rainwater
leading to the pipes of the cistern.
18
Chapter 4
Detailed Engineering Design
4.1 Loads and Codes
4.1.1 Introduction
The structural codes used in the structural design of the Proposed 4-Storey
Dormitory with Natural light, Ventilation and Rainwater Cistern in Emilio Jacinto Street
corner C.P. Garcia, Quezon City conforms to National Structural Code of the Philippines
2012 for Volume 1: For Building and other Vertical Structures and to American Concrete
Institute Code for Buildings. All values used on the design are found in NSCP 2012:
Minimum Design Loads. Seismic Considerations are in reference according to Uniform
Building Code 1997.
4.1.2 References and Standards
ACI 318-99 Building Code Requirements for Reinforced Concrete,
American Concrete Institute (ACI)
ACI 302.1R-96 Guide for Concrete Floor and Slab Construction,
American Concrete Institute (ACI)
ACI 360R Design of Slab on Grade,
American Concrete Institute (ACI)
ACI 224R Control of Cracking in Concrete Structures,
American Concrete Institute (ACI)
ACI 544.4R Design Construction for Steel Fiber Reinforced Concrete,
American Concrete Institute (ACI)
AISC 9th Edition Manual of Steel Construction, Allowable Stress Design,
American Institute of Steel Construction
AISI 1996 Edition Cold-Formed Steel Design Manual,
American Iron and Steel Institute
ASCE 7-95 Minimum Design Loads for Buildings and Other Structures
American Society of Civil Engineers
NSCP 6th Edition National Structural Code of the Philippines 2010. zVolume 1
UBC 1997 Edition Uniform Building Code
19
American Institute of Steel Construction (AISC) Publications:
Manual of Steel Construction, 9TH Edition, 1989
Detailing for Steel Construction, 1984
Engineering for Steel Construction, 1984
4.1.3 Design Loads
Unit weight of concrete 23.6 KN/m3
Unit weight of masonry grout 22 KN/m3
4.1.3.a Dead Loads
ON FLOORS
A. Slab self weight 4” thick (100mm) 2360 Pa
B. Floor Finish (ceramic tiles 20mm on 13mm
Mortar bed) 1200 Pa
D. Ceiling with suspended steel
Channel system 240 Pa
E. Movable Partition and miscellaneous 1000 Pa
F. CHB Wall” full plastered both faces 2940 Pa
4.1.3.b Live Loads
A. Residential 1900 Pa
4.1.3.c WIND LOAD (in accordance with NSCP-2010)
Location: Quezon City : Philippine Wind Zone II
Design Wind Pressure (P) shall be computed as follows:
p = qh [( G C pf ) – ( G C pi ) ]
20
Velocity Pressure (qz ) shall be computed as follows:
qz = 47.3 x 10 -6 Kz Kzt V2 IW
p = Design wind pressure in kPa
qh = Velocity pressure evaluated at height z = h, in kPa
qz = Velocity pressure evaluated at height z above ground in
kPa
Kz = Velocity pressure exposure coefficient evaluated at height z
(Refer to table 207-3 of NSCP)
Kzt = Topographic factor = (Refer to section 207.5.5 of NSCP}
IW = Importance factor = 1.0 (For Standard Occupancy)
GCpf = Product of equivalent external pressure coefficient and gust
effect factor to be used in determination of wind loads for
main wind-force resisting system of low-rise buildings
(Figure 207-4 of NSCP)
GCpi = Product of internal pressure coefficient and gust effect
factor to be used in the determination of wind loads for
buildings. (Figure 207-4 of NSCP)
4.1.3.d SEISMIC LOAD Location:
Quezon City: Seismic Zone 4
E = ρ Eh + Ev
Total Design Base Shear (Using Static Force Procedure):
V = CvI
RT W
Total Design Base need not exceed:
V = 2.5 Ca I
21
R W
Total Design Base Shear shall not be less than:
V = 0.11Ca I W
For Seismic Zone 4, Total Design Base Shear shall also not be less than:
V = 0.8 ZNvI
R W
WHERE:
E = The Earthquake load of an element of the Structure resulting from
the combination of the Horizontal Component, Eh, ant the Vertical
Component, Ev.
Eh = The Earthquake Load due to Base Shear, V
Ev = The load effect resulting from the vertical component of the
earthquake ground motion and is equal to an addition of 0.5CaID to
the dead load effect, D, for Strength Design, and may be taken as
zero for allowable Stress Design.
ρ = Reliability/Redundancy Factor = 1.0
V = Total Design Base Shear
R = 8.5 (for Special Moment-Resisting Frame, SMRF)
W = Total Seismic Dead Load
I = Importance Factor
= 1.0 (For Standard Occupancy Structure)
T = Ct (hn) ¾
= Elastic fundamental period of vibration, in seconds
Ct = 0.0853 (Steel Moment-Resisting Frames)
hn = Height of structure, in meters
22
4.1.3.e Load Combinations
Load combination 1 : DL + LL
Load combination 2 : 1.4DL + 1.7LL
Load combination 3 : 1.05DL + 1.275LL + 1.403EQX
Load combination 4 : 1.05DL + 1.275LL - 1.403EQX
Load combination 5 : 1.05DL + 1.275LL + 1.403EQY
Load combination 6 : 1.05DL + 1.275LL + 1.403EQY
Load combination 7 : 0.9DL + 1.43EQX
Load combination 8 : 0.9DL - 1.43EQX
Load combination 9 : 0.9DL + 1.43EQY
Load combination 10: 0.9DL - 1.43EQY
4.1.4 SLAB DESIGN
4.1.4.a Two-way Slab
S-1
Short span = 4m Long span = 7m m = .571 thickness = 125mm
Dead load: 7740 Pa Live load: 1900 Pa
Total factored load = 1.4(7740) + 1.7(1900) = 14.066 Kpa
Along short Span:
Computed negative moment = 20.42 KN - m
Computed Positive moment = 8.9 KN - m
fc = 27.6 Mpa
fy = 228, 12mm diameter conc. cover = 20mm
Edge reinforcements
Mu = .9 Ru bd2
20.42 x 10002 = .9(Ru) (1000) (99)2
23
Ru = 2.314
𝜌 = .0107 𝜌min = .0061 𝜌max = .0465
Use 𝜌 = .0107 𝜌 = As/Bd
As = 1061.51 mm2 n = 10
s = 100mm c/c
Midspan reinforcements
Mu = .9 Ru bd2
8.9 x 10002 = .9(Ru) (1000) (99)2
Ru = 1.009
𝜌 = .0045 𝜌min = .0061 𝜌max = .0465
Use 𝜌 = .0061 𝜌 = As/Bd
As = 607.89mm2 n = 6
s = 160mm c/c
Along long Span:
Computed negative moment = 4.62 KN - m
Computed Positive moment = 2.92 KN - m
fc = 27.6 Mpa
fy = 228, 12mm diameter conc. cover = 20mm
Edge reinforcements
Mu = .9 Ru bd2
4.62 x 10002 = .9(Ru) (1000) (87)2
Ru = .679
𝜌 = .003 𝜌min = .0061 𝜌max = .0465
Use 𝜌 = .0061 𝜌 = As/Bd
As = 534.21mm2 n = 5
s = 200mm c/c
Midspan reinforcements
24
Mu = .9 Ru bd2
2.92 x 10002 = .9(Ru) (1000) (87)2
Ru = .433
𝜌 = .0019 𝜌min = .0061 𝜌max = .0465
Use 𝜌 = .0061 𝜌 = As/Bd
As = 534.21mm2 n = 5
s = 200mm c/c
4.1.4.b One-way Slab
At supports
Mu = 7.912 KN – m
Mu = .9 Ru bd2
Ru = .897
𝜌 = .004 𝜌min = .006 𝜌max = .046
Use 𝜌 = .006 𝜌 = As/Bd
As = 607.895mm2 n = 6
s = 160mm c/c
At midspan
Mu = 9.042 KN – m
Mu = .9 Ru bd2
Ru = 1.025
𝜌 = .005 𝜌min = .006 𝜌max = .046
Use 𝜌 = .006 𝜌 = As/Bd
As = 607.895mm2 n = 6
s = 160mm c/c
25
Temperature bars
As = .002 (1000) (125) = 250mm2
S = 450mm c/c
4.1.5 Design of Stairs
T = 250 mm
R = 200 mm
G = 250 mm L = 1.9 M
S = 1.9575 m Cc = 15 mm
Øbar = 12 mm Steps = 8
f’c = 28 MPa Fy = 414 MPa
Δ conc = 24 KPa LL = 1.9 KN/m2
Slope of Stairs: θ = tan-1 (1.2125
1.7310) = 35°
Dimension of Stairs: 550 < 2R + T < 700
550 < 2(200) + (250) < 700
550 < 650 < 700
Therefore, sizes of stairs are adequate
Thickness of Waist: 𝑠
𝐸𝑓𝑓.𝐷𝑒𝑝𝑡ℎ = 30
d = 1957.5
30
for d effective:
26
Total W = d + cc + θ
2
Total W = 65.25 + 15 + 12
2
Total W = 86.25 mm
Assuming thickness waist of W = 90
d = 90 – 15 - 12
2
d = 69 mm
Dead Load of Staircase
B = √𝐺2 + 𝑅2
B = √(250)2 + (200)2
B = 296.81 mm
Say B = 297 mm
DL = 1
0.25 ((0.16)(0.297) +
(0.16)(0.20)
2+ (0.15)(0.27)(23.5))
DL = 7.2927 𝑘𝑁
𝑚2
Design Load per Staircase:
Wu = 1.2DL + 1.6LL
Wu = 1.2 (7.2927) + 1.6 (1.9)
Wu = 11.79 𝑘𝑁
𝑚2
Bending Moment per m width of Staircase
Mu = Wu𝐿2
8
Mu = (16.75)(1.9575)2
8
Mu = 8.0228 kN-m
Mu = 0.138f’cbd2
27
d = √Mu
0.138f’cb
d = √33.5𝑥106
0.138(28)(1000)
d = 45.57 mm < 69 mm
therefore, effective depth is effective
Area of Steel per m width staircase
Mu = 0.36 f’c (𝑥
𝑑) (1 − 0.59
𝑥
𝑑) bd2
Divided by 0.36 f’c (𝑥
𝑑) bd2
(6.68 Mu
f’cb𝑑2) = 2.4 (
𝑥
𝑑) - (
𝑥
𝑑)
2
(6.68 Mu
f’cb𝑑2) = (
6.68(8.0228𝑥102
28(1000)(69)2) = 1.6787
𝑥
𝑑 = 1.2 - √1.22 6.68 Mu
f’cbd2
𝑥
𝑑 = 1.2 - √1.22 − 1.6787
𝑥
𝑑 = 0.1811
z = d (1 – 0.416 (𝑥
𝑑))
z = 69 (1 – 0.416 (0.1811))
z = 63.8017
Asteel = Mu
0.85𝑓𝑦𝑧
Asteel = 8.0228𝑥106
0.85(414)(63.8017)
Asteel = 357.33 mm2 per width of staircase
Total Steel = Asteel (L)
28
Total Steel = 357.33 (1.9)
Total Steel = 678.927 mm2
No. of bars = Atotal steel
Abars
No. of bars = 678.927𝜋
4(12)2
= 6.003
say 7 bars
Spacing of main reinforcing bars
S = L
n =
1900
7 = 271.42
Say 270 mm
Therefore, provide 7 – 12 mm Ø @ 270 mm c/c
Distribution steel
Asteel ≥ AD
For fy = 248 MPa AD = 12% (Gross Area)
For fy = 414 MPa AD = 15% (Gross Area)
AD = 0.15
100 (1000)(200)
AD = 300 mm2
Spacing of distribution reinforcing bars per B of staircase
a. 5deffective = 5(139) = 695
b. 450
therefore, provide 24 – 12 mm Ø @ 95 mm c/c
29
Stair Detail Design
30
4.2 Structural Engineering
Structural Design
As the major area of civil engineering for this project is Structural Engineering, the
structure made focus of the project to design an eco-friendly dormitory for students. Consideration
on designing it thoroughly is very important to save building construction and operation costs.
AutoCAD 2013 will be used to design the structure while E-tabs are essential for the design
and computations of loadings. Google Sketch Up 8 on the other hand will conceptualize the project
and become available in three dimensional function. The researchers will provide an inverted roof
design with openings from frontal and posterior angles of the structure. At the same time, the
dormitory will go with a rainwater cistern that will provide sufficient utility water for the building.
In addition, the design will be govern by the National Structure Codes of the Philippines
(NSCP) (2010, 6TH Edition, Volume 2) for structural analysis and the Uniform Building Code
(UBC) (1997) for seismic analysis.
Dead loads were from the National Structural code of the Philippines (NSCP 2010) Volume
1 Table 204-2 Minimum Design Dead Loads. The loads depend on the materials listed on the Table
204-2 but you can alter the values as long as they are not lower than the suggested minimum values
of the NSCP.
The Live Load on one structure may vary depending on the type of occupancy of room or
a floor area
The Seismic Load location is in Quezon City which is Seismic Zone 4.
E = ρ Eh + Ev
Total Design Base Shear (Using Static Force Procedure): V = CvI
𝑅𝑇 𝑊
Total Design Base need not exceed: V = 2.5 𝐶𝑎 𝐼
𝑅 𝑊
Total Design Base Shear shall not be less than: V = 0.11Ca I W
For Seismic Zone 4, Total Design Base Shear shall also not be less than:
V = 0.8 𝑍𝑁𝑣𝐼
𝑅 𝑊
These are the following combinations used for the design, gathered from the National
Structural Code of the Philippines 2010 (NSCP 2010).
31
DL + LL
1.4DL + 1.7LL
1.05DL + 1.275LL + 1.403EQX
1.05DL + 1.275LL - 1.403EQX
1.05DL + 1.275LL + 1.403EQY
1.05DL + 1.275LL + 1.403EQY
0.9DL + 1.43EQX
0.9DL - 1.43EQX
0.9DL + 1.43EQY
0.9DL - 1.43EQY
For the materials, Ultimate compressive strength of concrete at 28th day, f’c = 27.6.0 MPa
(4000 psi). Yield strength of reinforcing bars; Fy = 414 MPa (Grade 60, 60,000psi) for all beams,
girders, and columns and footings for 16mmФ and larger barsFy = 228 MPa (Grade 33,000psi) for
12mmФ and smaller bars Yield strength of structural steel, fy = 248 Mpa (A36, 36,000 psi). Yield
strength of Light-gage Structural Steel, fy = 227 Mpa (A33, 33,000 psi). Steel Fiber reinforcement
for slab on grade shall be DRAMIX or approved equal.
The foundation shall be of isolated footing with tie beams and shall rest soil. Bearing
capacity is 160KPa.
The concept of this project is to construct an eco-friendly dormitory, identifying proper
placement of the building on site so that natural light and ventilation can be achieved o the
structure.
The design will include the design of structural members which are the roof truss, slabs,
columns, beams, and walls; while the substructure is composed of the foundation.
32
The proposed construction of four storey residential building is located in Emilio Jacinto
Street corner C.P. Garcia, Quezon City, Philippines. The proposed structure has an approximate
area of 700 square meters with a height of about 13 meters. The lateral loads shall be of a Special
Moment Resisting Frame in concrete gravity and lateral loads shall be transmitted to the supporting
soil strata by isolated footing stiffened by tie beams. The structural shall be modeled as three (3)
– dimensional space framing using ETABS Non Linear (Ver 9.70). Foundation of the structure
shall rest on soil with a bearing capacity of 160 KPa.
Although structural engineering is the major civil engineering area to tackle for his project,
its design is only considering the buildings resistance to its own weight and the other loads. The
considerations on the environmental and the water resources management are more crucial for this
project.
33
4.2.2 General Construction Notes
100 MATERIAL SPECIFICATIONS
100.1 CONCRETE Fc = 27 MPa
100.2 CEMENT PORTLAND ASTM C150
100.3 NORMAL WEIGHT AGGREGATES ASTM C33
100.4 ADMIXTURES ASTM C494
100.4.1 STEEL FIBER REINFORCEMENT DRAMIX OR APPROVED EQUAL
100.5 REINFORCING BARS FY = 414 MPA
100.6 STRUCTURAL STEEL A36 A 36
100.7 CONNECTION BOLTS AND NUTS A 325
100.8 SOIL BEARING CAPACITY 160 KPa
200 CONSTRUCTION SPECIFICATIONS:
200.1 ALL WORKS SHALL CONFORM TO THE FOLLOWING SPECIFICATIONS
ACI 318-99 AISC 9TH EDITION, UBC1997, NATIONAL STRUCTURAL CODE
OF THE PHILIPPINES (NSCP) 6TH EDITION AND ALL PERTINENT PHIL.
CODES.
300 EXCAVATION AND PREPARATION OF FOUNDATION BASE:
300.1 SOIL BEARING TYPE FOUNDATION SUCH AS LADDERS, STAIRS,
LOCAL PIPE SUPPORTS, SLEEPERS WALL FRAMING FOUNDATIONS
AND MINOR FOUNDATIONS MAY BE SET DIRECTLY ON CONCRETE
SLAB OR PAVEMENT.
300.2 MAJOR FOUNDATIONS FOR THE MAIN FRAME SHOULD BE FOUNDED
OR APPROPRIATE LEVEL SUITABLE TO THE HEIGHT OF THE
STRUCTURE AND TYPE OF SOIL OR AS DIRECTED BY THE SOIL
ENGINEERS.
300.3 MEMBRANE FOR DAMP PROOFING OF GRADE SLABS SHALL BE
POLYETHYLENE FILM 0.1MM TO PROTECT CEMENT SEGREGATION.
34
300.4 ALL BASES OF FOUNDATION SHALL BE PREPARED LEVEL AND EVEN
WITH 50MM. THK. BLINDING CONCRETE ON WELL PREPARED AND
COMPACTED SOIL TO 95% MAX. DRY DENSITY.
300.5 IN CASE OF EXCAVATION IS BELOW WATER LEVEL, PROVISION
SHALL BE MADE TO ARREST OR CONTAIN INDULGENCE OF
WATEROUS AREA.
300.6 VIBRATING MACHINERY FOUNDATIONS SHALL BE PROVIDED WITH
ISOLATION JOINT FROM PERIPHERY OF STRUCTURE WITH 25MM
MASTIC FILL EXPANSION JOINT OR COMPRESSIBLE JOINT FILLER.
400 CONCRETE WORKS:
400.1 CONCRETE SHALL BE PROPORTIONED BY APPROVED DESIGN MIX
ATTAINING THE REQ’D. CONCRETE DESIGN STRENGTH.
400.2 CONCRETING WORKS SHALL BE CONTINUOUS IN ORDER TO AVOID
SETTING OF CONCRETE CREATING A DANGEROUS JOINT.
400.3 CONCRETE TESTING SHALL CONFORM TO THE APPROVED
PROCEDURES ASTM C172
500 REINFORCING STEEL:
500.1 MIN. LENGTH OF SPLICING LAP SHALL BE 40 BAR DIAMETER FOR
CRITICAL SPLICING SUCH AS TENSION ZONES AND TOP BARS OTHER
SPLICING BAR SHALL BE 30 BAR DIAMETER OR AS APPROVED BY THE
ENGINEER.
500.2 SPLICES SHALL BE LOCATED AT STAGGERED POINT.
500.3 MIN. CONCRETE PROTECTION FOR REINFORCING BAR SHALL BE AS
FOLLOWS UNLESS OTHERWISE SHOWN ON THE DESIGN DRAWINGS.
35
DIVISION OBJECT COVER (MM.)
ABOVE SLAB AND NON BEARING EXPOSED 30
GROUND WALL, COLUMN, BEAM PLASTERED 20
AND BEARING WALL
RETAINING WALL
BELOW COLUMN, BEAM, SLAB EXPOSED 20
GROUND AND NON-BEARING WALL PLASTERED 40
FOUNDATION, RETAINING
WALL
NOTE:
600.1 CONTRACTOR TO PROVIDE SHOP DRAWINGS, ON MINOR DETAILS
FOR APPROVAL BY THE DESIGNER.
4.2.3 Foundation Design
The foundation shall be of isolated footing with tie beams and shall rest soil. Using
160 KPa bearing capacity.
Figure 4.1 Footing Schedule
The footing is design as doubly reinforced because of thickness (400mm) and additional
reinforcement for earthquake loads.
36
4.2.4 Slab Design
SLAB
DESIGNATION THICKNESS(mm)
SHORT SPAN LONG SPAN
ON
SUPPORTS MIDSPAN
ON
SUPPORTS MIDSPAN
S-1 (TWO-WAY) 125 100 160 200 200
S-2 (ONE-WAY) 125 160 160 450 (TEMP. BARS)
Figure 4.2 Slab Schedule
4.2.5 Beam Design
Figure 4.3 Beam Schedule
37
Figure 4.4 Beam Schedule
38
4.2.8 Column Design
Figure 4.5 Column Schedule
39
4.3 Water Resources Engineering
Rainwater Cistern Design
4.3.1 Introduction
Water Resources Engineering is the minor area of the project. Besides being a green
building. The dormitory has its own rainwater cistern that aims to somehow save water and energy
for utility usage.
Water Resources Engineering focuses on the use and management of land and water
resources in rural and urban watersheds. It is one of the areas of Civil Engineering which we
considered in our thesis project.
Water resources engineering is the major area of civil engineering in this project. It will be
provided through a cistern for storing rainwater to provide sanitary for the whole dormitory. The
cistern acts as a reservoir.
The design of the water harvesting system is dependent on many factors. First is the
catchment, which we designed the inverted roof that will serve as its catchment.
A system of gutters and downspouts directs the rainwater collected by the roof to the
storage cistern. The cistern, typically located underground, may be constructed of various materials
including cinderblock, reinforced concrete, or precast concrete or steel. The cistern supplies water
to the household through a standard pressurized plumbing system.
Current use of rainwater cisterns may be increasing. Those who live in areas where
groundwater and surface water are unobtainable or unsuitable for use have been compelled to
resort to other sources of water. Rainwater collection on a household scale is quite practical in
areas where there is adequate rainfall, and other acceptable sources of water are lacking.
The storage capacity of a rainwater cistern depends on several factors:
the amount of rainfall available for use,
the roof-catchment area available for collecting that rainfall,
the daily water requirements of the household,
and economics.
All but the first of these factors can be controlled to some extent by the cistern owner.
40
A water catchment system for roof rainwater is simple, and can store water for outdoor irrigation.
Gutters: Roof water gathers in the gutters and runs to a pipe towards the tank.
"First Flush": The first rain of the year is the dirtiest as it cleans the roof. This water is
directed away from the tank in a "first flush system" and the subsequent water continues to the tank.
Screen: The rainwater goes through a screen to remove leaves and debris, and then funnels into the top of the covered tank.
Storage: The tank is dark, to prevent algea from growing, and screened, to prevent
mosquitoes from entering.
Irrigation: A hose attachment is located near the bottom for irrigation.
The roof area to be used as the collection surface is usually predetermined by the size of
the existing house or other outbuilding roofs. However, when planning a rainwater collection
system from the ground up, where the size of the catchment is to be designed to suit domestic
water needs.
For roof catchments, rough-surfaced roofing materials will collect dirt and debris which
will affect the quality of the run off. All gutters and downspouts should be easy to clean and
inspect. Aluminum screening ¼-inch or ½-inch mesh hardware cloth will be cut into strips and
secured over the top of the gutters. Gutter guards will keep leaves, twigs and animals out but let
water in.
Concrete block is used for the walls of the cistern, all hollow cores should be filled with
concrete and reinforcing rods should be placed vertically to add strength to the structure. The top
of the cistern should be of reinforced concrete and should fit tightly onto the rest of the structure. a
manhole through the top of the cistern to allow access to the storage tank should be included. Such
an opening should be at least 2 feet across. Place the manhole opening near a corner or an edge of
the structure so that a ladder can be lowered into the cistern and braced securely against a wall.
The interior walls and floor of the cistern should be smooth to make acleaning easier. A
cement plaster can be spread over the interior. Cement based sealant will be applied to the interior
as well, to provide smoother finish and further protection against leakage.
41
A cistern should have sufficient storage capacity to carry the household through extended periods of low rainfall.
The rainwater cistern will be using cast-in-place reinforced concrete. Cast-in-place reinforced concrete is considered best, especially for underground cisterns.
Water quality is of concern especially when the rainwater is to be used for drinking
purposes in addition to other domestic uses. Rainwater and atmospheric dust that are collected by
roof catchments contain certain contaminants which may pose a health threat to those consuming
the water. Lead and other pollutants may accumulate in cistern bottom sediments; and untreated
rainwater is quite corrosive to plumbing systems.
Rainwater harvesting is one strategy in the greater scheme of reducing domestic water use.
By harvesting rainwater, we can be led to dozens of other practices that bring us into greater
sustainability. Growing plants that shade and insulate windows reduces energy use; increasing
home food production reduces demand for wasteful water use in industrial fields. Above all,
rainwater harvesting increases quality of life: ours, and that of life worldwide.
42
4.3.2 Section Detail
Figure 4.6 Cistern Section Detail
43
4.3.3 Foundation detail
Figure 4.7 Cistern Foundation Detail
44
4.3.4 Gutter guards
Figure 4.8 Gutter Guards
45
4.4 Environmental Engineering
Green Building
4.4.1 Introduction
Environmental engineering is the integration of science and engineering principles to
improve the natural environment, to provide healthy water, air, and land for human habitation and
for other organisms, and to clean up pollution sites.[citation needed] Environmental Engineering
can also be described as a branch of applied science and technology that address the issue of energy
preservation, production asset and control of waste from human and animal activities.
Environmental Engineering is also a minor area of this project. Green building (also known
as green construction or sustainable building) refers to a structure and using process that is
environmentally responsible and resource-efficient throughout a building's life-cycle: from siting
to design, construction, operation, maintenance, renovation, and demolition. This requires close
cooperation of the design team, the architects, the engineers, and the client at all project stages.
A green building focuses on the design of materials, processes, systems and devices with
the objective of minimizing overall impact (including energy utilization and waste production)
throughout the entire life cycle of a product or process, from initial extraction of raw materials
used in manufacture to ultimate disposal of materials that cannot be reused or recycled at the end
of the useful life of a product.
The focus of green building is to design an eco-friendly structure that is efficient,
economical and sustainable as well. A green building is a perfect example of satisfying the
economic and environmental standards while providing aesthetics.
In keeping with our client’s vision, and our own sense of responsibility and awareness, we
strive to integrate sustainable concepts at every phase of design and construction. We understand
all site layout and infrastructure decisions must consider the potential impacts on surrounding
communities. We manage construction issues through a staged approach to protect natural
resources, and our site plans are intentionally designed with sensitivity to biologically significant
areas to minimize habitat disturbance and provide ecological restoration as needed.
The researchers will focus on the capabilities and competence of the materials that will be used in
the structure since cleaning and treating water through treating processes. Also, the group will
focus on the least possible cost of materials needed in the design process.
The green features of this structure will include: an inverted roof design for catchment
purposes of the structure. Natural light and ventilation of the structure. And a rainwater cistern for
sanitary water reservoir of the structure.
46
4.4.2 Rainwater Cistern
A cistern is a large vessel which is used to hold a reserve of water. Cisterns can be either
above or below ground, and they come in a range of sizes and shapes, with varying features. The
cistern acts like a reservoir for rainwater. The use of rainwater is for tap water, cleaning and
flushing. If intended to use for drinking, a filtration system must be added.
A cistern is purposed for storing rainwater to provide sanitary water for the whole
dormitory. The cistern acts like a reservoir for rainwater. The use of rainwater is for tap water,
cleaning and flushing. If intended to use for drinking, a filtration system must be added.
The cistern will be placed underground but beside of the structure, not underneath the
structure like most of other structures that has cisterns. The cistern will consist of a filter layer
which segregates a huge amount of plant and other media from entering the cistern. It will also
prevent the cistern from being clogged due to the organic materials that can be caught from the
roof.
4.4.3 Inverted Gable Roof
. The roof will be designed to be an inverted gable roof. This will easily harvest rainwater
leading to the underground cistern through pipes. The roof material will be a corrugated
galvanized iron sheet. The advantages of this is to lessen the use of side gutters for the roof, since
rainwater will directly pour into the middle of the roof, there is no need for a gutter.
4.4.4 Natural Light and Ventilation
Natural ventilation is the process of supplying and removing air through an indoor space
by natural means, meaning without the use of a fan or other mechanical system. It uses outdoor air
flow caused by pressure differences between the building and its surrounding to provide ventilation
and space cooling. Significant energy savings are also achieved through the use of natural lighting
and ventilation.
Natural Lighting Systems
Natural lighting systems are the perfect complement to our natural ventilation systems.
Daylighting systems offer a modern, realistic and compelling alternative to artificial lighting for
commercial, industrial and domestic projects.
47
The benefits of piping brilliant, natural sunlight into a space are widespread and available
for both new and existing buildings. Our natural light systems have successfully transformed
homes, offices, schools, factories and hospitals. All the time reducing their energy consumption,
Some of the advantages of natural ventilation include a night time purge of stale air creating
a fresh working environment the following morning, better control of building and carbon dioxide
levels, free cooling and fresh air supply for the residents of the dormitory.
The design of the structure, to achieve the natural light and ventilation, will have opening
on the side, front and back of the dormitory. This is so that outdoor airflow caused by pressure
differences between the building and its surroundings to provide ventilation and space cooling.
48
4.5 Plan Set
4.5.1 Structural Plans
Figure 4.9 Grid 1 (form ETABS)
49
Figure 4.10 Grid 2 (from ETABS)
50
Figure 4.11 Grid 3 (from ETABS)
51
Figure 4.12 Grid 4 (from ETABS)
52
Figure 4.13 3D View (from ETABS)
53
Figure 4.14 Sample Moment Diagram
54
4.5.2 Architectural Plans
Figure 4.15 Ground Floor Plan
55
Figure 4.16 2-4th Floor Plan
56
Figure 4.17 Room Plan
57
Chapter 5
Promotional Material
58
59
Chapter 6
6.1 Budget Estimation
Below is the list of materials and their quantities that shows how much of each material
will be used in the overall construction of the structure. This will also be the basis for the overall
cost that the owner will be charged depending on the contracts signed.
Most unit prices were found over the internet which are up to date and some were asked to
experienced people in this field.
Project: Proposed 4-Storey Dormitory with Natural Light, Ventilation and Rainwater Cistern
Location: Emilio Jacinto Street corber C.P. Garcia, Quzon City, Philippines
Owner: Arch. Jun Chan
Date: December 2013
ITEM SCOPE OF WORK QTY UNIT AMOUNT
Table 6.1
PRELIMINARIES
1 MOBILIZATION 1.00 LOT 30, 000
2 TEMPORARY
FACILITIES
1.00 LOT 275,000
3 UTILITIES 8.00 MOS 80, 000
4 BUILDING PERMIT LOT 230,000
5 CARI 1.00 LOT 100,000
6 HAULING OF
GARBAGE AND DEBRIS
1.00 LOT 90, 000
7 AS BUILT PLANS 1.00 LOT 50,000
8 OCCUPANCY PERMITS LOT 100,000
9 DEMOBILIZATION 1.00 LOT 33,500
988,500
60
SITEWORKS
1 CLEANING &
GRUBBING
1.00 LOT 30,000
2 LAYOUTING &
STAKING
1.00 LOT 20,000
3 EXCAVATION 640 𝑚3 128,000
4 BACKFILLING 88 𝑚3 8,750
5 SOIL POISONING 1.00 LOT 15000
6 GRAVEL BEDDING 55 𝑚3 47,850
249, 600
Table 6.2
FORMWORKS & SCAFFOLDING
COLUMNS 3448 𝒎𝟐 2,568,462
BEAMS 3782 𝑚2 3,257,148
STAIRS 356 𝑚2 266,899
SLAB 2447 𝑚2 1,467,941
COLUMN FOOTING 168 𝑚2 100,521
7,660,968
Table 6.3
61
REINFORCING BARS/ STEEL WORKS
COLUMN FOOTING 16682 kgs 580,751
WALL FOOTING 5694 kgs 290,376
COLUMNS 68323 kgs 3,484,505
BEAMS 77434 kgs 3,949,106
SLAB 59214 kgs 3,019,905
STAIRS 5694 kgs 290,376
11,615,016
Table 6.4
CONCRETE WORKS
COLUMN FOOTING 154 𝒎𝟑 751,270
WALL FOOTING 58 𝑚3 281,726
COLUMNS 557 𝑚3 2,723,351
BEAMS 519 𝑚3 2,535,533
SLAB 577 𝑚3 2,817,260
STAIRS 58 𝑚3 281,726
9,390,864
Table 6.5
62
MASONRY WORKS
6’’ CHB LAYING 1660 𝒎𝟐 962,564
4’’ CHB LAYING 1580 𝑚2 911,903
PLASTERING 4882 𝑚2 2,685,046
CONCRETE TOPPING 91 𝑚3 329,299
LINEAR PLASTERING 592 m 177,315
5,066,124
Table 6.6
ELECTRICAL WORKS
WIRES & CABLES 1.00 LOT 470,000
PIPES, FITTINGS,
BOXES
1.00 LOT 380,000
WIRING DEVICES 1.00 LOT 190,000
LIGHTING FIXTURES 1.00 LOT 560,000
PANEL BOARDS 1.00 LOT 158,864
PEDESTAL 1.00 LOT 490,000
2,248,864
Table 6.7
63
PLUMBING WORK
WATERLINE 1.00 LOT 580,000
STORM DRAINAGE
LINE
1.00 LOT 520,000
SEWER SYSTEM 1.00 LOT 700,000
PLUMBING FIXTURES
& INSTALLATION
1.00 LOT 911,282
TESTING &
COMISSIONING
1.00 LOT 10,000
VENT SYSTEM 1.00 LOT 180,000
2,901,283
Table 6.8
SPECIALTY WORKS
1 WOOD&SASH WORKS 1.00 LOT 870,465
2 PAINTING WORKS 1.00 LOT 2,822,201
3 THERMAL &MOIST
PROTECTION
1.00 LOT 494,256
4 CEILING WORKS 1.00 LOT 1,413,573
5 GLASS WINDOW 1.00 LOT 2,466,338
6 WALL FINISH 1.00 LOT 785,867
7 FLOOR FINISH 1.00 LOT 1,554,435
Table 6.9
64
6.2 Project Cost
PARTICULARS COST IN PESOS
COST OF LAND (RENT ANNUALLY ) 1,260,000
COST OF BUILDING 49,425,600
FURNITURE & FIXTURE 1,579,000
ANNUAL OPERATING EXPENSES 384,000
TOTAL 52,648,600
Table 6.10
6.2.1 Estimated Gross Income
STUDIO UNITS 36 ROOMS
(4 person per unit)
7000/person 1,008,000
COMMERCIAL
UNITS
8 30 000 240,000
PARKING 3O CARS 30/hr (assuming
8 hrs a day)
216,000
TOTAL 1,464,000
Table 6.11
6.2.2 Estimated Expenses
LAND RENTAL 105,000
BULDING DEPRECIATION 164,752
REPAIR &MAINTAINANCE 20,000
CABINETRY&FURNTURES 6464
BEDSHEET&CUSHION 22,000
TOTAL 318,216
Table 6.12
65
NET INCOME IN 30 DAYS = 1,145,784
YEARLY NET INCOME = 13,794,408
PAYBACK PERIOD = 49,425,605
13,794,408 = 3.5 YEARS
RETURN OF INVESTMENT = 13,794,408
49,425,605 X 100 % = 28 %
66
Chapter 7
Project Schedule
The 4-Storey Dormitory with Natural light, air ventilation and Rainwater Cistern in Quezon City
has been planned to be completed in 130 working days. The project schedule is gathered using a
Project Management Software, Microsoft Project.
ITE
M
DE
SC
RIP
TI
ON
OF
CO
ST
ITE
M
CO
NT
RA
CT
PE
SO
VA
LU
E
% V
AL
UE
1S
T M
ON
TH
2N
D M
ON
TH
3R
D M
ON
TH
4T
H M
ON
T
5T
H M
ON
TH
6T
H M
ON
TH
7T
H M
ON
TH
8T
H M
ON
TH
I GE
NE
RA
L
CO
ST
RE
QU
IRE
-ME
NT
98
8,5
00
2
37
5,6
30
87
,55
3
87
,55
3
87
,55
3
87
,55
3
87
,55
3
87
,55
3
87
,55
3
II
EA
RT
H
WO
RK
S
24
9, 6
00
0.5
05
12
4,8
00
12
4,8
00
III
RE
BA
RS
11
,61
5,0
16
23
.5
2,9
03
,75
4
2,9
03
,75
4
2,9
03
,75
4
2,9
03
,75
4
IV
FO
RM
WO
RK
S
7,6
60,9
68
15.5
766,0
69
1,5
32,1
94
1,5
32,1
94
1,5
32,1
94
229,8
291
V
CO
NC
RE
T-I
NG
WO
RK
S
9,3
90
,86
4
19
1,8
78
,17
3
1,8
78
,17
3
1,8
78
,17
3
1,8
78
,17
3
1,8
78
,17
3
67
VI
MA
SO
NR
Y
5,0
66,1
24
10.2
5
389,7
02
779,4
04
779,4
04
779,4
04
779,4
04
779,4
04
VII
EL
EC
TR
ICA
L
WO
RK
S
2,2
48,8
64
4.5
5
149,9
25
299,8
49
299,8
49
299,8
49
299,8
49
299,8
49
299,8
49
299,8
49
VII
PL
UM
BIN
G &
SA
NIT
AR
Y
WO
RK
S
2,9
01
,283
5.8
7
38
6,8
38
38
6,8
38
38
6,8
38
38
6,8
38
38
6,8
38
38
6,8
38
38
6,8
38
IX
SP
EC
IAL
TY
WO
RK
S
A
TH
ER
MA
L
&
MO
IST
PR
OT
EC
TIO
N
49
4,2
56
1
16
4,7
52
16
4,7
52
16
4,7
52
B
PA
INT
ING
WO
RK
S
2,8
22
,20
1
5.7
1
403,1
72
403,1
72
403,1
72
403,1
72
403,1
72
403,1
72
403,1
72
C
WO
OD
& S
AS
H
WO
RK
S
870,4
65
1.6
6
174,0
93
174
,093
174,0
93
174,0
93
174,0
93
68
D
CE
ILIN
G
WO
RK
S
1,4
13,5
73
2.8
6
235,5
96
235,5
96
235,5
96
235,5
96
235,5
96
235,5
96
E
GL
AS
S
WIN
DO
WS
2,4
66,3
38
4.9
9
493,2
68
493,2
68
493,2
68
493,2
68
493,2
68
F
FL
OO
R
FIN
ISH
1,5
54,4
35
3.1
45
310,8
87
310,8
87
310,8
87
310,8
87
310
,887
GR
AN
D T
OT
AL
49
,42
5,6
00
10
0 %
PR
OJ
EC
TE
D
MO
NT
HL
Y V
AL
UE
4,3
20
,17
8
8,0
06
,02
9
8,6
71
,28
5
9,4
84
,78
1
7,5
11
,87
6
5,2
13
,58
5
3,1
70
,66
0
2,3
91
,25
6
% V
AL
UE
8.7
4%
16.2
0%
17.5
4%
20.4
9%
15.1
9%
10.5
5%
6.4
2%
4.8
4%
69
7.1 S-Curve
Figure 7.1
70
Figure 7.2
71
Figure 7.3
72
Figure 7.4
73
Figure 7.4
74
Figure 7.5
75
Figure 7.
76
Chapter 8
Conclusion and Summary
The said study can contribute tremendous improvements to air and light quality and visual
enhancement. The researchers coupled the green building with a rainwater cistern. The structure
is made up of reinforced concrete since we considered it as a conventional structural design.
Those innovations installed on the project infer as a green building and sustainable
development innovation. For the Natural light and air ventilation Natural light & ventilation the
researchers designed openings on the front and the back of the structure, there are airways or
breezeways located on the left and right wing of every floor, free – flowing light and air permeates
around the structure.
The cistern also will act as a reservoir for the whole building for sanitary purposes, but the
main challenge is filtering the water coming from the cistern making it potable for drinking to the
tenants of the building. The building will have an inverted gable roof for catchment of rainwater
leading to the pipes to the cistern.
77
Chapter 9
Recommendation
The project entitled “Proposed 4-storey Dormitory with Natural Light, Ventilation and
Rainwater Cistern” recommends to Architect Jun Chan a more intensive study regarding his plan
of building a green dormitory. This project would allow him to have a dormitory that offers
additional space for leisure activities. Also, the rainwater cistern design would help with the water
supply for the hotel.
The group recommends to City Officials in Quezon City to adopt the use of green building
designs even if they are located in rural areas to help in the prevention of further damage to the
environment.
The researchers also recommend to have further study on improving the quality of the
water collected through the rainwater cistern allowing it to be potable. If in case this project is
accepted, the group recommends value engineering to be done and considered for the project,
because the values and data obtained in this project were calculated using the standard procedure
in designing. Economic considerations are yet to be applied.
78
Chapter 10
Acknowledgements
This study would not have been possible without the guidance and the help of several
individuals who in one way or another contributed and extended their valuable assistance in the
preparation and completion of this study.
First and foremost, my utmost gratitude to Engr. Gary Alviento for his unselfish and
unfailing support as our adviser.
Engr. Arthur Casimiro for his steadfast encouragement to complete the study.
Architect Jun Chan, our beneficiary who helped us in our architectural plans and for sharing
valuable insights that can be added to our study.
The CE Faculty, for their untiring effort in encouraging us to pursue professional growth.
Likewise the staff of the Dean’s office for their relaying every communication.
Last but not the least, my family and the one above all of us, the omnipresent God, for
answering my prayers for giving us the strength to plod on despite my constitution wanting to give
up and throw in the towel, thank you so much Dear Lord.
79
Chapter 11
References
http://gbtech.emsd.gov.hk/english/utilize/natural.html
"Chapter 8 – Measurement of sunshine duration" (PDF). CIMO Guide. World
Meteorological Organization. Retrieved 2008-12-01.
http://www.google.com.ph/url?sa=t&rct=j&q=&esrc=s&source=web&cd=13&cad=rja
&ved=0CGoQFjAM&url=http%3A%2F%2Fwww.nltubular.com%2F&ei=7ufOUtT5BK
2XiAeL3IGIBw&usg=AFQjCNGmBjCAUcD32K62SS-
mPdQHASSrrg&sig2=qOxEz1g_ofApXUY7Vi-ssA&bvm=bv.59026428,d.aGc
http://www.greenbuilding.com/
http://www.ni.com/greenengineering/whatis.htm
http://www.unep.or.jp/ietc/publications/techpublications/techpub-8e/rainwater2.asp
http://www.google.com.ph/url?sa=t&rct=j&q=&esrc=s&source=web&cd=6&cad=rja
&ved=0CDwQFjAF&url=http%3A%2F%2Fwww.itnphil.org.ph%2Fdocs%2FHow%252
0to%2520construct%2520a%2520rainwater%2520harvesting%2520tank.pdf&ei=C-
rOUvGoBMj_iAe3moFQ&usg=AFQjCNGU4eYvzNngwrVQmMSwLMvfhcybxQ&sig2=u
T_YHDLGGQ9YIUghwAtBCw&bvm=bv.59026428,d.aGc
80
APPENDIX A
ARTICLE TYPE
81
4-STOREY DORMITORY WITH NATURAL LIGHT, VENTILATION AND
RAINWATER CISTERN
Jhamina Zarrah J. Almandus, John Matthew B. Icasiano, Rafaela A. Valenzuela
MAPUA INSTITUTE OF TECHNOLOGY
School of Civil, Environmental and Geological Engineering
(+63 2) 2475000 local 5109
SEPTEMBER 2014
82
Abstract
This project is to construct a dormitory with green feature, identifying proper placement of the
building site so that natural light and ventilation can be achieved on the structure. A rainwater
cistern installed at the side of the dormitory will be available to serve as a water source for sanitary
use.
One of the country’s top notching school, University of the Philippines (UP) in Diliman has a total
land area of 493 hectares (1,220 acres). Majority of the property has been utilized by the university
through building infrastructures and research facilities. Meanwhile, a remaining portion of the land
is forested, reserved for development and residential use or simply unoccupied.
Sustainable development can be divided into two categories; (1) social development and poverty
alleviation, and (2) natural resources and environment regeneration and protection.
With the continuous construction of various buildings within the vicinity, a proposed green
building/structure is the perfect solution to limited dormitory spaces of the university. Priority is
given to students from more distant homes and lower income bracket. The project will be located
within the UP campus. Adherence to the increasing awareness towards protecting the environment,
the structure will use natural ventilation and rainwater cistern. This way, the occupants will pay
less since electricity and water bills nowadays are very expensive.
83
1 Introduction
Civil Engineers believe that building structures are not limited for aesthetics. The
importance of satisfying standards which mostly conform to the economy and environment should
be considered in order to reach goals without sacrificing one from the other. The perfect concept
that can attest to this would be the technology behind green buildings. It has been around for
centuries which combines economic and environmental standards while providing aesthetics1.
The focus on optimizing system efficiency is where today’s climate of sustainable design
is headed. For instance, high occupancy buildings such as office and dormitory premises have
issues in their heating, cooling and air conditioning systems which are well known energy
consumers2. Energy efficiency measures are then proposed to reduce excess consumption.
Processes such as natural ventilation and cistern are key features that can help the industry in
building more refined building structures
1.1 Presenting the Challenges
The group believes that being efficient, economical and sustainable are the most relevant
norms to base the design and construction of the structures for this study.
Considering the design norm of being efficient, the group will focus on the capabilities and
competence of the materials. This will be used in the structure since cleaning and treating water
through series of filters will take lesser time and effort compared to other complex and expensive
treating processes. At the same time, the group will be economical since it will focus on the least
possible cost of materials needed in the design process. Finally, the design will be sustainable by
using the principle of natural light and ventilation with cistern.
______________________________________________________________________
1The Green (or Sustainable) Building: Part II – Aesthetics, Ambience and Synergy,
http://greeneconomypost.com/green-sustainable-building-2-2363.htm#ixzz3CFv9plQW 2Green Building – Building the Future with Intention, http://www.greenbuilding.com/
84
1.2 Environmental Examination Report
The environment is very significant to the world. It has a large impact that can influence
the natural resources as well as the weather conditions. Because of this impact the researchers
considered the environmental effect that may occur sooner or later in the project.
The project will be implemented at Emilio Jacinto Street corner C.P. Garcia, Quezon City,
Philippines.
This project is to be done in four phases: (1) Pre-construction/operational phase is the
preparation before starting the construction of the building, (2) construction phase is the actual
construction of the building, (3) operational phase discusses the works done within the
construction period of the building, and (4) abandonment phase is the final checking or assessment
of the building.
The project is resided in one of the main roads of Quezon City. Sunlight is strongly present
in the area. The site has establishments in front of it which makes it an ideal place to construct a
dormitory.
The environment is an open place. No existing structure on its vicinity so it is a good area
to incorporate natural lighting and ventilation.
The project location is a university community which means that the vicinity consists
mostly of students or employees in nearby establishments. The area is not that big and plenty of
establishments are located around it.
There will be a nominal effect on future environmental conditions without the project. It
will create job opportunities for the residents and will ease student’s adjustment to college life,
providing them with maximum opportunities to interact with their fellow students, and to put them
close to the school buildings and libraries.
85
Table 1. Summary Matrix of Proposed Mitigation and Enhancement Measures, Estimated
Cost and Responsibilities
Impacts Mitigation Responsibilities
Noise Transportation of
machineries to check
on noise & vibration
Contractor
Air Dust Control (Net
and water sprinklers
will be provided);
Mask for laborers;
Regular maintenance
of heavy equipment;
Distribute system of
Deliveries;
Contractor
Mass Population Guarantee safety of
the project to avoid
accidents to people
Contractor
The researchers considered the environmental effects of the project, as well as the
structural codes to be followed. Once it thus comply with the requirements of the
Engineering Office of the Quezon City Municipal, in the case of building an
establishment in the area.
86
2 Research Component
Green Engineering
Green engineering is the design, commercialization, and use of processes and
products, which are feasible and economical while minimizing3.
3. Generation of pollution at the source
4. Risk to human health and the environment
Green engineering embraces the concept that decisions to protect human health and
the environment can have the greatest impact and cost effectiveness when applied early to
the design and development phase of a process or product4.
Green Building
Green building is an approach towards a buildings’ design, construction and operation that
conserves resources while it protects human health. Green buildings use less energy,
consume fewer natural resources such as water and forest products, and omit pollutants
into the environment. Because they are designed to make use of natural light and good
ventilation, green buildings provide a healthier indoor environment for their occupants.
Studies show that students in green buildings learn better and workers in green buildings
are more productive5.
Natural Light and Ventilation
Natural ventilation is the process of supplying and removing air through an indoor
space without the use of a fan or other mechanical system. It uses outdoor air flow caused
by pressure differences between the building and its surrounding to provide ventilation and
space cooling6. Significant energy savings are also achieved through the use of natural
lighting and ventilation. The use of natural ventilation is definitely an advantage with the
raising concerns regarding the cost and environmental impact of energy use.
________________________________________________________________________
3 Green Engineering – Environmental Protection Agency,
http://www.epa.gov/oppt/greenengineering/pubs/whats_ge.html 4 Green Engineering – Environmental Protection Agency,
http://www.epa.gov/oppt/greenengineering/pubs/whats_ge.html 5 Building Survey: Help and Resources, http://dcsmarterbusiness.com/wp-
content/uploads/2013/02/Building-Survey-help-and-resources.pdf 6Natural Ventilation, http://gbtech.emsd.gov.hk/english/utilize/natural.html
87
Natural ventilation can reduce building construction and operation costs. At the
same time it can reduce the energy consumption for air-conditioning and circulating fans.
An additional bonus is that no noisy fan will be of your concern7.
Rainwater Cistern
Rainwater harvesting is the accumulation and deposition of rainwater for reuse
before it reaches the aquifer. Uses include water for garden, water for livestock, water
for irrigation, etc. In many places, the water collected is just redirected to a deep pit with
percolation. The harvested water can be used for drinking water. If the storage is a tank, that
can be accessed and cleaned when needed8.
Rainwater harvesting provides an independent water supply during regional water
restrictions and in developed countries is often used to supplement the main supply9.
Rainwater harvesting provides water when there is drought. Rainwater harvesting prevents
flooding of low lying areas. Rainwater harvesting replenishes the ground water table and
enables our dug wells and bore wells to yield in a sustained manner. It helps in the
availability of clean water by reducing the salinity and the presence of iron salts.
3 Methodology
Research for new possible innovation for building design.
Consultation of the beneficiary for the expectation and needs of the project.
Suggestion of possible green engineering features for the project.
Preparation of the architectural plans of the structure.
Application of the building codes and provisions with respect to NSCP 2010 manual.
Utilization of computer software/s to be used in designing the project.
________________________________________________________________________
7Natural Ventilation, http://gbtech.emsd.gov.hk/english/utilize/natural.html 8 Rainwater harvesting, http://en.wikipedia.org/wiki/Rainwater_harvesting 9 Rainwater harvesting, http://green.wikia.com/wiki/Rainwater_harvesting
88
Flow Chart
4
Results and Discussion
After comprehensive study on green buildings, the researchers found out that it can really
contribute remarkable improvements to air, light quality and visual enhancement. Coupling the
green building with rainwater cistern will increase the structures use and efficiency.
According to the study, green building is an approach to building design, construction and
operations that protects resources while it protects human health. Green buildings use less energy,
consume less natural resources and secrete less pollutants into the environment. Because they are
designed to make use of natural light and good ventilation, green buildings provide a healthier
indoor environment for their occupants. Studies show that green buildings are more conducive for
students to learn and workers in green buildings are more productive.
Additional for the green building is the rainwater cistern that will be used to store and filter
the rain water. It can be used for sanitary and drinking purposes.
GREEN ENGINEERING
Location AnalysisSustainability of
Green Engineering
STRUCTURAL DESIGN
Application of innovative design &
materialsCost Estimation
4 STOREY BUILDING
Innovative Construction
MaterialsMaterial Resources
89
5 Conclusion and Summary
The said study can contribute tremendous improvements to air and light quality and visual
enhancement. The researchers coupled the green building with a rainwater cistern. The structure
is made up of reinforced concrete since we considered it as a conventional structural design.
The structure is built up of reinforced concrete since we considered it as a conventional
structural design. The greatest challenge of our project is its location, Emilio Jacinto Street corner
C.P. Garcia, Quezon City because it stands in one of the busiest streets of Quezon City.
The cistern also will act as a reservoir for the whole building for sanitary purposes, but the
main challenge is filtering the water coming from the cistern making it potable for drinking to the
tenants of the building. The building will have an inverted gable roof for catchment of rainwater
leading to the pipes to the cistern.
6 Recommendation
The group recommends to City Officials in Quezon City to adopt the use of green building
designs even if they are located in rural areas to help in the prevention of further damage to the
environment.
The researchers also recommend to have further study on improving the quality of the
water collected through the rainwater cistern allowing it to be potable. If in case this project is
accepted, the group recommends value engineering to be done and considered for the project,
because the values and data obtained in this project were calculated using the standard procedure
in designing. Economic considerations are yet to be applied.
90
7 Acknowledgements
This study would not have been possible without the guidance and the help of several
individuals who in one way or another contributed and extended their valuable assistance in the
preparation and completion of this study.
First and foremost, my utmost gratitude to Engr. Gary Alviento for his unselfish and
unfailing support as our adviser.
Engr. Arthur Casimiro for his steadfast encouragement to complete the study.
Architect Jun Chan, our beneficiary who helped us in our architectural plans and for sharing
valuable insights that can be added to our study.
The CE Faculty, for their untiring effort in encouraging us to pursue professional growth.
Likewise the staff of the Dean’s office for their relaying every communication.
Last but not the least, my family and the one above all of us, the omnipresent God, for
answering my prayers for giving us the strength to plod on despite my constitution wanting to give
up and throw in the towel, thank you so much Dear Lord.
91
APPENDIX B
PANEL ASSESSMENT
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
APPENDIX C ENGLISH ASSESSMENT AND
EVALUATION RUBRIC
117
118
119
APPENDIX D
ACCOMPLISHED CONSULTATION
FORMS
120
121
122
123
APPENDIX E
COMPILATION OF ASSESSMENT
FORMS
124
125
126
127
128
129
130
131
132
133
134
APPENDIX F
DRAWINGS AND PLANS
135
Foundation Plan
136
2n Floor Framing Plan
137
3rd Floor Framing Plan
138
4th Floor Framing Plan
139
Roof Framing Plan
140
Roof Beam Framing Plan
141
Ground Floor Plumbing Plan
142
2nd Floor Plumbing Plan
143
3rd Floor Pluming Plan
144
4th Floor Plumbing Plan
145
Cistern Ladder Rung Detail
146
Cistern Slab Detail
147
Cistern Slab Detail
148
Manhole Cover Detail
149
Septic Tank Plan
150
Septic Plan Detial
151
APPENDIX G
SOIL REPORT
152
153
154
155
156
157
158
159
160
161
APPENDIX H
PROJECT POSTER
162
163
APPENDIX I
PHOTOCOPY OF RECEIPTS
164
165
APPENDIX J
OTHER REQUIRED FORMS
166
167
168
169
170
171
172
173
174
APPENDIX K
STUDENT REFLECTIONS
175
176
177
178
179
180
181