17 April 2013 Present by: TRAN THI MINH THU RAO II BRIDGE AND THE BIM STORY IN MTHOJGAARD VN mth.com

description

 

Transcript of 4 - MT H_jgaard_13thApr2013_TTm

17 April 2013

Present by: TRAN THI MINH THU

RAO II BRIDGE AND THE BIM STORY IN MTHOJGAARD VN

mth.com

Contents

I. Introduce MT Højgaard

II. Rao II bridge – Engineering and construction

III. Tekla structures - BIM story in MTH Vietnam

IV. Stratergy

17 April 2013 2

I) Introduce MT Højgaard

17 April 2013 3

Design, construction and refurbishment

of plants, bridges, housing and

commercial and industrial buildings

4,700 employees

Headquartered in Denmark

Focused international activities

30% of our revenue comes from international activities such as:

17 April 2013 4

Set-up of mine, Fiskefjorden, Greenland

Shopping centre, Nuuk Centre, Greenland

Tunnel, Eidi 2, The Faroe Islands

School, Mid Yell, Shetland

Hydro power plant, Changuinoula, Panama

Foundations for offshore wind farm, Lincs, England

Water intake, Qatar

Commercial and fishing port, Oluvil Port, Sri Lanka

Bridge, RAOII, Vietnam

Bridge, Södertälje, Sweden

April 17, 2013 5

MT Højgaard Vietnam is established in

2007

Part of Design & Engineering

Technical support for all departments

External Design

I) Introduce MT Højgaard

MT Højgaard Vietnam Co., Ltd.

April 17, 2013 6

Workshop Drawings

Construction Drawings

Material Take Out

BIM for:

• 3D, 4D visualizations

• Constructability Checks

• Model on mobile devices

II) Rao II bridge – Engineering and construction

17 April 2013 7

One pylon cable-stayed bridge

Constant steel and concrete girder structure

Length: 248 m

Finish: Dec. 2012

II) Rao II bridge – Engineering and construction

17 April 2013 8

+) Requests:

Workshop drawings

• Steel structures

• Secondary steels

Working drawings

• Reinforced concrete structures

Erection sequences

Nesting drawings

3D model for inspections

+) Solutions:

Using Tekla structures for both steel and concrete structures

Export information to .nc files for nesting

II) Rao II bridge – Engineering and construction

17 April 2013 9

Tekla model

II) Rao II bridge – Engineering and construction

17 April 2013 10

Tekla model

II) Rao II bridge – Engineering and construction

17 April 2013 11

Tekla model

II) Rao II bridge – Engineering and construction

17 April 2013 12

On site

II) Rao II bridge – Engineering and construction

17 April 2013 13

On site

II) Rao II bridge – Engineering and construction

17 April 2013 14

On site

II) Rao II bridge – Engineering and construction

17 April 2013 15

+) Additional benefits:

Check geometry of cables

Preview collisions

Purchase accurate amount of material

• Using nesting drawings

• Bar bending schedule

+) Challenges:

Bridge’s pre-camber

4D model

Inspection

III) Tekla structures - BIM story in MTH Vietnam

17 April 2013 16

+) BIM process – the fact:

“Nothing says more than a building information model”

We are only on the way heading toward it

3D modeling solution is the only choice

+) Purpose:

Consistent model input and output

More automatically

Support other departments during constructions: design and engineering,

manufacturer, inspectors, etc.

Better communication

III) Tekla structures - BIM story in MTH Vietnam

17 April 2013 17

+) Firm folder setting

Minimize inconsistent input

Easy for filtering

No numbering error

Easy control project

+) Custom component

More automatically

Speed up QA

+) Tekla Open API

Applying available shared extensions on Tekla extranet

Built some small macros and applications

17 April 2013 18

Template administrator

Engineer 1

Firm folder

Project folder

Engineer 2 Engineer 3...

Server

Firm folder setting

Input Output

17 April 2013 19

Server Firm folder

Model template

Reports

Drawings

Client 2

Client 3

Client 1

Assembly list

MTO

Part list

Surface treatments…

Single part

Assembly

GA

Cast-in drawing…

Same properties

Layer (color)

Text, dimension…

Printing (Same paper size, line thickness…)

Scale….

Same info as per company template

Using 1 server

All computer have same setup for Firm folder

Template guideline

Firm folder setting

17 April 2013 20

Firm folder setting

III) Tekla structures - BIM story in MTH Vietnam

17 April 2013 21

Custom components

• Built up custom components for typical

structures/details

• Using extension Custom coponent Dialog

editor

17 April 2013 22 GCC project

17 April 2013

Presentation by: BNV

23

Step 5 Use tool ”Custom Component Dialog Editor” extension on

the extranet to edit interface of custom component.

III.2 How we create custom components?

17 April 2013 24

17 April 2013 25

Any questions?

17 April 2013 26