BOUG VI SAP BusinessObjects 4 1 Nowa Wersja Platformy Raportowej
3RX Feasibility study alternative Rhein – Ruhr Rail Connection and … · 2019-11-26 · 21 Way...
Transcript of 3RX Feasibility study alternative Rhein – Ruhr Rail Connection and … · 2019-11-26 · 21 Way...
3RX Feasibility study alternative Rhein – Ruhr Rail Connection and State of Play trilateral discussions Brussels, 25/11/2019
Willem Vuylsteke
Flemish Ministry of Mobility and Public Works
2
3RX?• 3RX connects Antwerp (Belgium) with Mönchengladbach (Germany),
via Lier and Mol (Belgium), Weert, Roermond, Venlo (The
Netherlands) and Viersen (Germany).
– As the section Antwerp – Lier is common with the Montzen route,
the study has concentrated on the section between Lier and
Mönchengladbach.
• An alternative for revitalisation of the historical Iron Rhine route
and for the previously studied A52 route,
3
3RX?• Makes as much as possible use of existing rail infrastructure.
• The study compares the 3RX with the two alternatives (historical
Iron Rhine, A52 route).
• Concept was developed to expand capacity of the East-West rail
routes between the Flemish and Dutch North Sea Ports and
Germany, thereby supporting a modal shift policy towards rail....
• The 3RX could relieve existing routes, but also provide an
alternative route in case one of the other East-West rail routes
would be temporarily unavailable (e.g. accident on Montzen route in
2013).
4
3RX?• Commissioned by the Flemish Government and co-financed by the
European Union (CEF Transport programme).
• A five party steering committee to oversee the study
(representatives from the Netherlands, Germany, Belgium,
Nordrhein-Westfalen and Flanders)
• Carried out by AR-T-ECO-RAIL and with support of the rail
infrastructure managers
– Consortium of consultancy companies from all three countries
involved (Arcadis, TML, Ecorys en Railistics)
• Duration: 2015-2017
• All results publicly available on
http://departement-mow.vlaanderen.be/nl/press-release/opnieuw-
perspectief-voor-ijzeren-rijn
5
Assumptions• Design capacity of 72 trains per day (both ways)
• Full electrification
• State of the art safety systems (ERTMS).
• Curves are assumed to avoid the necessity of a change of direction
of the train. From a commercial point of view the route is only
attractive if rail traffic can run East-West with at maximum one
stop for changing direction of the train.
• Mitigating measures
6
7
8
Necessary measures• Belgium/Flanders
– Electrification Mol - Hamont – border BE/NL (in construction)
– Track doubling Mol – border BE/NL (in study)
• Netherlands
– Electrification border BE/NL – Weert
– Measures Budel - Weert (bird directive) connection with Weert
– Curve at Roermond
– Track doubling Roermond-Venlo
– Yard Venlo
– ERTMS
• Germany
– Track doubling Kaldenkirchen – Dülken
– Curve Viersen
9
Costs• Cheapest solution is estimated at € 770 million (prices 2015,
including risk provision, excluding vat; uncertainty margin: + or -
30%).
10
Costs• Taking into account the commitments already made by Belgium
and Germany, an additional investment commitment of €590
million (excluding vat) would be required.
– Belgium: section Mol– Neerpelt – Hamont/Dutch border
(electrification) (€46,3 mln)
– Germany: section Dutch/German border - Kaldenkirchen –
Dülken, section Viersen (€133,4 mln)
– The Netherlands: interested in developing passenger transport on
the two border sections (Weert – Hamont - Antwerp; Eindhoven –
Venlo – Düsseldorf).
11
Costs• The investment cost of 3RX is substantially cheaper than either the
revitalisation of the historical route, or the construction of the A52
alternative.
– Investment cost reactivation historical route = updating existing
study
– Investment cost A52 route has not been analyzed in detail,
estimates are between 0.9 and 1.7 billion
12
Expected freight traffic on 3RX• Expected average daily use is 17 to 20 trains in 2030, increasing to
19 to 23 trains in 2040
– Increased use if curve at Venlo is constructed
• 3RX relieves Montzen route
• 3RX would also relieve the Brabant route, the Aachen marshalling
yard and the Aachen-Düren-Köln route
13
Benefits of 3RX• Presently the Montzen route is the predominant route for rail
freight transport between the Flemish seaports and the German
hinterland. However, this route has several limitations.
– longer transport distance and time as 3RX
– inclinations and the need to change direction at Aachen for
southbound trains: negative impact on time and costs.
• Not the case for 3RX!
• 3RX is a substitute for Montzen route and can also relieve Brabant
route.
– The current alternative Brabant-, Betuwe- and Athus-Meuse
routes all imply much longer travel distances, as well as the need
for trains to change direction at least once. Moreover, the
capacity of these routes to cope with additional rail freight is
limited.
14
Benefits of 3RX• BASF: “In comparison to Montzen-Route, the number of trains
required for the same transport volume on the 3 RX-Route would
be reduced by 25% same transport volume does require 25% less
trains. Which does represent a significant reduction of total costs,
energy consumption and noise emissions.”
15
Benefits of 3RX• Benefits of passenger transport were not taken into account in the
study and would increase the benefits of 3RX
• Strategic importance of 3RX (chemical cluster – security of supply
of Ruhr area – logistics hotspots in Limburg)
• Alternative to Montzen route in the event of calamities: of great
importance for operational reliability of the network.
16
Necessity of new East-West railconnection
• The Antwerp port authority expects that freight traffic flows
between the port and its German hinterland will continue to rise
from currently around 68 million tonnes yearly up to 90 million
tonnes in 2030
• Ambitious modal shift goals of port of Antwerp
17
Way forward: political process• Several political contacts in 2018 between the five governments
involved.
• Installation of a trilateral international working group on the
follow-up of the 3RX study.
– On invitation of German Minister Scheuer and State Secretary
Ferlemann.
– DE (BMVI), NRW, BE, VL, NL, Dutch regional delegation (province
of Limburg + city of Venlo)
– Kick-off meeting in December 2018, second meeting in July 2019.
– So far mainly discussions on the mandate/ToR of this working
group.
18
Way forward: political process
• For 2020 focus of international working group expected on
– improving the SCBA
– impacts on livability and environment
– financing strategy
Need for win-win-win situation > synergies with passenger
transport
19
Way forward: financing
• 3RX study (2015-2017) learnt that financing will most probably have
to come from public sources.
• In our view conclusion of political consensus (including financing)
should be settled in a State Treaty between the Member States
concerned (with a MoU as a possible intermediate step).
20
Way forward: financing• Making optimal use of available EU financing opportunities under
CEF Transport
– Quick win, CEF call 2019 on cross-border sections.
• Belgium successfully submitted a study proposal on doubling tracks
online 19 between Balen and Neerpelt.
• The Netherlands successfully submitted a study proposal on
removing bottlenecks on the section Venlo – Kaldenkirchen.
– As of 2021, access to new funds under CEF 2.
• The section Antwerp – Duisburg is a pre-identified cross-border link
on the comprehensive network. This increases chances for EU co-
financing for 3RX.
21
Way forward: procedures• Finding a political consensus is now a priority.
• Various legal steps need to be taken and various in-depth studies
will be required: estimated time differs by country, but could take
up to 10 years.
• The construction works would additionally take 7 to 13 years.