3.Pmp Integration v1.2

42
STEVBROS Global PMI R.E.P Chapter 3: Project Integration Management Stevbros Training and Consultancy Copyright@STEVBROS 1 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc.

description

PMP Integration

Transcript of 3.Pmp Integration v1.2

Page 1: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Chapter  3:   Project  Integration  Management

Stevbros  Training  and  Consultancy

Copyright@STEVBROS1

PMI,  PMP  and  PMBOK  are  registered  marks  of  the  Project  Management  Institute,  Inc.

Page 2: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

The  key  role• The   key   role   of   the   project   manager   is   to  perform  integration  

• The   key   role   of   the   project   team   is   to  concentrate   on   completing   the   project  activities  

• The   key   role   of   the   project   sponsor   is   to  protect   the   project   team   from   unnecessary  changes  and  loss  of  resources

Copyright@STEVBROS2

Page 3: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

The  key  role• The  project  expediter  works  as  staff  assistant  and   communications   coordinator.   The  expediter   cannot   personally  make  or   enforce  decisions.    

• The  project  coordinators  have  power  to  make  some   decisions,   have   some   authority,   and  report  to  a  higher-­‐level  manager.  

Copyright@STEVBROS3

Page 4: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Project  selection  methods

• Discounted  cash  flow  • Net  Present  Value  (NPV)  • Internal  Rate  of  Return  (IRR)  • Payback  Period    • Benefit  Cost  Ratio  (BCR)  • Return  on  Investment  (ROI)

Copyright@STEVBROS4

Page 5: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Discounted  cash  flow

• Present  Value  (PV):  means  value  today  of  future  cash  flows:  

  PV  =  FV/(1  +  i)n    – PV  -­‐  Present  Value  to  be  calculated  – FV  -­‐  Expected  Future  Cash  inflow  – i  -­‐  Notional  Interest  or  Expected  Rate  of  Interest

Copyright@STEVBROS5

Page 6: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Net  Present  Value• Net  Present  Value  (NPV):  present  value  of  the  total  benefits  (income  or  revenue)  less  the  costs  over  time  period:  

NPV  =  PV1  +  PV2+  PV3  ..  +  PVn  -­‐  Invested  Amount  

Copyright@STEVBROS6

Page 7: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Net  Present  Value• Example:  Invested  Amount  :  $500,000  Income  Expected  (Future  Value)-­‐  1  Year  :  $200,000  Income  Expected  (Future  Value)-­‐  2  Year  :  $300,000  Income  Expected  (Future  Value)-­‐  3  Year  :  $100,000  Rate  of  Interest  :  5%  per  year.  Now  calculate  the  PV  for  every  year:  

  Year   Future  Value   Calculation     PV     1   $200,000   200,000/(1  +  0.05)   190,476.2     2   $300,000   300,000/(1  +  0.05)2   272,108.84   3   $100,000   100,000/(1  +  0.05)3   86,383.76  

NPV  for  the  project  =  Total  PV  -­‐  Original  Investment  =  $548,968.8  -­‐  $500,000    =>  So  the  final  NPV  is  48,968.8.

Copyright@STEVBROS7

Page 8: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Internal  Rate  of  Return  

• Internal  Rate  of  Return  (IRR):  is  the  rate  of  discounting  at  which  the  PV  of  costs  match  the  PV  of  benefits.    

• In  other  words,  it  is  the  rate  of  return  internal  to  the  project  and  it  is  the  interest  rate  that  makes  the  NPV  zero.    

• The  company  should  accept  projects  where  IRR  is  greater  than  interest  rate  and  should  reject  projects  where  IRR  is  less  than  interest  rate.

Copyright@STEVBROS8

Page 9: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Internal  Rate  of  Return  

• Example:    Invest  $2,000  now,  receive  3  yearly  payments  of  $100  each,  plus  $2,500  in  the  3rd  year.  What  is  IRR?  

Let  us  try  10%  interest:     Now:  PV  =  -­‐$2,000     Year  1:  PV  =  $100  /  1.10  =  $90.91     Year  2:  PV  =  $100  /  1.102  =  $82.64     Year  3:  PV  =  $100  /  1.103    +  $2,500  /  1.103    =  $75.13  +  $1,878.29     NPV  =  -­‐$2,000  +  $90.91  +  $82.64  +  $75.13  +  $1,878.29  =  $126.97  I  will  take  a  better  guess  now,  and  try  a  12%  interest  rate.

Copyright@STEVBROS9

Page 10: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Internal  Rate  of  Return  

• Try  12%  interest  rate     Now:  PV  =  -­‐$2,000     Year  1:  PV  =  $100  /  1.12  =  $89.29     Year  2:  PV  =  $100  /  1.122  =  $79.72     Year  3:  PV  =  $100  /  1.123  +  $2,500  /  1.123  =  $71.18  +  $1,779.45     NPV  =  -­‐$2,000  +  $89.29  +  $79.72  +  $71.18  +  $1,779.45  =  $19.64  

• Try  12.4%  interest  rate     Now:  PV  =  -­‐$2,000     Year  1:  PV  =  $100  /  1.124  =  $88.97     Year  2:  PV  =  $100  /  1.1242  =  $79.15     Year  3:  PV  =  $100  /  1.1243    +  $2,500  /  1.1243  =  $70.42  +  $1,760.52     NPV  =  -­‐$2,000  +  $88.97  +  $79.15  +  $70.42  +  $1,760.52  =  -­‐$0.94

Copyright@STEVBROS10

Page 11: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Internal  Rate  of  Return  

That  is  good  enough!  Let  us  stop  there  and  say  the  Internal  Rate  of  Return  is  12.4%.In  a  way  it  is  saying  "this  investment  would  earn  12.4%"  (assuming  it  all  goes  according  to  plan!).

Copyright@STEVBROS11

Page 12: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

NPV,  IRR  questionsin  PMP  exam

• Q:  You  have  two  projects  to  choose  from.  Project  X  will  take  2  years  to  complete  and  has  a  NPV  of  $35,000.  Project  Y  will  take  5  years  to  complete  and  has  an  NPV  of  $95,000.  Which  one  will  you  take  up?  

A:  Project  Y,  because  it  has  a  higher  NPV.  Don’t  get  confused  with  the  longer  duration  of  the  project.  What  is  important  is  that  the  NPV  should  be  greater.  

• Q:  If  you  have  to  choose  between  Project  A  with  an  IRR  of  25%  or  Project  B  with  an  IRR  of  %15.  Which  one  will  you  take  up?  

 A:  Project  A.  Reason:  the  IRR  of  Project  A  is  greater  than  the  one  for  Project  B.

Copyright@STEVBROS12

Page 13: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Payback  period• Payback  period:  the  number  of  time  periods  it  takes  to  recover  your  investment  in  the  project  before  your  start  accumulating  profits.  

Q:  You  have  2  projects  to  choose  from.  Project  A  with  payback  period  of  5  months  or  Project  B  with  a  payback  period  of  12  months.  Which  one  would  you  go  for?  A:  Project  A.

Copyright@STEVBROS13

Page 14: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Benefit  Cost  Ratio  

• Benefit  Cost  Ratio  (BCR):  the  benefit  cost  ratio  compares  the  present  value  of  benefits  to  the  present  value  of  costs  (benefit/cost).  A  BCR  of  more  than  1  means  that  the  benefits  are  greater  than  the  cost.  

Q:  if  the  BCR  of  Project  A  is  2.5  and  BCR  of  Project  B  is  1.5,  which  project  would  you  select?  A:  The  answer  is  Project  A

Copyright@STEVBROS14

Page 15: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Return  on  Investment  

• Return  on  Investment  (ROI):  is  the  rate  of  return  on  the  project  normalized  by  the  initial  investment.    

Example:  if  a  project  involves  an  initial  investment  of  $100,000  and  on  average  it  results  in  benefits  of  $20,000  per  year,  the  ROI  is  20,000/100,000  =  20%

Copyright@STEVBROS15

Page 16: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Project  selection  methods

• Net  present  value:  (NPV)  –  select  greatest  one  

• Internal  Rate  of  Return:  (IRR)  –  select  highest  one  

• Payback  period:    – select  shortest  one  

• Benefit-­‐Cost  ratio:  (BCR)    – select  higher  one

Copyright@STEVBROS16

Page 17: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P17

• Opportunity  Cost:  refers  to  the  opportunity  given  up  by  selecting  one  project  over  another  

Question:   you   have   2   projects   to   choose   from:  project  A  with  NPV  of  45,000  or  project  B  with  an  NPV   of   $85,000.  What   is   the   opportunity   cost   of  selecting  project  B?    Answer:  $45,000

Terms

Copyright@STEVBROS

Page 18: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P18

• Sunk  Costs:  are  expended  costs.  Be  aware  of  that  accounting  standards  say  that  sunk  costs  should  NOT  be  considered  when  deciding  whether  to  continue  with  a  troubled  project.  

Question:  you  have  a  project  with  an  initial  budget  of  $1,000,000.  You  are  halfway  through  the  project  and   have   spent   $2,000,000.   Do   you   consider   the  $1,000,000   over   budget   when   determining  whether  to  continue  with  the  project?    Answer:  No.  the  money  spent  is  gone.

Terms

Copyright@STEVBROS

Page 19: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P19

• Depreciation:  Equipment  purchased  by  a  company  lose  value  over  time.  Accounting  standards  call  this  depreciation.  – Straight   Line   Depreciation:   the   same   amount   of  depreciation  is  taken  each  year:  

  E.g:  A  $1,000  item  with  a  10-­‐year  useful  life  and  no  salvage   value   (how   much   the   item   is   worth   at   the  end  of  its  life)  would  be  depreciated  at  $100  per  year.  

– Accelerated  Depreciation:       E.g.  A  $1,000  item  with  a  10-­‐year  useful  life  and  no  salvage   value   (how   much   the   item   is   worth   at   the  end  of  its  life)  would  be  depreciated  at  $180  the  first  year,  $150  the  second,  $130  the  next,  etc.

Terms

Copyright@STEVBROS

Page 20: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Processes   Initiating  process  group

Planning  process  group

Executing  process  group

Monitoring  &  controlling  process  group

Closing  process  group

• Develop  project  charter

• Develop  project  management  plan  

• Direct  and  Manage  Project  Execution

• Monitor  and  Control  Project  Work  

• Perform  Integrated  Change  Control

• Close  Project  or  Phase

Copyright@STEVBROS20

Page 21: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Develop  charter• The   process   of   developing   a   document   that  formally   authorizes   a   project   or   a   phase   and  documenting   initial   requirements   that   satisfy  the  stakeholder's  needs  and  expectations.

Copyright@STEVBROS21

(A   Guide   to   the   Project   Management   Body   of   Knowledge,   Fifth   Edition   (PMBOK®   Guide)   ©2013   Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐2  Page  66.)

Page 22: 3.Pmp Integration v1.2

Important  ITTOs

• Facilitation  techniques  • Project  charter

22

Page 23: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Facilitation    techniques

• Brainstorming,   conflict   resolution,   problem  solving,   and   meeting   management   are   key  techniques   used   by   facilitators   to   help   teams  and   individuals   achieve   agreement   to  accomplish  project  activities.  

Copyright@STEVBROS23

Page 24: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Project  charter•It  comprises  of:  

Project  purpose  or  justification,  Measurable  project  objectives  and  related  success  criteria,  High-­‐level   requirements,   level   project   description   and  boundaries  Assumptions  and  constraints,    High-­‐level  risks,  Summary  milestone,  schedule,  budget,  Project   approval   requirements   (i.e.,   what   constitutes   project  success,  who  decides  the  project   is  successful,  and  who  signs  off  on  the  project),  Assigned   project  manager,   responsibility,   and   authority   level,  and  Name  and  authority  of  the  sponsor.

Copyright@STEVBROS24

Page 25: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Develop  project  management  plan

• The   process   of   documenting   the   actions  necessary  to  define,  prepare,  integrate,  and  co-­‐ordinate  all  subsidiary  plans  and  baselines.  

Copyright@STEVBROS25

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐3  Page  72.

Page 26: 3.Pmp Integration v1.2

Important  ITTOs

• Facilitation  techniques  • Projectmanagement  plan

26

Page 27: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Facilitation    techniques

• Brainstorming,   conflict   resolution,   problem  solving,   and   meeting   management   are   key  techniques   used   by   facilitators   to   help   teams  and   individuals   achieve   agreement   to  accomplish  project  activities.  

Copyright@STEVBROS27

Page 28: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Project  management    plan

Copyright@STEVBROS28

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Table  4-­‐1  Page  78.

Page 29: 3.Pmp Integration v1.2

Project  management  plan

• Project  management  plan  comprises  of:  Project  baseline:    • scope  baseline,    • schedule  baseline,  and    • cost  baseline  

Subsidiary  management  plan  (next  slide)

29

Page 30: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Project  management    plan

No. Subsidiary  management  plan Knowledge  area1 Requirement  management  plan Scope2 Scope  management  plan3 Schedule  management  plan Time4 Cost  management  plan Cost5 Quality  management  plan Quality6 Process  improvement  plan7 Human  resource  management  plan HR8 Communications  management  plan Communications9 Procurement  management  plan Procurement10 Stakeholder  management  plan Stakeholder11 Risk  management  plan Risk12 Change  management  plan Integration13 Configuration  management  planCopyright@STEVBROS

30

Page 31: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Direct  and  manage  project  execution

• The   process   of   leading   and   performing   the  work  defined   in  the  project  management  plan  and   implementing   approved   changes   to  achieve  the  project’s  objectives.

Copyright@STEVBROS31

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐6  Page  79.

Page 32: 3.Pmp Integration v1.2

Important  ITTOs

• Project  management  information  system  (PMIS)  

• Deliverables

32

Page 33: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

PMIS

• PMIS  is  part  of  the  environmental  factors.  • PMIS  provides  access  to  tools,  such  as  a  scheduling  tool,  a  work  authorization  system,  a  configuration  management  system,  an  information  collection  and  distribution  system,  or  interfaces  to  other  online  automated  systems.  

• Automated  gathering  and  reporting  on  key  performance  indicators  (KPI)  can  be  part  of  this  system.  

Copyright@STEVBROS33

Page 34: 3.Pmp Integration v1.2

Deliverables

• A  deliverable  is  any  unique  and  verifiable  product,  result  or  capability  to  perform  a  service  that  is  required  to  be  produced  to  complete  a  process,  phase,  or  project.  

• Deliverables  are  typically  tangible  components  completed  to  meet  the  project  objectives  and  can  include  elements  of  the  project  management  plan.  

34

Page 35: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Monitor  and  control   project  work

• The   process   of   tracking,   reviewing,   and  report ing   the   progress   to   meet   the  performance  objectives  defined   in   the  project  management  plan.

Copyright@STEVBROS35

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐8  Page  86.

Page 36: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Perform  integrated  change  control

• The   process   of   reviewing   all   change   requests;  approving  changes  and  managing  changes.

Copyright@STEVBROS36

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐10  Page  94.

Page 37: 3.Pmp Integration v1.2

Important  ITTOs

• Change  requests  • Change  log

37

Page 38: 3.Pmp Integration v1.2

Change  management

• Step  1:  submit  change  request  • Step  2:  PM  consider  to  accept  or  reject  or  transfer  to  Change  Control  Board  (CCB)  for  further  review  

• Step  3:  CCB  is  responsible  for  meeting  and  reviewing  the  change  requests  and  approving,  rejecting,  or  other  disposition  of  those  changes.

38

Page 39: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Change  request

Copyright@STEVBROS39

Page 40: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Change  log

Copyright@STEVBROS40

Page 41: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Close  project or  phase

• The  process  of  finalizing  all  activities  across  all  of  the  Project  Management  Process  Groups  to  formally  complete  the  project  or  phase.

Copyright@STEVBROS41

A  Guide  to  the  Project  Management  Body  of  Knowledge,  Fifth  Edition  (PMBOK®  Guide)  ©2013  Project  Management  Institute,  Inc.    All  Rights  Reserved.    Figure  4-­‐12  Page  100.

Page 42: 3.Pmp Integration v1.2

STEVBROS  -­‐  Global  PMI  R.E.P

Summary• The  key  role  of  the  project  manager,  project  team,  project  sponsor,  project  coordinator  and  project  expediter  

• Project  selection  methods:  NPV,  IRR,  PP,  ROI  • Term:  opportunity  cost,  sunk  cost,  depreciation.  • Key  outputs  in  this  knowledge  area:  charter,  PM  plan,  deliverables,  approved  CR.

Copyright@STEVBROS42