3D DESIGN FOR MACHINE CONTROL GRADING A Case Study of ODOT's I-5: Willamette River Bridge Project...
-
Upload
maurice-franklin -
Category
Documents
-
view
212 -
download
0
Transcript of 3D DESIGN FOR MACHINE CONTROL GRADING A Case Study of ODOT's I-5: Willamette River Bridge Project...
3D DESIGN FOR 3D DESIGN FOR MACHINE CONTROL MACHINE CONTROL
GRADINGGRADINGA Case Study of ODOT's
I-5: Willamette River Bridge ProjectEugene/Springfield, Oregon
Tom Metcalf, PE– OBEC Consulting Engineers in Eugene,
Oregon– 13 years of roadway engineering
experience– Lead Roadway Engineer on the I-5:
Willamette River Bridge Project– Phone: 541-683-6090– Email: [email protected]
PRESENTATION BY:PRESENTATION BY:
CASE STUDY BACKGROUNDCASE STUDY BACKGROUND
ODOT I-5: Willamette River Bridge Project– $150M bridge replacement project in Eugene,
Oregon
Twin 1900-foot-
long I-5 Bridges
Twin 1900-foot-
long I-5 Bridges
2500 feet of I-5
Roadway Work
2500 feet of I-5
Roadway Work
2300 feet of I-5
Roadway and Ramp Reconstruc
tion
2300 feet of I-5
Roadway and Ramp Reconstruc
tion
How did machine control grading get incorporated into the I-5: Willamette River Bridge project?– Project is an alternative delivery project
where the prime contractor(Hamilton) participates in the design
– K&E Excavating requested machine control grading to be utilized because of cost savings
CASE STUDY BACKGROUNDCASE STUDY BACKGROUND
ODOT utilizes a 3D design software program called InRoads to model proposed surfaces– Past version of InRoads were not as powerful
What is 3D Design?What is 3D Design?
Note the
"tethered
modem"!
Initiating
Redesign!
Initiating
Redesign!
ODOT utilizes a 3D design software program called InRoads to model proposed surfaces– Past version of InRoads were not as powerful
What is 3D Design?What is 3D Design?
Old industry standard – Minimized design effort (save design time and design expenditures) by providing just enough design data for field staff to "fill in the gaps"New industry standard due to machine control grading – Increased design effort to eliminate all gaps in 3D design to minimize "field modifications" during construction
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
Used to do "close enough" 3D modeling–Why?
Remember – Past industry practice was to minimize design effort (save design time and design $$$) by providing just enough design data for field staff to "fill in the gaps"
– Examples?
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
BEWARE: TECHNICAL CONTENT AHEAD!!!!!!
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
Old = Large gaps between template dropsNew = Smaller gaps
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
• Modeling around bridges, abutments and wingwalls
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
Guardrail benches, sideslope transitions and structure section transitions
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
Some modeling was accidentally overlooked, such as drainage features
How Machine Control Grading How Machine Control Grading Changes 3D DesignChanges 3D Design
• Need experienced field staff to interpret design for "field fitting" gaps in the design
• Quantity overages since modeling is not accurately reflecting final field conditions
• Change orders for "filling in" the gaps in the design
Effects of Past 3D Design on Effects of Past 3D Design on Construction ProjectsConstruction Projects
• MORE RISK TO CONTRACTORS = MORE RISK BUILT INTO PROJECT BIDS = MORE EXPENSIVE PROJECTS FOR ODOT
• Greatly reduces field interpretation of design• More accurate quantities• LESS RISK TO CONTRACTORS = LESS
RISK BUILT INTO PROJECT BIDS = LESS EXPENSIVE PROJECTS FOR ODOT
• This is a proven concept. For a number of years, contractors have been requiring and paying for this level of modeling effort from designers on design-build projects.
Results of New 3D Modeling Results of New 3D Modeling PracticesPracticeson Construction Projectson Construction Projects
• Design $$$ < Construction $$$
• Must decide at the beginning of a project to do more detailed modeling– Difficult and time-consuming to upgrade
a design not tailored for machine control grading
• Introduces need for QA review of modeling– This results in substantially more design
time and design dollars
Impacts of New 3D DesignImpacts of New 3D Designon Engineering Effortson Engineering Efforts
• How does the 3D design get to the construction equipment?
• Contractors don't use InRoads….they all have different proprietary software
• Have to convert design models to Proprietary software models for machines to "read"
• Designer must QC proprietary software models before work begins
• Increases design time and design expenditures
Impacts of New 3D DesignImpacts of New 3D Designon Engineering Effortson Engineering Efforts
Can utilize this concept for other design disciplines, such as traffic control plans
– Converting 2D traffic control plans to 3D staging design
Impacts of New 3D DesignImpacts of New 3D Designon Engineering Effortson Engineering Efforts
• ODOT's current design software is InRoads XM, and it is more than capable of generating the 3D designs required for machine control grading. This is not a futuristic concept. It has been utilized on a number of past and current projects.
• 3D designs require more design time and design budget.
• Embrace change = Better product = Reduced construction cost to ODOT
CONCLUSIONCONCLUSION
Tom Metcalf, PE– OBEC Consulting Engineers – Phone: 541-683-6090– Email: [email protected]
QUESTIONSQUESTIONS