Definition• The temporary timbers supporting the soil at the

side of an excavation.

Any heavy wood beam used for shoring or bracing.

A generic term for unconsolidated natural surface material above bedrock.

The removal of earth, usually to allow the construction of a foundation or basement.

Page 3: 3.3.1 planking strutting

What is planking??

(Apa itu planking??

?)

Material used for flooring,

decking, or scaffolding.

The temporary timber

s supporting the soil at the

side of an excavation.

A piece of lumber two or more inches thick and

six or more inches wide.

Designed to be laid flat as part of a

load-bearing surface, such as a bridge deck.

Bahan yang digunakan untuk menutup lantai, tingkat atau perancah.

Kayu sementara menyokong tanah di sebelah penggalian.

Direka untuk dibentangkan rata sebagai sebahagian permukaan yang menanggung beban, seperti geladak jambatan.

Dua atau lebih kepingan kayu atau

Page 4: 3.3.1 planking strutting

Materials

(Bahan-II) Timber

(Kayu)Steel

(Keluli)

Page 5: 3.3.1 planking strutting

•Timber has always been used the past and is still the most commonly used material for planking.(Kayu sentiasa digunakan dan masih merupakan bahan yang paling biasa digunakan untuk lantai)

•Struts, ties and coupler are necessary to main rigidity that timber is usually found to be quicker and more economical of labour.(Tupang, ikatan dan pengganding adalah kebiasaan utama kayu , biasanya digunakan untuk menjadi lebih cepat dan lebih menjimatkan buruh)

back

Page 6: 3.3.1 planking strutting

• Steel stanchions and, particularly, steel needles are often used for dead shoring.Stanchions keluli dan, terutamanya, jarum keluli sering digunakan untuk penyokong mati.

• Tubular scaffolding is less frequently used for this purpose.Perancah tiub kurang digunakan untuk tujuan ini.

Page 7: 3.3.1 planking strutting

•Although effective flying and raking shores can be constructed with tubular scaffolding.

Walaupun berkesan terbang dan menggeledah pantai-pantai boleh didirikan dengan perancah tiub

cont…

Page 8: 3.3.1 planking strutting

Why do we need Planking

?

Page 9: 3.3.1 planking strutting

To give support to walls which are dangerous or are likely to become unstable, bulging or leaning. Untuk memberi sokongan kepada dinding yang berbahaya ataupun dinding yang tidak stabil, membonjol atau melentur.To avoid failure of sound walls caused by the removal of subjacent support such as where a basement is being constructed near to a sound wall. Untuk mengelakkan kegagalan dinding bunyi yang disebabkan oleh penyingkiran sokongan yg terletak di bawah seperti mana ruangan bawah tanah sedang dibina berhampiran dinding bunyi.To give support to a floor or roof to enable a support wall to be removed and replaced by a beam. Untuk memberi sokongan kepada lantai atau bumbung untuk membolehkan dinding sokongan di keluarkan dan diganti dengan rasuk.To support the upper part of wall during formation of a large opening in the lower section of the wall. Untuk menyokong bahagian atas dinding semasa pembentukan pembukaan besar di bahagian bawah dinding

Page 10: 3.3.1 planking strutting

MeasurementsThe dimensions shall be measured correct to the nearest cm and the area of the face supported shall be worked out in square meters correct to two places of decimal.Dimensi hendaklah diukur betul ke cm terdekat dan kawasan permukaan disokong hendaklah menggunakan meter persegi kepada dua tempat perpuluhan

Works shall be grouped according to the following:

(a) Depth not exceeding 1.5 m.(b) Depth exceeding 1.5m in stages of 1.5 m.

Kerja-kerja hendaklah dikumpulkan mengikut kepada perkara-perkara berikut:

(a) Kedalaman tidak melebihi 1.5 m.(b) Kedalaman melebihi 1.5m dalam peringkat 1.5 m.

Page 11: 3.3.1 planking strutting

2. Planking and strutting to the following shall be measured separately:Planking dan tumpang hendaklah diukur secara berasingan :• Trenches. (parit)• Areas- The description shall include use and waste of raking

shores.• Kawasan – penerangan perlu meliputi kegunaan dan

pembuangan • Shafts, walls, and manholes. (Batang, dinding-dinding, dan

lurang-lurang )

• Planking and strutting required to be left permanently in position shall be measured separately.

Planking dan tumpang diperlukan untuk dibiarkan kekal dalam kedudukan hendaklah diukur secara berasingan.