3223 ultraroof380 installation A4 68pp AW JAN 2018 MAIN · 6 Fixing panel to beam 300mm CTRS RRR...
Transcript of 3223 ultraroof380 installation A4 68pp AW JAN 2018 MAIN · 6 Fixing panel to beam 300mm CTRS RRR...
V4 | February 2018
ULTRAROOF INSTALLATION GUIDE
2
Dear Customer,
Thank you for choosing the Ultraframe Ultraroof380 product. This guide is designed to make tting as straightforward as possible.
Before you commence installation of the roof, please take a moment to read the guide.
This guide is written on the basis that a quali ed surveyor has undertaken correct checks for the capability / structural performance of any existing framework / walls / foundations to verify they are t for purpose. Any feedback - positive or negative - is welcomed so we can make our systems even better.
Please contact the Tech Support Team on 01200 452 918 or email [email protected] FITTERS:
Look out for this registration form and pass to the homeowner please
CONTENTS PAGE PAGE
Tools required / items not supplied 3Fixing summary 4-8Ultraroof380 tters tips 9Documentation checklist 10Box beam cross section assembly 11Product overview / assemblies 12-13Fitting sequence for box beams, OSB boards 14Box beam on window frame 15Box beam on brick work 16Box beam on brick and window frame 17Installation - Solid - Georgian - Box eaves beam 18-22Installation - Solid - Georgian - Structural framework 23-24Installation - Solid - Georgian - Panel assembly 25Installation - Solid - Georgian - OSB boarding 26-27Installation - Georgian - Water proof under layer 27-28Installation - Georgian - Hip spines/Ultratile/Cappings 29-34Installation - Georgian - Fascia so t and guttering 35Installation - Down lights 36
Installation - Plasterboarding 37-38Installation - Plasterboarding columns 39Installation - Georgian - Roof glass 40-46Installation - Lean-to solid 47-50Installation - Lean-to glazed 51-53Installation - Lean-to glazed to adjacent wall 54Installation - Gable end solid 55-57Installation - Gable reinforcement 58-59Installation - Gable standard so t 60Installation - Gable extended so t 61Installation - Box beam on column 62Installation - Tudor nishing 63-64Installation - Beam jointing post 65-66
3
Clamps 2.5m straight edge
Small sca old tower & Youngman boards
Drill/imapct screwdriver
8mm Hex head socket
10 and 17mm spanner
Long (1,500mm) and short spirit levels
Tape measure
Plumb bob and string line
Acro prop
Heat gun
6mm drillbitStaple gun
TOOLS REQUIRED
NOT SUPPLIED:Several items are not supplied by Ultraframe as they are easier and cheaper to source locallyThese are:-
• Velux roof windows and EDL ashing kits (the roof arrives prepared for Velux)• Anchor or Masonry xng bolts to host wall• 12.5 foiled backed plaster board and skimming beads• LED ( re resistant) lighting• Internal 20mm x 50mm and 25mm x 50mm timber plastering battens• Timber support props (75mm x 50mm) beam support• Structural support (available from Ultraframe)• Frame to boxbeam xings
For everything you need to know about Ultraroof380 including guides and installation videos visit
www.ur380info.co.uk
4
CHA0064.0 x 13 self drill
wafer head
PHILLIPSSCREWDRIVER
BIT
PLEASE USE THE SUPPLIED FIXINGS WHEN INSTALLING THE ULTRAROOF380 TO ENSURE A SECURE AND CORRECT INSTALLATION.
FIXINGS SUPPLIED Below shows the various xings supplied for an installation of an Ultraroof380. These should be found in the box containing this document.
NRBA 0124.8 x 32 Phillips CSK HD S/Drill
BPS 0104.8 x 80 baypole screw, self drill
Phillips wafer head
NRTS 0504.2 x 25 wafer head Self drilling screws
RRX 0255.0 x 50 C’SNK pozi
heco x wood screw
RRR 0255.5 x 32 Hex head
self drill screw
NRRSA 005BL5.5 x 90 Hex washer
head tek screw
NRBF 0504.0 x 40 Deck-tite pozi countersink
screw
NRES 0044.8 x 32
pan head self drill
NRSF 0124.8 x 38
pan head self drill
NRAF 0255.5 x 50 self drilling
C’SNK, winged screw
PHILLIPSSCREWDRIVER
BIT
PHILLIPSSCREWDRIVER
BIT
PHILLIPSSCREWDRIVER
BIT
PHILLIPSSCREWDRIVER
BIT
PHILLIPSSCREWDRIVER
BIT
PHILLIPSSCREWDRIVER
BIT
POZISCREWDRIVER
BIT
POZISCREWDRIVER
BIT
M8 HEXSCREWDRIVER
BIT
M8 HEXSCREWDRIVER
BIT
ULTRAROOF380 FIXING SUMMARY
NRTT001Tile screw xing tool
NRTT0014.2 x 25 Wafer head piercing point screw
PHILLIPSSCREWDRIVER
BIT
5
Fixing support shelf to existing frames
6 xings per corner
NRBA 0124.8 x 32 Phillips CSK HD S/Drill
Ultraframe recommends HILTI chemical anchors where speci ed and expanding anchors in other locations (to resist pull out forces). Using HILTI product codes/descriptions, use a HIT-V 80mm x M8 threaded anchor (stud*) fastened into a 10mm clean drill hole with gun injected mortar or adhesive capsules (with a minimum 80mm embedded) - always rigorously follow manufacturers guidance www.hilti.comIn addition Ultraframe recommends the following alternatives;Fischer M8/M10 masonry injection anchor FIS VRawl Fixings M8/M10 CFS RM50 or CFS RP30* Design load for each stud 2.5k
Fixing hanger bracket to wall
Fixing through head of window frame into beam
4 xings per bracket
Securing corner cleats
Securing upper box beam cleats
200mm from corner, 450mm CTRS
NOT SUPPLIED
NOT SUPPLIED
12 per cleat, 6 through pre drilled holes, 6 through gutter support channel
NRTS 0504.2 x 25 wafer head self drilling screws
6 per cleat
NRTS 0504.2 x 25 wafer head self drilling screws
Fixing beam to corner
6 xings per corner
RRX 0255.0 x 50 C’SNK pozi
heco x wood screw
Fixing wall brackets to the beam
6 xings per bracket
RRX 0255.0 x 50 C’SNK pozi
heco x wood screw
Ultraframe recommends HILTI chemical anchors where speci ed and expanding anchors in other locations (to resist pull out forces). Using HILTI product codes/descriptions, use a HIT-V 80mm x M8 threaded anchor (stud*) fastened into a 10mm clean drill hole with gun injected mortar or adhesive capsules (with a minimum 80mm embedded) - always rigorously follow manufacturers guidance www.hilti.comIn addition Ultraframe recommends the following alternatives;Fischer M8/M10 masonry injection anchor FIS VRawl Fixings M8/M10 CFS RM50 or CFS RP30* Design load for each stud 2.5k
NOT SUPPLIED
Fixing ridge hanger to the wall
Minimum 2 xings
Fixing hip bar support brackets
4 xings per bracket
NRTS 0504.2 x 25 wafer head self drilling screws
Fixing ridge to ridge hanger
2 xings
RRR 0255.5 x 32 Hex
head self drill screw
FIXING LOCATION SUMMARY
6
Fixing panel to beam
300mm CTRS
RRR 0255.5 x 32 Hex
head self drill screw
300mm CTRS (Pre drilled holes)
RRR 0255.5 x 32 Hex
head self drill screw
Fixing panel to hip and ridge
300mm CTRS
RRR 0255.5 x 32 Hex
head self drill screw
Fixing panel to starter
Ultraframe recommends HILTI chemical anchors where speci ed and expanding anchors in other locations (to resist pull out forces). Using HILTI product codes/descriptions, use a HIT-V 80mm x M8 threaded anchor (stud*) fastened into a 10mm clean drill hole with gun injected mortar or adhesive capsules (with a minimum 80mm embedded) - always rigorously follow manufacturers guidance www.hilti.comIn addition Ultraframe recommends the following alternatives;Fischer M8/M10 masonry injection anchor FIS VRawl Fixings M8/M10 CFS RM50 or CFS RP30* Design load for each stud 2.5k
NOT SUPPLIED
Within 200mm from ridge/eaves,another equidistant
Fixing starter to house wall
Fixing extention batterns to beam
NRAF 0255.5 x 50 self drilling
C’SNK, winged screw
2 xings per batten
Fixing OSB to panel and beam
24 per panel
NRBF 0504.0 x 40 Deck-tite pozi countersink
screw
Fixing steel hip plates
NRTS 0504.2 x 25 wafer head self drilling screws
300mm CTRS (Pre drilled holes)
Fixing aluminium ridge plate
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
Fixing UltraTile starter tile strip
NRTS 0504.2 x 25 wafer head self drilling screws
x through all available holes
Fixing Ultratile panel
NRTS 0504.2 x 25 wafer head
piercing point screw
11 per full tile
FIXING LOCATION SUMMARY
Fixing hip spines
NRTS 0504.2 x 25 wafer head self drilling screws
500mm CTRS per side
7
Fixing intermediate glazing bar bracket
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
Fixing glazing bar at box beam shoe
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
Fixing glazing ridge to glazing bars
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
Fixing glazing bar to box beam external face
NRTS 0504.2 x 25 wafer head self drilling screws
2 xings either side
BPS 0254.8 x 80 baypole
screw, self drill Phillips wafer head
Securing glazing bar against panel timber
500mm CTRS
Fixing glazing support section
NRTS 0504.2 x 25 wafer head self drilling screws
200mm CTRS
Fixing ridge top cap
Pre drill MAX 750mm CTRS
NRRSA 005BL5.5 x 90 Hex washer
head tek screw
Fixing end caps
Screw port
NRES 0044.8 x 32
pan head self drill
FIXING LOCATIONS FOR GLAZED ROOFS The following shows an overview of where the supplied xings are used based on a roof contaning glazing.
Fixing glazing bar shoes at box beam
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
Fixing glazing bar adjustable connection bracket
NRTS 0504.2 x 25 wafer head self drilling screws
Pre drilled holes
FIXING LOCATION SUMMARY
BPS025
RRR 0255.5 x 32 Hex
head self drill screw
Fixing through ridge into purlin 300mm CTRS
8
Pre drilled holes
NRES 0044.8 x 32
pan head self drill
Fixing glazing bar end caps
NRRSA 005BL5.5 x 90 Hex washer
head tek screw
500mm CTRS
Fixing ridge under capping central
Fixing black architrave
300mm CTRS
Fixing screen framework at ridge
NRBF 0504.0 x 40 Deck-tite pozi countersink
screw
300mm CTRS
NRSF 0124.8 x 38
pan head self drill
Fixing tile stop aluminium 300mm CTRS
Fixing tile screen
Single xing
NRBF 0504.0 x 40 Deck-tite pozi countersink
screw
BPS 0104.8 x 80 baypole
screw, self drill Phillips wafer head
Fixing through purlin into cassette
Single xing
RRX 0255.0 x 50 C’SNK pozi
heco x wood screw
Re-fi tting panel timbers
origional xing holes
Fixing ridge under capping into tile stop
NRTS 0504.2 x 25 wafer head self drilling screws
500mm CTRS
FIXING LOCATION SUMMARY
Half ridge intermediate bar shoe
CHA0064.0 x 13 wafer head self drilling screws
NRBF 0504.0 x 40 Deck-tite pozi countersink
screw
9
ULTRAROOF380 FITTERS TIPS
If this if the first time you’re fitting an Ultraroof380 we suggest you familiarise yourself with the Installation guide before you start.
Ensure that you have all the key documents outlined on page 10 and all the correct tools on site, these are outlined on page 3. If you don’t have any of the key documents, please call Technical Support at Ultraframe on 01200 452 918 - have your order number handy.
For everything you need to know about Ultraroof380 including guides and installation videos visit
www.ur380info.co.uk
Here are some top tips from Ultraframe to help your installation run smoothly.
1. Ensure the beams are laid on top of the frames in the correct order. The correct ‘fitting sequence’ is shown on page 14 of the installation guide.
2. When positioning the beams check the dimensions vs the critical dimensions sheet supplied with the roof. Start by ensuring the beams that attach to the house wall are parallel and the correct distance apart. Ultraroof380 will accommodate slightly out of square bases and frames. Please call Paul Saltis on 07740 067070 for advice if this is the case.
3. In order to ensure the stability of the beam it needs to be sufficiently supported. Details are shown on the flyer included with the beams and on page 19 of this guide.
4. Always use the fixings, sealants and adhesives specified within the installation guide in order to ensure the strength and water tightness of the roof.
5. Don’t forget to prop the ridge as shown on page 23.
6. When fitting the batten extensions to the box beam, ensure that the lower end of the batten extension rests against the edge of the aluminium extrusion on the front of the box beam. This will ensure the OSB is in the correct position. See detail on page 26.
7. Start by placing the OSB boards next to the box beam first. Work your way around the box beam with the OSB before working your way up to the ridge. Only remove the props once the OSB boards and steel hip plates are fixed in place.
8. The waterproof membrane can be fitted when damp, but always remove surface water before fitting if it’s been raining. 100mm overlap is sufficient on the roof surface with 150mm lapping up the wall.
9. Always use tile fixing tool provided. This will prevent over tightening.
10. The tiles are designed for expansion and contraction. DO NOT BE TEMPTED TO FORCE THE TILES TOO CLOSE TOGETHER. Always work to the insertion lines ensuring the spaces between the tiles are even across the roof. Use the starter tile strip to guide you and refer to the tile leaflet included for further information (ref p29).
11. Look out for the handy guides supplied with products for extra tips on fitting.
10
DOCUMENTATION CHECKLIST SENT WITH EACH ROOF
General pointsChoose a suitable area for unpacking the components and always check them before tting. Any claims for missing or damaged parts are only accepted in line with our standard terms and conditions of sale. Health & safetySite safety is paramount. The Construction (Design & Management) Regulations 2015 apply to the whole construction process, on all construction projects from concept through to completion. Compliance is required to ensure construction projects are carried out in a way that secures health and safety. The installation company shall be responsible for the safety of all of the tting team, the customer and members of the public.
The Surveyor should have carried out a risk assessment to reduce risk on site and this should have been discussed with you prior to starting.
Please use safe working platforms and ladders that comply with BS EN 131. Always use equipment in line with manufacturers recommendations. Personal Protective Equipment – such as goggles, mask and ear defenders – should be used when, for example, grinding out for the ashing. Careful consideration should be given to the safe disposal of all packaging – Ultraframe packaging is predominantly made from recycled materials and can be readily recycled.
ProductThe Ultraroof380 kit is supplied with a location plan and, of course, this installation guide. The location plan is used to match individual components to their respective position on the roof.
The SuperstructureCheck the side frames are level all round. Before starting to install the Ultraroof380, please check the condition of the host wall and whether it’s plumb – depending upon what you nd, these conditions can seriously a ect the nal integrity of the roof.
Check the condition of the host wall as this may aff ect the quality of the fi nal installation. Check the host wall is plumb - any running in/or out should have been accounted for by the surveyor. If not, the ridge and starter bars may require packing out with aluminium shims. Correct alignment in this area is critical to a successful installation - Plumb frames/level ridge. Only use the specifi ed fi xings - never be tempted to substitute alternative sizes/gauges.
HOST WALL
PRE INSTALLATION CHECKS
Check you have:1. Critical set out dimensions2. Confi rmation of roof order3. OSB layout4. Tile layout5. Panel layout6. Modesty panel layout7. Component location plan8. Ultraroof380 component box list
11
(Window frame thickness may vary)(when using 70mm frames)40mm
70mm
284mm
UltraTile in 3 colours
Powder coated tile starter support
Integrated Marley Classic gutter system - bracket snaps onto aluminium gutter support channel
321.5mm
Counter battens
190mm Unidek aero panel,
0.16W/m2 ºC (240mm panel to follow)
Waterproof breathable membrane
OSB3 (Oriented Strand Board) - tongue and groove
to 4 sides
OSB3 (Oriented Strand Board) - structural grade
Fascia board
Ultratile starter strip
High performance corrosion resistant steel
High performance corrosion
resistant steel
High performance mineral wool insulation
25x50mm timber battens (Not supplied)
Double plasterboard when roof is
glazed
12.5mm foil backed
plasterboard(Not supplied)
Window frame
380mm
Internal Frame (Datum)
BOX BEAM CROSS SECTION ASSEMBLY
Soffi t channel
Additional timber batten(Not supplied)
Alternative (only option if sat on super-insulated columns) - see Appendix 1.
210mm
(Window frame thickness may vary)70mm
151.5mm172.5mm
Standard Soffi tNOT SUITABLE FOR SUPER INSULATED COLUMNS
Extended Soffi tMUST BE USED ABOVE SUPER INSULATED COLUMNS
12
Ridge glass glass
Beam glass Beam solid
PRODUCT ASSEMBLIES
Ridge solid solid Ridge solid glass
265 boxgutter
13
PRODUCT ASSEMBLIES
Boxgutter glass Tapered boxgutter
Wallplate glass Wallplate solid
Bars Gable extended
Lean to gable stiff enerLean to only
Lean to roof gable end frame sti ener is NOT supplied as standard. Must be requested if required (for example above door openings). Please refer to Ultraframe if tting bi-folds to gable ended or gable ends on lean-to roofs.
14
FITTING SEQUENCE BOX BEAMS OSB
IMPORTANT: FOLLOW THE FITTING ASSEMBLY SEQUENCE
KEY: OSB BOX BEAM
1 2
3
1 2
5
3 4
VICTORIANGEORGAN
BOX BEAM SUPPORT SHELFGEORGIAN STANDARD SOFFIT GEORGIAN EXTENDED SOFFIT
96mm 207.5mmInternal frame line Internal frame line
15
The most common kind of situation for installing an Ultraroof380 will be existing conservatries roof replacement. This means that the roof will x to the top of the window frames of the original conservatory. The details for xing a box beam to the top of window frames as shown below.
DOUBLE PLASTERBOARD
STANDARD SOFFIT
DOUBLE PLASTERBOARD
BOX BEAM ON WINDOW FRAME
STANDARD SOFFIT 40MM
EXTENDED SOFFIT 151.5MM
16
BRICK SOFFIT DEPTH 94mm
OFFSET TO INTERNAL BRICK (FRAME DATUM)
DOUBLE PLASTERBOARD
FAC
mm
mmmm
mm
FRAME DATUM
300
BRICK
DEFAULT STANDARD SOFFIT
OFFSET TO INTERNAL BRICK
DOUBLE PLASTERBOARD
ON BRI
mm
mm
mm
mm
mm
FRAME DATUM
(FRAME DATUM)
SOFFIT DEPTH 40mm
A common instance with Ultraroof380 will be that it is sat on brick work for support. If this is the case there are di erent details of how the roof sits on the brickwork and depending on which of these is required give di erent results. Below contains the details for xing a box beam to the top of solid brick work.
BOX BEAM ON BRICK WORK
STANDARD SOFFIT WITH BRICK
FACE
N BRICK WALLFFIT WIDTH WHEN SITTINGON BRICK WALLSOFFIT WIDTH WHEN SITTING
EXTENDED SOFFIT WITH BRICK
17
BRICK
OFFSET TO INTERNAL BRICK
DOUBLE PLASTERBOARD
FRAME DATUM
SOFFIT DEPTH 40mm
mm
mmmm
mm
Some situations will have a mix of window frames and brickwork that will support the length of the box beam. Below contains the details for xing a box beam to the top of window frames with brick work.
BOX BEAM ON BRICK AND WINDOW FRAME
BRICK
DEFAULT STANDARD SOFFIT
DOUBLE PLASTERBOARD
ST
INC
mm
FRAME DATUM
mmmm
STANDARD SETOUT
INCLUDED
SITTING ON A BRICK
BOX BEAM ALIGNING WITH BRICK FACE
BRICK WORK ALIGNING WITH INTERNAL FRAME DATUM
FACE
18
GEORGIAN INSTALLATION SOLID ROOF BOX EAVES BEAM
NRSS 090Beam support shelf for 90° corner
NRSS 135Beam support shelf for 135° corner
NRBA 0124.8 x 32 Phillips CSK HD S/Drill. 6 xings per shelf.
NRSS 150Beam support shelf for 150° corner
2
Secure support shelves to frames with 6 x xings (3 each side) 4.8 x 32mm Phillips counter sunk self drill screw (NRBA 012).
Timber positioning spacers attached to underside of support shelves. Ensure these abut internal frame (also shown below).
3a
If replacing an existng roof fold back the ashings, safely remove the existing roof and recycle it. If plastered, certain areas will need removing. Fixed light sealed units will need to be removed to allow xing of box eaves beam. Remove old silicone from head of all frames. NOTE: If tting onto super-insulated columns refer to page 62.
1
Using low modulous neutral clear silicone, apply generous beads to head of frames and corner post. Locate the OSB beam support shelf’s (NRSS 090) to the front corners.
5
Apply beads of low modulus neutral clear silicone to remainder of all frame heads. Seal along inner legs.
6
Now t the NRWB001 box beam wall brackets - one to each side - Bracket sits 8mm inside internal frame line and is set 9mm above window frames (measured to underside of bracket). Remove any interfering plaster work. Bracket must go back to host wall. Not required if sat on masonry, galvanised straps to be used (not supplied).
4
Mark positions for resin anchors (not supplied) appropriate to substrate. Try to x into solid masonry - 4 xings.
3b
NRSL 001Beam support shelf sticker
19
GEORGIAN INSTALLATION SOLID ROOF BOX EAVES BEAM
8
Fix a prop into the steel section of the beam as shown above. Props should be at max 2000mm centres within 250mm from each corner (prop xings NOT SUPPLIED) 75x50 timber props NOT SUPPLIED.
9
Check page 14 for box beam assembly sequence. Lift side beam 1 into position (2 man lift). Set the beam 10mm away from host wall. Position side beam 2.
7
Check the beam is level. Pack o top of frames if necessary. Insert a support prop under the beam. Adjust the height of the prop to ensure the beam is level side to side.
11
With set out sta ush with underside of beam, x to face of beam using 2 x (NRTS050) provided. Sta set-out cleat xed to internal face of box beam. Once xed the sta s will
ensure beams remain parallel to each other.
10
EXAMPLEAbove is a typical 4m x 4m layout, this shows positions of 75mm x 50mm support props and set out sta .
READ BEFORE FITTING BEAMS AND RIDGE MUST BE PROPPED SUPPORTED THROUGHOUT THE
INSTALLATION SEE GUIDE BELOW FOR DETAILS OF PROPS SUPPORT.
DO NOT REMOVE ANY PROPS UNTIL THE OSB AND STEEL HIP PLATES ARE FULLY FIXED INTO PLACE.
PROPS SUPPORTS MUST BE POSITIONED 250mm FROM CORNERS AND MAX 2000mm CENTRES AT THE PROP LOCATION MARKS, PROPS NOT REQUIRED AT
HOST WALL REAR L BRACKET POSITION
BEAMS SET 10MM AWAY FROM HOST WALL
20
GEORGIAN INSTALLATION SOLID ROOF BOX EAVES BEAM
16
Gutter support channel extrusion is factory tted but ease out both sections and slide external cleat behind.
17
Line up bottom of the cleat with the bottom edge of the steel using (NRTS 050) xings, t 12 per cleat, 6 in predrilled holes, 6 through gutter support channel extrusion (screws provided).
NRTS 0504.2 x 25mm wafer head self drilling screws
GUTTER SUPPORT CHANNEL
NRBE 135Box beam external cleat required for each 135° mitre
NRBE 150Box beam external cleat required for each 150° mitre
NRBE 090Box beam external cleat required for each 90° mitre
NRTS 0504.2 x 25mm wafer head self drilling screws.[6 per cleat predrilled holes]
19
Then attach top box beam cleat (one to each corner) - these cleats are speci c to the roof pitch. Lay over the mitred joint and position so that the top edge abuts the angle. Then x using 6 x 4.2 x 25mm wafer head self drilling screws (NRTS 050) provided.
18
Use expanding foam where two beams join to seal any gaps between them.
13
Once the beams have been propped and are level, check the rear L brackets and pack if required.
14
Width of set out sta matches size given on critical dimension sheet. Pushing or pulling a beam will move adjacent beam the same distance. Equalise so t overhang. Finally check diagonals are equal.
12
Having installed side beams lift the front beam into position, beam 3.
21
GEORGIAN INSTALLATION SOLID ROOF BOX EAVES BEAM
20
Check all is level - pack o top of frames if necessary. CHECK THE UNDERSIDE OF THE BOXBEAM IS LEVEL PRIOR TO FINAL FIXING. PROP IF NECESSARY.
If packers used, recheck for being square, also check diagonals (corner to corner measurement). When these checks are complete nally secure by screwing up though head of frames into box beam. Fixings need to be within 200mm of each corner and at 450mm centres using, for example 4.8 x 80mm baypole screw not provided.
21
BPS 010M4.8 x 80 baypole screw, self drill Philips wafer head[ xings 200 from corner, 450 CTRS]
Remove timber positioning dowels (see step 3b). Fix up through the front 90° beam support shelves into the box beam using 6x5.0 x 50mm countersunk wood screw (RRX 025) provided. See xing points at 22b (standard so t) and 22c (extended so t).
22a
RRX 0255.0 x 50 C’SNK pozi heco x wood screw.[6 xings each]
Fixing positions for standard so t.
22b
Fixing positions for extended so t.
22c 23
Fix up through the rear box beam wall brackets into the box beam using 6 x 50 x 50mm countersunk wood screws (RRX 025) provided. Finally ensure all box beam joints are fully sealed inside and out.
22
GEORGIAN INSTALLATION SOLID ROOF BOX EAVES BEAM
Once assembled lift and position against the host wall. Slot onto beam support ledge.
With the box beam secured assemble the 3 part ridge hanger. This consists of 1 x ridge hanger plate (NRRI 006) and 2 x aluminium starter bar extrusions (NRPA__/6) .
25
24
Fit the hip bar support brackets (NRHB 001) to the internal front corners of the box beams. One to each corner. The bracket is positioned tight up to the panel support ledge and secured with 4 x 4.2 x 25mm wafer self drilling screws (NRTS 100) provided. Hip bracket supplied for 90°. If super-insulated corner columns used please refer to page 82. For 3 and 5 facet victorians the box beam hip bracket is bent by hand to suit. 135° for 3 facet or 150° for 5 facet.
NRTS 0504.2 x 25mm wafer head self drilling screws.[4 xings each]
26
TONGUEUPPER FACE
NRRI 006
3 facet
135°
5 facet
150°
28
Final position of aluminium starter bar extrusions next to host wall.
27
From critical dimension sheet, check that the UPPER FACE of the ridge hanger ‘tongue’ is set at the correct height. i.e. frame height 2070 + 861 (roof) = 2931mm. Ensure the plate is level. Pack o the host wall with suitable aluminium shims if required. Fix the ridge hanger (NRRI 006) back to the host wall with anchors suitable for the substrate (not supplied).
NRSB 001 Box beam hip bracket required for each hip
23
GEORGIAN INSTALLATION SOLID ROOF STRUCTURAL FRAMEWORK
30
O er up into position the hip bars. Using the tenon on the glazing bar end o er the ‘ball’ into the matching speedlock housing attached to the ridge.
31
O er ridge onto ridge hanger plate, set the rear end of the ridge body 20mm away from the host wall and temporarily secure with 1 x 5.5 x 32mm hex head drill screw (RRR 025). NOTE: This may be adjusted later. IMPORTANT: Support the ridge with adjustable support props. The props must stop in place until the roof is fully built.
29
33
Check critical dimension sheet for dimension x and then nally x the ridge to the ridge hanger bracket with 2 x 5.5 x 32mm hex head drill screws (RRR 025) provided.
34
Using your thumb push down the upper dead lock until ush. DO NOT push up the lower wedge lock at this stage.
32
Sit the lower end of the hip bar on the already installed hip bar support brackets.
RRR025 Hex head drill screw 5.5mm x 32mm [2 xings each]
XBOX BEAM
RIDGE
UPPER DEADLOCK
IMPORTANT: CHECK DIMENSION X
End of ridge body
IF THE ROOF HAS GLAZED UNITS GO TO P40 IF THE ROOF HAS VELUX ROOF SEE VELUX INSTALLATION GUIDE
36
The lower end locates on the box beam support ledge. IF THERE IS GLAZING AGAINST HOST WALL POSITION THE PANELS EITHER SIDE OF THE FINIAL POINT INSTEAD.
37
Next install Unideck SIP panels (one each side) adjacent to host wall.
35
The upper end hooks onto ridge body.
24
39
Fit front central panel in-line with ridge.
38
This pack comes complete with further detailed assembly instructions. For each matching pair of panels along the ridge, a coupler needs to be tted to brace the panels across the ridge.
41
Ensure coupler assembly is nger tight into panel extrusions.
42
Assemble nut and threaded bar. Screw down into ridge body. See note below.
40
Now complete next step of ridge coupler assembly.
Finally, nger tighten the locking nut.
43
RIDGE COUPLER
Ridge Coupler Assembly
Change - No longer speci ed for rst panel pair at host wallReason - Not required in this position due to xings already present under panel at host wall.
GEORGIAN INSTALLATION SOLID ROOF STRUCTURAL FRAMEWORK
25
GEORGIAN INSTALLATION SOLID ROOF PANEL ASSEMBLY AND FIXING
44
From the location plan supplied continue to install all remaining SIP panels (working from the host wall, in pairs, remembering to t the ridge coupler assemblies as you go. FINGER TIGHT ONLY AT THIS STAGE.
46
Screw up into panels through the panel support ledge. DO NOT OVER TIGHTEN TO PREVENT CRUSHING THE PROFILE. Screw at 300 centres using hex head drill screw 5.5 x 32 (RRR 025) provided.
45
Using (RRR 025) screws, screw up through the hip bars (predrilled holes). DO NOT OVER TIGHTEN TO PREVENT CRUSHING THE PROFILE.
Screw through aluminium starter bar extrusions into panels at 300mm centres. Finally screw through ridge section (predrilled holes) again using (RRR 025) provided.
47 48
Lightly tighten roof coupler(s), using a 17mm spanner. Remove hip bar support brackets (p22, step 24). Push lower wedge locks into position on underside of speedlocks to lock out roof (see p23, step 32)
49
Fix aluminium starter bar extrusions to host wall within 200mm of ridge / eaves plus at least one more equidistant between the two. Use resin anchors suitable for substrate. (Not provided).
Foam
3mm nominal Gap
Foam
Box beam
Use expanding foam to ll gaps between panels, panel and box beam and between panels and host wall. (Foam not supplied)
INSULATION IS SUPPLIED IN ROLLS. Cut and install into all hip and ridge sections.
5150
26
GEORGIAN INSTALLATION SOLID ROOF OSB BOARDING
Fit batten extensions onto box beam. Bottom of batten sits against gutter channel and line up with battens on panels. At every corner place a batten either side of the mitred joint on top of cleat.
ENSURE BATTENS SIT TIGHT TO GUTTER CHANNEL THIS SETS THE ROOF TILES.
NREB01020 x 44 x 330mm Tanalised softwood timber battens (pack of 10)
52 53
NRBF050
4.0 X 40mm
DECK-TITE
COUNTERSINK
SCREW
55
Using location plan, lift OSB board panel A into approximate position. Having xed tile starter support onto end of OSB, place against ends of batten extensions to locate OSB. Locate rst row of OSB panels around the roof using tile starter support to position. Work in the same order that the beams were put on (sides toward front).
TIP: USE A 30MM BLOCK TO CHECK OFFSET AT HIPS. Where required support OSB at joints with Batten extensions.
54b
Fit tile starter support, silicone + push t.
54a OSB groove to bottom edge
Tile starter support
NOTE: PRINTED SIDE OF OSB BOARD FITTED FACE DOWN ROUGH FACE
250
100
225
75
PANEL
BOX BEAM
BATTEN CENTERLINE
IMPORTANT The rst row of OSB boards around the perimeter of the roof lock together the box beam and the structural insulated panel. It is important to use the xings shown and follow the screw pattern across along every batten centerline.
NRAF0255.5 x 50m self drilling countersunk winged screw. (2 xings per batton).
27
GEORGIAN INSTALLATION SOLID ROOF OSB BOARDING
Place aluminium ridge cover plate 10mm away from host wall. Fix through the predrilled holes using 4.2 x 25 wafer head drilling screws (NRTS 050) provided.
60
Where required support OSB board at joints with support battens supplied. Battens are 65 x 19 x 700mm long (NRPB 010).
57 58
NRBF0504.0 x 40mm Deck-tite pozi countersink screw (24 per panel)
NRTS050 4.2 x 25mm wafer head self drilling screws.
59
Fit steel hip plates aligning bottom with tile starter support strip. [ xings 300 centres through predrilled holes using NRTS050].
NOTE: THESE ARE SUPPLIED IN TWO HALVES IF OVER 3.2M IN LENGTH TO ALLOW FOR ADJUSTMENT OVERLAP IF REQUIRED.
56
Fit remaining OSB panels working one side at a time left to right, eaves to ridge. NOTE: ALL OSB PANELS HAVE TONGUE AND GROOVE EDGES FOR IMPROVED FIT, SECURE ALL BOARDS WITH 3 FIXINGS TOP, MIDDLE AND BOTTOM USING 4MM X 40MM DECKTITE POZI COUNTERSUNK SCREW NRBF 050 PROVIDED.
61
Image shows roof covered with breathable membrane. Follow the sequence. Membrane part no: RRMA050
Start at eaves and position 150mm up the host wall. Place membrane (as step 63). Overlap each hip (as step 64).
62
The breathable membrane is aligned to the front edge of the tile starter support
63
Place breathable membrane
28
GEORGIAN INSTALLATION SOLID ROOF WATER PROOF UNDER LAYER
64
Work up the roof, overlapping the previous layer by 150mm at pitches of 14 or below and 100mm at 15 and above.
65
Minimum 200mm overlap over hips. Fix using staple hammer with maximum 12mm stainless steel staples. Take care not to cut through lower layers whilst trimming.
On solid roof, the membrane layer straddles the ridge. Slit as shown to allow transition to the opposite side. If the membrane falls short of the ridge plate, install an additional canopy, centrally over the ridge.
66
67
Patch fully taped.
68
Install additional patch of membrane to protect the apex at the host wall. Secure with tape supplied.
Finally cover the previously installed patch with a third layer to ensure positive seal. Staple into position.
69
70
Use tape to seal the layer at ridge end.
29
GEORGIAN INSTALLATION SOLID ROOF HIP SPINES ULTRATILE
GLAZED ROOF SOLID ROOF
If a roof contains rectangular glazing panels, starter strips must be set out from the glazing bar centre.
KEYFitting order is labelled to
Direction of starter strip tting
FIRST STARTER STRIP FITTED FROM HERE
Hip spine to hip spine
Details shown also apply to Victorian shapes.
HOST WALL
Hip SpineHip Spine
1
1 5
2
5
4
3
HOST WALL
Hip SpineHip Spine
FIRST STARTER STRIP FITTED FROM HERE
1 3
2
If a roof contains no rectangular glass panels and is classed as ‘solid’ then starter strips must be set out from the hip spine.
KEYFitting order is labelled to
Direction of starter strip tting
1 3
Tile starter strips are lettered in correspondence with its location shown in the tile location plan. TILE STARTER STRIPS ARE NOT FITTED IN ALPHABETICAL ORDER, PLEASE FOLLOW INSTALLATION SEQUENCE ON THIS PAGE FOR CORRECT FIT.
READ BEFORE FITTING FAILURE TO FOLLOW THESE INSTRUCTIONS CAN RESULT IN TEMPORARY DISTORTION WHICH MAY MEAN TILES WILL NEED TO BE RE-LAID. Following these instructions allows tiles to correctly ‘ oat’ for expansion and contraction.
1. ENSURE TILES ARE FITTED TO THE CORRECT INSERTION LINE – DO NOT PUSH TILES TOGETHER. Insertion lines vary according to temperature when installed
2. DO NOT OVERTIGHTEN SCREWS
The NRTT001 Tile Screw Fixing Tool can be found with the NRTF050 screws inside the xings component box.
Hold the tool in place as shown whilst installing each screw and remove to ensure a t which is close but not too tight – This is to allow for the expansion and contraction of the tiles.
Correctly tightened
XOvertight
30
GEORGIAN INSTALLATION SOLID ROOF HIP SPINES ULTRATILE
1 2
Place starter tile strip on starter tile support, make sure strip is a tight t up against support.
Fix through the central xing hole for temporary tting. DO NOT FIX THROUGH SLOTTED HOLES UNTIL ALL
STARTER STRIPS ARE IN PLACE
3 4
Following the direction stated in the tting guide (see p29). Align next starter tile strip with the standard insertion lines. NOTE: IF AIR TEMPERATURE IS BELOW 5°C, ALIGN WITH THE LOW TEMPERATURE LOCATION MARK TOP RIGHT OF STRIP
Repeat steps 3&4 following the tting order guide until all starter strips are in place and are correctly tted. Once correct, fully x through slotted holes
along the starter strips for permanent x.
5 6
Mark position of hip spines and remove from roof, this helps with tting of the tile panels.
Using the tile location plan provided, locate position of rst tile panel (labelled aa1), slide down onto the starter
strip leaving 23mm from the starter strip edge. This allows expansion of the tiles in warm temperatures.
UltraTile starter strip
Tile starter support
Slide strip up to insertion lines
Central fixing hole Slotted hole
Standard insertion lines
Low temperature, insertion lines
Slotted hole Correctly tightened
Overtight
X
31
GEORGIAN INSTALLATION SOLID ROOF HIP SPINES ULTRATILE
7 8
STEP 1 – x through central non adjustable xing hole STEP 2 – x through remaining slotted holes (10 holes)
At normal temperatures, of around 15°C, use the insertion lines indicated red in the image. For low temperature installations, below 5°C, use the single insertion line indicated blue, at the top right of the tile.
9 10
To slot the tiles together, a down and left action is used in one movement. Make sure all tabs have interlocked. Tiles are tted to the roof from left to right bottom to top. Repeat steps 7,8 and 9 for entire layer.
When inserting next layer, overlay tiles in line with insertion lines (marked in red above) on the tile. Repeat steps 8, 9 and 10 until the roof is fully tiled. See tile nishing references on back for accurate t and best results.
L
FIGURE 1 FIGURE 2
If the roof contains full rectangular glass panels, the starter strips MUST be tted from the glazing bar.
If the roof contains no rectangular glass panels, then the starter strips MUST be tted at the hip spines rst.
UltraTile starter strip
Tiles overlap up to guide lines
32
Distance from bottom tile edge to tile overlap insertion lines.This is the amount of tile that should be visible on each layer of the roof. This is a good check to see if the tiles are in the correct position with correct spacing allowances for heat expansion.
H O
S T
W A
L L
25mm FROM EDGE TO WALL
Tiles fi nishing at host wall Tiles fi nishing at gable end
Tiles fi nishing at lean-to ridge Tiles fi nishing at ridge
537mm
REFERENCE DIMENSIONS ONLY - NOT SET OUT DIMENSIONS - site conditions may cause these dimensions to vary.
INSTALLATION TILE FINISHING REFERENCES
33
INSTALLATION TILE FINISHING REFERENCES
1
Lay rst length of the Ultratile starter strip into position (15mm from hip spine centre line) hard against the base of hip spine. IF THERE IS A GLAZING SECTION IN THE ROOF WORK FROM THERE. Temporarily x using (NRTS 050).
2
Working anti-clockwise, temporarily x all hip spines top
and bottom. Spine set 10mm out beyond lower hip point.
Mark position of hip spines and remove from roof, this helps with tting of the tile panels. Using 4.2 x
25mm wafer head self drilling screws (NRTS 050) provided.
3
4
Complete the front facet.
5
Starting with front central facet, continue to lay front row of tiles working from left to right, bottom to top, following the tile location plan.
Using the tile location plan provided, locate position of rst tile panel (labelled aa1), slide down onto the starter strip leaving 23mm from starter strip edge (page 30 step 6). This allows expansion of the tiles in warm temperatures.
6
7
Fully tiled roof. Ensure the 30mm spacing is maintained between tiles on adjacent facets to accommodate the hip spine. Fit the hip spine on completion of the tiling.
8
Continue tiling the roof as above, working anti-clockwise around the roof. Each set of tiles are pushed down, then slid to the left to engage.
NRTS 0504.2 x 25 wafer head self drilling screws
(2 each).
TIP: USE STRAIGHT EDGE TO LINE UP SPINES TO HIDDEN FINIAL POINT.
NRTF 0504.2 x 25 wafer
head self drilling screws
(11 per tile).
34
NRES 004 4.8 x 32 pan head self drill screw (2 per cap)
NRHB002 Aluminium hip spine end plate
GEORGIAN INSTALLATION SOLID ROOF CAPPINGS
1
Centralise ridge to cap over apex. Position 5mm away from host wall. Foam ll void, prior to dress leading.
2
Pre-drill ridge cap at max 750 centres, 6mm holes.
Fix ridge top capping using 5.5mm x 90mm (NRRSA 005BL) provided. Ensure hip spines are aligned with corners of ridge top capping.
3
4a
Fit hip spine end caps. NOTE: (NRES 004) end cap xing screw comes complete with 2 part coloured screw cap cover.
5
Clip t hip capping, ensure xing clips are set at 500 centres (pre - tted clips). In Georgian / Edwardian
situation the hip bar cappings are pre - mitred to abut ridge top capping. NOTE: 3 AND 5 FACET VICTORIANS. THE HIP BAR CAPPINGS AT THE RADIUS END REQUIRE LMEC 004 FITTING, THESE SIMPLY SILICONE AND PUSH FIT ONTO THE END OF EACH BAR.
6
If using existing ashing, dress down over the roof and ridge area then nish as normal. Flashing may need trimming to t neatly. Apply patination oil to lead for peace of mind (Avoids unsightly lead sulphate run o ). Alternatively install new code 4 lead.
NRRSA 005BL 5.5 x 90mm hex washer head self drilling tek screw (with G16 stainless steel sealing washer)
On 3 and 5 facet victorians after tiling, t the preformed external tile ashing
trim (NRVT001). Secure into position using 2 x screws (NRTS 050) provided.
4b
The hip bar top cappings at the radius end require (LMEC004) tting, these require a bead of silicone applying prior to push tting onto the end of each bar.
4c
35
Screw x PVCu so t channel into head of window frame or base of OSB board (screws not provided).
7
Clip t PVCu fascia board locating upper leg to lower leg of aluminium gutter channel (see cross section detail on page 11).
8
GEORGIAN INSTALLATION SOLID ROOF FASCIA SOFFIT AND GUTTERING
9
Fit gutter bracket by placing lower leg onto aluminium gutter channel then ‘snap back’ upper leg. Space at maximum 750mm centres and within 200mm of corner.
10
Fit PVCu fascia corners with silicone.
Fit Marley Classic guttering. Ensure when tting the gutter you t to the insertion marked lines within the unions / gutter corners.
11
12
Extended so t in detail (must be used above super-insulated columns). Silcone seal to retain fascia into ‘H’ section and so t innto ‘U’ channel.
13
Standard so t in detail. Silicone seal ‘U’ channel to retain lower edge of fascia.
36
DOWN LIGHT INSTALLATION
1
The cables can be passed through the grommet and chased above or between the internal battens as shown. Internally, the wiring should be passed beneath the mineral woolinsulation (see inset diagram).
2
Cut a hole in the base of the pelmet for your light tting. Cut a corresponding 20mm dia. hole in the vertical face and t a rubber grommet.
At lower pitches, when only one batten is tted, the hole (and grommet) are positioned lower on the vertical face and the batten split to allow cable access.
3
4
If the light is coincident with one of the internal foam llets (de ned by the marking on the vertical face) it must be positioned in the190mm safe zone.
5
At pitches lower than 17 degrees there is insu cient space on the vertical face to t the 20mm grommet. Drill 2 holes either side of the light xing to allow installation of the wires
as shown. A ‘channel’ can be created using 2 narrow strips of plasterboard covered with a top panel.
Drill through the OSB and vertical face creating the wiring access. The size of the tting may require additional space.NOTE: The cavity should not exceed 130mm from the underside of the beam face
6
THE ULTRAROOF380 BEAM IS NOW INSULATED WITH MINERAL WOOLThis guide shows our recommendations when installing internal down lights in the Ultraroof380 beam. All electrical work must be carried out by a quali ed electrician and tested in accordance with current BS7671 IEE wiring.
THE ULTRAROOF380 BEAM IS NOW INSULATED WITH MINERAL WOOL
37
PLASTERBOARD GUIDELINES
Solid Roof
Glazed Roof
25mm battens to roof panels(Not Supplied)
12.5mm Foil-backed Plasterboard(Single layer – solid roof)
25mm battens to internal beam(Not Supplied)
12.5mm Foil-backed Plasterboard(Double layer –glazed roof *)
25mm battens to roof panels(Not Supplied)
25mm battens to internal beam(Not Supplied)
Eaves Glazed zone
Pitch 15 20 25 30 35 40‘A’ Solid Roof 25 59 92 127 163 202‘A’ Glazed Roof 29 63 98 134 172 212
LVAR multiboard(Supplied)
PVCu PlasterboardTrim (Not Supplied)
20mm batten(Not Supplied)
* Boardintersection
LVAR multiboard(Supplied)
PVCu PlasterboardTrim (Not Supplied)
* Note: Double layer of plasterboard on internal beam upright ensures a single plasterboard seam where ceiling, beam and glazed area boards intersect.
Ridge Glazed Zone
Internal Pelmet Height Calculator
A
A
38
PLASTERBOARD GUIDELINES
Solid Roof
Glazed Roof
Align boards to form a single seamAt internal corner of beam
Variations on Brickwork * Note: Double board if roof features glazing
Attach plasterboard to masonry using timber or metal stud frame. Double board if roof is glazed
Lean-to at 12.5 Degrees
*
*
Attach plasterboard to masonry using timber or metal stud frame
39
PLASTERBOARD GUIDELINES SUPER INSULATED COLUMNS
1
Loggia column
Additional 12mm OSB cladding installed on internal face of super-insulated column. Note: Column aligned 25mm inset from internal beam.
2
3
Finished plasterboard view with board xed to 12mm OSB cladding.
4
Plasterboard in ll to battens adjacent to 12mm OSB cladding.
Finished plasterboard, internal view.
5
25mm
Double board adjacent to OSB cladding
Additional 12mm OSB cladding on internal Loggia face (supplied)
Existing external
loggia OSB cladding
40
INSTALLATION FITTING ROOF GLAZING
FOLLOW MAIN GUIDE UP TO PAGE 11, STEP 28 THEN FOLLOW THIS SECTION
TRANSOM ‘A’ FRAME BAR (GLASS)
TRANSOM INTERMEDIATE BAR (GLASS)
TIMBER TRANSOM ‘A’ FRAME BAR (SOLID)
TIMBER TRANSOM INTERMEDIATE BAR (SOLID)
RIDGE BEAM
STARTER ‘A’ FRAME BAR (GLASS)
STARTER ‘A’ FRAME BAR (SOLID)
GLAZING PANEL
KEY
41
INSTALLATION FITTING ROOF GLAZING
42
GEORGAN
Glass
Glass
Glass
Glass
INSTALLATION FITTING ROOF GLAZING
1
When installing 24mm double glazed units, the box beam OSB face will be marked with the vertical lines which indicate glazing bar centres. On the marked lines, locate to the top edge of the box beam the appropriate box beam shoes (NRBE 001 or NRBE 002) supplied. Fix to the beam using 8 x 4.2mm x 25mm wafer head self drill screws (NRTS 050) provided.
2
THE MAIN GLAZING GUIDE IS BASED ON THIS DESIGN
Drop into position the wall abutment panels, one either side of the ridge (see steps 35-37, page 23). Then the front centre panel (step 38, page 24). From location plan, continue to install all remaining sip panels in pairs, remembering to t the ridge couplers as you go.
3
4
Each glazed area as 2 x ‘A’ frame glazing bar assemblies. These comprise 2 x glazing bars and 1 x adjustable connection bracket (NRAB 001). Attach the bracket to the pre drilled glazing bar using 4 x 4.2mm x 25mm wafer head self drill screw (NTRS 050) provided.
5
When glazing either side of ridge, lower into position. The pre-manufactured ridge purlin cassettes (OSB boarded side nearest the ridge) the bottom edge hooks to the ridge side (like a solid panel).
Lower the glazing bar (with bracket attached) into place along the top of the timber batten and into the already tted box beam shoe.
6
4
Lift the opposite glazing bar into position (to create ‘A’ frame). When aligned, secure the bracket again using 4 screws (NRTS 050) provided. The ‘A’ frame is not to be xed further at this stage. Assemble
and position opposite facing ‘A’ frame as above.
5
Glazing bar in position. If two glass panels sit side by side, intermediate bar must be installed. Mark a centreline on the glazing ridge spacer beam (see location plan). Mark a line 31mm to left and right of centreline then attach 2 x ‘U’ shaped brackets (NRRA001) using 4 x 4.2mm x 25 screws (NRTS 050) provided, for each bracket.
6
43
INSTALLATION FITTING ROOF GLAZING
NRTS050 4.2 x 25mm wafer head self drilling screws
10
Adjust glazing ridge beam height using thumb screws to ensure glazing gaskets are in aligned.
11
Locate the glazing ridge/spacer beam into the adjustable bracket shoes. Check ‘A’ frames are parallel to each other.
‘A’ frame being fastened into box beam shoe.
12
13
Ensure glazing section is square, checking diagonals are equal. Secure adjustable connection bracket into ridge spacer beam using 4 x 4.2mm x 25mm (NRTS 050) provided. Repeat on opposite side of ‘A’ frame.
14
Locate the intermediate glazing bar into the installed ‘W’ brackets.
Again, check intermediate bar for squareness, then secure with 4 x 4.2mm x 25mm (NRTS 050) provided. Repeat on opposite side
15
16
Secure glazing bar to external face of box beam. Two screws each side using (NRTS 050) provided.
17
Fix all glazing bars into box beam shoes, again, using 4 x (NRTS 050) for shoe (NRBE001) or 6 x (NRTS 050) for shoe (NRBE002) provided.
Temporarily remove lower timber batten to allow xing through upper batten. Secure all glazing bars by xing through the upper panel batten at 500mm ctrs. using 4.8mm x 80mm baypole screw self drill Philips wafer head (BPS010) provided. IMPORTANT: ANY GAP BETWEEN GLAZING BAR AND UPPER PANEL BATTEN NEEDS PACKING TO ENSURE NO FLEXING OF GLAZING BAR.
18
44
19
Next, locate aluminium glazing support trims between glazing bars. See inset for location point.
20
Ensure ridge purlin cassette sits square to underside of glazing bar, check bottom hook is located onto ridge and in-line with hooks on adjacent panels by pulling forward. Fix into place using 1 x xing 4.8 x 80mm (BPS010) provided.
Secure the glazing support section at 200mm ctrs. using 4.2mm x 25mm wafer head self drill screws (NRTS050) provided.
21
22
Fix through each side of the purlin cassette into the panel edge using (BPS010) provided.
23
Screw up through ridge section into purlin cassette at 300mm ctrs. using 5.5mm x 32mm hex head drill screw (RRR025) provided.
Now t the tile screen framework (OSB board uppermost) position this 6mm back from purlin cassette front edge (TIP: use 6mm architrave supplied to set position). Fix at 300mm ctrs using xing 4.0mm x 40mm (NRBF050) supplied.
24
25
Where glazing is present, allow the membrane to overlap into the glazing bar as shown. The drainage channel can then be installed to clamp the membrane in place.
26a
Now re t the lower panel batten (which was removed at step 18). Fix using 5.0mm x 50mm c’sunk pozi head x wood screws (RRX025) provided.
RRX025
NRBF050
Tape the joint between the breather membrane and drainage channel as shown using weathering tape (supplied).
INSTALLATION FITTING ROOF GLAZING
26b
45
27
Fit the glazed ridge panel ashing trim to left and right side of ridge, (NRRI 011R right shown). These are bedded down using clear low modulus silicone provided.
28
At each side of the glazing area, an aluminium upper tile stop is tted. The lower edge of the tile stop is positioned a set distance from the edge of the bottom tile starter support. See critical dimension sheet for dimension A, see step 29. The tile stop is bedded down with clear low modulus silicone, then screwed at 300mm ctrs using (NRSF012) 4.8 x 38 pan head screws provided. Finally seal lower edge of the tile stop to underlayer again using clear low modulus silicone.
29
30
Lay carefully into position the 24mm thick double glazed unit tight to the upstand on the lower glazing support section. See seperate detail if tting roof vent.
31
Position the box beam tile screens. Place in-line with adjacent tiling (not covering ventilation mesh) and secure with a single 4 x 40mm screw top centre (NRBF 050) provided.
Prior to tting the pre-notched glazing end pro le, run a bead of silicone, low modulus (for none coated glass) or MS Polymer (self clean glass) immediately behind the co-extruded gasket before tapping down into position. Then seal each end to protect the seal.
32 33
Fold the rubber sealing tabs over the top of each glazing bar.
INSTALLATION FITTING ROOF GLAZING
A
Dimension A given on critical dimension sheet. This gives distance from face of tile stop to outer edge of tile starter support.
NOTE: CHECK FOR 30MM SPACE BETWEEN OSB BOARDS. THIS WILL ENSURE INNER TOP CAP SEALS ARE POSITIONED CORRECTLY ON THE TILES STOPS.
15mm 15mm
46
36
Over solid panel area screw down either side of the capping at 500mm ctrs into the upper tile stop using (NRTS 050) screws provided.
37
Lay aluminium ridge ashing cap. It is positioned 10mm away from the host wall. Then predrill the capping to suit steps 37 and 38.
Over glazed area, also at 500mm centres, screw down through the ridge capping centre line using the longer 5.5mm x 90mm (NRRSA 005BL) screws tted with G16 stainless steel sealing washer. Run a continuous bead of silicone, low modulus (for non coated glass) or MS polymer (self clean glass) along the head of the unit tight to the Q LON gasket.
38 39
Seal and t the front radius end ashing kit using 250 x 250 square butyl sealing tape (supplied). Heat the sealing tape with a heat gun and position the tape over the ridge end (100mm from ridge end). Press rmly into place over the capping then
make 2 slits (as indicated) before forming the nal position.
40
Seal and t the rear host wall pre-formed ashing saddle (NRRI010). Using clear low
modulus silicone.
When tting the glazing top cappings ensure you have the brush seal gasket covering the tiles and the QLon gasket on the glass, prior to knocking the capping down.
41 42
Attach the aluminium transom end cap plates to the end of each glazing bar using 2 x 4.8 x 32mm pan head self drill screw (NRES 004) provided. Each screw comes with a 2 part coloured screw cap cover.
INSTALLATION FITTING ROOF GLAZING
Slide the ridge tile upper screen into position. No xing required.
34
The upper ridge tile screen is trapped by tting 6mm thick black architrave (provided). This will nish ush with the purlin cassette but tight up to the glass unit. Fix at 300mm centres using 4 x 40mm screws (NRBF 050) provided.
35
47
1
From internal frame the front beam overhangs the frames by 94mm (standard so t) and by 170mm (extended so t) equalize so t overhang.
2
ONLY IF GABLE FRAME STIFFENERS SPECIFIED: Fix the aluminium gable beam xing plate to the underside of the box
beam using 6 x RRX 025 screws. NOTE: ALIGN PLATE ‘V’ NOTCH GROOVES WITH EDGE OF BEAM.
For box beam/support and levelling see pages 19 steps 8 to 9.
3 4
Using the measuring sta supplied with the roof, engage the bottom of the guage into the support shelf on the box beam.
5
Temporarily x the half-ridge (cut to internal frame, see image 6) at the height given in the critical dimensions sheet, ensuring the ridge is level. Adjust the half ridge height if necessary. NOTE: DIMENSION IS FROM UNDERSIDE OF BOX BEAM TO TOP EDGE OF HALF RIDGE SEE PAGE 50 .
With measuring sta inserted into the box beam shelf check that the upper end of the sta is aligned with the edge of the hook section on the half-ridge. Pack the half-ridge o the wall if necessary to align in the correct position to box beam. O er up a panel to double check distance and pitch.
6 7
ONLY IF GABLE FRAME STIFFENERS SPECIFIED: Silicone the head of the frames. Place the aluminium gable frame sti ener with V-groove uppermost.
8
Using sta , check in various positions to ensure half ridge is running parallel to box beam. Fully secure half ridge to host wall at 500mm centres using xings appropriate to substrate. Finally secure box beam (see image 21 page 21)
INSTALLATION LEAN TO SOLID
Apply low modulus silicone to the head of frames local to beam area before lifting the box beam into position. Temporarily x the box beam in position.
3
INTERNAL FRAME
48
Fix the gable frame sti ener to the aluminium beam xing plate using 4 x RRR025. Secure along the length of the sti ener at 500mm centres into frames ( xings not supplied). Set out image 10.
9
INSTALLATION LEAN TO SOLID
10
Apply silicone to the gable support extrusion and x the gable frame. Trial t the in ll wedge and coupler prior to nal xing.
11
The 4 xing positions.
Hook the top of roof panels into the half ridge and rest the lower end on the box beam support shelf. Fit all roof panels as shown in the roof panel layout sheet. Ensure barge boards are ush with the end of the beam. See page 23 step 36 and 37 of main guide. NOTE: IF THERE IS GLAZING AGAINST A RETURN WALL SEE PAGE 61.
12 12a
Mark a line on the house wall that is aligned with the top of the battens
13
Screw up into panels through the panel support ledge at 300mm centres through pre-drilled holes in half ridge to secure the panels using RRR025 hex head screw 5.5 x 32mm provided. If panels attaching to return wall (see steps 47 and 48 on page 25 of the main guide)
Fix the batten provided to the wall on the line marked in 13. This provides support for the roof deck as it meets the house wall.
14 15
IMPORTANT: ENSURE BOTTOM ROW OF OSB IS FIXED AS PER IMAGE 55 PAGE 26 OF THE MAIN GUIDE AS THIS LOCKS TOGETHER BOX BEAM TO PANEL.
16
Fit batton extensions and OSB baording as per steps 52 to 58, pages 26 and 27 of main guide.
49
INSTALLATION LEAN TO SOLID
18
Fix the end cap in place using the NRES 004 4.8 x 32 pan head screw with cover caps.
19
Insert the aluminium dry verge end cap into a square cut end. The end adjacent to the house will be angled to run parallel with the house wall.
Apply a bead of clear low modulus silicone to the underside of the dry verge.
20 21
Fix the dry verge to the OSB using NRTS 050 screws at 300mm centres.
22
Position the dry verge on the top edge of the bargeboard, with the membrane folded down the face of the barge board.
Fix the dry verge to the roof deck with NTRS 050 screws, max 300mm centres
23 24
If obstructed on the RHS, remove 15mm from the clips to allow tting.
25
See p29 and the tiling guide in the tile box for details on tiling method.
Cut the breathable membrane underlayer to the width of the roof deck plus 50mm over hanging the OSB barge-board at each end and 150mm up the host wall. See page 27 steps 62 to 65 for minimum overlaps.
17
50
Fit so t trims to underside of barge boards.
26 27
Fit 90° external corner cover trims
28
Fit pvc barge board box ends and barge board
Fit internal and external gable sti ener claddings (if ordered)
29 30
Lead ash to exiting host wall.
INSTALLATION LEAN TO SOLID
LEAN TO SOLID ROOF HALF RIDGE CROSS SECTION
*Set out height given on critical dimension sheet/INSTALLATION - GABLE END - SOLID
*
NOTE: HIPPED LEAN TO1. Box beam will return to host wall.2. Centralise half ridge (if hipped
each end).3. Attach hip bar to speedlock
housing.4. Remainder as Georgian
51
INSTALLATION LEAN TO GLAZED
Follow main guide then follow this section.
GLAZING
PANEL STARTER (GLASS)
TRANSOM
TRANSOM INTERMEDIATE BAR
TRANSOM TRANSOM STARTER STARTER
52
1
Temporarily x the half ridge (cut to internal frame, see image 1) at the height given in the critical dimensions sheet, ensuing the ridge is level adjust the half ridge height if necessary. NOTE: DIMENSION IS FROM UNDESIDE OF BOX BEAM TO TOP EDGE OF HALF RIDGE.
2
Position front box beams on frames. Ensure equal overhang at each end. Support / prop and level as page 19 steps 8 and 9.
When tting intermediate transom glazing bar(s), the centre line of each bar is marked on front box beam. Check centres match roof plan then transfer to rear half ridge. Ensure intermediates are set parallel and square to transoms. Then t pre-cut glazing support trims.
3 4
Fix intermediate glazing bar shoe secure into OSB using 2 x CHA006.
5
Hook onto rear half ridge and secure upper leg using 2 x NRES 004, 4.2mm x 25mm screw.
Locate intermediate bar into shoe on half ridge and shoe on box beam.
6 7
Silicone seal the head of the glazing bar.
8
Secure using 4 X (NRTS 050) screws. Ensure glazing bar gaskets align with glazing support trims. (Pack o timber purlin cassette if required.
INSTALLATION LEAN TO GLAZED
2a
Secure transom bars to upper panel battens (see page 43 step 18). Ensure glazing gasket aligns with top of glazing support trim tape (see inset). You may need to pack o upper panel batten to achieve this.
NOTE: INTERMEDIATE TRANSON BAR SHOW AT STEP 3 ONLY USED WHEN 2 GLASS PANELS SIT SIDE BY SIDE.
53
10
1200mm lengths of CODE4 lead overlapping 150mm and protruding 50mm, beyond nose of top capping to be used. Coat with patination oil to avoid oxidation run o .
11
Centralise and t half ridge aluminium top capping. Secure using (CHA006) at 500mm centres. Beware: Longer screws will penetrate glass units.
INSTALLATION LEAN TO GLAZED
Prior to glazing, insert the tile screen framework. (See step 19 page 44). Position box beam tile screen (see step 30 page 45). Insert double glazed unit (then follow steps 32 to 35 page 45).
9
54
1
Starter bar rides over the front box beam and drops into box beam shoe. Secure the shoe with 2 x (NRTS 050) screws.
2
Set the half ridge (wallplate) 5mm away from the host wall. The height (as step 6 page 47). Upper end of starter bar positioned so that glazing gasket aligns with glazing support trim. Secure to host wall within 200mm of half ridge and box beam plus at least one more equidistant between the two. Use resin anchors suitable to substrate - not provided.
Seal top edge of starter bar bung (NRRA002). Place the bung tight into the junction of the host wall and starter bar. Then seal with clear low modulus silicone.
3
4
Secure the half ridge top capping into starter using (CHA006) screws provided.
5
Silicone the edge of the bung against the starter bar.
Using butyl tape supplied, ensure adequate seal between top capping and starter bar upstand.
6
7
Finally, manipulate code 4 lead over the glazing bar top capping and half ridge capping with overplaps as step 11 page 53.
INSTALLATION LEAN TO GLAZED TO ADJACENT WALL
Refer to Lean to solid section of this guide to complete
55
1
Apply low modulus silicone to the head of frames local to beam area before lifting the box beam into position. Temporarily x the box beam in position.
2
Fix the aluminium gable beam xing plate to the underside of the box beam using 6 x RRX 025 screws. NOTE: ALIGN PLATE ‘V’ NOTCH GROOVES WITH EDGE OF BEAM.
For box beam/support and levelling see pages 19 steps 8 to 9.
3
Silicone the head of the frames. Place the aluminium gable frame sti ener with V-groove uppermost.
4
Fix the gable frame sti ener to the aluminium beam xing plate using 4 x RRR025. Secure along the length of the sti ener at 500mm centres into frames ( xings not supplied). Set out image 10 page 48.
5
INSTALLATION GABLE END SOLID
Apply silicone to the gable support extrusion and x the gable frame. Trial t the in ll wedge and coupler prior to nal xing.
6
After installing the ridge as detailed in pages 22 and 23, images 25 to 30, check that the end of the ridge is in line with the gable end internal frame line.
7
Referring to the panel layout sheet, t the rst panels at the gable end as shown in
images 35 to 37 on page 23.
8
Check that the panel is in line with the end face of the beam and parallel to the gable frame.
9
56
10
Refer to pages 25 to 27 when fi xing the panels, insulation osb and membrane.Note: ensure the membrane extends 50mm beyond the gable end panels.
11
Continue tting the panels from the host wall, remembering to install the ridge coupler assembly shown on page 24 images 39 to 43
When glazing refer to pages 40 to 46, images 1 to 42.
12
13
Fit gable cladding alignment strip intothe aluminium dry verge.
14
Fit one side of the dry verge as shown in steps 18 to 23 on page 49.
Fit opposite aluminium dry verge and point joints on upper and inner edges.
15
16
Continue referring to page 46 images 36 to 39.
17
Slide tile stop under dry verge and xed in place. See page 45 images 27
to 29 for details.
Fit the gable ashing. Mark and trim to t the dry verge.
18
INSTALLATION GABLE END SOLID
57
19
Fit rst 200mm Butyl tape strip sealing the gable ashing to the ridge ashing cap.
20
Apply clear low modulus silicone to the faces shown and re t.
Fit second 200mm Butyl tape sealingthe dry verge to the gable ashing.Cut the tape to allow it to be folded as shown in the following two images
21
22
Finally cover joint with a third layer.
23
Fold down and press rmly into position.
Fit the ridge top capping using the NRRSA 005BL supplied.
24
25
Fit the pre-cut fascia and eaves trims.See page 50, images 26 to 29for more detail.
26
Apply clear low modulus silicone to the joint between the ridge top cap and the dry verge.
Fit the fascia ridge trim, modifyingwhere necessary ensuring a neat nish.
27
INSTALLATION GABLE END SOLID
58
The gable apex cover is a product for an improved nish at the exterior apex of a duo-pitched gable roof. This new 2-part product is used to cloak the joint between two adjoining dry verge claddings.
Scribe the lower part to t beneath the step in the aluminium dry verge cladding as shown. Fix using a suitable silicone adhesive.
1
2
Position as shown and x using 2 x NRTS 4.2 x 25 self drilling wafer head screws (supplied).
3
Bend the wings of the upper part to match the desired roof pitch – by default they are set to 25 degrees.
Finished installation shown above.
4
INSTALLATION GABLE APEX COVER
25°
NRGC002/2 NRGC002/1
59
INSTALLATION GABLE REINFORCEMENT BOX DETAIL
GABLE REINFORCEMENT BOX
A
1 FRAME STIFFENERTERN CLADDING
SUGGESTED 10mmREDUCTION IN FRAME SIZE FOR NEW BUILD TO ALLOW FOR SETTLEMENT
40
5.175 SECTION I-I
IFL
UNDERSIDE OF BEAM
GABLE REINFORCEMENT BOX SECTION(SEBA---/4)80 x 120 x 6.75mm
WINDOW SUPPORT L SECTION (RRP---/4)SENT FULL LENGTH OF GABLE ATTACHED FULL LENGTH OR CUT TO SIZE AS REQUIRED ON SITE
STUB CILL NOT SUPPLIED
TRIM NOT SUPPLIED
ONSITE
CEMENT
GABLE REINFORCEMENT BOX SECTION FIXED TO BRACKET
COUNTERSINK HOLES
Detail may vary if tting on brickwork. Refer to brickwork section.
NOTE: A cill will be required if on super-insulated columns
60
INSTALLATION GABLE REINFORCEMENT BOX DETAIL
A
2mm OFFSET
DETAIL A
REINFORCEMENT CUT SQUARE AT INTERNAL FACE OF BEAMPACK OUT AREA UNDER BEAM ONSITE OR CAP EXPOSED END OF REINFORCEMENT BOX [PACKING OR END CAP NOT SUPPLIED]
NRRB001GABLE REINFORCEMENT BRACKETFIXED TO BEAM ONSITESEBA---/4GABLE REINFORCEMENT BOX SECTION80 x 120 x 6.75mm
GABLE REINFORCEMENT
REPLACES NRFS---/1 FRAMAND SSPC--- LANTERN C
CAD MODEL IS MA
WINDOW SUPPORT L SECTION
GABLE REINFORCEMENT BOX SECTION FIXED TO BRACKET
COUNTERSINK HOLES
G O
INTERNAL FRAME LINE
GABLE REINFORCEMENT BRACKET(NRRB001)FIXED TO BEAM POCKET ONSITE
GABLE END OF BEAM
61
GABLE SYSTEM OVERVIEW SECTION THROUGH STANDARD SOFFIT
50mm overlap
44mm
STANDARD SOFFIT
ALUMINIUMDRY VERGE
GABLE EDGING (PRE-FITTED TO PANEL)
EXTERNAL FASCIA
GABLE TIMBER (PRE-FITTED TO PANEL)
9mm MULTIBOARD
GABLE FRAME
RIDGE BODY (ALIGNED WITH GABLE FRAME)
PANEL
TILE STOP(INSERTED INTO DRY VERGE)T&G OSB BOARD
RIDGE FLASHING CAP(ALIGNED WITH DRY VERGE)
WATERPROOFMEMBRANE
62
GABLE SYSTEM OVERVIEW SECTION THROUGH EXTENDED SOFFIT
EXTENDED SOFFIT
GABLE TIMBERS (PRE-FITTED TO PANEL)
63
BOX BEAM ON SUPER INSULATED COLUMN
25mmCOLUMN EXTERNAL FACE TOBOX BEAM EXTERNAL FACE
207.50mm EXTENDED SOFFIT ONLYON SUPER-INSULATED COLUMN
If your installation contains a super-insulated column, then it is possible to support the box beam on the column providing that the beam is installed with the following details.
EXTENDED SOFFIT ONLY ON A SUPER INSULATED COLUMN
64
INSTALLATION INTERNAL EXTERNAL FINISH TUDOR
1
Batten out to suit plasterboard xing.
2
NO MATERIALS SUPPLIED FOR THIS FINISH. Attach corner beam support shelf
Attach additional battens.
3
4
Fix into position.
5
Slide into position additional external OSB board.
Plasterboard the roof.
6
7
Fix into place.
8
Fabricate 70 x 45mm triangular studding framework to suit.
Attach additional mating timber battens.
9
65
INSTALLATION INTERNAL EXTERNAL FINISH TUDOR
10
Plasterboard face of gable
11
Insulate void with mineral wool. Fit external so t channeling.
12
13 14
Fit external ship lap cladding edge channel.
Cut and t ship lap to suit.
15
External ship lap cladding edge channel detail.
66
PLEASE READ BEFORE FITTING
SUPPLIED COMPONENTS Below shows the various components that should be supplied as a beam joining on post kit.
BEAM FIXING SCREW5.0 x 50 C’SNK pozi heco fix
wood screw
NRSP0012500mm Post Sleeve with beam joing plate
RRF004Post base plate
with spigot
POST COUPLING BOLT M12 x 110 SOCKET CSK SCREW
X1 X1 X12 X2
X2
WASHER NUT
X2
NRSK001Fixing Kit
INSTALLATION BEAM JOINING POSTThis document shows how to join two Ultraroof380 Beams that are over 7m+ onto a stanchion post.
1
Measure from the surface the post will sit on to the top of the window frames, this will drive the length of the post sleeve (NRSP001)
2
NOTE: The post can be placed either at floor level or on top of a dwarf wall. Guide will show instruction from dwarf wall level.
Cut the post sleeve (NRSP001) to the length measured in step 1
3surface to
window frame top
FITTING THE POST
Cut
surface to window frame
top
67
INSTALLATION BEAM JOINING POST
4
Align the two sections as shown in the image above.
5
Slide the base plate(RRF004) all the way into the cut post sleeve.
Secure the two sections together using the fixing bolts provided. Drill a 13mm hole through both sections and counter sink, secure with nuts provided.
6
7
Fix the post into the brick (FIXING NOT SUPPLIED)NOTE: CILL MAY REQUIRE NOTCHING
8
Offer up the post onto the brick work; maintain a 20mm gap between the post and the external brick internal/window frame. Make sure the post is in the correct orientation. (SEE STEP 1)
Once secured, place the first box beam onto the post followed by the second beam.
9
10
Use the extra cleats provided to secure through the metal sections of the box beam. (see above image)
11
Once both beams are in place, secure the post into the beams. (Fix through the 12 counter sunk holes using the screws provided.)
Insulate between the post and the external brick when post is set within the cavity wall.
12
Top plateBase plate
20mmbetween post and window frame
Fix cleat
Fix cleat
Insulate (not supplied)
Job No.: 3223 2/18 V4 NRIG001 It is Ultraframe’s policy to continually seek to improve its products, processes and services, and we reserve the right to change speci cations without prior notice. Ultraframe is a trading name of Ultraframe (UK) Limited.
www.ultraframetrade.co.uk