3 Month Look Ahead DD 25th Sept-2015

6
Activity ID Activity Name Original uration Physical % Complete Start Finish BL Project Start BL Project Finish Variance - BL Project Start Date JI-2024 - Khazza JI-2024 - Khazzan CPF, Oman - Level 4 Schedule - 488 04-Feb-15 A 29-Oct-16 04-Feb-15 03-Oct-16 0 COMMON AREA COMMON AREA (CMA) 465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0 PERMANENT WOR PERMANENT WORKS ( SITE PREP, PIPE SU PORTS & PIPIN G FA 465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0 CONSTRUCTION CONSTRUCTION 465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0 Civil Civil 106 25-Aug-15 A 05-Jan-16 25-Aug-15 04-Jan-16 0 PFCMACCV111A CMA - Cable Trench Excav-GWES from SS100 to 72 50% 25-Aug-15 A 17-Nov-15 25-Aug-15 22-Nov-15 0 PFCMACCV111B CMA - Cable Trench Excav-GWES from SS100 to 30 0% 26-Nov-15 31-Dec-15 28-Nov-15 03-Jan-16 2 PFCMACCV110E CMA - General Sleepers 21 0% 10-Dec-15 05-Jan-16 09-Dec-15 04-Jan-16 -1 Electrical Electrical 60 14-Oct-15 26-Dec-15 15-Oct-15 28-Dec-15 1 PFCMACEL010A CMA - U/G Ele Cable Pulling-GWES from SS100 to 60 0% 14-Oct-15 26-Dec-15 15-Oct-15 28-Dec-15 1 Piping Piping 442 02-Mar-15 A 02-Oct-16 02-Mar-15 29-Aug-16 0 Welder Qualificati Welder Qualificatios 178 02-Mar-15 A 14-Dec-15 02-Mar-15 17-Nov-15 0 PFCMACPF130AA Welder Qualifications 96 26% 02-Mar-15 A 14-Dec-15 02-Mar-15 17-Nov-15 0 PFCMACPF130AB Prepartory Works for Pipe Fabrication 45 80% 18-Aug-15 A 05-Oct-15 18-Aug-15 30-Sep-15 0 Pipe Fabrication Pipe Fabrication 306 01-Sep-15 A 02-Oct-16 27-Aug-15 29-Aug-16 -4 PFCMACPF130J ICR - A/G Piping Fabrication 139 16% 01-Sep-15 A 29-Feb-16 27-Aug-15 07-Feb-16 -4 PFCMACPF130E GP1 - A/G Piping Fabrication 281 0% 05-Oct-15 02-Oct-16 04-Oct-15 22-Aug-16 -2 PFCMACPF130A UTA - A/G Piping Fabrication 152 0% 15-Oct-15 12-Apr-16 07-Oct-15 06-Apr-16 -6 PFCMACPF130B PGA - A/G Piping Fabrication 106 0% 15-Oct-15 18-Feb-16 07-Oct-15 11-Feb-16 -6 PFCMACPF130M ECA - A/G Piping Fabrication 258 0% 21-Oct-15 13-Sep-16 19-Oct-15 22-Aug-16 -2 PFCMACPF130K LTA - A/G Piping Fabrication 245 0% 09-Nov-15 22-Sep-16 17-Nov-15 29-Aug-16 6 PFCMACPF130L CSA - A/G Piping Fabrication 169 0% 28-Nov-15 19-Jun-16 16-Dec-15 10-Jul-16 16 PFCMACPF130D PWA - A/G Piping Fabrication 109 0% 22-Dec-15 28-Apr-16 22-Dec-15 28-Apr-16 0 Pipe Supports Fab Pipe Supports Fabrication 146 21-Oct-15 12-Apr-16 21-Oct-15 19-Mar-16 1 PFCMACPF130T ICR - A/G Piping Supports Fabrication 146 0% 21-Oct-15 12-Apr-16 21-Oct-15 19-Mar-16 1 PFCMACPF130U GP1 - A/G Piping Supports Fabrication 63 0% 28-Oct-15 12-Jan-16 28-Oct-15 13-Jan-16 1 PFCMACPF130Q PGA - A/G Piping Supports Fabrication 55 0% 04-Nov-15 10-Jan-16 04-Nov-15 11-Jan-16 1 PFCMACPF130P PWA - A/G Piping Suppor ts Fabr ication 54 0% 16-Nov-15 20-Jan-16 16-Nov-15 21-Jan-16 1 PFCMACPF130R LTA - A/G Piping Supports Fabrication 66 0% 26-Nov-15 13-Feb-16 26-Nov-15 14-Feb-16 1 PFCMACPF130N UTA - A/G Piping Supports Fabrication 32 0% 05-Dec-15 11-Jan-16 05-Dec-15 12-Jan-16 1 PFCMACPF130X FLA - A/G Piping Supports Fabrication 46 0% 19-Dec-15 10-Feb-16 14-Dec-15 07-Feb-16 -3 PFCMACPF130Y CSA - A/G Piping Supports Fabrication 64 0% 22-Dec-15 06-Mar-16 21-Dec-15 06-Mar-16 0 Painitng Painitng 306 04-Oct-15 29-Oct-16 03-Oct-15 03-Oct-16 -1 Piping Piping 306 04-Oct-15 29-Oct-16 03-Oct-15 03-Oct-16 -1 PFCMACPT100G ICR - A/G Piping Painting 227 0% 04-Oct-15 18-Jul-16 03-Oct-15 17-Jul-16 -1 PFCMACPT100A UTA - A/G Piping Painting 178 0% 18-Oct-15 17-May-16 25-Oct-15 23-Apr-16 7 PFCMACPT100D PGA - A/G Piping Painting 120 0% 18-Oct-15 08-Mar-16 25-Oct-15 29-Feb-16 7 PFCMACPT100I GP1 - A/G Piping Painting 263 0% 27-Oct-15 02-Oct-16 19-Oct-15 06-Sep-16 -7 PFCMACPT100L ECA - A/G Piping Painting 251 0% 09-Nov-15 29-Sep-16 09-Nov-15 03-Oct-16 0 PFCMACPT100E LTA - A/G Piping Painting 238 0% 26-Dec-15 29-Oct-16 17-Dec-15 02-Oct-16 -7 Pipe Supports Pipe Supports 168 07-Nov-15 25-May-16 07-Nov-15 26-May-16 1 PFCMACPT100T ICR - A/G Piping Support Painting 168 0% 07-Nov-15 25-May-16 07-Nov-15 26-May-16 1 UTILITIES AREA UTILITIES AREA (UTA) 252 18-Mar-15 A 08-Feb-16 18-Mar-15 11-Feb-16 0 CONSTRUCTION CONSTRUCTION 252 18-Mar-15 A 08-Feb-16 18-Mar-15 11-Feb-16 0 Civil General Civil General 114 12-Sep-15 A 07-Feb-16 28-Sep-15 08-Feb-16 10 PFUTACCV040A UTA - Manholes, Catch Basin, Valve Pit, Drain Ditc 86 10% 12-Sep-15 A 14-Jan-16 28-Sep-15 10-Jan-16 10 PFUTACCV040B UTA - UG AOC Piping 98 0% 11-Oct-15 07-Feb-16 12-Oct-15 08-Feb-16 1 PFUTACCV070E UTA - Pipe Concrete Trench 40 0% 31-Oct-15 17-Dec-15 01-Nov-15 19-Dec-15 1 PFUTACCV050A UTA - E&I Cable Trench Excavation 18 0% 24-Nov-15 15-Dec-15 21-Nov-15 12-Dec-15 -2 Concrete Concrete 252 18-Mar-15 A 08-Feb-16 18-Mar-15 08-Feb-16 0 PFUTACCV040D UTA - Concrete TG-823003 Sump Pit 147 67% 18-Mar-15 A 14-Oct-15 18-Mar-15 30-Sep-15 0 PFUTACCV034A UTA - Z-812101/201/301/401/501- Air Compressor 75 0% 15-Oct-15 14-Jan-16 04-Oct-15 05-Jan-16 -8 PFUTACCV032A UTA - Z-815003- HP Nitrogen Compres sor Founda 64 0% 19-Oct-15 04-Jan-16 19-Oct-15 05-Jan-16 0 PFUTACCV034B UTA - Z-811006 A/B - Air Dryer Foundation 75 0% 19-Oct-15 17-Jan-16 07-Oct-15 07-Jan-16 -8 PFUTACCV032B UTA - Z-815102 - Nitrogen Compressor Foundation 59 0% 02-Nov-15 12-Jan-16 02-Nov-15 13-Jan-16 0 PFUTACCV036A UTA - EEH-813001-HP Fuel G as Heater Foundatio 27 0% 02-Nov-15 05-Dec-15 24-Oct-15 25-Nov-15 -8 PFUTACCV036D UTA - F-813001A-HP Fuel G as Filter Foundation 27 0% 02-Nov-15 05-Dec-15 01-Nov-15 03-Dec-15 -1 PFUTACCV032C UTA - Z-815202 -Nitrogen Compressor Foundation 61 0% 11-Nov-15 24-Jan-16 10-Nov-15 24-Jan-16 -1 PFUTACCV036E UTA - F-813001B-HP Fuel G as Filter Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1 PFUTACCV036J UTA - V-813001A-HP Fuel Gas KO Drum Foundati 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1 PFUTACCV036K UTA - V-813001B-HP Fuel Gas KO Drum Foundati 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1 PFUTACCV036L UTA - V-813002-LP Fuel Gas KO Drum Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1 PFUTACCV036F UTA - H-811046/47/48/49/50 Instrument Air Compr 29 0% 17-Nov-15 24-Dec-15 08-Nov-15 14-Dec-15 -8 PFUTACCV036M UTA - V-815001-Nitrogen Storage Vessel Foundati 47 0% 17-Nov-15 14-Jan-16 08-Nov-15 05-Jan-16 -8 PFUTACCV032D UTA - Z-815001A/B-Nitrogen Generation Package 59 0% 30-Nov-15 07-Feb-16 29-Nov-15 07-Feb-16 -1 PFUTACCV036I UTA - V-812002B-Instrument Air Receiver Foundat 45 0% 16-Dec-15 07-Feb-16 15-Dec-15 07-Feb-16 -1 PFUTACCV036H UTA - V-812002A-Instrument Air Receiver Foundat 40 0% 24-Dec-15 08-Feb-16 22-Dec-15 08-Feb-16 -1 Piping Piping 40 24-Nov-15 11-Jan-16 21-Nov-15 25-Jan-16 -2 PFUTACPI010A UTA - U/G Fire Water Piping 40 0% 24-Nov-15 11-Jan-16 21-Nov-15 25-Jan-16 -2 Electrical Electrical 44 15-Dec-15 06-Feb-16 12-Dec-15 11-Feb-16 -2 PFUTACEL020A UTA - U/G Electrical Cable Pulling 28 0% 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2 PFUTACEL010A UTA - Earthing 43 0% 16-Dec-15 06-Feb-16 24-Dec-15 11-Feb-16 6 Instrumentation & C Instrumentation & Controls 28 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2 PFUTACIN010A UTA - U/G Instrument Cable Pulling 28 0% 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2 INTERCONNEC INTERCONNECTING PIPERACK (ICR) 308 23-Jun-15 A 06-Aug-16 23-Jun-15 07-Aug-16 0 CONSTRUCTION CONSTRUCTION 308 23-Jun-15 A 06-Aug-16 23-Jun-15 07-Aug-16 0 Concrete Concrete 26 01-Oct-15 01-Nov-15 30-Sep-15 01-Nov-15 -1 PFICRCCV060B ICR - Crossing Concrete Trenc h 02 24 0% 01-Oct-15 29-Oct-15 30-Sep-15 29-Oct-15 -1 PFICRCCV060A ICR - Crossing Concrete Trenc h 01 24 0% 04-Oct-15 01-Nov-15 30-Sep-15 29-Oct-15 -3 PFICRCCV060C ICR - Crossing Concrete Trenc h 03 24 0% 04-Oct-15 01-Nov-15 03-Oct-15 01-Nov-15 -1 Structural Structural 148 23-Jun-15 A 09-Jan-16 23-Jun-15 25-Oct-15 0 PFICRCST010E ICR - Steel Erection - PR05 82 84% 23-Jun-15 A 20-Oct-15 23-Jun-15 05-Oct-15 0 PFICRCST010C ICR - Steel Erection - PR03 64 84% 05-Jul-15 A 27-Sep-15 05-Jul-15 17-Sep-15 0 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 er 2015 October 2015 November 2015 December 2015 Central Processing Facility (CPF) Khazzan Project Level 4 Interiam Schedule -3 MLA Data Date: 25-Sep-15 Run Date: 04-Oct-15 Project ID: JI-2024 L4-B03-16 Total Pages:6 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone Date Revision Checked Approved 25-Sep-15 L4 Interiam 3MLA Schedule - 25 Sept 2015

description

3 Month Look Ahead Schedule DD 25th Sept-2015

Transcript of 3 Month Look Ahead DD 25th Sept-2015

Page 1: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

JI-2024 - Khazzan CPF, Oman - Level 4 Schedule - B03- 3MLA DD 25 Sept-15JI-2024 - Khazzan CPF, Oman - Level 4 Schedule - B03- 3MLA DD 25 Sept-15488 04-Feb-15 A 29-Oct-16 04-Feb-15 03-Oct-16 0

COMMON AREA (CMA)COMMON AREA (CMA) 465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0

PERMANENT WORKS ( SITE PREP, PIPE SUPORTS & PIPING FAB & PAINTING)PERMANENT WORKS ( SITE PREP, PIPE SUPORTS & PIPING FAB & PAINTING)465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0

CONSTRUCTIONCONSTRUCTION 465 02-Mar-15 A 29-Oct-16 02-Mar-15 03-Oct-16 0

CivilCivil 106 25-Aug-15 A 05-Jan-16 25-Aug-15 04-Jan-16 0

PFCMACCV111A CMA - Cable Trench Excav-GWES from SS100 to North 72 50% 25-Aug-15 A 17-Nov-15 25-Aug-15 22-Nov-15 0

PFCMACCV111B CMA - Cable Trench Excav-GWES from SS100 to South 30 0% 26-Nov-15 31-Dec-15 28-Nov-15 03-Jan-16 2

PFCMACCV110E CMA - General Sleepers 21 0% 10-Dec-15 05-Jan-16 09-Dec-15 04-Jan-16 -1

ElectricalElectrical 60 14-Oct-15 26-Dec-15 15-Oct-15 28-Dec-15 1

PFCMACEL010A CMA - U/G Ele Cable Pulling-GWES from SS100 to North 60 0% 14-Oct-15 26-Dec-15 15-Oct-15 28-Dec-15 1

PipingPiping 442 02-Mar-15 A 02-Oct-16 02-Mar-15 29-Aug-16 0

Welder QualificatiosWelder Qualificatios 178 02-Mar-15 A 14-Dec-15 02-Mar-15 17-Nov-15 0

PFCMACPF130AA Welder Qualifications 96 26% 02-Mar-15 A 14-Dec-15 02-Mar-15 17-Nov-15 0

PFCMACPF130AB Prepartory Works for Pipe Fabrication 45 80% 18-Aug-15 A 05-Oct-15 18-Aug-15 30-Sep-15 0

Pipe FabricationPipe Fabrication 306 01-Sep-15 A 02-Oct-16 27-Aug-15 29-Aug-16 -4

PFCMACPF130J ICR - A/G Piping Fabricat ion 139 16% 01-Sep-15 A 29-Feb-16 27-Aug-15 07-Feb-16 -4

PFCMACPF130E GP1 - A/G Piping Fabrication 281 0% 05-Oct-15 02-Oct-16 04-Oct-15 22-Aug-16 -2

PFCMACPF130A UTA - A/G Piping Fabrication 152 0% 15-Oct-15 12-Apr-16 07-Oct-15 06-Apr-16 -6

PFCMACPF130B PGA - A/G Piping Fabrication 106 0% 15-Oct-15 18-Feb-16 07-Oct-15 11-Feb-16 -6

PFCMACPF130M ECA - A/G Piping Fabrication 258 0% 21-Oct-15 13-Sep-16 19-Oct-15 22-Aug-16 -2

PFCMACPF130K LTA - A/G Piping Fabrication 245 0% 09-Nov-15 22-Sep-16 17-Nov-15 29-Aug-16 6

PFCMACPF130L CSA - A/G Piping Fabrication 169 0% 28-Nov-15 19-Jun-16 16-Dec-15 10-Jul-16 16

PFCMACPF130D PWA - A/G Piping Fabrication 109 0% 22-Dec-15 28-Apr-16 22-Dec-15 28-Apr-16 0

Pipe Supports FabricationPipe Supports Fabrication 146 21-Oct-15 12-Apr-16 21-Oct-15 19-Mar-16 1

PFCMACPF130T ICR - A/G Piping Suppor ts Fabr icat ion 146 0% 21-Oct-15 12-Apr-16 21-Oct-15 19-Mar-16 1

PFCMACPF130U GP1 - A/G Piping Supports Fabrication 63 0% 28-Oct-15 12-Jan-16 28-Oct-15 13-Jan-16 1

PFCMACPF130Q PGA - A/G Piping Supports Fabrication 55 0% 04-Nov-15 10-Jan-16 04-Nov-15 11-Jan-16 1

PFCMACPF130P PWA - A/G Piping Suppor ts Fabr ication 54 0% 16-Nov-15 20-Jan-16 16-Nov-15 21-Jan-16 1

PFCMACPF130R LTA - A/G Piping Supports Fabrication 66 0% 26-Nov-15 13-Feb-16 26-Nov-15 14-Feb-16 1

PFCMACPF130N UTA - A/G Piping Supports Fabrication 32 0% 05-Dec-15 11-Jan-16 05-Dec-15 12-Jan-16 1

PFCMACPF130X FLA - A/G Piping Supports Fabrication 46 0% 19-Dec-15 10-Feb-16 14-Dec-15 07-Feb-16 -3

PFCMACPF130Y CSA - A/G Piping Supports Fabrication 64 0% 22-Dec-15 06-Mar-16 21-Dec-15 06-Mar-16 0

PainitngPainitng 306 04-Oct-15 29-Oct-16 03-Oct-15 03-Oct-16 -1

PipingPiping 306 04-Oct-15 29-Oct-16 03-Oct-15 03-Oct-16 -1

PFCMACPT100G ICR - A/G Piping Painting 227 0% 04-Oct-15 18-Jul-16 03-Oct-15 17-Jul-16 -1

PFCMACPT100A UTA - A/G Piping Painting 178 0% 18-Oct-15 17-May-16 25-Oct-15 23-Apr-16 7

PFCMACPT100D PGA - A/G Piping Painting 120 0% 18-Oct-15 08-Mar-16 25-Oct-15 29-Feb-16 7

PFCMACPT100I GP1 - A/G Piping Painting 263 0% 27-Oct-15 02-Oct-16 19-Oct-15 06-Sep-16 -7

PFCMACPT100L ECA - A/G Piping Painting 251 0% 09-Nov-15 29-Sep-16 09-Nov-15 03-Oct-16 0

PFCMACPT100E LTA - A/G Piping Painting 238 0% 26-Dec-15 29-Oct-16 17-Dec-15 02-Oct-16 -7

Pipe SupportsPipe Supports 168 07-Nov-15 25-May-16 07-Nov-15 26-May-16 1

PFCMACPT100T ICR - A/G Piping Suppor t Paint ing 168 0% 07-Nov-15 25-May-16 07-Nov-15 26-May-16 1

UTILITIES AREA (UTA)UTILITIES AREA (UTA) 252 18-Mar-15 A 08-Feb-16 18-Mar-15 11-Feb-16 0

CONSTRUCTIONCONSTRUCTION 252 18-Mar-15 A 08-Feb-16 18-Mar-15 11-Feb-16 0

Civil GeneralCivil General 114 12-Sep-15 A 07-Feb-16 28-Sep-15 08-Feb-16 10

PFUTACCV040A UTA - Manholes, Catch Basin, Valve Pit, Drain Ditches 86 10% 12-Sep-15 A 14-Jan-16 28-Sep-15 10-Jan-16 10

PFUTACCV040B UTA - UG AOC Piping 98 0% 11-Oct-15 07-Feb-16 12-Oct-15 08-Feb-16 1

PFUTACCV070E UTA - Pipe Concrete Trench 40 0% 31-Oct-15 17-Dec-15 01-Nov-15 19-Dec-15 1

PFUTACCV050A UTA - E&I Cable Trench Excavation 18 0% 24-Nov-15 15-Dec-15 21-Nov-15 12-Dec-15 -2

ConcreteConcrete 252 18-Mar-15 A 08-Feb-16 18-Mar-15 08-Feb-16 0

PFUTACCV040D UTA - Concrete TG-823003 Sump Pit 147 67% 18-Mar-15 A 14-Oct-15 18-Mar-15 30-Sep-15 0

PFUTACCV034A UTA - Z-812101/201/301/401/501- Air Compressors Foundation75 0% 15-Oct-15 14-Jan-16 04-Oct-15 05-Jan-16 -8

PFUTACCV032A UTA - Z-815003- HP Nitrogen Compres sor Foundation 64 0% 19-Oct-15 04-Jan-16 19-Oct-15 05-Jan-16 0

PFUTACCV034B UTA - Z-811006 A/B - Air Dryer Foundation 75 0% 19-Oct-15 17-Jan-16 07-Oct-15 07-Jan-16 -8

PFUTACCV032B UTA - Z-815102 - Nitrogen Compressor Foundation 59 0% 02-Nov-15 12-Jan-16 02-Nov-15 13-Jan-16 0

PFUTACCV036A UTA - EEH-813001-HP Fuel Gas Heater Foundation 27 0% 02-Nov-15 05-Dec-15 24-Oct-15 25-Nov-15 -8

PFUTACCV036D UTA - F-813001A-HP Fuel Gas Filter Foundation 27 0% 02-Nov-15 05-Dec-15 01-Nov-15 03-Dec-15 -1

PFUTACCV032C UTA - Z-815202 -Nitrogen Compressor Foundation 61 0% 11-Nov-15 24-Jan-16 10-Nov-15 24-Jan-16 -1

PFUTACCV036E UTA - F-813001B-HP Fuel Gas Filter Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1

PFUTACCV036J UTA - V-813001A-HP Fuel Gas KO Drum Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1

PFUTACCV036K UTA - V-813001B-HP Fuel Gas KO Drum Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1

PFUTACCV036L UTA - V-813002-LP Fuel Gas KO Drum Foundation 27 0% 14-Nov-15 16-Dec-15 15-Nov-15 17-Dec-15 1

PFUTACCV036F UTA - H-811046/47/48/49/50 Instrument Air Compressor Pack29 0% 17-Nov-15 24-Dec-15 08-Nov-15 14-Dec-15 -8

PFUTACCV036M UTA - V-815001-Nitrogen Storage Vessel Foundation 47 0% 17-Nov-15 14-Jan-16 08-Nov-15 05-Jan-16 -8

PFUTACCV032D UTA - Z-815001A/B-Nitrogen Generation Package Foundation59 0% 30-Nov-15 07-Feb-16 29-Nov-15 07-Feb-16 -1

PFUTACCV036I UTA - V-812002B-Instrument Air Receiver Foundation 45 0% 16-Dec-15 07-Feb-16 15-Dec-15 07-Feb-16 -1

PFUTACCV036H UTA - V-812002A-Instrument Air Receiver Foundation 40 0% 24-Dec-15 08-Feb-16 22-Dec-15 08-Feb-16 -1

PipingPiping 40 24-Nov-15 11-Jan-16 21-Nov-15 25-Jan-16 -2

PFUTACPI010A UTA - U/G Fire Water Piping 40 0% 24-Nov-15 11-Jan-16 21-Nov-15 25-Jan-16 -2

ElectricalElectrical 44 15-Dec-15 06-Feb-16 12-Dec-15 11-Feb-16 -2

PFUTACEL020A UTA - U/G Electrical Cable Pulling 28 0% 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2

PFUTACEL010A UTA - Earthing 43 0% 16-Dec-15 06-Feb-16 24-Dec-15 11-Feb-16 6

Instrumentation & ControlsInstrumentation & Controls 28 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2

PFUTACIN010A UTA - U/G Instrument Cable Pulling 28 0% 15-Dec-15 18-Jan-16 12-Dec-15 14-Jan-16 -2

INTERCONNECTING PIPERACK (ICR)INTERCONNECTING PIPERACK (ICR) 308 23-Jun-15 A 06-Aug-16 23-Jun-15 07-Aug-16 0

CONSTRUCTIONCONSTRUCTION 308 23-Jun-15 A 06-Aug-16 23-Jun-15 07-Aug-16 0

ConcreteConcrete 26 01-Oct-15 01-Nov-15 30-Sep-15 01-Nov-15 -1

PFICRCCV060B ICR - Crossing Concrete Trenc h 02 24 0% 01-Oct-15 29-Oct-15 30-Sep-15 29-Oct-15 -1

PFICRCCV060A ICR - Crossing Concrete Trenc h 01 24 0% 04-Oct-15 01-Nov-15 30-Sep-15 29-Oct-15 -3

PFICRCCV060C ICR - Crossing Concrete Trenc h 03 24 0% 04-Oct-15 01-Nov-15 03-Oct-15 01-Nov-15 -1

StructuralStructural 148 23-Jun-15 A 09-Jan-16 23-Jun-15 25-Oct-15 0

PFICRCST010E ICR - Steel Erection - PR05 82 84% 23-Jun-15 A 20-Oct-15 23-Jun-15 05-Oct-15 0

PFICRCST010C ICR - Steel Erection - PR03 64 84% 05-Jul-15 A 27-Sep-15 05-Jul-15 17-Sep-15 0

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015

Central Processing Facility (CPF) Khazzan Project

Level 4 Interiam Schedule -3 MLA

Data Date: 25-Sep-15 Run Date: 04-Oct-15

Project ID: JI-2024 L4-B03-16 Total Pages:6Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Baseline Milestone

Milestone

Date Revision Checked Approved

25-Sep-15 L4 Interiam 3MLA Schedule - 25 Sept 2015

Page 2: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

PFICRCST010H ICR - Steel Erection - PR08 - with extension 53 82% 03-Aug-15 A 22-Oct-15 03-Aug-15 27-Sep-15 0

PFICRCST010I ICR - Steel Erection - PR09 53 71% 12-Aug-15 A 31-Oct-15 12-Aug-15 05-Oct-15 0

PFICRCST010J ICR - Steel Erection - PR010 with loop 51 77% 23-Aug-15 A 26-Oct-15 23-Aug-15 12-Oct-15 0

PFICRCST010K ICR - Steel Erection - PR011 44 75% 23-Aug-15 A 27-Oct-15 23-Aug-15 21-Oct-15 0

PFICRCST010L ICR - Steel Erection - PR012 44 68% 31-Aug-15 A 05-Nov-15 10-Sep-15 25-Oct-15 9

PFICRCST020D ICR - Steel Erection - PR018 - Bridge 51 78% 01-Sep-15 A 10-Oct-15 19-Sep-15 21-Oct-15 15

PFICRCST010M ICR - Steel Erection - PR013 42 68% 02-Sep-15 A 05-Nov-15 13-Sep-15 25-Oct-15 9

PFICRCST010N ICR - Steel Erection - PR014 - with Platform 37 70% 08-Sep-15 A 05-Nov-15 13-Sep-15 25-Oct-15 4

PFICRCST010O ICR - Steel Erection - PR019 35 60% 08-Sep-15 A 03-Nov-15 13-Sep-15 22-Oct-15 4

PFICRCST010G ICR - Steel Erection - PR07 with loop & Platform 43 18% 09-Sep-15 A 03-Nov-15 08-Sep-15 21-Oct-15 -1

PFICRCST010P ICR - Steel Erection Miscllaneous supports 30 0% 05-Dec-15 09-Jan-16

PipingPiping 235 11-Oct-15 06-Aug-16 07-Oct-15 07-Aug-16 -3

PFICRCPI020B ICR - A/G Piping Erection on Rack - SS 200 0% 11-Oct-15 06-Jun-16 07-Oct-15 02-Jun-16 -3

PFICRCPI020A ICR - A/G Piping Erection on Rack - LTCS 192 0% 25-Oct-15 12-Jun-16 24-Oct-15 11-Jun-16 -1

PFICRCPI030A ICR - A/G Pipe Supports Installation 189 0% 03-Dec-15 01-Aug-16 03-Dec-15 02-Aug-16 1

PFICRCPI040A ICR - A/G Hydrotesting 174 0% 24-Dec-15 06-Aug-16 26-Dec-15 07-Aug-16 1

ElectricalElectrical 84 02-Nov-15 10-Feb-16 28-Dec-15 03-Apr-16 45

PFICRCEL010A ICR - Earthing 84 0% 02-Nov-15 10-Feb-16 28-Dec-15 03-Apr-16 45

FIREWATER & CHEMICAL OFFLOADING AREA (FWA)FIREWATER & CHEMICAL OFFLOADING AREA (FWA) 226 13-Apr-15 A 03-Feb-16 13-Apr-15 01-Feb-16 0

CONSTRUCTIONCONSTRUCTION 226 13-Apr-15 A 03-Feb-16 13-Apr-15 01-Feb-16 0

Civil GeneralCivil General 226 13-Apr-15 A 03-Feb-16 13-Apr-15 30-Jan-16 0

PFFWACCV050G FWA - Concrete TG 823009 Sump Pit 133 41% 13-Apr-15 A 15-Oct-15 13-Apr-15 12-Oct-15 0

PFFWACCV020M FWA - UG AOC Piping 60 0% 17-Nov-15 28-Jan-16 21-Nov-15 30-Jan-16 1

PFFWACCV020H FWA - Manholes, Catch Basin, Valve Pit, Drain Ditches 60 0% 25-Nov-15 03-Feb-16 21-Nov-15 30-Jan-16 -4

ConcreteConcrete 154 13-Jul-15 A 28-Jan-16 13-Jul-15 28-Jan-16 0

PFFWACCV040B FWA - Firewater Storage Tank Foundation (FAC1-T-610002)88 72% 13-Jul-15 A 05-Nov-15 13-Jul-15 05-Nov-15 0

PFFWACCV040A FWA - Firewater Storage Tank Foundation (FAC1-T-610001)78 78% 13-Jul-15 A 14-Oct-15 13-Jul-15 12-Oct-15 0

PFFWACCV020C FWA - Pipe Concrete Trenc h 49 0% 24-Oct-15 21-Dec-15 26-Oct-15 26-Dec-15 2

PFFWACCV050C FWA - Electrical Fire Water Pump Foundation - Z-611001 41 0% 12-Nov-15 03-Jan-16 12-Nov-15 03-Jan-16 0

PFFWACCV020D FWA - Duct Bank 31 0% 14-Nov-15 21-Dec-15 16-Nov-15 26-Dec-15 2

PFFWACCV030A FWA - Pipe Bridge 01 Foundation 28 0% 26-Nov-15 29-Dec-15 26-Nov-15 29-Dec-15 0

PFFWACCV050D FWA - Diesel Fire Water Pump Foundation- Z-611002 A/B 46 0% 29-Nov-15 23-Jan-16 29-Nov-15 23-Jan-16 0

PFFWACCV030B FWA - Pipe Bridge 02 Foundation 28 0% 09-Dec-15 11-Jan-16 10-Dec-15 12-Jan-16 1

PFFWACCV030C FWA - Pipe Bridge 03 Foundation 28 0% 09-Dec-15 11-Jan-16 10-Dec-15 12-Jan-16 1

PFFWACCV050E FWA - Fire Water Jockey Pump Foundation - Z-611003 A/B40 0% 13-Dec-15 28-Jan-16 13-Dec-15 28-Jan-16 0

EquipmentEquipment 86 21-Oct-15 01-Feb-16 14-Oct-15 01-Feb-16 -6

Mechanical - StaticMechanical - Static 86 21-Oct-15 01-Feb-16 14-Oct-15 01-Feb-16 -6

PFFWACMS010A FWA - Firewater Storage Tank Annular Plates/Bottom T-61000122 0% 21-Oct-15 16-Nov-15 14-Oct-15 09-Nov-15 -6

PFFWACMS010B FWA - Firewater Storage Tank Annular Plates/Bottom T-61000222 0% 07-Nov-15 05-Dec-15 07-Nov-15 05-Dec-15 0

PFFWACMS020A FWA - Firewater Storage Tank Shell T-610001 50 0% 16-Nov-15 17-Jan-16 09-Nov-15 10-Jan-16 -6

PFFWACMS020B FWA - Firewater Storage Tank Shell T-610002 50 0% 05-Dec-15 01-Feb-16 05-Dec-15 01-Feb-16 0

PRODUCED WATER (PWA)PRODUCED WATER (PWA) 243 22-May-15 A 02-Apr-16 23-May-15 04-Apr-16 0

CONSTRUCTIONCONSTRUCTION 243 22-May-15 A 02-Apr-16 23-May-15 04-Apr-16 0

Civil GeneralCivil General 121 17-Oct-15 08-Mar-16 14-Oct-15 12-Mar-16 -2

PFPWACCV050M PWA - Concrete TG 823011 Sump Pit 63 0% 17-Oct-15 02-Jan-16 14-Oct-15 30-Dec-15 -2

PFPWACCV050F PWA - Manholes, Catch Basin, Valve Pit, Drain Ditches 49 0% 13-Dec-15 08-Feb-16 15-Dec-15 11-Feb-16 2

PFPWACCV050E PWA - UG AOC Piping 65 0% 24-Dec-15 08-Mar-16 27-Dec-15 12-Mar-16 2

ConcreteConcrete 210 22-May-15 A 23-Feb-16 23-May-15 21-Feb-16 0

PFPWACCV010A PWA -Produced Water Buffer Tank T-440001 114 72% 22-May-15 A 09-Nov-15 23-May-15 15-Oct-15 0

PFPWACCV020A PWA - 19 Pipe Trastles Foundation 94 75% 13-Jul-15 A 28-Nov-15 13-Jul-15 30-Nov-15 0

PFPWACCV060A PWA - "T" Post Foundation 62 0% 13-Dec-15 23-Feb-16 09-Dec-15 21-Feb-16 -3

PFPWACCV046C PWA - Foundation T-440015 PWT Pack Backwash clarifires A/B48 0% 16-Dec-15 10-Feb-16 16-Dec-15 10-Feb-16 0

PFPWACCV060D PWA - GMP01,02,03,04 foundation 39 0% 21-Dec-15 04-Feb-16 22-Dec-15 07-Feb-16 1

StructuralStructural 71 07-Dec-15 29-Feb-16 10-Dec-15 02-Mar-16 2

PFPWACST020B PWA - Install 19 Tres tles Steel Structure 71 0% 07-Dec-15 29-Feb-16 10-Dec-15 02-Mar-16 2

EquipmentEquipment 132 27-Oct-15 02-Apr-16 31-Oct-15 04-Apr-16 2

Mechanical - StaticMechanical - Static 132 27-Oct-15 02-Apr-16 31-Oct-15 04-Apr-16 2

PFPWACMS010A PWA - Tanks T-440001 - Annular Plates/Bottoms 36 0% 27-Oct-15 10-Dec-15 31-Oct-15 13-Dec-15 2

PFPWACMS020A PWA - Tanks T-440001 Produced Water - Tanks Shells 96 0% 10-Dec-15 02-Apr-16 14-Dec-15 04-Apr-16 2

CENTRAL CONTROL BUILDING (CCB)CENTRAL CONTROL BUILDING (CCB) 264 26-Apr-15 A 31-Mar-16 26-Apr-15 02-Apr-16 0

CONSTRUCTIONCONSTRUCTION 264 26-Apr-15 A 31-Mar-16 26-Apr-15 02-Apr-16 0

Civil GeneralCivil General 264 26-Apr-15 A 31-Mar-16 26-Apr-15 31-Mar-16 0

PFCCBCCV010I CCB - Concrete TG-823006 Sump Pit 164 24% 26-Apr-15 A 14-Dec-15 26-Apr-15 17-Nov-15 0

PFCCBCCV010A CCB - Manholes, Catch Basin, Valve Pit, Drain Ditches 36 0% 28-Oct-15 10-Dec-15 28-Oct-15 31-Dec-15 0

PFCCBCCV010B CCB - UG AOC Piping 59 0% 28-Oct-15 07-Jan-16 07-Nov-15 25-Feb-16 8

PFCCBCCV010G CCB - Deep Found. P-945001 A/B - CPF SEWAGE LIFT PUMP90 0% 30-Nov-15 14-Mar-16 30-Nov-15 14-Mar-16 0

PFCCBCCV010H CCB - Found P-945002 A/B - GATE HOUSE SEWAGE LIFT PUMP (CPF)90 0% 17-Dec-15 31-Mar-16 17-Dec-15 31-Mar-16 0

ConcreteConcrete 63 08-Nov-15 23-Jan-16 07-Nov-15 21-Jan-16 -1

PFCCBCCV010C CCB - Duct Bank 36 0% 08-Nov-15 21-Dec-15 07-Nov-15 20-Dec-15 -1

PFCCBCCV010E CCB - Pipe concrete Trench 63 0% 08-Nov-15 23-Jan-16 07-Nov-15 21-Jan-16 -1

BuildingsBuildings 222 14-Jun-15 A 29-Mar-16 14-Jun-15 02-Apr-16 0

Building - CCB/ SS-105Building - CCB/ SS-105 222 14-Jun-15 A 29-Mar-16 14-Jun-15 02-Apr-16 0

Concrete WorksConcrete Works 214 14-Jun-15 A 20-Mar-16 14-Jun-15 27-Feb-16 0

PFCCBCCV730A CCB/SS105 - Columns / Beams 114 87% 14-Jun-15 A 16-Nov-15 14-Jun-15 31-Oct-15 0

PFCCBCCV730B CCB/SS105 - Blast Proof Walls 104 80% 05-Jul-15 A 05-Dec-15 05-Jul-15 02-Nov-15 0

PFCCBCCV730C CCB/SS105 - Staircases/Steps/Ramps 56 0% 11-Oct-15 19-Dec-15 16-Sep-15 29-Nov-15 -17

PFCCBCCV740A CCB/SS105 - Roof Slab & Parapet walls above Roof 124 0% 24-Oct-15 20-Mar-16 12-Oct-15 27-Feb-16 -9

PFCCBCCV760A CCB/SS105 - Transformer /EDG Foundations & Walls 65 0% 12-Dec-15 27-Feb-16 12-Dec-15 27-Feb-16 0

Blockworks & Miscellaneous CivilBlockworks & Miscellaneous Civil 67 04-Nov-15 25-Jan-16 05-Nov-15 25-Jan-16 1

PFCCBCCV750E CCB/SS105 - Block work 42 0% 04-Nov-15 27-Dec-15 05-Nov-15 28-Dec-15 1

PFCCBCCV750F CCB/SS105 - Doors/ Louvers/ Metal works 42 0% 06-Dec-15 25-Jan-16 06-Dec-15 25-Jan-16 0

HVACHVAC 94 06-Dec-15 26-Mar-16 08-Dec-15 27-Mar-16 1

PFCCBCHV700A CCB/SS105 - HVAC Duct Works 94 0% 06-Dec-15 26-Mar-16 08-Dec-15 27-Mar-16 1

MEP WorksMEP Works 111 21-Nov-15 29-Mar-16 15-Nov-15 02-Apr-16 -4

PFCCBCPI700A CCB/SS105 - Electrical First installation (conduits/tracking)102 0% 21-Nov-15 20-Mar-16 15-Nov-15 15-Mar-16 -4

PFCCBCPI700B CCB/SS105 - Mechanical First installation (Plumbing,...) 97 0% 07-Dec-15 29-Mar-16 09-Dec-15 02-Apr-16 2

Building - LaboratoryBuilding - Laboratory 43 02-Dec-15 23-Jan-16 05-Dec-15 24-Jan-16 2

Concrete WorksConcrete Works 43 02-Dec-15 23-Jan-16 05-Dec-15 24-Jan-16 2

PFCCBCCV500A LAB - Footing and ring foundation 43 0% 02-Dec-15 23-Jan-16 05-Dec-15 24-Jan-16 2

Building - Gate HouseBuilding - Gate House 36 10-Dec-15 23-Jan-16 05-Dec-15 16-Jan-16 -5

Concrete WorksConcrete Works 36 10-Dec-15 23-Jan-16 05-Dec-15 16-Jan-16 -5

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015

Page 3: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

PFCCBCCV600A Gate House - Footing and ring foundation 36 0% 10-Dec-15 23-Jan-16 05-Dec-15 16-Jan-16 -5

POWER GENERATION AREA (PGA)POWER GENERATION AREA (PGA) 407 04-Feb-15 A 14-Jul-16 04-Feb-15 18-Jul-16 0

CONSTRUCTIONCONSTRUCTION 407 04-Feb-15 A 14-Jul-16 04-Feb-15 18-Jul-16 0

Civil GeneralCivil General 233 05-Apr-15 A 03-Feb-16 05-Apr-15 16-Jan-16 0

PFPGACCV050B PGA - Concrete Works Deep Found. Pit/ Sump TG-823010159 39% 05-Apr-15 A 15-Nov-15 05-Apr-15 21-Oct-15 0

PFPGACCV020B PGA - Manholes, Catch Basin, Valve Pit, Drain Ditches 64 40% 20-Aug-15 A 22-Nov-15 20-Aug-15 26-Oct-15 0

PFPGACCV060A PGA - Elect. and Inst. Buried Trench - Excavation 56 80% 24-Aug-15 A 28-Nov-15 24-Aug-15 31-Oct-15 0

PFPGACCV020C PGA - UG AOC Piping 98 5% 22-Sep-15 A 03-Feb-16 15-Sep-15 16-Jan-16 -6

PFPGACCV020F PGA - Concrete Works Deep Found. GTG Wash Drain Pit60 0% 05-Oct-15 16-Dec-15 19-Sep-15 05-Dec-15 -10

ConcreteConcrete 288 04-Feb-15 A 08-Feb-16 04-Feb-15 09-Feb-16 0

PFPGACCV030A PGA - GAS TURBINE GENERATORS 03 Foundation 197 86% 04-Feb-15 A 14-Oct-15 04-Feb-15 18-Oct-15 0

PFPGACCV030B PGA - GAS TURBINE GENERATORS 02 Foundation 196 90% 04-Feb-15 A 14-Oct-15 04-Feb-15 15-Oct-15 0

PFPGACCV030C PGA - GAS TURBINE GENERATORS 01 Foundation 195 90% 04-Feb-15 A 15-Oct-15 04-Feb-15 15-Oct-15 0

PFPGACCV030D PGA - GAS TURBINE GENERATORS 04 Foundation 196 86% 04-Feb-15 A 26-Oct-15 04-Feb-15 18-Oct-15 0

PFPGACCV030E PGA - GAS TURBINE GENERATORS 05 Foundation 198 87% 04-Feb-15 A 26-Oct-15 04-Feb-15 20-Oct-15 0

PFPGACCV010B PGA - Pipe Rack 02 Foundation 114 95% 05-May-15 A 14-Oct-15 05-May-15 06-Oct-15 0

PFPGACCV010C PGA - Pipe Rack 03 Foundation 116 95% 05-May-15 A 14-Oct-15 05-May-15 07-Oct-15 0

PFPGACCV010D PGA - Pipe Rack 04 Foundation 117 95% 05-May-15 A 14-Oct-15 05-May-15 12-Oct-15 0

PFPGACCV070A PGA - V-806001 - Diesel Storage Vessel 83 30% 20-Jul-15 A 01-Nov-15 21-Jul-15 25-Oct-15 0

PFPGACCV010A PGA - Pipe Rack 01 Foundation 45 81% 16-Aug-15 A 12-Oct-15 16-Aug-15 12-Oct-15 0

PFPGACCV065B PGA - Duct Bank 86 25% 10-Sep-15 A 27-Dec-15 29-Aug-15 14-Dec-15 -11

PFPGACCV065A PGA - Elect & Inst Concrete Trench 60 0% 24-Oct-15 04-Jan-16 17-Oct-15 10-Jan-16 -6

PFPGACCV090A PGA - Pipe Concrete Trench 70 0% 16-Nov-15 08-Feb-16 16-Nov-15 09-Feb-16 0

PFPGACCV010K PGA - Grade Platform Ladder GM04/05 39 0% 15-Dec-15 30-Jan-16 15-Dec-15 31-Jan-16 1

PFPGACCV035A PGA - FAC1-F-806001A - Diesel Filter Foundation 25 0% 15-Dec-15 13-Jan-16 15-Dec-15 14-Jan-16 1

Steel StructureSteel Structure 62 12-Oct-15 28-Dec-15 12-Oct-15 02-Jan-16 0

PFPGACST010A PGA - Steel Erect ion Pipe Rack - PR01 44 0% 12-Oct-15 06-Dec-15 12-Oct-15 05-Dec-15 0

PFPGACST010B PGA - Steel Erect ion Pipe Rack - PR02 41 0% 15-Oct-15 05-Dec-15 12-Oct-15 02-Dec-15 -2

PFPGACST010C PGA - Steel Erect ion Pipe Rack - PR03 39 0% 22-Oct-15 08-Dec-15 22-Oct-15 09-Dec-15 0

PFPGACST010D PGA - Steel Erect ion Pipe Rack - PR04 40 0% 09-Nov-15 28-Dec-15 12-Nov-15 02-Jan-16 3

BuildingBuilding 229 07-Jun-15 A 30-Mar-16 07-Jun-15 09-Apr-16 0

SUBSTATION / LER 100SUBSTATION / LER 100 229 07-Jun-15 A 30-Mar-16 07-Jun-15 09-Apr-16 0

Concrete WorksConcrete Works 121 07-Jun-15 A 01-Dec-15 07-Jun-15 12-Nov-15 0

PFPGACCV730C SS/LER100 - Staircases/Steps 88 8% 07-Jun-15 A 25-Oct-15 07-Jun-15 29-Sep-15 0

PFPGACCV760A SS/LER100 - Transformer Foundations / Walls 68 80% 25-Aug-15 A 01-Dec-15 25-Aug-15 29-Oct-15 0

PFPGACCV760B SS/LER100 - Chiller Foundations 38 0% 08-Oct-15 25-Nov-15 28-Sep-15 12-Nov-15 -9

Blockworks & Miscellaneous CivilBlockworks & Miscellaneous Civil 112 10-Aug-15 A 29-Dec-15 10-Aug-15 06-Jan-16 0

PFPGACCV750A SS/LER100 - External/Internal Block Works 57 80% 10-Aug-15 A 26-Oct-15 10-Aug-15 15-Oct-15 0

PFPGACCV750P SS/LER100 - External/Internal Plastering 40 0% 07-Oct-15 26-Nov-15 21-Sep-15 12-Nov-15 -10

PFPGACCV740B SS/LER100 - Roof Screed & Waterproofing 40 0% 27-Oct-15 14-Dec-15 19-Oct-15 06-Dec-15 -7

PFPGACCV750B SS/LER100 - Wall / base Screed & 1st Coat Paint 40 0% 28-Oct-15 15-Dec-15 31-Oct-15 17-Dec-15 2

PFPGACCV750E SS/LER100 - Doors / Louvres / Metalwork 25 0% 03-Nov-15 05-Dec-15 01-Nov-15 08-Dec-15 -2

PFPGACCV750G SS/LER100 - Base Skirting Screeding 30 0% 03-Nov-15 10-Dec-15 01-Nov-15 08-Dec-15 -2

PFPGACCV750N SS/LER100 - Cable Basement - Gravel Fill 14 0% 12-Dec-15 29-Dec-15 20-Dec-15 06-Jan-16 7

HVACHVAC 85 02-Nov-15 11-Feb-16 02-Nov-15 11-Feb-16 0

PFPGACHV700B SS/LER100 - HVAC Ducting - Fab & Install 85 0% 02-Nov-15 11-Feb-16 02-Nov-15 11-Feb-16 0

PFPGACHV710B SS/LER100 - HVAC Chilled Water Piping Installation 75 0% 14-Nov-15 11-Feb-16 14-Nov-15 11-Feb-16 0

MEP WorksMEP Works 56 22-Sep-15 A 05-Dec-15 27-Sep-15 13-Dec-15 1

PFPGACCV750C SS/LER100 - Electric First Fixing (Conduits/Trunking) 40 10% 22-Sep-15 A 28-Nov-15 27-Sep-15 14-Nov-15 1

PFPGACCV750D SS/LER100 - Mechanical First Fixing ( Piping) 35 0% 11-Oct-15 24-Nov-15 29-Sep-15 10-Nov-15 -10

PFPGACCV750F SS/LER100 - Electromechanical Final Fittings & Accessories40 0% 17-Oct-15 05-Dec-15 25-Oct-15 13-Dec-15 7

Finishing WorksFinishing Works 60 06-Dec-15 15-Feb-16 09-Dec-15 18-Feb-16 3

PFPGACCV750I SS/LER100 - Switchgear Room - Rubber Matt Flooring & Final Wall Paint45 0% 06-Dec-15 28-Jan-16 09-Dec-15 01-Feb-16 3

PFPGACCV750L SS/LER100 - Battery Room - Tiling & Final Wall Paint 45 0% 12-Dec-15 03-Feb-16 15-Dec-15 07-Feb-16 3

PFPGACCV750J SS/LER100 - UPS Room - Epoxy Floor Finishing & Final Wall Paint45 0% 17-Dec-15 09-Feb-16 21-Dec-15 13-Feb-16 3

PFPGACCV750H SS/LER100 - EPDMS Room - Vinyl Sheet Flooring & Final Wall Paint45 0% 24-Dec-15 15-Feb-16 28-Dec-15 18-Feb-16 3

ElectricalElectrical 101 22-Oct-15 21-Feb-16 31-Oct-15 22-Feb-16 7

PFPGACEL770A SS100 - Cable Tray Ins tallation 50 0% 22-Oct-15 22-Dec-15 31-Oct-15 31-Dec-15 7

PFPGACEL780A SS100 - Electrical Cable Pulling 50 0% 28-Oct-15 29-Dec-15 05-Nov-15 06-Jan-16 7

PFPGACEL760A SS100 - Lighting & Misc. Works 65 0% 06-Dec-15 21-Feb-16 07-Dec-15 22-Feb-16 1

PFPGACEL700B SS100 - Trans formers (8 No.) Installation 38 0% 14-Dec-15 28-Jan-16 17-Dec-15 01-Feb-16 3

PFPGACEL700A SS100 - Bus Ducts 33 0% 20-Dec-15 28-Jan-16 24-Dec-15 01-Feb-16 3

Instrumentation & ControlsInstrumentation & Controls 99 06-Dec-15 30-Mar-16 14-Dec-15 09-Apr-16 7

PFPGACIN750A SS/LER100 - Instrument Cables Pulling 99 0% 06-Dec-15 30-Mar-16 14-Dec-15 09-Apr-16 7

EquipmentEquipment 127 17-Oct-15 15-Mar-16 29-Aug-15 12-Mar-16 -37

Mechanical - RotatingMechanical - Rotating 127 17-Oct-15 15-Mar-16 29-Aug-15 12-Mar-16 -37

HLPFPGACMR010A PGA - Install Z-864001/2/3 3 0% 17-Oct-15 19-Oct-15 29-Aug-15 01-Sep-15 -37

PFPGACMR010A PGA - Install GT Generator Package 1 100 0% 20-Oct-15 16-Feb-16 17-Oct-15 13-Feb-16 -3

HLPFPGACMR040A PGA - Install Z-86400 4 & 5 3 0% 20-Oct-15 22-Oct-15 01-Sep-15 05-Sep-15 -37

PFPGACMR020A PGA - Install GT Generator Package 2 100 0% 22-Oct-15 18-Feb-16 19-Oct-15 15-Feb-16 -3

PFPGACMR030A PGA - Install GT Generator Package 3 100 0% 03-Nov-15 01-Mar-16 31-Oct-15 27-Feb-16 -3

PFPGACMR040A PGA - Install GT Generator Package 4 100 0% 05-Nov-15 03-Mar-16 02-Nov-15 29-Feb-16 -3

PFPGACMR050A PGA - Install GT Generator Package 5 100 0% 17-Nov-15 15-Mar-16 14-Nov-15 12-Mar-16 -3

PipingPiping 179 04-Nov-15 05-Jun-16 07-Nov-15 05-Jun-16 3

PFPGACPI010A PGA - U/G Fire Water Piping 60 0% 04-Nov-15 17-Jan-16 07-Nov-15 27-Jan-16 3

PFPGACPI050A PGA - A/G Piping Erection - Around Equipment FOR First 3 GTGs - LTCS120 0% 16-Jan-16 05-Jun-16 16-Jan-16 05-Jun-16 0

ElectricalElectrical 209 24-Oct-15 14-Jul-16 17-Oct-15 14-Jul-16 -6

PFPGACEL040A PGA - U/G Electrical Cable Pulling 209 0% 24-Oct-15 14-Jul-16 17-Oct-15 14-Jul-16 -6

PFPGACEL010A PGA - Earthing 59 0% 24-Dec-15 01-Mar-16 24-Dec-15 01-Mar-16 0

PFPGACEL020A PGA - Cable Trays / Conduits 99 0% 24-Feb-16 02-Jul-16 25-Feb-16 02-Jul-16 0

Instrumentation & ControlsInstrumentation & Controls 196 04-Nov-15 11-Jul-16 02-Nov-15 18-Jul-16 -2

PFPGACIN020A PGA - U/G Ins trument Cable Pulling 163 0% 04-Nov-15 16-May-16 02-Nov-15 18-Jul-16 -2

PFPGACIN010A PGA - Instrument Cable Trays 99 0% 28-Feb-16 11-Jul-16 29-Feb-16 11-Jul-16 0

FLARE AREA (FLA)FLARE AREA (FLA) 240 29-Apr-15 A 07-Mar-16 29-Apr-15 07-Mar-16 0

CONSTRUCTIONCONSTRUCTION 240 29-Apr-15 A 07-Mar-16 29-Apr-15 07-Mar-16 0

Civil GeneralCivil General 129 29-Apr-15 A 25-Oct-15 29-Apr-15 25-Oct-15 0

PFFLACCV020C FLA - Deep Founds Pits/Sump V-824001 130 85% 29-Apr-15 A 25-Oct-15 29-Apr-15 25-Oct-15 0

ConcreteConcrete 136 27-Sep-15 07-Mar-16 01-Oct-15 07-Mar-16 4

PFFLACCV010C FLA - Pipe Trestle 01 Foundation 30 0% 27-Sep-15 01-Nov-15 01-Oct-15 05-Nov-15 4

PFFLACCV010D FLA - Pipe Trestle 02 Foundation 30 0% 29-Sep-15 03-Nov-15 01-Oct-15 05-Nov-15 2

PFFLACCV010E FLA - Pipe Trestles 03,04,05,06 Foundation 30 0% 06-Oct-15 10-Nov-15 08-Oct-15 12-Nov-15 2

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015

Page 4: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

PFFLACCV010F FLA - Pipe Trestles 07,08,09,10,11,12 Foundation 24 0% 14-Oct-15 10-Nov-15 17-Oct-15 12-Nov-15 2

PFFLACCV010G FLA - Pipe Trestles 13,14,15 Foundation 24 0% 21-Oct-15 17-Nov-15 24-Oct-15 22-Nov-15 2

PFFLACCV080C FLA - Duct Bank 49 0% 25-Oct-15 22-Dec-15 26-Oct-15 24-Dec-15 1

PFFLACCV010H FLA - Pipe Trestles 16,17,18,19,20,21,22,23 Foundation 24 0% 28-Oct-15 26-Nov-15 24-Oct-15 22-Nov-15 -4

PFFLACCV050A FLA - Sonic Flare Stack - HP flare + LT Fare + Derrick Foundation Z-50200156 0% 29-Oct-15 05-Jan-16 07-Nov-15 13-Jan-16 7

PFFLACCV010I FLA - Pipe Trestles 24,25,26,27 Foundation 24 0% 04-Nov-15 03-Dec-15 31-Oct-15 29-Nov-15 -4

PFFLACCV010J FLA - Pipe Trestles 28,29,30 Foundation 36 0% 07-Nov-15 20-Dec-15 31-Oct-15 13-Dec-15 -6

PFFLACCV030B FLA - LP and LLP Blower Fnd 28 0% 11-Nov-15 15-Dec-15 14-Nov-15 17-Dec-15 2

PFFLACCV010K FLA - Pipe Trestles 31,32 Foundation 36 0% 14-Nov-15 28-Dec-15 07-Nov-15 20-Dec-15 -6

PFFLACCV080G FLA - Pipe Concrete Trench 52 0% 14-Nov-15 16-Jan-16 14-Nov-15 16-Jan-16 0

PFFLACCV010L FLA - Pipe Trestles 33,34,35,36,37 Foundation 24 0% 23-Nov-15 20-Dec-15 14-Nov-15 13-Dec-15 -6

PFFLACCV010M FLA - Pipe Trestles 38,39,40 Foundation 27 0% 25-Nov-15 28-Dec-15 23-Nov-15 26-Dec-15 -2

PFFLACCV030G FLA - HT-LT Flare KO Drum Blower 501003 24 0% 28-Nov-15 26-Dec-15 30-Nov-15 28-Dec-15 2

PFFLACCV010O FLA - Pipe Trestles 51,52,53 Foundation 30 0% 28-Nov-15 03-Jan-16 23-Nov-15 29-Dec-15 -4

PFFLACCV030C FLA - HP Flare KO Drum Foundation V-501003 24 0% 28-Nov-15 26-Dec-15 30-Nov-15 28-Dec-15 2

PFFLACCV010N FLA - Pipe Trestles 41,42,43,44,45,46,47,48,49,50 Foundation24 0% 28-Nov-15 26-Dec-15 23-Nov-15 20-Dec-15 -4

PFFLACCV030D FLA - LP Flare KO Drum Foundation V-511002 24 0% 01-Dec-15 29-Dec-15 03-Dec-15 31-Dec-15 2

PFFLACCV030H FLA - LP Flare KO Drum Blower 511002 24 0% 03-Dec-15 31-Dec-15 06-Dec-15 03-Jan-16 2

PFFLACCV030E FLA - LLP Flare KO Drum Foundation V-521001 24 0% 05-Dec-15 02-Jan-16 07-Dec-15 04-Jan-16 2

PFFLACCV030F FLA - LT Flare KO Drum Foundation V-561001 24 0% 08-Dec-15 05-Jan-16 10-Dec-15 07-Jan-16 2

PFFLACCV030J FLA - LLP Flare KO Drum Blower 521001 24 0% 16-Dec-15 13-Jan-16 19-Dec-15 16-Jan-16 2

PFFLACCV080E FLA - Ingition Panles LP, LLP, HP 24 0% 16-Dec-15 13-Jan-16 19-Dec-15 16-Jan-16 2

PFFLACCV050B FLA - Flare Stack - LP Flare Derrick Foundation Z-50200267 0% 20-Dec-15 07-Mar-16 20-Dec-15 07-Mar-16 0

StructuralStructural 72 21-Nov-15 13-Feb-16 21-Nov-15 13-Feb-16 0

PFFLACST010A FLA - Install Pipe Trestle - TR01 20 0% 21-Nov-15 13-Dec-15 21-Nov-15 13-Dec-15 0

PFFLACST010B FLA - Install Pipe Trestle - TR02 21 0% 30-Nov-15 24-Dec-15 30-Nov-15 24-Dec-15 0

PFFLACST010C FLA - Install Pipe Trestles - TR 03,04,05,06 43 0% 07-Dec-15 26-Jan-16 07-Dec-15 26-Jan-16 0

PFFLACST010D FLA - Install Pipe Trestles - TR 07,08,09,10,11,12 52 0% 14-Dec-15 13-Feb-16 14-Dec-15 13-Feb-16 0

PFFLACST020G FLA - Install LP and LLP Blower Steel 27 0% 16-Dec-15 18-Jan-16 19-Dec-15 20-Jan-16 2

PFFLACST010E FLA - Install Pipe Trestles - TR 13,14,15 45 0% 20-Dec-15 10-Feb-16 20-Dec-15 10-Feb-16 0

LIQUID TRAIN (LTA)LIQUID TRAIN (LTA) 279 02-Mar-15 A 23-Feb-16 02-Mar-15 23-Feb-16 0

CONSTRUCTIONCONSTRUCTION 279 02-Mar-15 A 23-Feb-16 02-Mar-15 23-Feb-16 0

Civil GeneralCivil General 263 02-Mar-15 A 04-Feb-16 02-Mar-15 23-Feb-16 0

PFLTACCV025A LTA - Deep Found. Liquid train closed drain drum V-824002167 95% 02-Mar-15 A 21-Oct-15 02-Mar-15 21-Sep-15 0

PFLTACCV025B LTA - Concrete TG-823007 Sump Pit 165 90% 08-Mar-15 A 21-Oct-15 08-Mar-15 30-Sep-15 0

PFLTACCV020C LTA - Manholes, Catch Basin, Valve Pit, Drain Ditches 70 0% 22-Oct-15 16-Jan-16 14-Oct-15 07-Jan-16 -7

PFLTACCV020D LTA - UG AOC Piping 80 0% 01-Nov-15 04-Feb-16 28-Oct-15 23-Feb-16 -3

PFLTACCV030A LTA - E&I Cable Trench Excavation 28 0% 21-Dec-15 23-Jan-16 24-Dec-15 26-Jan-16 3

ConcreteConcrete 156 25-Jul-15 A 03-Feb-16 25-Jul-15 13-Feb-16 0

PFLTACCV048B LTA - Stabiliser Feed/ Bottoms Exchanger H-233001 Foundation69 60% 25-Jul-15 A 02-Nov-15 25-Jul-15 17-Oct-15 0

PFLTACCV040A LTA - Found- Condensate Stabiliser -V-233001 60 23% 04-Aug-15 A 31-Oct-15 04-Aug-15 18-Oct-15 0

PFLTACCV049G LTA - Stabiliser Overhead Compressor KO Drum -V-309001 Foundation59 12% 05-Aug-15 A 01-Nov-15 05-Aug-15 21-Oct-15 0

PFLTACCV046A LTA - Desalter Package -Z-232001 Foundation 59 24% 06-Aug-15 A 01-Nov-15 06-Aug-15 15-Oct-15 0

PFLTACCV048A LTA - Wash Water Exchanger H-232001 Foundation 62 12% 08-Aug-15 A 05-Nov-15 08-Aug-15 11-Oct-15 0

PFLTACCV045A LTA - Water clarifier/deoiler -Z-223006 Foundation 113 12% 22-Aug-15 A 21-Jan-16 12-Dec-15 13-Feb-16 88

PFLTACCV045B LTA - Paraffin Inhibitor Injection -Z-246003 Foundation 113 12% 22-Aug-15 A 10-Jan-16 29-Nov-15 10-Jan-16 78

PFLTACCV010A LTA - Pipe Rack PR01 Foundation 45 12% 23-Aug-15 A 20-Oct-15 23-Aug-15 15-Oct-15 0

PFLTACCV010B LTA - Pipe Rack PR02 Foundation 50 12% 23-Aug-15 A 24-Oct-15 23-Aug-15 18-Oct-15 0

PFLTACCV010C LTA - Pipe Rack PR03 Foundation 75 12% 25-Aug-15 A 29-Nov-15 28-Sep-15 29-Nov-15 25

PFLTACCV010D LTA - Pipe Rack PR04 Foundation 57 29% 25-Aug-15 A 16-Nov-15 25-Aug-15 22-Oct-15 0

PFLTACCV044A LTA - FLASH GAS COMP Z-305001 A/B Foundation 71 12% 26-Aug-15 A 06-Dec-15 26-Aug-15 23-Nov-15 0

PFLTACCV044B LTA - FLASH GAS COMP Z-305002 A/B Foundation 77 12% 26-Aug-15 A 13-Dec-15 26-Aug-15 26-Nov-15 0

PFLTACCV044C LTA - STABILISER OVERHEAD COMP C-309001 Foundation65 12% 26-Aug-15 A 28-Nov-15 30-Sep-15 03-Jan-16 26

PFLTACCV020B LTA - Pipe concrete Trench 40 0% 26-Nov-15 13-Jan-16 26-Nov-15 13-Jan-16 0

PFLTACCV049N LTA - Antifoam dosing Pack Z-851002 35 0% 24-Dec-15 03-Feb-16 26-Dec-15 04-Feb-16 1

PFLTACCV049A LTA - Flash Gas Comp Luboil Cooler -V-305001A Foundation28 0% 24-Dec-15 26-Jan-16 26-Dec-15 27-Jan-16 1

PFLTACCV049B LTA - Flash Gas Comp. interstage KO drum -V-305002A Foundation24 0% 24-Dec-15 A 21-Jan-16 26-Dec-15 23-Jan-16 1

PFLTACCV049C LTA - Flash Gas Comp Scrubber -V-305003A Foundation 24 0% 24-Dec-15 21-Jan-16 26-Dec-15 23-Jan-16 1

StructuralStructural 99 20-Oct-15 16-Feb-16 21-Oct-15 27-Jan-16 1

PFLTACST010A LTA - Install Pipe Rack - PR 01 35 0% 20-Oct-15 02-Dec-15 21-Oct-15 03-Dec-15 1

PFLTACST010B LTA - Install Pipe Rack - PR 02 50 0% 08-Nov-15 09-Jan-16 09-Nov-15 22-Dec-15 1

PFLTACST010C LTA - Install Pipe Rack - PR 03 65 0% 29-Nov-15 14-Feb-16 29-Nov-15 16-Jan-16 0

PFLTACST010D LTA - Install Pipe Rack - PR 04 59 0% 08-Dec-15 16-Feb-16 08-Dec-15 27-Jan-16 0

BuildingBuilding 231 01-Apr-15 A 31-Dec-15 01-Apr-15 01-Feb-16 0

Building - SS-103 / LER 103Building - SS-103 / LER 103 231 01-Apr-15 A 31-Dec-15 01-Apr-15 01-Feb-16 0

Concrete WorksConcrete Works 231 01-Apr-15 A 31-Dec-15 01-Apr-15 01-Feb-16 0

PFLTACCV720A SS/LER103 - Ground Slab 145 96% 01-Apr-15 A 26-Oct-15 01-Apr-15 30-Sep-15 0

PFLTACCV730B SS/LER103 - Walls 115 80% 01-Jun-15 A 22-Nov-15 01-Jun-15 27-Oct-15 0

PFLTACCV730A SS/LER103 - Columns / Beams 76 90% 14-Jun-15 A 15-Oct-15 14-Jun-15 08-Oct-15 0

PFLTACCV730C SS/LER103 - Staircases/Steps 127 39% 25-Aug-15 A 30-Dec-15 25-Aug-15 01-Feb-16 0

PFLTACCV740A SS/LER103 - Roof Slab & Parapet Walls 63 32% 19-Sep-15 A 31-Dec-15 10-Oct-15 26-Dec-15 14

EquipmentEquipment 40 09-Jan-16 23-Feb-16 28-Nov-15 14-Jan-16 -34

Mechanical - StaticMechanical - Static 40 09-Jan-16 23-Feb-16 28-Nov-15 14-Jan-16 -34

PFLTACMS020A LTA - Install V-233001 - Condensate Stabiliser 40 0% 09-Jan-16 23-Feb-16 28-Nov-15 14-Jan-16 -34

GAS PROCESSING TRAIN 1 (GP1)GAS PROCESSING TRAIN 1 (GP1) 250 21-Mar-15 A 08-Feb-16 21-Mar-15 23-Feb-16 0

CONSTRUCTIONCONSTRUCTION 250 21-Mar-15 A 08-Feb-16 21-Mar-15 23-Feb-16 0

Civil GeneralCivil General 248 21-Mar-15 A 07-Feb-16 21-Mar-15 23-Feb-16 0

PFGP1CCV025B GP1 - Concrete TG -823008 Sump Pit 157 70% 21-Mar-15 A 22-Oct-15 21-Mar-15 14-Oct-15 0

PFGP1CCV025A GP1 - Deep Found. Pits/Sump TG-311109/ V-824101 140 90% 15-Apr-15 A 03-Nov-15 15-Apr-15 26-Oct-15 0

PFGP1CCV027A GP1 - E&I Cable Trench Excavation 28 30% 20-Sep-15 A 08-Dec-15 10-Dec-15 13-Jan-16 64

PFGP1CCV020F GP1 - Manholes, Catch Basin, Valve Pit, Drain Ditches 58 0% 22-Oct-15 02-Jan-16 21-Oct-15 31-Dec-15 -2

PFGP1CCV020G GP1 - UG AOC Piping 82 0% 29-Oct-15 07-Feb-16 28-Oct-15 23-Feb-16 -2

ConcreteConcrete 188 27-May-15 A 02-Feb-16 27-May-15 31-Jan-16 0

PFGP1CCV010E GP1 - Pipe Rack 05 Foundation 94 95% 27-May-15 A 11-Oct-15 27-May-15 21-Sep-15 0

PFGP1CCV010A GP1 - Pipe Rack 01 Foundation 85 95% 07-Jun-15 A 11-Oct-15 07-Jun-15 21-Sep-15 0

PFGP1CCV010B GP1 - Pipe Rack 02 Foundation 87 95% 08-Jun-15 A 11-Oct-15 08-Jun-15 21-Sep-15 0

PFGP1CCV010C GP1 - Pipe Rack 03 Foundation 58 95% 22-Jul-15 A 11-Oct-15 22-Jul-15 21-Sep-15 0

PFGP1CCV010D GP1 - Pipe Rack 04 Foundation 59 95% 22-Jul-15 A 11-Oct-15 22-Jul-15 05-Oct-15 0

PFGP1CCV020B GP1 - Elect. Concrete Trench 82 17% 28-Aug-15 A 07-Dec-15 11-Nov-15 06-Jan-16 59

PFGP1CCV020I GP1 - Pipe Concrete Trenc h 66 0% 27-Sep-15 15-Dec-15 15-Sep-15 09-Dec-15 -5

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015

Page 5: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

PFGP1CCV040A GP1 - Feed Gas Trim Cooler Foundation H-323102 /03 18 0% 08-Oct-15 29-Oct-15 11-Oct-15 01-Nov-15 2

PFGP1CCV070C GP1 - Equip. Supp. Structure - TS3 Foundation 45 0% 10-Oct-15 05-Dec-15 10-Oct-15 05-Dec-15 0

PFGP1CCV020A GP1 - Duct Bank 32 0% 11-Oct-15 21-Nov-15 16-Sep-15 29-Oct-15 -16

PFGP1CCV040B GP1 - Gas-Gas Exchanger Foundation H-333101 18 0% 11-Oct-15 01-Nov-15 11-Oct-15 01-Nov-15 0

PFGP1CCV070B GP1 - Equip. Supp.Structure -TS2 Foundation 29 0% 25-Oct-15 30-Nov-15 25-Oct-15 30-Nov-15 0

PFGP1CCV070A GP1 - Equip. Supp. Structure - TS1 Foundation 28 0% 25-Oct-15 29-Nov-15 25-Oct-15 29-Nov-15 0

PFGP1CCV040E GP1 - Dry Gas Scrubber Foundation V-311108A 40 0% 29-Oct-15 17-Dec-15 15-Oct-15 03-Dec-15 -12

PFGP1CCV040N GP1 - Galycol Dehydration Pack. Z-311101 Foundation 69 0% 29-Oct-15 21-Jan-16 05-Nov-15 28-Jan-16 6

PFGP1CCV030A GP1 - Gas Recovery Compressor Foundation Z-552101 56 0% 08-Nov-15 16-Jan-16 07-Nov-15 14-Jan-16 -1

PFGP1CCV040O GP1 - Gas Recovery Compr Discharge Foundation V-55210321 0% 08-Nov-15 05-Dec-15 05-Nov-15 02-Dec-15 -2

PFGP1CCV040F GP1 - Dry Gas Scrubber Foundation V-311108B 40 0% 10-Nov-15 30-Dec-15 11-Nov-15 31-Dec-15 1

PFGP1CCV040G GP1 - Feed Gas Ko Drum Foundation V-323101 43 0% 10-Nov-15 03-Jan-16 11-Nov-15 04-Jan-16 1

PFGP1CCV040P GP1 - Gas Mercury Removal Bed Foundation V-323102 47 0% 10-Nov-15 07-Jan-16 11-Nov-15 09-Jan-16 1

PFGP1CCV040C GP1 - Gas-Lts Liquids Exchanger Foundation H-333103 21 0% 12-Nov-15 08-Dec-15 12-Nov-15 08-Dec-15 0

PFGP1CCV040D GP1 - Treated Gas Fines Filter F-323101 Foundation 21 0% 12-Nov-15 08-Dec-15 12-Nov-15 08-Dec-15 0

PFGP1CCV040H GP1 - Expander Suction Scrubber Foundation V-333101 40 0% 14-Nov-15 03-Jan-16 15-Nov-15 04-Jan-16 1

PFGP1CCV040I GP1 - Low Temperature Separator Foundation V-333102 47 0% 17-Nov-15 14-Jan-16 21-Nov-15 16-Jan-16 1

PFGP1CCV040J GP1 - Wet Gas Coalesing Filter Foundation V-311101A 45 0% 17-Nov-15 12-Jan-16 21-Nov-15 13-Jan-16 1

PFGP1CCV040K GP1 - Wet Gas Coalesing Filter Foundation V-311101B 45 0% 17-Nov-15 12-Jan-16 21-Nov-15 13-Jan-16 1

PFGP1CCV040L GP1 - Glycol Contactor Package Foundation Z-311102 52 0% 17-Nov-15 20-Jan-16 21-Nov-15 21-Jan-16 1

PFGP1CCV040M GP1 - Gas Recovery Comp Lub oil cooler Z-552101 Foundation35 0% 17-Nov-15 31-Dec-15 21-Nov-15 02-Jan-16 1

PFGP1CCV070D GP1 - Grade Platform 01 - GMP01 37 0% 14-Dec-15 27-Jan-16 12-Dec-15 25-Jan-16 -3

PFGP1CCV070E GP1 - Grade Platform 02 - GMP02 42 0% 14-Dec-15 02-Feb-16 12-Dec-15 31-Jan-16 -3

StructuralStructural 98 12-Oct-15 08-Feb-16 06-Oct-15 08-Feb-16 -5

PFGP1CST010A GP1 - Install PR01 with Pltf at Top 30 0% 12-Oct-15 16-Nov-15 06-Oct-15 10-Nov-15 -5

PFGP1CST010B GP1 - Install PR02 with Pltf at Top 23 0% 15-Oct-15 11-Nov-15 19-Oct-15 15-Nov-15 4

PFGP1CST010C GP1 - Install PR03 with Pltf at Top 30 0% 17-Oct-15 22-Nov-15 26-Oct-15 02-Dec-15 9

PFGP1CST010D GP1 - Install PR04 with Pltf at Top 34 0% 28-Oct-15 08-Dec-15 26-Oct-15 07-Dec-15 -1

PFGP1CST010E GP1 - Install PR05 with Pltf at Top 23 0% 04-Nov-15 03-Dec-15 02-Nov-15 01-Dec-15 -1

PFGP1CST040A GP1 - Install Equip. Supp. Structure.- TS1 45 0% 16-Dec-15 08-Feb-16 16-Dec-15 08-Feb-16 0

PFGP1CST040B GP1 - Install Equip. Supp. Structure.- TS2 37 0% 16-Dec-15 28-Jan-16 16-Dec-15 28-Jan-16 0

BuildingBuilding 201 10-May-15 A 01-Feb-16 10-May-15 03-Feb-16 0

Building - SS-101 / LER 101Building - SS-101 / LER 101 201 10-May-15 A 01-Feb-16 10-May-15 03-Feb-16 0

Concrete WorksConcrete Works 201 10-May-15 A 01-Feb-16 10-May-15 03-Feb-16 0

PFGP1CCV710A SS/LER101 - Elevated Concrete up to EL +103.15 108 58% 10-May-15 A 21-Oct-15 10-May-15 10-Oct-15 0

PFGP1CCV730B SS/LER101 - Walls 82 20% 06-Jul-15 A 08-Nov-15 06-Jul-15 26-Oct-15 0

PFGP1CCV730A SS/LER101 - Columns / Beams 109 13% 06-Jul-15 A 12-Dec-15 06-Jul-15 14-Dec-15 0

PFGP1CCV720A SS/LER101 - Ground Slab 76 24% 22-Jul-15 A 08-Nov-15 22-Jul-15 26-Oct-15 0

PFGP1CCV720B SS/LER101 - Cable Basement Slab at EL +3.15 42 0% 22-Oct-15 12-Dec-15 11-Oct-15 14-Dec-15 -9

PFGP1CCV740A SS/LER101 - Roof Slab & Parapet Walls 67 0% 11-Nov-15 01-Feb-16 14-Nov-15 03-Feb-16 2

EXPORT COMPRESSION & HOT OIL AREA (ECA)EXPORT COMPRESSION & HOT OIL AREA (ECA) 275 28-Mar-15 A 16-Mar-16 28-Mar-15 23-Mar-16 0

CONSTRUCTIONCONSTRUCTION 275 28-Mar-15 A 16-Mar-16 28-Mar-15 23-Mar-16 0

Civil GeneralCivil General 241 22-Apr-15 A 02-Mar-16 22-Apr-15 23-Mar-16 0

PFECACCV090G ECA- Concrete TG-823002 Sump Pit 154 74% 22-Apr-15 A 17-Nov-15 22-Apr-15 03-Nov-15 0

PFECACCV090H ECA- Deep Founds Pits/Sump Drum V-804002 / V-804006139 66% 10-May-15 A 17-Nov-15 10-May-15 03-Nov-15 0

PFECACCV017G ECA - Manholes, Catc h Basin, Valve Pit, Drain Ditches 66 0% 27-Oct-15 16-Jan-16 26-Oct-15 26-Jan-16 0

PFECACCV017H ECA - UG AOC Piping 94 0% 10-Nov-15 02-Mar-16 09-Nov-15 23-Mar-16 0

ConcreteConcrete 275 28-Mar-15 A 16-Mar-16 28-Mar-15 15-Mar-16 0

PFECACCV035A ECA- Export Gas Compressor Foundation C-342301 136 90% 28-Mar-15 A 10-Oct-15 28-Mar-15 20-Sep-15 0

PFECACCV035B ECA- Export Gas Compressor Foundation CGT-342301 135 90% 28-Mar-15 A 08-Oct-15 28-Mar-15 20-Sep-15 0

PFECACCV030A ECA- Export Gas Compressor Foundation C-342101 134 90% 30-Mar-15 A 10-Oct-15 30-Mar-15 21-Sep-15 0

PFECACCV030B ECA- Export Gas Compressor Foundation C-342201 135 90% 30-Mar-15 A 11-Oct-15 30-Mar-15 16-Sep-15 0

PFECACCV030C ECA- Export Gas Compressor Foundation CGT-342101 133 90% 30-Mar-15 A 08-Oct-15 30-Mar-15 21-Sep-15 0

PFECACCV030D ECA- Export Gas Compressor Foundation CGT-342201 132 90% 30-Mar-15 A 07-Oct-15 30-Mar-15 16-Sep-15 0

PFECACCV010B ECA - Pipe Track 02 Foundation 102 92% 05-May-15 A 08-Oct-15 05-May-15 29-Sep-15 0

PFECACCV010C ECA - Pipe Track 03 Foundation 98 92% 10-May-15 A 08-Oct-15 10-May-15 30-Sep-15 0

PFECACCV010A ECA - Pipe Track 01 Foundation 97 92% 11-May-15 A 08-Oct-15 11-May-15 29-Sep-15 0

PFECACCV015A ECA - Pipe Track 06 Foundation 81 92% 29-May-15 A 07-Oct-15 30-May-15 30-Sep-15 0

PFECACCV025C ECA - Export Gas Suction Scrubber Foundation V-34220189 83% 01-Jun-15 A 20-Oct-15 01-Jun-15 05-Oct-15 0

PFECACCV070B ECA- Equip Supp Struc TS2 Export Air Cooler H-342201 Foundation83 87% 01-Jun-15 A 12-Oct-15 01-Jun-15 11-Oct-15 0

PFECACCV025B ECA - Export Gas Suction Scrubber Foundation V-34210175 83% 21-Jun-15 A 20-Oct-15 21-Jun-15 05-Oct-15 0

PFECACCV070A ECA- Equip Supp Struc TS1 Export Air Cooler H-342101 Foundation74 87% 21-Jun-15 A 20-Oct-15 21-Jun-15 06-Oct-15 0

PFECACCV025D ECA - Export Gas Suction Scrubber Foundation V-34230180 12% 01-Jul-15 A 02-Nov-15 01-Jul-15 19-Oct-15 0

PFECACCV070D ECA- Equip Supp Struc TS4 GTD 342101 Filter House Foundation92 84% 05-Jul-15 A 21-Nov-15 05-Jul-15 26-Oct-15 0

PFECACCV070C ECA- Equip Supp Struc TS3 Export Air Cooler H-342301 Foundation76 88% 21-Jul-15 A 25-Oct-15 21-Jul-15 12-Oct-15 0

PFECACCV070F ECA- Pltf Foundation around Comp C-342101 83 62% 22-Jul-15 A 16-Nov-15 22-Jul-15 22-Oct-15 0

PFECACCV070G ECA- Pltf Foundation around Comp C-342201 83 61% 22-Jul-15 A 16-Nov-15 22-Jul-15 22-Oct-15 0

PFECACCV010D ECA - Pipe Track 04 & 05 Foundation 78 92% 29-Jul-15 A 16-Nov-15 29-Jul-15 24-Oct-15 0

PFECACCV015B ECA - Pipe Finger Rack 07 & 08 Foundation 77 50% 17-Aug-15 A 05-Dec-15 17-Aug-15 19-Dec-15 0

PFECACCV015C ECA - Pipe Finger Rack 09 & 10 Foundation 73 12% 17-Aug-15 A 30-Nov-15 17-Aug-15 17-Dec-15 0

PFECACCV017J ECA - Pipe Concrete Trench 65 0% 15-Oct-15 03-Jan-16 14-Oct-15 02-Jan-16 0

PFECACCV017A ECA - Duct Bank 55 0% 21-Oct-15 28-Dec-15 19-Oct-15 26-Dec-15 -1

PFECACCV017B ECA - Elect. Concrete Trench 69 0% 25-Oct-15 17-Jan-16 24-Oct-15 16-Jan-16 0

PFECACCV130D ECA- Water Mist Fire Fighting Skid 21 0% 25-Oct-15 21-Nov-15 22-Oct-15 15-Nov-15 -2

PFECACCV130E ECA- Portable Gas Turbine Water Wash System Skid 21 0% 25-Oct-15 21-Nov-15 22-Oct-15 15-Nov-15 -2

PFECACCV020B ECA- Deep Founds Hot Oil Heater Package Including Heater Stack Z-80400198 0% 26-Oct-15 20-Feb-16 27-Oct-15 22-Feb-16 2

PFECACCV025E ECA - Mineral Luboil - Air Cooler for 3 Comp Foundation 45 0% 02-Nov-15 28-Dec-15 28-Oct-15 22-Dec-15 -4

PFECACCV025A ECA- Filters Foundation 804001, 3042001A/B,804002 21 0% 21-Nov-15 14-Dec-15 15-Nov-15 12-Dec-15 -2

PFECACCV130C ECA- Mineral Lube Oil Skid Skid 57 0% 21-Nov-15 27-Jan-16 21-Nov-15 26-Jan-16 0

PFECACCV070E ECA- Equip Supp Struc TS5 GTD 342201/ 342301 Foundation49 0% 30-Nov-15 27-Jan-16 30-Nov-15 27-Jan-16 0

PFECACCV021A ECA - Waste Heat Recovery Unit Foundation H-804001 81 0% 12-Dec-15 16-Mar-16 10-Dec-15 15-Mar-16 0

PFECACCV015E ECA - Pipe Finger Rack 11 & 12 Foundation 41 0% 19-Dec-15 06-Feb-16 17-Dec-15 04-Feb-16 -1

PFECACCV130F ECA- Exhust system Export Comp for 3 Comp Foundation21 0% 20-Dec-15 14-Jan-16 20-Dec-15 13-Jan-16 0

Steel StructureSteel Structure 58 22-Nov-15 30-Jan-16 22-Nov-15 14-Feb-16 0

PFECACST010A ECA - Install Pipe Track 01 35 0% 22-Nov-15 03-Jan-16 22-Nov-15 02-Jan-16 0

PFECACST010B ECA - Install Pipe Track 02 35 0% 02-Dec-15 13-Jan-16 02-Dec-15 12-Jan-16 0

PFECACST010C ECA - Install Pipe Track 03 35 0% 02-Dec-15 13-Jan-16 02-Dec-15 12-Jan-16 0

PFECACST010D ECA - Install Pipe Track 04 & 05 42 0% 10-Dec-15 30-Jan-16 10-Dec-15 14-Feb-16 0

BuildingBuilding 263 02-Apr-15 A 07-Mar-16 02-Apr-15 06-Mar-16 0

Building - SS-104 / LER 104Building - SS-104 / LER 104 263 02-Apr-15 A 07-Mar-16 02-Apr-15 06-Mar-16 0

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015

Page 6: 3 Month Look Ahead DD 25th Sept-2015

Activity ID Activity Name Original

Duration

Physical %Complete

Start Finish BL Project Start

BL ProjectFinish

Variance -BL ProjectStart Date

Concrete WorksConcrete Works 263 02-Apr-15 A 07-Mar-16 02-Apr-15 06-Mar-16 0

PFECACCV710A SS/LER104 - Elevated Concrete up to EL +3.150 130 99% 02-Apr-15 A 08-Oct-15 02-Apr-15 21-Sep-15 0

PFECACCV720A SS/LER104 - Ground Slab 122 70% 19-Apr-15 A 17-Oct-15 19-Apr-15 05-Oct-15 0

PFECACCV730A SS/LER104 - Columns / Beams 86 72% 14-Jun-15 A 28-Oct-15 14-Jun-15 23-Nov-15 0

PFECACCV730B SS/LER104 - Walls 73 42% 14-Jul-15 A 01-Nov-15 14-Jul-15 11-Nov-15 0

PFECACCV720B SS/LER104 - Cable Basement Slab at EL +3.150 47 67% 16-Aug-15 A 26-Oct-15 16-Aug-15 27-Oct-15 0

PFECACCV740A SS/LER104 - Roof Slab & Parapet Walls 46 0% 29-Oct-15 24-Dec-15 18-Oct-15 24-Dec-15 -10

PFECACCV730C SS/LER104 - Staircases/Steps 42 0% 24-Dec-15 10-Feb-16 24-Dec-15 10-Feb-16 0

PFECACCV760A SS/LER104 - Transformer Foundations 62 0% 26-Dec-15 07-Mar-16 24-Dec-15 06-Mar-16 -1

PFECACCV760B SS/LER104 - Chiller Foundations 42 0% 26-Dec-15 11-Feb-16 24-Dec-15 10-Feb-16 -1

EquipmentEquipment 1 24-Dec-15 24-Dec-15 24-Dec-15 24-Dec-15 0

Mechanical - RotatingMechanical - Rotating 1 24-Dec-15 24-Dec-15 24-Dec-15 24-Dec-15 0

HLPFECAMS010D ECA - CGT-342101 1 0% 24-Dec-15 24-Dec-15 24-Dec-15 24-Dec-15 0

SLUG CATCHER AREA (SCA)SLUG CATCHER AREA (SCA) 283 13-Apr-15 A 11-Apr-16 13-Apr-15 07-Apr-16 0

CONSTRUCTIONCONSTRUCTION 283 13-Apr-15 A 11-Apr-16 13-Apr-15 07-Apr-16 0

Civil GeneralCivil General 217 13-Apr-15 A 24-Jan-16 13-Apr-15 03-Feb-16 0

PFSCACCV045A SCA - Concrete TG-823001 Sump Pit 142 84% 13-Apr-15 A 04-Nov-15 13-Apr-15 10-Oct-15 0

PFSCACCV060A SCA - Deep Founds Pits/Sump V-824005 136 44% 29-May-15 A 14-Dec-15 30-May-15 17-Nov-15 0

PFSCACCV040I SCA - Manholes, Catc h Basin, Valve Pit, Drain Ditches 56 5% 20-Sep-15 A 15-Dec-15 14-Oct-15 20-Dec-15 16

PFSCACCV040K SCA - UG AOC Piping 65 7% 20-Sep-15 A 14-Jan-16 04-Nov-15 03-Feb-16 34

PFSCACCV040A SCA - Elec t. and Inst. Buried Trench - Excavation 40 0% 08-Dec-15 24-Jan-16 08-Dec-15 24-Jan-16 0

ConcreteConcrete 245 28-May-15 A 11-Apr-16 28-May-15 07-Apr-16 0

PFSCACCV020A SCA - Pipe Track 01 Foundation 94 90% 28-May-15 A 24-Oct-15 28-May-15 05-Nov-15 0

PFSCACCV020B SCA - Pipe Track 02 Foundation 94 90% 28-May-15 A 22-Oct-15 28-May-15 12-Oct-15 0

PFSCACCV020C SCA - Pipe Track 03 Foundation 94 90% 28-May-15 A 22-Oct-15 28-May-15 10-Oct-15 0

PFSCACCV020D SCA - Pipe Track 04 Foundation 96 90% 28-May-15 A 25-Oct-15 28-May-15 18-Oct-15 0

PFSCACCV040C SCA - Pipe Concrete Trench 65 0% 25-Oct-15 12-Jan-16 19-Oct-15 05-Jan-16 -6

PFSCACCV040J SCA - Duct Bank 65 0% 26-Oct-15 13-Jan-16 28-Oct-15 14-Jan-16 1

PFSCACCV025B SCA - Slug Catcher Foundation Z-213001 125 0% 14-Nov-15 11-Apr-16 09-Nov-15 07-Apr-16 -3

PFSCACCV040D SCA - Water Soluble antifoam Shelter Foundations 24 0% 13-Mar-16 10-Apr-16 12-Dec-15 10-Jan-16 -78

Steel StructureSteel Structure 56 15-Nov-15 23-Jan-16 16-Nov-15 23-Jan-16 0

PFSCACST010A SCA - Install Pipe Track 01 25 0% 15-Nov-15 16-Dec-15 16-Nov-15 16-Dec-15 0

PFSCACST010B SCA - Install Pipe Track 02 44 0% 17-Nov-15 11-Jan-16 21-Nov-15 11-Jan-16 0

PFSCACST010C SCA - Install Pipe Track 03 25 0% 24-Dec-15 23-Jan-16 24-Dec-15 23-Jan-16 0

INLET FACILITIES AREA (IFA)INLET FACILITIES AREA (IFA) 56 01-Dec-15 04-Feb-16 02-Dec-15 09-Mar-16 1

CONSTRUCTIONCONSTRUCTION 56 01-Dec-15 04-Feb-16 02-Dec-15 09-Mar-16 1

Civil GeneralCivil General 56 01-Dec-15 04-Feb-16 02-Dec-15 09-Mar-16 1

PFIFACCV010J IFA - UG AOC Piping 56 0% 01-Dec-15 04-Feb-16 02-Dec-15 09-Mar-16 1

ConcreteConcrete 52 06-Dec-15 04-Feb-16 02-Dec-15 01-Feb-16 -3

PFIFACCV020A IFA - Pipe Track 01 Foundation - 8 Fnd 52 0% 06-Dec-15 04-Feb-16 02-Dec-15 01-Feb-16 -3

CONDENSATE STORAGE & EXPORT AREA (CSA)CONDENSATE STORAGE & EXPORT AREA (CSA) 213 13-May-15 A 18-Feb-16 13-May-15 20-Feb-16 0

CONSTRUCTIONCONSTRUCTION 213 13-May-15 A 18-Feb-16 13-May-15 20-Feb-16 0

Civil GeneralCivil General 194 29-May-15 A 11-Feb-16 30-May-15 10-Feb-16 0

PFCSACCV050A CSA - Deep Founds Pits/Sump V-824003 142 48% 29-May-15 A 29-Nov-15 30-May-15 28-Nov-15 0

PFCSACCV050N CSA - Concrete TG-823004 Sump Pit 63 0% 30-Nov-15 11-Feb-16 28-Nov-15 10-Feb-16 -1

PFCSACCV050G CSA - Manholes, Catc h Basin, Valve Pit, Drain Ditches 43 0% 03-Dec-15 23-Jan-16 05-Dec-15 24-Jan-16 1

ConcreteConcrete 213 13-May-15 A 18-Feb-16 13-May-15 20-Feb-16 0

PFCSACCV012A CSA - Tank T-246001 Foundations 119 95% 13-May-15 A 08-Nov-15 13-May-15 14-Oct-15 0

PFCSACCV012B CSA - Tank T-246002 Foundations 115 95% 19-May-15 A 08-Nov-15 19-May-15 14-Oct-15 0

PFCSACCV010B CSA - Pipe Treastl 01,2,3,4,5,6 Foundation 82 22% 13-Jul-15 A 11-Nov-15 13-Jul-15 18-Oct-15 0

PFCSACCV010C CSA - Pipe Treastl 07,8,9,10,11,12 Foundation 88 22% 13-Jul-15 A 21-Nov-15 13-Jul-15 25-Oct-15 0

PFCSACCV010D CSA - Pipe Treastl 13,14,15,16,17,18 Foundation 35 0% 06-Oct-15 17-Nov-15 19-Sep-15 04-Nov-15 -11

PFCSACCV010E CSA - Pipe Treastl 19,20,21,22,23,24 Foundation 35 0% 21-Oct-15 03-Dec-15 07-Oct-15 21-Nov-15 -11

PFCSACCV020A CSA - condensated Degassing drum Foundation V-24600136 0% 30-Nov-15 11-Jan-16 28-Nov-15 10-Jan-16 -1

PFCSACCV010F CSA - Pipe Treastl 25,26,27,28,29 Foundation 35 0% 30-Nov-15 10-Jan-16 30-Nov-15 10-Jan-16 0

PFCSACCV050K CSA - Pipe Concrete Trench 66 0% 03-Dec-15 18-Feb-16 05-Dec-15 20-Feb-16 1

PFCSACCV010A CSA - Sleepers 55 0% 08-Dec-15 10-Feb-16 08-Dec-15 10-Feb-16 0

EquipmentEquipment 51 07-Dec-15 06-Feb-16 07-Dec-15 06-Feb-16 0

Mechanical - StaticMechanical - Static 51 07-Dec-15 06-Feb-16 07-Dec-15 06-Feb-16 0

PFCSACMS010A CSA - Condens ate Storage Tank Annular Plates/Bottoms T-24600143 0% 07-Dec-15 27-Jan-16 07-Dec-15 27-Jan-16 0

PFCSACMS010B CSA - Condens ate Storage Tank Annular Plates/Bottoms T-24600239 0% 21-Dec-15 06-Feb-16 21-Dec-15 06-Feb-16 0

GAS PROCESSING TRAIN 2 (GP2)GAS PROCESSING TRAIN 2 (GP2) 281 07-Apr-15 A 02-Apr-16 07-Apr-15 18-Apr-16 0

CONSTRUCTIONCONSTRUCTION 281 07-Apr-15 A 02-Apr-16 07-Apr-15 18-Apr-16 0

Civil GeneralCivil General 281 07-Apr-15 A 02-Apr-16 07-Apr-15 18-Apr-16 0

PFGP2CCV025B GP2 - Concrete TG-823005 Sump pit 175 70% 07-Apr-15 A 23-Nov-15 07-Apr-15 12-Nov-15 0

PFGP2CCV025A GP2 - Deep Found. Pits/Sump V-311209/V824201 124 84% 30-May-15 A 17-Nov-15 30-May-15 04-Nov-15 0

PFGP2CCV020F GP2 - Manholes, Catch Basin, Valve Pit, Drain Ditches 60 0% 09-Dec-15 17-Feb-16 07-Dec-15 15-Feb-16 -2

PFGP2CCV020G GP2 - UG AOC Piping 88 0% 21-Dec-15 02-Apr-16 21-Dec-15 18-Apr-16 0

ConcreteConcrete 147 08-Aug-15 A 07-Feb-16 08-Aug-15 07-Feb-16 0

PFGP2CCV010B GP2 - Pipe Rack 02 Foundation 60 89% 08-Aug-15 A 03-Nov-15 08-Aug-15 05-Nov-15 0

PFGP2CCV010C GP2 - Pipe Rack 03 Foundation 61 89% 08-Aug-15 A 05-Nov-15 08-Aug-15 25-Oct-15 0

PFGP2CCV010E GP2 - Pipe Rack 05 Foundation 63 27% 08-Aug-15 A 07-Nov-15 08-Aug-15 25-Nov-15 0

PFGP2CCV010D GP2 - Pipe Rack 04 Foundation 63 70% 08-Aug-15 A 07-Nov-15 08-Aug-15 17-Nov-15 0

PFGP2CCV010A GP2 - Pipe Rack 01 Foundation 60 82% 09-Aug-15 A 04-Nov-15 09-Aug-15 26-Nov-15 0

PFGP2CCV020I GP2 - Pipe Concrete Trenc h 65 0% 22-Nov-15 06-Feb-16 21-Nov-15 04-Feb-16 -1

PFGP2CCV040B GP2 - Gas Exchanger Foundation H-333101 28 0% 01-Dec-15 04-Jan-16 30-Nov-15 03-Jan-16 -1

PFGP2CCV040C GP2 - Gas-Lts Liquids Exchanger Foundation H-333203 20 0% 15-Dec-15 09-Jan-16 14-Dec-15 07-Jan-16 -1

PFGP2CCV070C GP2 - Equip. Supp. Struc Foundation TS3 40 0% 19-Dec-15 04-Feb-16 19-Dec-15 04-Feb-16 0

PFGP2CCV030A GP2 - Gas Recovery Compressor Foundation Z-552201 42 0% 19-Dec-15 07-Feb-16 19-Dec-15 07-Feb-16 0

PFGP2CCV040L GP2 - Glycol Contactor Package Z-311202 27 0% 19-Dec-15 20-Jan-16 19-Dec-15 20-Jan-16 0

PFGP2CCV040N GP2 - Glycol Dehydration Pack. Z311201 Foundation 40 0% 19-Dec-15 04-Feb-16 19-Dec-15 04-Feb-16 0

BuildingBuilding 214 09-May-15 A 15-Feb-16 09-May-15 16-Feb-16 0

Building - SS102 / LER102Building - SS102 / LER102 214 09-May-15 A 15-Feb-16 09-May-15 16-Feb-16 0

Concrete WorksConcrete Works 214 09-May-15 A 15-Feb-16 09-May-15 16-Feb-16 0

PFGP2CCV710A SS/LER102 - Elevated Concrete up to EL +3.15 123 73% 09-May-15 A 07-Nov-15 09-May-15 29-Oct-15 0

PFGP2CCV730A SS/LER102 - Columns / Beams 145 22% 05-Jul-15 A 23-Jan-16 05-Jul-15 14-Jan-16 0

PFGP2CCV730B SS/LER102 - Walls 100 13% 06-Jul-15 A 30-Nov-15 06-Jul-15 29-Nov-15 0

PFGP2CCV720A SS/LER102 - Ground Slab 71 24% 28-Jul-15 A 07-Nov-15 28-Jul-15 05-Nov-15 0

PFGP2CCV720B SS/LER102 - Cable Basement Slab at EL +3.15 42 0% 08-Nov-15 29-Dec-15 31-Oct-15 20-Dec-15 -7

PFGP2CCV740A SS/LER102 - Roof Slab & Parapet Walls 73 0% 21-Nov-15 15-Feb-16 22-Nov-15 16-Feb-16 1

19 26 03 10 17 24 31 07 14 21 28 05 12 19 26

September 2015 October 2015 November 2015 December 2015