3. earthen roads 30 aug
-
Upload
prathamesh-kulkarni -
Category
Engineering
-
view
241 -
download
3
Transcript of 3. earthen roads 30 aug
General Terms used in Earthwork of Roads
1. Borrow Pits2. Balancing Earthwork3. Lead & Lift4. Spoil Bank
Borrow PitsSmall pits dug parallel to the road alignment
on both sides of the road formation to draw extra earth required to fill in embankment.
Spoil BankExtra earth excavated and to be dumped on
the road sides in road in cutting.Dumped in regular shape for future use.
Balancing EarthworkWhile constructing road, it is desirable for a
segment of road, that the quantity of earthwork in cutting and embankment should be nearly equal if the soil available is good for the use.
If possible, keeping in mind the limiting values of gradients and curves, the alignment is so fixed to have the equal quantity of earthwork in cutting and banking.
This is known as balancing earthwork.
Lead & LiftLead: Horizontal distance travelled by the
earth to be moved for banking or dumping.Lift : Vertical distance travelled by the
earthwork after excavating.
Construction Procedure for Earthen RoadPreparation of Sub-Grade: Arranging sub-
grade in proper gradient & camber.The sub-grade is rolled & watered to have
OMC & compacted to MDD.Over it, a layer of soil 10cm thick is sprayed,
rolled, & finished to have required camber & gradient.
4-5 days curing.Opening to traffic.Watering for 10 days after opening to traffic.
Sub-Grade
Soil Layer 10 cm Thick
Marking Road Levels & BoundariesMarking the centre line of alignment on
ground with the help of theodolite.Marking carriageway, shoulder, berms,
borrow pits & road boundaries.Putting pegs & clearing stakes in the sides &
cleaning the area within the clearing stakes.
Construction StepsClearing & Grubbing: It includes removing
any unwanted material i.e. tree roots, grass, loose soil, Preparing the leveled surface
Stripping off the top of soil to avoid the plant growth on the road.
Excavation: if the existing material is not suitable for the road, other suitable material is dumped in the excavated portion.
Embankment preparation
Sheep Foot Roller