279A METRO 0.5bis1.5 V1.1 EN · If all hopper loaders are full and no material required is pending...
Transcript of 279A METRO 0.5bis1.5 V1.1 EN · If all hopper loaders are full and no material required is pending...
Operating Manual
Hopper loaderMETRO 0.5 to 1.5
CE
11/2005 279A-00.0.EN V1.1096/05
3 Technical specificationsSpecifications METRO 0.5 to 1.5
12 Edition: November 2005
3.3 Specifications
3.3.1 Dimensions of the hopper loaders
Fig. 3.2 – Dimensions of the hopper loaders
Size METRO H** 0.5 METRO H** 1.5 METRO M** 0.5 METRO M** 1.5
A 456 mm
(17.8 inch)
549 mm
(21.4 inch)
450 mm
(17.5 inch)
543 mm
(21.1 inch)
B 302 mm
(11.8 inch)
395 mm
(15.4 inch)
296 mm
(11.5 inch)
389 mm
(15.1 inch)
Edition: November 2005 13
METRO 0.5 to 1.5Technical specifications 3
Specifications
3.3.2 Dimensions of the hopper loaders
Fig. 3.3 – Dimensions of the hopper loaders
Size METRO HC/J* METRO HP* METRO MC/J* METRO MP*
C 102 mm
(4.0 inch)
D 253 mm
(9.8 inch)
232 mm
(9.0 inch)
242 mm
(9.4 inch)
221 mm
(8.6 inch)
E 317 mm
(12.4 inch)
317 mm
(12.4 inch)
295 mm
(11.5 inch)
306 mm
(11.9 inch)
3 Technical specificationsSpecifications METRO 0.5 to 1.5
14 Edition: November 2005
3.3.3 Dimensions (connections) - hopper loaders
3.3.4 Dimensions of flange METRO H/M**
[F] Ø material inlet[G] Ø vacuum pipe
Fig. 3.4 – Dimensions of the hopper loaders
Option Size METRO 0.5 METRO 1.5
1F 38 mm (1.5 inch)
G 45 mm (1.7 inch)
2F 45 mm (1.7 inch)
G 45 mm (1.7 inch)
Fig. 3.5 – Dimensions of flange METRO H/M**
Size METRO H** 0.5 METRO H** 1.5 METRO M** 0.5 METRO M** 1.5
A 215 mm (8.3 inch) 100 mm (3.9 inch)
B 7 mm (0.3 inch 9 mm (3.5 inch)
C 171 mm (6.7 inch) 47 mm (1.8 inch)
D 195 mm (7.6 inch) 75 mm (2.9 inch)
METRO H** METRO M**
Edition: November 2005 15
METRO 0.5 to 1.5Technical specifications 3
Specifications
3.3.5 Weight and other data
3.3.6 Electrics and pneumatics
METRO H** 0.5 METRO H** 1.5 METRO M** 0.5 METRO M** 1.5
Weight 4.5 kg
(9.9 lbs)
5.0 kg
(11.0 lbs)
2.9 kg
(6.4 lbs)
3.4 kg
(7.5 lbs)
Capacity 0.5 l
(0.02 cft)
1.5 l
(0.05 cft)
0.5 l
(0.02 cft)
1.5 l
(0.05 cft)
Mesh size of filter 500µ
METRO 0.5 METRO 1.5
Control voltageP-loader/C-loader 24 V DC
Control voltageJ-loader 120 V AC
Compressed air connection
4–6 bar (60–90 psi)
Edition: November 2005 17
METRO 0.5 to 1.5Transport and setup 4
Mounting hopper loader
4 Transport and setup
4.1 Mounting hopper loader
Position the flange seal [3] on the machine or drying bin.
Position the hopper loader on the machine or drying bin.
Connect the hopper loader tightly to the machine or drying bin as shown above. Note the different design of discharge and machine module.
Discharge module Machine module
Fig. 4.1 – Attaching hopper loader
[1] Hexagon-headed screw[2] Washer[3] Flange seal
[4] Hexagon nut self-locking[5] Spring washer[6] Hexagonal nut
4 Transport and setupConnections METRO 0.5 to 1.5
18 Edition: November 2005
4.2 Connections
4.2.1 Compressed air connectionConnect the air hose (PU tube Ø 4x1 mm (Ø 0.16x0.04")) to the compressed air connection on the unit [1].
The operating pressure must be 0.4–0.6 MPa (4–6 bar (60–90 psi)).
[1] Compressed air connectionFig. 4.2 – Connecting compressed air METRO *C/J*
[1] Compressed air connectionFig. 4.3 – Connecting compressed air METRO *P*
Note
The operating pressure must not fall below 0.4 MPa (4 bar (60 psi)).
Edition: November 2005 19
METRO 0.5 to 1.5Transport and setup 4
Connections
4.2.2 Fastening material/vacuum hose
Note the flow direction (PU tubes only, optional), (see figure 4.4). Incorrect installation direction may influence the transport output.
Remove the wire spiral [1] from the tube and bend it inwards to make it contact the hopper loader.
Slide the material/vacuum hose on to the connection on the hopper loader and fasten the hose with a suitable hose band clip (see Figure 4.5).
CAUTION!
MATERIAL DAMAGE!Incorrectly attached material tubes cause transport problems and damage to the hop-per loader.
Lay out material/vacuum hose to the hopper loader with a sufficiently wide curve.Ground the hose.
[1] Flow direction with PU tubesFig. 4.4 – Flow direction
[1] Wire spiralFig. 4.5 – Grounding material/vacuum hose
4 Transport and setupConnections METRO 0.5 to 1.5
20 Edition: November 2005
4.2.3 Electrical connection
Connecting the control cable
The electrical power is supplied from the controller via the controller cable (see figure 4.64.7).
CAUTION!
MATERIAL DAMAGE!Radiant heat and hot surfaces may damage the controller cable.
Lay out the controller cable so it will not be damaged by the heat of downstream units (hot surfaces or radiant heat)!
[1] Control cable connectionFig. 4.6 – Connecting control cable METRO *C/J*
[1] Control cable connectionFig. 4.7 – Connecting control cable METRO *P*
Edition: November 2005 21
METRO 0.5 to 1.5Structure and function 5
Function
5 Structure and function
5.1 Function
In a hopper loader system with METRO H** and/or METRO M** hopper loaders one central Motancontroller controls all units in the system.
The different hopper loaders report a material requirement to the relevant controller and are then processed in succession.
METRO H**: Material required via the Proximity switch if the discharge flap is closed
METRO M**: Material required via the demand probe if the granulate no longer covers the demand probe.
If material is required by one or more hopper loaders, the blower station starts and generates underpressure in the vacuum line. The bypass valve on the filter closes and simultaneously open the vacuum valve in the hopper loader. An underpressure forms in the vacuum line and continues through the hopper loader to the material line through to the suction point.
Fig. 5.1 – Layout of the hopper loaders
[1] Unit cover[2] Implosion module[3] Material inlet module[4] Multifunction panel METRO *C/J*[5] Glass/stainless steel
[6] Material discharge module (bin loader)[7] Proximity switch (METRO H** only)[8] Multifunction panel METRO *P*[9] Material discharge module (machine hopper
loader)[10] Demand probe (METRO M** only)
5 Structure and functionFunction METRO 0.5 to 1.5
22 Edition: November 2005
The aspirated air forms a mixture of air and granulate in the material line. The granulate falls down by gravity when it enters the hopper loader. The dust particles in the granulate pass through the screen filter and are removed by the central filter. This removes dust from the granulate at the same time.
Depending on the specified conveying time the vacuum valve closes to form an airtight seal. Because of the underpressure in the hopper loader the implosion valve now opens suddenly for a short time. The implosion cleans the screen filter after every loading cycle.
METRO H**: as a result of the implosion the underpressure in the hopper loader collapses and the weight of the granulate opens the discharge flap. The material flows into the machine bin.
The vacuum valve in the hopper loader opens at the next demand. The loading cycle starts.
Only one hopper loader at a time can be filled on a blower line.
If all hopper loaders are full and no material required is pending at the controller, the bypass valve on the filter opens, the blower aspirates fresh air and switches off after a specified run-on time. This reduces the load on the blower station.
If a hopper loader reports material required again to the controller, the blower station is switched on and a new loading cycle starts.
Fig. 5.2 – Functional diagram of the METRO H 0.5/1.5 hopper loader
[1] Vacuum line[2] Implosion valve open[3] Material tube[4] Discharge flap[5] Inlet flap open
[6] Vacuum valve open[7] Inlet flap closed[8] Vacuum valve closed[9] Proximity switch
9 Maintenance and repairMaintenance and cleaning METRO 0.5 to 1.5
34 Edition: November 2005
Prepare the hopper loader for maintenance (see "Maintenance and repair" on Page 32).
Open the spring clips on the top of the unit.
Open the cover.
Remove the screen filter.
Tap the screen filter to clean it and clean the screen filter with a vacuum cleaner.
Check its condition and if necessary replace the screen filter.
Structure
Insert the screen filter so the screen filter seal contacts the fastener ring [2].
Check that the screen filter [1] is correctly positioned, i.e. the rods of the filter fastener (see figure 9.2) are not in the vicinity of the vacuum valve.
Close the cover and lock it with the spring clips.
[1] Screen filter[2] Filter fastener rod
Fig. 9.2 – Screen filter
[1] Screen filter[2] Fastener ring
Fig. 9.3 – Replace screen filter
CAUTION!
MALFUNCTION!The required vacuum may not be generated if the rods of the filter fastener project above the hopper housing.
Never force the cover closed.Make sure that the screen filter is precisely positioned and that the rods do not project above the hopper housing.
Edition: November 2005 35
METRO 0.5 to 1.5Maintenance and repair 9
Maintenance and cleaning
9.4.2 Check inlet flap
Prepare the hopper loader for maintenance (see "Before starting work" on Page 32).
Remove the screen filter (see "Clean screen filter." on Page 33).
Check the inlet flap [1] for wear (see arrows in the magnified view).
Note
The screen filter clogs up faster when regrind material is transported.
Reduce cleaning intervals appropriately.
[1] Check inlet flapFig. 9.4 – Check inlet flap
9 Maintenance and repairRepair work METRO 0.5 to 1.5
36 Edition: November 2005
9.5 Repair work
9.5.1 Disassemble METRO 0.5-1 to 1.5-1 hopper loader into its modules
Separating modules
Prepare the hopper loader for maintenance (see "Before starting work" on Page 32).
To separate the module, slacken the screw [4] and remove the profile clamp [1] (also the ground for glass units [6]).
Disengage the module.
Remove the seal [3].
Remove the ground clamp [2].
Fig. 9.5 – METRO H** hopper loaders
[A] METRO HC/J*[B] METRO HP*[1] Profile clamp[2] Ground terminal
[3] Seal[4] Screw[5] Multifunction panel[6] Ground (glass units only)
CAUTION!
Material damage!Parts which fall into the unit may cause operational faults.
Make sure that no parts fall into the unit.Cover the opening of the machine and bin.
6
A B
Edition: November 2005 37
METRO 0.5 to 1.5Maintenance and repair 9
Repair work
Assembling modulesAttach the ground clamp [2].
Place the seal [3] on the contact surface of the bottom module.
Position the module.
Position the profile clamp [1] and fasten the clamp with screw [4] (also the ground for glass units [6]).
9.5.2 Replacing vacuum valve
RemovalPrepare the hopper loader for maintenance (see "Before starting work" on Page 32).
CAUTION!
Material damage!Parts which fall into the unit may cause operational faults.
Make sure that no parts fall into the unit.Cover the opening of the machine and bin.
Fig. 9.6 – Vacuum valve
[1] Hexagonal nut[2] Implosion valve[3] Spacer rod[4] Contact surface of the spacer rod[5] Sealing disk
[6] Vacuum seal[7] Hexagon-headed screw M6[8] Spring[9] Piston rod[10] Contact surface of the piston rod[11] Pneumatic cylinder
9 Maintenance and repairAdjusting proximity switch (METRO H** only) METRO 0.5 to 1.5
38 Edition: November 2005
Unscrew the M6 hexagon-headed screw [7]. Using a forked wrench (WAF 9), push against the contact surface of the piston rod [4].
Press the spacer rod [3] back manually and pull the sealing disk [5] out.
Remove the spring [8].
Slacken the hexagon nut [1] on the pneumatic cylinder [11].
Unscrew the pneumatic cylinder [11] and remove the implosion valve [2].
Loosen the spacer rod with forked wrench (WAF 9). Using a forked wrench (WAF 9), push against the contact surface of the piston rod [10].
Unscrew the spacer rod [3].
InstallationAssemble in reverse order.
Make sure that the sealing disk [5] contacts the seal [6] after assembly.
Lock the thread of the piston rod [9] with Loctite 270 and the hexagon-headed screw [7] with Loc-tite 242.
9.6 Adjusting proximity switch (METRO H** only)
Prepare the hopper loader for maintenance (see "Before starting work" on Page 32).
Close the discharge flap.
Set the clearance as shown in the diagram 9.7.
Lock the proximity switch [1] with the hexagon nuts [2].
Note
Make sure that no parts fall into the unit.
Cover the opening of the machine and bin.
[1] Proximity switch[2] Hexagon nuts
Fig. 9.7 – Adjusting proximity switch
2
1
Edition: November 2005 39
METRO 0.5 to 1.5Maintenance and repair 9
Adjusting discharge flap (METRO H** only)
9.7 Adjusting discharge flap (METRO H** only)
Slide the weight on to the tension pin and fix the weight. Installation position: see diagram 9.8.
Tighten the set screw and lock it with Loctite 242.
Screw the spring-loaded thrust pad [1] (see figure 9.9) up until the gap between the discharge [3] and the discharge flap [2] is 5-8 mm.
[1] WeightFig. 9.8 – Positioning weight
[1] Spring-loaded thrust pad[2] Discharge flap[3] Discharge
Fig. 9.9 – Adjusting discharge flap
Note
The air gap at the discharge flap ensures that particles of granulate on the discharge flap are sucked in by the vacuum at the start of transport.
The discharge flap is pulled up by the vacuum and forms an airtight seal.
Edition: November 2005 43
METRO 0.5 to 1.5Option 11
Implosion filter option
11 Option
11.1 Implosion filter option
The implosion filter prevents the entry of dust into the unit and prevents the release of dust into the environment.
11.1.1 Intervals for inspections, maintenance and cleaning work
Monthly
11.1.2 Maintenance work
Prepare the hopper loader for maintenance (see "Before starting work" on Page 32).
Check the implosion filter (visual check) for damage.
Check the cable passage gland for damage.
Check the seal for damage.
Component Activity Target value/Meaning Qualification
Implosion filter for damage and clean See "Maintenance work" on Page 43
Operator
Seal for damage See "Maintenance work" on Page 43
Operator
[1] Nut[2] Sealing ring[3] Cover plate of implosion filter[4] Implosion filter[5] Spacer[6] Seal[7] Cable passage[8] Plug connector
Fig. 11.1 – Implosion filter
11 OptionImplosion filter option METRO 0.5 to 1.5
44 Edition: November 2005
11.1.3 Maintenance
Removing implosion filterPrepare the hopper loader for maintenance (see "Before starting work" on Page 32).
Label the PU tubes to the implosion filter and undo the PU tubes.
Remove the plug connector [8].
Slacken the nut [1] and remove the sealing ring [2].
Remove the cover plate of the implosion filter [3] and pull the implosion filter [4] off.
Remove the spacer [5] and the seal [6].
Installing implosion filterAssemble in reverse order.
Make sure that the PU tubes are correctly installed.
[1] Nut[2] Sealing ring[3] Cover plate of implosion filter[4] Implosion filter[5] Spacer[6] Seal[7] Cable passage[8] Plug connector
Fig. 11.2 – Implosion filter
Edition: November 2005 45
METRO 0.5 to 1.5Option 11
Implosion filter option
11.1.4 Spare parts
Spare parts listItem Unit Designation Article no. Remarks
1 1 Bend 4119050
2 2 Screw-plug connector straight M5 4110160
3 rm PU tube Ø 4x1 mm (Ø 0.16x0.04") 4037050 Calibrated
4 1 Pressure connection for implosion filter 4119040
5 1 Implosion filter seal 4119060
6 1 Implosion filter spacer 4119070
7 1 Implosion filter 4119100
8 1 Cover plate of implosion filter 4119110
9 1 Sealing ring 4044270
10 1 Nut 4072970
11 1 Plug connector 4070220
12 1 Cable passage 1168150
Edition: November 2005 47
METRO 0.5 to 1.5Appendix 12
METRO 0.5 to 1.5
12 Appendix
12.1 METRO 0.5 to 1.5
Spare parts listItem Unit Designation Article no. Remarks
1 1 Implosion module complete 5084700
2 1 Inlet flap 4114910
3 1 Glass module 4117020 available for 1.5 l only1 Steel module 4118000
4 1 Proximity switch 24 V 4038130
1 Proximity switch 120 V 25008512
5 1 Discharge module complete 5084650
6 1 Ground terminal 4117720 METRO 0.5
2 METRO 1.5
7 1 U-profile seal 4115040 METRO 0.5
2 METRO 1.5
8 1 Profile clamp 4114930 METRO 0.5
2 METRO 1.5
9 1 Machine module 4115030
10 1 Demand probe 24 V 4102410 for materialup to 80 °C1 Demand probe 120 V
12 AppendixMETRO 0.5 to 1.5 METRO 0.5 to 1.5
48 Edition: November 2005
Spare parts listItem Unit Designation Article no. Remarks
11 1 Screen filter 500 µ 4115370
1 Screen filter 1200 µ 4158730
12 1 Filter fastener 4115380
13 2 Cap 4158590
Edition: November 2005 49
METRO 0.5 to 1.5Appendix 12
METRO 0.5 to 1.5
12.1.1 Implosion module METRO 0.5 to 1.5
Spare parts listItem Unit Designation Article no. Remarks
1 1 Cover 4115450
2 1 Warning sign 4103380
3 2 Countersunk screw M4 1237810
4 1 Edge protector 1192960
5 1 Implosion module 4115720
7 2 O-ring 1110660
6 1 Axis at cover 4115470
8 4 Hexagon nut M4 1238200
9 1 Vacuum seali
i Secured with Loctite 406
4158100
10 1 Hexagon-headed screw M6ii
ii Secured with Loctite 242
1228900
11 1 Vacuum sealing disk 4114870
12 1 Spring 4115580
13 1 Spacer rod to implosioniii
iii Secured with Loctite 270
4114430
14 1 Implosion mechanical components complete 4158400
15 1 Pneumatic cylinder 4158440
16 2 L-connector screw retainer 4158630
17 2 Spring clip 4158310
18 1 Seal for cover 4115460
12 AppendixMETRO 0.5 to 1.5 METRO 0.5 to 1.5
50 Edition: November 2005
12.1.2 Discharge module METRO 0.5 to 1.5
Spare parts listItem Unit Designation Article no. Remarks
1 1 Discharge module welded 4117730
2 2 Silencer 4063970
3 2 Sealing ring 4044670
4 1 Flap shaft 4116960
5 1 Bearing plate 4083770
6 1 Weight 4070150
7 1 Thread pin M5i
i Secured with Loctite 242
4063030
8 1 Thrust pad M8 spring-loaded 4069230
9 2 Hexagon nut M8 3034630
10 2 Philips-head screw M4 4050900
11 2 Spring washer A4 1210880
12 1 Screw M6i 4083720 Verbus Ripp
13 1 Fastener t= 1.5 4117310
14 2 Hexagon nut M6 with clamp sectioni 1902350 ISO 7042
15 2 Lens flange flat-head screw M6 4073190
16 1 Flap t=0.5 4117330
17 1 O-ring 4078360
Edition: November 2005 51
METRO 0.5 to 1.5Appendix 12
Multifunction panel METRO *C/J/P*
12.2 Multifunction panel METRO *C/J/P*
Spare parts listItem Unit Designation Article no. Remarks
A 1 Multifunction panel METRO C basic 5062440 See page 12-52
B 1 Multifunction panel METRO J 5069500 See page 12-53
C 1 Multifunction panel METRO P 5086070 See page 12-54
12 AppendixMultifunction panel METRO *C/J/P* METRO 0.5 to 1.5
52 Edition: November 2005
12.2.1 Multifunction panel METRO C basic
Spare parts listItem Unit Designation Article no. Remarks
A 1 Multifunction panel METRO C basic 5062440 complete
1 1 Controller METRO C 4158010
2 1 Valve cable 4158600
3 1 MFP component carrier 4118010
4 6 Philips-head screw M4 4050900
5 1 L-connector screw retainer 4158630
6 1 Silencer 4063970
7 2 Philips-head screw M4 1206930
8 1 4/2 directional control valve 4158580
12 AppendixMultifunction panel METRO *C/J/P* METRO 0.5 to 1.5
54 Edition: November 2005
12.2.3 Multifunction panel METRO P
Spare parts listItem Unit Designation Article no. Remarks
C 1 Multifunction panel METRO P 5086070 complete
1 2 Philips-head screw M3 1206260
2 1 Control plug 5074240
3 1 Valve cable 4158600
4 1 Fastener P-loader 4118010
5 2 Philips-head screw M4 4050900
6 1 L-connector screw retainer 4158630
7 1 Silencer 4063970
8 2 Philips-head screw M4 1206930
9 1 4/2 directional control valve 4158580
Edition: November 2005 55
METRO 0.5 to 1.5Appendix 12
Pneumatics diagram
12.3 Pneumatics diagram
12.3.1 METRO 0.5 to 1.5
[1] Vacuum valve
�nderung
Datum
Name
Datum
Bearb.
Gepr.
Norm
Blatt
Gr.:
Kommission:
Zeichng.Nr.:
Projekt:
Urspr.
Ers. f.
Ers. d.
Vers.
A B C D E F2
1
1
18.10.2005
EKA
2
2
METRO C basic
SPS (PLC)/SELVAC
27.11.2001
3
3
REG4
4
Motan GmbH
Max-Eyth-Weg 42
88316 Isny
Steuerung
Control (unit)
5
5
6
6
Convey
280A-90.0.00
7
7
= +F1F1
8
8 +KAUE/1
1.0
5
A B C D E F
A1+ZSW
+KK
W5F1
PVC Steuerleitung
12x1mmý
PE P
E
GNYE
-XS
PE
-X41
3PE
+ 24V
1
1 1
W5Y1
H05VV-F/F
3x0,75
Vakuum Ventil
Vacuum Valve
2 BU
M 2
2 2
VACV
3
3 3 1 BN
-5Y1
1 2
GNYE
PE Vakuum
Vacuum
+F16
-5H11 2
Niveau
Level-5H21 2
W5B1
SENSOR
3x0,34
**
Anforderung Material
Demand Material
ANFO
6
6 6 6 BK
4 BN
+FH-LOADER
-5B1
BN
BK
BU +FM-LOADER
-5B1
BN
WH
BU5 BU
+F
7PE
Ï
+F16
ONLP
5
5 5
-5H31 2
Ein Aus Alarm
On Off Alarm
ONTS
7
7 7
-5S1
3 4
W5B2
SENSOR
4x0,34
Niveau Beh„lter
Level Hopper
NIBE
4
4 4 10
BK
8 BN
-5B2
BN
BK
BU9 BU * Option 1
** Option 2
*
W5Y2
H05VV-F/F
3x0,75
Zwangsverschluss
Operated flap
12
BUZWVV
8
8 8 11
BN
-5Y2
1 2
**
GNYE
14RES 9
9 9 13
15PE
RES
10
10
10
16PE
RES
11
11
11
�nderung
Datum
Name
Datum
Bearb.
Gepr.
Norm
Blatt
Gr.:
Kommission:
Zeichng.Nr.:
Projekt:
Urspr.
Ers. f.
Ers. d.
Vers.
A B C D E F2
1
1
10.05.2005
EKA
2
2
METRO P-LOADER
29.10.2002
3
3
REG4
4
Motan GmbH
Max-Eyth-Weg 42
88316 Isny
Steuerung
Control (unit)
5
5
6
6
Convey
280G-90.0.00
7
7
= +F1F1
8
8 +KAUE/1
11
A B C D E F
=ZSW
F”rdersteuerung
Conveying control
WF1
PVC Steuerleitung
5x1mmý
L+
1
-11XS1.1
1
-11XS1
1
+F
H-LOADER
-11B1
BN
BK
BU
+FM-LOADER
-11B1
BN
WH
BU
Anforderung
Demand
M
2 2 2
1,0 mmý
GNYE
H05V-K
+EX
-PE
Ï
WY1
PVC Steuerleitung
1m
3x1mmý
2
PE
GNYE
Ï Ï GNYE 5 VA
-11Y1
Ï1 2
Vakuumventil
Vaccum valve
VAKUUM
3 3 3 1
ANFO 4 4 4
�nderung
Datum
Name
Datum
Bearb.
Gepr.
Norm
Blatt
Gr.:
Kommission:
Zeichng.Nr.:
Projekt:
Urspr.
Ers. f.
Ers. d.
Vers.
A B C D E F2
1
1
03.11.2005
EKA
2
2
METRO J LOADER
27.11.2001
3
3
REG4
4
Motan GmbH
Max-Eyth-Weg 42
88316 Isny
Steuerung
Control (unit)
5
5
6
6
Convey
280F-90.0.00
7
7
= +F1F1
8
8 +KAUE/1
1.0
5
A B C D E F
Alle Litzen sind
als Multinorm Einzeladern
UL-CSA-HAR auszuf�hren!
A1+ZSW
+KK
W5F1
PVC Steuerleitung
7xAWG20
W5XS1
JZ-603
0,2m
7xAWG18
PE P
E
GNYE
GN
+KK13
-XS1
PE
GNYE
AWG16
BK
H07-V2K
Sensor Ein
sensor on
5
5 BN 5 5
+KK13
-5S1
1 1a
W5Y1
PVC Steuerleitung
3xAWG20
Vakuum Ventil
Vacuum Valve
VACV
1
1 RD 1 1
-X01
1 1 RD
-5Y1
1 2
120VAC
N 4
4 WH 4 4 11
2 WH
1PE
GNYE
GN
PE
+F
-5B1
W5B1
PVC Steuerleitung
3xAWG20
Anforderung Material
Demand Material
2 1 BN
1
ANFO
6
6 BU 6 6 3 2 BU
2
2PE
GNYE
GN
PE
W5Y2
PVC Steuerleitung
3xAWG20
ZWV 2
2 OG 2 2 4 1 RD
-5Y2
1 2
Zwangsverschluss
operated flap
12
2 WH
2PE
GNYE
GN
PE
*
W5Y3
PVC Steuerleitung
3xAWG20
DUOM
3
3 BK 3 3 5
+KK13
-XS2
1 1 RD
-5Y3
1 2
DUOMIXVENTIL
Proportioning Valve
13
2 2 WH
3PE
PE
GNYE
GN
PE
3
Ringkabelschuh M5
AWG16
0,25m
GNYE
H07-V2K
+F
3PE
Ï
* Option