Page 1: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

27 August 2013

Page 2: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

WELCOME TO THE COMMUNITY FORUM CREMORNE WARD

6.30pm Welcome Mayor, Cr Jilly Gibson

6.35pm Introduction Penny Holloway, General

Manager

6.40pm What’s happening in your local area?

7.20pm Have your say Opportunity to ask questions of Council -

Raise your issues and concerns

8.00pm Close

Page 3: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

WHAT’S HAPPENING IN CREMORNE WARD?

Local projects: • Cremorne Ward public domain

improvements • Arrangements for International Fleet

Review • Cremorne Reserve improvements • Boat storage options at Hayes Street

Beach

Page 4: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

AIMS OF FORUM Community Forums provide all residents and

businesses with the opportunity: • to be informed of changes in their

neighbourhood • to find out what is happening locally • to share information with

residents/neighbours; and • to participate in the delivery of Council

services and facilities

Page 5: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

FORUM PROTOCOLS • Save questions until the end of each

presentation • During the Q&A section participants may

speak for up to 2 minutes • The MC will accept only 1 question at a

time. • Do not talk over another participant,

Councillor or staff member who is addressing and/or responding to a question

Page 6: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

GET INVOLVED....

Page 7: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Cremorne Ward public domain improvements

Duncan Mitchell Director Engineering and Property

Services

Page 8: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Young Street – Neutral Bay

Page 9: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Young Street – Neutral Bay

Page 10: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Young Lane – Neutral Bay

Page 11: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Young Lane – Neutral Bay

Page 12: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Parraween Street Car park Redevelopment – Cremorne

Page 13: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Parraween Street Car park Redevelopment – Cremorne

Page 14: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Mural at May Gibbs Place – Neutral Bay

Page 15: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Public Domain Upgrades – Neutral Bay

Page 16: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Public Domain Upgrades – Neutral Bay

Before After

Page 17: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Public Domain Upgrades – Neutral Bay

Before After

Page 18: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Road Upgrade

Major Projects in your Area

After

Page 19: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Re sheeting in Asphalt commencing October 2013

Major Projects in your Area

Page 20: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Paving Upgrade

Major Projects in your Area

Before After

Page 21: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Paving Upgrade

Major Projects in your Area

Before After

Page 22: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Kerb and Gutter Upgrade

Major Projects in your Area

Before After

Page 23: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Kerb and Gutter Upgrade

Major Projects in your Area

Before After

Page 24: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Spofforth Street – Drainage Upgrade

Major Projects in your Area

Before After

Page 25: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

General Road Works completed in 2012/13

Roads Quantity Unit

Road Pavement Repairs

18,793 Sq m

Road Pavement Marks Repairs

123 Sq m

Road Line Marking

80 Lin m

Repair Road Signs

1,010 Each

Meter Bay Line Repairs

69 Each

Meter Pad Repairs

4 Each

Page 26: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Bertha Road – Cremorne – May 2013

Page 27: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Bertha Road – Cremorne

Page 28: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Bertha Road – Cremorne

Page 29: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Claude Avenue – Cremorne – May 2013

Page 30: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Claude Avenue – Cremorne – Completed May 2013

Page 31: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Claude Avenue – Cremorne – Completed May 2013

Page 32: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Cremorne Lane – Cremorne – Completed Dec 2012

Page 33: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Harrison Street – Cremorne – Underway – due for completion end of September 2013

Page 34: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Harrison Street – Cremorne – Underway – due for completion end of September 2013

Page 35: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Road works in your Area

Project to be completed this financial Year • Harrison St, Neutral Bay – Underway – due for Copletion Sept

• Spofforth St, Cremorne- Underway – due for completion Oct

• Cremorne Rd, Cremorne – Late 2013

• Rawson St, Neutral Bay – Early 2014

Page 36: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

General Road Footpath Works completed in 2012/13

Footpaths Quantity Unit

Footpath Concrete Repairs

3,719 Sq m

Footpath Paver Repairs

10 Sq m

Repair Kerb Ramp

10 Each

Clean Footpath Pavers

1,755 Sq m

Clean Plaza

2 Each

Page 37: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area Major Projects to completed 2012-13

•Spofforth Street – Cremorne – complete July 2013

•Rawson Street – Neutral Bay – Dec 2012

•Lower Boyle Street – Cremorne – Completed may 2013

•Bogota Avenue, Neutral Bay – Completed mid 2012

•Hayes St, Neutral Bay – September 2012

•Green Street – Cremorne Point – early 2012

Page 38: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Spofforth Street - Cremorne – Completed August 2013

Page 39: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Harrison Street - Cremorne – Underway

Page 40: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Harrison Street - Cremorne – Underway

BEFORE AFTER

Page 41: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Rawson Street – Neutral Bay

Page 42: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Cremorne Community Mental Health Centre Entry DDA works

BEFORE AFTER

Page 43: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Lower Boyle Street – Cremorne – Completed May 2013

Page 44: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Green Street & Cremorne Road Footpath upgrade –Cremorne Point – Early 2012

Page 45: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Green Street – Cremorne Point Kerb and Fence replacement – Early 2012

Page 46: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain works in your Area

Footpath restoration works Bogota Avenue – Neutral Bay Completed Mid 2012

BEFORE AFTER

Page 47: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Projects in your Area

Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and

repaved the adjoining area in Hayes Street Neutral Bay.

Page 48: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Footpath works in your Area

Projects to be completed 2013-14 • Harrison St, Neutral Bay – in progress

• Military Road and Spencer Street’

• Military Road between Hampton and Murdoch Streets

Page 49: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Drainage works in your Area

General Road Drainage Works completed in 2012/13

Complete Scheduled

Hodgson Street

Bogota Avenue

Barry Lane

Forsyth Park Neutral

Bay

Holdsworth Street Kurraba Road

Milson & Rialto Roads Bertha Street

Premier / Spruson

Street

Claude & Bannerman

Sts

Cremorne Road

COMMENCED - Harrison Street

Page 50: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Drainage works in your Area

Hodgson Street – Cremorne – Completed Nov 2012

BEFORE AFTER

Page 51: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Drainage works in your Area

Hodgson/Murdoch Street Road- Cremorne - Completed Feb 2013

BEFORE AFTER

Page 52: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Drainage works in your Area

Barry Lane – Neutral Bay

BEFORE AFTER

Page 53: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Drainage works in your Area

Holdsworth Street – Neutral Bay Completed March 2013

Page 54: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Retaining Wall works in your Area

These are will commence end of August 2013 and be completed by end Sept 2013.

Council has recently Councils has awarded a tender for repairing 3 retaining walls at 47-49 Cremorne Road;

12 Bertha Road and

46 Murdoch Street

Page 55: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Under Awning Lighting – Stage 4 now complete

Page 56: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Major Projects in your Area

Under Awning Lighting – Stage 4 now complete

Page 57: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

"Raised Pedestrian Crossing" in Cranbrook Avenue, at Allister Street.

General Traffic Improvements in your Area

Page 58: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Traffic Improvements in your Area

Raised Threshold - Rawson St, Neutral Bay

Page 59: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Traffic Improvements in your Area

Pedestrian Refuge – Montpellier St, Neutral Bay

Page 60: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Traffic Safety Fence – Rawson Street – Cremorne Completed??

General Traffic Improvements in your Area

Page 61: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Traffic Safety Fence – Rawson Street – Completed??

General Traffic Improvements in your Area

Page 62: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

RMS – scheduled to be completed October 2013

General Traffic Improvements in your Area

Sound Walls Sexton Place - Neutral Bay

Page 63: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

RMS – scheduled to be completed October 2013

General Traffic Improvements in your Area

Sound Walls Sexton Place - Neutral Bay

Page 64: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

RMS – scheduled to be completed October 2013

General Traffic Improvements in your Area

Sound Walls Sexton Place - Neutral Bay

Page 65: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

RMS – scheduled to be completed October 2013

General Traffic Improvements in your Area

Sound Walls Sexton Place - Neutral Bay

Page 66: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Traffic Improvements in your Area

Ben Boyd Road, Neutral Bay – Traffic Calming in Planning

Page 67: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

In your Area opportunities at Ben Boyd Road as part of Traffic Calming Works

General Traffic Improvements in your Area

Page 68: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Bicycle Route Improvements in your Area

Bicycle Route Upgrade – Bannerman Street, at Harriette Street Now complete

Before

Page 69: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

New Pocket Bike Map launched in 2012

Bicycle Route Improvements in your Area

Page 70: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Share Path Campaign – August 2013

Bicycle Route Improvements in your Area

Page 71: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Share Path Campaign – August 2013

Bicycle Route Improvements in your Area

Page 72: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain

works in your Area – Drainage S/W Drainage Quantity Unit

Repair S/W Conduit

974 Lin m

Repair S/W Pit

42 Each

Clean S/W Conduit

845 Each

Clean S/W Pit

3,419 Each

Page 73: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Environmental Initatives in your Area

We have 3 GPTs in the Cremorne Ward located at:

1) Manns Avenue, Neutral Bay

2) Honda Road, Neutral Bay

3) Rawson Street, Neutral Bay

Annual total or 84.6 tonnes collected in Cremorne

Page 74: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Rawson Street & Manns Avenue – Neutral Bay

Environmental Initatives in your Area

Page 75: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Honda Road – Cremorne

Environmental Initatives in your Area

Page 76: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain Improvements in your Area

Street Furniture Quantity Unit

Repair Fences

836 Lin m

Paint Fences

422 Lin m

Repair Bollard

41 Each

Repair Street Signs

15 Each

Repair Seat

22 Each

Page 77: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain Improvements in your Area

There are 12 bus shelters in Cremorne Ward - 11 are cleaned fortnightly and 1 is cleaned weekly ("Hampden" at corner of

Military Rd and Monford Place).

Page 78: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain Improvements in your Area

836 linear meter of fences replaced / repaired

Bent Street Kareela Road Milson Road

Page 79: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain Improvements in your Area

22 Benches and seats replaced / repaired

Page 80: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

General Streetscape & Public Domain Improvements in your Area

Future Fencing works

Timber fence work programmed for next 3 months in Cremorne Ward to be undertaken by contractors: 1. Timber fence reconstruction 303.5 lin m. - Kareela Road 132 lin m - Bertha Rd and Guthrie Ave 18.2 lin m - Murdoch St and Bennett St 38 lin m - Ben Boyd Rd and Kurraba Reserve 57 lin m

2. Timber fence painting 261 lin m. - Fences in Claude Ave, Guthrie Ave, Kareela Rd, and Milson Rd.

Page 81: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

NSC- Child Restraint Service

Last October - Authorised Fitters checked and fitted 66 restraints from 42 cars.

Page 82: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

NSC- Child Restraint Service I am very happy that this was checked by a license child restraint fitter and this is very helpful for my child safety. Thanks to North Sydney Council.

Great service provided by the council

Great please keep them going I have used them many of times! Thanks

Page 83: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

NSC- Safety Around Schools Campaign

NSC is working with Willoughby, Lane Cove, Mosman and Ku-ring-Gai Councils – Launched May 2013

Page 84: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

NSC- Safety Around Schools Campaign

NSC is working with Willoughby, Lane Cove, Mosman and Ku-ring-Gai Councils – Launched May 2013

Page 85: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

NSC- Safety Around Schools Campaign

Flashing “40” around schools

NSC has been lobbying on behalf of schools in the area for many years and now the RMS advise that schools to benefit from this latest roll-out include the following school(s) within the North Sydney LGA.

• Cammeray Public School, Cammeray

• Palmer Street at Cammeray Public School,

• Marist College North Sydney, North Sydney

• Neutral Bay Public School, Neutral Bay

Page 86: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

April/May 2013, a speed reduction campaign “Speeding You’re in Our Sights” was launched – Ben Boyd Road

Traffic Safety Campaigns

Page 87: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Traffic Safety Campaigns

The campaign will commence in early 2013

•North Sydney Council worked closely with participating licensed venues and bottle shops. Information including, posters, coasters, T-shirts, stickers, DVDs, bottle bags as well as the installation of temporary breathalysers were offered to all 57 venues in North Sydney (all 33 licensed venues and 24 bottle shops) as part of the campaign promotion during the Christmas/New Year Festive season.

Page 88: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Transport Submissions

NSC made submissions on NSW Long Term Transport Master

Plan and the BRT

Page 89: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Transport Submissions

Boat & Trailer Working Group – Now established – for more information

http://www.transport.nsw.gov.au/publications-reports/boat-trailer-working-group-report

Page 90: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Public Domain Lighting

Ausgrid Standard Street Light will be LED from late 2014 – Onwards

Before – 42W Compact Fluorescent After – 29W LED

Page 91: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area Graffiti Solutions - Our leaflet provides the information

Page 92: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

16 15

14

5

7

3

16

13

2

10

14

12

10 10

6

2

9

6

26

9

7

11

13

17

0 0 0 0 0 0 0 0 0 0 0 0 0

5

10

15

20

25

30

2012-07 2012-08 2012-09 2012-10 2012-11 2012-12 2013-01 2013-02 2013-03 2013-04 2013-05 2013-06

Num

ber o

f Job

s

Calendar Year/Month

Figure 1: Cremorne Ward - Removal Jobs 2012/2013 Private Property Council Property

Service Authorities

Unusually high because of 8 hits at Kurraba Wharf Reserve. Prompt removal of graffiti on this site was succesful - no further hits for the rest of year.

1 private property hits 3 times. Prompt removal of graffiti on this site was succesful - property has not been hit again.

5 hits at Neutral Bay Community Centre. More frequest inspections have been made to better control this site.

Page 93: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

85

25 23

47

17

26 22

15

0

10

20

30

40

50

60

70

80

90

2006 2007 2008 2009 2010 2011 2012 2013

No

of A

gree

men

ts R

ecei

ved

Calendar Year

Figure 2: Cremorne Ward - Number of Private Property Agreements Received

Percentage of Private Properties with agreements for Cremorne Ward : 3%

In Cremorne Ward we have 8573 properties only 233 have

registered agreements with Council.

Page 94: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

• In 2011 /12 we responded to and removed over 1400 pieces of grafitti.

• Council offers this Service Free • We only need you to sign up for approval purposes

• To report Grafitti contact Council on 9936 8100 • To Join up to our agreement or find out more

information Go to our Website • http://www.northsydney.nsw.gov.au/www/html/6731-graffiti.asp

or come to our Customer Service Desk.

Page 95: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

Removal from Private Property and Utilities

Page 96: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

Removal from Private Property and Utilities

Page 97: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Grafitti Removal Program in your Area

Removal from Private Property and Utilities

Page 98: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Events coming up

Harbour Hike - Sunday 1st of September.

For more information contact?? and go to this website

Page 99: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Events coming up

Blackmoores Sydney Running Festival - Sunday 22nd of September

For more information contact?? and go to this website

Page 100: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Events coming up

Ride to Work – Wednesday 16th of October.

For more information contact?? and go to this website

Page 101: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Events coming up

NSW Spring Cycle Ride - Sunday 20th of October.

For more information contact?? and go to this website

Page 102: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Events coming up

7 Bridges Walk - Sunday 27th of October. For more information contact?? and go to this website

Page 103: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

Cremorne Reserve improvements, boat storage options at Hayes

Street Beach and Arrangements for the International Fleet Review

Robert Emerson

Director Open Space and Environmental Services

Page 104: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

CREMORNE RESERVE IMPROVEMENTS

Page 105: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

BOAT STORAGE AT HAYES

STREET BEACH

Page 106: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

INTERNATIONAL FLEET REVIEW

3 - 11 October 2013 Commemorating the centenary of the first entry of the Royal Australian Navy's Fleet into Sydney.

Approximately 40 warships and 20 tall ships will participate

Page 107: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

SCHEDULE OF EVENTS (OCT) Date (Oct)

Time Event

3 1100 Approx 20 tall ships enter Sydney Harbour 0730 Approx 40 warships depart Jarvis Bay for passage to Sydney.

4 0600-1600 Warships enter Sydney Harbour - proceed to temp moorings

1000 Ceremonial Fleet Entry and 21 Gun Salute

5 1100-1430 Ceremonial Fleet Review Sydney Harbour 1300-1200 Formation flypast-rotary & fixed winged aircraft: Sydney Harbour. 1400-1900 Military demonstrations and Naval band performances. 1940-2010 Pyrotechnics and Lightshow: Sydney Harbour.

6 1300-1800 Tall ships open to general public: Cockle Bay/Darling Harbour 1300-1800 Warships Open Day: Fleet Base East,Garden Island/Barangaroo.

7 0800-1800 Warships Open Day: Fleet Base East,Garden Island/Barangaroo. 0800-1800 Tall ships open to general public: Cockle Bay/Darling Harbour

9 1500-1730 Twilight sailing with RAN Sailing Association Sydney Harbour. 10 1100 Tall ships depart Sydney Harbour 11 TBC Warships depart Sydney Harbour

Page 108: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

ARRANGEMENTS • Crowd numbers & restrictions • Police & Emergency Services • Public transport • Road Closures & Special event

clearways • Alcohol restrictions • North Sydney Olympic Pool • Community Information • Post event clean-up

Page 109: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

HAVE YOUR SAY

• Call for questions from the floor • We will record ALL questions, issues and

concerns raised • Within 2 to 3 weeks we will publish a

response the community’s concerns on www.northsydney.nsw.gov.au

• Attendees will receive a copy of the Q&A Summary via post/email

Page 110: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

WANT MORE INFORMATION ABOUT OTHER COUNCIL PROJECTS, EVENTS OR

FACILITIES?

• See info table/Council Officers at end of forum

• Councils website www.northysydney.nsw.gov.au

• Sign up to Council’s e-news

Page 111: 27 August 2013 - North Sydney Council€¦ · Following the Hayes Street Wharf upgrade, Council carried out a stormwater drainage upgrade, installed replacement fencing and repaved

FEEDBACK PLEASE

Please provide your feedback using the forms provided or complete online:

https://www.surveymonkey.com/s/cremwardforumfb2013 or use the QR code below: