25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct...

29
25 th Avenue Grade Separation February 20, 2018

Transcript of 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct...

Page 1: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

25th Avenue

Grade Separation

February 20, 2018

Page 2: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Agenda

I. Overview

II. Project Description

III. Project Construction

IV. Outreach

V. Questions

2

Page 3: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Overview

Page 4: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Project Location

4

Page 5: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

E. 25th Ave Railroad Crossing

• 92 Caltrain trains each weekday use this

crossing, in addition to freight

• Lack of grade separation increases delays

along corridor

5

Page 6: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Project Description

Page 7: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Project Elements

Construct Grade Separation (elevated rails,

lowered roads) between Hillsdale Blvd and

Highway 92

Concrete bridge 25th & 28th Ave

Steel bridge at 31st Ave

Concrete retaining walls

MSE walls

7

Page 8: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Elevated Track

8

Page 9: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Grade Separation (25th Ave)

9

Page 10: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

East-West Connection (28th Ave)

10

Page 11: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

East-West Connection (31st Ave)

11

Ramp Access to

Ped Viaduct

Page 12: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Relocated Hillsdale Station

12

Page 13: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Station Improvements

13

Page 14: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Station Improvements – Mosaic Wall

14

Station Signage

Page 15: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Station Improvements

15

Stairway Entrance to Platform

Page 16: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Station Improvements - Platform

16

New Station Platform,

Shelters, Lights

Page 17: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Station Improvements - Furnishings

17

Page 18: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Project Benefits

• Safe rail operations

• Fewer system-wide delays

• Improved traffic flow

• Improved pedestrian and motorist safety

• Facilitate Caltrain electrification which will

reduce noise and vibration

18

Page 19: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Project Construction

Page 20: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Schedule: Overview

20

Activity Date

Mobilization Sept 2017 - Oct 2017

Begin Construction Oct 2017

Hillsdale Station Temp Parking

(available for public use)

Oct 2017 – Jan 2019

Bridges and MSE Walls Nov 2017 – Nov 2018

E. 25th Ave. (lane closures) Nov 2017 – Oct 2019

Bridge at E. 25th Ave

(14FT clearance)

May 2018 – Oct 2019

Page 21: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

21

Activity Date

Station Closed Dec 2018 – May 2019

Road Completed – 28th Ave May 2019

E. 25th Ave. Closure (full) Oct 2019 – Dec 2019

Roads Completed Oct 2019 – 31st Ave

Dec 2019 – 25th Ave

Project Completed Jan 2020

Schedule: Overview cont.

Page 22: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

22

Activity Date

Temporary Sheet Pile

Shoring

Nov 2017 – Dec 2017

(25th Ave: 5 nights in Feb.)

Cast-in-drilled-hole pile

construction

Nov 2017 – Feb 2018

MSE walls March 2018 – Sept 2018

Bridges March 2018 – July 2018

Final Track Cutover Dec 2018 & Jan 2019

Schedule: Night Work Overview

Page 23: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

23

Construction Sheet Piles

Pedestrian Underpass

Page 24: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Construction CIDH Piles

24

31st Avenue

Borel Creek

Page 25: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

25

Construction Pile Caps

Forming Pile Cap

Pile Cap at Pedestrian Underpass

Page 26: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

26

Construction Temporary Parking Lot

Paving

Installing Lighting

Page 27: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Construction Notices

27

Page 28: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Public Outreach & Community Engagement

• Project website:

www.caltrain.com/25thGS

• Construction Outreach Hotline: 650.508.7726

• Email: [email protected]

• Regular Updates and Public Meetings

Prior to Station Closure

Prior to Street Closure

Page 29: 25th Avenue - CaltrainAffairs/Capital...Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Jan 2019

Questions