2.2.e. Chiller vs Vrf_multi v III

download 2.2.e. Chiller vs Vrf_multi v III

of 26

description

sistem ac

Transcript of 2.2.e. Chiller vs Vrf_multi v III

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 0

    VS.

    CHILLER SYSTEMCHILLER SYSTEM

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 1

    1. Design Comparison

    VRF is very simplified refrigerant piping system. More flexible VRF is very simplified refrigerant piping system. More flexible than water piping.than water piping.

    Chiller

    MULTI V III (VRF)Chiller system

    Outdoor unit (air-cooled type) Indoor unit Refrigerant piping

    Chiller FCU (Fan Coil Unit) AHU (Air Handling Unit)

    Systemcomposition

    Feature

    Cooling tower Water piping, Duct working Water pumps

    System concept

    DesignDesign CommissioningOperation MaintenanceInstallation Reliability

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 2

    Network

    Feature Chiller system

    Complicated wiring

    MULTI V III (VRF)

    Simple wiring

    DesignDesign CommissioningOperation MaintenanceInstallation Reliability

    Easy network wiringEasy network wiring

    1. Design Comparison Network design

    ACP

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 3

    1. Design Comparison Total management

    DesignDesign CommissioningOperation MaintenanceInstallation Reliability

    [Manufacturer]

    VAV boxes supplier

    Controlsystem

    Feature Chiller system MULTI V III (VRF)

    (For VRF) M(For VRF) Manufactureranufacturer

    provide all equipmentprovide all equipment

    Simple control structureNo additional control provider

    Central control and energy monitoring with low cost available

    Complicated control structure, additional control manager in the system needed, increasing cost

    Third part control provider needed, interconnectivity problems.

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 4

    Design Commissioning

    MULTI V III (VRF)Chiller system

    The systems condition only the necessary rooms with regard to user demands.

    The systems commonly condition the entire building at predetermined times, with no regard to user demands.(very hot midnight, weekend, holiday etc)

    Capacitycontrol

    Feature

    After office hours operation, VRF could be operated for the userAfter office hours operation, VRF could be operated for the user

    demands.demands.

    Operating Area

    < Limited operation>

    Individual operation

    OperationOperation MaintenanceInstallation Reliability

    2. Operation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 5

    Temperaturecontrol

    Feature Chiller system

    Require1 or 2

    MULTI V III (VRF)

    Very precise 0.5

    Precise temperature controlPrecise temperature control

    3030

    2525

    2020

    1515

    1010 2020 3030 4040 5050 6060 7070

    CoolingCooling

    MIN.MIN.

    Chiller system MULTI V system

    R

    o

    o

    m

    t

    e

    m

    p

    .

    R

    o

    o

    m

    t

    e

    m

    p

    . 0.5 0 C from set point

    Design CommissioningOperationOperation MaintenanceInstallation Reliability

    Temp. control2. Operation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 6

    VRF system doesnVRF system doesnt need a duct space.t need a duct space.

    SpaceEfficiency

    Feature MULTI V III (VRF)

    Small refrigerant space

    Chiller system

    Large duct space

    Design CommissioningOperation MaintenanceInstallationInstallation Reliability

    Space (Duct working)3. Installation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 7

    Chiller

    Pump

    Boiler

    Coolingtower

    (On the rooftop)

    (Machine room drawing)

    OutdoorUnit

    (On the rooftop)

    (Rooftop drawing)

    VRF system is no need for a machine room. VRF system is no need for a machine room.

    Installationspace

    Feature MULTI V III (VRF)

    No need a machine room

    Chiller system

    Need a machine room

    Design CommissioningOperation MaintenanceInstallationInstallation Reliability

    Installation space3. Installation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 8

    Efficient use of space is possible for VRF systemEfficient use of space is possible for VRF system

    Chiller system

    SpaceEfficiency

    Feature

    P P

    1/3

    CHILLER SYSTEMCHILLER SYSTEM

    Large pipe shaft is needed for water piping

    MULTI V III (VRF)

    VRF SystemVRF System

    Small pipe shaft is needed

    Design CommissioningOperation MaintenanceInstallationInstallation Reliability

    Space (Pipe shaft)3. Installation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 9

    VRF system expansion is very easy with extra outdoor & indoor unVRF system expansion is very easy with extra outdoor & indoor unit.it.

    Chiller system

    SystemExpansion

    Feature

    Capacity addition is difficult as additional mechanical room, pump, cooling tower,panel and piping is required.

    MULTI V III (VRF)

    System Expansion is Easy

    +

    Design CommissioningOperation MaintenanceInstallationInstallation Reliability

    System expansion3. Installation Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 10

    1 step Commissioning6 steps Commissioning

    MULTI V Plus

    (VRF)Chiller system

    Commissioning

    Feature

    There are a lot of commissioning points for the chiller systemThere are a lot of commissioning points for the chiller system

    6 Steps Commissioning 1 Step Commissioning

    Water cooled chiller (3)

    (4)

    Design CommissioningCommissioningOperation MaintenanceInstallation Reliability

    NO. of commissioning point4. Commissioning Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 11

    Maintenance

    Feature

    Maintenance costs for a Multi V is lower than chilled water systMaintenance costs for a Multi V is lower than chilled water systems.ems.

    Water cooled chiller (3)

    (4)

    MULTI V III (VRF)

    Filter cleaning Heat exchanger cleaning Cycle check by notebook (LG MV)

    Chiller system Filter cleaning Duct cleaning Water pipe maintenance Periodical oil change, overhaul

    Pump Water treatment Cooling tower cleaning

    Design CommissioningOperation MaintenanceMaintenanceInstallation Reliability

    Maintenance list5. Maintenance Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 12

    (For Chiller Water treatment is required for clean water)(For Chiller Water treatment is required for clean water)

    Watertreatment

    Feature Chiller system

    Water treatment is required(deficient service can cause legionary disease in the system)

    MULTI V III (VRF)

    No water treatment is needed

    Design CommissioningOperation MaintenanceMaintenanceInstallation Reliability

    Water treatment5. Maintenance Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 13

    Scalecleaning

    Feature Chiller system MULTI V III (VRF)

    < The system is consist of refrigerant pipes >

    No water pipes : No scale (use refrigerant) Need to clean the water pipesSystem efficiency drop & origin of germs

    After 2~3year After 5~6year After 7~8year10% 25~30% 35~40%

    thickness of scale

    Energy Loss

    Unit : mm

    Unit : %

    (For Chiller) Maintenance & cleaning periodically by exclusive c(For Chiller) Maintenance & cleaning periodically by exclusive companyompany

    Design CommissioningOperation MaintenanceMaintenanceInstallation Reliability

    Scale cleaning5. Maintenance Comparison

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 14

    Maintenance Staff5. Maintenance Comparison

    Design CommissioningOperation MaintenanceMaintenanceInstallation Reliability

    MaintenanceStaff

    Feature Chiller system MULTI V III (VRF)

    (For Chiller) Certified maintenance staff is needed(For Chiller) Certified maintenance staff is needed

    No need special maintenance staff. Economic and easy maintenance

    The system requires certified maintenance staff not only for chillers but also pumps, boilers, cooling towers etc.

    More expensive maintenance cost.

    < Maintenance Staff>

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 15

    Pipe Erosion6. Reliability Comparison

    Design CommissioningOperation MaintenanceInstallation ReliabilityReliability

    PipeErosion

    Feature Chiller system MULTI V III (VRF)

    (For Chiller) Certified maintenance staff is needed(For Chiller) Certified maintenance staff is needed

    Refrigerant does not cause corrosion thereforeno pipe damage occurred

    Pipe erosion can cause leakage. System capacity reduction. Brines use increase corrosion, anti corrosion

    additives needed

    < Water pipe leakage >

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 16

    Category Product Initial Cost(USD)Initial Cost(USD)Total

    Water Cooled C

    hiller

    Chiller Price 355,484

    877,097AHU / Cooling T ower / Pump, Pr

    ice148,065

    Installation 383,871

    VRVMulti V 874,498

    1,109,660Installation 235,161

    April 2008Cooling OnlyAir Duct Included

    Initial CostInitial Cost Running Cost Maintenance Cost Total cost

    Type of Building: Shopping Mall Total area 9,000 m2 : 6 storey Building :1,500 m2/floor Actual cooling area : 1,500 m2 * 80 % * 6 Floor = 7,200 m2 Cooling Load (Tr) / m2 : 700 Tr *12000 Btu/Hr = 1,166 Btu/m2

    Equipment : Water cooled chiller /Multi V unit- Water Cooled Chiller :Trane Water cooled chiller

    350 Tr x 2 set =700 Tr + 300 Back upPumps =400 Tr x 2 setAHU = 8000 CFM x 36 setCooling Tower =1200 Gpm x 3 +3 Back up

    - VRF System :LG Multi V Plus II48 Hp x 19 set=912 Hp 726 Tr

    Air conditioning time : Operation- 13 hour a day (09:00 ~ 22:00)- 30 days a month- average load by month

    Equipments & Installation costEquipments & Installation cost

    MULTI V vs Chiller7. Economic analysis

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 17

    Multi V running cost is 65 % compare to chiller

    Category Product

    RunningCost

    (USD)Tota l

    Water Cooled C

    hiller

    Chiller Price

    308,697AHU / Coolin g Tower / Pu

    mp, Price

    Multi V Price 200,158

    Based on KW data chiller/Multi VBased on, Thailand electrical standardARI-Air conditioning & Refrigeration Institute

    $0k

    $100k

    $200k

    $300k

    $400k

    year 2n

    d 4th 6th 8th 10th

    12th

    14th

    Chiller

    Multi V

    Running costSavings up to15th yr : 35%

    Chiller

    Multi V

    Electrical costElectrical cost

    MULTI V vs Chiller7. Economic analysis

    Initial Cost Running CostRunning Cost Maintenance Cost Total cost

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 18

    Category PriceMaintenance

    Cost(USD)Total

    Water Cooled C

    hiller

    Chiller Price

    32,177AHU / Cooling Tower / Pump,

    Price

    Multi V Price 11,468

    $0k

    $100k

    $200k

    $300k

    $400k

    year 2nd 4th 6th 8th 10th

    12th

    14th

    Chiller

    Multi V

    Chiller

    Multi V

    MaintenanceCost savings Up to 15th yr: 66%

    Maintenance breakdownChiller system -31 USD / Rt / yr.- 6 times/yrMulti V- 48 USD / Indoor / yr.- 6 times/yr

    - 145 USD / Outdoor / yr.- 6 times/yr

    Multi V maintenance cost is 24 % compare to chiller

    Maintenance costMaintenance cost

    MULTI V vs Chiller7. Economic analysis

    Initial Cost Running Cost Maintenance CostMaintenance Cost Total cost

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 19

    Category Chiller system VRF system Remarks

    Economic Analysis

    Initial cost (USD) 877,097 927,057

    Running cost (USD) 308,698 200,158

    Shopping mall 6F,

    9,000

    Maintenace cost (USD) 32,177 11,468

    Total cost (USD) 1,217,972 1,138,683

    BEP - 1.7 years

    7. Economic analysis

    Initial Cost Running Cost Maintenance Cost Total costTotal cost

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 20

    LCC (Life Cycle Cost for 15 years) : Chiller 5.99 M$ > Multi V 4.27 M$ (71%)BEP (Break Even Point) : 1.7 Years

    LCC (15 years) BEP

    1st year 2nd year 3rd year 4th year- 20K$

    +10K$

    +40K$

    +70K$

    BEP :1.7 Years

    $0k

    $1000k

    $2000k

    $3000k

    $4000k

    $5000k

    $6000k

    $7000k

    y

    e

    a

    r

    1

    s

    t

    2

    n

    d

    3

    r

    d

    4

    t

    h

    5

    t

    h

    6

    t

    h

    7

    t

    h

    8

    t

    h

    9

    t

    h

    1

    0

    t

    h

    1

    1

    t

    h

    1

    2

    t

    h

    1

    3

    t

    h

    1

    4

    t

    h

    1

    5

    t

    h

    Chiller

    Multi V

    Cost savings : 29%

    BEP :1.7 Years

    8. LCC

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 21

    Chiller Multi V

    1,228

    1,109877

    32

    308 200

    11

    1,3217%

    Product &Installation

    Maintenance

    Electrical Fee

    Chiller Multi V

    5,992

    23%15%

    8%

    77% 73%

    4%

    4,27435%

    Product &Installation

    Maintenance

    Electrical Fee

    Initial Cost (1st year) ( K US$ )

    LCC (15 years)

    8. LCC

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 22

    Type of building : Shopping mallWater cooled Chiller :350 TR x 2 set=700 Tr + 300Tr (back up)VRF system:48 Hp x 19 set = 912 Hp (726TR)Commercial Building : (Shopping Mall - 9,000 Total Area) - 6 storey building:1500 per floorActual cooling area : 1,500 * 80% * 6F = 7,200Cooling load(TR) / : 700TR * 12,000Btu/h/TR 7,200 = 1167 Btu/

    Capacity Price EA Sub total (THB) % Sub total (USD)350 RT 3,960,000 2 7,920,000 255,484 300 RT 3,100,000 1 3,100,000 100,000 400 RT 500,000 2 1,000,000 32,258 400 RT 500,000 1 500,000 16,129

    1200 GPM 100,000 3 300,000 9,677 840 GPM 90,000 3 270,000 8,710

    8,000 CFM 70,000 36 2,520,000 81,290 15,610,000 57% 503,548

    9,000,000 33% 290,323 2,900,000 11% 93,548

    11,900,000 43% 383,871 27,510,000 100% 887,419

    48 Hp 957,000 19 18,183,000 586,548 Indoor unit ceiling duct 10 Hp 91,355 90 8,221,950 265,224

    2,915 90 262,350 8,463 81,125 1 81,125 2,617

    141,570 1 141,570 4,567 1,650 57 94,050 3,034 3,300 38 125,400 4,045

    27,109,445 79% 874,498

    Indoor unit ceiling duct

    36,000 90 3,240,000 104,516 7,290,000 21% 235,161

    34,399,445 100% 1,109,660

    I lot

    back up cooling tower (open type)

    Duct working

    45,000

    back up chiller (screw type)

    Wired remote controllerCentrol controller (ACP)

    Centrol control software (AC Manager)

    Sub totalTotal (Product + Installation)

    Pump (Evaporator) + 1 back upAHU

    Outdoor unit

    Sub total

    130,645

    Y branchODU joint

    90 4,050,000

    VRF Sub total

    Sub total

    Outdoor unit

    Total (Product + Installation)

    Product

    Installationduct work

    piping & electrical work

    Water Cooled Chiller(Screwtype)

    Classification

    Pipe & InsulationValve & Acc.

    Power & Control

    Product

    Installation

    Chiller (screw type)

    Cooling tower (open type)

    Pump (Condenser) + 1 back up

    App. Cost estimation

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 23

    Energy consumption

    / unit

    Totalenergy

    consumption(kW) (kW)271 2 542

    14.9 2 29.84 Load 100% 75% 50% 25%55.2 6 331.2 Chillier 542 179 84 472.35 48 112.8 Others 474 474 474 474

    1015.84 Total 1016 653 558 521Outdoor Unit 48 HP-R410a 42 19 798Indoor Unit 10 HP CCD 0.8 90 72 Load 100% 75% 50% 25%

    870.0 VRF 870 609 287 165

    1330

    100% kW portion1% 100% 542 100% Used by Schedule 4.2.2 condition

    42% 75% 179.2 33% electrical charge in Thailand45% 50% 83.9 15% THB / month USD12% 25% 47.2 9% VRF 517,076 16,680

    Chiller 797,469 25,725 Gap 280,393 9,045

    Operationhours kWh / day kWh / month

    Operationhours kWh / day kWh / month

    0.1 113.1 3,393.0 0.1 132.06 3,961.78 5.5 3,325.1 99,754.2 5.5 3,565.60 106,967.95 VRF 200,158 5.9 1,679.5 50,386.1 5.9 3,262.78 97,883.37 Chiller 308,698 1.6 257.9 7,736.0 1.6 812.82 24,384.67

    13.0 5,375.6 161,269.3 13.0 7,773.3 233,197.8

    VRF system

    Cooling load portion IPLV100% cooling load

    VRF (MULTI V system) Chiller system

    75% cooling load50% cooling load25% cooling load

    VRF

    AHU-10 tr

    Total

    operating time / day (hours)operating day / month

    ChillerPower consumptionLoad

    operating cost 1 year

    Chiller system

    Category EA

    Total

    Power consumption under partial loadWater Cooled Chiller(Screwtype)

    Chiller-350 TrCooling tower-1260 GPM

    Pump-50 Hp

    App. Actual running cost

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 24

    Cost Unit350 RT 105,000 Baht/unit 2 210,000 400 RT 60,000 Baht/unit 2 120,000

    1200 GPM 15,600 Baht/unit 6 93,600 15 RT 2,000 Baht/unit 70 140,000

    2 persons 20,000 Baht/unit 12 240,000 803,600

    840 Hp 3,000 Baht/unit 90 270,000 Outdoor unit 4,500 19 85,500

    355,500

    THB USD RemarksChiller 997,500 32,177 6 times / year

    270,000 6 times / year85,500 6 times / year

    355,500 11,468

    Pump

    TotalVRF

    1500 THB / indoor unit, year4500 THB / ODU module, yea

    950 THB / RT, year

    Control engineer

    Chiller(Screwtype)

    Chiller (Screw type)Cooling tower

    AHU

    Total

    TotalVRF

    Indoor unit

    A noteCategory CapacityMaintenance cost

    EA Maintenancecost / year

    App. Maintenance cost

  • Copyright 2012 @LG Electronics / AC Company All Rights ReservedMULTI V III vs CHILLER 25

    ARI Released The New Standard in 2003

    Available through the ARI web site:WWW.ARI.ORG

    Portion by cooling load (%)Portion by cooling load (%)

    IPLVIPLVOROR

    APLVAPLV==

    0.010.01 + + 0.420.42 + + 0.450.45 + + 0.120.12A B C DA B C D

    11

    kW / kW (ARI Part load weighting factors)

    1% 1% 42% 45% 42% 45% 12%12%

    100% 75% 50% 25%100% 75% 50% 25%

    WEIGHTED (%)WEIGHTED (%)

    ARI550/590ARI550/590--20032003

    Cooling LoadCooling Load

    App. Energy efficiency (IPLV)

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25ARI Released The New Standard in 2003