Reference:Dongsheng Lu’s Normalization slides Normalization.
220,132,11KV Shutdown Normalization Procedure
-
Upload
arsalanhamid -
Category
Documents
-
view
220 -
download
0
Transcript of 220,132,11KV Shutdown Normalization Procedure
-
8/19/2019 220,132,11KV Shutdown Normalization Procedure
1/2
Carpediem Tech
Engr. Qazi Arsalan Hamid
1
220/132/11KV Shutdown Normalization Procedure :
At times of Shutdown, Both Earth
Switches -S2 and -S4 of main bus bar ,interlink earth switches -S6 and -S8 must
be at on position with breakers -S1,-S3,-S5
and -S7 are at off position. all off position
breakers must be verified before
commencing
operation/repair/maintenance work.
Ground Rods are best choice for checking
it.
-
8/19/2019 220,132,11KV Shutdown Normalization Procedure
2/2
Carpediem Tech
Engr. Qazi Arsalan Hamid
2
Shutdown normalization process :
Engineer must well aware of Team clearance for shutdown normalization. Safety personnel clearance is mandatory.
both breakers at 132/11KV Transformer must be remain in off position during normalization.
In good practice the earth switch (Isolators) are couple mechanically with Breakers , in the normalization case S2 and S4 will be off and
Breaker S1 or S3 will be at on position
after that make -S6 at off position
then put on -S5
after that make -S8 at off position
then put on -S7 (Transformer Primary Breaker )
now you can normalized transformer breakers, 1st primary then secondary , all feeders breaker must remain at off position during
normalization process