National Energy Board Presentation to the PRRD board 22 September, 2016
Brian Martin and Wayne Marshall
Handout D-1
September 22, 2016
1
• Who we are • Strategic Priorities • Pipelines Updates • Questions
Outline Handout D-1
September 22, 2016
2
Who we are Handout D-1
September 22, 2016
3
What We do Handout D-1
September 22, 2016
4
Energy Information and Engagement Handout D-1
September 22, 2016
5
• Safety of Canadians and Environment
• Regulatory Excellence • Engaging with Canadians
Strategic Priorities
Handout D-1
September 22, 2016
6
Safety and Protection of Canadians and the Environment
2015 Compliance Activities Inspections 142
Emergency Exercises 20
Emergency Procedures Manual Review
13
Compliance Meetings 137
Audits 6
Report Reviews 30
Total: 348
2015 Enforcement Actions Notices of Non-Compliance
143
Inspection Officer Orders 4
Safety Orders 8
Administrative Monetary Penalties (AMPs)
12
Handout D-1
September 22, 2016
7
Damage Prevention Shannon Neufeld [email protected] Emergency Management Graham Gibson [email protected]
Handout D-1
September 22, 2016
8
NEB Regulated Projects : Approved Company Name Project Title Summary of Facilities Status NOVA Gas Transmission Limited
Wolverine (Carmon Creek section) Loop
61 km of large diameter pipeline Company cancelled project (Sept 2016)
NOVA Gas Transmission Limited
North Montney Pipeline 306 km of large diameter pipeline
3 Compressor Station additions
Project delayed
NOVA Gas Transmission Limited
Boulder Creek South Lateral 2 Pipeline sections totaling 21 km Fall 2016 Construction expected
Pouce Coupe Pipe Line Ltd
Pouce Coupe Lateral 27km of 12 NPS pipeline Construction in progress
Westcoast Energy Inc. (Spectra)
High Pine Expansion 2 pipeline sections totaling 39 km of large diameter pipeline
Construction in progress
Westcoast Energy Inc. (Spectra)
Jackfish Lake Expansion 2 pipeline sections totaling 23 km of large diameter pipeline
Construction in progress
Handout D-1
September 22, 2016
9
NEB Regulated Projects : Under Consideration Company Project Summary of Facilities Status NOVA Gas Transmission Limited
2017 Expansion 5 pipeline sections totaling 230 km of large diameter pipeline
2 Compressor Station unit additions
Pending decision of the Governor in General
NOVA Gas Transmission Limited
Towerbirch Expansion 2 pipeline sections totaling 87 km of large diameter pipeline
NEB proceeding underway
Handout D-1
September 22, 2016
10
Other Projects/Work
1. Pipeline Abandonments, Deactivation and Decommissioning
e.g. NGTL Peace River Mainline Abandonment (under consideration)
2. Pipeline Sales and Purchases
e.g. NGTL Abersum Pipeline purchase (under consideration)
3. Operations and Maintenance Activities
e.g. pipeline replacements, vegetation management, cathodic protection, pipeline integrity
4. Post-construction Monitoring
e.g. air quality, noise, water and land reclamation monitoring
Handout D-1
September 22, 2016
11
Brian Martin, Director, Regional Office Vancouver [email protected] Tel: 604-666-3975 Cell: 604-360-5094
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016
Handout D-1
September 22, 2016