206-Inspection Request No. AM 101 - 29.06.15

4
INSPECTION REQUEST PROJECT: Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3 PROJECT NO: Job-230 CLIENT: M/s Osool Gulf Investment Co. REQUEST NO: J-230/ AM - 001 ISSUED TO: UNIQUE CONTRACTING CO L.L.C DATE: 29.06.2015 CONSULTANT: Al Saqf Engineering Consultancy DISCIPLINE: POST TENSIONING Sr. PROJECT MANAGER (UNIQUE): WE REQUEST THE INSPECTION OF THE FOLLOWING WORK: We hereby request you to kindly inspect the Stressing work of Upper Basement floor slab - Pour 5 X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT Sohail Khan (Site Incharge) Requested By : Ready for Inspection at Date: 30.06.2015 10:00 AM Signature of Sub-contractor (As applicable) Signed for and on behalf of Al Azaem Al Muttahida MAIN CONTRACTOR REMARKS Signed for and on behalf of the Consultant Resident Engineer Date : Signed for and on behalf of the Consultabt MEP Engineer Date : Notes: 1. A minimum of 24 hours notice is required prior to inspection time 2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable. Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C Revison-0 Date: 29th June 2015 Document # AM-101 Page 1 of 1 LOCATION : Upper Basement Floor Slab - POUR 5 ( Location Drawing Attached ) Approved as no Approve Rejected Revise & Re

description

q

Transcript of 206-Inspection Request No. AM 101 - 29.06.15

Page 1: 206-Inspection Request No. AM 101 - 29.06.15

INSPECTION REQUEST

PROJECT: Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO: Job-230

CLIENT: M/s Osool Gulf Investment Co. REQUEST NO: J-230/ AM - 001 ISSUED TO: UNIQUE CONTRACTING CO L.L.C DATE: 29.06.2015

CONSULTANT: Al Saqf Engineering Consultancy DISCIPLINE: POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):

WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work of Upper Basement floor slab - Pour 5

X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT

Sohail Khan (Site Incharge)Requested By :

Ready for Inspection at Date: 30.06.2015 10:00 AM

Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida

MAIN CONTRACTOR REMARKS

Signed for and on behalf of the Consultant Resident Engineer Date :

Signed for and on behalf of the Consultabt MEP Engineer Date :Notes:1. A minimum of 24 hours notice is required prior to inspection time2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0 Date: 29th June 2015 Document # AM-101 Page 1 of 1

LOCATION : Upper Basement Floor Slab - POUR 5 ( Location Drawing Attached )

Approved as notedApproved RejectedRevise & Resubmit

Page 2: 206-Inspection Request No. AM 101 - 29.06.15

INSPECTION REQUEST

PROJECT: Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO: Job-230

CLIENT: M/s Osool Gulf Investment Co. REQUEST NO: J-230/ AM - 002 ISSUED TO: UNIQUE CONTRACTING CO L.L.C DATE: 6th July, 2015

CONSULTANT: Al Saqf Engineering Consultancy DISCIPLINE: POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):

WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 6 & Pour 7

X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT

Sohail Khan (Site Incharge)Requested By :

Ready for Inspection at Date: 7th July, 2015 10:00 AM

Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida

MAIN CONTRACTOR REMARKS

Signed for and on behalf of the Consultant Resident Engineer Date :

Signed for and on behalf of the Consultabt MEP Engineer Date :Notes:1. A minimum of 24 hours notice is required prior to inspection time2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0 Date: 6th July, 2015 Document # AM-002 Page 1 of 1

LOCATION : Upper Basement Floor Slab - POUR 6 & POUR 7 ( Location Drawing Attached )

Approved as notedApproved RejectedRevise & Resubmit

Page 3: 206-Inspection Request No. AM 101 - 29.06.15

INSPECTION REQUEST

PROJECT: Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO: Job-230

CLIENT: M/s Osool Gulf Investment Co. REQUEST NO: J-230/ AM - 003 ISSUED TO: UNIQUE CONTRACTING CO L.L.C DATE: 22th July, 2015

CONSULTANT: Al Saqf Engineering Consultancy DISCIPLINE: POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):

WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 4

X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT

Sohail Khan (Site Incharge)Requested By :

Ready for Inspection at Date: 23th July, 2015 10:00 AM

Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida

MAIN CONTRACTOR REMARKS

Signed for and on behalf of the Consultant Resident Engineer Date :

Signed for and on behalf of the Consultabt MEP Engineer Date :Notes:1. A minimum of 24 hours notice is required prior to inspection time2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0 Date: 7th July, 2015 Document # AM-003 Page 1 of 1

LOCATION : Upper Basement Floor Slab - POUR 4( Location Drawing Attached )

Approved as notedApproved RejectedRevise & Resubmit

Page 4: 206-Inspection Request No. AM 101 - 29.06.15

INSPECTION REQUEST

PROJECT: Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO: Job-230

CLIENT: M/s Osool Gulf Investment Co. REQUEST NO: J-230/ AM - 004 ISSUED TO: UNIQUE CONTRACTING CO L.L.C DATE: 8th Aug, 2015

CONSULTANT: Al Saqf Engineering Consultancy DISCIPLINE: POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):

WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 2

X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT

Sohail Khan (Site Incharge)Requested By :

Ready for Inspection at Date: 9th Aug, 2015 10:00 AM

Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida

MAIN CONTRACTOR REMARKS

Signed for and on behalf of the Consultant Resident Engineer Date :

Signed for and on behalf of the Consultabt MEP Engineer Date :Notes:1. A minimum of 24 hours notice is required prior to inspection time2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

LOCATION : Upper Basement Floor Slab - POUR 4( Location Drawing Attached )

Approved as notedApproved RejectedRevise & Resubmit