2021 CONSTRUCTION PROJECTS

1
2021 CONSTRUCTION PROJECTS 0.0 0.5 1.0 1.5 2.0 2.5 Water Main Replacement Hydrant Painting and Flow Testing LEGEND Water PETERBOROUGH UTILITIES Water Construction Produced by the Peterborough Utilities GIS. 2021 Construction datum derived from GeoMedia GIS warehouse. ERRORS and OMISSIONS: Bring any verified errors and omissions to Engineering GIS for revisions. June 1st, 2021 - R4 1 Site Number See Water Construction Table 1 for details D4527 0.0 0.5 1.0 1.5 km mi km mi Water Main Structural Lining HYDRANT PAINTING AND FLOW TESTING NORTH EAST QUADRANT Contact John Ellison @ 1239 1 3 4 5 6 2 10 9 8 7 Water Main New Construction Water Tower Coating Replacement 1 High St. Coating Replacement Higher St Tower Rehabitation Kevin Conlin 1296 2 Nassau Mills Rd. Armour Rd. Pioneer Rd. New Construction Clean Tech Commons Brad Nurse 1318 3 Townsend St. George St. Bethune St. COP Contract - Eliminate Dead End - Casing pipe Steve Billings 1242 4 Bethune St. Townsend St. Dublin St. COP Contract - Replacement with Services Steve Billings 1242 5 Willowcreek Subdivision John Boddy Developments Ltd. - Subdivision Steve Billings 1242 6 Lily Lake West Subdivision Durham Building Corp. - Subdivision Steve Billings 1242 7 AppleGrove Ave. Highland Rd. Chemong Rd. COP Contract - Replacement with Services John Ellison 1239 8 Parkhill Rd West Wallis Dr. Pinehill Dr. Structural Lining (CIPP) John Ellison 1239 9 Stannor Dr. Sherbrooke St. Albertu Ave. Structural Lining (CIPP) John Ellison 1239 10 Burnham Meadows Subdivision Safe Harbour Developments Inc. Steve Billings 1242 TABLE 1: 2021 Water Construction Site # Street From To Project Contact 705.748.9301

Transcript of 2021 CONSTRUCTION PROJECTS

2021 CONSTRUCTION PROJECTS

0.0 0.5 1.0 1.5 2.0 2.5

Water Main Replacement

Hydrant Painting and Flow Testing

LEGEND

Water

PETERBOROUGH UTILITIES

Water Construction

Produced by the Peterborough Utilities GIS. 2021 Construction datum derived from GeoMedia GIS warehouse.ERRORS and OMISSIONS: Bring any verified errors and omissions to Engineering GIS for revisions. June 1st, 2021 - R4

1 Site NumberSee Water Construction Table 1 for details

D4527

0.0 0.5 1.0 1.5

km

mi

km

mi

Water Main Structural Lining

HYDRANT PAINTING

AND FLOW TESTING

NORTH EAST QUADRANT

Contact John Ellison @ 1239

1

3

4

5

6

2

10

9

8

7

Water Main New Construction

Water Tower Coating Replacement

1 High St. Coating Replacement Higher St Tower Rehabitation Kevin Conlin 1296

2 Nassau Mills Rd. Armour Rd. Pioneer Rd. New Construction Clean Tech Commons Brad Nurse 1318

3 Townsend St. George St. Bethune St. COP Contract - Eliminate Dead End - Casing pipe Steve Billings 1242

4 Bethune St. Townsend St. Dublin St. COP Contract - Replacement with Services Steve Billings 1242

5 Willowcreek Subdivision John Boddy Developments Ltd. - Subdivision Steve Billings 1242

6 Lily Lake West Subdivision Durham Building Corp. - Subdivision Steve Billings 1242

7 AppleGrove Ave. Highland Rd. Chemong Rd. COP Contract - Replacement with Services John Ellison 1239

8 Parkhill Rd West Wallis Dr. Pinehill Dr. Structural Lining (CIPP) John Ellison 1239

9 Stannor Dr. Sherbrooke St. Albertu Ave. Structural Lining (CIPP) John Ellison 1239

10 Burnham Meadows Subdivision Safe Harbour Developments Inc. Steve Billings 1242

TABLE 1: 2021 Water Construction

Site # Street From To ProjectContact

705.748.9301