2019 Street Improvement ProjectNeighborhood Meeting
February 7. 2019
1
Agenda
2
- Update on Feasibility Report
- Project Overview
- Project Schedule
Project Location
- Birchwood Road
- Lost Lake Court
3
Background
- Feasibility Ordered by City Council December 4, 2018
- Birchwood Road
- Lake Links Trail Project affects the design of Birchwood Road
- Deteriorating & aging watermain along Birchwood Road
- Portion of sanitary sewer needs to be replaced
- High water table
- Lost Lake Court
- Deteriorating pavement conditions
- Feasibility Presentation Before City Council on March 5, 2019
4
Birchwood Road
- Watermain & service line replacements
- Sanitary sewer replacement near intersection of Birchwood Road and
Wildwood Beach Road.
- City will repair/reline remaining sanitary sewer as part of sewer lining
project in 2020.
- Surface reconstruction
- Bituminous surfacing with concrete curb & gutter
- Travel lanes reduced to 10 feet to accommodate Lake Links Trail
- Parking restricted on both sides
5
Proposed Improvements – Birchwood Road
Lost Lake Court
- Surface reconstruction
- Bituminous surfacing with concrete curb & gutter in place of existing
bituminous curb
- Minor storm sewer adjustments
6
Proposed Improvements – Lost Lake Court
7
8
9
Wood Fence for Lake Links Trail
10
Proposed Improvements
Construction
- Access to driveways and Birchwood Road will be restricted
- Expect detours during the day
- Road and driveway access will be restored at end of day
- Working hours are 7:00 AM to 7:00 PM Monday – Friday, 8:00 AM to 5:00
PM Saturday (if needed)
- The City will communicate with periodic newsletters and door hangers
- Neighborhood Meeting prior to construction
11
Special Assessments
12
Special Assessment Policy
Special Assessments are Proposed for Properties Receiving Benefit from Improvements
Surface Improvements
- Unit rate for single family homes & duplexes
- Front foot for commercial, industrial, tax-exempt and multi-family residential
13
Special Assessments: Surface Improvements Only
Single Family/Duplex Assessment
- Complete Roadway Reconstruction: $6,850/Unit
- Partial Roadway Reconstruction: $4,450/Unit
- May be paid up front or assessed with property taxes over 10 years
- Interest rate TBD at time of bond sale
- Senior citizen/disabled persons deferral available
14
Special Assessments
- Lots adjacent to streets receiving
improvements are proposed to be assessed
- Single Family/Duplex (Per Unit)
- Complete Reconstruction:
$6,850/Unit
- Partial Reconstruction:
$4,450/Unit
15
1 unit
Street A
1/2 unit
1/2
un
it
Street X
Stre
et Y
Special Assessments (cont.)
- Assessments will be considered at a separate hearing following construction.
- Assessments:
- May be prepaid or
- Levied over 10-year period to property taxes
- Deferment options are available for property owners age 65+ and on fixed
income
16
Project Schedule
17
Project Schedule
18
Action Date
Authorize Feasibility Report December 4, 2018
Neighborhood Meeting February 7, 2019
Accept Feasibility Report March 5, 2019
Public Hearing & Order Project- Time to voice concerns about the project to the City
Council
April, 2019
Construction Summer/Fall 2019 or Spring 2020
Assessment Hearing Following Construction
THANK YOU