Teacher’s E-learning Readiness Scale (TELRS): Development ...
2017/2018 Winter Generator Readiness Seminar · ISO-NE PUBLIC W E D N E S D A Y , N O V E M B E R 0...
Transcript of 2017/2018 Winter Generator Readiness Seminar · ISO-NE PUBLIC W E D N E S D A Y , N O V E M B E R 0...
ISO-NE PUBLIC
W E D N E S D A Y , N O V E M B E R 0 1 , 2 0 1 7
ISO New England System Operations
2017/2018 Winter Generator Readiness Seminar
ISO-NE PUBLIC
Welcome
• ISO New England is here to work with you as partners ensuring reliable and efficient operations of the Bulk Electric System for this coming winter and beyond
• ISO New England recognizes that we CAN NOT do this with out a coordinated response to expected conditions this winter
• If we can’t get answers today, we will take back questions and get answers and publish on line
2
ISO-NE PUBLIC
3
Agenda
Topic Presenter Opening Remarks
New England Winter Operations Summary John Norden
Director, Operations Winter Preparedness Review Review of 2016/17 Winter Ops, Weather, and Winter Reliability Solutions Program
Capacity Outlook
2017/18 Winter Capacity, Natural Gas Pipeline Outlook, Offer Flexibility,
Control Room’s Role during Normal, Abnormal, and Emergency
Conditions, FERC Pipeline Communication & Information Policy Mike Knowland
Supervisor, Forecasting and Scheduling
Winter Outlook Weather and Loads
NERC Lessons Learned and Generator Freeze Protection Readiness
John Norden
Winter Reliability Solutions Stephen George
Manager, Operational Performance, Training & Integration
Dual Fuel Testing Jim Nichols
Lead Analyst, Asset Registration & Auditing
Demand Response Service Chad Nelson
Manager, Asset Registration & Auditing
OP-21 Actions During an Energy Emergency John Norden
Review of OP-21 Fuel Survey Process Josh Lenzen
Supervisor, Operations Analysis & Integration
ISO-NE PUBLIC ISO-NE PUBLIC
WINTER PREPAREDNESS REVIEW WINTER 2016/17 WEATHER, ENERGY, AND PEAK LOADS John Norden
4
ISO-NE PUBLIC
Winter 2016/17 Weather, Energy and Peak Loads* • December 2016: Colder than previous December
– Energy demand of 10,884 GWh is 6.8% higher than December 2015 – Peak load of 19,647 MW is 7.9% higher than December 2015 – Peak occurred on December 15, 2016 at HE 18:00 at 18O F
• January 2017: Milder than previous January – Energy demand of 10,724 GWh is -2.6% lower than January 2016 – Peak load of 19,592 MW is 0.7% higher than January 2016 – Peak occurred on January 9, 2017 at HE 18:00 at 17O F
• February 2017: Milder than previous February – Energy demand of 9,440 GWh is -6.8% lower than February 2016 – Peak load of 18,165 MW is -7.1% lower than February 2016 – Peak occurred on February 9, 2017 at HE 19:00 at 18O F
• March 2017: Colder than previous March
– Energy demand of 10,439 GWh is 6.3% greater than March 2016 – Peak load of 17,502 MW is 0.9% higher than March 2016 – Peak occurred on March 15, 2017 at HE 20:00 at 23O F
(*) – All data obtained from the ISO-NE Net Energy and Peak Load Report located at: https://www.iso-ne.com/isoexpress/web/reports/load-and-demand/-/tree/net-ener-peak-load
5
ISO-NE PUBLIC
New England Winter Daily Average Temperature
6
-5
5
15
25
35
45
55
65
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91
Tem
per
atu
re (
ᴼF)
New England Winter Average Daily Temperature (ᴼF): 12/1 - 2/29 Each Month Sorted Low to High
Winter 2014/15 Winter 2015/16 Winter 2016/17
Colder Milder Milder
ISO-NE PUBLIC
New England Winter Daily Average Temperature
7
-5
5
15
25
35
45
55
65
Tem
per
atu
re (
ᴼF)
New England Winter Average Daily Temperature (ᴼF): 12/1 - 2/29
Winter 2014/15 Winter 2015/16 Winter 2016/17
ISO-NE PUBLIC
Winter 2016/17 Reliability Program (As of the Start of the Program on December 1, 2016)
• Oil Program – Participation from 84 units – 3.052 million barrels of the total inventory on December 1 were eligible
for compensation per the winter reliability program rules – Total oil program cost was $30.3M
• LNG Program – Participation from 2 units, representing 171,000 MMBTU – Total LNG program cost was approximately $277,868
• DR Program – Participation from 6 assets providing 23.0 MW of interruption capability – Total DR program cost was $126,480
Ref: https://www.iso-ne.com/markets-operations/markets/winter-program-payment-rate
9
ISO-NE PUBLIC
Winter 2016/17 Reliability Program Usage
• Winter Program Oil Inventory Use • Dec 2016: 121,091 bbl
• Jan 2017: 52,010 bbl
• Feb 2017: 72,401 bbl
• Mar 2017: 3,797 bbl
• Winter Program LNG Use: • December 2016 through March 2017 = None
• Winter Program DR Use (Events): – December 2016, February & March 2017 = None – January 10, 2017: 1 event - 6:39 AM – 9:04 AM, all assets dispatched
(Pre-OP4 real-time-only cuts due to transmission/generation outages)
• Final Program Ending Oil Eligible Inventory
– 3,034,668 BBLs
10
ISO-NE PUBLIC
Winter 2016/17 Electric Operations Review
Event Type
December 2016
January 2017
February 2017
March 2017
OP4 None None None None
MLCC2 (Reason)
December 16 (Cap. Def. – All N.E.)
None February 9 (Severe Weather)
March 13-14 (Severe Weather)
Peak Load Date (H.E.)
19,647 MW Dec 15 (18:00)
19,592 MW Jan 9
(18:00)
18,165 MW Feb 9
(19:00)
17,502 MW Mar 15 (20:00)
Minimum Generation Warning/Event
None None None None
14
ISO-NE PUBLIC
Winter Electric Operations Summary
• While system operations this past winter were relatively uneventful, challenges remain for future winters with fuel security and pending and actual retirements
• World LNG prices and contracts have an impact on how much fuel shows up in New England – Increased LNG injections are very helpful in maintaining grid reliability
• The Winter Reliability Program was instrumental in augmenting liquid fuel security for the region – This winter will be the last Winter Reliability Solutions Program – Pay-For-Performance market design becomes effective in June 2018
15
ISO-NE PUBLIC
Winter 2016/17 Gas Operations Review
• Over the winter 2016/17, regional natural gas pipelines declared: – 6 Unplanned Outages – All related to partial or full compressor station
outages – 15 - 20 Critical Notices (CNs) or Operational Flow Orders (OFOs) – All
related to extreme weather
• The Critical Notices/OFOs posted during this winter were typical for natural gas pipeline operations during most winters
17
ISO-NE PUBLIC
Winter 2016/17 Natural Gas Sector Highlights
• Spectra Energy put the majority of the AIM project (245,000 Dth/d) into service on November 1, 2016, and subsequently put the final piece (Hudson River crossing = all 342,000 Dth/d) into service on January 7, 2017
• Spectra Energy put the Salem Lateral into service on November 1, 2016
• February 27, 2017 – The Spectra Energy – Enbridge company merger was completed
• The Connecticut Expansion project (72,000 Dth/d) on Tennessee Pipeline was delayed until 2018
• March 27, 2017, FERC gave Algonquin Transmission LLC permission to begin building its Atlantic Bridge gas project connecting points in New Jersey and New York with New England and Canada’s Maritime provinces. Approval was for Connecticut facilities only.
• Several open seasons took place for gas pipeline capacity releases (for the off- peak season of April - November)
19
ISO-NE PUBLIC
Capacity Outlook
• Forecasted loads are similar to last year – 50/50 forecast is 21,197 MW – 90/10 forecast is 21,895 MW – All-time winter peak load was 22,818 MW on January 15, 2004
• Forecasted loads from last year (mild winter) – 50/50 forecast was 21,340 MW – 90/10 forecast was 22,029 MW – Actual peak was 19,673 MW on December 16, 2016
• Winter energy and peak loads have been decreasing over the past few years due to an increase in energy efficiency and distributed, behind-the-meter generation, primarily solar
22
ISO-NE PUBLIC
Peak Load Trend
Source: Forecast Data 2017 | https://www.iso-ne.com/static-assets/documents/2017/05/forecast_data_2017.xlsx
23
ISO-NE PUBLIC
Capacity Outlook
• Operable Capacity surplus on the 50/50 forecast and the 90/10 forecast, using Capacity Supply Obligation – Includes CSO from OP 4 Actions
• 50/50: surplus 1,448 MW (1,060 MW Surplus, pre-OP 4) • 90/10: surplus 347 MW (41 MW Deficiency, pre-OP 4)
– Eco Max offers are consistently above CSO • Can range from 1,500 to 4,000 MW • Approximately 2,500 MW difference between SCC and CSO
24
ISO-NE PUBLIC
Operational Capacity Analysis
• (+) Total Supply (CSO) – Generators – Demand Resources dispatchable within OP-4 – external capacity transactions
• (–) Demands and Supply Reductions – Planned and unplanned outages – Gas related outages (also unplanned) – Peak load and reserve requirements
25
ISO-NE PUBLIC
Where to find this information
• Most recently available data is in the COO report every month – Posted to the ISO New England website
• Committees and Groups > Participants Committee
• Look for COO Report from each month
28
ISO-NE PUBLIC
Abnormal / Emergency Situations OP 4 Actions
• Notifications • Begin to allow depletion
of 30 min Reserve • Power Caution
5% Voltage Reduction < 10min
• Request all customer generation not contractually available to MP.
• Request voluntary load curtailments.
Dispatch Real-Time Demand Response
as necessary.
Request Generating Resources not subject to
a CSO to voluntarily supply energy for reliability.
• Radio and Television Appeals
• Power Warning
Voluntary Load Curtailment by Participants
• 5% Voltage Reduction > 10 min.
• Dispatch Real-Time Emergency Generation Resources.
Governor Appeals
Power Watch Arrange to purchase
emergency power and capacity
1
2
3
4
8
7
6
5
9
10
11
29 Demand Response Voltage Reduction Appeals
ISO-NE PUBLIC
New England Natural Gas Infrastructure Overview Map
Source: U.S. Energy Information Administration based on Ventyx’s Energy Velocity Suite
32
ISO-NE PUBLIC
New England Gas Flow Estimates – Peak Days
• Western supply at capacity every day – Southeast Compressor Station (Algonquin) – Station 254 (Tennessee)
• Additional Pipeline Supply (when available) – Waddington (Iroquois) supply to NY – Pittsburg (PNGTS) depending on Montreal Temperature / gas demand
• Deep Panuke – Expecting approximately 50,000 MMBtu per day on average
• Sable Island (volumes per the National Energy Board) – Last Winter: Approximately 125,000 MMBtu per day – This Winter: Projecting 85,000 MMBtu per day on average
• Northeast Gateway Deepwater Port – Cargoes are possible at the Excelerate hub line connection for injection
into the Algonquin Pipeline, up to 400,000 MMBtu per day
33
ISO-NE PUBLIC
34
Pipeline Expansion Projects
• Algonquin Incremental Market (AIM) – 342,000 MMBtu/d expansion of the Algonquin pipeline – In service in 2016 – Fully subscribed
• Atlantic Bridge – 132,700 MMBtu/d expansion of Algonquin pipeline
• Pipeline expansion • Compressor upgrades: replacement and new construction
– Expected in-service date: November 2017 – Fully subscribed
• Connecticut Expansion – Approximately 72,000 MMBtu/d expansion of the Tennessee pipeline – In service by 11/1/2016 Delayed
ISO-NE PUBLIC
New England Gas Flow Estimates
• Sable Island Production – Source: Canada-Nova Scotia Offshore Petroleum Board
35
ISO-NE PUBLIC
New England Gas Flow Estimates
• Deep Panuke Production – Source: Canada-Nova Scotia Offshore Petroleum Board
36
ISO-NE PUBLIC
Canaport Send Out Last Two Winters
• Expect facility to deliver on peak days similar to last winter
37
ISO-NE PUBLIC
Fuel Price Volatility and Offer Flexibility
• Offer Flexibility allows for Generators to update offers intraday as fuel prices fluctuate on spot market
• For a more detailed overview of the Energy Market Offer Flexibility (EMOF) project, visit http://www.iso-ne.com/static-assets/documents/support/training/courses/energy_mkt_ancil_serv_top/energy_market_offer_flexibility_06_2014.pdf
40
ISO-NE PUBLIC
Offer Parameter Flexibility
• Most parameters can be offered on an hourly granularity and re-offered or redeclared throughout the course of the day – Generator limits can be redeclared – Prices and Fees can be re-offered
• Gives Market Participants ability to proactively adjust offer parameters in response to changes in fuel prices
41
ISO-NE PUBLIC
Timeline – Daily Routine
ISO New England Activity Time Gas Procurement Schedule
Final Load Forecast Published ≤ 09:30
DAM bidding window closes 10:00
DAM results published Re-offer period opens
≤ 13:30
Re-offer period closes RAA Process begins
14:00 Timely Cycle Nomination Deadline
RAA Process completed ≤ 17:00
Intraday Re-offer window opens 18:30
19:00 Evening Cycle Nomination Deadline
42
ISO-NE PUBLIC
Commitment Decisions (review)
• Hourly Reoffers makes it possible for changing supply offers intraday
• Increases complexity of commitment process
• NCPC calculations based on offers in place at time of commitment and dispatch
• Necessitates the concept of a Commitment Decision (CD) – Identify the components of the supply offer in place at the time of
commitment – Ensure proper cost allocation through Settlements – Snapshots the offer price at the time of commitment
43
ISO-NE PUBLIC
CD Components
• A CD consists of the following – Start and End hours for a Generator commitment – Supply offer data in effect at the time of commitment – Commitment Reason (e.g. Capacity, Voltage Support, RMR, etc…) – Reliability Region (if applicable)
44
ISO-NE PUBLIC
Normal Operating Conditions
• Collect Pipeline Bulletin Board Data – After the RAA process is completed, run (2) Nominations Reports for
the overlapping gas day and electric day • DE for every Generator that has not nominated and scheduled adequate
gas to their meter will be contacted and requested to confirm if gas will be scheduled
• The information provided in the reports, the information from the Generator, and all known interstate pipeline conditions will be used to determine if supplemental Generator commitments are required to ensure reliability
47
ISO-NE PUBLIC
Normal Operating Conditions, cont Forecaster Calls Plants showing Deficiency from Midnight to 10:00 am (Steps 4 through 8 in Attachment D) Collect Pipeline Bulletin Board Data, cont
Plant MWh Burned So Far MWh Before
Midnight MWh After Midnight MWh Scheduled MWh Surplus Gas Scheduled
1 2201 169 1932 4493 191 34600 2 777 0 663 0 (1440) 0 3 1910 0 901 2849 38 20700 4 2131 0 0 2736 605 20028 5 5903 403 0 7706 1400 53800 6 2369 0 798 3097 (70) 22500 7 1253 0 350 93 (1510) 1000 8 2402 185 1850 5129 692 45500 9 0 0 0 28 28 300
10 3 0 525 0 (528) 0 11 0 0 0 0 0 0 12 1 0 0 0 (1) 0 13 4 0 0 0 (4) 0 14 5077 389 2864 9591 1261 65621 15 3394 215 0 3347 (262) 25048 16 3554 550 6017 221 (9900) 1500 17 10639 797 4157 17418 1825 126540 18 7249 545 3892 11096 (590) 80813 19 972 45 1066 9 (2074) 100 20 0 0 0 0 0 0 21 0 0 0 0 0 0 22 6294 0 2476 1643 (7127) 17471 23 2758 0 1209 3944 (23) 30000 24 2400 250 1250 579 (3321) 5000 25 4998 0 2317 6917 (398) 52595 26 3208 250 1189 0 (4647) 0 27 2434 0 0 2747 313 23512 28 4222 0 0 5634 1412 42963 29 2121 0 0 2343 222 20000 30 0 0 0 0 0 0 31 1141 86 860 2344 257 27000 32 0 0 0 0 0 0 33 1071 0 3490 5037 476 38325 48
ISO-NE PUBLIC
Follow Up
• If sufficient gas has not been nominated and scheduled to the Generator meter – Assessments will be done to determine the impact on system
operations – ISO Control Room will call to inquire as to whether the Generator
intends to secure the requisite gas supply to match its dispatch
• It is always the responsibility of the DE to communicate any changes in Generator capability.
49
ISO-NE PUBLIC
Cold Weather Terminology and Criteria
• When Cold Weather conditions are met, public notifications are issued independent of M/LCC 2 notifications for Cold Weather Watch, Cold Weather Warning or Cold Weather Event.
• Cold Weather conditions are met when both of the following conditions are true simultaneously: The “Effective Temperature” is forecast to be < 0 F for any single on-peak hour and the “Effective Heating Degree Days” for the day are forecast to be > 65. This temperature and degree day criteria are based on a New England, eight city, load weighted average – Peak hours are considered: HE 08 through HE 23
• Effective Heating Degree Days = 68 – (avg of max and min Effective Temperature of the day)
• Effective Temperature = DryBulb – [ WindSpeed x ( 65 - DryBulb ) / 100
• Cold Weather Watch – Capacity forecast indicates a capacity margin greater than or equal to 1,000 MW.
• Cold Weather Warning – Capacity forecast indicates a capacity margin less than 1,000 MW.
• Cold Weather Event – Capacity forecast indicates a capacity margin less than or equal to 0 MW.
http://www.iso-ne.com/rules_proceds/operating/mast_satllte/mlcc2.pdf
50
ISO-NE PUBLIC
FERC Pipeline Communication/Info Policy (Review)
• January 11, 2014 FERC approval
• ISO-NE changed the Information Policy effective January 11, 2014
• Provides explicit authority to interstate natural gas pipelines and ISOs to share non-public, operational information with each other for the purpose of promoting reliable service or operational planning
• Permits transmission operators to share the information that they deem necessary to promote the reliability and integrity of their systems with each other.
• Parties are subject to a No-Conduit Rule that prohibits subsequent disclosure of that information to an affiliate or third party.
51
ISO-NE PUBLIC
Currently Sharing Fuel Burn Expectations Pipeline Specific/Plant Specific
A) Each evening after the RAA process is complete, the on-shift Forecaster 1) Prepares the Generator specific hourly fuel burns to each pipeline report to the
following pipeline contacts: a) Algonquin (AGT) b) Iroquois c) Maritimes and Northeast (M&N) d) Portland Natural Gas Transmission System (PNGTS) e) Tennessee Gas (TGP)
•Plant Specific Fuel Burn Expectation to Interstate Gas Pipelines •Determine the Generator Fuel Schedules
PIPELINE NAME Date: 7/21/2014 Note: Hourly Values Are in Dekatherms
Meter Name Meter # LDC 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Total
Plant A 700 N 562 1,748 2,372 2,541 2,541 3,458 3,458 3,458 3,458 3,458 3,458 3,458 3,458 3,458 3,458 3,458 1,178 48,978
Plant B 701 N 1,007 1,007 1,007 1,007 1,007 1,007 1,007 1,250 1,242 1,233 1,233 1,225 1,225 1,217 1,217 1,217 1,217 1,225 1,225 1,233 1,242 1,242 1,250 1,007 27,749
Plant C 702 N 5,122 5,122 5,122 5,122 5,122 5,122 5,122 3,698 5,122 4,352 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 5,122 120,730
Plant D 703 N 2,367 2,367 2,367 2,579 3,257 3,852 4,789 3,681 4,078 3,729 4,789 4,789 4,789 5,090 5,090 5,090 5,090 5,090 5,090 4,803 4,803 4,803 4,803 4,789 101,980
Plant E 704 N 71 212 354 495 637 707 707 707 707 707 1,061 1,061 1,061 1,061 859 859 707 11,973
Plant F 705 N 2,180 2,180 2,180 2,180 2,180 2,180 2,180 3,487 3,444 3,400 3,371 3,327 3,327 3,313 3,298 3,284 3,298 3,327 3,342 3,385 3,429 3,444 3,458 2,180 71,371
Plant G 706 N 1,489 1,489 1,489 1,489 1,489 1,498 1,489 1,064 1,064 1,064 1,454 1,445 1,436 1,427 1,427 1,427 1,427 1,427 1,436 1,445 1,454 1,462 1,471 1,480 33,839
Plant H 707 N 171 342 513 1,256 1,922 1,922 1,922 2,033 2,025 2,042 2,042 2,059 2,067 2,084 2,102 1,948 2,110 1,922 30,481
Plant I 708 N 3,689 3,689 3,689 3,689 3,689 3,689 3,689 3,683 3,689 3,683 3,689 4,205 4,205 4,205 4,205 4,205 4,205 4,205 4,205 4,205 4,205 2,096 2,096 2,096 88,905
Plant J 709 N 206 412 412 412 412 497 497 497 532 532 497 446 412 412 6,175
Total 15,854 15,854 15,854 16,066 16,814 17,560 19,363 19,447 22,365 22,376 25,241 26,612 26,603 27,069 27,400 27,402 27,451 27,506 27,301 27,040 26,933 23,986 21,489 18,596 542,183
52
ISO-NE PUBLIC
Currently Sharing Generator Planned Outages Pipeline Specific/Plant Specific
• Provide ISO-NE unit specific outage information to individual pipelines associated with those units. This information is shared on a 6 month forward looking basis in the interest of outage coordination between all parties concerned.
• ISO is actively coordinating pipeline and generator outages on a real-time and forward looking basis
53
ISO-NE PUBLIC
Anticipated Winter Highlights
• Above-normal probability of warmer than normal winter
56
ISO-NE PUBLIC
60
Normal and Record Temperatures
• Always the potential for very low temperatures
• Winter Ready?
ISO-NE PUBLIC ISO-NE PUBLIC
GENERAL PREPAREDNESS, NERC LESSONS LEARNED, & GENERATOR FREEZE PROTECTION READINESS
John Norden
62
ISO-NE PUBLIC
Review Previous Rule Changes
In preparation for winter, New England continues:
• Winter Reliability Solutions Program-Last Winter
• Accelerated Day-Ahead Market timing to better coordinate with gas day timing
• Increased reserve requirements and added Replacement Reserve requirements (120% of Largest, 50% of Second, 180 MW RR or as determined)
• Increased RCPFs ($250 RR, $1000 TMOR, and $1500 Ten plus $50 Spin)
• Tightened the FCM Shortage Event trigger to create better incentives for performance
63
ISO-NE PUBLIC
Previous Rule Change Review
• “Offer Flexibility” Hourly Markets
• The Commission clarification on generator obligations – For units, this includes the obligation to have inventory to meet
obligations: • Under Good Utility Practice, cost-of-service oil units keep sufficient inventory
to meet load
• The order confirms that capacity resources have a higher performance
obligation
• As oil cannot be procured “just in time,” oil-fired generators must make
arrangements in advance to ensure that they will have oil inventory sufficient
to produce energy when dispatched this winter
• On most days Natural Gas is available in the east from LNG suppliers
• Limited Energy Option should only be used when no fuel is available and not
as an economic option and consultation with the Market Monitor is
encouraged
64
ISO-NE PUBLIC
Other Preparations for Winter – Coordination and Communication
ISO-NE continues to step up communications through:
• Regular conference calls with NPCC Reliability Coordinators
• Pre-winter conference calls with the Northeast Gas Association – Emphasized importance of maintaining close coordination regarding
outages
• Regular communications with gas pipelines – Information Policy changes were made to improve gas-electric
coordination per FERC Order 787
• Winter generation readiness seminar – That’s why we are here
• Fuel surveys – Initially monthly; can become twice-weekly and daily at different points in
the winter
• New NERC Guideline on Gas and Electric Coordination should be approved by Operating Committee in December 2017
65
ISO-NE PUBLIC
Transmission & Distribution
Load shed plans consider
• Electric generators
• Gas wellheads
• Gas pipeline compressors
• Gas gathering facility
• Hospitals
• Other critical / essential loads
Voltage Reductions tested 10/26/17
66
ISO-NE PUBLIC
ISO-NE Actions & Plans
Identify critical NG supply facilities – don’t shed loads like: – Compressor stations – Gathering facilities – Processing plants
MLCC 16 – Seasonal Preparations
• Assess generator outages
• Gas pipeline communications
• Transmission System Preparedness – GIS Readiness – ACB Readiness – Voltage Reduction Test – Infrared Testing – Maintenance – Aerial and Foot Patrols
67
ISO-NE PUBLIC
New England Actions
• Generator audits
• Dual fuel testing
• Black start resource testing
• Monthly, Weekly, Daily generator fuel surveys
• Daily calls to dual-fuel generators
• Increased monitoring of gas pipeline maintenance
• Direct communication with pipeline operators
68
ISO-NE PUBLIC
ISO-New England Communications
• Expedited updates to government and news media
• Media Affairs
• Press releases
• Web site: – Power system conditions – Notices – ISO Express
69
ISO-NE PUBLIC
71
Normal and Record Temperatures R U Ready
• Always the potential for very low temperatures
• Winter Ready?
ISO-NE PUBLIC
Generator Planning
• Plant-specific Winter Readiness Plan
• Ensure adequate winter supplies of fuel
• Freeze protection per guidelines
• Access to primary and secondary fuel
• Verify fuel switching capability
• Environmental Permits In Place
• Notify the ISO when constraints arise
72
ISO-NE PUBLIC
Generator Planning (continued)
• Monitor heat tracing
• Consider increased staffing during severe weather
• Develop plant-specific operating plans
• Wind barriers to protect instrument cabinets & sensing lines
These recommendations are consistent with NERC’s Winter Preparedness Guidance – These are things all generators can do to get ready for severe weather.
73
ISO-NE PUBLIC
Further Resources
• The industry has reached a level of understanding of winter operations that prepares us for what may happen
• NERC.COM – Report on February 1-5, 2011 Southwest Cold Weather – Lessons Learned -Southwest Cold Weather Event – Polar Vortex Review – Previous Cold Weather Event Analysis – Reliability Guideline: Generating Unit Winter Weather Readiness – NERC Cold Weather Training Packet Refresher
74
ISO-NE PUBLIC
Winter Reliability Solutions 2017/2018
Winter Reliability Solutions program is: • Documented in Market Rule 1, Appendix K • Appendix K is unchanged from last winter • Current program effective through 3/15/2018 • Bridge to Pay for Performance
77
ISO-NE PUBLIC
Winter Reliability Solutions Program Services
The program is made up of 4 services:
1) Oil Fuel Service 2) Liquefied Natural Gas Service 3) Dual Fuel Commissioning Service 4) Demand Response Service
78
ISO-NE PUBLIC
Winter Reliability Solutions Eligibility Requirements For Oil & LNG Service
• Participating Generator Assets must: – Be located in New England – Be modeled in the EMS – Be dispatchable per OP-14 or Self-Scheduled for the entire winter
period – offer into the Day-Ahead and Real-Time Energy Markets at EcoMax for
each hour of the Operating Day during the obligation period
• Participants may not sell the fuel (or fuel rights) during the obligation period
• Generator Assets must have notified ISO of intent to participate by October 1
79
ISO-NE PUBLIC
Winter Reliability Solutions Oil Fuel Service
Purpose
• Incent oil-fired Generator Assets to secure a fuel supply as of December 1 and to provide compensation to mitigate a portion of the costs related to unused fuel at the end of winter
80
ISO-NE PUBLIC
Winter Reliability Solutions Oil Fuel Service
• Generators with a shared fuel supply must participate in aggregate – Inventory of all shared fuel tanks will be aggregated
• Tanks OOS for the winter period may be excluded
• Generators OOS for the winter period may be excluded
81
ISO-NE PUBLIC
Winter Reliability Solutions Oil Fuel Service
• Generator Assets will report inventory levels on December 1, January 1, February 1, March 1, and March 15
• ISO will assess December 1 inventory for eligibility – Minimum eligible inventory is lesser of 85% of usable fuel storage
capability or supply needed for 10 days continuous operation at WSCC – Maximum eligible inventory is lesser of 95% of usable fuel storage
capability or supply needed for 10 days continuous operation at WSCC
• Oil burned from November 15 will be credited to December 1 level
82
ISO-NE PUBLIC
Winter Reliability Solutions Oil Fuel Service Compensation
• Formula for compensation = (Eligible Inventory * Set Rate) * Performance Adjustment
• Eligible Inventory is the lesser of:
• Actual December 1 Inventory • Maximum December 1 Inventory (95%/10 days) • March 15 Inventory (less oil added after Feb 1 that is sold before
Nov 30 2018)
• Performance adjustment is the percentage of winter hours where the asset is fully or partially available or unavailable due to a transmission outage
• Set Rate is $10.33/Barrel
83
Winter Program Payment Rate Reference: https://www.iso-ne.com/markets-operations/markets/winter-program-payment-rate
ISO-NE PUBLIC
Winter Reliability Solutions Liquefied Natural Gas Service
Purpose
• Incent gas-fired Generator Assets to secure a fuel supply from an LNG provider as of December 1 and to provide compensation to mitigate a portion of the costs related to unused fuel at the end of winter
84
ISO-NE PUBLIC
Winter Reliability Solutions LNG Service Contracts
• Proposed contract submitted to ISO by October 1
• Specify parties , volume and commitment to meet Appendix K requirements
• ISO provisionally accepts up to 6 BCF on a first come/first served basis
• Assets would be notified of acceptance by October 15
85
ISO-NE PUBLIC
Winter Reliability Solutions LNG Service Contracts
• Finalized contracts submitted to ISO by December 1 specifying
• Take or pay construct
• Volume and ability to call entire volume between December 1 and February 28
• Delivery point , gas meter number and pipeline transport
• Failure to meet all of these results in ISO acceptance withdrawal
86
ISO-NE PUBLIC
Winter Reliability Solutions LNG Service Measurement
• Remaining available volume must be reported to ISO Customer Service on the first of December, January, February, March and as otherwise requested.
87
ISO-NE PUBLIC
Winter Reliability Solutions LNG Service Compensation
• Formula for compensation = (Unused Quantity* Set Rate) * Performance Adjustment
• Unused Quantity is the lesser of December 1 and March 1 contract
volumes capped at amount of fuel need to operate continuously for 4 days at WSCC
• Performance adjustment is the percentage of winter hours where the asset is fully or partially available or unavailable due to a transmission outage
• Set Rate is $1.72/MMBTU
88
ISO-NE PUBLIC
Winter Reliability Solutions Qualified Inventories*
– Oil Service participation 84 units – 2.848 M Barrels
– LNG participation 0 units
– Actual qualifying inventories will be determined on December 1
*Note that these are preliminary numbers subject to review and revision Source: http://isonewswire.com/updates/2017/10/27/update-on-the-20172018-winter-reliability-program.html
89
ISO-NE PUBLIC
Shortage Event Triggers Summary
• System wide • 30 or more contiguous minutes of Ten Minute Non Spinning Reserve
constraint pricing • 30 or more contiguous minutes of both Thirty Minute Operating
Reserve constraint pricing and implementation of OP-4 Action 2 (RTDR activation)
• Shortage events are not triggered by deficiencies in Replacement Reserves
• Import Constrained Capacity Zone • For an Import Constrained Capacity Zone (CT, SWCT, NEMA/Boston),
30 or more contiguous minutes of both Local TMOR constraint pricing and OP-4 Action 2 implementation or any OP-7 event that is not declared for the rest of the system
• Under Pay for Performance, effective 6/1/18, a Capacity Scarcity Condition will occur with the first five minute deficiency interval
90
ISO-NE PUBLIC
Shortage Event Triggers
• Current triggers have been effective since November 3, 2013
• Last Shortage Event occurred on August 11, 2016 based on violation of the TMOR RCPF for over thirty contiguous minutes when Action 2 of OP-4 was implemented for a capacity zone.
91
ISO-NE PUBLIC
The Asset Registration and Auditing department is available to help. Contact information can be found
at the end of this presentation.
94
ISO-NE PUBLIC
95
Auditing of Dual Fuel Resources Background
• Market Rule 1, Section III.1.5.2 – ISO-Initiated Parameter Auditing allows for ISO to initiate audits of
operating parameters and dual fuel capability – Audits for dual fuel capability are announced and scheduled in
advance
• Dual Fuel Audits: – Confirm operational readiness of the Generating Asset on a specific
fuel – Verify the maximum capability on a specific fuel – Verify fuel switching information (switch time, on-line capable)
• ISO has chosen generators to perform dual fuel audits in the fall as part of winter readiness
ISO-NE PUBLIC
96
• Generators required to audit – Those chosen by ISO as part of winter readiness – Those required to audit annually as part of the Dual Fuel
Commissioning Service (Appendix K)
• Market Rule 1, Appendix K (Dual Fuel Commissioning Service): – Per MR 1.III.K.5, commissioned generators shall audit each year
through 2018 pursuant to Section III.1.5.2 of Market Rule to confirm capability to operate on oil and switch fuels within 8 hours
– Compensation shall not be received for more than one audit per year
Auditing of Dual Fuel Resources Fall 2017
ISO-NE PUBLIC
97
Auditing of Dual Fuel Resources Fall 2017
• Notifications were sent out in late September for generators requested to audit prior to December 1st
• Notifications included: – Instructions for scheduling an audit – Real time communication needs – Guidance for supply offers – Demonstration requirements
• Fuel or fuels on which generator must operate (typically start on gas, swap to oil and run 1 hour at EcoMax)
ISO-NE PUBLIC
98
Auditing of Dual Fuel Resources Scheduling the Audit
• Requests must be made via a CROW application with a follow-up call to the Short Term Outage Group no later than 9AM on the business day prior to the test
• CROW application – Must clearly indicate Dual Fuel Audit
• State that it is a Dual Fuel Audit in External Comments • Outages Cause Code = “615-Dual Fuel Audit Request” • Outage Priority = “Owner Testing”
– A test plan must be included with the application – Requests are subject to approval
ISO-NE PUBLIC
99
Auditing of Dual Fuel Resources Communications
• The generator’s Designated Entity must notify the ISO control room in real time of the following actions/times (as applicable): – Test Start – Fuel Swap Start – Stable on Oil at ECOMIN (End of Fuel Swap) – Completed 1 Hour at Max Output – Test Completion
• Notify the ISO NE control room of any changes to the auditing schedule ASAP and please realize that a generator may be dispatched up or down if system security conditions warrant or an emergency situation occurs.
ISO-NE PUBLIC
100
Auditing of Dual Fuel Resources
• A demonstration that meets the audit requirements may be submitted for consideration if the generator was otherwise committed without previously scheduling the testing – The generator would not be eligible for back-dated NCPC
compensation
ISO-NE PUBLIC
101
Auditing of Dual Fuel Resources Compensation/Offers
• Resources will be compensated through real time NCPC pursuant to Market Rule 1, Section III.F.3.2.1
• Offers – For the Real time Market, hourly offers in eMarket should reflect the fuel
and fuel blend percentages appropriately – Any supply offers made in the Day Ahead Market should reflect the
primary fuel
• A Market Rule revision took affect last fall allowing Day-Ahead committed generation to be eligible for real time NCPC for dual fuel audits.
• Failure to provide timely notification, a clear indication of the purpose of the test, and other required information including supply offers as described above may jeopardize proper compensation.
ISO-NE PUBLIC
102
Auditing of Dual Fuel Resources Results
• If audit was not successful: – Generator may be required to audit again – Provide a plan with actions and timelines to resolve issues – May elect to remove dual fuel capability from NX-12
• Generators commissioned via Dual Fuel Commissioning Service : – Subject to pay back of compensation as described in MR 1.III.K.5(g)
Failure to Meet Obligations
ISO-NE PUBLIC
Review
• On September 11, 2015 FERC approved the NEPOOL proposal for a Winter Reliability Program for the next three winter seasons (2015-2018)
• The DR opportunity is essentially identical to 2016-17 program, with a slightly higher payment rate for 2017-18
• Payment rate is determined annually and posted by July 15
• The Winter Reliability program is Appendix K of Market Rule 1, linked Here.
105
ISO-NE PUBLIC
106
Notice (deadline passed for 2017-18)
• Notice of Participation for each season is required by October 1 preceding the relevant season
• Notice includes: – Asset Name & Address or aggregation details – Electrical Location (p-node or dispatch zone for aggregations) – MW Quantity of demand reduction and any net supply – Methodology for load reduction/net supply – If details are not known on Oct. 1, a minimum of the MW, dispatch
zone, and how requirements will be met is required
• ISO may reject a registration based on deliverability or other grounds
ISO-NE PUBLIC
107
Eligibility and Operational Parameters
• Real-time Demand Response Assets with a demand response baseline reflecting load at the Retail Delivery Point – can have behind the meter generation capable of producing net
supply, so long as normal operation reflects load
• Not required to be part of a capacity resource – If part of capacity resource, performance must be incremental to CSO
• Available for dispatch 0500-2300 every day from December through February – minimum 100 kW, aggregations allowed within dispatch zone – performance cannot be from the incremental use of natural gas – able to respond to dispatch Instructions within 30 minutes
ISO-NE PUBLIC
• Must have a DDE, baseline built and ready to respond by December 1 – 5 minute metering at the Retail Delivery Point and at DG output
• Maximum 30 dispatches/season – Maximum 6 hours/dispatch – Maximum 2 dispatch/day with at least 4 hours in between
dispatches
• Dispatched in advance of or concurrent to OP4
• Metering for assets not mapped to capacity resources: – 5 minute interval meter data due within 2.5 days of operating day – Delivered via the Demand Response Market User Interface
(DRMUI)
108
Operational Parameters (Cont.)
ISO-NE PUBLIC
109
Weekly Capacity Forecast
• In addition to existing forecasting requirements for all FCM RTDR Resources, ISO requires a weekly forecast of – each asset’s estimated availability for the peak hour each week – incremental availability for an FCM resource with winter program
asset(s) mapped post winter program dispatch
• The form is provided by ISO to participating DDE’s
• Due by the first business day of each week December through February
• Any updates are also requested if local conditions change
ISO-NE PUBLIC
110
Sample: Winter Dema nd Response Reliability Program
Estimated Availability
OPERATING WEEK BEGIN :
Demand Designated Entity: A acme, Inc.
Asset / Resource ID
Winter Obligation MW
Asset Forecast Availability
Winter Program MW Peak Hour
Resource Forecast Incremental *
Availability OP 4 Action 2
MW Peak Hour
Asset 1 2.5
Asset 2 1.5
Resource A
Asset 3 10.0
* This i s the estimated additional MW available for an OP4 dispatch after a Winter Reliability event has
been called.
Sample dispatch instruction is as follows: “This is ISO New England (Insert Name), we are manually
dispatching Asset ID xxxx, yyyy and zzzzz under the “Winter Reliability Program”. The ISO New
England Operator receives a repeat back and then acknowledge if the repeat back is correct to complete
the three part communication. The return to service should use the same t hree part communication
process.
ISO-NE PUBLIC
111
Dispatch Instructions
• Dispatch is from ISO control room to DDE via recorded voice line using standard three part communication
• Three-part dispatch instruction: ”This is ISO New England (Insert Name), we are manually
dispatching Asset ID’s xxxxx, yyyyy, and zzzzz under the “Winter Reliability Program”.
– The ISO New England Operator receives a repeat back then – acknowledge if the repeat back is correct to complete the
three part communication
• The return to service should use the same three part communication process
ISO-NE PUBLIC
112
Auditing
• Audits are required in the event that there are no dispatches to establish performance levels
• If the participating winter asset is participating in the FCM as part of an RTDR Resource, the dispatch of the associated FCM Resource is also effectively an audit of the mapped winter program assets – this could be an OP4 based dispatch or a seasonal audit – Note that there is no separate dispatch of the Winter Program assets
when the associated FCM Resource is audited – DDE’s must know to dispatch both
– any simultaneous FCM/winter dispatch periods are used to determine the ‘Performance Factor’, which may reduce program payments if performance is not incremental to FCM obligations
• If the participating winter asset is not mapped to an RTDR Resource, auditing will be used to establish performance in the absence of sufficient dispatch intervals
ISO-NE PUBLIC
• Monthly payment Rate for 2017-18 is $1,033 per MW-month for each of the three months per season – Payment rates for each winter season posted by the prior July 15 on ISO
website (latest is here.)
• Monthly payment is forfeit if performance is under 75% of commitment
• Energy payment rate is higher of ($250 or real time zonal LMP) times 1.065 per MWh – 1.065 factor applies only to the demand reduction portion of MWh
Delivered and not to the net supply portion
• Energy payments are reduced by: – payments to generators located behind the same retail delivery point – transitional demand response payments – energy payments from FCM dispatch or audit
113
Program Compensation
ISO-NE PUBLIC
114
Settlement Timing
• Initial Winter Program monthly payments are made one month after normal FCM settlement – The costs are collected in the month following the delivery month – The payments are made the month after that
• Resettlement of the monthly payments is not delayed from FCM settlement timeline
• Winter Program initial energy based payments also occur on a 1 month delay, for the same reason (costs must be received prior to being paid)
ISO-NE PUBLIC
117
Response to Abnormal and Emergency Conditions Involving Energy
• Assess Severity of Issues on Region within NPCC and New England as well as Gas Pipeline Operations and Liquid Fuels
• In order of severity implement the following: – Dispatch additional resources in economic order to replace any
generation curtailed or expected to be curtailed as a result of the loss – Implement MLCC-2 Abnormal Conditions Alert – Implement OP-4 Action During a Capacity Deficiency – Implement OP-7 Action in Emergency – Implement OP-21 Action During an Energy Emergency
• This implementation includes actions of OP-4 and up to and including firm load-shedding under OP-7 Action in Emergency
ISO-NE PUBLIC
118
OP-4 Overview Action During a Capacity Deficiency
• Implemented when: – The resources available to the New England Reliability Coordinator Area/ Balancing
Authority Area (RCA/BAA) outside of OP-4 are insufficient to meet the anticipated load plus Operating Reserve Requirements. It will not be utilized to maintain Replacement Reserve Requirements.
– One or more contingencies have occurred resulting in an immediate deficiency in the New England RCA/BAA available capacity resources required to meet the load plus Operating Reserve Requirements.
– Transmission facilities into a sub area of the New England RCA/BAA are loaded beyond established transfer capabilities.
– A sub area of the New England RCA/BAA is experiencing abnormal voltage and/or reactive conditions.
– The need to implement manual load shedding as required by ISO New England Operating Procedure No. 7 - Action in an Emergency (OP-7) is imminent but load shedding may be avoided, or reduced in magnitude, by application of this procedure.
– Another Northeast Power Coordinating Council (NPCC) RCA/BAA, or a remote system or pool, is experiencing a capacity deficiency and has requested assistance from ISO, which, if provided, will reduce the New England RCA/BAA actual Operating Reserve below the required levels.
– Any other serious threat to the integrity of the Bulk Electric System (BES) for which ISO determines that this procedure will mitigate the impact.
ISO-NE PUBLIC
119
OP-7 Action in an Emergency
• Implemented when: – Experiencing an acute Operating Emergency involving unusually low
frequency, equipment overload, capacity or energy deficiency, unacceptable voltage levels, or any other emergency that ISO deems appropriate in an isolated or widespread area of New England.
– The objectives in establishing these emergency actions are: 1) To protect reliable operation of the Eastern Interconnection. 2) To restore balance between customers' load and available generation in
the shortest practicable time. 3) To minimize risk of damage to equipment. 4) To minimize interruption of customer service.
– Actions involve the ability of the ISO New England Control Room to order the New England Local Control Centers to disconnect up to 50% of the firm load in New England within 10 minutes of the order • This procedure is tested and practiced monthly
ISO-NE PUBLIC
120
OP-21 Action During an Energy Emergency
• Potential Initiating Conditions Any of the conditions listed below or a combination of these conditions can lead to an Energy Emergency Condition: – One or more pipeline Operational Flow Orders (OFOs) have been declared – Significant reductions of generation resource capability due to natural gas related
issues – Weather forecast for a extended period of cold or hot weather – Fuel delivery to a significant number of fossil fuel-fired generating resources is, or
may be impaired – Prolonged drought – Adverse weather conditions within the Gulf of Mexico, Western Canada, or
regional shale gas basins – Abnormal conditions at regional LNG import, satellite storage, or LNG trucking
facilities – Extreme cold weather conditions in Ontario, New Brunswick and Quebec – Extreme storm conditions off shore in the Maritimes – Any viable threat to one or more of the pipelines or LDCs supplying New England – Any other serious threat to the integrity of the BES for which ISO determines that
this procedure may mitigate the impact.
ISO-NE PUBLIC
121
OP-21 Action During an Energy Emergency
• When analysis indicates that an Energy Emergency Condition should be implemented, the ISO will perform the following: – Promptly alert the LCCs and MPs, Federal and State Governments . – Alert the surrounding Reliability Coordinators (RCs) and coordinate with
these Reliability Coordinator Areas (RCAs) – Request that each dual-fuel Generator, that is scheduled to operate,
voluntarily switch to operation on the fuel source that is not in short supply.
– Implement specific capacity and load relief measures available through Actions of OP-4, excluding requesting New England Governor’s to reinforce appeals for voluntary load curtailment.
– Implement a New England Governor’s appeal in accordance with OP-4: Request New England State Governors to reinforce appeals for voluntary electrical load curtailment and the declaration of a Power Warning.
– Under extreme conditions, ISO will seek reliability relief through load shedding actions available through implementation of OP-7.
ISO-NE PUBLIC
124
OP-21 Appendix A Generator Fuel Inventory Survey
• Purpose of Generator Fuel Inventory Survey – Current Inventory of fuel reserves within the region – Assess available and maximum volumes of fuel
• Data Collection and Evaluations: – ISO distributes OP-21 Appendix A to LMPs of oil and coal-
fired generators
ISO-NE PUBLIC
125
OP-21 Appendix A Generator Fuel Inventory Survey
• Frequency: – Monthly during normal conditions – Fuel surveys will be distributed more frequently during Energy
Emergency conditions (as frequent as daily if needed)
• Responsibilities: – Lead Market Participant:
- Complete periodic fuel surveys accurately and return to the ISO as soon as possible - Communicate to the ISO (Must be through the DE):
- Any anticipated or actual reductions in Generator availability, including but not limited to the ability to procure fuel for the Operating Day
- Any knowledge of changes to real-time fuel deliverability
ISO-NE PUBLIC
128
Contact Information
• John Norden Phone: 413-535-4353 Email: [email protected]
• Mike Knowland Phone: 413-540-4525 Email: [email protected]
• Stephen George Phone: 860-683-3299 Email: [email protected]
• Josh Lenzen Phone: 860-683-3288 Email: [email protected]
• Jim Nichols Phone: 413-540-4678 Email: [email protected]
• Chad Nelson Phone: 413-540-4508 Email: [email protected]
ISO-NE PUBLIC
Customer Support
• Ask ISO – Self-service interface for submitting inquires – Accessible through the SMD Applications Homepage – Requires a valid digital certificate with the role of Ask ISO/External User – Contact your Security Administrator for assistance
• Phone: 413-540-4220 – Monday through Friday, 7:30 A.M. to 5:30 P.M. Eastern Time – Recorded/monitored conversations
• Email: [email protected]
129
ISO-NE PUBLIC
130
ISO Website References
Rules and Procedures Transmission, Markets & Services Tariff
• Section III of Market Rule 1 » Section III.1.5.2 (ISO-Initiated Parameter Auditing) » Appendix K.5 (Winter Reliability Solutions – Dual Fuel Commissioning Service)
This Webinar will be posted on iso-ne.com, under ISO Training Materials: https://www.iso-ne.com/participate/training/materials/?key-topic=System Operations Training
www.iso-ne.com
ISO-NE PUBLIC
• Subscribe to the ISO Newswire – ISO Newswire is your source for regular news
about ISO New England and the wholesale electricity industry within the six-state region
• Log on to ISO Express – ISO Express provides real-time data on New
England’s wholesale electricity markets and power system operations
• Follow the ISO on Twitter – @isonewengland
• Download the ISO to Go App – ISO to Go is a free mobile application that puts
real-time wholesale electricity pricing and power grid information in the palm of your hand
For More Information…
131
ISO-NE PUBLIC
133
Follow Up to Questions from Today’s Webinar
Please see below for items related to questions from today’s webinar:
Question: What is the definition of Capacity Scarcity Condition definition under Pay for Performance (PFP), from Section III.13.7.2.1, effective 6/1/18:
Answer: A Capacity Scarcity Condition shall exist in a Capacity Zone for any five-minute interval in which the Real-Time Reserve Clearing Price for that entire Capacity Zone is set based on the Reserve Constraint Penalty Factor pricing for:
(i)the minimum Thirty-Minute Operating Reserve requirement sub-category of the system-wide Thirty-Minute Operating Reserves requirement; (ii) the system-wide Ten-Minute Non-Spinning Reserve requirement; or (iii) the local Thirty-Minute Operating Reserve requirement,
each as described in Section III.2.7A(c); provided, however, that a Capacity Scarcity Condition shall not exist if the Reserve Constraint Penalty Factor pricing results only because of resource ramping limitations that are not binding on the energy dispatch.
Note: Additional Pay For Performance related information can be found here: https://www.iso-ne.com/committees/key-projects/fcm-performance-incentives
Question: Where is Real-Time price information posted?
Answer: https://www.iso-ne.com/isoexpress/