2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23...

67
2016 Annexure – XII DETAILED PROJECT REPORT ON HALDIA WATER SUPPLY PROJECT

Transcript of 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23...

Page 1: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

2016

Annexure – XII

DDEETTAAIILLEEDD PPRROOJJEECCTT RREEPPOORRTT

OONN

HHAALLDDIIAA WWAATTEERR SSUUPPPPLLYY PPRROOJJEECCTT

Page 2: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

Chapter Particulars Page No.

1 INTRODUCTION 1

1.1 GENERAL 1

2 HYDROGEOLOGY & TOPOGRAPHY 3

3 CLIMATE 4

4 PROJECT DESCRIPTION 4

4.1 OLD 25 MGD WTP & WATER SUPPLY SYSTEM IN HALDIA 5

4.1.1 WATER INTAKE AND TREATMENT 5

4.1.2 WATER TRANSMISSION AND STORAGE 8 SCHEMATIC DIAGRAM OF WATER TREATMENT PROCESS

AT OLD 25 MGD WATER TREATMENT PLANT AT GEONKHALI

11

STEP-I 11

STEP-II 12

STEP-III 13

STEP-IV 14

4.2 NEW 25 MGD WTP & WATER SUPPLY SYSTEM IN HALDIA 15

4.2.1 LIST OF MAJOR EQUIPMENTS 16

SCHEMATIC DIAGRAM OF WATER TREATMENT PROCESS AT NEW 25 MGD WATER TREATMENT PLANT AT GEONKHALI

21

4.2.2 NEW 25 MGD WATER TREATMENT PLANT PROCESS DESCRIPTIONS

22

4.2.2.1 PRE-CHLORINATION 22

4.2.2.2 COAGULATION AND FLOCCULATION 22

4.2.2.3 INCLINED PLATE SETTLER 23

4.2.2.4 DISSOLVED AIR FLOTATION AND FILTRATION SYSTEM 23

4.2.2.5 POST CHLORINATION 24

5. PIPELINE NETWORK DETAILS AND VALVES ETC 24

5.1 PIPE MATERIAL, DIAMETER AND VELOCITY OF FLOW THROUGH PIPES

25

6. DETAILS OF 14 NOS. SERIES TUBE WELL WITH RESPECTIVE LOCATION

26

7. WATER DEMAND PROJECTION 28 8. DETAILS OF EXISTING CONSUMERS OF HALDIA WATER

SUPPLY PROJECT 29

8.1.1 LIST OF EXISTING INDUSTRIAL CONSUMERS 29

8.1.2 LIST OF EXISTING COMMERCIAL CONSUMERS 33

8.1.3 EXISTING DOMESTIC & MUNICIPAL CONSUMERS 34

8.1.3.1 LIST OF EXISTING DOMESTIC CONSUMERS 35

8.1.3.2 LIST OF EXISTING MUNICIPAL CONSUMERS 38

9 INDICATIVE DETAILS OF WATER DEMAND FOR NEW

CONSUMERS/ ENHANCEMENT OF WATER REQUIREMENT OF EXISTING CONSUMERS OF HALDIA WATER SUPPLY PROJECT

39

9.1 INDICATIVE FUTURE WATER REQUIREMENT OF INDUSTRIAL CONSUMERS

39

Page 3: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

9.2 INDICATIVE FUTURE WATER REQUIREMENT OF COMMERCIAL CONSUMERS

40

9.3 INDICATIVE FUTURE WATER REQUIREMENT OF DOMESTIC CONSUMERS

40

9.4 INDICATIVE FUTURE WATER REQUIREMENT OF MUNICIPAL CONSUMERS

40

9.5 SUMMARY OF WATER DEMAND PROJECTION 40

10. RAW WATER QUALITY 41

Table 1 Data on Raw Water Quality 41

10.1 Salinity in Hooghly near Geonkhali 42

Table 2 Salinity levels at different seasons 42

Table 3 Chloride data for summer seasons of 2011, 2012, 2013, 2014 & 2015 43

10.2 Raw Water Pumping Capacity 44

11. HISTORICAL DATA OF WATER SALE IN INDUSTRIAL AND

TOTAL WATER (INDUSTRIAL, COMMERCIAL, DOMESTIC & MUNICIPAL) CATEGORY

44

12. HISTORICAL DATA OF EXPENDITURE FOR OPERATION &

MAINTAINANCE OF HALDIA WATER SUPPLY PROJECT 45

13. SAMPLE AGREEMENT WITH CONSUMERS OF HALDIA WATER

SUPPLY PROJECT 46

14. LIST OF MAPS & DRAWINGS 50

FIGURE 1 LAND MAP OF BASUDEVPUR BOOSTING STATION 50

FIGURE 2 SATELLITE IMAGE OF BASUDEVPUR PUMPING STATION 51

FIGURE 3 LAND MAP OF GEONKHALI OLD & NEW 25 MGD WTP 52

FIGURE 4 SATELLITE IMAGE OF GEONKHALI OLD 25 MGD WTP 53

FIGURE 5 SATELLITE IMAGE OF GEONKHALI NEW WTP 54

FIGURE 6 LAND MAP OF CHAITANYAPUR BOOSTING AND PUMPING STATION

55

FIGURE 7 SATELLITE IMAGE OF CHAITANYAPUR BOOSTING AND PUMPING STATION

56

FIGURE 8 LAND MAP OF HATIBERIA BOOSTING STATION 57

FIGURE 9 SATELLITE IMAGE OF HATIBERIA BOOSTING STATION 58

FIGURE 10 SATELLITE IMAGE OF BRAJALALCHAK CLEAR WATER RESERVOIR

59

FIGURE 11 SATELLITE IMAGE OF HALDIA INDUSTRIAL BELT 60

FIGURE 12 MAP OF HALDIA PLANNING AREA 61

FIGURE 13 NETWORK DRAWING FROM CHAITANYAPUR TO IOCL 62

FIGURE 14 WATER FLOW DIAGRAM OF INDUSTRIAL WATER SUPPLY OF HALDIA WATER SUPPLY PROJECT

63

FIGURE 15 WATER FLOW DIAGRAM OF PHASE-II & III OF HALDIA WATER SUPPLY PROJECT

64

FIGURE 16 NETWORK MAP OF HALDIA WATER SUPPLY PROJECT 65

Page 4: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

1

1 INTRODUCTION:

1.1 GENERAL

1.1.1 Water has a unique place in all the renewable resources of the planet. Water resources of

a country constitute one of its vital assets. Where there is water, there is life and where

water is scarce, life has to struggle. It is essential to sustain all forms of life, food

production, economic development, industrial growth and for general well being. It is

impossible to substitute water for most of its uses.

1.1.2 Water supply scenario in India has considerably improved during last two decades.

Planning commission report states that in India water is supplied to about 85% of the

urban and rural population but the challenge is in providing 24x 7 services. The main

issue of concern is the pollution of available surface water sources and depletion of

ground water table due to over exploitation. In India, the primary responsibility for

providing drinking water and sanitation facilities in the country rests with the State

Governments, and, more specifically, the local bodies in the urban areas.

1.1.3 Haldia city is fortunate to have water supply system for both industrial and domestic

supply. Haldia Development Authority (H.D.A.) the nodal agency and Statutory

Authority in charge of development of urban and industrial infrastructure in the region.

HDA is actively encouraging implementation and maintenance of infrastructure projects.

One of the key infrastructure requirements of the region is availability of reliable and

quality water supply. Haldia is an important industrial town with a residential

population of 200,762 as per 2011 census. Presence of several important industries such as

Haldia Petrochemicals Limited , Mitsubishi (MCCPTA) , Indian Oil Corporation Limited,

Indian Oil Petronas Limited, Tata Power, Tata Chemicals, Exide Industries , South Asian

Petrochem Limited, Reliance Industries, Electro-Steel Castings, Bharat Petroleum

Corporation Limited and others have made it a major industrial hub.

1.1.4 Haldia is also an important logistics hub, having a large riverside port. Haldia Dock

Complex, an important part of Kolkata Port System, has an annual throughput of 128,470

TEUs in Container Freight Service (CFS). Presence of several large industries, a large

Page 5: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

2

dock complex and a growing population has made Haldia an important hub in West

Bengal.

1.1.5 Haldia is in the process of being transformed into the most coveted industrial destination

in Eastern India. Hence, providing quality civic infrastructure and utility services has

emerged as a policy priority for Government of West Bengal. In order to achieve and

sustain this position, HDA has been working towards achieving of World class

infrastructure facilities in Haldia.

1.1.6 As part of its key obligation, HDA supplies treated water to industrial, commercial,

domestic & municipal consumers in and around Haldia town and Haldia Industrial Area.

For this purpose, it has set up a water treatment facility of 25 MGD capacity at Geonkhali

in 1992. In addition, there are fourteen (14) deep tube wells within the Haldia Planning

area to supplement potable water supply to the Booster Pumping station at

Chaitanyapur. The water treatment plant gets raw water from the Hooghli river through

an intake jetty, located close to the confluence of the rivers Rupnarayan and Hooghli.

This portion of the river is a tidal stretch, witnessing high and low tides twice in 24 hours

period. Turbidity reaches around 1600 NTU during monsoon. Because of proximity to

sea, the stretch suffers from high salinity level, which reaches more than 2000 ppm

during lean season of the year when there is no freshet in Hooghly and during high tides.

HDA mixes ground water drawn from 14 tube wells, at Chaitanyapur boosting station

before it is distributed to consumers. Also it has a 200 million gallon capacity of Pre-

Settling Tank, which receives raw water through three inlet channels. During low tide,

water quality is generally of acceptable level and salinity issue remains under control. So

by controlling intake flow of water, a proper mix can be achieved so that actual supply

does not get significantly affected by salinity problem. At distribution end, water supply

system consists of three boosting stations with semi underground reservoirs. The

boosting stations are located at Chaitanyapur, Basudevpur and at Hatiberia. Another

Pumping Station with reservoir is being constructed which is expected to be operational

in July, 2016. In 2005-06, augmentation of the old treatment facility was made by adding a

new 5 MGD filter to the existing 20 MGD capacity filters and by modification of the

existing clariflocculators with tube settlers at the periphery and Water Treatment facility

had been expanded to 25 MGD.

Page 6: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

3

1.1.7 Construction and commissioning of new 25 MGD WTP over and above the existing 25

MGD had been operational since December, 2014. The new plant has separate intake

arrangement. It uses the existing raw water inlet channels (3 nos.) and settling tank of 200

million gallon capacity as a common facility. The new 25 MGD treatment plant with

semi-automated control system has been designed to supply water to Basudevpur

Boosting Pumping Station directly through a newly laid 900/1000 mm diameter D.I pipe

line through a bifurcation station, from where a separate pipe branches out and feeds

water to IOCL reservoir. HDA is now having at its disposal, combined water treatment

capacity of 52 MGD (50 MGD from water plants and 2 MGD from tube wells) for meeting

water demand of its valued consumers in Haldia Industrial Area.

1.1.8 In the year 2008, HDA entered into a Concession agreement with Haldia Water

Management Limited (HWML), a joint venture company of JUSCO and Ranhill Utilities,

Malaysia for construction of a new 25 MGD water treatment plant and the O&M of the

entire water supply network of Haldia for a period of 25 years. However for municipal

supply, HWML delivered bulk water to different zones of Haldia Municipality to its

reservoirs. The distribution network of Haldia Municipality is maintained by Haldia

Municipality. The agreement between HDA and HWML was in effect since November

2008 to March-2013. Since April, 2013 the Haldia Water Supply Project is being operated

and maintained by Haldia Development Authority.

2.0 HYDROGEOLOGY & TOPOGRAPHY

Haldia is a rapidly developing urban centre in southern part of Purba Medinipur district

of West Bengal. It is located at latitude 22º 03´ N and longitude 88º 06´ E. It is a major

riverine port and an industrial city of Eastern India. Haldia is located at the confluence of

River Haldi and River Hoogly and is 56 Nautical miles downstream of Kolkata. Haldia is

well connected by South-Eastern railways and by NH 41 and NH 6 with rest of India.

Haldia municipality covers a total area of 104.9 sq. km, comprising 26 wards. Haldia is

situated close to the confluence of River Hoogly and Haldi. River Hoogly, a distributary

of River Ganga, is the main drainage course of the area. Both Hoogly and Haldi are

estuarine in nature and experience tides. The rivers are fed mostly by upland discharge,

which is maximal during monsoon. Tides are diurnal with mean range during spring

being 4.90 m. Average velocity during tidal cycle is 1.75 m/sec. The soil in Haldia has a

Page 7: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

4

characteristic high water holding capacity. In rainy season, the water level rises to the

maximum of 1.50 m and during summer it falls to a depth of 5.5 m from the ground level.

Due to the high salinity of the Rivers Hoogly and Haldi in stretches near Haldia, they are

not suited for water supply. The required water for domestic and industrial water supply

is obtained from an upstream point at Geonkhali where Roopnarayan River meets River

Hoogly.

The general topography of Haldia town, which is spread over an area of 104.9 sq. km, is

relatively flatter having general gradient from North to South and South to West. The

river Hoogly meandering in a direction of South West to East flows by the Southern

boundary of the Haldia Municipality.

3.0 CLIMATE

Haldia has a moderate tropical climate with winter temperatures ranging from a low of

around 7 degrees Celsius to a high of 22 degrees Celsius. Summers can be very hot and

humid. Usual summer temperatures in May, the hottest month, range from a low of 24

degrees Celsius to high of around 39 degrees Celsius. Rainfall is heavy during monsoons,

and the rainy season spans between the months of June and September. The annual

rainfall is about 1600 mm.

4.0 PROJECT DESCRIPTION:

Old Water Treatment Plant has been renovated and new water treatment of equal

capacity has been in operation since December, 2014. Sufficient water supply network

with water reservoirs, pump houses and pipeline network have already been created.

The details are:

• Old 25 MGD Water Treatment Plant: It consists of intake jetty, intake channels, raw water

pump house, presetting tanks, settled water pump house, chemical house, flash mixers,

clarifloculators, Elevated storage reservoir, filter house, clear water reservoir, sludge

pump house, sludge ponds, laboratory and electrical sub stations etc.

• 25 MGD New Water Treatment Plant: New Water Treatment Plant of 25 MGD capacity

consists of intake jetty, raw water pump house, settled water sump and pump house,

chemical house, DAF house, clear water storage tank and clear water pump house,

chlorine room and electrical substation etc.

Page 8: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

5

• Three nos. pumping stations with reservoirs, chemical houses and pump houses are

located at different places of Haldia Water Supply project. Another pumping station is

being constructed at Brajalalchak which is expected to be operational by July, 2016.

• Other associated infrastructure like electrical substations, water intake facility and settled

water pump house etc.

• Laying of pipeline from Chaitanyapur to Brajalalchak (Phase-II) has been constructed.

Construction of reservoir at Brajalalchak (Phase-II) and laying of distribution network

from Brajalalchak to Hatiberia (Phase-III) have been started and is expected to be added

with the Haldia Water Supply Project by July, 2016.

The raw water drawn from the river at Geonkhali is treated at the Water

Treatment Plants after which it is pumped to boosting station at Chaitanyapur. Then the

water is pumped at Chaitanyapur to Basudevpur from where the water is distributed to

different industries and domestic consumers. The water from series tube wells are mixed

with treated water at different pumping station to regulate the salt content of the water in

addition to other chemical treatments. Some dedicated water pipelines have been built

which supply water directly to different consumers. Regular operation and maintenance

is vital for ensuring proper water supply.

4.1 OLD 25 MGD WTP & WATER SUPPLY SYSTEM IN HALDIA

4.1.1 WATER INTAKE AND TREATMENT

The supply of water for the entire Haldia is sourced from the Hooghly River at

Geonkhali. Haldia Development Authority (H.D.A.) has an Old 25 MGD water treatment

plant at Geonkhali to cater to the demand of industries as well as domestic water in its

designated command area. Geonkhali is situated on the western bank of the river

Hooghly at the confluence of river Rupnarayan and river Hooghly. Raw Water from the

Hooghly river is collected through a 1000 mm suction mains (4 units) laid inside the river

bed with the help of intake -jetty. This is conveyed to pre-settling tanks of 200 Million

Gallons capacity by 3 nos. of intake channels. Water from pre-settling tanks is passed

through Filter Beds via Clariflocculators and Flash Mixer and finally through filter media.

It is then stored in Underground Clear Water Reservoirs

Page 9: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

6

The technical details of water intake and treatment are indicated below:

FACILITY OLD 25 MGD WTP: PPROJECT DETAILS

Land 238.15 Acres

Intake Jetty For supporting four (4) Nos. 1000 mm dia. MS suction mains and

chloride monitoring unit

Raw Water Pump

House

Plinth area 170 Sq Mtrs for housing four (4) Nos raw water

pumping machinery.

Raw Water

Pumps

Four (4) Nos. split casing centrifugal pumps of capacity 4500 Cu

Mtr/ Hour each against a total head of 12 MWC. The motor rating

is 200KW. Make of Pumps: Mather & Platt. Suction Valves:

Manually operated Sluice Valves of 1000 mm dia. Delivery valves :

electrically actuated sluice valves of 750mm dia.

Raw Water Mains Two (2) Nos. 1100 mm dia MS pipeline, 470 mtrs each for supplying

raw water to intake channels

Intake Channels Three (3) Nos. intake channels each of 400 mtrs long, 30 mtrs wide

and 4 mtrs deep, capacity of each channel is 10 million gallons

Presetting Tank One (1) No. 600 mtrs x 500 mtrs x 3 mtrs size with 200 million

gallons capacity

Settled Water

Pump House

One (1) No. RCC underground sump of 16.25 mtrs x 4 mtrs x 6.5

mtrs size through two pipes from the intake well. constructed in the

presetting tank

Settled Water

Pumps

Floor area 275 Sq Mtrs for housing four (5) nos. settled water

pumping machinery. Five (5) nos split casing centrifugal pumps of

capacity 1800 Cu Mtrs /Hour, 980 RPM each against a total head of

15.2 MWC. Motor rating is 110 KW. Make of Pumps: Mather &

Platt. Suction Valves : manually operated Sluice Valves. Deliveries:

manually operated sluice valves

Chemical House

for alum and

chlorine dosing

At present there is provision for solid Alum, liquid poly aluminum

chloride, liquid chlorine dosing. Chemical house is divided into

two sections for alum dosing into each parshall flume and chlorine

dosing. Motors and agitators of the dosing tank are in working

condition. Alum blocks are dissolved in solution tank and from

there the alum solution flows to dosing tank through PVC piping.

From this tank, alum is dosed to parshall flumes. Three alum tanks

Page 10: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

7

FACILITY OLD 25 MGD WTP: PPROJECT DETAILS

have been modified for liquid PAC dosing. Alum storage space for

two (2) months consumption. Six (6) nos. alum solution tanks.

Alum dosing by gravity rate settling mechanism. Space for storing

chlorine cylinders with lifting tackles, four (4) nos. gaseous

chlorinators.

Flash mixers,

inlet, wells and

ventury fumes

Two (2) nos. inlet wells for receiving settled water

Two (2) nos. flash mixers each of 4.90 SqMtr x 5.80 Mtr deep with 1

minute detention

Two (2) nos. ventury flumes with dial type flow recorders

Clarifloculators Two (2) nos. each, 48.5 Mtr dia with 3 Mtr side water depth, 900

mm dia RCC Hume pipe inlet, 350 mm dia sludge pipe. Detention

time: 3 Hours

Weigh Bridge One (1) no. 30 MT capacity Weigh Bridge for weighing materials

such as Alum, Chlorine etc

Elevated reservoir

for backwashing

of filter beds and

town supply

One (1) RCC elevated reservoir of 682 Cu Mtrs capacity with

staging height 15.25 mtrs

Filter House Size of each filter bed is 84.80 Sq Mtrs having 650 mm thick sand

over 450 mm thick gravels, having air scour system backwash

system and control devises

Clear Water

Reservoir

One (1) RCC underground reservoir capacity 23 lakhs Litres

Clear Water Pump

House

Floor area 323.32 SqMtrs for housing 5 Nos. Clear water pumps and

3 nos. Backwash pumps

Clear Water

Pumping

Machinery

Four (4) Nos. Split casing centrifugal pumps each capable of

pumping 1850 Cu Mtrs per hour against a total head of 36 mtrs for

supplying treated water to Chaitanyapur reservoir. Motor rating is

260 KW

Sludge sump and

sludge pump

house

One (1) underground RCC sludge sump of 250,000 ltrs capacity

One (1) sludge pump house over the sludge pump of floor area 200

SqMtrs for housing two (2) nos sludge pumps

Page 11: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

8

FACILITY OLD 25 MGD WTP: PPROJECT DETAILS

Sludge pumps Two (2) nos split casing pumps with open impeller. Sludge pump

each capable of pumping 400 Cu Mtrs of sludge water per hour

against a total head of 15 m. Motor rating is 30 KW.

Sludge ponds Two (2) nos. each of size 37 mtrs x 33 mtrs x 3 mtrs deep for

collecting sludge water from clarioculators and filter house

Laboratory and

Annexe Building

One (1) well equipped laboratory for testing physical, chemical and

bacteriological quality of treated water and raw water

Two (2) nos. Air compressors and two (2) nos. blowers for

operation of pneumatically controlled valves and for air scour

arrangements, installed in the ground floor of Annexe building

Inspection

Bunglow, Staff

quarters, stores etc

One (1) two storied inspection bunglow having four (4) complete

AC suites, one conference hall, one lounge, toilets, kitchen, dining

room etc. The inspection bunglow has presently been leased out as

a Hotel

Three (3) nos. three (3) storied staff quarters having six (6) quarters

in each building

Electrical Sub-

station

Tow (2) nos of feeders. Contract demand : 2200 KVA Three (3) nos. Outdoor type 1250 KVA transformer (2 working and 1 stand-by) Make: Kirloskar: 50 Hz, 33 / 0.433 rating

4.1.2 WATER TRANSMISSION AND STORAGE

Raw water after treatment at Geonkhali is conveyed to the Chaitanyapur water works,

which is approx. 9 Kms from Geonkhali, be means of clear water pumps, through rising

mains of about 1100 mm ,1000mm & 700 mm dia. At Chaitanyapur, an underground

storage tank of capacity 2.3 Million liters (ML) has been provided. From the Clear Water

Reservoir at Chaitanyapur, water is transferred by means of:

� 1100 mm diameter pipeline for distribution to various industrial and domestic

areas of Haldia with intermediate location of Basudevpur Water Works

� 900 mm diameter pipeline for distribution to dedicated water supply to Indian Oil

Corporation Limited

Page 12: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

9

� 500 mm dedicated pipeline for water supply to Haldia Petro Chemicals Ltd.

At Chaitanyapur, there are 14 Nos. of Tube wells (TWs). The water from these TWs

(About 2 MGD) is also added to the Clear Water Reservoir. The purpose of Tube wells is

to compensate for any resultant salinity.

The details of the system at Chaitanyapur are indicated below:

Main CWR Capacity: 2.3 Million litres ( ML)

Pumps 6 Nos. ( 4 Working + 2 Stand by)

1150 m3/ hr, Head – 47 metres

CWR for HPL Capacity: 0.45 Million litres ( ML)

Pumps 3 Nos., ( 2 Working + 1 Stand by)

600 m3/hr, Head – 60 m

CWR for IOCL Capacity: 8 Million litres ( ML)

Pumps 4 Nos., ( 2 Working + 2 Stand by)

1150 m3/ hr, Head – 27 m

The details of the system at Basudevpur & Hatiberia are indicated below:

Old CWR at Basudevpur Capacity: 22.7 Million litres ( ML)

Primary Grid (industrial as well as Township Supply)

6 Nos 1135 m3 / hr, (4 Working + 2 Stand by), Head – 40 m

Secondary Grid 5 Nos. 285 m3 / hr ( 4 Working + 1 Stand by), Head – 33 m

B.H.T. Pumps for Mitsubishi 2 Nos. 860 m3 )/ hr ( 1 Working + 1 Stand by, Head – 37.3 m

B.H.T. Pumps for Mitsubishi 3 Nos. 1260 m3/ hr ( 2 Working + 1 Stand by, Head – 30 m

New CWR at Basudevpur Capacity: 18 Million litres ( ML)

Pumps for Medical/ Ural India 6 Nos 1140 m3 / hr ( 4 Working + 2 Stand by) , Head – 30 m

Pumps for IPCL 2 Nos. 1050 m3 / Hr, Head – 30 m (Not operational yet)

Page 13: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

10

CWR at Hatibera Capacity: 2 Million Liters ( ML)

Pumps at Hatiberia 2Nos. ( 1 Working + 1 Stand by) , 640 m3 / hr, Head – 35 m 2 Nos. ( 1 Working + 1 Stand by 430 m3 / hr, Head – 29 m

CWR at Brajalalchak ( expected to

be operational in July, 2016)

Capacity: 3.15 Million Litres

Pumps at Brajalalchak ( expected

to be operational in July, 2016)

3 Nos. ( 2 Working + 1 Stand by)

660 m3 / Hr, Head – 30 m

Page 14: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

11

SCHEMATIC DIAGRAM OF WATER TREATMENT PROCESS AT OLD 25 MGD

WATER TREATMENT PLANT AT GEONKHALI

STEP-I

Page 15: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

12

STEP-II

Page 16: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

13

STEP-III

Page 17: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

14

STEP-IV

Page 18: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

15

4.2 NEW 25 MGD WTP & WATER SUPPLY SYSTEM IN HALDIA

The new plant has separate intake arrangement. However, it uses the existing raw water

inlet channels (3 nos.) and 200 million gallon capacity pre-settling tank as a common

facility. The new 25 MGD treatment plant with modern technology will supply water to

Basudevpur Boosting Pumping Station directly through a newly laid 1000 mm diameter

D.I pipe line through a bifurcation station, from where a separate pipe branches out and

feeds water to IOCL reservoir.

The water treatment plant consists of following units:

� Raw Water Intake Jetty

� Raw Water Pump House

� Raw Water Conveyance Main

� Settled Water Pump House including Suction arrangement from settled water

tank to pump house

� Pre-chlorination system

� Coagulation and Flocculation.

� Plate Settler

� Dissolved Air Floatation (DAF) System with Sand Filtration.

� Post Chlorination system

� Sludge Handling System

� Clear Water Reservoir

� Clear Water Pump House

Page 19: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

16

4.2.1 LIST OF MAJOR EQUIPMENTS: The water treatment plant consists of several electromechanical equipments. Lists of

major electromechanical equipments are given below.

FACILITY New 25 MGD WTP: PROJECT DETAILS

Intake & Raw Water Pumping Station

• Conductivity Sensor & Transmitter – 1 no.

• PLC Panel – 1 no.

• 1100 Dia Manually operated Sluice Valve – 4 nos.

• 1100 Dia Manually operated Butterfly Valve – 4 nos.

• Horizontal Centrifugal Pump with Vertical Execution. Pump:- 5100 Cum/Hr, Head-16 m, Motor:- 325 KW (HT) - 4 nos.

• Dewatering Pump (Submersible) Capacity: 20cum/hr, Head 20 m – 2 nos.

• 1000 mm dia NRV – 4 nos.

• 1000 mm dia Butterfly Valve with actuator – 4 nos.

• 1400 mm dia butterfly valve – 2 nos.

• 7.5 MT HOT crane with Electric hoist 7.5 MT capacity – 1 no.

• 6.6 KV 800 A VCB HT switchgear with motor feeder – 1 Set

• 6.6 KV HT capacitor Bank – 4 nos.

• AC distribution Board – 1 no.

• Lighting Distribution Board – 1 no.

• Battery Charger with Battery Bank – 1 set.

Settle Water Pumping Station

• Settle Water Sampling Pump – 2 nos.

• PLC Panel – 1no.

• 1200 mm dia Butterfly Valves – 5 nos.

• 900 mm dia butterfly Valves – 4 nos.

• Horizontal Centrifugal Pump, Capacity: 2580 Cum/hr, Head: 18 m , Motor: 180 KW – 4 nos.

• Dewatering Pump (Submersible) Capacity: 20cum/hr, Head 20 m – 2 nos.

• 700 dia NRV – 4 nos.

• 700 mm dia Butterfly Valve with actuator – 4 nos.

• 1000 mm dia Butterfly Valve with actuator – 1 no.

• 5 MT HOT crane with Electric hoist 5 MT capacity – 1 no.

• HT switchgear with motor feeder – 1 set

• HT capacitor Bank – 4 nos.

• AC distribution Board – 1 no.

• Lighting Distribution Board – 1 no.

• Battery Charger with Battery Bank – 1 set.

Flush Mixer, Flocculator and Plate settler

• Flow Meter – 1 No.

• Penstock gate – 6 Nos.

• Inclined Plates – 3120 Nos.

• Outlet Launder of Plate settler – 24 Nos.

Page 20: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

17

FACILITY New 25 MGD WTP: PROJECT DETAILS

• Sludge bottom scrapper arrangement including gear and motor – 12 Sets

• Sludge transfer pump at plate settler – 4 Sets

• Clarified water sampling pump – 2 Sets

• Residual Chlorine sensor & transmitter – 1 Set

• pH sensor and transmitter – 2 Sets

• Turbidity and SS sensor and transmitter – 1 Set

• PLC Panel – 1 Set.

• 200 mm dia Pneumatic Butterfly Valve – 12 Nos.

Filter House

o RVP-49/1

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Sets

• High Pressure Pump – 2 Sets

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

• Pneumatic Valve Panel – 1 Set.

o RVP-49/2

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Set

• High Pressure Pump – 2 Set

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

• Pneumatic Valve Panel – 1 Set.

o RVP-49/3

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Set

• High Pressure Pump – 2 Set

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

Page 21: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

18

FACILITY New 25 MGD WTP: PROJECT DETAILS

• Pneumatic Valve Panel – 1 Set.

o RVP-49/4

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Set

• High Pressure Pump – 2 Set

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

• Pneumatic Valve Panel – 1 Set.

o RVP-49/5

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Set

• High Pressure Pump – 2 Set

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

• Pneumatic Valve Panel – 1 Set.

o RVP-49/6

• Carriage Motor – 1 No.

• Scoop motor – 1 No.

• Air Blower – 2 Nos.

• Back Wash Pump – 2 Set

• High Pressure Pump – 2 Set

• PLC Panel – 1 Set

• 200 mm dia Pneumatic Butterfly Valve – 48 Nos.

• 80 mm dia Pneumatic Butterfly Valve – 23 Nos.

• 500 mm dia Pneumatic Butterfly Valve – 2 Nos.

• Pneumatic Valve Panel – 1 Set.

o Air Compressor and its accessories – 2 Set o Air Dryer – 2 Set o PLC Panel – 1 Set o Sump Pump -2 Set o Air Receiver Tank -1 No o Turbidity analyzer -1 No

Page 22: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

19

FACILITY New 25 MGD WTP: PROJECT DETAILS

o APFC Capacitor Panel -2 Set o Sub Lighting Distribution Board -1 Set

Contact and Balancing Tank

• Balancing Tank Ultrasonic Level Sensor – 1No

Chlorination Room

• Chlorinator – 3 Set

• Lifting Bar Assembly -1No

• Chlorine Leak Detector -3 Sets

• Chlorine Gas Filter -2 Sets

• Emergency Repair Kit for Chlorine Tonner – 1 Set

• Electrically operated Hoist with travelling trolley, 3 MT Capacity -2 Nos.

• PLC panel -1 Set

• Breathing Apparatus -1 Set

• Canister Type Gas Musk -1 Set

• Blower with Electric Motor -2 Set

• Absorption Tower -1No

• Caustic Reticulating pump & motors -2 Sets

• Booster Pumps -3 Sets Clear Water Pump House

• Flow Meter -1No

• pH Sensor & Transmitter -1No

• .Turbidity Analyzer -1 No

• PLC Panel -1No

• Residual Chlorine Analyzer -1No

• 700 mm dia Butterfly Valves at suction side, Manual -6Nos

• Horizontal Centrifugal Pump, Capacity: 1250 Cum/hr, Head: 65m , Motor: 300 KW - 6 Nos.

• Dewatering Pump(Submersible) Capacity: 20cum/hr, Head 20 m -2 Nos

• 500 mm dia NRV -6Nos

• 500 mm dia Butterfly Valve with actuator -6Nos

• 1000 mm dia Butterfly Valve with actuator -1No

• 5 MT HOT crane with Electric hoist 5 MT capacity -1No

• HT switchgear with motor feeder -1Set

• HT capacitor Bank- 6Nos

• AC distribution Board -1No

• Lighting Distribution Board-1No

• Battery Charger with Battery Bank -1Set Sludge Handling Plant

• Sludge Holding tank Pump -2Set

• Sludge Thickner scraper with Gear and motor -1Set

• Supernatant Recycle Pump -2Sets

• Sludge Feed Pump- 2Sets

• Sludge Transfer Bypass Pump 1Set

• Sludge Feed Tank agitator -1Set

• Decanter -2Sets

Page 23: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

20

FACILITY New 25 MGD WTP: PROJECT DETAILS

• Sludge Conveyor -1Set

• Polymer Dosing Pump-2Sets

• 200mm dia Valve -1No

• Flow Meter -1No

Chemical House

• Lime Dosing Pump -2Sets

• .PAC Dosing Pump-2Sets

• Polymer Dosing Pump-2Sets

• PLC Panel -1No

• PAC Ultrasonic Sensor -2Nos

33 KVA Transformer Yard

• Transformer 4 MVA-33/6.6KV -2Nos

• Transformer 630 KVA-6.6/0.4KV -2Nos

• PCVCV -5Nos

• Potential Transformer -12 Nos

• Current Transformer -12Nos

• LT Switchgear -1No

• APFC Capacitor Panel -2Sets

• DCDB Battery Charger & Battery Set -1Set

• Control and Relay Panel -1Set

• HT Switchgear -1Set

• Main LDB -2Sets

• Sub LDB -2Sets

Page 24: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

21

SCHEMATIC DIAGRAM OF WATER TREATMENT PROCESS AT NEW 25 MGD

WATER TREATMENT PLANT AT GEONKHALI

Page 25: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

22

4.2.2 NEW 25 MGD WATER TREATMENT PLANT PROCESS DESCRIPTIONS:

4.2.2.1 PRE-CHLORINATION:

Pre- Chlorination is the application of chlorine to water prior to any treatment process.

The point of application, dosages will be determined by the objectives viz. control of

biological growths in raw water conduits, promotion of improved coagulation,

prevention of mud ball and slime formation in filter beds, reduction of algal growth

in sedimentation tank and filter beds, reduction in colour, odour, taste. It also

minimizes the post chlorine dosages when dealt with heavily polluted water. In this

treatment plant Pre- Chlorination dosing is done at the inlet point of flush mixer.

4.2.2.2 COAGULATION AND FLOCCULATION:

Coagulation refers to destabilization produced by compression of electrical double layer

of the surrounding colloidal particles, while flocculation refers to destabilization by the

adsorption of the large organic polymers and subsequent formation of particle-polymer-

particle bridges. This distinction can have practical significance, since colloidal

aggregation involving destabilization by double layer compression occurs at constant

concentration of coagulant, regardless of the concentration of colloidal material. In

contrast, colloidal aggregation involving destabilization by the adsorption of large

polymers can involve a linear (stoichiometric) dependence of optimum coagulant dose on

the concentration of colloidal material.

The coagulation and flocculation process are accompanied with rapid mixing with

coagulant and subsequent slow mixing for flocculation. Slow and rapid mixing can be

done by mechanical means or by hydraulic means. Here slow mixing and rapid mixing

are done by hydraulic means. A series of baffle wall has been constructed in order to

achieve hydraulic mixing in the coagulation and flocculation chamber with closer spacing

in coagulation zone.

The coagulation and flocculation tank is specifically designed for water treatment mixing

application. It is to ensure complete dispersion of coagulants in the water by passing the

water through a series of baffle walls in the tank with a retention time of 30 minutes.

Page 26: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

23

Upon mixing of coagulant to water, a complete physic-chemical reaction occur leading to

the formation of stable floc which will be settled at subsequent sedimentation unit.

4.2.2.3 INCLINED PLATE SETTLER:

It is basically a rectangular sedimentation tank with a series of inclined plate within the

tank where the settle able flocs are settled at the bottom of plate settler. This unit helps

to reduce the amount of fine suspended and colloidal particles present in raw water.

The working principle of plate settler is described below:

• The liquid which contain floc formation particles are introduced between two

inclined plates. Every particle together with liquid will rise until it touches the

surface of the uppermost plate.

• Once the particle and liquid touches the plate surface liquid will rise to the surface

by sliding along the plate.

• Whereas the floc will fall back and touches the lower plate and will slide down

along the lower plate surface.

• Floc present in the liquid will not collide with floc / particular that is sliding down

along the lower plate.

As a result separation of floc / suspended / colloidal particles present in water takes

place. Finally the supernatant water, rising from bottom, will come out through a launder

from the plate settler and is sent to the Filtration Process. The settled sludge will be

transferred to the sludge treatment unit via timer control. The plates are usually set at an

angle between 45 to 60º above the horizontal to obtain self cleaning of sludge from plates.

Normal spacing between the plates is 50 mm.

4.2.2.4 DISSOLVED AIR FLOTATION AND FILTRATION SYSTEM:

Revo-Plus (RVP) is a unique combination of Dissolved Air Flotation (DAF) clarification

and dual media sand filtration in a self contained water treatment module that achieves

excellent water quality. This unit consists of 23 radial chambers in single RVF which

allows 22 chambers in operation and one unit in back washing mode. Thus continuous

production of filtered water and backwashing can be done simultaneously without any

interruption in segments within one RVP.

Page 27: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

24

Raw water enters the flocculation section of RVP. Directional inlet nozzles impart a

circular flow required mixing for optimum floc formation. Through the dissolved air

release mechanism located at the top of the inlet zone of RVP micro bubbles are

introduced which adhere to the floc and cause agglomerated particles to rise to the

surface of the treated water. A portion of the RVP effluent is recycled with pressurized

and semi saturated air. The recycled flow is mixed with unpressurised main stream just

before admission to the flotation tank, with the result that the air comes out of solution

in contact with particulate matter at the entrance of the tank. A spiral scoop then removes

the floated and concentrated accumulation of floc via central pipe. RVP has 23 isolated

cells, hence it is possible to back wash one cell at a time without interfering with

filtered water production from the remaining cells. To accomplish this, a backwash hood

is mounted on a rotating carriage, which is supported and driven by wheels at the top of

the RVP tank. The carriage is programmed to either rotate pass a given cell, or to stop,

lower the backwash hood, and backwash a particular cell. The frequency and the

duration of cell backwash is pre set by control panel, which can be adjusted to suit

process condition. The carriage supports the sludge scoop and the electrical rotary slip

rings which distribute electrical power and control function for the carriage drive

motor and scoop drive motor. A rotary air joint supplies air to raise and lower the

backwash hood. All of these functions are operated by the programmable controller.

4.2.2.5 POST CHLORINATION:

Post Chlorination is the application of chlorine to treated water before it enters into

distribution system to maintain the required amount of free chlorine i.e. ≥ 0.5 ppm. The

objective of post chlorination is to destroy the micro-organisms present in water.

Sufficient chlorine is added to maintain free residual chlorine of ≥ 0.5 ppm as specified in

CPHEEO Manual. Chlorine residual is required to prevent re growth of microorganism /

future contamination in distribution system. Liquid chlorine is used for this purpose.

Chlorinator has been provided for proper dosing of chlorine in to the system. A chlorine

analyzer has been installed to determine the free residual chlorine in the system.

Page 28: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

25

5.0 PIPELINE NETWORK DETAILS AND VALVES ETC:

• Geonkhali to Chaitanyapur - 1100 mm CI pipeline, 9.0 KM

• Geonkhali to Chaitanyapur - 700 mm DI pipeline, 9.0 KM

• Geonkhali to Chaitanyapur - 1000 mm DI pipeline, 6.85 KM

• Chaitanyapur to Basudevpur - 1100 mm CI pipeline, 10.0 KM

• Chaitanyapur to Basudevpur - 900 mm DI pipeline, 8.55 KM

• Chaitanyapur to HPL - 500 / 600 mm DI pipeline, 12.0 KM

• Chaitanyapur to IOCL - 900 mm DI pipeline, 14.5 KM

• Chaitanyapur to IPCL - 800 mm DI pipeline, 5.240 KM

• Basudevpur to MCCPTA - 500 mm CI pipeline 10.0 KM

800 mm DI pipeline 10.0 KM

• Primary Grid - 1100 mm to 100 mm CI pipeline 30 KM

• Secondary Grid - 750 mm to 20 mm CI pipeline 7 KM

• Basudevpur to Medical College/ - 80 mm to 900 mm DI pipeline, 20.33 KM

Upto URAL India Ltd.

• Series Tube wells line - 300 mm and 500 mm 11 KM

• Chaitanyapur to Brajalalchak - 700 mm DI pipeline, 8.6 KM

(Expected to be operational in

July, 2016)

• Brajalalchak to Hatiberia - 700/600 mm DI pipeline, 8.735 KM

(Expected to be operational

in July, 2016)

• Flow meters at Customers end - 20 mm to 800 mm / 152 Nos.

• Valves - 20 mm to 1100 mm dia Sluice / Butterfly valve,

Air release valve, Non Return valves & Dirt Box etc

5.1 PIPE MATERIAL, DIAMETER AND VELOCITY OF FLOW THROUGH PIPES

For transmission and distribution of water from Water Treatment Plant to consumer end,

distribution network of Haldia water supply project consists of more than 100 km long

pipe lines of different diameters ranging from 20 mm to 1100 mm. The pipe materials are

Cast Iron (CI), Ductile Iron (DI) and High Density Poly Ethylene (HDPE). In some old

Page 29: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

26

domestic water supply networks Asbestos Cement (AC) pipes are also used. The use of

AC pipes is now obsolete and no new AC lines are being laid. The distribution networks

mainly consist of CI and DI pipe lines with diameter ranging from 80 mm to 1100 mm.

The branch connections consist of CI and DI pipes with diameter ranging from 80 mm to

450 mm. Velocities of flow in the pipes are around 1.0-1.75 m/s. These are within the

limits specified by manual.

6.0 DETAILS OF 14 NOS. SERIES TUBE WELL WITH RESPECTIVE LOCATION

Serial number 01

Motor location chaitanyapur pumping station near godown

Motor description Tube Well Pump Motor # 1B

KW. Power 12.5 HP

Serial number 02

Motor location Chaitanyapur Pumping Station near boundary

wall

Motor description Tube Well Pump Motor # 1C

KW. Power 12.5 HP

Serial number 03

Motor location Chaitanyapur Pumping Station Near Sub Station

Motor description Tube Well Pump Motor # 1A

KW. Power 15 HP

Serial number 04

Motor location Rambag

Motor description Tube Well Pump Motor # 15

KW. Power 15 HP

Serial number 05

Page 30: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

27

Motor location Near Azra High School

Motor description Tube Well Pump Motor # 14

KW. Power 35 HP

Serial number 06

Motor location Azra

Motor description Tube Well Pump Motor # 13

KW. Power 15 HP

Serial number 07

Motor location Gazipur

Motor description Tube Well Pump Motor # 11

KW. Power 15 HP

Serial number 08

Motor location Bahur Hat

Motor description Tube Well Pump Motor # 10

KW. Power 15 HP

Serial number 09

Motor location Laksya

Motor description Tube Well Pump Motor # 9

KW. Power 20 HP

Serial number 10

Motor location Duriberia Shib Mandir

Motor description Tube Well Pump Motor # 8

KW. Power 15 HP

Serial number 11

Motor location Duriberia School More

Page 31: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

28

Motor description Tube Well Pump Motor # 7

KW. Power 25 HP

Serial number 12

Motor location Duriberia Mile Post

Motor description Tube Well Pump Motor # 5

KW. Power 25 HP

Serial number 13

Motor location Deulpata

Motor description Tube Well Pump Motor # 4

KW. Power 17.5 HP

Serial number 14

Motor location Inside Annex Building

Motor description Annex Tube Well Pump Motor

KW. Power 20 HP

7.0 WATER DEMAND PROJECTION:

In a big water supply project like Haldia Water supply Project, where industrial water

demand predominates over others, future water demands are calculated mainly considering

the following parameters-

1. Industrial water demand( existing and new )

2. Present population and growth pattern (considering rate of water supply for domestic

and municipal demand)

3. Commercial water demand( existing and new )

Page 32: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

29

8.0 DETAILS OF EXISTING CONSUMERS OF HALDIA WATER SUPPLY PROJECT:

Haldia Development Authority supplies water to industrial, commercial, municipal and

domestic consumers. Water supply to Haldia Municipality is made from several intake

points to their reservoirs. Domestic supply includes bulk supply to housing complexes or

large residential complexes.

8.1.1 LIST OF EXISTING INDUSTRIAL CONSUMERS:

Haldia being an industrial region, industrial water supply to existing and upcoming

industrial units is of paramount importance to HDA. The major industrial consumers of

Haldia Development Authority are MCCPTA, HPL, IOCL, Tata Power etc. They consume

about 86% of total industrial water consumption of Haldia Water Supply Project. The raw

water is drawn from river Hooghly and is allowed to settle in big settled water ponds. The

settled water is then pumped to the treatment plants. Treatment method followed in the

water treatment plant consists of Coagulation, flocculation, sedimentation, filtration and

disinfection. The treated water is stored in an underground reservoir having capacity of 2300

CUM and pumped through 1100 mm and 700 mm dia pipe to the booster pumping station at

Chaitanyapur. A dedicated booster pumping station with three centrifugal pumps has been

constructed at Chaitanyapur to supply water to HPL through a dedicated 500 mm dia

pipeline. From Chaitanyapur booster pumping station, water is pumped to the Basudevpur

Booster pumping Station. MCCPTA is fed by a dedicated line from Basudevpur Booster

Pumping Station through a separate set of pumps. All other industries are directly fed from

Basudevpur Underground Reservoir (UGR). IOCL , Haldia Refinery receives water through

a dedicated 900 mm dia D.I pipeline from Chaitanyapur. From Basudevpur, MCCPTA is

served using five vertical pumps of which two were installed in 1988 and another set of three

installed during 2009. The rest of the industries are served from Basudevpur pumping station

using ‘Primary Grid’ supply network. ‘Primary Grid’ is connected to six pumps located at

Basudevpur pumping station drawing water from the existing 22.7 ML (million litres)

reservoir.

Page 33: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

30

A list of existing industrial consumers is given below:

SL

No

Consumer name Contractual Volume (Kilolitre/month)

1 BPCL (Site-1) 600

2 BPCL (Site-2) 60

3 Electro Steel Casting Ltd 48,000

4 Adani Wilmer Ltd 3,000

5 KoPT/HDC 75,000

6 Exide Industries Ltd 18,000

7 Greenways Shipping Industries Pvt Ltd 1,500

8 Haldia Bar & Restaurant/ M/s. Millennium

Inn

60

9 Haldia Friends Electronics Pvt Ltd. 681

10 Haldia Petrochemical Ltd (Phase - III) 953,400

11 Tata Chemicals 27,000

12 Hindustan Lever Ltd 2,250

13 HPCL 800

14 IOC Petronas Ltd 4,500

15 IOCL Haldia Refinery 540,000

16 Petrocarbons & Chemicals Pvt Ltd 6,000

17 Mercus Oil & Chemicals Ltd 5,100

18 MCCPTA India Corp Pvt Ltd 1,269,000

19 RDB Rasayans Ltd 150

20 Manaksia Ltd 7500

21 Himadri Coke & Petro Ltd 60

Page 34: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

31

SL

No

Consumer name Contractual Volume (Kilolitre/month)

22 United Phosphorus Ltd 6,000

23 South Asian Petrochem Ltd/ Dhunsari

Petrochemicals Ltd.

6,000

24 SAIL 60

25 Tata Power 432,000

26 TISCO Ltd 180

27 Ralson Petrochemicals Ltd 10

28 Reliance Industries Ltd 150

29 Sanjana Cryogenic Storage Ltd 900

30 SE Rly Panskura (Sick Line) 1,632

31 M/S Ruchi Soya Industries Ltd 15,000

32 Shree Renuka Sugar Ltd 1,500

33 KS Oil LTD 30

34 Haldia Nirman Projects Ltd 300

35 West Bengal Waste Management Ltd 2,100

36 Exide Industries Ltd-2 (traction factory) 12,000

37 Emami Biotech Pvt Ltd 9000

38 Indicative Consultants 150

39 Ennore Power & Coke Pvt Ltd 2,000

40 Shamon Ispat Ltd 2,700

41 Lal Baba Seamless Tubes P Ltd 1650

42 MSTC Ltd 180

43 Gokul Refoils & Solvent Ltd 6,000

Page 35: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

32

SL

No

Consumer name Contractual Volume (Kilolitre/month)

44 WBSE Tr Cntrl Room & Qtr Complex 300

45 Progressive Packing & Printing Unit 60

46 Modern India Concast Ltd 6,000

47 RH Projects 150

48 Rohit Ferro 5,250

49 IPCL Haldia 3,000

50 Haldia Barauni Pipe Line 4,500

51 Ruchi 2nd Connection 6,000

52 Hindustan Colas Ltd. 1,200

53 Aegis Logistic Ltd. 300

54 JVL Oil Refinery 12,000

55 Industrial Services 150

56 East India Packaging Pvt. Ltd. 750

57 Ralson Petrochemicals Ltd. 22,500

58 IMC Ltd. 300

59 Aegis Logistics 1,500

60 BPCL, HPL Link Road 6,000

61 Bridge & Roof Company 1,500

Total, in Kilolitre per month 3533663

Total, in Million Gallon per day 25.94

Page 36: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

33

8.1.2 LIST OF EXISTING COMMERCIAL CONSUMERS:

SI

No

Consumer Name Contractual Volume (Kilolitre/month)

1 Rose Vally 450

2 Bargabhima Timer Mare 12

3 Benfish Durgachak 90

4 Central Ware house Corporation 120

5 Chakroborty Hotel Basudevpur 60

6 Contai Co-Operative Bank 90

7 KoPT/HDC (Durgachak Camp Office) 3,750

8 Dr. S Naskar (Nursing Home) 60

9 Adarsha Hotel & Restaurant 60

10 Ganga Tourist Lodge 300

11 Haldia Distn (O&M) Sub-Divn, Wbsedcl 48

12 (Mohona Market - Township), Haldia

Municipality

250

13 Uttar Durgachalk(New Market), Haldia

Municipality

1,000

14 LICI, Haldia 240

15 M/S Gangadhar Bera, Manjushree Morh 600

16 Wb State Fisherman’s Co-Op. Federation Ltd 30

17 Nirapada Nayek, Hotel –Cum-Restaurant 60

18 Port Land Hotel 120

19 R.D.B Construction (Construction Phase) 60

20 Ramkrishna Hindu Hotel, Finger Jetty 60

21 Subhas Chandra Mondal, Hotel Cum Restaurant 30

Page 37: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

34

SI

No

Consumer Name Contractual Volume (Kilolitre/month)

22 Tamluk Ghatal Co-Operative 30

23 W.B Small Scale Industries Ltd 3,150

24 West Bengal State Warehousing Corp -

25 Park Hotel & Restaurant Debhog; City Center 90

26 Roy Construction, Khanjanchak, Haldia 30

27 Haldia Lions Trust, Basudevpur, Near Govt.sch 225

28 Haldia logistic Pvt. Ltd. (Boys Hostel) 300

29 Ambuja Realty 1500

30 Global Education Society 450

31 Hiralal Maity 103

32 Haldia Bhoj Hotel 146

33 Burger King Fast Foods Center 30

34 Ganga Developers 10

35 Benia Commercial Pvt. Ltd. 120

36 Sitala Sweets 60

37 SAS Nirman Pvt. Ltd. ( Plot C) 600

38 CESC Properties Ltd. 3,000

39 Remendra Sundar Maity 150

Total, in Kilolitre per month 17,484

Total, in Million Gallon per day ( MGD) 0.13

8.1.3 EXISTING DOMESTIC & MUNICIPAL CONSUMERS

Water to domestic and municipal consumers is supplied mainly from Basudevpur Booster

Pumping Station and Hatiberia Booster Pumping Station. Only a little part of domestic water

supply is undertaken from Geonkhali water treatment plant and Chaitanyapur Booster

Page 38: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

35

Pumping Station. Geonkhali Rehabilitation Colony is supplied directly from Over Head

Reservoir at Geonkhali Water Treatment Plant site. Sutahata area of Haldia is served from

Chaitanyapur Booster Pumping Station.

8.1.3.1 LIST OF EXISTING DOMESTIC CONSUMERS

Sl

No

Customer Name Contractual volume

(Kiloliter/month)

1 STPI Building, Software Tech Parks of India 337

2 Near Mohanna Market Township 250

3 Akashdeep Dormitory 188

4 Housing construction Sub-Div 2,190

5 B.Chakraborty 83

6 Bharatiya Vidya Bhaban 36

7 CIPET Annexe Building 1,800

8 Chrinjibpur Police Station 2,331

9 KoPT/HDC (Cluster – 10,19,9&5) Haldia

Township

68,190

10 KoPT/HDC(CPT Office Chiranjibpur) 7,500

11 CWC Complex Residence, Haldia 450

12 Dilip Kumar Samanta, Basudevpur 30

13 HFCL 21,000

14 Haldia Distribution (O&M) Sub-Div WBSEDCL 381.36

15 Haldia Distn (O&M) Sub Div WBSEDCL 410

16 Haldia Govt Sponsored Secondary School 272.4

17 OFC MTCE Haldia, BSNL Haldia, OFC/MW

Stn

204

18 Haldia Sub-Divisional Hospital(Non-Resi) 4,050

Page 39: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

36

Sl

No

Customer Name Contractual volume

(Kiloliter/month)

19 Haldia Sub-Divisional Hospital(Residence) 6,129

20 Indian Oil Corporation Ltd 72,000

21 Indian Oil Petronas Ltd 60

22 Lions Club of Haldia Durgachak Haldia 300

23 MCC PTA India Corpn Ltd Residence 6,000

24 MCC PTA India Crpn Ltd Workers Colony 2,000

25 Meghnad Saha Institute of Technology 3,000

26 Priyambada Apartment Owners Association 160

27 Raja Rammohan Siksha Niketan 30

28 SBI/HPB 900

29 SE Rly, Panskura (Durgachak Town Station) 540

30 SP Purba Medinipur Tamluk 41

31 Sadanand Maity, Basudevpur 30

32 Uttam Bedding Shop 15

33 Kushadwaj Panda, Basudevpur 26

34 Smt Rekha Maity, Basudevpur 60

35 Swapan Ponda, Debbhog 30

36 Swati Housing Owners Association 2016

37 Telecom Staff Qtrs 300

38 Telephone Exchange, SDO 300

39 Telephone Exchange Basudevpur 240

40 WBSEB GTP Chiranjibpur 3,750

41 Chief Medical Officer Health 575

Page 40: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

37

Sl

No

Customer Name Contractual volume

(Kiloliter/month)

42 Haldia Riverside Estates Ltd (HREL) 9,990

43 Haldia Presbyterian Church Basudevpur 30

44 Millitary Engineer Services, B/R Haldia 1,200

45 Santidham Ashram -

46 Kannya Milan Girls High School 90

47 SE Rly, Panskura (Durgachak Station Alichak) 1,230

48 Classic Enterprise 1,800

49 HDA Connections (16 Connections) -

50 PHE Bungalow, Basudevpur SGS 120

51 Life Insurance Corporation of India 1,550

52 MCCPTA Colony 67

53 Rumi Bibi 56

54 Land Mark Cultural Society Ltd. 300

55 Vivekananda Mission Ashram Rampur 100

56 IOCL Co-operative Credit Society Plot no. 5,6,7

& 8

1200

57 IOCL Co-operative Credit Society Plot no. 9 300

58 IOCL Co-operative Credit Society Plot no. 1 135

59 IOCL Co-operative Credit Society Plot no. 10 300

60 Coast Guard 1500

61 Coast Guard, Residential area 4920

62 Coast Guard, Vikram Enclave 5000

Total, in Kilolitre per month 2,38,092.76

Total, in Million Gallon per day ( MGD) 1.75

Page 41: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

38

8.1.3.2 LIST OF EXISTING MUNICIPAL CONSUMERS

SI

No

Customer Name Contractual Volume

(Kilolitre/month)

1 HM (Sutahata-Amlat) 65,700

2 HM (Bisnabchak W/S) 29,400

3 HM (New Rehab Col at Durgachak) -

4 Haldia Municipality (ADM Building) 1,960

5 Sudipta Sahoo (HFC) 68

6 Subhash Chandra Ghosh 60

7 Srijib Kumar Nayak 240

8 Arup Kumar Dey 30

9 SMT Chhabi Chatterjee 20

10 Mahadeb Chandra Samanta 30

11 Biswanath Nandi 60

12 (Rehabilitation Colony) opposite Hotel Millenium 7

13 Basudevpur Scheme Zone_1(4013) 1,13,400

14 Chaktraun 26,700

15 Hindustan Market -

16 Brajanathchak Colony 3,900

17 Khudiramnagar 64,800

18 Beside Utsav Bhaban -

19 Gandhari Nagar Colony 24,300

20 Uttar Durgachak-II near Durgachak Super Market 22,800

21 Birangana Colony

Page 42: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

39

SI

No

Customer Name Contractual Volume

(Kilolitre/month)

22 Bagam Rakea Girl’s School

23 Azad Hind Nagar

Hatiberia Satish Samanta Park

33,600

24 Satish Samanta Park

25 Uttarchak-II near Durgachak Super Market 83,400

26 Baishnabchak, Debhog 24,900

27 Padampukur, Hatiberia

Total, in Kilolitre per month 4,95,375

Total, in Million Gallon per day ( MGD) 3.64

9.0 INDICATIVE DETAILS OF WATER DEMAND FOR NEW CONSUMERS/

ENHANCEMENT OF WATER REQUIREMENT OF EXISTING CONSUMERS OF

HALDIA WATER SUPPLY PROJECT:

Haldia Development Authority has received many applications regarding new requirement of

water/additional requirement from new/existing industrial, commercial, municipal and

domestic establishments which have been summarized categorically as under:

9.1 INDICATIVE FUTURE WATER REQUIREMENT OF INDUSTRIAL CONSUMERS:

NAME OF

INDUSTRY

PROJECTED ADDITIONAL/NEW FUTURE DEMAND (IN MGD) IN

FUTURE YEARS

2016 2017 2018 2019 2020

IPCL 2.5 7.5 15 15 15

IOCL 0 0 4 4 4

Page 43: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

40

9.2 INDICATIVE FUTURE WATER REQUIREMENT OF COMMERCIAL CONSUMERS

NAME OF

COMMERCIAL

CONSUMERS

PROJECTED ADDITIONAL/NEW FUTURE DEMAND (IN MGD) IN

FUTURE YEARS

2016 2017 2018 2019 2020

SAS NIRMAN

( Plot B)

0.004 0.004 0.004 0.004 0.004

IOCL, Retail Outlet

at Bhawanipur

0.001 0.001 0.001 0.001 0.001

Deep Shikha

Enterprise

0.001 0.001 0.001 0.001 0.001

9.3 INDICATIVE FUTURE WATER REQUIREMENT OF DOMESTIC CONSUMERS

NAME OF DOMESTIC

CONSUMER

PROJECTED ADDITIONAL/NEW FUTURE DEMAND (IN MGD)

IN FUTURE YEARS

2016 2017 2018 2019 2020

CESC Properties Ltd. 0 0.077 0.077 0.077 0.077

9.4 INDICATIVE FUTURE WATER REQUIREMENT OF MUNICIPAL CONSUMERS

NAME OF

MUNICIPAL

CONSUMERS

PROJECTED ADDITIONAL/NEW FUTURE DEMAND (IN MGD)

IN FUTURE YEARS

2016 2017 2018 2019 2020

Haldia Municipality 4.0 4.0 4.1 4.1 4.1

9.5 SUMMARY OF WATER DEMAND PROJECTION:

Category Year:2016 Year:2017 Year:2018 Year:2019 Year:2020

Industrial 28.44 33.44 44.94 44.94 44.94

Page 44: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

41

Commercial 0.13 0.13 0.13 0.13 0.13

Domestic 1.75 1.83 1.83 1.83 1.83

Municipal 4.00 4.00 4.10 4.10 4.10

Total, in MGD 36.43 39.40 51 51 51

10.0 RAW WATER QUALITY:

The present water supply system primarily uses raw water of river Hooghly drawn through

Intake jetties near Geonkhali Water Treatment Plant.

Raw water collected through intake jetty at Geonkhali has two key quality issues: high turbidity

and high salinity. Out of that, the turbidity issue can be addressed relatively easily through

primary sedimentation and clariflocculation system in the WTPs.

The water to be handled may vary both in quality and quantity. The water quality of river

Hooghly varies from season to season. The turbidity level in rainy season is as high as 1600 NTU

to as low as below 100 NTU in winter. The degree of treatment required may vary seasonally,

monthly and even hourly. Raw water quality of river Hooghly, in terms of turbidity, pH and

Total Alkalinity is given below.

Table 1: Data on Raw Water Quality

Month

Av pH

Av Turbidity (NTU)

Total Alkalinity mg/l as CaCO3

January 7.92 100 188

February 7.95 160 190

March 7.98 200 150

April 8.05 240 155

May 7.98 280 160

June 7.82 400 95

July 7.80 650 100

August 7.85 750 120

September 7.93 530 125

Page 45: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

42

October 7.96 280 120

November 7.85 170 148

December 7.98 120 171

10.1 Salinity in Hooghly near Geonkhali

Geonkhali, the location of the WTPs is in a stretch of Hooghly which experiences a semi-diurnal

tidal cycle. Mixing of saline sea water of the Bay of Bengal with the freshet of Hooghly makes it a

source which is not always a fresh water source. The level of salinity is highest during the dry

period of no or insignificant freshet through Hooghly. Salinity decreases with increase in freshet

during Monsoon and Post Monsoon seasons. Again, level of salinity varies during the semi-

diurnal tidal flows, two high tides in a day giving rise to high levels of salinity while salinity

levels are significantly low during two low tides, in general. The following Table describes

quality of raw water generally available and corresponding duration in a day during different

seasons in a year:

Table 2: Salinity levels at different seasons

Season

Period

Duration (months) in a Year

Semi-Diurnal Low Tide Hrs

Expected Salinity Range

during low tides (ppm)

Remarks

1st Cycle

2nd Cycle

Monsoon

3rd week of June to Oct

4.5

8 8 20-100 Fresh Water

Post-Monsoon

Nov to 3rd week of Feb

3.75 5.5 5.5 60-300 Fresh Water

Summer (Dry)

Last week of Feb to 2nd week of June

3.75 3.5 3.5 450-900 Saline water, salinity to be monitored strictly and pumping to be planned accordingly.

Details below regarding salinity measured in raw water samples taken during different hours of

the day, duly covering the high and low tides during the day and summarized as under:

Page 46: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

43

Table 3: Chloride data for summer seasons of 2011, 2012, 2013, 2014 & 2015

Year Month Chloride, ppm (Max) Chloride, ppm (Min) Mean Value (ppm)

2011 March 2950 180 941

April 2710 520 1179

May 1970 201 880

June 912 21 1179

2012 March 2344 460 1290

April 2695 278 1140

May 1764 216 752

June 1686 115 590

2013 March 1706 107 616

April 1878 264 855

May 2128 226 909

June 1036 46 304

2014 March 2237 471 1209

April 2367 278 1140

May 1739 216 768

June 1661 105 590

2015 March 1721 115 603

April 1826 234 798

May 2197 197 898

June 1011 46 297

Data were collected three to six times a day, as required for establishment of a daily trend in salinity. During March and June, samples are generally within the WHO guidelines (cause for Rejection) of

potable water that is less than 1000 ppm during low tides. Strict monitoring, however, is required

during April to draw water during the low tides, only for the periods when chloride levels are

within 500-700 ppm levels. Salinity issue is being addressed by HDA by strict monitoring of

Page 47: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

44

salinity levels during low tides, prudent operation of pumps and mixing treated water with

ground water from the existing bore wells near Chaitanyapur Pumping Stations.

10.2 Raw Water Pumping Capacity

The Present System has 4 raw water pumps (@ 4500 cum / hour capacity) of the old plant and 4

raw water pumps (@ 5100 cum / hour capacity) for the new plant. Though there are separate

raw water pump houses, raw water reservoir is common. Therefore, raw water pumps could be

run in tandem to supply raw water to both the plants from a common reserve.

Considering no overloading for the pumps, the existing capacity of raw water pumping comes to

28800 cum per hour (3X4500+3X5100). For 7 hours’ pumping, total raw water drawn is about

201600 cum i,e 44.4 MGD. (Loss in treatment, transmission could be met by minor overloading of

raw water pumps for supply of water upto 51 MGD). The suction pipes having 1000mm

diameter, shall be subject to a suction velocity which is well within the permissible limit of

velocity in suction pipes in accordance with the Manual.

11.0 HISTORICAL DATA OF WATER SALE IN INDUSTRIAL AND TOTAL WATER

(INDUSTRIAL, COMMERCIAL, DOMESTIC & MUNICIPAL) CATEGORY:

Industrial Water Consumption Total Water Consumption

Year Consumption, MGD Year Consumption, MGD

2009-10 18.24 2009-10 21.10

2010-11 21.40 2010-11 24.79

2011-12 21.19 2011-12 24.50

2012-13 20.47 2012-13 24.71

2013-14 19.81 2013-14 23.82

2014-15 17.62 2014-15 21.45

Apr,15-Dec,15 21.43 Apr,15-Dec, 15 25.51

Page 48: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

45

12.0 HISTORICAL DATA OF EXPENDITURE FOR OPERATION & MAINTAINANCE OF

HALDIA WATER SUPPLY PROJECT

For day to day operation & maintenance of Haldia Water Supply Project, following are the

variable and uncertain factors:

A. Labour Charges

B. Chemical Charges

C. Repair & maintenance charges

D. Replacement/ Rehabilitation charges

E. Establishment/ Administrative Charges

F. Details of power charges are not provided as Haldia Development Authority will

make payment for power consumption to WBSEDCL directly and thus this scope is

excluded for the bidders.

Historical data of expenditures under the above-stated variable factors (A, B, C, D & E) are

given below:

* New 25 MGD WTP started operation since December, 2014.

Year Labour Charges( in Rs. Crores)

Chemical Charges( in Rs. Crores)

Repair and maintenance charges( in Rs. Crores)

Replacement/rehabilitation charges ( in Rs. Crores)

Establishment/administrative Charges ( in Rs. Crores)

Total ( in Rs. Crores)

2009-10 2.46 0.70 2.92 2.94 0.310 9.33

2010-11 2.95 0.74 4.28 0 0.330 8.30

2011-12 3.48 0.77 3.49 0 0.340 8.08

2012-13 4.01 0.81 4.14 0 0.430 9.39

2013-14 4.23 0.92 0.91 1.00 0.012 7.07

2014-15*

5.25 1.71 1.36 1.00 0.0125 9.33

Apr,15-Dec-15

4.13 1.41 4.13 2.00 0.013 11.67

Page 49: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

46

13.0 SAMPLE AGREEMENT WITH CONSUMERS OF HALDIA WATER SUPPLY PROJECT

This Agreement made on the___________day of____________________ two thousand

_____________ BETWEEN Haldia Development Authority, constituted under the West Bengal

Town and Country (Planning and Development) Act, 1979 (hereinafter called the Authority) of

the ONE PART and________________________________ (herein called the Consumer) of the

OTHER PART.

Whereas the Authority has decided to supply clear/filtered water to the consumer for the

purpose of Industrial/ Commercial/ Domestic use at ___________________________________ .

AND WHEREAS the consumer has agreed to purchase water from the Authority on the terms

and conditions hereinafter appearing;

NOW, THEREFORE, the parties hereto, hereby covenant with each other to observe and

perform the following that is say :-

1) The Authority will supply filtered/cleared water to the consumer ________K.L. per day,

at his _______________ at ______________ for ____________ use, @ _______ (Rupees

_________________only) per K.L. and a monthly Meter rent of Rs. 10/-(Rupees

_________ only) will be charged by the Authority from the consumer.

2) Filtered / Clear water will be supplied to underground water reservoir to be constructed

by the consumer within his premises. In no circumstances water will be drawn directly

by pumping from the service connection;

3) Supply will be metered and meter rent @ …./- (Rupees …..only) per month will be

payable by the consumer.

4) A suitable water meter will be supplied and installed by the Haldia Development

Authority and the same will be maintained by the Authority or its Agency.

Page 50: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

47

5) Monthly bills will be raised against consumption of water at the rates mentioned in

schedule hereunder for payment within the due date, and a penalty charges @ …..

(Rupees ….) per ….. litres per month or part thereof or at any other rate as may be

revised by the Authority from time to time will be charged if the bill is not paid within

the due date.

6) The Authority shall have the right to revise from time to time the rate of water charges

and connection charges mentioned in the schedule as and when considered necessary.

The penal rate may also be revised as and when considered necessary.

7) If the bill is not paid within 15 days from the due date, the water connection will be liable

to be cut off with a prior notice and re-connection charges as given in the schedule will

have to be borne by the consumer. The reconnection charges are also subject to revision

from time to time.

8) If no water is consumed or water consumed is less than 50% of the sanctioned quantity,

consumer will have to pay the minimum charge at the rate of 50% of the water charge for

the quantity of water sanctioned to him at the rate fixed by the Authority from time to

time.

9) Maximum 20% in excess of the sanctioned quantity may be drawn. But if the demand

exceeds that limits, fresh application is to be given for sanction of additional quantity.

10) The Authority assumes no responsibility in case of failure of water supply due to power

failures, major breakdown of supply system or any other reason which is beyond control

of the Authority.

11) If the water meter is out of order or do not function due to any reason during any period,

the bill for the said period will be prepared on the basis of average consumption for three

previous bills or other reasonable basis as may be determined by the Authority and will

be binding on consumer.

Page 51: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

48

12) One month's advance water charges calculated on the basis of sanctioned quantity of

water at the rate fixed by the Authority from time to time is to be paid as Security

Deposit. In addition, for new connection, separate connection charges as mentioned in

schedule fixed by the Authority from time to time is to be deposited before getting

connection.

13) The Authority may, at its discretion, revise the terms and conditions regarding supply of

water to its consumers, with prior intimation to them.

IN WITNESS WHEREOF the Chief Executive Officer of the Haldia Development

Authority for and on behalf of the Authority duly authorised by the Authority to sign these

presents on the day, month and the year first above written.

_____________________________________ (Signed by for and on behalf of the Authority)

_____________________________________ (Signed by for and on behalf of the Consumer)

Address:

____________________________________

____________________________________

____________________________________

Address:

____________________________________

____________________________________

____________________________________

1. Witness:

____________________________________

Address: ___________________________

____________________________________

____________________________________

1. Witness:

____________________________________

Address: ___________________________

____________________________________

____________________________________

2. Witness:

____________________________________

Address: ___________________________

____________________________________

____________________________________

2. Witness:

____________________________________

Address: ___________________________

____________________________________

____________________________________

Page 52: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

49

14.0 LIST OF MAPS & DRAWINGS

FIGURE 1: LAND MAP OF BASUDEVPUR BOOSTING STATION

Page 53: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

50

FIGURE 2: SATELLITE IMAGE OF BASUDEVPUR PUMPING STATION

Page 54: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

51

FIGURE 3: LAND MAP OF GEONKHALI OLD & NEW 25 MGD WTP

Page 55: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

52

FIGURE 4: SATELLITE IMAGE OF GEONKHALI OLD 25 MGD WTP

Page 56: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

53

FIGURE 5: SATELLITE IMAGE OF GEONKHALI NEW WTP

Page 57: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

54

FIGURE 6: LAND MAP OF CHAITANYAPUR BOOSTING AND PUMPING STATION

Page 58: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

55

FIGURE 7: SATELLITE IMAGE OF CHAITANYAPUR BOOSTING AND PUMPING STATION

Page 59: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

56

FIGURE 8: LAND MAP OF HATIBERIA BOOSTING STATION

Page 60: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

57

FIGURE 9: SATELLITE IMAGE OF HATIBERIA BOOSTING STATION

Page 61: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

58

FIGURE 10: SATELLITE IMAGE OF BRAJALALCHAK CLEAR WATER RESERVOIR

Page 62: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

59

FIGURE 11: SATELLITE IMAGE OF HALDIA INDUSTRIAL BELT

Page 63: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

60

FIGURE 12: MAP OF HALDIA PLANNING AREA

TOTAL PLANNING AREA: 1961 Sq. Km

Page 64: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

61

FIGURE 13: NETWORK DRAWING FROM CHAITANYAPUR TO IOCL

Page 65: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

62

FIGURE 14: WATER FLOW DIAGRAM OF INDUSTRIAL WATER SUPPLY OF HALDIA WATER

SUPPLY PROJECT

Page 66: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

63

FIGURE 15: WATER FLOW DIAGRAM OF PHASE-II & III OF HALDIA WATER SUPPLY PROJECT

Page 67: 2016 Annexure – XII · PDF file4.2.2.4 dissolved air flotation and filtration system 23 4.2.2.5 post chlorination 24 ... figure 13 network drawing from chaitanyapur to iocl 62

DETAILED PROJECT REPORT

64

FIGURE 16: NETWORK MAP OF HALDIA WATER SUPPLY PROJECT