2015-20 plan
-
Upload
murshed-sumon -
Category
Documents
-
view
215 -
download
0
description
Transcript of 2015-20 plan
The JICA Study has developed a Long Term Master Plan (PSMP-2010) according to the study for power demand forecasts and the power supply development plan by 2030 in Bangladesh. PSMP-2010 is divided into four period:
2010-2015
2015-2020
2020-2025
2025-2030Scope of transmission expansion planning in Long Term Master Plan (PSMP-2010) is shown in below:
2010-2015: Short term plan (Detail)
2015-2020: Mid & long term plan ( Only 400kV &230kV)
2020-2025: Mid & long term plan ( Only 400kV &230kV)
2025-2030: Mid & long term plan ( Only 400kV &230kV)
As for the implementation of the transmission network plan for horizon year 2030, 2010-2015 plan is under implementation. Scope of work of this study is preparing detail transmission plan for 2015-2020 based on PSMP-2010 & considering the following factors:
(1) Power demand forecast for 2015-2020.(2) Power development plan for 2015-2020.(3) Effective utilization and expansion of the existing transmission network.(4) Facilities expansion criteria.(5) Possible power system interconnected with the neighboring countries,
6) Least cost basis facilities development.
(7) Environmental situation.(8) Grid code.1.0 PSMP-2010 (2015-2020 season)1.1 Planning criteria
The following criterias were considered during transmission expansion plan in PSMP-2010: 1.1.1 Demand & generation forecast
1.1.2 Basic concept of substation expansion
If the power flow through the 230kV and 132kV substation exceeds this value which is shown in Table 1, the substation expansion will be basically studied. Table-1
SubstationUrbanRural
230/132kV500 MW300 MW
132/33kV100 MW100 MW
1.1.3 Reliability criteria in normal conditions and outage contingencies of facilitiesTable-2Normal conditions of facilities Facilities loading