2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

35
1 © 2012 Eaton Corporation. All rights reserved. CYME Distributed Generation Screening Tool PV Distribution System Modeling Workshop May 6 th , 2013. Jean-Sébastien Lacroix ing./Eng.

description

2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

Transcript of 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

Page 1: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

1 © 2012 Eaton Corporation. All rights reserved.

CYME Distributed Generation Screening Tool PV Distribution System Modeling Workshop May 6th, 2013. Jean-Sébastien Lacroix ing./Eng.

Page 2: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

2 © 2012 Eaton Corporation. All rights reserved.

Agenda

• Utility Context

• CYME DG Screening Tool

• Pre-Application

• Generator Interconnection Procedures (GIP)

• California Rule-21 (Fast Track)

• Federal Energy Regulatory Commission (FERC)

• DG Screening Tool Demo

• Conclusion

Page 3: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

3 © 2012 Eaton Corporation. All rights reserved.

Utility Context

Renewables Energy Facts • California Objective – 33% Renewables by 2020

• California Solar Initiative – 3 GW of PV by 2017

• Over 17 000 Solar Rooftops (130 MW)

• Over 1.5 GW for SDG&E

• More than 1000 PV interconnection applications in

California, Hawaii and New Jersey each month

Net Energy Metering Program

• Over 120,000 residential and non-residential accounts

enrolled in California's NEM program (< 1 MW)

Page 4: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

4 © 2012 Eaton Corporation. All rights reserved.

Utility Context

Interconnection Procedures Standard

• In 1999, the California Public Utilities Commission

(CPUC) adopted the Rule 21 to increase the

efficiency of the review of small generation

interconnection. Revised in 2012

• In 2003, IEEE-1547 Standard for Interconnection of

Distributed Resources with Power Systems

• In 2005, FERC adopted small generation

interconnection procedures called the Small

Generator Interconnection Procedures (SGIP).

Page 5: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

5 © 2012 Eaton Corporation. All rights reserved.

Utility Context

Interconnection Procedures Flow Example • Step 1 – Pre-Application Report Request

• Step 2 – Pre-Application Report

• Step 3 – Interconnection Request Process

Study Process - Fast Track

Non Exporting/Net Energy Metered

Exporting < 3 MW on a 12kV system

Detailed Study Process

Large impact on grid is anticipated

Projects that have failed in Fast Track

• Step 4 – Application Review & Initial Review

• Step 5 – Supplemental Review & Detail Interconnection Study

• Step 6 – Generating Facility Interconnection Agreement

• Step 7 – Execution of the Generator Inter. Agreement

Page 6: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

6 © 2012 Eaton Corporation. All rights reserved.

Utility Context

Proposed IT Solution • New Window Desktop Application

• Dashboard-type interface

• Manages and assesses various DG interconnection

requests

• Three Types of Screening

Pre-Application

Initial Screening – California Rule 21

Initial Screening – FERC

• Connected to CYME DB and enterprise DB

Page 7: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

© 2013 Eaton Corporation. All rights reserved.

CYME DG Screening Tool

Page 8: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

© 2013 Eaton, All Rights Reserved.

CYME Products and Services Overview

Best-in-Class System Analysis Tools and Services From Transmission to Distribution to Industrial

Power Engineering

Software

Integration Projects and Solutions Operations Solutions

Decision Support

for Network

Planning Analysis Engineering Consulting Services

Decision Support

for Real-Time

Applications

State Estimator

DG Impacts

Reliability

Harmonics

Volt/PF optimization

CYME Power System Analysis

Distribution

Transmission

Industrial

CYMCAP Cables

CYMTCC Protection

CYMGRD Substation Grounding

web

Utility

.

CYME

Network Model DMS

Volt/Var Control

Feeder

Automation

Studies & Services

CYME Gateway

CYME Server

GIS

SCADA

OMS

AMI

Page 9: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

9 © 2012 Eaton Corporation. All rights reserved.

CYME DG Screening Tool

NEW

CYME DG

Screening Tool

CYMECYME

DG Screening

Database

DG

Sim

ula

tio

n

Study

Distribution Engineer’s Desktop

CYME Server

DG Applications

Server

CYME

DatabaseNetwork Model

Application Architecture • Based on CYME Server and CYME DB

• New DB for DG Screening application

Page 10: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

10 © 2012 Eaton Corporation. All rights reserved.

Pre-Application

Screens a-d a. Total Capacity (MW) of substation/area bus or bank and circuit

b. Allocated Capacity (MW) of substation/area bus or bank and circuit

c. Queued Capacity (MW) of substation/area bus or bank and circuit

d. Available Capacity (MW) of substation/area bus or bank and circuit

Summary – Screens a,b,c,d

Device A (MW) B (MW) C (MW) D (MW)

Bank 50.5 15.4 28.1 7.0

Breaker 9.5 3.2 5.6 0.7

Page 11: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

11 © 2012 Eaton Corporation. All rights reserved.

Pre-Application

Screens e-I e. Substation nominal distribution voltage (e.g. 12 kV)

f. Nominal distribution circuit voltage (e.g. 12 kV)

g. Approximate circuit distance between the proposed site and the substation.

(e.g. 56,000 ft)

h. Relevant Line Section(s) peak load estimate, and minimum load data, when

available.

i. Number of protective devices and number of voltage regulating devices

between the proposed site and the substation/area. (e.g. 3 Protective Devices

and 1 regulating devices)

Device Peak (kW) Min (kW)

Bank 5,200 3,800

Breaker 2,500 1,000

Fuse 185 45

Page 12: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

12 © 2012 Eaton Corporation. All rights reserved.

Pre-Application

Screens j-l j. Whether or not three-phase power is

available at the site. (e.g. No)

k. Limiting conductor rating from proposed

Point of Interconnection to distribution

substation. (e.g. 120 Amps)

l. Based on proposed Point of Interconnection,

existing or known constraints such as, but

not limited to, electrical dependencies at that

location, short circuit interrupting capacity

issues, power quality or stability issues on

the circuit, capacity constraints, or

secondary networks. (e.g. Existent

Synchronous machines)

Page 13: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

13 © 2012 Eaton Corporation. All rights reserved.

Pre-Application

Report

• Automated

• WORD Format

• Customizable

Page 14: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

14 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

CYME DG Interconnection Application

California Rule-21

• Dashboard

• Step-by-Step

• Colors

• Pass – Green

• Failed – Red

• Arrows to guide

through screens

Page 15: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

15 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

DG Application

Properties

- Project General Info

- Nominal Ratings

- Feeder and Bank Id

- Installation Type

- Dates

Page 16: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

16 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Global Parameters

- FERC Limits

- Rule 21 Limits

- All limits are then user-

defined

- Default values are

found in FERC and

Rule 21 documentation

Page 17: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

17 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

DG List Manager

- Retrieved from enterprise database

- Status – Active, Widthdrawn…

- Possibility of adding projects (DG)

Page 18: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

18 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Pre-Screens – 1 through 4

• Screens 1-4

• Screen 1: Complete/Valid Interconnection Request

• Checks if DB connection and data is correct

• Screen 2: Does the Applicant choose to go directly to

Detailed Studies? Yes or No

• Screen 3: Non Export/Net Energy Metering (NEM) or

Export?

• Screen 4: Fast Track Eligibility

Page 19: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

19 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – A through H

• If Screens A through H fails, solutions to mitigate the

impact of failed screens:

• Replace an overloaded distribution transformer

• Replace overloaded secondary conductors

• If no quick solutions can be adopted, then

supplemental review is required

Page 20: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

20 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – A through H

• Screen A : Is the PCC on a Network Secondary

System. Yes or No

• Screen B: Is Certified Equipment used? Yes or No

• Screen C: Is the Starting Voltage Drop within

acceptable limits?

• Calculation for Induction Machines based on Starting In-

Rush current vs. Nominal Transformer Current

• Screen D: Transformer Rating

• Compares transformer rating with aggregated gross

nameplate rating of the installation

Page 21: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

21 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – A through H

• Screen E : Does the Single-Phase Generator cause

unacceptable imbalance? Yes or No

• Screen F: Is the Short Circuit Current Contribution

Ratio within acceptable limits?

• Short-Circuit Current Ratio (SSCR) Calculation

Where SCCR (%) = Short Circuit Contribution of DG / Short Circuit Current at PCC

Page 22: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

22 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – A through H

• Screen G : Is the Short Circuit Interrupting Capability

Exceeded?

• Screen H : Is the line configuration compatible with the

Interconnection type?

Primary Distribution

Line Type

Type of Interconnection to

Primary Distribution Line

Result/Criteria

Three-phase,

three wire

3-phase or single phase, phase-

to-phase

Pass screen

Three-phase,

four wire

Effectively-grounded 3 phase or

Single-phase, line-to-neutral

Pass screen

Three-phase,

four wire

All Others To Pass, aggregate DG Capacity must be

less than or equal to 10% of Line Section

Peak Load

Page 23: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

23 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Quick Review

Continue the Initial Review

or

Go to Supplemental Review

Page 24: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

24 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – I through M

• Screen I : Will power be exported across the PCC?

If no, Generating Facility must incorporate one of the following:

• Reverse Power Protection

• Minimum Power Protection

• Certified Non-Islanding Protection

• Relative Generating Facility Rating

• Inadvertent Export

• Screen J : Is the Gross Rating of the Generating

Facility 11 kVA or less?

Page 25: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

25 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Initial Review – I through M

• Screen K : Is NEM project whose nameplate capacity is <=

500kW?

• Screen L : Transmission Dependency and Transmission

Stability Test. Yes or No

• Screen M: Is the aggregate Generating Facility capacity on the

Line Section less than 15% of Line Section peak load for all line

sections bounded by automatic sectionalizing devices?

Page 26: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

26 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Supplemental Review – N through P

• Screen N : Penetration Test

• Similar to test M

• Screen O : Power Quality and Voltage Tests

• A) Voltage regulation

• B) Voltage fluctuation/flicker under limits IEEE 1453

• C) Harmonics levels meets IEEE 519 limits

• Screen P: Safety and Reliability Tests

• 1. Generation energy source

• 2. Modes of synchronization

• 3. Unique system topology

• 4. Possible impacts to critical load customers

Page 27: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

27 © 2012 Eaton Corporation. All rights reserved.

GIP California Rule 21

Report

• Automated

• WORD Format

• Customizable

• 10-12 page report

• Introduction

• Project Information

• Initial Review Process

• Summary

• Required Information to

conduct a supp. Review

• Next Steps

Page 28: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

28 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

CYME DG Interconnection Application

FERC

• Dashboard

• Step-by-Step

• Colors

• Pass – Green

• Failed – Red

Page 29: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

29 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

CYME DG Interconnection Application-FERC

• Similar to California Rule 21

• DG Application Properties

• Global Parameters

• DG List Manager

• Differences with California Rule 21

• Labels and screens title

• Global parameters default values

Page 30: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

30 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

Initial Review – 1 through 10

• Screen 1: Complete/Valid Interconnection Request Same as Screen 1 of Rule 21

• Screen 2: Aggregate generation <= 15% of line

section peak load? Same as Screen M of Rule 21

• Screen 3: Is the PCC on a Network Secondary

System. Same as Screen A of Rule 21

• Screen 4: Is the Short Circuit Current Contribution

Ratio within acceptable limits? Same as Screen F of Rule 21

• Screen 5: Is the Short Circuit Interrupting Capability

Exceeded? Same as Screen G of Rule 21

Page 31: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

31 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

Initial Review – 1 through 10

• Screen 6: Is the line configuration compatible with the

Interconnection type? Same as Screen H of Rule 21

• Screen 7: Single Phase Generating Facility <=

20kW? Similar as Screen J of Rule 21 (only for single phase)

• Screen 8: Single Phase Generator with Center Tap ?

For single phase generator,

comparison with gross nameplate

rating with distribution transformer

nameplate rating. The ratio must

be less than maximum distribution

transformer nameplate rating ratio

Page 32: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

32 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

Initial Review – 1 through 10

• Screen 9: Aggregate Generating Facility at

Transmission <= 10MW

• Screen 10: No Construction of Facility Required

Comparison with gross nameplate

rating with maximum aggregate

generating facilities at

transmission.

Page 33: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

33 © 2012 Eaton Corporation. All rights reserved.

GIP FERC

Report

• Automated

• WORD Format

• Customizable

• 10-12 page report

• Introduction

• Project Information

• Initial Review Process

• Summary

• Required Information to

conduct a supp. Review

• Next Steps

Page 34: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

34 © 2012 Eaton Corporation. All rights reserved.

Conclusion

CYME DG Screening Tool

• New software desktop application

• Facilitate generator interconnection review

• Connected to CYME DB through CYME Server

• Customize enterprise DB connection

Page 35: 2014 PV Distribution System Modeling Workshop: DG Screening Tool: Jean-Sebastien Lacroix, CYME

35 © 2012 Eaton Corporation. All rights reserved.

Q&A / Discussion