Los Angeles CountyMetropolitan Transportation Authority
2013 Call for ProjectsGrant Recipient Workshop
November 14, 2013
Agenda: 9:00 am – 12:30 pm
• Welcome Martha Welborne• Housekeeping/Overview of the Day Renee Berlin• Communication Materials Guidelines Noelia Rodriguez• Small Business Enterprise Program Tashai Smith• Active Transportation Program David Yale/Toye Oyewole• Funding Agreement & Letter of Agreement Toye Oyewole/Mona Jones
- Lapsing Policy• Transportation Improvement Program (TIP) Herman Cheng/Nancy Marroquin• Quarterly Report/Invoice Requirements Fanny Pan• General Scope Requirements Fanny Pan• Guidelines to Develop Project Scope Modal Leads
– Regional Surface Transportation Improvements Walter Davis– Goods Movement Philbert Wong– Signal Synchronization Improvements Reinland Jones– Transportation Demand Management Rufina Juarez– Bicycle Improvements Avital Shavit/Anthony Jusay– Pedestrian Improvements Silva Mardrussian/Tham Nguyen– Transit Capital Michael Richmai– TEA Desire Portillo-Rabinov
• Metro Audit Requirements Kathy Knox• Process for Federally Funded Projects Caltrans Staff• Questions All 2
Welcoming Remarks
Martha Welborne, FAIA
Chief Planning Officer
Countywide Planning
3
First Things First
• Evacuation of Building: exit the Board room leftthrough door immediately on the left are another setof exit doors leading down to the street
• Administrative and personal comfort issues
• Cafeteria
• Workshop overview
• Introduction/transition of modal leads
4
Modal Leads
Mode Staff Phone Number
Regional Surface TransportationImprovements (RSTI)
Walt Davis 213-922-3079
Goods Movement Philbert Wong 213-922-2642
Signal Synchronization and BusSpeed Improvements
Reinland Jones 213-922-2231
Transportation Demand Management(TDM) Rufina Juarez 213-922-7405
Bicycle Improvements Avital Shavit 213-922-7518
Pedestrian Improvements Silva Mardrussian 213-922-4425
Transit Capital Michael Richmai 213-922-2558
Transportation Enhancements (TEA) Desiree Portillo-Rabinov 213-922-3039
5
Communication Materials Guidelines
• Updated Guidelines on: www.metro.net/projects/call_projects/
• Provides Project Sponsors/Grantee with guidance onacknowledging Metro funding
• Requirements to ensure reimbursements:– Press Releases and Press Event Advisories must be approved by Metro
Public Relations two days before distribution to media
– Must Notify Metro Project Managers minimum of 30 days prior to thepress events to allow Metro participation
– Must include Metro Logo on all Communication Materials
– Must display Signage for project structures, facilities and constructionsites with the following phrase:
• “Another project made possible by Metro [Metro logo] (Provided by Metro)
6
Communication Materials Contact Info
• General Communications Materials and Metro Logo– Warren Morse, 213-922-5661, [email protected]
– Omark Holmes, 213-922-5246, [email protected]
• Construction Site Signage– Jeff Ringsrud, 213-922-5629, [email protected]
• Press Release, Press Events and others• Marc Littman, 213-922-4609, [email protected]
• Dave Sotero, 213-922-3007, [email protected]
7
Metro’s Transportation Business Advisory Council
Small Business Enterprise Program Questionnaire
8
Active Transportation Program
9
Metro Call for Projects Fund Estimate
10
FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19
LOCAL PROPOSITION C:
Transit Related Streets/Highway Imprv. ( Prop C 25%) -$ 5,000$ 6,000$ 12,000$ 20,000$ 43,000$
Commuter Rail, Park and Ride (Prop C 10%) 0 0 2,000 8,000 4,600 14,600$
State Repayment of Capital Projects Loan (LTF) 0 5,000 3,500 5,000 10,500 24,000$
STATE:
2014 State Transportation Improvement Program (STIP)
Transportation Alternatives (TA)** 0 0 0 14,200 14,400 28,600$
MAP-21 and Beyond :
Congestion Mitigation Air Quality Prog. (CMAQ) 0 0 0 15,300 0 15,300$
Regional Surface Transportation Program (RSTP) 0 0 0 4,500 20,000 24,500$
2012 De-Obligation
Deobligated Funds 15,000 20,000 14,300 0 0 49,300$
Total 15,000$ 30,000$ 25,800$ 59,000$ 69,500$ 199,300$
Transportation Enhancement and Alternatives 44,273$ 9,696$ 7,146$ 14,200$ 14,400$ 89,715$
* Individual FY total amounts are estimated and are subject to revisions without changing overall programming totals as approved
PRELIMINARY FUND ESTIMATE($ thousands)
** Federal, State and regional MAP-21 related legislation and policies may require the transfer of these funds to Caltrans and SCAG. There are no
uncommitted alternative funding sources should this occur.
Fiscal Years *TOTAL
Active Transportation Program
• The new State Active Transportation Program(ATP) consolidates:
– Transportation Alternatives Program (TAP)
– Transportation Enhancement Activities (TEA)
– Bicycle Transportation Account (BTA)
– State Safe Routes to School (SR2S)
– Recreational Trails
– Environmental Enhancement and MitigationProgram (EEMP)
11
Active Transportation Program Flow Chart
12
TAP/Rec. Trails
(Fed)TAP (TE)
(Fed)
HSIP orOther(Fed)
SR2S(State)
BTA(State)
EEMP(State)
ATP Program$129 M
40%(SCAG Administered)
Greater than 200K Regions$51.60 M
10%(CTC Administered)
Less than 200K Regions$12.90 M
50%(CTC Administered)
Statewide Competition$65 M
Regions State
• TAP• Rec. Trails• Other Federal• SHA• SR2S
• TAP• STP• SHA
• TAP• STP• SHA
25% of each share will be allocated to Disadvantaged Communities1
1
Preliminary Draft
ATP Funding Distribution
Three different competitive processes:
• 50% - California Transportation Commission (CTC)awards to projects statewide
• 40% - Metropolitan Planning Organizations (SCAG)award in urban areas with pop. greater than 200,000
• 10% - CTC awards to projects in areas with pop. of200,000 or less
13
Metro Board Action
“Conditionally approve the 2013 Call subjectto later review by the Metro Board ofDirectors once the impacts of State and theSouthern California Association ofGovernments (SCAG) project selectionprocesses are finalized for the ActiveTransportation Program”
14
ATP Programming Process
• Metro no longer programs TA or other ATP funds
– Local agencies must re-apply to SCAG/CTC for ATP funds
• Metro-programmed funds are insufficient to allowprogramming up to the original fund estimate level
– We estimate the shortfall to be approximately $90 million(including prior Calls)
• ATP is a critical resource to bridge the gap
– We want to help to develop successful applications
15
ATP Grant-writing Assistance
• Metro-selected consultant will be available todraft the new ATP application
• Agencies need to affirm they want assistance
• Project sponsors would need only review,approve, and submit application
16
Which Projects Are Eligible For Our Help
• Projects which are ready to construct by 2016and fall into any of these three categories:
1) Funded in 2011 or prior Call, & no MOU/LOA;
2) Funded with TEA in current STIP & have anunallocated balance; or
3) Funded in 2013 Call (Construction funds in FY 2016or Prior)
• Possible 2nd round of assistance for projectsprogrammed/ready FY 2017 - 2019
17
Summary
FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 TOTAL
Mode 2 - Regional Surface Transportation Improvements
Prop C 25% 742 5,402 4,791 6,834 11,130 28,899
CMAQ 4,158 2,684 973 - - 7,815
RSTP 100 414 2,985 2,166 770
Mode 2 - Goods Movements
Prop C 25% - 69 619 3,412 6,036 10,136
RSTP - 1,286 1,882 9,339 7,464 19,971
Mode 3 - Transit Capital
CMAQ 2,963 3,525 4,259 2,708 6,998 20,453
LTF 962 742 1,239 2,792 2,518 8,253
Prop C 10% 577 2,232 - - - 2,809
Mode 4 - Transportation Enhancement ActivitiesActive Transportation Program (1) 979 1,443 - 338 1,275 4,035
LTF - - 499 662 41 1,202
Mode 6 - Signal Synchronization & Bus Speed Improvements
Prop C 25% 323 2,700 1,500 14,151 15,499 34,173
Mode 7 - Bikeway ImprovementsActive Transportation Program (1) - 2,856 994 9,599 10,198 23,647
LTF - 311 972 1,016 851 3,150
Mode 7 - Pedestrian ImprovementsActive Transportation Program (1) - 4,326 5,904 3,565 7,625 21,420
LTF - 98 60 1,176 - 1,334
Mode 8 - Transportation Demand Management
LTF - 1,000 1,026 1,757 1,879 5,662
TOTAL 10,804 29,088 27,703 59,515 72,284 199,394
(1) Approximately $50 million worth of Active Transportation Program (ATP) eligible projects are included. Of this total, approximately $20 million
can be funded with alternate federal funds once the State & SCAG ATP results are known.
2013 COUNTYWIDE CALL FOR PROJECTS
SUMMARY OF FUND ASSIGNED BY MODE
18
Federal and State Requirements
• Don’t award a contract or start work without ------------------ AUTHORIZATION :– Caltrans (Federal or State funds) and/or– Metro (Local funds)
• All Sponsors/Grantee for Federal and State funds must meet ALL regulations required byCaltrans.– Caltrans and Metro Staff will summarize these requirements today
• Only Federal funds are available for:– Bicycle Improvements– Pedestrian Improvements and– Transportation Demand Management (TDM)
• If your project is truly “ready-to-go” , but your funds are programmed in an out year(not the current year):
– Contact Metro Project Manager to see what might be done to accelerate funding– “Truly ready-to-go” means Environmental Documents, and Plans, Specifications, and Estimates
are completed and approved.
19
Project Sponsor/ Grantee/Agency :
Executed Agreement between the Metro
&
Seek Allocation, Obligation or Expenditure
reimbursement as the first step.
20
• Funding Agreement (FA) is required for Local funding– Proposition C 10% (PC 10%), Proposition C 25%
(PC 25%) and Local Transportation Funds (LTF).
• Letter of Agreement (LOA) is required forFederal funding.– Congestion Mitigation and Air Quality Program
(CMAQ).– Regional Surface Transportation Program funds
(RSTP) .
21
FA/LOA Overview Agreements with FY 2013-14 funding MUST BE EXECUTED by:
December 31, 2013
Agreements will not be reviewed until the first program year of funding.
FA/LOA are developed by Project Manager & Project Sponsor/Grantee.
Metro Project Manager compiles and coordinates the review andexecution of agreement.
Project Sponsor/Grantee develops Attachment B (Scope of Works) &Attachment D (FTIP).
Project Sponsor/Grantee returns the signed agreements:
(3) THREE copies to Project Manager for Metro execution
Project Manager returns:
(1) ONE copy of fully executed agreement to ProjectSponsor/Grantee.
22
Agreement Details for Project Sponsors -
Terms & Conditions / Lapsing Policy
Communication Guidelines
Attachments Preparation(Funding, Lapsing & Local Match by Agency)
Attachment B - Scope of Work (Project Description, Schedule &Milestones related to Lapsing and Program funding consistent withMetro Board approval)
Attachment D - Federal Transportation Improvement Program (FTIP)Sheet Attachment
Attachment E - Special Grant Conditions placed on the project, seeSeptember Board Report Special Conditions
23
FA/LOA DETAILS
Terms & Conditions
• Metro Terms and Conditions are not negotiable
• Use only the assigned FA/LOA Agreement Numbers
• Do Not - Change wording of the Boilerplates
• Do Not - Change Font or Font Size
• Use the most current posted BOILERPLATE on Call for Projects Web site.http://www.metro.net/projects/call_projects/
[However always check with your Project Manager to ensure you have themost current documents.]
• Insert only in “Fill-In” fields of Agreements & Attachments as applicable
• Execution of FA/LOA must be by a person duly authorized to sign for theorganization (City Manager, General Manager, Executive Director, etc.)
24
Lapsing PolicyLapsing Policy
90 days of receiving formal transmittal from Metro or12/31/XX of the first fiscal year in which funds programmed Projects Programmed for FY2013-14 FA/LOA’s must be executed
no later than December 31, 2013.
Must meet Project milestone due dates as agreed upon byMetro and Grantee/Sponsors in Attachment B - Scope ofWork.
Must submit Quarterly Progress/Expenditure Report.
Must expend, allocate or obligate funds within 36 monthsfrom July 1 of the fiscal year funds are programmed Example: Funds Programmed in FY2013-14 Lapse June 30, 2016
Note: Projects are subject to lapse each Program Year Funded!
25
ATTACHMENT D - Federal Transportation Improvement Program (FTIP)Go to ProgramMetro - Website to obtain your TIP form that is the use as Attachment D of the Agreement;
http://www.metro.net/projects_studies/tip/program_metro.htm
Sample Attachment D
--Note more details will be presented later on about ProgramMetro that generated this attachment.
26
Lapsing PolicyFederal Funded Projects
LOA (FEDERAL FUNDS) LAPSING POLICY:• Project Sponsor must demonstrate timely use of the Funds by:
executing an LOA within ninety (90) days must be executed byDecember 31st of the first fiscal year of funding & meet the Projectmilestones due dates as agreed upon by Metro and the ProjectSponsor in the Scope of Work
• Project Preliminary Engineering must begin within six (6) monthsfrom the identified milestone start date. Funds programmed by Metrofor Project preliminary engineering or right-of-way costs must beexpended by the end of the second fiscal year following the fiscalyear the Funds were first programmed
Congestion Mitigation and Air Quality Program (CMAQ)
Regional Surface Transportation Program funds (RSTP)
27
Lapsing PolicyFederal Funded Projects Cont.
LOA (FEDERAL FUNDS) LAPSING POLICY:• Contracts for construction or capital purchase shall be executed
within nine (9) months from the date of completion of design.• Expending the Funds programmed within 36 months from July
1st of the first Fiscal Year in which the Funds are programmed.• Project Sponsor must demonstrate evidence of timely use or
obligation of Funds. Evidence of timely obligation will be eitheran executed “Authorization To Proceed” document (CaltransVersion E-76).
Caltrans staff will discuss the process later in the workshop.
28
FA/LOA REFERENCE DOCUMENTS
Use 2013 Call for Projects –Overview:http://www.metro.net/projects/call_projects/
REFERENCE LISTS – EXTERNAL USE:
29
How to Include 2013 CFP Fundsin the 2015 TIP
30
Herman Cheng (213) 922-2453 [email protected]
Nancy Marroquin (213) 922-7237 [email protected]
Jeeseong Chung (213) 922-2478 [email protected]
Natalya Garber (213) 922-2550 [email protected]
Derek Hung (213) 922-2451 [email protected]
Justine Pascual (213) 922-2445 [email protected]
Programming & Policy Analysis Staff
31
• A federally mandated six-year programming document(adopted biennially)
• A list of transportation projects that are programmed withfederal funds and/or are considered regionally significant
• All 2013 Call for Projects (CFP) projects must be listed inthe 2015 Transportation Improvement Program (TIP).
32
The TIP
The 2015 TIP & 2013 CFP
• The 2013 CFP funds are assigned in FY 2014-15 through FY 2018-19.
• The first four years of the TIP are fiscally constrained – any federalfunds assigned for between FY 2014-15 and FY 2017-18 may beobligated as early as FY 14-15.
33
CFP-Assigned Funds in ProgramMetro
• Agencies can review projects and submit them to the TIPusing the ProgramMetro online database athttp://program.metro.net
• Metro will import the basic data for the 2013 CFP intoProgramMetro on December 2, 2013.
• Projects that have been assigned CFP funds will be listedunder “REVIEW PROJECTS IN PROGRESS” onProgramMetro’s main menu.
• Agencies must review and update projects and submitthem to Metro through ProgramMetro by December 13,2013.
34
Existing projects receiving CFP funding
• 2013 CFP funding may go towards new projects or existing projects.
• If applicable, you may need to add the newly assigned 2013 CFPfunds to an existing project entry in ProgramMetro.
• Please contact Metro Programming and Policy Analysis staff so wecan assist you with this process.
35
CFP-Assigned Funds in ProgramMetro
• To find your 2013 CFP projects, click “REVIEW PROJECTSIN PROGRESS” on the main menu of ProgramMetro.
36
• Review your agency’s projects.
• Assign CFP funding to the proper phase – they will be placed inconstruction (CON) by default.
– Do not change the total assigned funding amount!
– Do not change the years that funds are assigned for!
• Select the appropriate local match fund types – all local match funds willbe listed as the CITY-CITY FUND type by default.
• Add any additional assigned federal, state, or local funds.
• Complete the project information section (i.e. completion date, projectstatus, and backup/supporting documents).
• By December 13, 2013, click “Submit to Metro” on ProgramMetro afterthe project entry has been reviewed for accuracy.
37
Required TIP Steps
• We have tentatively reserved the following dates for TIPworkshops
– December 3, 2013
– December 4, 2013
• More information will be emailed to interested partiescloser to the date
38
TIP Workshops
FA Quarterly Report/Invoice Requirements
Project Sponsors are required to report quarterly on all project activitiesand expenses- Must report even if there has been no activity
The Quarterly Report is due no later than 60 days after the Quarter endsDue Dates: November 30, February 28,May 31, and August 31
Reimbursement will not be made unless properly completedQuarterly Report/Invoice is received
Must include Quarterly Report as part of invoice Audit findings
Retainage needs to be shown, Metro withholds retainage on each invoice
39
FA Quarterly Report/Invoice Requirements
Project Sponsors must closely track project schedules andreport on project delay Projects not delivered in a timely manner may have funds deobligated Please do not provide the same comments in the report every quarter
FA Project expenses must be supported by appropriatedocumentation Costs incurred prior to FA/LOA execution are not eligible for
reimbursement Contractor invoices, receipts and timesheets Each invoice or receipt must be accompanied with a clear explanation
of its purpose and relevance to the project Must have spent local match share in proportion to Metro funds
40
LOA Quarterly Progress Report Requirements
The Quarterly Report is due no later than 60 days after thequarter ends
Due Dates: November 30, February 28, May 31, andAugust 31
Annually with the 4th quarter Progress report, submitphotos of key components and milestones demonstratingproject progress or completion
41
General Scope Requirements
Where is the project located?- Project limits
What does the project entail?- Project Elements- Use approved Project Description from the September Board report asa starting point
How will the project funds be spent to complete the project?- Project Budget - Needs to be as quantitative as possible:
1) Total cost with detailed breakdown2) Ensure correct project cost and local commitment(See September Board report Item #13)
42
General Scope Requirements
When will the project be implemented?
- Start and end dates for each component/phase of the
project scheduled
- Milestones and completion date must be consistentwith Metro’s adopted Lapsing policy
Maps/Pictures
43
Regional Surface Transportation Improvements
Project Description Clear, concise, specific - what is to be constructed and why Location, limits, length - if available include maps and photos Detailed cost breakdown of project components Consistent with the Board approved project description
Project Schedule and Milestones Begin/end dates for each component Be realistic and reasonable
Consistent with Metro lapsing policy Years funds are awarded
Think it through; does it make sense?
44
Goods Movement
Project DescriptionClear, concise, complete, specificLocation (limits, length); include mapComponents of project (detailed)Consistent with the originally submitted project applicationand Metro Board approved project description
Project Schedule and Milestones ( e.g. design begin/end, ROWacquisition, contract advertise, Notice to Proceed, constructionbegin/end)
Consistent with Metro lapsing policy
45
Signal Synchronization & Bus Speed Improvements
Detailed Project Description: specific project location including streetnames, limits, quantities - number of intersections, improvements at eachintersection including equipment to be purchased, etc.
All proposed uses of funds must be included on a line item basis & aschedule for each milestone
All fund recipients must participate in Metro’s Arterial ITS ConfigurationManagement Committee
Special Grant Conditions attachment- Upon completion, sponsor to demonstrate congestion
reduction/travel time benefits
LA County ITS Architecture Consistency Self Certification Form
46
Transportation Demand Management (TDM)
1. Complete a detailed Project Scope
A. Tell us how program funds will be expended
o What are we buying?
B. Tell us when you are completing phases of the project
o Clear project milestones
C. Tell us how you will be marketing your project.
2. Include a map clearly illustrating the location of your project, includingdigital pictures of the location and/or equipment before and afterinstallation.
47
Bicycle Improvements
Scope of Work; Project description-use only description fromapproved Board Report (not application for funds); SOW, detailedcosts (unit and total), project schedule Compliance with CAHDM and Manual of Uniform Traffic Control
Devices (MUTCD) CA Supplement Special Condition: required as part of the Board report,
Attachment DProject Completion Report includesBefore/after countsLessons/Learned and Evaluation report
Innovative non-standard designs need concurrence fromCTCDC/Federal Highway Administration (FHWA)Coordinate with Metro Planning, Operations and other
municipal bus operators as applicable
48
Bicycle Improvements continued:
Before/after counts must be conducted andreported to the SCAG/Metro Bike CountData Clearinghouse(http://www.bikecounts.luskin.ucla.edu/)
• Manual
• Automated
49
Innovative non-standard
design need to submit for aRequest to Experiment (RTE) toCTCDC/FHWA
49
Pedestrian Improvements
Project description– Location (project location, limits, length), text and map
– Purpose
– Project components & cost breakdown
– Conceptual plan & color photos of existing conditions (if applicable)
Project schedule (include clear milestones)
Attend at least one Metro active transportation workshop
Before/after pedestrian and bicycle counts
50
New York DOT NACTONACTO
50
Transit Capital
51
• Scope must be CONSISTENT with description approved by the Board
• Number of Buses being purchased (Base price only, fuel type, service routes)
• Bus Stop Improvements (location and elements at each stop)
• Transit Center (project site, design and construction elements)
• Maintenance Facility (fueling station, service bays, bus parking spaces)
• Project Schedule and Milestones:
• Must coincide with years of awarded funds
• Be Realistic and Detailed
• Detailed Budget:
• Buses: Cost per vehicle, fuel type, vehicle size
• Bus Stop Improvements: Shelters, benches, lighting, trash cans, etc.
• Transit Center/Maintenance Facility: Design, engineering, construction
Costs incurred prior to FA/LOA execution are not eligible for reimbursement!
Transportation Enhancement
Complete project description that includes design, elementsand construction activities as approved by the Board
Describe applicable performance monitoring and datacollection efforts post project development as prescribedunder MAP-21 guidance
Detailed cost breakdown
Schedule by tasks and milestones
Maps and photos with descriptions/captions (both locationand project)
52
Audit Overview
Audit Objective:
• To ensure Call for Projects dollars are properly spent
• To ensure project costs are allowable, reasonable and allocable
Purpose of the Audit:
• Funds are properly allocated
• Compliance with grant agreement terms and conditions
• Project cost incurred within lapsing period
• Verify adequate detail documentation exist
Local $Metro $
53
Audit Overview
Sponsor’s Accounting System– Track and report cost by project
– Distinguish between direct and indirect cost
Type of Engagement– Agreed-Upon Procedures
54
Allowability of Cost
• Grant Terms and Conditions
• Federal Acquisition Regulation Part 31
• 2 CFR Subtitle A, Chapter II, Part 225 (OMB A87)
• Use of funds in the most cost-effective manner- Consultant/contractor services must be procured in
accordance with Grantee’s contracting procedures andconsistent with State law
- Grantee staff or consultant with project oversight roles can notaward work to companies in which they have a financial orpersonal interest
- Purchase/Lease of equipment requires Metro’s writtenconsent prior to cost
55
Close-out Audit Requirements
• Total Project Cost
• All invoiced cost
• Total payment received
• Total retention withheld by Metro
• Interim cost reviewed
• Audited actual rates for indirect cost and fringe benefit
56
Required Audit Documentation
Quarterly Reports/Invoices
Summary of Project Billings by Cost Element
Direct Labor: support for hours and payroll rates audited fringe rates if part of billed cost
Indirect Rates:– Detail Calculations per fiscal year– Audited Rates
Other Direct Cost Support :– invoices and cancelled checks– purchase order
57
Required Audit Documentation (cont.)
Contractor/ Subcontractor Cost:– Invoices– Payment Vouchers, Cancelled Checks or Bank Statements– Agreement and Change Orders or Amendment
Equipment:– Lease Agreements– Metro’s approval prior to equipment purchase if applicable to
Memorandum of Understanding (MOU) or Funding Agreement (FA)– Support for equipment usage rate and hours
58
Required Audit Documentation (cont.)
Contract Award Verification:– Procurement Policy– Request for Proposal (RFP)– RFP Advertising– Bidders’ Proposals– Bid Evaluation Supporting Documents– Contract Award Notice or Approval by City Council– Executed Contract and Amendments
59
What to Expect During the Audit Process
Audit Notification Letter with Initial Data Request
Entrance Conference
Additional Data Requests
Fieldwork
Exit Conference
Draft Report and Final Report
60
Frequent Audit Issues
Incurred cost after MOU or FA lapsing period
Late Invoices not within invoicing terms of the MOU or FA
Indirect rates applied to wrong period
Funds used for non project expenses
Consultant Conflict of Interest
61
Process for Federally Funded Projects
Mr. David WangCaltrans District 7
Office of Local Assistance
– Handouts
62
2013 Call For Projects
For AdditionalQuestions, Please
Contact YourModal Leads
THANK YOU