2013-5thedition Changes SOE 20130313 Final

50
Mar 2013 Based on PMBOK 5th Edition Unauthorized Distribution not allowed 1 1 PMBOK 5th Edition Changes Presentation PMBOK 5 th Edition Changes By: Mohamed Arafa, M.Sc. PMP, RMP, MVP For more information , please visit: www.officena.net/pmp [email protected] 2 PMBOK 5th Edition Changes Presentation Contents Preface Q&A Integration Management 4 Scope Management 5 Time Management 6 Cost Management 7 Quality Management 8 Communication Management 10 HR Management 9 Risk Management 11 Procurement Management 12 Introduction 1 Org. Influence And Project Life Cycle 2 Project Mgmt Processes for a Project 3 Stakeholders Management 13

Transcript of 2013-5thedition Changes SOE 20130313 Final

Page 1: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 1

1 PMBOK 5th Edition Changes Presentation

PMBOK 5th Edition Changes

By: Mohamed Arafa, M.Sc. PMP, RMP, MVP

For more information , please visit: www.officena.net/pmp

[email protected]

2 PMBOK 5th Edition Changes Presentation

Contents

Preface

Q&A

Integration

Management

4

Scope

Management

5

Time

Management

6

Cost

Management

7

Quality

Management

8

Communication

Management

10

HR

Management

9

Risk

Management

11

Procurement

Management

12

Introduction

1 Org. Influence

And

Project Life

Cycle

2

Project Mgmt

Processes for

a Project

3

Stakeholders

Management

13

Page 2: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 2

Preface

What is PMI ?

o PMI is the world’s leading not-for-profit

membership association for the project

management profession, with more than half a

million members and credential holders in 185

countries.

3 PMBOK 5th Edition Changes Presentation

PMI Credentials

PMP

CAPM

PMI-SP

PMI-RMP

PGMP

ACP

PMI

Up to 31 Dec 2012

PMBOK 5th Edition Changes Presentation

510,434

834

20,157

1805

809

2,063

Page 3: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 3

PMI Today

5 PMBOK 5th Edition Changes Presentation

PMBOK® 4th Edition 42 PM Processes

6 PMBOK 5th Edition Changes Presentation 6

Initiating Planning ExecutingMonitoring &

ControllingClosing

•4.1 Dev. Project

Charter

•4.4 Monitor and Control

Project Work

•4.5 Peform Integrated

Change Control

•5.1 Collect Requirements •5.4 Verify Scope

•5.2 Define Scope •5.5 Control Scope

•5.3 Create WBS

•6.1 Define Activities

•6.2 Sequence Activities

•6.3 Estimate Activity Resources

•6.4 Estimate Activity Durations

•6.5 Develop Schedule

•7.1 Estimate Costs

•7.2 Determine Budget

08 Quality•8.1 Plan Quality •8.2 Perform Quality

Assurance

•8.3 Perform Quality

Control

•9.2 Acquire Project Team

•9.3 Develop Project Team

•9.4 Manage Project Team

•10.3 Distribute Information

•10.4 Manage Stakeholder

Expectations

•11.1 Plan Risk Management

•11.2 Identify Risks

•11.3 Perform Qualitative Risk Analysis

•11.4 Perform Quantitative Risk Analysis

•11.5 Plan Risk Responses

12 Procurement•12.1 Plan Procurements •12.2 Conduct Procurements •12.3 Administer

Procurements

•12.4 Close

Procurments

10

Communication

•10.1 Idetify

Stakeholders

•10.2 Plan Communications •10.5 Report

Performance

11 Risk

•11.6 Monitor and Control

Risks

07 Cost•7.3 Control Costs

09 Human

Resource

Management

•9.1 Develop Human Resource Plan

05 Scope

06 Time

•6.6 Control Schedule

Knowledge

Areas

Project Management Process Groups (PMBOK® 4th Edition)

04 Integration

•4.2 Develop Project Management Plan •4.3 Direct and Manage

Project Execution

•4.6 Close Project

or Phase

Page 4: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 4

Main Changes

7 PMBOK 5th Edition Changes Presentation

PMBOK 4th Edition

PMBOK 5th Edition

Process Groups

5 5

Knowledge Areas

9 10

Processes 42 47

Pages 345 pages + Appendices

461 pages + Appendices

467 589

8 PMBOK 5th Edition Changes Presentation

PMBOK® Processes 5th edition 47 Processes

Initiating Planning ExecutingMonitoring &

ControllingClosing

4.1 Dev. Project

Charter

4.4 Monitor and Control

Project Work

4.5 Peform Integrated

Change Control

5.1 Plan Scope Management 5.5 Validate Scope

5.2 Collect Requirements 5.6 Control Scope

5.3 Define Scope

5.4 Create WBS

6.1 Plan Schedule Management

6.2 Define Activities

6.3 Sequence Activities

6.4 Estimate Activity Resources

6.5 Estimate Activity Durations

6.6 Develop Schedule

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

08 Proejct Quality

Management

8.1 Plan Quality Management 8.2 Perform Quality

Assurance

8.3 Control Quality

9.1 Plan Human Resource Management 9.2 Acquire Project Team

9.3 Develop Project Team

9.4 Manage Project Team

10 Proejct

Communication

Management

10.1 Plan Communications

Management

10.2 Manage

Communications

10.3 Control

Communications

11.1 Plan Risk Management

11.2 Identify Risks

11.3 Perform Qualitative Risk Analysis

11.4 Perform Quantitative Risk Analysis

11.5 Plan Risk Responses

12.1 Plan Procurement Management 12.2 Conduct

Procurements

12.3 Control

Procurements

12.4 Close

Procurments

13 Proejct

Stakeholders

Management

13.1 Idetify

Stakeholders

13.2 Plan Stakeholders Management 13.3 Manage Stakeholders

Engagement

13.4 Control

Stakeholders

Engagement

11 Proejct Risk

Management

11.6 Monitor and

Control Risks

12 Proejct

Procurement

Management

09 Proejct Human

Resource

Management

07 Proejct Cost

Management

7.4 Control Costs

05 Proejct Scope

Management

06 Proejct Time

Management

6.7 Control Schedule

Knowledge

Areas

Project Management Process Groups (PMBOK® 5th Edition)

04 Proejct

Integration

Management

4.2 Develop Project Management Plan 4.3 Direct and Manage

Project Execution

4.6 Close Project

or Phase

Page 5: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 5

Main Changes

9 PMBOK 5th Edition Changes Presentation

Additions

5.1 Plan Scope Management—added

6.1 Plan Schedule Management—added

7.1 Plan Cost Management—added

13.2 Plan Stakeholder Management—added

13.4 Control Stakeholders Engagement—added

Main Changes

10 PMBOK 5th Edition Changes Presentation

Control X

8.3 Perform Quality Control—changed to Control Quality

10.5 Report Performance—changed to Section 10.3 Control Communications

11.6 Monitor and Control Risks—changed to Control Risks

12.3 Administer Procurements—changed to Control Procurements

Plan xxxx Management

8.1 Plan Quality—changed to Plan Quality Management

9.1 Develop Human Resource Plan—changed to Plan Human Resource

Management

10.2 Plan Communications—changed to Section 10.1 Plan Communications

Management

12.1 Plan Procurements—changed to Plan Procurement Management

Page 6: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 6

Main Changes

11 PMBOK 5th Edition Changes Presentation

Misc Changes

4.3 Direct and Manage Project Execution—changed to Direct and

Manage Project Work

5.5 Verify Scope—changed to Validate Scope

10.4 Manage Stakeholder Expectations—changed to Section 13.3

Manage Stakeholders Engagement

10.3 Distribute Information—changed to Section 10.2 Manage

Communications

10.1 Identify Stakeholders—moved to Section 13.1 Identify

Stakeholders

DIKW (Data, Information, Knowledge, Wisdom) model used in the field of Knowledge Management.

oWork Performance Data

oWork Performance Information

oWork Performance Reports

12 PMBOK 5th Edition Changes Presentation

Page 7: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 7

Information flow in 4th edition

13 PMBOK 5th Edition Changes Presentation

Direct and Manage Project Work

Monitoring and controlling processes

Report Performance

Work Performance measurements

Performance Reports

Work Performance Information

DIKW Model PMBOK 5th Edition

14 PMBOK 5th Edition Changes Presentation

Direct and Manage Project Work

Control Scope , Schedule , Costs , Quality , Communications, Procurements, Risks , Stakeholders Engagement , and Validate Scope

Work Performance Data

Monitor and Control Project Work

Work Performance Information

Work Performance Reports

Page 8: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 8

Project Management Office (PMO)

PMBOK 5th Edition Changes Presentation 15

PMBOK 4th Edition PMBOK 5th Edition

An organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain.

A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.

PMO Types

1.4.4 Project Management Office

16 PMBOK 5th Edition Changes Presentation

Take Control

Directly Manage

Support

Compliance

Consulted

Repository

Supportive Controlling Directive

Degree of Control

Page 9: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 9

1.8 Enterprise Environmental Factors

PMBOK 5th Edition Changes Presentation 17

Conditions, not under the control of the project team, that influence, constrain, or direct the project

Both internal and external environmental factors that surround or influence a project’s success

2.3 Stakeholders

PMBOK 5th Edition Changes Presentation 18

A stakeholder is an individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project.

Stakeholders are persons or organizations who are actively involved in the project or whose interests may be positively or negatively affected by the performance or completion of the project

Page 10: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 10

Sponsor

PMBOK 5th Edition Changes Presentation 19

Sponsor:

A sponsor is the person or group who provides resources and support for the project and is accountable for enabling success.

The sponsor may be external or internal to the project manager’s organization.

Sponsor:

A sponsor is the person or group that provides the financial resources, in cash or in kind, for the project.

Program Management

PMP Preparation Course 20

A program is defined as a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.

program is defined as a group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits not available from managing them individually.

Page 11: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 11

Project Governance

PMBOK 5th Edition Changes Presentation 21

Project governance is an oversight function that is aligned with the organization’s governance model and that encompasses the project lifecycle.

Project Success

PMBOK 5th Edition Changes Presentation 22

The success of the project should be measured in terms of completing the project within the constraints of scope, time, cost, quality, resources, and risk as approved between the project managers and senior management.

To ensure realization of benefits for the undertaken project, a test period (such as soft launch in services) can be part of the total project time before handing it over to the permanent operations.

Project success should be referred to the last baselines approved by the authorized stakeholders.

Page 12: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 12

Project Life Cycle Approaches

Predictive or plan Driven

Iterative and

Incremental Life Cycle

Adaptive or Change Driven (Agile)

23 PMBOK 5th Edition Changes Presentation

Chapter 03: Project Management Processes for a Project

Initiating Process Group

Planning Process Group

Executing Process Group

Monitoring and Controlling Process Group

Closing Process Group

24 PMBOK 5th Edition Changes Presentation

Page 13: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 13

Chapter 04: Project integration Management

25 PMBOK 5th Edition Changes Presentation

Bringing the pieces Together

Chapter 04: Project integration Management

26 PMBOK 5th Edition Changes Presentation

Project Integration Management includes the processes and activities needed to:

identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.

Page 14: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 14

4th Edition 5th Edition

4.1 Develop Project Charter

4.1 Develop Project Charter

4.2 Develop Project management Plan

4.2 Develop Project management Plan

4.3 Direct and manage Project execution

4.3 Direct and manage Project Work

4.4 monitor and Control Project work

4.4 monitor and Control Project work

4.5 Perform Integrated Change Control

4.5 Perform Integrated Change Control

4.6 Close Project or Phase

4.6 Close Project or Phase

Project integration Management Processes

27 PMBOK 5th Edition Changes Presentation

4.1 Develop Project Charter ITTO

28 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project statement of

work

.1 Expert judgment .1 Project

charter

.2 Business case 2. Facilitation techniques

.3 Contract Agreements

.4 Enterprise

environmental factors

.5 Organizational process

assets

Page 15: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 15

4.2 Develop Project mgmt Plan ITTO

29 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Project charter .1 Expert

judgment

.1 Project

management plan

.2 Outputs from Other processes 2. Facilitation

Techniques

.3 Enterprise environmental

factors

.4 Organizational process assets

4.3 Direct and manage Project Work ITTO

30 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Expert judgment .1 Deliverables

.2 Approved change

requests

.2 Project

management

information system

.2 Work performance

information Data

.3 Enterprise

environmental factors

3. Meetings .3 Change requests

.4 Organizational

process assets

.4 Project

management plan

updates

.5 Project document

updates

Page 16: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 16

4.4 monitor and Control Project work ITTO

31 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs .1 Project management plan .1 Expert judgment .1 Change requests

.2 Schedule forecasts .2 Analytical

techniques

.2 Work Performance Reports

.3 Cost forecasts .3 Project management

information system

.3 Project management

plan updates

.4 Validated changes .4 Meetings .4 Project document

updates

.5 Performance reports

Work performance information

.6 Enterprise environmental

factors

.7 Organizational process

assets

4.5 Perform Integrated Change Control ITTO

32 PMP Preparation Course

Inputs Tools &

Techniques

Outputs

.1 Project

management plan

.1 Expert judgment .1 Approved Change

request status updates

.2 Work performance

information Reports

.2 Meetings .2 Change Log

.3 Change requests .3 Change control

meetings Tools

.2 Project management

plan updates

.4 Enterprise

environmental

factors

.3 Project document

updates

.5 Organizational

process assets

Page 17: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 17

4.6 Close Project or Phase ITTO

33 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Expert judgment .1 Final product,

service, or result

transition

.2 Accepted

deliverables

.2 Analytical

techniques

.2 Organizational

process assets

updates

.3 Organizational

process assets

3. Meetings

Chapter 5: Project Scope Management

34 PMBOK 5th Edition Changes Presentation

What are we doing?

Page 18: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 18

Chapter 5: Project Scope Management

Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

35 PMBOK 5th Edition Changes Presentation

4th Edition 5th Edition

5.1 Plan Scope Management

5.1 Collect Requirements

5.2 Collect Requirements

5.2 Define Scope

5.3 Define Scope

5.3 Create WBS

5.4 Create WBS

5.4 Verify Scope

5.5 Validate Scope

5.5 Control Scope

5.6 Control Scope

Project Scope Management Processes

36 PMBOK 5th Edition Changes Presentation

Page 19: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 19

5.1 Plan Scope Management ITTO

37 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Expert judgment .1 Scope

management plan

.2 Project charter .2 Meetings .2 Requirements

management plan

.4 Enterprise

environmental factors

.5 Organizational

process assets

5.2 Collect Requirements ITTO

38 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Scope

management plan

.1 Interviews .1 Requirements

documentation

.2 Requirements

management plan

.2 Focus groups .2 Requirements

management plan

.2 Stakeholder

management plan

.3 Facilitated

workshops

.2 Requirements

traceability matrix

.4 Project charter .4 Group creativity

techniques

.5 Stakeholder

register

.5 Group decision

making techniques

Tools & Techniques

6. Questionnaires and

surveys

.9 Benchmarking

7.Observations .10 Context Diagraming

8.Prototypes .11 Document Analysis

Page 20: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 20

5.3 Define Scope ITTO

39 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Scope management

plan

.1 Expert judgment .1 Project scope

statement

.2 Project charter .2 Product analysis .2 Project document

updates

.3 Requirements

documentation

.3 Alternatives

identification

generation

.4 Organizational

process assets

.4 Facilitated

workshops

5.4 Create WBS ITTO

40 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

. 1 Scope management

plan

.1 Decomposition .1 WBS

.1 Project scope

statement

.2 Expert

judgment

.2 WBS dictionary

.2 Requirements

documentation

.1 Scope baseline

.4 Enterprise

environmental factors

.2 Project document

updates

.5 Organizational

process assets

Page 21: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 21

5.5 Validate Scope ITTO

41 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Project management

plan

.1 Inspection .1 Accepted

deliverables

.2 Requirements

documentation

.2 Group decision

making techniques

.2 Change requests

.3 Requirements

traceability matrix

.3 Work performance

Information

.4 Validated Verified

deliverables

.4 Project document

updates

.5 Work performance

data

5.6 Control Scope ITTO

42 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Variance analysis .1 Work performance

measurements

Information

.2 Requirements

documentation

.2 Change requests

.3 Requirements

traceability matrix

.3 Project

management plan

updates

.4 Work performance

information data

.4 Project document

updates

.5 Organizational

process assets

.5 Organizational

process assets updates

Page 22: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 22

Chapter 6: Project Time management

How long will it take?

43 PMBOK 5th Edition Changes Presentation

Chapter 6: Project Time management

Project Time Management includes the processes required to manage timely completion of the project.

44 PMBOK 5th Edition Changes Presentation

Page 23: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 23

4th Edition 5th Edition

6.1 Plan Schedule Management

6.1 Define Activities

6.2 Define Activities

6.2 Sequence Activities

6.3 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Estimate Activity Durations

6.5 Develop Schedule

6.6 Develop Schedule

6.6 Control Schedule

6.7 Control Schedule

Project Time Management Processes

45

6.1 Plan Schedule Management ITTO

46 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Expert judgment .1 Schedule

management plan

.2 Project charter .2 Analytical

techniques

.4 Enterprise

environmental factors

.3 Meetings

.5 Organizational

process assets

Page 24: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 24

6.2 Define Activities ITTO

47 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Schedule management

plan

.1 Decomposition .1 Activity list

.2 Scope baseline .2 Rolling wave

planning

.2 Activity attributes

.3 Enterprise

environmental factors

.3 Templates .3 Milestone list

.4. Organizational

process assets

.3 Expert judgment

6.3 Sequence Activities ITTO

48 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Schedule

management plan

.1 Precedence

diagramming method

(PDM)

.1 Project schedule

network diagrams

.2 Activity list

.2 Dependency

determination

.2 Project document

updates

.3 Activity attributes .3 Applying Leads

and lags

.4 Milestone list

.4 Schedule network

templates

.5 Project scope

statement

.6 EEFs

.7 OBAs

Page 25: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 25

6.4 Estimate Activity Resources ITTO

49 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Schedule

management plan

.1 Expert judgment .1 Activity resource

requirements

.2 Activity list .2 Alternatives

analysis

.2 Resource

breakdown structure

.3 Activity attributes .3 Published

estimating data

.3 Project document

updates

.4 Resource calendars .4 Bottom-up

estimating .5 Risk Register

.6 Activity cost

estimates .5 Project

management software

.9 EEFs

.8 OBAs

6.5 Estimate Activity Durations ITTO

50 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Schedule management plan

.1 Expert judgment .1 Activity duration

estimates

.2 Activity list .2 Analogous

estimating

.2 Project document

updates

.3 Activity attributes .3 Parametric

estimating

.4 Activity resource

requirements

.4 Three-point

estimates

.5 Resource calendars .5 Group decision-

making techniques .6 Project scope statement

.7 Risk Register .6 Reserve analysis

.8 Resource Breakdown

Structure

.9 EEFs

.10 OBAs

Page 26: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 26

6.6 Develop Schedule ITTO

51 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Schedule management

plan

.1 Schedule network analysis .1 Schedule baseline

.2 Activity list .2 Critical path method .2 Project schedule

.3 Activity attributes .3 Critical chain method .3 Schedule data

.4 Project schedule

network diagrams

.4 Resource leveling

Optimization Techniques

.4 Project calendars

.5 Activity resource

requirements

.5 What-if scenario analysis

Modeling Techniques

.5 Project management

plan updates.

.6 Resource calendars .6 Applying Leads and lags

.7 Activity duration

estimates

.7 Schedule compression .6 Project document

updates

.8 Project scope statement .8 Scheduling tool

.9 Risk Register Tools & Techniques

.10 Project Staff

Assignment

.12 EEFs

.11 Resource Breakdown Structure

.13 OBAs

6.7 Control Schedule ITTO

52 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Performance reviews .1 Work performance

measurements

Information

.2 Project schedule .2 Project management

software

.2 Schedule Forecasts

.3 Work performance

information Data

.3 Resource leveling

Optimization Techniques .3 Change requests

.4 Project Calendars .4 What-if scenario

analysis Modeling

Techniques

.4 Project management

plan updates

.5 Schedule Data .5 Applying Leads and lags .5 Project document

updates

.6 OBAs .6 Schedule compression .6 OBAs updates

.7 Scheduling tool

Variance analysis

Page 27: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 27

Chapter 7: Project Cost Management

How much will it cost?

53 PMBOK 5th Edition Changes Presentation

Chapter 7: Project Cost Management

Project Cost Management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget.

54 PMBOK 5th Edition Changes Presentation

Page 28: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 28

4th Edition 5th Edition

7.1 Plan Cost Management

7.1 Estimate Costs

7.2 Estimate Costs

7.2 Determine Budget

7.3 Determine Budget

7.3 Control Costs

7.4 Control Costs

Project Cost Management Processes

55 PMBOK 5th Edition Changes Presentation

7.1 Plan Cost Management ITTO

56 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Expert judgment .1 Cost management

plan

.2 Project charter .2 Analytical

techniques

.

.4 Enterprise

environmental factors

.3 Meetings

.5 Organizational

process assets

Page 29: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 29

7.2 Estimate Costs ITTO

57 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Cost management

plan

.1 Expert judgment .1 Activity cost

estimates

.2 Human resource

Management plan

.2 Analogous estimating .2 Basis of

estimates

.3 Scope baseline .3 Parametric estimating .3 Project

document updates .4 Project schedule .4 Bottom-up estimating

.5 Risk register .5 Three-point estimates

.6 Enterprise

environmental factors

.6 Reserve analysis

.7 OBAs .7 Cost of quality

.8 Project management

estimating software

.9 Vendor bid analysis

.10 Group Decision

Making Techniques

7.3 Determine Budget ITTO

58 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

. .1 Cost management

plan

.1 Cost

aggregation

.1 Cost performance

baseline

.2 Scope baseline .2 Reserve

analysis

.2 Project funding

requirements

.3 Activity cost estimates .3 Expert

judgment

.3 Project document

updates

.4 Basis of estimates .4 Historical

relationships .5 Project schedule

.6 Resource calendars

.7 Risk Register .5 Funding limit

reconciliation .8 Contracts Agreements

.9 OBAs

Page 30: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 30

7.4 Control Costs ITTO

59 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Earned value

management

.1 Work performance

measurements Information

.2 Project funding

requirements

.2 Forecasting .2 Budget Cost forecasts

.3 Work

performance

information Data

.3 To-complete

performance index

(TCPI)

.3 Change requests

.4 Organizational

process assets

.4 Performance reviews . Project management plan

updates

.5 Project management

software

.5 Project document

updates

.6 Variance analysis

Reserve Analysis

.6 Organizational process

assets updates

Chapter 8: Project Quality Management

What are the Specs & How are we going to meet them?

60 PMBOK 5th Edition Changes Presentation

Page 31: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 31

4th Edition 5th Edition

8.1 Plan Quality

8.1 Plan Quality Management

8.2 Perform Quality Assurance

8.2 Perform Quality Assurance

8.3 Perform Quality Control

8.3 Control Quality

Project Quality Management Processes

61 PMBOK 5th Edition Changes Presentation

8.1 Plan Quality ITTO

62 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Scope baseline

Schedule baseline

Cost performance

baseline

Project Management

Plan

.1 Cost-benefit analysis .1 Quality management

plan

.2 Cost of quality .2 Process improvement

plan

.3 Control charts , - Flowcharting

Seven basic quality tools

.3 Quality metrics

.2 Stakeholder

register

.4 Benchmarking .4 Quality checklists

. 3 Risk register .5 Design of experiments .5 Project document

updates . 4 Requirements

Documentation .6 Statistical sampling

. 5 Enterprise

environmental factors .7 Additional quality planning

Tools .6 Organizational

process assets

.8 Proprietary quality management

methodologies Meetings

Page 32: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 32

8.2 Perform Quality Assurance ITTO

63 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project Quality

management plan

.1 Plan Quality and

Perform Quality

Management and

Control tools and

techniques

.1 Change requests

.2 Process

Improvement Plan

.2 Project

management plan

updates

.2 Quality metrics .2 Quality audits

.3 Project document

updates

.3Work performance

information Quality

control measurements

.3 Process analysis

.4 OBAs Updates

.4 Project Documents

8.3 Perform Quality Control ITTO

64 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Cause and effect

Diagrams, Control charts,

Flowcharting, Histogram,

Pareto chart, Run chart,

Scatter diagram

Seven Basic Quality Tools

.1 Quality control

measurements

.2 Quality metrics .2 Validated changes

.3 Quality checklists .3 Validated deliverables

4 Work performance

measurements Data .2 Statistical sampling

.4 Work Performance

information .5 Approved change

requests

.3 Inspection

.5 Change requests

.6 Deliverables

.4 Approved change request

review. .6 Project management plan

updates

.7 Project Documents .7 Project document

updates

.8 Organizational

process assets

Organizational process

assets updates

Page 33: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 33

Chapter 09: Project Human Resource

management

Who will do it?

65 PMBOK 5th Edition Changes Presentation

Chapter 09: Project Human Resource

management Project Human Resource Management

includes the processes that organize, manage, and lead the project team

66 PMBOK 5th Edition Changes Presentation

Page 34: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 34

4th Edition 5th Edition

9.1 Develop Human Resource Plan

9.1 Plan Human Resource Management

9.2 Acquire Project Team

9.2 Acquire Project Team

9.3 Develop Project Team

9.3 Develop Project Team

9.4 Manage Project Team

9.4 Manage Project Team

Project HR Management Processes

67 PMBOK 5th Edition Changes Presentation

9.1 Plan Human Resource Management ITTO

68 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Organization charts

and position

descriptions

.1 Human resource

management plan

.2 Activity resource

requirements

.2 Networking

.3 Enterprise

environmental factors

.3 Organizational

theory

.4 Organizational

process assets

4. Expert Judgment

.5 Meetings

Page 35: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 35

9.2 Acquire Project Team ITTO

69 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Project Human Resource

management plan

.1 Pre-assignment .1 Project staff

assignments

.2 Enterprise environmental

factors

.2 Negotiation .2 Resource

calendars

.3 Organizational process

assets

.3 Acquisition .3 Project

management plan

updates

.4 Virtual teams

.5 Multi-criteria

decision analysis

9.3 Develop Project Team ITTO

70 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

1 Project Human

Resource

management plan

.1 Interpersonal skills .1 Team performance

assessments

.2 Project staff

assignments

.2 Training .2 EEFs Updates

.3 Resource

calendars

.3 Team-building

activities

.4 Ground rules

.5 Co-location

.6 Recognition and

rewards

.7 Personnel assessment

tools

Page 36: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 36

9.4 Manage Project Team ITTO

71 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 1 Project Human

Resource

management plan

.1 Observation and

conversation

.1 Change requests

.2 Project staff

assignments

.2 Project

performance

appraisals

.2 Project management

plan updates

.3 Team performance

assessments

.3 Conflict

management

.3 Project Documents

Updates

.4 Issue log .4 Interpersonal

skills

.4 EEFs updates

.5 Work Performance

reports

.4 Issue log

.5 OPAs Updates

.6 OPAs

Chapter 10: Project Communications

management

Who should know

What When and How? 72 PMBOK 5th Edition Changes Presentation

Page 37: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 37

Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

73 PMBOK 5th Edition Changes Presentation

Chapter 10: Project Communications

management

4th Edition 5th Edition

10.1 Identify Stakeholders

Moved to 13.1

10.2 Plan Communications

10.1 Plan Communications Management

10.3 Distribute Information

10.2 Manage Communications

10.4 Manage Stakeholder Expectations

Moved to 13.3

10.5 Report Performance

10.5 Control Communications

Project Communication Management Processes

74 PMBOK 5th Edition Changes Presentation

Page 38: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 38

10.1 Plan Communications ITTO

75 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

Management Plan

.1 Communication

requirements analysis

.1 Communications

management plan

.2 Stakeholder register .2 Communication

technology

.2 Project document

updates

.3 Enterprise

environmental factors

.3 Communication

models

.4 Organizational

process assets

.4 Communication

methods

Stakeholder

management strategy

.5 Meetings

10.2 Manage Communications ITTO

76 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

Communications

management plan

.1 Communication

Technology

.1 Project

communications

.2 Work Performance

reports

.2 Communication

Models

.2 Project

management plan

updates

.3 EEFs .3 Communication

methods

.3 Project Documents

Updates

.4 Organizational

process assets

.4 Information

Management systems

.4 OPAs Updates

.5 Performance

reporting

Information

Distribution Tools

Page 39: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 39

10.3 Control Communications ITTO

77 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Information management systems

.1 Work Performance

reports Information

.2 Project

communications

.2 Expert judgment .2 Change requests

.3 Issue Log .3 Meetings .3 Project

management plan

updates

.4 Work performance

Information Data

.1 Variance analysis .4 Project documents

updates

.5 Organizational

process assets

.2 Forecasting methods .5 OPAs updates

.6 Work Performance

measurements

.3 Communication

methods

.7 Budget forecasts .4 Reporting systems

Chapter 11: Project Risk Management

What are the threats and opportunities? And how to deal with them?

78 PMBOK 5th Edition Changes Presentation

Page 40: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 40

Chapter 11: Project Risk Management

Systematic process of identifying, analyzing and responding to project risk.

79 PMBOK 5th Edition Changes Presentation

4th Edition 5th Edition

11.1 Plan Risk Management

11.1 Plan Risk Management

11.2 Identify Risks

11.2 Identify Risks

11.3 Perform Qualitative Risk Analysis

11.3 Perform Qualitative Risk Analysis

11.4 Perform Quantitative Risk Analysis

11.4 Perform Quantitative Risk Analysis

11.5 Plan Risk Responses

11.5 Plan Risk Responses

11.6 Monitor and Control Risks

11.6 Control Risks

Project Risk Management Processes

80 PMBOK 5th Edition Changes Presentation

Page 41: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 41

11.1 Plan Risk Management ITTO

81 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs 1 .1 Project management

plan

.1 Analytical

techniques

.1 Risk

management

plan 2 .2 Project charter .2 Expert judgment 3 .3 Stakeholder register .3 Meetings

4 .4 Enterprise

environmental factors

Planning meetings

and analysis 5 .5 Organizational

process assets 6 Project scope statement

Schedule, Cost, and

Communications

management plans

11.2 Identify Risks ITTO

82 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs 1 .1 Risk management plan .1 Documentation reviews .1 Risk register

2 .2 Cost management plan .2 Information gathering

techniques 3 .3Schedule management plan .3 Checklist analysis

4 .4 Quality management plan .4 Assumptions analysis 5 .5 Human resource

management plan

.5 Diagramming

techniques 6 .6 Scope baseline .6 SWOT analysis 7 .7 Activity cost estimates .7 Expert judgment

8 .8 Activity duration estimates

9 .9 Stakeholder register Tools & Techniques

10 .10 Project documents

.12 Enterprise environmental

factors

11 .11 Procurement documents .13 Organizational process

assets

Page 42: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 42

11.3 Perform Qualitative Risk Analysis ITTO

83 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

1 .1 Risk

management plan

.1 Risk probability and

impact assessment

.1 Project

Documents updates 2 .2 Project scope

statement Scope

baseline

.2 Probability and

impact matrix

Risk register

updates

3 .3 Risk register .3 Risk data quality

assessment 4 .4 EEFs .4 Risk categorization 5 .5 OPAs

.5 Risk urgency

assessment 6 .6 Expert judgment

11.4 Perform Quantitative Risk Analysis ITTO

84 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

1 .1 Risk management

plan

.1 Data gathering and

representation

techniques

.1 Project

Documents updates

2 .2Cost management

plan

.2 Quantitative risk

analysis and

modeling techniques

Risk register

updates

3 .3 Schedule

management plan

.3 Expert judgment

4 .4 Risk register

5 .5 EEFs

6 .6 Organizational

process assets

Page 43: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 43

11.5 Plan Risk Responses ITTO

85 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

1 .1 Risk management

plan

.1 Strategies for

negative risks or

threats

Project

management plan

updates

2 .2 Risk register

.2 Strategies for

positive risks or

opportunities

Project document

updates

3 .3 Contingent

response strategies

Risk register

updates

4. Expert judgment Risk-related

contract decisions

11.6 Monitor and Control Risks ITTO

86 PMBOK 5th Edition Changes Presentation

Inputs T&T Outputs 1 .1 Project

management plan

.1 Risk

reassessment

.1 Work performance

information 2 .2 Risk register

.2 Risk audits .2 Change requests

3 .3 Work

performance

information Data

.3 Variance and

trend analysis

.3 Project management

plan updates

4 .4 Work

Performance

reports

.4 Technical

performance

measurement

.4 Project document

updates

5 .5 Reserve analysis .5 Organizational

process assets updates 6 .6 Status Meetings Risk register updates

Page 44: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 44

Chapter 12: Project Procurements

management

What to buy & How?

87 PMBOK 5th Edition Changes Presentation

Chapter 12: Project Procurements

management

Project Procurement Management includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team. The organization can be either the buyer or seller of the products, services, or results of a project.

88 PMBOK 5th Edition Changes Presentation

Page 45: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 45

4th Edition 5th Edition

12.1 Plan Procurements

12.1 Plan Procurement Management

12.2 Conduct Procurements

12.2 Conduct Procurements

12.3 Administer Procurements

12.3 Control Procurements

12.4 Close Procurements

12.4 Close Procurements

Project Procurement Management Processes

89 PMBOK 5th Edition Changes Presentation

12.1 Plan Procurements ITTO

90 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Scope baseline , Cost

performance baseline Project

management plan.

.1 Make-or-buy

analysis

.1 Procurement

management plan

.2 Requirements documentation .2 Expert

judgment

.2 Procurement statements

of work

.3 Risk register .3 Market

research

.3 Procurement documents

.4 Activity resource requirements .4 Meetings .4 Source selection criteria

.5 Project schedule Contract types .5 Make-or-buy decisions

.6 Activity cost estimates .6 Change requests

.7 Stakeholder register .7 Project documents

updates.

.8 Enterprise environmental factors

.9 Organizational process assets

.10 Risk-related contract decisions

.11 Teaming agreements

Page 46: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 46

12.2 Conduct Procurements ITTO

91 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management plan .1 Bidder conferences .1 Selected sellers

.2 Procurement documents .2 Proposal evaluation

techniques

.2 Procurement

contract award

Agreements .3 Source selection criteria .3 Independent

estimates

.4 Seller proposals .4 Expert judgment .3 Resource calendars

.5 Project documents .5 Advertising .4 Change requests

.6 Make-or-buy decisions .6 Analytical

techniques

.5 Project

management plan

updates .7 Procurement statement of

work

.7 Procurement

negotiations

.8Organizational process

assets

.8 Internet search .6 Project document

updates

.9 Qualified seller list

.10 Teaming agreements

12.3 Control Procurements ITTO

92 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Contract change

control system

.1 Work Performance

information

.2 Procurement

documents

.2 Procurement

performance reviews

.2 Change requests

.3 Contract Agreements .3 Inspections and audits .3 Project management

plan updates

.4 Approved change

requests

.4 Performance reporting .4 Project documents

updates

.5 Work Performance

reports

.5 Payment systems .5 Organizational

process assets updates

.6 Work performance

information Data

.6 Claims administration Procurement

documentation

.7 Records management

system

Page 47: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 47

12.4 Close Procurements ITTO

93 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project

management plan

.1 Procurement audits .1 Closed

procurements

.2 Procurement

documentation

.2 Negotiated

settlements

Procurement

negotiations

.2 Organizational

Process Assets

Updates

.3 Records

management system

Chapter 13: Stakeholders Management

Stakeholders

94 PMBOK 5th Edition Changes Presentation

Page 48: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 48

4th Edition 5th Edition

10.1 Identify Stakeholders 13.1 Identify Stakeholders

13.2 Plan Stakeholder Management

10.4 Manage Stakeholders Expectations

13.3 Manage Stakeholders Engagement

13.4 Control Stakeholders Engagement

Project Stakeholders Management Processes

95 PMBOK 5th Edition Changes Presentation

13.1 Identify Stakeholders ITTO

96 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project charter .1 Stakeholder analysis .1 Stakeholder

register

.2 Procurement

documents

.2 Expert judgment .2 Stakeholder

management strategy

.3 Enterprise

environmental factors

.3 Meetings

.4 Organizational

process assets

Page 49: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 49

13.2 Plan Stakeholders Management ITTO

97 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Expert judgment .1 Stakeholder

management plan

.2 Stakeholder register .2 Meetings

.2 Project documents

updates

.4 Enterprise

environmental factors

.3 Analytical

techniques

.5 Organizational

process assets

Project charter

13.3 Manage Stakeholder Engagement ITTO

98 PMBOK 5th Edition Changes Presentation

Inputs Tools &

Techniques

Outputs

.1 Stakeholder register

management plan

.1 Communication

methods

.1 Issue Log

.2 Project management

plan Communications

management plan

.2 Interpersonal

skills

.2 Change requests

.3 Change log .3 Management

skills

.3 Project

management plan

updates

.4 Organizational process

assets

.4 Project document

updates

.Stakeholder

management strategy

.5 Organizational

process assets updates

. Issue log

Page 50: 2013-5thedition Changes SOE 20130313 Final

Mar 2013 Based on PMBOK 5th Edition

Unauthorized Distribution not allowed 50

13.4 Control Stakeholder Engagement ITTO

99 PMBOK 5th Edition Changes Presentation

Inputs Tools & Techniques Outputs

.1 Project management

plan

.1 Information

management systems

.1 Work performance

information

.2 Issue log .2 Expert Judgment .2 Change requests

.3 Work Performance

data

.3 Meetings .3 Project

management plan

updates

.4 Project documents

4 Project document

updates

.5 OPAs Updates

The End

Q & A

100 PMBOK 5th Edition Changes Presentation

Thanks and Good Luck