Government Contractors Financial & Project Management Systems Seminar Page 1 Thrive. Grow. Achieve. Seth Zarny – Raffa Partner Kellye Jennings – BDO Partner Glenn Anstead – Raffa Senior Manager September 26, 2013 Government Contractors Financial & Project Management Seminar

description

 

Transcript of 2013-09-26 Government Contractors Project Management Systems

Page 1: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 1

Thrive. Grow. Achieve.

Seth Zarny – Raffa Partner Kellye Jennings – BDO Partner Glenn Anstead – Raffa Senior Manager

September 26, 2013

Government Contractors Financial & Project

Management Seminar

Page 2: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 2

Agenda

• The regulatory environment

• Business systems • Time and expense challenges and requirements

• Job costing

• Definition and allocation of direct and indirect costs

• Allocation bases

• How rates are calculated

Presenter
Presentation Notes
Text slide with title and body text (Slide layout option: Title and Content) This slide exists as a ‘slide master’. Text is entered directly into the prompt boxes provided when a new ‘Title and Content’ slide is inserted from the slide layout options. The ‘slide master’ also includes the correctly sized and positioned BDO logotype and other graphic elements. All the slide title text is in BDO Red, Trebuchet MS bold, upper case. Where there is a sub-heading, the second line should be changed to BDO Teal. Within body text, subheadings should be set at the same size in Trebuchet MS Bold, BDO Red. To advance to each level from the previous one, select ‘Increase List Level’ on the ‘Paragraph’ ribbon tab. To return to the previous level, select ‘Decrease List Level’ on the ‘Paragraph’ ribbon tab. The starting position of the text is fixed but the text box will grow if text extends beyond the depth determined by the ‘slide master’. Care should be taken to keep text within the boundary of the bottom margin. Start a new page if necessary. Note: The presentation footer includes the Client name, event details and the Presentation title. You can change these details. To make a change to the footer details, click ‘Insert’ from the PowerPoint ribbon. From the Text tab, click on ‘Header and Footer’, a dialogue box will open. To change the Footer text, simply overtype the sample text that appears in the ‘Footer’ area of the dialogue box. The details will be updated on all presentation slides that include the footer text. It is not necessary to change any of the other options on this panel.
Page 3: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 3

Agenda (continued)

• Other issues

• Provisional versus actual rates

• Types of government contracts

• Government audits • Questions?

Page 4: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management System Seminar Page 4

SECTION 1 – THE REGULATORY ENVIRONMENT

Page 5: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 5

The Regulatory Environment

Heavily regulated: • Many potential pitfalls for the naïve or unwary seller • Compliance costs (personnel, systems, procedures) require up front investment

Federal Acquisition Regulation (FAR):

• Covers all aspects of contracting for the Federal Government • Includes “Cost Principles” and many other administrative procedures

Agency Supplements (e.g., DFARS):

• Provide additional Agency-specific guidance Cost Accounting Standards (CAS):

• Provide guidance on acceptable cost accounting practices

Page 6: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 6

The Regulatory Environment

Key regulatory compliance issues include:

• Identification and Segregation of “Unallowable” Costs: o As discussed further below, Government contractors are required to identify,

segregate, and exclude certain types of costs from proposals, billings, and claims.

o “Flexibly priced” contracts may require certification of proposed indirect cost rates.

• Government Property Control Requirements: o Contractors are required to identify, track and maintain Government Property,

including items acquired in performance of a contract.

o Lost, damaged, stolen or destroyed property must be promptly reported.

o Periodically, inventories of Government Property must be performed and submitted to Government customers.

Page 7: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 7

(FAR) Federal Acquisition Regulation vs. (CAS) Cost Accounting Standards FAR Cost Principles Determine ALLOWABLE Costs Cost Accounting Standards govern COST ACCOUNTING PRACTICES used for Government Contracts:

• Measurement of Costs • Assignment of Costs to Cost Accounting Periods • Allocation of Costs

Page 8: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 8

What is “FAR”? The Federal Acquisition Regulation (FAR) is the principal set of rules in the Federal Acquisition Regulation System. This system consists of sets of regulations issued by agencies of the Federal government of the United States to govern what is called the "acquisition process," which is the process through which the government purchases ("acquires") goods and services. That process consists of three phases:

(1) need recognition and acquisition planning, (2) contract formation, and (3) contract administration

The FAR System regulates the activities of government personnel in carrying out that process. It does not regulate the purchasing activities of private sector firms, except to the extent that parts of it are incorporated into government solicitations and contracts by reference.

Page 9: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 9

Purpose of “FAR” The purpose of the FAR is to provide "uniform policies and procedures for acquisition." FAR 1.101. Among its guiding principles is to have an acquisition system that

(1) satisfies customer's needs in terms of cost, quality, and timeliness; (2) minimize administrative operating costs; (3) conduct business with integrity, fairness, and openness; and (4) fulfill other public policy objectives. FAR 1.102(b).

The FAR also includes socioeconomic requirements, such as requiring certain items to be purchased from the United States firms only and that large organizations to use smaller businesses as subcontractors.

Page 10: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 10

What is “CAS”? The Cost Accounting Standards (CAS) are methodologies and techniques used to guide and consistently measure the cost accounting practices amongst government contractors. The Cost Accounting Standards Board (CASB) consists of members from the Office of Management and Budget (OMB), Department of Defense (DOD), General Services Administration (GSA), and private sector. To promote consistency across agencies, the Cost Accounting Standards which address the assignment of costs to government contracts are different from the ‘Cost Principles’ which provide guidance for cost allowability. Some of the principles are based upon certain cost accounting standards and should be referenced to determine if a cost is unallowable. Cost accounting can be categorized into the following three areas:

(1) measurement of cost (market vs. present value), (2) cost accounting period assignment (accrual vs. cash basis), and (3) allocation of costs (direct vs. indirect)

Page 11: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 11

Purpose of “CAS” The purpose of the CAS is to ensure your cost accounting practices as a contractor are fairly standard, practical, yet flexible across the industry, while remaining consistent with your disclosed practices, procedures, and policies for cost recovery:

(1) CAS should be considered during the design and configuration of your financial systems, (2) CAS directly affect compliance (3) CAS have a direct impact on your ability to recover costs

Your disclosed (submitted statement, if applicable) cost accounting policies and practices must also be adequate and compliant and should be the basis for your accounting and financial system design.

Page 12: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 12

Compliance Is Your Friend

Compliance Is Your Friend

Government Contracting Industry is heavily regulated

• Many potential pitfalls for the naïve or unwary seller • Compliance costs (personnel, systems, procedures) require up front investment

Federal Acquisition Regulation (FAR) • Covers all aspects of contracting for the Federal Government • Includes “Cost Principles” and many other administrative procedures

Agency Supplements (e.g., Defense Federal Acquisition Regulation Supplement - DFARS)

• Provide additional Agency-specific guidance

Cost Accounting Standards (CAS) • Provide guidance on acceptable cost accounting practices

Compliance generally leads to a competitive advantage. Noncompliance may lead to imposition of penalties, suspension, debarment, and no award

Page 13: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management System Seminar Page 13

SECTION 2 - BUSINESS SYSTEMS

Page 14: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 14

Business Systems Rule Simply stated… the Contractor shall establish and maintain acceptable business systems…

• Establishes criteria for mandatory adherence of requirements specifically related to a contractors business systems to ensure best practices are maintained for all government contracts.

• Criteria reflects a combination of existing requirements as found in CAS, FAR, DFARS, and those historically enforced by DCAA, DCMA, cognizant audit agency, etc.

• Identifies the relevant business systems, corresponding guidelines and compliance requirements.

Page 15: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 15

Business Systems Rule (cont.)

• Provides for mandatory financial penalties for any noncompliance that is deemed a “significant deficiency”

• Allows for discretion (as exercised by government audit agency and reviewers) in how compliance will be achieved; final determination resides with ACO, CO directs withholding decision

• Defines grace period for implementing corrective action plan to rectify deficiencies

Page 16: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 16

Acceptable / Deficient

“Deficiency” is defined as a shortcoming in the contractors business system(s) that materially affects the ability of officials of the Department of Defense to rely upon information produced by the system that is needed for management purposes.

“Acceptable contractor business systems” are contractor business systems which are found to be in compliance with relevant laws and regulations [Cost Accounting Standards (CAS) clauses and Federal Acquisition Regulations (FAR) principles] as reviewed by your cognizant audit agency.

Page 17: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 17

What happens if found “Deficient”? You must respond in writing to your Contracting Officer (CO) within 30 days of receiving your determination of identified business systems deficiencies to include your comments –rationale for disagreement CO may issue a notice of intent to Contractor to withhold amounts from interim billings not to exceed:

• 5% for one or more identified significant deficiencies in any single business system • 10% significant deficiencies in multiple business systems

Page 18: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 18

What happens if found “Deficient”? (cont.) If you correct the deficiencies or submit an acceptable corrective action plan (one that includes milestones and steps taken to eliminate issues) within 45 days of notice of intent to withhold, and as verified by the cognizant audit agency (auditor), the CO may:

• Decrease the withholding percentage until such time all deficiencies have been corrected and verified

• Discontinue withholding and release previously withheld amounts (if not related to other system deficiencies) and verified by auditor

• If no determination of the corrective action plan by the CO has been made within 90 days, withholding could be reduced by 50%, but not release payment for previous withholdings

If the corrective plan is not followed and the deficiencies continue to exist, the CO may:

• Increase the withholding percentage if the corrective action plan is not followed and deficiencies continue to exist

Page 19: 2013-09-26 Government Contractors Project Management Systems

BDO USA, LLP, a Delaware limited liability partnership, is the U.S. member of BDO International Limited, a UK company limited by guarantee, and forms part of the international BDO network of independent member firms. BDO is the brand name for the BDO network and for each of the BDO Member Firms.

What systems can I use to run my business?

Page 20: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 20

Microsoft Integrated Solutions

• Dynamics ERP • SharePoint

2

Page 21: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 21

What is Microsoft Dynamics?

• Integrated Financial and Operational/Project Management Software

• Familiar to Your Employees • Government Contracting Industries:

• Professional Services • Contracting • Manufacturing • Distribution

• Accepted by DCAA

2

Page 22: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 22

Functionality Provided by Dynamics

•Financials •Accounting •Fringe, Overhead and G&A Rate Calculations

- Cost Segregation – Allowable vs. Unallowable •Job Costing •Purchasing & Requisition Mgmt •Manufacturing •Inventory Management •Sales Orders •Service Management •Customer Relationship Management

2

Page 23: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 23

Microsoft SharePoint

What is Microsoft SharePoint? A foundation for connected information

• Team Collaboration • Dashboard • Key Performance Indicators • Dynamics Business Portal • Integrated with Project Server

2

Page 24: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 24

What will you get from the Integrated Solution?

Organized flow of information • Project Management • Resource Allocation • Financial Reporting

Seamless integration of information One view of the data Tools your team is familiar with…

2

Page 25: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 25

Project Manager Support

2

• WEB ACCESS TO YOUR DATA • Immediate access to Projects profitability • Maintain projects • Assign resources to projects, tasks or subtasks • Create initial and subsequent budgets • Set maximums for Projects and Tasks • Store and share Project invoices in a document

repository • Enter time remotely supporting your companies

needs: bi-weekly, semi monthly…

Page 26: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 26

Reporting vs. Dashboards

Many people use the terms interchangeably What is the purpose of a report in Government Contracting

company? • Compliance • Company Directed What is the purpose of a dashboard? • Drive user towards decision How do you know what the Dashboards should be? • Key Performance Issues of Company What are KPI’s? • Key Performance Indicator

2

Page 27: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 27

Critical Requirements for Success

What to look for when reviewing integrated solutions? Out of the Box, Proven Financial and Operational Software

- Proven management of Indirect and Direct Costs - Integrated across Finance and Project Management / Operations - Business Process Automation - Setup Flexibility to meet business needs

2

Page 28: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 28

Business Process Improvements

Indirect Rates • Monitor Trends via standard reports • More Accurate Cost Information for Bidding • More Accurate Historical Procurement Costs

Traceability of Source Documents

• Management Reporting Drill Down • On line Inquiry Screens • Transaction Level Detail • Imaging/Document Management

2

Page 29: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 29

Statement of Indirect Expense

2

Page 30: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 30

Operational Benefits

What benefits should Operations & Project Managers receive from Microsoft Dynamics?

- Superior Cost Control

- Real time visibility into committed costs

- Immediate access to supporting documentation via document imaging

- Earned Value Management visibility

3

Page 31: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 31

Job Summary Report

3

Page 32: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 32

Dynamics SL Overview Exec Mgmt Dashboards

Real-time visibility into your data Top 10 Customers Year over year Sales and Margin

3

Page 33: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 33

Dynamics SL Overview Project Dashboard

Real-time visibility into your data

Project P&L

Labor hours statistics

3

Page 34: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 34

Dynamics Overview Increased Visibility

Real-time visibility into your data Labor statistics by Customer

3

Page 35: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 35

Dynamics Overview Project Visibility

Online Project visibility – multiple levels…

3

Page 36: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 36

Dynamics Overview Project Visibility

Online Project visibility – multiple levels… Commitments & Budgets

3

Page 37: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 37

Dynamics Overview Self Service Access

Online Project visibility – multiple levels… Self-service – Project

profitability

3

Page 38: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 38

Dynamics Overview Ability to drill into the details

Online Project visibility – multiple levels… Self-service – Drill into the supporting details

3

Page 39: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management System Seminar Page 39

SECTION 3 – TIME AND EXPENSES

Page 40: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 40

Objectives of Timekeeping System

• Ensure that proper and reliable contract labor costs, identified as either direct or indirect, are: - Accumulated - Reported - Billed

• Billings to the government via a system of accurate, timely, and complete posting of labor hours on individual employee timecards

Page 41: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 41

T&E System Best Practices

• Employee understanding of procedures for preparing time sheets/cards/entering time, and preparing expense reports

• Employee independence in preparing and correcting time sheet/expense report and adequate management review and submission to accounting

• Adequate written policy and procedures that employees and management must follow

• Traceability of changes

• System for detecting errors/required changes

Page 42: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 42

T&E System Best Practices (continued)

• Proper coding of expenses to corresponding accounts.

• Inclusion of sufficient business purpose on expense reports. - A business purpose of “miscellaneous reimbursement” is not adequate and does not

provide transparency into the nature of the expense.

• Detail regarding number of attendees for meal expenses on expense reports

(dependent on Company policy)

• Itemized receipts for expenses relating to meals (dependent on Company policy)

Page 43: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 43

Basic Requirements of Timekeeping System

• Employee is given or mapped to correct project or charge number via work authorization before work commences

• Time cards/sheets or access to system provided to employee at beginning of pay period

• Time cards/sheets are pre-coded with pay period, name, etc., if manual

• Employee has control or possession of timesheet (if manual) or sole access to electronic system

• Employees record time daily

• Supervisors or other personnel do not prepare timesheet entries for employees (unless out due to sickness, etc.)

Page 44: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 44

Basic Requirements of Timekeeping System (continued)

• Audit trail for changes made to initial timekeeping entries

• Management approval of timesheet corrections noted

• Explanation of timesheet corrections provided

• Timesheet signed by employee at end of pay period

• Paid absences charged to correct indirect code

• Indirect duties (training, meetings, etc.) properly charged

• Timesheets collected by appropriate official and reviewed and approved

Page 45: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 45

What DCAA observations will elevate audit risk?

• Mix of cost plus government & commercial contracts

• Lack of written or inadequate t&e procedures

• Significant adjusting entries to G/L labor charges

• Data indicated on timesheet during floor check does not match time sheet after entered to labor distribution

• Significant and non-verifiable changes and alterations to employee timesheets

• Timesheets without employee signature

• Inadequate demonstration of employee training for preparing time sheets

Page 46: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 46

How do I know if I have Timekeeping System problems?

• Timekeeping procedure is twelve years old and has not been updated to reflect current electronic methods

• At end of payroll period, electronic time entries for several employees are changed & then “approved” by supervisor

• John Doe provides Lisa Smith, another employee (not his supervisor) his timekeeping password so that Lisa can prepare entries for him while John is in rehab

• Jane Doe, an “exempt” G&A person, often works uncompensated OT, but does not record more than 40 hrs/week

• Company cannot reconcile total payroll to labor distribution

Page 47: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 47

Time Reporting

• All time worked should be reported, including all time worked in excess of the standard workweek. This includes all time worked for clients, whether billable or not.

• All time and expenses associated with an individual contract should be recorded in a Work Breakdown Structure (WBS) element. Any time or expense related to the execution of a specific contract should be charged to the correct WBS elements, regardless of whether or not those time and expenses can be billed. All other time and expenses should be charged to the appropriate WBS element.

Page 48: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 48

Labor System Authorization/Approvals

• The contractor should have procedures to ensure the segregation of duties for work authorizations and/or job assignments to the extent practical. Work authorizations/job assignments should be controlled and issued by individuals independent of those responsible for performing the work - a critical control is the procedure used to open and close work authorizations.

• The contractor should have procedures for the preparation of labor documentation/work descriptions that require clear identification of the nature of the work performed - trackable to intermediate or final cost objectives

• The contractor should establish a labor charging awareness program to train all employees, as appropriate, on proper labor charging practices.

Page 49: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 49

Labor System Authorization/Approvals cont.

• The contractor should assure that labor hours are accurately recorded and that any corrections to time keeping records are documented including the appropriate authorizations and approvals.

• The contractor should assure the proper allocation of labor costs to cost objectives.

• The contractor should provide reasonable assurance that labor transfers or adjustments of the labor distribution are documented and approved.

• The contractor should monitor the overall integrity of the time keeping system.

Page 50: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 50

Overtime Approval

• Requests for overtime should be made by project managers or department managers. Overtime must only be authorized when a project or department manager has documented the following in writing: - Overtime is necessary to meet delivery requirements, - Overtime is necessary to meet performance requirements, or - Overtime is necessary to make up for delays beyond the control or without the fault

or negligence of the contractor

• When required by contract provisions, the project manager authorizing overtime must obtain the contracting officer's written approval.

Page 51: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 51

Timecard Changes / Modifications

• It is improper for supervisors to unilaterally make changes to an employee’s timecard. Doing so may result in disciplinary action.

• If a time correction is necessary PRIOR TO submitting the time sheet to the Payroll Department, the employee should ensure that the time sheet correction is made in ink and initialed. The reason should be clearly documented and approved by a supervisor.

• When making a correction(s) to reported time SUBSEQUENT TO submitting the time sheet to the Payroll Department: - The correction may not be more than 30 days old. - Employees must indicate the reason for the correction, the job numbers affected by

the adjustment, and the related hours. - The documentation for the labor corrections must be signed by a supervisor and

submitted to accounting. - Consider creating a “Labor Correction Form” that will state the necessary procedures

for making labor corrections.

Page 52: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 52

Distribution of Labor Costs and Labor Transfers • Written justification is required for any transfer of labor costs to ensure the

proper allocation of labor costs to each project. Each justification should be retained in accordance with the contractor’s record retention policy. Journal vouchers are commonly used to document labor transfers.

• The contractor should consider additional procedures for more closely scrutinizing transfers.

• The contractor should include procedures to address management review and approval of labor transfers, labor distribution edit errors, and review and correction of labor errors.

• Labor distribution edit errors should be processed in a suspense account and billed to customers only after correction.

Page 53: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 53

Consequences for Deliberate Failure to Follow Timekeeping Policies and Procedures • The contractor should be committed to the enforcement of all timekeeping

procedures. Any clear infraction of the policy stated above will result in disciplinary action which may include a warning, reprimand, probation, suspension, reduction in salary, demotion, or dismissal.

• Employees should be aware, in addition to company imposed sanctions, that individuals directly responsible for deliberate mischarging of time or materials may be held personally liable for civil penalties and actual damages sustained by the government as a result of the mischarging. Criminal prosecution may also result which carries fines and/or imprisonment.

Page 54: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 54

Consequences for Deliberate Failure to Follow Timekeeping Policies and Procedures cont. • Employees must be vigilant in their efforts to accurately record time. The

penalties for knowingly mischarging time can be as severe as termination and other Governmental ramifications (i.e., False Claims Act).

• The contractor should periodically conduct floor checks to ensure timekeeping practices are being followed and actual hours worked are accurately recorded.

Page 55: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 55

Dynamics Overview Web based Timecards

Online Timesheets

5

Page 56: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 56

Web Based EE Expense Report

5

Page 57: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 57

Dynamics SL Overview - Assign Resources

5

Presenter
Presentation Notes
next he needs to assign resources to the tasks for this project
Page 58: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 58

Dynamics Overview - Increased Visibility

Real-time visibility into your data Labor statistics by Customer

5

Page 59: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management System Seminar Page 59

SECTION 4 – JOB COSTING

Page 60: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 60

Job Cost Accounting Systems

• Used to determine cost of a product or service • Can be used to determine prices – government contract prices are often based on costs

charged to a job • Used to record cost of an individual transaction • May be used to distribute indirect costs to cost objectives • Government does not require “on book” distributions • “Memo records” are acceptable • Facilitates integration of production data into accounting records

Page 61: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 61

Job Cost Accounting Systems (continued)

• Costs must be accumulated under general ledger control o Job costs must be reconcilable and posted to general ledger control accounts o Costs must be posted at least monthly to books of account

• Costs must be segregated between direct and indirect types o Controls must exist to preclude direct charging of indirect expenses

• Direct costs must be accumulated by contract o Must either have a subsidiary job cost ledger or accounts receivable ledger o Must be able to “drill down” to at least Contract Line Item Number (“CLIN”) level

• Indirect costs must be allocated to jobs o Accumulated in logical cost groupings and allocated based on causal or beneficial

relationships

Page 62: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 62

Allocation of Expenses

When a company incurs an expense, it is either a direct expense that is charged to a specific project or it is an indirect expense that benefits various projects and the company as a whole.

Page 63: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 63

Accounting for Unallowable Costs

An allowable cost in government contracting terms means billable – it’s allowable if the rules permit it to be included in an invoice to the government. An unallowable cost is just the opposite; it’s the kind of cost you can’t bill the government for. Under the FAR 31.201-2, a cost is allowable only when it meets all of these requirements: Terms of the contract Limitations set for the in FAR 31.201 Reasonable and allocable

Page 64: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 64

What is a Direct Cost?

If a cost is easily identified with a single project, it is generally considered a direct cost.

To help make this determination, ask… “If we did not have this contract, would we still incur this cost?” A “no” answer to this question indicates that it is probably a direct cost.

Page 65: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 65

Direct Costs Examples

• Labor performed while working on a

project • Travel to project status meetings • Material consumed entirely on a project • Subcontractors/consultants hired to

work on a project .

Page 66: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 66

What is an Indirect Cost?

An indirect cost is a cost incurred that: • Benefits more than one contract • Incurred for the common good of the company • Impractical to split • Immaterial direct cost

Page 67: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 67

Defining Indirect Costs

Fringe benefits Company expenses incurred for the benefit of its employees

• Employer payroll taxes • Medical insurance paid by the company • Company 401(k) contributions • Paid time off

Page 68: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 68

Defining Indirect Costs

Overhead Costs not directly related to cost objectives but are support-type costs necessary for the production of goods or services • Salaries and wages of support and production personnel • Facilities cost • Supplies

It is common to find separate overhead pools for engineering, manufacturing, and for certain off-site activities

Page 69: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 69

Defining Indirect Costs

G&A Costs associated with the general administration and overall management of a company

• Compensation of company executives and related fringe • Legal and professional fees • Administrative personnel and costs • Business insurance • Company taxes (except federal income taxes) • Bid and proposal costs

Page 70: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 70

Defining Indirect Costs

Subcontractor/material handling Costs associated with overall administration of subcontractor and materials acquisitions • Selecting, negotiating, and managing subcontractors and materials purchases

Page 71: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 71

Direct or Indirect – Gray Areas Example: Company A and B ship monthly program reports to their clients Company A

• Charges the shipping expense against the contract

• Support personnel charge time to overhead

Company B • Charges all shipping to overhead

• Administrative staff charge:

o Time supporting projects

o Overhead when working on support of a general nature

The same approach can be taken on many other types of expenses, such as photocopies, phone calls, faxes, etc.

Page 72: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 72

G&A or Overhead

Company A charges HR costs to G&A while Company B allocates the cost of HR across the entire company. HR benefits the Company as a whole,

meeting the criteria of a G&A cost, but HR also benefits all ee’s of the Company.

Company B rational:

• The fundamental costs of the majority of ee’s are maintained in OH

• HR costs will be allocated between OH & G&A based on a method such as using proportionate number of ee’s

Can certain G&A costs qualify as OH expenses?

Deciding to allocate costs between G&A and OH takes detailed planning and consideration of materiality and cost /benefit relationship

Page 73: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 73

Defining Allocation Bases

Assigning an indirect cost pool to a particular allocation base depends upon: • Types of costs included in the pool • Whether the base provides a reasonable representation of the relative

consumption of pooled indirect costs by direct cost activities

Labor costs are an appropriate allocation base for the fringe expenses.

There is a clear relationship between the two.

Page 74: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 74

Indirect Rates

Indirect rates are equitable, logical and consistent process for allocating costs not directly associated with a single project or cost objective. The only requirement of the FAR is that the allocation of indirect costs be: • Fair • Reasonable • Equitable

Page 75: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 75

Indirect Rates Key points to establish and manage indirect cost structures: Fiscal year

The period for allocating indirect costs is a contractor’s fiscal year – it is not related to a period of performance for a given contracts.

Simplicity When substantially the same result can be achieved through less precise methods, a company is permitted to keep the allocation simple and not be forced into more complicated allocation formulas that are technically more accurate but not materially different.

Consistency Once treated as a direct (or indirect cost), a cost should be treated consistently.

Companies have a great deal of latitude to determine indirect rate

structure

Page 76: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 76

Calculation of Indirect Rates

Indirect rate = Similar cost (pool)

Allocation base

The calculation of indirect rates is simple math – it is just a matter of grouping, adding, and dividing. It’s how and why certain numbers are grouped together that can be complex.

Page 77: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 77

Indirect Rates

Page 78: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 78

Indirect Rates

Page 79: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 79

Indirect Rates

Methods practiced to reduce indirect rates:

• Charge as many costs direct as possible. By charging shipping and copying directly to a contract, it will keep it out of overhead pool, which will in turn reduce the overhead rate.

• Direct charge unique costs to a specific contract • More indirect rates by splitting large groupings • Indirect rates for different types of work • Establish a services center

A company with high rates may not really be any more expensive -- though they are often perceived that way. When developing or evaluating indirect rates, a company should keep in mind ways to reduce at least the appearance of indirect rates.

Page 80: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 80

Indirect Cost Allocation Cycle

Indirect cost allocation typically follows the cycle depicted in the following figure:

Forward Pricing Estimate Indirect

Contract Costs

Final Allocation Allocate

Indirect Costs to Contracts

Billing Progress

Payments Cost Reimbursement

Page 81: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 81

Indirect Cost Allocation Cycle

Forward Pricing- During this phase, the contractor proposes forward pricing rates and uses those rates in contract proposal pricing. Contract Billing- Provisional / Target rates are indirect rate projections used on contract billing that have been reviewed and approved by the DCAA or the contractor’s cognizant agency for proposal and estimating purposes.

For example, a company may develop budgeted rates for the current year and forecasted rates for the next two years. All three years of rates can be approved for proposal preparation purposes.

Page 82: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 82

Indirect Cost Allocation Cycle

Final Pricing. After the cost accounting period is completed, contractors can calculate actual indirect cost rates to determine actual contract cost.

• For contracts that require final pricing (e.g. cost plus) the responsible contracting officer or auditor must determine final indirect rates for the contract.

• Final indirect rate proposal is submitted by the contractor. • Months or years may be required to complete this process. Under certain limited

conditions, the contracting officer and the contractor may agree to use estimated quick-closeout indirect cost rates for final pricing.

• Data used to support final rates will become part of the data available for estimating forward pricing and billing rates for subsequent accounting periods.

Page 83: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 83

Government Contract Life-Cycle

Pre-Award

Award

Accounting

Controls

[Policies, Procedures, Training]

Accounting System

Page 84: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 84

Dynamics SL Overview Project Dashboard

• Real-time visibility into your data

• Project P&L

• Labor hours statistics

8

Page 85: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 85

Dynamics SL Overview - Create New Project

8

Presenter
Presentation Notes
View projects no matter where you are The project our PM is working is for a current client, so he chooses to copy from the previous project to speed up the process of creating a new project
Page 86: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 86

Dynamics SL Overview - Create New Project

8

Presenter
Presentation Notes
Now a new Project is setup and ready to review/edit. This new Project Maintenance screen is a compilation of information found on 5 different screens in the rich client. This provides Project Managers access to the information they need to run their projects all from the web (business portal) Security can be set up for each of these tabs so now you can open up these screens to those who most likely don’t have access to the rich client.
Page 87: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 87

Dynamics SL Overview - Assign Resources

8

Presenter
Presentation Notes
next he needs to assign resources to the tasks for this project
Page 88: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 88

Dynamics SL Overview - Create/Update Budget

8

Presenter
Presentation Notes
The budget screen then reflects the Labor amounts entered into the Resource assignment screen
Page 89: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 89

Benefits Beyond The Norm

8

Traditional Project Management

• On time versus original schedule estimate

• Within budget versus original cost estimate

• Within scope versus original deliverables

• Meet or exceed customer expectations

• “Best available” resource utilization

Project Management & Accounting

Reduced time to market and/or cycle time

Project revenue, cost, and profitability

Business value of services delivered

Alignment with business and client objectives

“Best fit” skills-based resource optimization

Page 90: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 90

Other Measurable Benefits

9

• Better Prioritization of Projects and Services It is shocking how many “projects” operate below the radar screen with no plans, controls or accountability

• Shorten Billing Cycles Better allocation of resource T&E to project schedules and invoicing, and faster resolution of billing disputes

• Minimize Revenue Leakage Eliminate errors from manual entry or redundant systems used to invoice client services

• Improved Service Agility Quicker response to sudden or unexpected changes in business priorities, competitive pressures, new technology, and economic downturns

Page 91: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 91

Bringing it All Together

9

A SINGLE VIEW OF OPERATIONAL DATA

• Discover the one truth for your business • Provide people access and empower them with

simple but sophisticated tools • Focus on what is important and act! • Institute the command and control you need to

meet goals

Page 92: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 92

Dynamics SL Overview Exec Mgmt Dashboards

Real-time visibility into your data Top 10 Customers Year over year Sales and Margin

9

Page 93: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 93

Dynamics Overview Increased Visibility

Real-time visibility into your data Labor statistics by Customer

9

Page 94: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 94

Dynamics Overview Web based Timecards

Online Timesheets

9

Page 95: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 95

Dynamics Overview Project Visibility

Online Project visibility – multiple levels…

9

Page 96: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 96

Dynamics Overview Project Visibility

Online Project visibility – multiple levels… Commitments & Budgets

9

Page 97: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 97

Dynamics Overview Self Service Access

Online Project visibility – multiple levels… Self-service – Project profitability

9

Page 98: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 98

Dynamics Overview Ability to drill into the details

Online Project visibility – multiple levels… Self-service – Drill into the supporting details

9

Page 99: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 99

Web Based EE Expense Report

9

Page 100: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 100

Dynamics Rate Table Setup

1

Page 101: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 101

Provisional vs. PTD Actual reporting

1

Page 102: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 102

Provisional vs. YTD Actual

1

Page 103: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 103

Statement of Indirect Expense

1

Page 104: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 104

Project – GL reconciliation report

1

Page 105: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 105

Job Summary Report

1

Page 106: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 106

Employee Labor Distribution

1

Page 107: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management System Seminar Page 107

SECTION 5 – OTHER ISSUES

Page 108: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 108

Actual versus Provisional Rates

• Provisional rates – estimated rates that are required to reimburse contractors on an interim basis. o Sometimes referred to as “target rates.” o Should be adjusted as facts and circumstances change to prevent substantial

underpayments or overpayments.

• Actual rates – final indirect rates that are determined during or after a contractor’s fiscal period. o Subject to audit o Required to be submitted in the final indirect proposal within six months after

year-end o Used in the contract close-out process

Page 109: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 109

Basic Types of Government Contracts

• Fixed price – contractor is paid a predetermined fixed amount for a specified scope of work and has full responsibility for the performance costs.

• T&M and labor hour – contractor is paid fixed hourly rates for direct-labor hours expended under specified labor categories. Materials and other non-labor costs are usually reimbursed at actual costs plus allocable indirect costs.

• Cost reimbursement – contractor is reimbursed for allowable incurred costs plus a fee (if specified).

TIP: Do not make your accounting systems decision based on the contract mix that you have today.

Page 110: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 110

Scope of Government Audits

• Proposal / pre-award • Incurred cost • Business systems • Forward pricing/estimating • Special

o Termination proposals o Progress payments o Financial capabilities o Other claims

• Other audits o CAS Compliance o Defective pricing o Other

Page 111: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 111

The Current Audit Environment

• Increased oversight on contractor business systems and controls • Stringent rigor applied to audit practices, programs and documentation

o Decreased cooperation with contractors to prevent appearance of bias o “Zero tolerance” with respect to meeting control objectives. o Elimination of recommendations on deficiencies o Inadequate/adequate findings – no more “inadequate in part”

• As a result, an increasing number of contractors now have inadequate systems with “significant deficiencies” and “material weaknesses”

• Most inadequacies have been accompanied with recommendations to ACOs to pursue withhold of payments

• ACOs face an up hill battle in disagreeing with auditor findings • Impacting contractors ability to win new awards and sub-awards

Page 112: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 112

The Current Audit Environment (continued)

• Through periodic business systems audits and flash reports – opportunities for inadequate systems are higher.

• Since there are no longer “inadequate in part” determinations, a single finding is now a “significant deficiency” representing a “material weakness.”

• As a result, a single audit finding can now result in a recommendation of withhold of fees/payments.

• Since there is a backlog of audits and because audits > 4 years old are no longer current, there is an increased number of contractors with unaudited systems.

• DCAA is working on reducing the backlog of open incurred cost audits. o Data is old o Personnel may have changed o Systems may have changed

• Results in increased audit scrutiny (e.g., substantive testing) in all other audits and impacts contractors ability to obtain new awards

Page 113: 2013-09-26 Government Contractors Project Management Systems

Government Contractors Financial & Project Management Systems Seminar Page 113

Dealing with government auditors

• Understanding what is being audited o Pre-award – evaluation of whether the contractor is capable of performing the

proposal. o Post-award – evaluation of accuracy, completeness, and currency of pricing data

submitted. o Incurred costs – evaluation of whether direct and indirect costs are properly claimed

for reimbursement on flexibly-priced contracts. • Be prepared

o Establish an audit liaison o Understand the programs that the auditor will be using o Insist on an entrance and an exit conference o Be prompt in your responses

• Understand that not all government auditors are the same.