2012 Corporate Update January

download 2012 Corporate Update January

of 33

Transcript of 2012 Corporate Update January

  • 8/3/2019 2012 Corporate Update January

    1/33

    C o r p o r a t e U p d a t eJ A N U A R Y 2 0 1 2

  • 8/3/2019 2012 Corporate Update January

    2/33

    This presentation contains forward-looking statements, within the meaning of the United States Private Securities Litigation Reform Act

    of 1995 and applicable Canadian securities legislation, concerning the business, operations and financial performance and condition ofGoldcorp Inc. (Goldcorp). Forward-looking statements include, but are not limited to, statements with respect to the future price of gold,silver, copper, lead and zinc, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing andamount of estimated future production, costs of production, capital expenditures, costs and timing of the development of new deposits,success of exploration activities, permitting time lines, hedging practices, currency exchange rate fluctuations, requirements for additionalcapital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, timing and possibleoutcome of pending litigation, title disputes or claims and limitations on insurance coverage. Generally, these forward-looking statementscan be identified by the use of forward-looking terminology such as plans, expects or does not expect, is expected, budget,scheduled, estimates, forecasts, intends, anticipates or does not anticipate, believes or variations of such words and phrases orstatements that certain actions, events or results may, could, would, might or will be taken, occur or be achieved. Forward-

    looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level ofactivity, performance or achievements of Goldcorp to be materially different from those expressed or implied by such forward-lookingstatements, including but not limited to: risks related to the integration of acquisitions; risks related to international operations; risks relatedto joint venture operations; actual results of current exploration activities; actual results of current reclamation activities; conclusions ofeconomic evaluations; changes in project parameters as plans continue to be refined; future prices of gold, silver, copper, lead and zinc;possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents,labour disputes; delays in obtaining governmental approvals or financing or in the completion of development or construction activities andother risks of the mining industry, as well as those factors discussed in the section entitledDescription of the Business Risk Factors inGoldcorps annual information form for the year ended December 31, 2010 available at www.sedar.com. Although Goldcorp hasattempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking

    statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance thatsuch statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in suchstatements. Accordingly, readers should not place undue reliance on forward-looking statements. Goldcorp does not undertake to updateany forward-looking statements that are included in this document, except in accordance with applicable securities laws.

    All amounts are in U.S. dollars, unless otherwise stated.

    Forward Looking Statements

    2

  • 8/3/2019 2012 Corporate Update January

    3/33

    3

    Growth Leader

    Low Cost Producer

    Outstanding BalanceSheet

    Low Political Risk

    Responsible Mining

    SUSTAINABLE

    PROSPERITY

  • 8/3/2019 2012 Corporate Update January

    4/33

    163

    305 295 274

    209

    540

    563683

    966 1,329

    2007 2008 2009 2010 Q3'11 YTD

    By-Product Cash Costs Cash Margin

    $703

    $868$978

    $1,240

    ($ per Oz)REALIZED GOLD PRICE $1,538

    Sector Leading Cash Margins

    4

  • 8/3/2019 2012 Corporate Update January

    5/33

    Strong Growth on a Per Share Basis

    5

    $1.22 $1.31

    $1.61

    $2.33 $2.32

    $0.00

    $0.50

    $1.00

    $1.50

    $2.00

    $2.50

    2007 2008 2009 2010 Q3'11 YTD

    Cash flow / Share1(US$ / share)

    61.565.0 66.7

    78.0

    40.0

    50.0

    60.0

    70.0

    80.0

    2007 2008 2009 2010

    $0.62 $0.56

    $0.80

    $1.37$1.59

    $0.00

    $0.40

    $0.80

    $1.20

    $1.60

    2007 2008 2009 2010 Q3'11YTD

    Reserves / Share3(per 1000 shares)

    Earnings / Share2(US$ / share)

    1 Cash flow before changes in working capital2 Adjusted earnings per share3 Reserves for gold only4 Includes Cerro Negro update March 2011

    4

  • 8/3/2019 2012 Corporate Update January

    6/33

    39,700

    43,40046,300

    48,800

    62,250

    2006 2007 2008 2009 2010*Gold proven & probable reserves (000s oz)

    2012 Exploration Budget - $200M

    2010* INCREASE OF 28%,17% ON A PER SHARE BASIS

    Steady, Continuous Reserve Growth Success

    6

    * Includes Cerro Negro update March 2011

  • 8/3/2019 2012 Corporate Update January

    7/33

    Gold production (oz) 2,600,000 2,514,700

    Cash costs $/oz - By-Product $250 - $275 ~$220

    - Co-Product $550 - $600 ~$530Capital expenditures $2.6B TBA

    Exploration expenditures $200M TBA

    Corporate administration $160M TBA

    Depreciation /oz $325 TBA

    Tax rate 30% TBA

    20121

    Guidance

    2012 Guidance

    7

    1 2012 price assumptions: Au=$1600/oz, Ag=$34/oz, Cu=$3.50/lb, Zn=$0.90/lb, Pb=$0.90/lb

    2011

    Actual

  • 8/3/2019 2012 Corporate Update January

    8/33

    Cash & cash equivalents ~$1.7B

    Available debt facility undrawn $2.0B

    Convertible senior notes due 2014 $862.5M

    Forecast avg. annual operating $3.7B2

    cash flow over next 5 years

    Financial Position Excellent Liquidity

    1 Moodys: Baa2; S&P: BBB+; Fitch: BBB2 Price assumptions 2012-2016: Au=$1600/oz, Ag=$34/oz, Cu=$3.50/lb, Zn=$0.90/lb, Pb=$0.90/lb

    Investment Grade1 Balance Sheet

    As at Dec. 31, 2011

    8

  • 8/3/2019 2012 Corporate Update January

    9/33

    19%17%

    13%

    11%10%

    9%

    15%

    13%

    11%

    9%8%

    6%

    0%

    2%

    4%

    6%

    8%

    10%

    12%

    14%

    16%

    18%20%

    Newmont Goldcorp Yamana Newcrest Barrick Kinross

    2011E 2012E

    9

    Source: Bloomberg consensusCompany reports

    Dividend as % of Operating Cash Flow

  • 8/3/2019 2012 Corporate Update January

    10/33

    Focus on Stable Jurisdictions

    2012E Gold Production

    OPERATING MINES

    DEVELOPMENT PROJECTS

    AMERICAS ORIENTATION

    ARGENTINA

    DOMINICANREPUBLIC

    CANADA

    CHILE

    MEXICO

    GUATEMALA

    USA

    10

    Canada

    46%

    US

    5%

    Mexico

    33%

    Guatemala

    8%

    Argentina

    5%

    Dominican

    Republic

    3%

  • 8/3/2019 2012 Corporate Update January

    11/33

    2011A 2012E 2013E 2014E 2015E 2016E

    Current Operations New Projects

    (Ounces)

    Steady, Strong Growth Profile

    11

    2,514,700 2,600,000

    3,200,000

    3,800,0004,000,000 4,200,000

  • 8/3/2019 2012 Corporate Update January

    12/33

    Scoping

    Feasibility

    Construction

    Production

    Red Lake & other operating mines

    Marlin (2006)

    Los Filos (2008)

    Peasquito (2010)

    Pueblo Viejo (2012)

    Cerro Negro (2013)

    Cochenour (2014)

    lonore (2014)

    El Morro (2017)

    Camino Rojo (2014)

    Noche Buena

    Cerro Blanco

    Agua Rica

    Red Lake Bulk UG

    Peasquito UG

    A Robust Development Pipeline

    12

  • 8/3/2019 2012 Corporate Update January

    13/33

    High grade vein system Outstanding reserve growth

    potential

    Updated feasibility study results:

    - 550 koz Au annually (1st 5 years)

    -

  • 8/3/2019 2012 Corporate Update January

    14/33

    Cerro Negro Advancing Construction

    140,350 meters exploration drilling

    in 2011 Eureka decline advanced to

    1,620 meters

    6 levels of development into Eureka

    vein Construction & development

    activities advancing: Approval of amended EIA received Plant construction underway Development of Mariana Central

    and Mariana Norte veinscommenced

    14

  • 8/3/2019 2012 Corporate Update January

    15/33

    15

    Cerro Negro Large Percentage of Veins Untested

    San Marcos

    Mariana Norte

    Mariana Central

    Mariana SurEureka

    Buena Vista

    El Retiro

    Vein Zone

    Bajo Negro

    Sur Vein

    4810000N

    4805000N

    5 kilometersAreas of vein tested

    Pre-mineral rock within Bonanza elevation

    Concession Boundary

    Quartz vein

    11.0m111.00 g/t Au238 g/t Ag

    2.0m5.4 g/t Au3,244 g/t Ag

    4.0m3.67 g/t Au3 g/t Ag

    8.0m20.1 g/t Au265 g/t Ag

    2400000E Fault

    6.5m

    150 g/t Au172 g/t Ag

    1.5m92.6 g/t Au72 g/t Ag

    2.0m41.12 g/t Au217 g/t Ag

  • 8/3/2019 2012 Corporate Update January

    16/33

    lonore Pure Gold in a Safe Jurisdiction

    Currently sinking exploration shaft 3.03M oz Au reserves

    +0.48M oz Au M&I resources+4.17M oz Au inferred resources

    Development plan:- Upper/lower mine concept; 7 ktpd- Mine life ~15 years- +600,000 oz Au

    - Cash costs:

  • 8/3/2019 2012 Corporate Update January

    17/33

    Exploration shaft over 640 metres

    Exploration ramp extended over 830metres

    Plant construction underway

    Surface preparation for sinking ofsecond production shaft advancing

    EPCM contract awarded Continued exploration success

    lonore Progressing Towards Construction

    17

  • 8/3/2019 2012 Corporate Update January

    18/33

    5.9 million ounces of Au reserves1

    4.3 billion pounds of Cu reserves1

    Large, under-explored land position

    Access infrastructure in progress

    Feasibility study update completed 17-year mine life Capital cost ~ $3.9B First production: 2017 +210,000 oz Au2; +200Mlb Cu2

    By-product cash costs: ($700)/oz

    El Morro A World Class Project in Mining Friendly Chile

    18

    1Goldcorp interest 70%2 LOM average annual production (70% interest)

  • 8/3/2019 2012 Corporate Update January

    19/33

    9.5 million ounces of Au reserves*

    Life of mine +25 years

    $350 million capital budget for 2012

    First gold mid-2012

    Average annual output 415,000 to450,000 ounces per year* in first fiveyears

    Pueblo Viejo Next New Source of Gold Production

    19

    * Goldcorp interest 40%

  • 8/3/2019 2012 Corporate Update January

    20/33

    Initial resource of 2.7M gold ounces Construction underway:

    - Mine life ~20 years

    - 250,000 - 275,000 ounces Auannually

    - Cash costs < $350 per ounce

    - Capex - $420M

    - First production late 2014

    Cochenour Key Growth Driver in Red Lake District

    20

  • 8/3/2019 2012 Corporate Update January

    21/33

    Shaft widening underway Haulage drift 36% complete

    - 2 rigs actively drilling

    - Exploration potential on untestedground

    Surface exploration with 4 drill rigs

    Installation of headframe surfaceinfrastructure completed andoperational

    Cochenour Construction Progress

    21

  • 8/3/2019 2012 Corporate Update January

    22/33

    22

    High Speed Drift

    Rahill - Bonanza

    Bruce Channel Discovery

    WesternDiscovery

    Zone

    EastWest

    Drift location at end of 2012 Current drif t location

    Red Lake HSD Provides Exciting Exploration Opportunities

  • 8/3/2019 2012 Corporate Update January

    23/33

    Red Lake New Opportunities at Worlds Richest Gold Mine

    Robust, low cost gold production 2012 gold production forecast of

    650,000 ounces

    2012 exploration budget $38M- Focus on High Grade Zone

    extension- Hanging Wall exploration

    success

    District optimization plansadvancing: Cochenour, bulk u/gmining

    23

  • 8/3/2019 2012 Corporate Update January

    24/33

    Peasquito Hitting Stride in 2012

    2012 gold production forecast -

    425,000 ozs at negative cash costs

    Ramp up to full capacity on track forend of Q1 2012

    Largest cash flow generator in 2012

    Average annual production:- 500Koz Au; 204Kt Zn; 90.7Kt Pb;28Moz Ag

    22-year mine life

    24

  • 8/3/2019 2012 Corporate Update January

    25/33

    Peasquito Advancing District Projects

    25

    Camino Rojo Over 77,000 meters drilled in 2011

    Testing oxide & sulphide expansion

    Feasibility study due H1 2012

    Noche Buena

    Resource expansion drillingcontinues

    In-fill drilling on higher grademineralization trends

  • 8/3/2019 2012 Corporate Update January

    26/33

    Delivering Superior Returns

    Goldcorp+627%

    Peers*+266%PhiladelphiaGold / SilverIndex+232%

    Gold Price

    +461%

    Dow Industrials+22%

    * Peers include Barrick, Newmont, Kinross and AgnicoSource: Bloomberg data Dec. 31/01 - Dec. 31/11

    26

    -30%

    70%

    170%

    270%

    370%

    470%

    570%

    670%

    770%

    870%

    2001 2003 2005 2007 2009 2011

  • 8/3/2019 2012 Corporate Update January

    27/33

    Flat mine supply

    - Inflation hedge- Currency protection- Safe haven/asset class

    Why Gold?

    Growing physical demand- Asia- Central bank buying

    Growing investment demand

    Gold Price Has Increased 12 Consecutive Years

    27

  • 8/3/2019 2012 Corporate Update January

    28/33

    28

    Growth Leader Low Cost Producer

    Outstanding Balance

    Sheet

    Low Political Risk

    Responsible Mining

    SUPERIOR

    INVESTMENTPROPOSITION

  • 8/3/2019 2012 Corporate Update January

    29/33

    Appendix A Metals Production (% of Revenues)

    29

    Price assumptions 2012-2016: Au=$1400/oz, Ag=$26/oz, Cu=$3.30/lb, Zn=$0.90/lb, Pb=$0.90/lb

    86% 84% 87%88% 90% 91%

    14% 16% 13%12% 10% 9%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    2011E 2012E 2013E 2014E 2015E 2016E

    Total Precious Metals Base Metals

  • 8/3/2019 2012 Corporate Update January

    30/33

    -

    1,000,000

    2,000,000

    3,000,000

    4,000,000

    5,000,000

    6,000,000

    2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

    GEO actual production

    5.2 Moz

    (Ounces)

    GEO est. production

    Appendix B Increasing GEO Production

    30

  • 8/3/2019 2012 Corporate Update January

    31/33

    CFPS($/share)

    Appendix C 2012 Sensitivities

    31

    Base Price Change

    Increments

    CFPS

    ($/share)

    By Product Cash

    Costs ($/oz)

    FCF

    ($mm)Gold Price ($/oz) $1,600 $100 $0.23 $186

    Silver Price ($/oz) $34.00 $2.00 $0.06 $23 $41

    Copper Price ($/lb) $3.50 $0.50 $0.04 $14 $25

    Zinc Price ($/lb) $0.90 $0.10 $0.04 $15 $28

    Lead Price ($/lb) $0.90 $0.10 $0.02 $8 $15

    Canadian Dollars 1.00 10% $0.04 $17 $118

    Mexican Peso 13.00 10% $0.04 $17 $40

    Diesel ($/barrel) $95.00 10% $0.01 $7 $12

    Electricity ($/kWh) $0.09 10% $0.02 $10 $17

  • 8/3/2019 2012 Corporate Update January

    32/33

    Appendix D Operating Costs Breakdown

    32

    22%

    14%

    7%

    10%

    10%

    15%

    2%

    5%

    4%

    11%

    Consolidated

    Labour Contractors Fuel Costs Power Maintenance Parts Consumables Tires Explosives Site Costs Others

    38%

    19%

    5%

    6%

    9%

    10%

    1%2%

    6%4%

    Canada / USA12%

    14%

    8%

    12%

    9%

    18%

    2%

    6%

    4%

    15%

    Mexico

    18%

    8%

    7%

    14%

    13%

    16%

    1%

    6%

    4%

    13%

    CSA

  • 8/3/2019 2012 Corporate Update January

    33/33

    1. Goldcorp has included non-GAAP performance measures, total cash costs, by-product and co-product, per gold ounce, throughout thispresentation. Total cash costs are defined as cost of sales divided by ounces of gold and silver sold or pounds of copper sold. The calculation

    of total cash costs per ounce of gold is net of by-product sales revenue (by-product copper revenues for Alumbrera; by-product silver revenuesfor Marlin at market silver prices; by-product lead, zinc and 75% of the silver for Peasquito at market silver prices and 25% of the silver forPeasquito at $3.90 per silver ounce sold to Silver Wheaton). The Company reports total cash costs on a sales basis. In the gold miningindustry, this is a common performance measure but does not have any standardized meaning. The Company follows the recommendations ofthe Gold Institute Production Cost Standard. The Company believes that, in addition to conventional measures prepared in accordance withGAAP, certain investors use this information to evaluate the Companys performance and ability to generate cash flow. Accordingly, it isintended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared inaccordance with GAAP. Total cash costs on a by-product basis are calculated by deducting by-product copper, silver, lead and zinc salesrevenues from production cash costs.

    Production costs in 2012 are allocated to each co-product based on the ratio of actual sales volumes multiplied by budget metals prices of$1,600 per ounce of gold, $34 per ounce of silver, $3.50 per pound of copper, $0.90 per pound of lead and $0.90 per pound of zinc, rather thanrealized sales prices.

    2. All Mineral Reserves and Mineral Resources have been calculated as at December 31, 2010 in accordance with the standards of the CanadianInstitute of Mining, Metallurgy and Petroleum and National Instrument 43-101, or the AusIMM JORC equivalent. Cautionary Note to UnitedStates Investors Concerning Estimates of Measured, Indicated and Inferred Resources. United States investors are advised that while suchterms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them.Inferred Mineral Resources have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot beassumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates ofInferred Mineral Resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assumethat all or any part of Goldcorps Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. United States investorsare also cautioned not to assume that all or any part of an Inferred Mineral Resource exists, or is economically or legally mineable. Calculationshave been prepared by employees of Goldcorp, its joint venture partners or its joint venture operating companies, as applicable, under thesupervision of Maryse Belanger, Director Technical Services. Reserve calculations incorporate current and/or expected mine plans and costlevels at each property. Varying cut-off grades have been used depending on the mine and type of ore contained in the reserves. Goldcorpsnormal data verification procedures have been employed in connection with the calculations. For a breakdown of Reserves and Resources by

    category and for a more detailed description of the key assumptions, parameters and methods used in calculating Goldcorps Reserves andResources, see Goldcorps Annual information Form/ Form 40-F on file with Canadian provincial securities regulatory authorities and the U.S.Securities and Exchange Commission.

    3. Goldcorps exploration programs are designed and conducted under the supervision of Charlie Ronkos, Senior Vice-President, Exploration ofGoldcorp. For information on geology, exploration activities generally, and drilling and analysis procedures on Goldcorps material properties,see Goldcorps Annual Information Form/Form 40-F on file with Canadian provincial securities regulatory authorities and the U.S. Securities andExchange Commission.

    Endnotes

    33