2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

download 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

of 43

Transcript of 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    1/43

    City Budget

    2012

    Toronto Police Service

    Capital Budget Program Summary

    The City of Toronto's budget is presented by program and service, inAnalyst Note format. The City's Capital Budget funds major infrastructure.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    2/43

    Page 1

    2012-2021 Capital Program

    ........................................................................ 2

    10-Year Capital Plan Summary (2012 Budget, 2013-2021 Plan) ................................... 3

    10-Year Capital Plan Overview ............................................................................. 5

    10-Year Capital Plan: Operating Impact Summary ............................................. 14

    2012 Capital Budget by Project Category and Funding Source ........................... 16

    2012 Cash Flow & Future Year Commitments ................................................... 17

    2012 Capital Project Highlights ........................................................................ 18

    2012 and Future Year Issues .............................................................................. 20

    Issues Referred to the 2012 Capital Budget Process ......................................... N/A

    2011 Performance .................................................................................... 22

    10-Year Capital Plan Project Summary ..................................................... 24

    2012 Capital Budget; 2013 to 2021 Capital Plan ....................................... 25

    2012 Cash Flow & Future Year Commitments ............................................ 26

    2012 Capital Projects with Financing Details ............................................. 27

    2012 Reserve / Reserve Fund Review ......................................................... 28

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    3/43

    Page 2

    City Council approved the following recommendations:

    1. Council approve the 2012 Capital Budget for the Toronto Police Service with a total

    project cost of $26.827 million, and 2012 cash flow of $57.354 million and future year

    commitments of $16.954 million comprised of the following:

    a) New Cash Flow Funding for:

    i) 15 new/change in scope sub-projects with a 2012 total project cost of

    $26.827 million that requires cash flow of $25.527 million in 2012 and a

    future year commitment of $1.300 million in 2013;

    ii) 4 previously approved sub-projects with a 2012 cash flow of $16.219 million

    and a future year commitment of $10.788 million in 2013 and, $4.866 million

    in 2014;

    b) 2011 approved cash flow for 11 previously approved sub-projects with carry

    forward funding from 2011 and prior years into 2012 totaling $15.608.

    2. Council approve new debt service costs of $0.202 million in 2012 and incremental debt

    costs of $1.413 million in 2013, $2.239 million in 2014, $3.174 million in 2015, and

    $3.991 million in 2016 resulting from the approval of the 2012 Capital Budget, to be

    included in the 2012 and future year operating budgets;

    3. Council approve the 2013-2021 Capital Plan for the Toronto Police Service totaling

    $437.130 million in project estimates, comprised of $28.419 million in 2013, $39.037

    million in 2014, $51.661 million in 2015, $60.971 million in 2016, $51.211 million in

    2017, $57.733 million in 2018, $49.419 million in 2019, $44.833 million in 2020, and

    $53.846 million in 2021, and;

    4. Council consider operating impacts of $0.971 million in 2012, $0.224 million in 2013,

    $1.376 million in 2014, $0.022 million in 2015; and $0.194 million in 2016 emanating

    from the approval of the 2012 Capital Budget for inclusion in the 2012 and future year

    operating budgets.

    5. The Police Service Information Technology Services staff work with City InformationTechnology staff to determine if there are any opportunities to leverage City investments

    with respect to data warehousing and report back to the Deputy City Manager/Chief

    Financial Officer prior to the 2013 Capital Budget Submission.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    4/43

    Page 3

    `

    2012 2013 2014 2015 2016 2012-20165-Year

    Total

    BudgetProjected

    Actual

    Gross Expenditures:

    2011 Capital Budget & Approved FY Commitments 100,946 64,746 24,696 5,916 990 31,602 13%

    Changes to Approved FY Commitments (8,477) 4,872 3,876 271 1%

    2012 New/Change in Scope and Future Year Commitments 25,527 1,300 26,827 11%

    2013 - 2016 Capital Plan Estimates 28,419 39,037 51,661 60,971 180,088 75%

    2-Year Carry Forward for Reapproval

    1-Year Carry Forward to 2012 15,608

    Total Gross Annual Expenditures & Plan 100,946 80,354 41,746 40,507 43,903 51,661 60,971 238,788 101%

    Program Debt Target 44,633 33,339 11,619 20,051 30,443 36,321 131,773

    Financing:

    Debt 44,634 24,666 16,422 23,923 30,442 36,321 131,774 55%

    Reserves/Reserve Funds 32,196 13,926 23,854 18,259 18,654 23,054 97,747 41%

    Development Charges 2,264 1,434 231 1,721 2,565 1,596 7,547 3%

    Recoverable Debt 1,720 1,720 1%

    ISF 9,124

    Provincial/Federal

    Other Revenue 12,728

    Total Financing 100,946 41,746 40,507 43,903 51,661 60,971 238,788 100%

    By Project Category:

    Health & Safety

    Legislated

    SOGR 81,039 36,862 26,998 30,090 44,748 54,075 192,773 81%

    Service Improvement 19,907 4,884 13,509 13,813 6,913 6,896 46,015 19%

    Growth Related

    Total By Project Category 100,946 41,746 40,507 43,903 51,661 60,971 238,788 100%

    Ass et Value - end of each year ( $) 969,163 969,163 969,163 969,163 969,163 969,163

    Yearly SOGR Backlog Estimate (not addressed by current p lan) (1,310) (1,205) (1,066) (765) (731)

    Accumulated Backlog Estimate (end of year) 10,228 8,918 7,713 6,647 5,882 5,151

    Backlog: Percentage of Asset Value (%) 1.1% 0.9% 0.8% 0.7% 0.6% 0.5%

    Debt Service Costs 202 1,413 2,239 3,174 3,991 11,019

    Operating Impact on Program Costs 971 224 1,376 22 194 2,787

    New Positions (4) 1 (3)

    2011

    2012 Re c. Budget and 2013-2016 Plan

    0

    20,000

    40,000

    60,000

    80,000

    100,000

    120,000

    2011 Budget 2011 P rojectedActuals

    2012 Budget 2013Plan

    2014Plan

    2015Plan

    2016Plan

    2011 Carry Forward (into 2012) Gross Expenditure Debt Program Debt Target

    Carry Fwd to '12

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    5/43

    Page 4

    `

    2017 2018 2019 2020 2021 2012-2021

    10-Year

    Total

    Percent

    Gross Expenditures:

    2011 Capital Budget & Approved FY Commitments 31,602 6%

    Changes to Approved FY Commitments 271 1%

    2012 New/Change in Scope and Future Year Commitments 26,827 5%

    2017 - 2021 Capital Plan Estimates 51,211 57,733 49,419 44,833 53,846 437,130 88%

    2-Year Carry Forward for Reapproval

    Total Gross Annual Expenditures & Plan 51,211 57,733 49,419 44,833 53,846 495,830 100%

    Program Debt Target 33,487 36,845 37,131 38,788 38,788 316,812

    Financing:

    Debt 33487 31,757 26,691 23,784 29,321 276,814 55%

    Reserves/Reserve Funds 17,451 24,325 19,567 19,519 24,525 203,134 41%

    Development Charges 273 1,651 3,161 1,530 14,162 3%

    Recoverable Debt 1,720 1%

    ISF

    Provincial/Federal

    Other Revenue

    Total Financing 51,211 57,733 49,419 44,833 53,846 495,830 100%

    By Project Category:

    Health & Safety

    Legislated

    SOGR 48,137 54,108 45,191 41,318 50,560 432,087 87%

    Service Improvement 3,074 3,625 4,228 3,515 3,286 63,743 13%

    Growth Related

    Total By Project Category 51,211 57,733 49,419 44,833 53,846 495,830 100%

    Asset Value - end of each year ($) 969,163 969,163 969,163 969,163 969,163

    Yearly SOGR Backlog Estimate (not addressed by current plan) (247) (241) (338) (385) (274)

    Accumulated Backlog Estimate (end of year) 5,151 4,904 4,663 4,325 3,940 3,666

    Backlog: Percentage of Asset Value (%) 0.5% 0.5% 0.4% 0.4% 0.4%

    Debt Service Costs 4,564 4,226 3,939 3,338 3,137 30,223

    Operating Impact on Program Costs 600 350 (178) 3,559

    New Positions 5 2

    2017 - 2021 Capital Plan

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    2017 Plan 2018 Plan 2019 Plan 2020 Plan 2021 Plan

    2010 Carry Forward (into 2011) Gross Expenditure Debt Program Debt Target

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    6/43

    Page 5

    The strategic direction reflected in the Toronto Police Service's 10-Year Capital Plan

    focuses on improving and updating the Service's aging facility infrastructure, and

    ensuring information and technology needs are appropriately addressed.

    The Toronto Police Service manages an asset inventory valued at over $969.163 million

    based on 2010 replacement cost. Facility assets such as Police facilities, Divisions

    (Stations) and Storage Facilities comprise approximately $683.163 million of the

    Service's total asset inventory value, while equipment, vehicles, radio infrastructure and

    security systems account for the remaining $286,000 million.

    The 10-Year Capital Plan for the Toronto Police Service, excluding carry forward

    funding, totals $495.830 million of which $276.814 million or 55.8% is funded by debt.

    The remaining funding consists of Vehicle and Equipment Reserve funding in the

    amount of $203.134 million or 41.0%, Development Charges funding of $14.162

    million or 2.9% and Recoverable Debt of $1.720 million or 0.3%.

    The 10-Year Capital Plan is in line with the debt affordability targets over the first five

    years, but under target by $40 million in the second five years. The 10-Year Capital

    Plan is below the annual debt target by $8.673 million in 2012, $5.088 million in 2018,

    $10.440 million in 2019, $15.004 in 2020 and $9.467 in 2021, and above the annual

    debt target by $4.803 million in 2013 and $3.872 million in 2014.

    The 10-Year Capital Plan consists of State of Good Repair (SOGR) Projects which

    account for $432.087 million or 87% and Service Improvement Projects which account

    for the remaining $63.743 million or 13%.

    The State of Good Repair (SOGR) backlog for the Toronto Police Service is estimated at

    $10.228 million or 1.1% of the Service's asset value at end of 2011. The 2012 Capital

    Budget and 2013-2021 Capital Plan will provide $48.811 million in funding to address

    SOGR work internal to Police facilities and Divisions (Stations). It is estimated that the

    Service's SOGR backlog will be reduced to $3.666 million or 0.4% of the Service's asset

    replacement value by 2021.

    The 2012-2021 Capital Plan will impact future year Operating Budgets for the Toronto

    Police Service requiring $3.559 million net over the ten-year period. The majority ofthese impacts are attributed to the replacement of the current Records Management

    System (Integrated Records and Information System) project and the Data Warehouse

    Establishment project.

    The 2012 - 2021 Capital Plan includes the replacements of Division 41, 54 and 13 with

    a combined total project cost of $114.604 million, renovations to Divisions 32, 52, 55,

    22 with a total projected cost of $24.577 million, State-of-Good-Repair program at

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    7/43

    Page 6

    $46.811 million, Radio Replacement program at $35.360 million, and a Vehicle

    Replacement program valued at $46.916 million.

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    80,000

    90,000

    1 2 3 4 5 6 7 8 9 10 11

    2011-2020 Approved Capital Plan 81,897 48,411 35,739 39,876 51,037 59,046 51,773 62,297 61,679 85,109

    2012-2021 Capital Budget & Plan 41,746 40,507 43,903 51,661 60,971 51,211 57,733 49,419 44,833 53,846 The 2012 Capital Budget of $41.746 million represents a decrease of $6.665 million or 13.8

    % compared to 2012 Capital Plan estimate of $48.411 million approved in the 2011-2020

    Capital plan. There is a $52.983 million or 10.7% decrease in the 2012 Capital Budget and

    2013-2020 Capital Plan over the nine year period. The key changes to the 10-Year Capital

    Plan as compared to the 2012 2021 Approved Capital Plan are noted below:

    The Progress Avenue (Property & Evidence Management Storage Facility) estimate has

    been revised. The Toronto Police Service had developed an estimate of $15.300 million

    required to house the Property Unit at Progress Avenue. Following the acquisition of the

    Progress site, only $13.900 million remained from the original project estimate for the

    work required. As such, an adjustment of $1.400 million (with no net impact on the total

    capital program) has been made to this project. The adjustment was possible due to the

    deletion of the Smart Card project previously approved in the 2011 2020 Approved

    Capital Plan.

    3 new reserve funded projects were added to the lifecycle replacement program (FleetEquipment, CCTV and AED-Defibrillators) at a cost of $2.241 million along with a budget

    increase of $3.160 million to the In-Car Camera Replacement program. The additional

    reserve funding requirements have been accommodated through various reductions in

    other lifecycle replacement projects.

    In conjunction with City Court Services, the Toronto Police Service will be implementing

    the eTicketing Solution for Provincial Offence Notices project. Project costs of $1.720

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    8/43

    Page 7

    million will be repaid by future operational savings primarily in City Court Services over

    the next two-and-a-half years.

    Funding for the Integrated Records and Information System (IRIS) has been deferred due

    to a delay in the decision on software acquisition. This has resulted in a revised cash flow

    for the project with no net increase to the project's cost.

    2012 2013 2014 2015 2016 2017 2018 2019 2020 2012-2020

    Project

    Changes

    Total

    2012-2021

    Forecast

    State-of-Good-Repair - Police 40,701 761 (164) (305) 81 439 3 29 (0) 28 871 41,572

    Radio Replacement 5,371 0 0 0 0 0 0 0 0 0 0 5,371

    14 Division - Central Lockup 8,910 0 0 0 0 0 0 0 0 0 0 8,910

    Progress Site (Property & Evidence) 10,465 0 1,300 0 0 0 0 0 0 (2,035) (736) 9,729

    IRIS - Police Operations Mgmt Syst em Impl'n 14,373 (8,674) 4,803 3,871 0 0 0 0 0 0 0 14,373

    Upgrade to Microsoft 7 160 0 0 0 0 0 0 0 0 0 0 160

    54 Division (includes land) 36,446 0 0 0 0 0 0 0 0 0 0 36,446

    Data Warehouse Est ablishment 8,204 0 (336) 336 0 0 0 0 0 0 0 8,204

    Electronic Document Management 490 0 0 0 0 0 0 0 0 0 0 490

    HRMS Upgrade 836 0 0 0 0 0 0 0 0 0 0 836

    TRMS Upgrade 3,413 0 0 0 0 0 0 0 0 0 0 3,413

    Digital Content Manager 3,033 0 0 0 0 0 0 0 0 0 0 3,033

    41 Division (includes land) 39,079 0 0 0 0 0 0 0 0 0 0 39,079

    Expansion of Fibre Opt ics Network 12,051 0 0 0 0 0 0 0 0 0 0 12,051

    Radio Replacement 23,806 0 0 0 0 0 1 0 0 (27) (27) 23,779

    13 Division (includes land) 39,079 0 0 0 0 0 0 0 (1,507) 1,507 (0) 39,079

    AFIS (next rep lacement) 3,053 0 0 0 0 0 0 0 0 0 0 3,053

    Long Term Facility Plan (Divisions 32, 52 55, 22) 9,159 0 0 0 0 0 0 0 881 2,035 2,916 12,075

    eTicketing Solution 0 1,719 0 0 0 0 0 0 0 0 1,719 1,719

    Vehicle and Equipment (LR) 42,748 (64) (66) (112) (135) (133) (135) (135) (146) (226) (1,152) 41,596

    Workstation, Laptop, Printer (LR) 29,173 (50) (63) 617 (60) 232 (684) 391 339 341 1,063 30,236

    Servers (LR) 41,313 (75) (79) (74) (75) (78) (80) (75) (83) (12,906) (13,525) 27,788

    IT Business Resumption (LR) 20,677 (39) (41) (31) (38) (40) (42) (32) (42) (6,430) (6,735) 13,942

    Mobile Workstations (LR) 18,149 (3) (69) (14) 0 0 (3) (70) (17) 0 (176) 17,973

    Network Equipment (LR) 16,365 (12) (62) (28) (25) (12) (63) (29) (28) (5,372) (5,631) 10,734

    Locker Replacement (LR) 979 243 (2) (2) (2) 249 (2) (2) (2) 103 583 1,562

    Furniture Replacement (LR) 11,132 (30) (15) (15) (15) (30) (16) (16) (17) (2,293) (2,447) 8,685AVL (LR) 2,434 (15) 0 (8) (14) (15) 0 0 0 (7) (59) 2,375

    In - Car Camera (LR) 2,970 0 (11) (7) 1,051 1,138 0 657 105 227 3,160 6,130

    Voice Logging (LR) 1,954 0 (6) 0 (9) (6) 0 (6) 0 (16) (43) 1,911

    Electronic Surveillance (LR) 1,089 0 0 0 0 (20) 0 0 0 0 (20) 1,069

    Digital Photography (LR) 378 0 0 0 (3) (3) 0 0 0 (5) (11) 367

    DVAM I (LR) 2,178 0 0 0 (27) 0 0 0 (1,101) 1,071 (57) 2,121

    Voicemail / Call Centre (LR) 618 0 0 0 (6) 0 500 0 (312) 306 488 1,106

    DVAM II (LR) 2,782 0 0 (173) 0 0 0 0 (143) 0 (316) 2,466

    Asset and Inventory Mgmt.System (LR) 126 0 0 0 0 (3) 0 0 0 0 (3) 123

    Property & Evidence Scanners (LR) 119 0 0 0 0 (2) 0 0 0 0 (2) 117

    DPLN (LR) 1,527 0 (256) 0 0 0 0 (71) 0 0 (327) 1,200

    Small Equipment (e.g. t elephone handset) (LR) 2,715 59 59 (290) (291) (297) (303) (309) (316) (327) (2,015) 700

    Video Recording Equipment (LR) 0 92 92 92 92 92 92 92 92 92 828 828

    Livescan Machines (LR) 431 0 0 0 0 (8) 0 0 0 0 (8) 423

    Wireless Parking Syst em (LR) 2,971 0 0 0 0 (55) 0 0 0 0 (55) 2,916

    CCTV 0 0 182 70 0 182 70 0 182 70 756 756

    AEDs 0 0 195 0 0 195 0 0 195 0 585 585

    Future Use of P rogress Site 32,040 0 0 0 0 0 0 (5,088) (10,440) (16,512) (32,040) 0

    Smart Card 1,471 (678) (793) 0 0 0 0 0 0 0 (1,471) 0

    Fleet Equipment 0 100 100 100 100 100 100 100 100 100 900 900

    4 94 ,9 67 (6,66 6) 4 ,7 68 4,02 6 6 24 1,92 5 (5 63 ) (4 ,5 64 ) (1 2,26 0) (40 ,2 77 ) (5 2,98 6) 44 1,98 1

    Project ($000s)2011Total

    Project Cost

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    9/43

    Page 8

    $0

    $10,000

    $20,000

    $30,000

    $40,000

    $50,000

    $60,000

    $70,000

    2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

    Service

    Improvement

    SOGR

    The 10-Year Capital Plan provides for $432.087 million in State of Good Repair projects and

    $63.743 million in Service Improvement projects.

    State of Good Repair (SOGR) Projects account for $432.087 million or 87% of the 10-

    Year Capital Plan, and primarily focus on continued improvement and upgrading of the

    Service's aging facilities. Also included within the scope of SOGR work are information

    technology upgrades and the Radio Replacement projects. Details of the 10-year SOGR

    work is as follows:

    $157.822 or 36.5% of all SOGR projects is required for facility rehabilitation and

    replacement,

    Information Technology related projects account for 27.9% or $120.470 million of

    the 2012 -2021 SOGR projects costs,

    Other SOGR projects account for $153.795 million which consist of the Radio

    Replacement project ($35.360 million), the Vehicle and Equipment Lifecycle

    project ($46.8916 million), the State of Good Repair project ($46.811 million) and

    various other SOGR projects ($24.708 million).

    Service Improvement projects account for $63.743 million or 13% of the 10-Year

    Capital Plan and include the following projects:

    Acquisition and implementation of a new Record Management System (IRIS) at

    $14.373 million,

    $33.422 million for new workstations, printers and laptops,

    Digital Content Manager System at $3.033 million,

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    10/43

    Page 9

    $8.204 for the Data Warehouse Establishment project,

    eTicketing Solution for Provincial Offence Notices project at $1.720 million,

    other various Service Improvement Projects totalling $2.991 million.

    $0

    $10,000

    $20,000

    $30,000

    $40,000

    $50,000

    $60,000

    $70,000

    2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

    Recoverable Debt

    Development

    ChargesReserve/Reserve

    FundsDebt / CFC

    The Toronto Police Service's 10-Year Capital Plan is primarily funded by debt and

    reserve funds. $276.814 million or 56% of the $495.830 million 10-Year Capital Plan

    is funded by debt, while $203.134 million or 41% will be funded from Reserve Funds,$14.162 million and $1.720 million will be funded from Development Charges and

    Recoverable Debt respectively.

    Debt funding is primarily driven by facility related projects as the Service updates

    its aging infrastructure.

    The 10-Year Capital Plan is in line with the debt affordability targets over the first

    five years, but under target by $40 million in the second five years of the 10-Year

    Capital Plan.

    The 2012-2021 Capital Plan is below the annual debt target by a total of $8.673

    million in 2012, $5.088 million in 2018, $10.440 million in 2019, $15.004 in

    2020 and $9.467 in 2021, and above the annual debt target by $4.803 million in

    2013 and $3.872 million in 2014.

    The Vehicle & Equipment Reserve continues to fund lifecycle replacement projects.

    This allows the Service to replace equipment through their Capital Budget without

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    11/43

    Page 10

    requiring debt financing. Fluctuations in Reserve funding reflect the timing of

    lifecycle replacement projects.

    Development Charges funding of $14.162 million is being utilized in the 10-Year

    Capital Plan for various facility related projects. This level of funding maximizes

    the contribution from existing Reserve Funds established under the previous DC

    By-Law and is in line with forecasted DC recoveries under the current By-Law.

    Expanded Division facilities are partially funded by Development Charges.

    Recoverable Debt is being used to fund the eTicketing Solution for Provincial

    Offence Notices project. Operational savings of $1.480 million within City Court

    Services, arising from this Service Improvement project, will be applied to service

    the debt within two-and-a-half years with no impact on the City s debt

    affordability target.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    12/43

    Page 11

    Total Project

    Cost

    2012 Rec.

    Budget

    2013

    Plan

    2014

    Plan

    2015

    Plan

    2016

    Plan

    2017

    Plan

    2018

    Plan

    2019

    Plan

    2020

    Plan

    2021

    Plan

    2012-2021

    Total

    State of Good Repair (incl. H&S , & Leg.)

    - 14 Division - Central Lockup 35,515 8,910 8,910

    - Progress Site (Property & Evidence 37,068 7,149 2,581 9,730- 54 Division 36,946 9,060 21,665 5,721 36,446

    - 41 Division 39,079 372 8,564 20,636 9,507 39,079

    - 13 Division 39,079 372 8,645 19,903 10,159 39,079

    - Servers 47,351 3,060 3,164 2,958 2,998 3,121 3,228 3,017 3,058 3,184 3,292 31,080

    - Vehicles & Equipment 95,164 2,627 2,627 4,422 5,320 5,320 5,320 5,320 5,320 5,320 5,320 46,916

    - State-of-Good-Repair 46,810 4,510 4,565 4,594 4,469 4,621 4,331 4,529 4,841 5,113 5,238 46,811

    - Furniture Lifecycle Replacement 11,677 1,426 713 713 713 1,455 727 727 727 1,484 742 9,427

    - Police Radio Comm Syatem Replacement 28,389 5,371 5,371

    - Police Radio Comm Syatem Replacement (2016-2020) 35,360 10,193 2,836 4,622 1,174 4,954 11,581 35,360

    - AFIS Replacement 3,053 3,053 3,053

    - Fibre Optics 12,051 881 5,585 5,585 12,051

    - Wireless Parking System 8,808 2,916 2,916 5,832

    - Livescan Replacement 1,277 423 431 854

    - Time Resource Management System 3,413 1,943 1,470 3,413

    - Human Resource Management System 837 155 682 837

    - Replacement of DVAMS I 3,230 1,050 1,071 2,121

    - 32 Division 6,987 3,052 3,934 6,986

    - 52 Division 8,300 3,559 4,741 8,300

    - 55 Division 8,000 1,529 6,471 8,000- 22 Division 8,000 1,290 1,290

    - IT Business Resumption 25,788 1,612 1,669 1,269 1,522 1,644 1,702 1,294 1,553 1,677 1,736 15,678

    - Locker Replacement 3,811 417 47 47 47 426 48 48 48 434 49 1,611

    - Mobile Workstation 25,788 240 7,214 1,443 245 7,359 1,472 17,973

    - Network Equipment 17,588 493 2,466 1,104 998 502 2,515 1,126 1,018 512 2,565 13,299

    - AVLS Replacement Lifecycle 3,841 605 299 562 604 305 573 2,948

    - In-Car Camera Replacement 7,268 657 788 1,051 1,138 657 788 1,051 1,138 7,268

    - Voice Logging Lifecycle Replacement 3,006 353 437 315 360 446 321 2,232

    - Electronic Surveillance Lifecycle Replacement 3,230 1,069 1,091 2,160

    - Digital Photography Lifecycle Replacement 748 119 126 122 128 495

    - Voicemail/Call Centre 1,421 300 500 306 1,106

    - DVAMS - II Lifecycle Replacement 2,466 1,203 1,263 2,466

    - Asset and Inventort Management System Replacement 372 123 126 249

    - Property and Evidence Scanners Lifecycle 353 117 119 236

    - DPLN Replacement 1,200 500 700 1,200

    - Small Equipment Replacement 1,754 442 442 92 92 92 92 92 92 92 692 2,220

    Sub-Total 615,028 36,862 26,998 30,090 44,748 54,075 48,137 54,108 45,191 41,318 50,560 432,087

    Service Improvements

    - IRIS Police Operations Mgmt System Impl'n 24,420 9,507 4,866 14,373- Workstations, Printer, Laptops 57,335 2,904 3,525 3,751 3,345 3,186 2,904 3,525 3,751 3,345 3,186 33,422

    - Electronic Document Management 490 49 441 490

    - Digital Content Manager 3,033 1,360 1,673 3,033

    - Data WarehouseEstablishment 8,204 3,617 1,354 3,233 8,204

    - eTicketing 1,720 1,720 1,720

    - Upgrade to Microsoft 7 1,652 160 160

    - CCTV 756 182 70 182 70 182 70 756

    - AED's 585 195 195 195 585

    - Fleet Equipment 1,000 100 100 100 100 100 100 100 100 100 100 1,000

    Sub-Total 99,195 4,884 13,509 13,813 6,913 6,896 3,074 3,625 4,228 3,515 3,286 63,743

    Total 714,223 41,746 40,507 43,903 51,661 60,971 51,211 57,733 49,419 44,833 53,846 495,830

    The 2012 Capital Budget and 2013-2021 Capital Plan reflects the Toronto Police Service

    strategic direction to improve and update its aging infrastructure to support key service

    priority needs.

    The 10-Year Capital Plan is primarily allocated to State of Good Repair facility projects

    totalling $432.087 million, as the Service continues to focus on improving and

    updating its aging facility infrastructure. This includes the completion of 14 Division in

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    13/43

    Page 12

    2012 and the Property and Evidence Management Storage Facility in 2013, as well as

    the commencement of 54 Division in 2014, 41 Division in 2015 and 13 Division in

    2017. Renovations will also be undertaken commencing in 2018 on 32 Division, in

    2020 on 52 Division and 55 Division, and in 2021 on 22 Division.

    The Service's Radio Replacement (2016-2021) project requires funding of $35.360

    million during the 2016-2021 period. This project supports the next life-cycle

    replacement of communication radios as well as continuing to ensure operability of the

    new shared EMS, Toronto Fire and Toronto Police Service platform.

    The lifecycle replacement of Vehicles, Equipment and Servers is fully funded from the

    Vehicle & Equipment Reserve, which funds 41% of the 10-Year Capital Plan.

    Contributions to this Reserve are made through the Toronto Police Service Operating

    Budget.

    The 10-Year Capital Plan includes $14.373 million for the replacement of the current

    Records Management System (Integrated Records and Information System Project).

    Since its implementation in 2003, several deficiencies with the current system (eCOPS)

    have been identified. The replacement of this system with a commercial-off-the-shelf

    solution has been at a cost of $24.420 million, with anticipated completion by 2014.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    14/43

    Page 13

    0.0%

    0.5%

    1.0%

    1.5%

    2.0%

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

    SOGR Funding Accumulated Backlog Estimate ( end of year) Backlog % of Asset Value

    The current State Of Good Repair backlog for the Toronto Police Service is estimated at

    $10.228 million by the end of 2011, representing a increase of $1.032 million or 11% from

    the $9.196 million in backlog identified in the 2011 Approved Capital Budget.

    The current SOGR backlog represents 1.1% of the Service's total asset replacement value

    of $969.163 million.

    The Service projects an annual increase in new SOGR requirements of $3.200 million for

    internal renovations and upgrades to various Police facilities and Police Divisions across

    the City.

    The 10-Year Capital Plan provides $46.811 million for State of Good Repair work

    internal to Police facilities and Divisions and represents 9.4 % of cash flow in the 10-

    Year Capital Plan.

    SOGR Backlogs consists of unaddressed projects relating to the on-going internal

    maintenance and repair of Police-occupied buildings. The scope of works include major

    renovations (e.g. flooring replacement, window coverings, painting) and Occupational

    Health & Safety renovations.

    SOGR work on the exterior of Police Service buildings is included in Facilities

    Management Capital Budget.

    The backlog will be reduced to $5.151 million or 0.5% of the Service's total asset value

    by the end of 2016. It is estimated that the Service's SOGR backlog will be further

    reduced by 2021 to $3.666 million or 0.4% of the Services asset value.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    15/43

    Page 14

    2012

    Budget

    2013

    Plan

    2014

    Plan

    2015

    Plan

    2016

    Plan

    2017

    Plan

    2018

    Plan

    2019

    Plan

    2020

    Plan

    20201

    Plan

    2012-

    2021

    Total

    2012 Capital Budget

    Program Cost (Net) 971 24 218 (497) 716Approved Positions (4) (4)

    10-Year Capital Plan

    Program Cost (Net) 200 1,158 519 194 600 350 (178) 2,843

    Approved Positions 1 5 6

    Total

    Program Cost (Net) 971 224 1,376 22 194 600 350 (178) 3,559

    Approved Positions (4) 1 5 2

    The 10-Year Capital Plan will result in a future year Operating Budget impact of $3.559

    million net for the Toronto Police Service of over the ten-year period. The majority of these

    impacts are attributed to the following:

    Incremental operating costs totaling $0.971 million will be required in 2012, comprisedof $0.328 million for the September 2011 occupancy of 11 Division Facility, $0.373

    from the third quarter 2012 completion and occupancy of Division 14 facility, $0.050

    million for building operations and utilities at the Progress Avenue site, $0.035 million

    for the maintenance of Microsoft 2007 upgrades, $0.025 million for maintenance of

    911 Hardware/Handsets, and $0.160 for maintenance of the Voice Mail/Call Centre

    operating costs.

    The Replacement of the current Records Management System will result in incremental

    operating costs of $0.200 million in 2013 and an additional $1.655 million in 2014 for

    increased maintenance costs and lifecycle contributions.

    eTicketing Solution for Provincial Offences Notices will see incremental increases in

    operating costs of $0.073 in 2013, $0.218 in 2015. Annualized operating costs of

    $0.560 million for overall maintenance and planned equipment replacement costs will

    be offset by annualized savings of $0.269 million in the Service related to staff

    reductions in Document Services. It should be noted that additional costs of the

    eTicketing project to the Toronto Police Service will be offset with savings contained in

    the City Court Services future operating budgets once these savings retire debt costs

    arising from the project after two-and-a-half years.

    An incremental impact of $1.056 million in 2017 has also been identified for the Data

    Warehouse Establishment project. This project will integrate all silo data and databases

    to a corporate Data Warehouse environment and reduce the time users spend in the

    search, acquisition and understanding of data results. The operating costs include

    $0.600 million for 5 positions to sustain the new Data Warehouse environment and

    $0.456 million for system maintenance.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    16/43

    Page 15

    There are no temporary Capital Project positions required for the delivery of the

    Toronto Police Service 2012 2021 Capital Program. Information technology projects

    are delivered by existing staff or contracted services.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    17/43

    Page 16

    The 2012 Capital Budget, excluding carry forward funding from 2011 to 2012, required new

    cash flow funding of $41.746 million

    State of Good Repair projects account for $36.861 million or 88% of the 2012 Capital

    Budget. SOGR projects focuses on improving and updating the Service's aging facility

    infrastructure, and ensuring information and technology needs are appropriately

    addressed.

    Service Improvement projects account for the remaining $4.884 million or 12% of the

    2012 Capital Budget and include such key projects as the Acquisition and

    Implementation of eTicketing Solution for Provincial Offences project, funding for Fleet

    and Equipment, upgrading workstations, printers and laptops, and upgrading to the

    Microsoft 7 operating system.

    The 2012 Capital Budget is primarily funded by debt and reserve funds. $24.666

    million or 59% of the 2012 Capital Budget is funded by debt, while $13.926 million or

    33% is funded from the Vehicle & Equipment Reserve, $1.434 million or 4% is funded

    from Development Charges and $1.720 million or 4% from Recoverable Debt.

    The 2012 Capital Budget for the Toronto Police Service is $8.673 million below the

    $33.339 million debt affordability target set by the City for 2012. This is the result of

    deferral of the Integrated Records and Information System (IRIS) project to 2012

    2014.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    18/43

    Page 17

    2010 &

    Prior Year

    Carry

    Forward

    2012 Previously

    Approved Cash

    Flow

    Commitments

    2012 New

    Cash Flow

    2012 Total

    Cash Flow

    2011 Carry

    Forwards

    Total 2012

    Cash Flow

    (Incl 20 10

    C/Fwd)

    2013 2014 2015 2016 2017 2018 2019 2020 2021 Total Cost

    Expenditures

    Previously Approved 16,219 16,219 15,608 31,827 10,788 4,866 47,481

    Change in Scope 1,300 1,300

    New 7,091 7,091 7,091 7,091

    New w/Future Year 18,436 18,436 18,436 18,436

    Total Expenditure0 16,219 25,527 41,746 15,608 57,354 12,088 4,866 74,308

    Financing

    Debt 14,554 10,112 24,666 11,411 36,077 11,857 4,866 52,800

    Other

    Reserves/Res Funds 13,695 13,695 4,197 17,892 17,892

    Development Charges 1,665 1,665 1,665 231 1,896

    Recoverable Debt 1,720 1,720 1,720 1,720

    Provincial/Federal

    Total Financing 0 16,219 25,527 41,746 15,608 57,354 12,088 4,866 74,308

    *Please refer to Appendix 4 for detailed project listings

    The Toronto Police's 2012 Capital Budget of $57.354 million including carry forward

    funding from 2011 to 2012 provides funding of $16.219 million for previously approved

    projects, $25.527 million for new/change of scope projects and $15.608 million for

    2011 projects carried forward into 2012 for completion. Included are several large

    projects such as the Integrated Records and Information System, IT-related replacement

    projects, and the Automated Fingerprint Identification System.

    The 2012 Capital Budget will be financed by debt of $36.077 million (62.9%), reserve

    funds of $17.892 million (31.2%), Development Charges of $1.665 million (2.9%) and

    Recoverable Debt funding of $1.72 million (3.0%).

    Approval of the 2012 Capital Budget will result in commitments to future year cash flow

    funding of $12.108 million in 2013 and $4.866 million in 2014 to complete multi-year

    projects is noted in following table.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    19/43

    Page 18

    Project

    Total

    Project

    Cost 2012 2013 2014 2015 2016

    2012 -

    2016 2017 2018 2019 2020 2021

    2012 -

    2021

    State-of-Good-Repair - Police 46,810 4,510 4,510 4,510

    11 Divison 39,579 500 500 500

    Radio Replacement 28,389 5,371 5,371 5,371

    14 Division - Central Lockup 35,515 9,909 9,909 9,909

    Progress Site (Property & Evidence) 37,068 7,149 2,581 9,729 9,729

    IRIS - Police Operations Mgmt System Impl'n 24,420 7,933 9,507 4,866 22,306 22,306

    Upgrade to Microsoft 7 1,652 160 160 160

    eTicketing Solution 1,719 1,720 1,720 1,720

    Vehicle and Equipment (LR) 95,164 2,627 2,627 2,627

    Workstation, Laptop, Printer (LR) 57,335 3,322 3,322 3,322

    Servers (LR) 47,351 4,101 4,101 4,101

    IT Business Resumption (LR) 25,788 2,881 2,881 2,881

    Voicemail/Call Centre 1,421 315 315 315

    Asset and Inventory Management Replacement 372 123 123 123

    Livescan Replacement 1,277 423 423 423

    Automated Fingerprint Identification System 3,053 1,979 1,979 1,979

    Mobile Workstations (LR) 25,943 240 240 240

    Network Equipment (LR) 17,588 493 493 493

    Locker Replacement (LR) 3,811 417 417 417

    Furniture Replacement (LR) 11,677 1,426 1,426 1,426

    AVL (LR) 3,841 1,213 1,213 1,213

    Small Equipment (e.g. telephone handset) (LR) 1,754 350 350 350

    Video Recording Equipment (LR) 1,058 92 92 92

    Fleet Equipment 1,000 100 100 100

    Total (including carry forward) 57,353 12,088 4,866 74,307 74,307

    The 2012 Capital Budget provides funding of $57.354 million to:

    Complete construction of the 14 Division; Construction is well underway for the new 14

    Division facility at 11 St. Annes Road.

    The facility has been designed and will be constructed to meet the requirements

    for LEED-Silver certification.

    Substantial construction completion is expected to be achieved in June 2012, with

    the move-in anticipated for the third quarter of 2012.

    Implement the Integrated Records and Information System; The IRIS project provides

    funding for a commercial off-the-shelf (COTS) integrated records and information

    system.

    At its October 21, 2011 meeting, the Board approved Versaterm as the vendor for

    this project. As a result of the deferral of vendor approval, only $1.4M is projected

    to be spent in 2011 and the rest will be carried forward to 2012.

    The projects timelines have been adjusted to accommodate this deferral, and a

    revised cash flow for the project has been included in years 2012-2014.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    20/43

    Page 19

    Undertake renovations of 330 Progress Avenue for the Property & Evidence

    Management Storage Facility; Construction work will commence in 2012 to house the

    Property & Evidence Management Unit (PEMU) on the Progress Avenue site.

    The original total cost estimate for the project was $35.7 million. Included in this

    estimate was a preliminary cost estimate of $15.3 million for the construction

    work required to house the PEMU.

    After acquisition of the Progress property, only $13.9 million remained in the

    project budget to complete the required construction work. An adjustment of $1.4

    million has been made to this project to better reflect the estimated cost for this

    project. The increase was accommodated by the deletion of the Smart Card project

    previously identified in the Capital Plan.

    The design process is currently underway and is expected to be complete by year-

    end 2011. The process for retaining the services of a construction management

    firm is also underway.

    It is expected that the design phase and tendering process will be complete so

    that construction can commence in 2012.

    Undertake the eTicketing Solution for Provincial Offence Notices;

    In conjunction with City Court Services, the Toronto Police Service is implementing

    eTicketing Solution for Provincial Offence Notices project with project costs of

    $1.720 million to be fully recovered by 2015 from future operational savings

    primarily in City Court Services.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    21/43

    Page 20

    eTicketing Solution for Provincial Offence Notices

    During the 2010 Budget process Council directed that the Toronto Police Service and

    City Court Services, in consultation with the Deputy City Manager and Chief Financial

    Officer, further review the capital and operating costs and the potential savings of an

    eTicketing Solution for Provincial Offence Notices prior to the 2011 Capital Budget

    process.

    In 2011 the Toronto Police Service and Court Services reviewed the capital costs and

    potential operating savings to determine the Business Case for an eTicketing Solution

    and reported to the Deputy City Manager and CFO any changes in estimated costs and

    Court Services' debt repayment schedule prior to the submission of the 2012-2021

    Capital Plan.

    This project was originally estimated to cost $4.300 million over three years (2012

    2014). As a result of the decision to proceed with the Versaterm records management

    system (IRIS project), the eTicketing capital costs have been reduced to $1.720 million

    (2012).

    The project has a net overall payback of two-and-a-half years to the City. Annualized

    operating costs of $0.562 million (for overall maintenance and planned equipment

    replacement costs) will be offset by annualized savings of $1.751 million ($0.271million savings in the Police Service related to staff reductions in Document Services

    and $1.480 million savings in City Court Services from increased revenues and reduced

    costs) once the savings are used to fully repay the debt servicing costs for this project.

    Integrated Records and Information System (IRIS)

    As a result of the deferral of vendor selection for the Integrated Records and

    Information System , the IRIS project is expected to be under spent in 2011 by $7.933

    million which will be carried forward to 2012.

    The projects timelines have been adjusted to accommodate the deferral, and a revised

    cash flow for the project has been included in the Services 2012 2021 capital

    program.

    These cash flow requirements result in variances from the City debt targets in three

    years. The Capital Plan is under the debt target by $8.7 million in 2012; over target by

    $4.8 million in 2013; and over target by $3.9 million in 2014.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    22/43

    Page 21

    Data Warehouse Project

    $8.204 million for the Data Warehouse Establishment project is contained in years

    2014-2016 of the Police Service's 10-Year Capital Plan. This project has been

    identified as a key Service requirement for several years, and has been deferred due to

    funding availability.

    This project will fund the building of a corporate Integrated Database (DB) and Data

    Warehouse (DW) with Business Intelligence (BI) to re-engineer the corporate business

    processes, information requirements and decision-making process. It will integrate all

    silo data and databases into a corporate DW environment, and reduce the time users

    spend in the search, acquisition, and understanding of data results.

    This project has an ongoing operating budget impact of $1.056 million annually,

    requiring 5 new staff commencing in 2017 at a cost of $0.600 million, and system

    maintenance costs of $0.456 million when operational.

    As similar technology investments are being considered by the City, it is that the Police

    Service Information Technology Services staff work with City Information Technology

    staff to determine whether the City's technology could be leveraged by the Police

    Service and report back to the Deputy City Manager/Chief Financial Officer prior to the

    2013 Capital Budget Submission.

    Future Use of 330 Progress Avenue

    The City's acquisition of 330 Progress Avenue for the Police Service Property and

    Evidence facility also provided open space for additional other uses. There are no

    projects for additional uses of this site included in the 2012-2021 Police Service 10-

    Year Capital Plan. Once specific uses are outlined and project details developed,

    including operating costs and savings, consideration can be given to including them

    in a future 10 Year Capital Plan.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    23/43

    Page 22

    Key accomplishments and developments related to the implementation and management of

    the Services capital program in 2011 are as follows:

    New 11 Division was completed on budget with move-in on September 26, 2011.

    In-Car camera installations have been completed on budget in 415 marked cars.

    Voicemail replacement will be completed utilizing Voice over Internet Protocol (VoIP)

    based on the Citys review and recommendation for use of VoIP.

    Replacement of the Automated Fingerprint Identification System (AFIS) has commenced

    in 2011 and is scheduled for completion in 2012.

    Construction for the new 14 Division is continuing and is expected to be finished by

    mid-2012.

    An architectural firm has been approved by the Board to complete the design and

    working drawings for the Services new Property and Evidence Management Facility.

    2011 Approved

    $ $ % Spent $ % Spent $ % Unspent

    100,946 33,104 32.8% 64,746 64.1% 36,200 35.9%

    Actuals as of September 30th

    (3nd Qtr Variance)Projected Actuals at Year End Unspent Balance

    Capital expenditures for the period ended September 30, 2010 totalled $33.104 million or

    32.8% of the 2011 Approved Capital Budget of $100.947 million. The Toronto Police Serviceis projecting year-end spending of $64.746 million or 64.1% of its 2011 Approved Capital

    Budget. The projected year-end under-spending of $36.200 million is primarily the result of

    the following:

    The Property & Evidence Management Facility project will be $5.371 under-spent. This

    funding will be carried forward to 2012.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    24/43

    Page 23

    It is expected that $15.802 million of the $20.764 million in approved cash flow for 14

    Division will be spent in 2011, with $4.962 million to be carried forward in 2012 to

    complete construction of the facility. Substantial construction completion is expected

    to be achieved in June 2012 with move-in anticipated for the third quarter 2012.

    As a result of the deferral of vendor selection for the Integrated Records and

    Information System, the IRIS project is expected to be under-spent by $7.933, million

    which will be carried forward to 2012. The projects timelines have been adjusted to

    accommodate the deferral, and a revised cash flow for the project has been included in

    the Services 2012-2021 Capital Plan.

    It is expected that of the approved $2.827 million cash flow funding for the Automated

    Fingerprint Identification System (AFIS), $0.644 million will be spent in 2011. $2.183

    million will be carried forward to 2012.

    $12.088 million in under-spending for Vehicle and Equipment Lifecycle Replacements.

    The projected under-spending in 2011 is primarily due to timing of acquisition of

    server replacements, cashflow deferrals for vehicle replacements and the re-issuance

    of the Request for Proposal for the replacement of the Wireless Parking System.

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    25/43

    Page 24

    Total Total

    2012 2013 2014 2015 2016 2012-2016Request

    2017 2018 2019 2020 2021 2017-2021Forecast

    State-of-Good-Repair - Police 4,510 4,565 4,594 4,469 4,621 22,759 4,331 4,529 4,841 5,113 5,238 24,051

    Radio Replacement 5,371 5,371

    14 Division - Central Lockup 8,910 8,910

    Progress Site (Property & Evidence) 7,149 2,581 9,729

    IRIS - Police Operations M gmt Syst em Impl'n 9,507 4,866 14,373

    Upgrade to Microsoft 7 160 160

    54 Division (includes land) 9,060 21,665 5,721 36,446

    Data Warehouse Establishment 3,617 1,354 3,233 8,204

    Electronic Document Management 49 441 490

    HRMS Upgrade 155 682 836

    TRMS Upgrade 1,943 1,470 3,413

    Digital Content M anager 1,360 1,673 3,033

    41 Division (includes land) 372 8,564 8,937 20,636 9,506 30,142

    Expansion of Fibre Optics Network 881 5,585 6,466 5,585 5,585

    Radio Replacement 10,193 10,193 2,836 4,622 1,174 4,954 11,581 25,167

    13 Division (includes land) 372 8,645 19,903 10,159 39,079

    AFIS (next replacement) 3,053 3,053

    32 Division - Renovation 3,053 3,934 6,98752 Division - Renovation 3,559 4,741 8,300

    55 Division - Renovation 1,529 6,471 8,000

    22 Division - Renovation 1,290 1,290

    eTicketing Solution 1,719 1,719

    Vehicle and Equipment (LR) 2,627 2,627 4,422 5,320 5,320 20,316 5,320 5,320 5,320 5,320 5,320 26,600

    Workstation, Laptop, Printer (LR) 2,904 3,525 3,751 3,345 3,186 16,711 2,904 3,525 3,751 3,345 3,186 16,711

    Servers (LR) 3,060 3,164 2,958 2,998 3,121 15,301 3,228 3,017 3,058 3,184 3,292 15,779

    IT Business Resumption (LR) 1,612 1,669 1,269 1,522 1,644 7,716 1,702 1,294 1,553 1,677 1,736 7,962

    Mobile Workstations (LR) 240 7,214 1,443 8,897 245 7,359 1,472 9,076

    Network Equipment (LR) 493 2,466 1,104 998 502 5,563 2,515 1,126 1,018 512 2,565 7,736

    Locker Replacement (LR) 417 47 47 47 426 984 48 48 48 434 49 627

    Furniture Rep lacement (LR) 1,426 713 713 713 1,455 5,020 727 727 727 1,484 742 4,407

    AVL (LR) 605 0 299 562 604 2,070 305 573 878

    In - Car Camera (LR) 657 788 1,051 1,138 3,634 657 788 1,051 1,138 3,634

    Voice Logging (LR) 353 437 315 1,105 360 446 321 1,127

    Electronic Surveillance (LR) 0 1,069 1,069 0 1,091 1,091

    Digital Photography (LR) 119 126 245 122 128 250

    DVAM I (LR) 1,050 1,050 1,071 1,071

    Voicemail / Call Centre (LR) 300 300 500 306 806DVAM II (LR) 1,203 1,203 1,263 1,263

    Asset and Inventory Mgmt.System (LR) 123 123 126 126

    Property & Evidence Scanners (LR) 117 117 119 119

    DPLN (LR) 500 500 700 700

    Small Equipment (e.g. telephone handset) (LR) 350 350 700 0 600 600

    Video Recording Equipment (LR) 92 92 92 92 92 460 92 92 92 92 92 460

    Livescan M achines (LR) 423 423 431 431

    Wireless Parking System (LR) 2,916 2,916 2,916 2,916

    CCTV 182 70 182 434 70 182 70 322

    AEDs 195 195 390 195 195

    Fleet Equipment 100 100 100 100 100 500 100 100 100 100 100 500

    41,745 40,507 43,902 51,662 60,971 238,786 51,211 57,733 49,419 44,832 53,846 257,041

    Project ($000s)

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    26/43

    Page 25

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    27/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    0366 11 Division

    facility cost (S2) 0 003S2CW 500 0 0 0 0 500 0 500 0 0

    Sub-total 0500 0 0 0 0 500 0 500 0 00

    0367 14 Division

    14 Div. - 1100 King Street -Design &Construction

    1,052 003S2CW 9,909 0 0 0 0 9,909 0 9,909 0 0

    Sub-total 09,909 0 0 0 0 9,909 0 9,909 0 1,0520

    0441 41 Division

    41 Division S6 387 003S6CW 0 0 0 372 8,564 8,936 30,142 39,078 0 0

    Sub-total 00 0 0 372 8,564 8,936 30,142 39,078 0 3870

    6123 54 Division

    54 Division - new facility 5,796 003S6CW 0 0 9,060 21,665 5,721 36,446 0 36,446 0 0

    Sub-total 00 0 9,060 21,665 5,721 36,446 0 36,446 0 5,7960

    6259 Furniture Lifecycle Replacement

    Furniture LIfecycle 2012-2020 S5 0 9,42703S5CW 1,426 713 713 713 1,455 5,020 4,407 9,427 0 0

    Sub-total 9,4271,426 713 713 713 1,455 5,020 4,407 9,427 0 00

    6539 13 Division

    new 13 Facility 6,314 003S6CW 0 0 0 0 0 0 39,079 39,079 0 0

    Sub-total 00 0 0 0 0 0 39,079 39,079 0 6,3140

    6576 Vehicle & Equipment Reserve - TPS.

    Vehicle and Equipment Reserve 2012-2020(s5)

    0 46,91603S5CW 2,627 2,627 4,422 5,320 5,320 20,316 26,600 46,916 0 0

    Sub-total 46,9162,627 2,627 4,422 5,320 5,320 20,316 26,600 46,916 0 00

    6582 workstation,printers and laptops

    previously approved portion (S2) 0 41803S2CW 418 0 0 0 0 418 0 418 0 0

    2012-2020 Requirements (S5) 0 33,42204S5CW 2,904 3,525 3,751 3,345 3,186 16,711 16,711 33,422 0 0

    Sub-total 33,8403,322 3,525 3,751 3,345 3,186 17,129 16,711 33,840 0 00

    6583 Servers

    Servers 2012-2021 program (S5) 0 31,08003S5CW 3,060 3,164 2,958 2,998 3,121 15,301 15,779 31,080 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    28/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    6583 Servers

    previously approved protion (S2) 0 1,04103S2CW 1,041 0 0 0 0 1,041 0 1,041 0 0

    Sub-total 32,1214,101 3,164 2,958 2,998 3,121 16,342 15,779 32,121 0 00

    6584 IT business resumption

    2012-2021 IT business resumption (S5) 0 15,67803S5CW 1,612 1,669 1,269 1,522 1,644 7,716 7,962 15,678 0 0

    previoulsy approved plan (S2) 0 1,26903S2CW 1,269 0 0 0 0 1,269 0 1,269 0 0

    Sub-total 16,9472,881 1,669 1,269 1,522 1,644 8,985 7,962 16,947 0 00

    6835 Progress site (property and evidence)

    cost increase (S3) 0 003S3CW 0 1,300 0 0 0 1,300 0 1,300 0 0

    Progress site (property and evidence) 613 003S2CW 7,149 1,281 0 0 0 8,430 0 8,430 0 0

    Sub-total 07,149 2,581 0 0 0 9,730 0 9,730 0 6130

    7110 Data Warehouse Establishment

    Data Warehouse Establishment 2013-2016 0 004S6CW 0 0 3,617 1,354 3,233 8,204 0 8,204 0 0

    Sub-total 00 0 3,617 1,354 3,233 8,204 0 8,204 0 00

    7174 Locker Replacement

    Locker Replacement pro ject - 2012-2021program (S5

    0 1,61103S5CW 417 47 47 47 426 984 627 1,611 0 0

    Sub-total 1,611417 47 47 47 426 984 627 1,611 0 00

    7175 Mobile workstation

    Mobile Workstation (S5) 0 17,97303S5CW 240 7,214 1,443 0 0 8,897 9,076 17,973 0 0

    Sub-total 17,973240 7,214 1,443 0 0 8,897 9,076 17,973 0 00

    7186 Network equipment

    network equipment 2012-2021 program 0 13,29903S5CW 493 2,466 1,104 998 502 5,563 7,736 13,299 0 0

    Sub-total 13,299493 2,466 1,104 998 502 5,563 7,736 13,299 0 00

    7509 Acquisition and Implementation of a New RMS

    Replacement o f the cur rent RMS 2010- 2014funding

    0 004S2CW 7,933 9,507 4,866 0 0 22,306 0 22,306 0 0

    Sub-total 07,933 9,507 4,866 0 0 22,306 0 22,306 0 00

    7511 AVLS Replacement Lifecycle

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    29/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    7511 AVLS Replacement Lifecycle

    Replacement of Automated Vehicle Locat ingS5

    0 2,94803S5CW 605 0 299 562 604 2,070 878 2,948 0 0

    Replacement of AVLS S2 0 60803S2CW 608 0 0 0 0 608 0 608 0 0

    Sub-total 3,5561,213 0 299 562 604 2,678 878 3,556 0 00

    7512 In-Car Camera Replacement

    In-Car Camera Replacement 0 7,26803S6CW 0 657 788 1,051 1,138 3,634 3,634 7,268 0 0

    Sub-total 7,2680 657 788 1,051 1,138 3,634 3,634 7,268 0 00

    7513 Voice Logging Lifecycle Replacement

    Replacement of the Voi ce LoggingEquipment (S5)

    0 2,23203S6CW 0 353 0 437 315 1,105 1,127 2,232 0 0

    Sub-total 2,2320 353 0 437 315 1,105 1,127 2,232 0 00

    7516 Electronic Surveillance System Lifecycle Replac

    Replacement of the Electron ic Survei llance(S6)

    0 2,16003S6CW 0 0 0 0 1,069 1,069 1,091 2,160 0 0

    Sub-total 2,1600 0 0 0 1,069 1,069 1,091 2,160 0 00

    7517 Digital Photography Lifecycle Replacement

    Dig ital Photography Li fecycle Replacement(S6)

    0 49503S6CW 0 0 0 119 126 245 250 495 0 0

    Sub-total 4950 0 0 119 126 245 250 495 0 00

    7520 Voicemail/Call Centre

    Replacement of Call Centre Application (S2) 0 31503S2CW 315 0 0 0 0 315 0 315 0 0

    Voicemail/Call Centre (S6) 0 1,10603S6CW 0 0 0 300 0 300 806 1,106 0 0

    Sub-total 1,421315 0 0 300 0 615 806 1,421 0 00

    7521 DVAMS -11 Lifecycle Replacement

    Digi tal Video Asset Mgmt System IIReplacement

    0 2,46603S6CW 0 0 1,203 0 0 1,203 1,263 2,466 0 0

    Sub-total 2,4660 0 1,203 0 0 1,203 1,263 2,466 0 00

    7522 Asset and Inventory Management System Replac

    Asset and Inventory ManagementReplacement S2

    0 12303S2CW 123 0 0 0 0 123 0 123 0 0

    Asset and Inventory ManagementReplacement S6

    0 24903S6CW 0 0 0 0 123 123 126 249 0 0

    Sub-total 372123 0 0 0 123 246 126 372 0 00

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    30/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    7523 Property and Evidence Scanners Lifecycle

    Replacement of the Scanners at theProperty S6

    0 23603S6CW 0 0 0 0 117 117 119 236 0 0

    Sub-total 2360 0 0 0 117 117 119 236 0 00

    7524 DPLN Replacement

    Divisional Parking Lot NetworksReplacement

    0 1,20003S6CW 0 500 0 0 0 500 700 1,200 0 0

    Sub-total 1,2000 500 0 0 0 500 700 1,200 0 00

    7525 Small Equipment Replacement

    Telephone Handset Replacement (S5) 0 1,30003S5CW 350 350 0 0 0 700 600 1,300 0 0

    video equipment - 2012-2021 (S5) 0 92003S5CW 92 92 92 92 92 460 460 920 0 0

    Sub-total 2,220442 442 92 92 92 1,160 1,060 2,220 0 00

    7526 DVAMS 1 Lifecycle Replacement

    Replacement of the DVAMS 1 Equipment(S6)

    0 2,12103S6CW 0 0 0 1,050 0 1,050 1,071 2,121 0 0

    Sub-total 2,1210 0 0 1,050 0 1,050 1,071 2,121 0 00

    7532 Human Resources Management System (HRMS)

    Human Resources Management System(HRMS) Upgrade

    0 003S6CW 0 0 155 682 0 837 0 837 0 0

    Sub-total 00 0 155 682 0 837 0 837 0 00

    7533 Time Resource Management System (TRMS) Up

    T ime Resource Management Sys tem(TRMS) Upgrade

    0 003S6CW 0 0 1,943 1,470 0 3,413 0 3,413 0 0

    Sub-total 00 0 1,943 1,470 0 3,413 0 3,413 0 00

    7534 Fibre Optics

    Fibre Optics 0 003S6CW 0 0 0 881 5,585 6,466 5,585 12,051 0 0

    Sub-total 00 0 0 881 5,585 6,466 5,585 12,051 0 00

    7535 Electronic Document Management

    Electronic Document Management - S6 0 004S6CW 0 0 49 441 0 490 0 490 0 0

    Sub-total 00 0 49 441 0 490 0 490 0 00

    7612 Livescan replacement

    livescan S2 0 42303S2CW 423 0 0 0 0 423 0 423 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    31/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    7612 Livescan replacement

    livescann S6 0 85403S6CW 0 0 0 0 423 423 431 854 0 0

    Sub-total 1,277423 0 0 0 423 846 431 1,277 0 00

    7613 AFIS replacement

    Automated Fingerpr in t Ident if icat ion System(AFIS)

    0 003S2CW 1,979 0 0 0 0 1,979 0 1,979 0 0

    AFIS - 2018 - S6 0 003S6CW 0 0 0 0 0 0 3,053 3,053 0 0

    Sub-total 01,979 0 0 0 0 1,979 3,053 5,032 0 00

    7616 Digital Content Manager

    Digital Content Manager system 0 004S6CW 0 0 1,360 1,673 0 3,033 0 3,033 0 0

    Sub-total 00 0 1,360 1,673 0 3,033 0 3,033 0 00

    7734 Radio Replacement (2016-2020)

    Radio Replacement (2016-2020) 0 003S6CW 0 0 0 0 10,193 10,193 25,167 35,360 0 0

    Sub-total 00 0 0 0 10,193 10,193 25,167 35,360 0 00

    7735 Upgrade to Microsoft 7

    upgrade to microsoft 7 0 004S2CW 160 0 0 0 0 160 0 160 0 0

    Sub-total 0160 0 0 0 0 160 0 160 0 00

    7785 CCTV (S6)

    0 75604S6CW 0 182 70 0 182 434 322 756 0 0

    Sub-total 7560 182 70 0 182 434 322 756 0 00

    7786 AED's (S6)

    AED's (S6) 0 58504S6CW 0 195 0 0 195 390 195 585 0 0

    Sub-total 5850 195 0 0 195 390 195 585 0 00

    7788 Fleet Equipment

    Fleet Equipment (S5) 0 1,00004S5CW 100 100 100 100 100 500 500 1,000 0 0

    Sub-total 1,000100 100 100 100 100 500 500 1,000 0 00

    7802 32 Division Upgrade

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    32/43

    Feb-03-2012 14:58:40

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    7802 32 Division Upgrade

    32 Division Upgrade 0 003S6CW 0 0 0 0 0 0 6,987 6,987 0 0

    Sub-total 00 0 0 0 0 0 6,987 6,987 0 00

    7803 52 Division Upgrade

    52 Division Upgrade 0 003S6CW 0 0 0 0 0 0 8,300 8,300 0 0

    Sub-total 00 0 0 0 0 0 8,300 8,300 0 00

    7804 55 Division Upgrade

    55 Division Upgrade 0 003S6CW 0 0 0 0 0 0 8,000 8,000 0 0

    Sub-total 00 0 0 0 0 0 8,000 8,000 0 00

    7805 22 Division Upgrade

    22 Division Upgrade 0 003S6CW 0 0 0 0 0 0 1,290 1,290 0 0

    Sub-total 00 0 0 0 0 0 1,290 1,290 0 00

    7806 E-Ticketing

    E-Ticketing 0 004S4CW 1,720 0 0 0 0 1,720 0 1,720 0 0

    Sub-total 01,720 0 0 0 0 1,720 0 1,720 0 00

    024 POLICE Radio Communication System Replace

    2012 requirements (S4) 0 003S4CW 5,371 0 0 0 0 5,371 0 5,371 0 0

    Sub-total 05,371 0 0 0 0 5,371 0 5,371 0 00

    0050 State-of Good Repair

    8 2012-2016 program 0 003S5CW 4,510 4,565 4,594 4,469 4,621 22,759 24,052 46,811 0 0

    Sub-total 04,510 4,565 4,594 4,469 4,621 22,759 24,052 46,811 0 00

    7549 Wireless Parking System

    Wireless Parking System (s6) 0 5,83203S6CW 0 0 0 0 2,916 2,916 2,916 5,832 0 0

    Sub-total 5,8320 0 0 0 2,916 2,916 2,916 5,832 0 00

    l Program Expenditure 14,162 207,33157,354 40,507 43,903 51,661 60,971 254,396 257,042 511,438 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    33/43

    Feb-03-2012 14:58:40

    Ward Stat. Cat. Reserves

    Project No. Project Name

    y SubProj No. Sub-project Name

    d By:

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments and Estimates

    2012

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2,S5,S6 Part C Sub-Project Status S2

    OF TORONTO

    Expenditures ($000's)

    endix 3 - 2012 Capital budget: 2013 to 2021 Capital Plan

    nto Police Service

    Current and Future Year Cas

    ProvincialGrants andSubsidies

    Federal DevelopmentSubsidy Charges

    14,162 0velopment Charges 1,434 231 1,721 2,565 1,596 7,547 6,615 14,162 0 0

    0 207,331serves (Ind. "XQ" Ref.) 18,123 23,854 18,259 18,654 23,054 101,944 105,387 207,331 0 0

    0 0bt 36,077 16,422 23,923 30,442 36,321 143,185 145,040 288,225 0 0

    0 0bt - Recoverable 1,720 0 0 0 0 1,720 0 1,720 0 0

    l Program Financing 14,162 207,33157,354 40,507 43,903 51,661 60,971 254,396 257,042 511,438 0 0

    Code Description

    S2 P rior Year (With 2012 and \o r Future Yea r Cash flow)

    S3 Prior Year - Change of Scope 2012 and\or Future Year Cost\Cashflow)

    S4 New - S tand -A lone P ro ject (Cur rent Year Only)

    S5 New (On-going or Phased Projects)

    S6 New - Fu tu re Year (Commencing in 2013 & Beyond)

    ry Code Description

    Health and Safety C01

    Legislated C02

    State of Good Repair C03

    Service Improvement and Enhancement C04

    Growth Related C05

    Reserved Category 1 C06Reserved Category 2 C07

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    34/43

    Page 26

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    35/43

    Feb-03-2012 15:04:27

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2 Part C Sub-Project Status S2,S3,S4

    endix 4 - 2012 Cash Flow and Future Year commitments

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    0366 11 Division

    facility cost (S2) 0 003S2CW 500 0 0 0 0 500 0 500 0 0

    Sub-total 0500 0 0 0 0 500 0 500 0 00

    0367 14 Division

    14 Div. - 1100 King Street -Design &Construction

    1,052 003S2CW 9,909 0 0 0 0 9,909 0 9,909 0 0

    Sub-total 09,909 0 0 0 0 9,909 0 9,909 0 1,0520

    6259 Furniture Lifecycle Replacement

    Furniture LIfecycle 2012-2020 S5 0 1,42603S5CW 1,426 0 0 0 0 1,426 0 1,426 0 0

    Sub-total 1,4261,426 0 0 0 0 1,426 0 1,426 0 00

    6576 Vehicle & Equipment Reserve - TPS.

    Vehicle and Equipment Reserve 2012-2020(s5)

    0 2,62703S5CW 2,627 0 0 0 0 2,627 0 2,627 0 0

    Sub-total 2,6272,627 0 0 0 0 2,627 0 2,627 0 00

    6582 workstation,printers and laptops

    previously approved portion (S2) 0 41803S2CW 418 0 0 0 0 418 0 418 0 0

    2012-2020 Requirements (S5) 0 2,90404S5CW 2,904 0 0 0 0 2,904 0 2,904 0 0

    Sub-total 3,3223,322 0 0 0 0 3,322 0 3,322 0 00

    6583 Servers

    Servers 2012-2021 program (S5) 0 3,06003S5CW 3,060 0 0 0 0 3,060 0 3,060 0 0

    previously approved protion (S2) 0 1,04103S2CW 1,041 0 0 0 0 1,041 0 1,041 0 0

    Sub-total 4,1014,101 0 0 0 0 4,101 0 4,101 0 00

    6584 IT business resumption

    2012-2021 IT business resumption (S5) 0 1,61203S5CW 1,612 0 0 0 0 1,612 0 1,612 0 0

    previoulsy approved plan (S2) 0 1,26903S2CW 1,269 0 0 0 0 1,269 0 1,269 0 0

    Sub-total 2,8812,881 0 0 0 0 2,881 0 2,881 0 00

    6835 Progress site (property and evidence)

    cost increase (S3) 0 003S3CW 0 1,300 0 0 0 1,300 0 1,300 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    36/43

    Feb-03-2012 15:04:27

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2 Part C Sub-Project Status S2,S3,S4

    endix 4 - 2012 Cash Flow and Future Year commitments

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    6835 Progress site (property and evidence)

    Progress site (property and evidence) 613 003S2CW 7,149 1,281 0 0 0 8,430 0 8,430 0 0

    Sub-total 07,149 2,581 0 0 0 9,730 0 9,730 0 6130

    7174 Locker Replacement

    Locker Replacement pro ject - 2012-2021program (S5

    0 41703S5CW 417 0 0 0 0 417 0 417 0 0

    Sub-total 417417 0 0 0 0 417 0 417 0 00

    7175 Mobile workstation

    Mobile Workstation (S5) 0 24003S5CW 240 0 0 0 0 240 0 240 0 0

    Sub-total 240240 0 0 0 0 240 0 240 0 00

    7186 Network equipment

    network equipment 2012-2021 program 0 49303S5CW 493 0 0 0 0 493 0 493 0 0

    Sub-total 493493 0 0 0 0 493 0 493 0 00

    7509 Acquisition and Implementation of a New RMS

    Replacement o f the cur rent RMS 2010- 2014funding

    0 004S2CW 7,933 9,507 4,866 0 0 22,306 0 22,306 0 0

    Sub-total 07,933 9,507 4,866 0 0 22,306 0 22,306 0 00

    7511 AVLS Replacement Lifecycle

    Replacement of Automated Vehicle Locat ingS5

    0 60503S5CW 605 0 0 0 0 605 0 605 0 0

    Replacement of AVLS S2 0 60803S2CW 608 0 0 0 0 608 0 608 0 0

    Sub-total 1,2131,213 0 0 0 0 1,213 0 1,213 0 00

    7520 Voicemail/Call Centre

    Replacement of Call Centre Application (S2) 0 31503S2CW 315 0 0 0 0 315 0 315 0 0

    Sub-total 315315 0 0 0 0 315 0 315 0 00

    7522 Asset and Inventory Management System Replac

    Asset and Inventory ManagementReplacement S2

    0 12303S2CW 123 0 0 0 0 123 0 123 0 0

    Sub-total 123123 0 0 0 0 123 0 123 0 00

    7525 Small Equipment Replacement

    Telephone Handset Replacement (S5) 0 35003S5CW 350 0 0 0 0 350 0 350 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    37/43

    Feb-03-2012 15:04:27

    Reserves

    Project No. Project Name

    ySubProj No. Sub-project Name

    nto Police Service

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2 Part C Sub-Project Status S2,S3,S4

    endix 4 - 2012 Cash Flow and Future Year commitments

    Ward Stat. Cat.

    Current and Future Year

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments

    ProvincialGrants andSubsidies

    DevelopmentCharges

    FederalSubsidy2012

    Expenditures ($000's)

    OF TORONTO

    7525 Small Equipment Replacement

    video equipment - 2012-2021 (S5) 0 9203S5CW 92 0 0 0 0 92 0 92 0 0

    Sub-total 442442 0 0 0 0 442 0 442 0 00

    7612 Livescan replacement

    livescan S2 0 42303S2CW 423 0 0 0 0 423 0 423 0 0

    Sub-total 423423 0 0 0 0 423 0 423 0 00

    7613 AFIS replacement

    Automated Fingerpr in t Ident if icat ion System(AFIS)

    0 003S2CW 1,979 0 0 0 0 1,979 0 1,979 0 0

    Sub-total 01,979 0 0 0 0 1,979 0 1,979 0 00

    7735 Upgrade to Microsoft 7

    upgrade to microsoft 7 0 004S2CW 160 0 0 0 0 160 0 160 0 0

    Sub-total 0160 0 0 0 0 160 0 160 0 00

    7788 Fleet Equipment

    Fleet Equipment (S5) 0 10004S5CW 100 0 0 0 0 100 0 100 0 0

    Sub-total 100100 0 0 0 0 100 0 100 0 00

    7806 E-Ticketing

    E-Ticketing 0 004S4CW 1,720 0 0 0 0 1,720 0 1,720 0 0

    Sub-total 01,720 0 0 0 0 1,720 0 1,720 0 00

    024 POLICE Radio Communication System Replace

    2012 requirements (S4) 0 003S4CW 5,371 0 0 0 0 5,371 0 5,371 0 0

    Sub-total 05,371 0 0 0 0 5,371 0 5,371 0 00

    0050 State-of Good Repair

    8 2012-2016 program 0 003S5CW 4,510 0 0 0 0 4,510 0 4,510 0 0

    Sub-total 04,510 0 0 0 0 4,510 0 4,510 0 00

    l Program Expenditure 1,665 18,12357,354 12,088 4,866 0 0 74,308 0 74,308 0 0

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    38/43

    Feb-03-2012 15:04:27

    Ward Stat. Cat. Reserves

    Project No. Project Name

    y SubProj No. Sub-project Name

    d By:

    Total Total Total

    2012-2016 2017-2021 2012-20212013 2014 2015 2016

    Current and Future Year Cash Flow Commitments and Estimates

    2012

    Phase 5 - Program 19 Toronto Police Service Program Phase 5 Sub-Project Category 01,02,03,04,05 Part B Sub-Project Status S2 Part C Sub-Project Status S2,S3,S4

    OF TORONTO

    Expenditures ($000's)

    endix 4 - 2012 Cash Flow and Future Year commitments

    nto Police Service

    Current and Future Year Cas

    ProvincialGrants andSubsidies

    Federal DevelopmentSubsidy Charges

    1,665 0velopment Charges 1,434 231 0 0 0 1,665 0 1,665 0 0

    0 18,123serves (Ind. "XQ" Ref.) 18,123 0 0 0 0 18,123 0 18,123 0 0

    0 0bt 36,077 11,857 4,866 0 0 52,800 0 52,800 0 0

    0 0bt - Recoverable 1,720 0 0 0 0 1,720 0 1,720 0 0

    l Program Financing 1,665 18,12357,354 12,088 4,866 0 0 74,308 0 74,308 0 0

    Code Description

    S2 P rior Year (With 2012 and \o r Future Yea r Cash flow)

    S3 Prior Year - Change of Scope 2012 and\or Future Year Cost\Cashflow)

    S4 New - S tand -A lone P ro ject (Cur rent Year Only)

    S5 New (On-going or Phased Projects)

    ry Code Description

    Health and Safety C01

    Legislated C02

    State of Good Repair C03

    Service Improvement and Enhancement C04

    Growth Related C05

    Reserved Category 1 C06

    Reserved Category 2 C07

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    39/43

    Page 27

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    40/43

    Sub-Project Summary

    Project/Financing

    Priority Project Project Name

    Phase 5) 19-Toronto Police Service Sub-Project Category: 01,02,03,04,05,06,07 Type: B Sub-Project Status: S2 Type: C Sub-Project Status: S2,S3,S4,S5

    Feb-03-2012 15:13

    Appendix 5 - 2012 Capital Project with Financing Details

    2012 Fina

    Start Date DevelopmtCharges

    Reserves ReservFunds

    CompletionDate

    Cash Flow FederalSubsidy

    ProvincialGrants

    Subsidies

    CITY OF TORONTO

    Toronto Police Service

    11 DivisionPOL0003660

    facility cost (S2)0 7 8/31/2008 8/31/2011 500 0000

    Project Sub-total: 500 0000

    14 DivisionPOL0003670

    14 Div. - 1100 King Street -Design & Construction0 1 4/1/2005 12/31/2011 9,909 01,05200

    Project Sub-total: 9,909 01,05200

    Furniture Lifecycle ReplacementPOL9062590

    Furniture LIfecycle 2012-2020 S51 5 1/1/2008 8/14/2013 1,426 1,426000

    Project Sub-total: 1,426 1,426000

    Vehicle & Equipment Reserve - TPS.POL9065760

    Vehicle and Equipment Reserve 2012-2020 (s5)0 6 4/4/2009 12/31/2020 2,627 2,627000

    Project Sub-total: 2,627 2,627000

    workstation,printers and laptopsPOL9065820

    previously approved portion (S2)0 5 6/1/2006 6/1/2016 418 418000

    2012-2020 Requirements (S5)0 6 9/9/2008 12/31/2020 2,904 2,904000

    Project Sub-total: 3,322 3,322000

    ServersPOL9065830

    Servers 2012-2021 program (S5)0 3 10/20/2007 12/31/2020 3,060 3,060000

    previously approved protion (S2)0 4 9/23/2009 9/23/2009 1,041 1,041000

    Project Sub-total: 4,101 4,101000

    IT business resumptionPOL9065840

    2012-2021 IT business resumption (S5)0 5 8/24/2006 12/31/2020 1,612 1,612000

    previoulsy approved plan (S2)0 6 9/9/2010 9/9/2010 1,269 1,269000Project Sub-total: 2,881 2,881000

    Progress site (property and evidence)POL9068350

    Progress site (property and evidence)2 1 1/1/2012 12/31/2015 7,149 038200

    Project Sub-total: 7,149 038200

    Locker ReplacementPOL9071740

    Locker Replacement project - 2012-2021 program (S50 2 8/24/2006 12/31/2020 417 417000

    Project Sub-total: 417 417000

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    41/43

    Sub-Project Summary

    Project/Financing

    Priority Project Project Name

    Phase 5) 19-Toronto Police Service Sub-Project Category: 01,02,03,04,05,06,07 Type: B Sub-Project Status: S2 Type: C Sub-Project Status: S2,S3,S4,S5

    Feb-03-2012 15:13

    Appendix 5 - 2012 Capital Project with Financing Details

    2012 Fina

    Start Date DevelopmtCharges

    Reserves ReservFunds

    CompletionDate

    Cash Flow FederalSubsidy

    ProvincialGrants

    Subsidies

    CITY OF TORONTO

    Toronto Police Service

    Mobile workstationPOL9071750

    Mobile Workstation (S5)0 1 4/1/2009 12/31/2016 240 240000

    Project Sub-total: 240 240000

    Network equipmentPOL9071860

    network equipment 2012-2021 program0 2 8/4/2010 12/31/2020 493 493000

    Project Sub-total: 493 493000

    Acquisition and Implementation of a New RMSPOL9075090

    Replacement of the current RMS 2010- 2014 funding0 2 1/1/2009 12/31/2012 7,933 0000

    Project Sub-total: 7,933 0000

    AVLS Replacement LifecyclePOL9075110

    Replacement of Automated Vehicle Locating S50 1 9/10/2010 9/10/2018 605 605000

    Replacement of AVLS S20 2 9/10/2009 9/10/2018 608 608000

    Project Sub-total: 1,213 1,213000

    Voicemail/Call CentrePOL9075200

    Replacement of Call Centre Application (S2)0 1 9/11/2010 12/31/2015 315 315000

    Project Sub-total: 315 315000

    Asset and Inventory Management System ReplacementPOL9075220

    Asset and Inventory Management Replacement S20 1 4/10/2011 12/31/2011 123 123000

    Project Sub-total: 123 123000

    Small Equipment ReplacementPOL9075250

    Telephone Handset Replacement (S5)0 1 1/10/2012 12/31/2018 350 350000

    video equipment - 2012-2021 (S5)0 3 9/3/2010 9/3/2010 92 92000

    Project Sub-total: 442 442000

    Livescan replacementPOL9076120

    livescan S20 1 9/22/2011 9/22/2011 423 423000

    Project Sub-total: 423 423000

    AFIS replacementPOL9076130

    Automated Fingerprint Identification System (AFIS)0 1 9/22/2011 9/22/2011 1,979 0000

    Project Sub-total: 1,979 0000

    Upgrade to Microsoft 7POL9077350

    upgrade to microsoft 70 1 1/1/2011 12/31/2012 160 0000

    Project Sub-total: 160 0000

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    42/43

    Sub-Project Summary

    Project/Financing

    Priority Project Project Name

    Phase 5) 19-Toronto Police Service Sub-Project Category: 01,02,03,04,05,06,07 Type: B Sub-Project Status: S2 Type: C Sub-Project Status: S2,S3,S4,S5

    Feb-03-2012 15:13

    Appendix 5 - 2012 Capital Project with Financing Details

    2012 Fina

    Start Date DevelopmtCharges

    Reserves ReservFunds

    CompletionDate

    Cash Flow FederalSubsidy

    ProvincialGrants

    Subsidies

    CITY OF TORONTO

    Toronto Police Service

    Fleet EquipmentPOL9077880

    Fleet Equipment (S5)0 1 1/1/2012 12/31/2021 100 100000

    Project Sub-total: 100 100000

    E-TicketingPOL9078060

    E-Ticketing0 1 9/2/2011 9/2/2011 1,720 0000

    Project Sub-total: 1,720 0000

    POLICE Radio Communication System ReplacementTED9070240

    2012 requirements (S4)0 4 9/22/2009 9/22/2009 5,371 0000

    Project Sub-total: 5,371 0000

    State-of Good RepairPOL0000501

    2012-2016 program0 18 10/5/2005 10/5/2016 4,510 0000

    Project Sub-total: 4,510 0000

    Program Total: 57,354 18,1231,43400

    Status Code Description

    S2 S2 P rior Yea r (Wi th 2012 and \or Fu tu re Yea r Cashf low)

    S3 S3 Prior Year - Change of Scope 2012 and\or Future Year Cost\Cashf low)

    S4 S4 New - S tand-Alone P roject (Cu rrent Yea r Only)

    S5 S5 New (On-going or Phased Projects)

    Category Code Description

    Health and Safety C0101

    Legislated C0202

    State of Good Repair C0303

    Service Improvement and Enhancement C0404

    Growth Related C0505

    Reserved Category 1 C0606

    Reserved Category 2 C0707

  • 7/30/2019 2012 City of Toronto Budget Toronto Police Service Capital Budget Program Summary

    43/43

    Reserve / Reserve Fund

    Name Project / SubProject Name and Number

    2012

    Budget2013 Plan 2014 Plan 2015 Plan 2016 Plan 2017 Plan 2018 Plan 2019 Plan 2020 Plan 2021 Plan

    2012 - 2021

    Total

    Beginning Balance 2,446 2,446 2,446 3,677 3,461 2,446 2,446 3,819 3,862 2,446 2,714

    Division 14 (1,052) (1,052)

    Division 41 (86) (206) (95) (387)

    Division 54 (1,721) (2,565) (1,510) (5,796)

    Division 13 (67) (1,556) (3,161) (1,530) (6,314)

    Property & Evidence Facility (382) (231) (613)

    Total Proposed Withdrawals (1,434) (231) (1,721) (2,565) (1,596) (273) (1,651) (3,161) (1,530) (14,162)

    Projected Contributions 1,434 1,462 1,505 1,550 1,596 1,646 1,694 1,745 1,798 1,851 16,281

    TOTAL RES ERVE FUND BALANCE AT YEAR-END 2,4 46 2,446 3,677 3,461 2,446 2,446 3,819 3,862 2,446 2,714 4,565

    Reserve / Reserve Fund

    Name Project / SubProject Name and Number

    2012

    Budget2013 Plan 2014 Plan 2015 Plan 2016 Plan 2017 Plan 2018 Plan 2019 Plan 2020 Plan 2021 Plan

    2012 - 2021

    Total

    Beginning Balance 249 249 4,713 (1) 1,630 2,866 (298) 2,791 (344) 1,279 2,950

    Vehic le and Eq uip ment (LR) (2,627) (2,627) (4,422) (5,320) (5,320) (5,320) (5,320) (5,320) (5,320) (5,320) (46,916)

    Workstat ion, Laptop, Prin ter (LR) (2,904) (3,525) (3,751) (3,345) (3,186) (2,904) (3,525) (3,751) (3,345) (3,186) (33,422)

    Servers (LR) (3,060) (3,164) (2,958) (2,998) (3,121) (3,228) (3,017) (3,058) (3,184) (3,292) (31,080)

    IT Bu sin es s Resu mp tio n (LR) (1,612) (1,669) (1,269) (1,522) (1,644) (1,702) (1,294) (1,553) (1,677) (1,736) (15,678)

    Mobile Workstations (LR) (240) (7,214) (1,443) (245) (7,359) (1,472) (17,973)

    Network Equipment (LR) (493) (2,466) (1,104) (998) (502) (2,515) (1,126) (1,018) (512) (2,565) (13,299)

    Locker Replacement (LR) (417) (47) (47) (47) (426) (48) (48) (48) (434) (49) (1,611)

    Furniture Replacement (LR) (1,426) (713) (713) (713) (1,455) (727) (727) (727) (1,484) (742) (9,427)

    AVL (LR) (605) (299) (562) (604) (305) (573) (2,948)

    In - Car Camera (LR) (657) (788) (1,051) (1,138) (657) (788) (1,051) (1,138) (7,268)

    Voice Logging (LR) (353) (437) (315) (360) (446) (321) (2,232)Electronic Surveillance (LR) (1,069) (1,091) (2,160)

    Digital Photography (LR) (119) (126) (122) (128) (495)

    DVAM I (LR) (1,050) (1,071) (2,121)

    Voicemail / Call Centre (LR) (300) (500) (306) (1,106)

    DVAM II (LR) (1,203) (1,263) (2,466)

    Asset and Inventory Mgmt.System (LR) (123) (126) (249)

    Property & Evidence Scanners (LR) (117) (119) (236)

    DPLN (LR) (500) (700) (1,200)

    Small Equip (e.g. telephone hands et) (350) (350) (600) (1,300)

    Video Recording Equipment (LR) (92) (92) (92) (92) (92) (92) (92) (92) (92) (92) (920)

    Radios - Replacement

    Livescan Machines (LR) (423) (431) (854)

    Wireless Parking System (LR) (2,916) (2,916) (5,832)

    EDU/CBRN Explosiv e Containment (LR)

    CCTV (182) (70) (182) (70) (182) (70) (756)

    AEDs (195) (195) (195