2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
Transcript of 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
1/56
FINDINGS OF FACTS, CONCLUSIONS AND RECOMMENDED CONDITIONS OF
APPROVAL BY THE COURT BASED UPON HEARINGS HELD ON AUGUST 8, 9, 21, 22
and 23, 2012, BEFORE DOUGLAS WOLFSON, HEARING OFFICER, AND IN THEPRESENCE OF ELIZABETH C. MCKENZIE, AICP, PP, SPECIAL MASTER
November 10, 2012
SUBMITTED TO THE HONORABLE LISA CHRYSTAL, JSC,
UNION COUNTY SUPERIOR COURT,
in the matter of CRANFORD DEVELOPMENT ASSOCIATES, LLC, et al. vs. TOWNSHIP OFCRANFORD AND PLANNING BOARD OF TOWNSHIP OF CRANFORD,
DOCKET NO.: UNN-L-003759-08
________________________________________________________________________
BACKGROUND
On July 29, 2011, the Law Division of the Superior Court (The Honorable Lisa Chrystal,
JSC, sitting), having previously ruled that defendant Cranford Township is in violation of its low
and moderate income fair share housing obligations, determined that plaintiff, Cranford
Development Associates, LLC, et al.(hereinafter collectively CDA) is entitled to a site-
specific Builders Remedy, namely the right to construct an inclusionary development consisting
of 360 total housing units on its property located at 215-235 Birchwood Avenue and identified
on the Cranford Township Tax Map as Block 291, Lot 15.01, and Block 292, Lot 2 (hereinafter
the Property) that would include a 15 percent set-aside of low and moderate income units on
terms specified by the Court. On December 9, 2011, the Court entered an Order embodying this
decision.
In implementation of its Order granting the Builders Remedy, the Court designated and
appointedDouglas Wolfson, a formerMount Laurel Judge (Middlesex Vicinage), as the SpecialHearing Officer (the Hearing Officer) in this matter to assume jurisdiction over the site plan
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
2/56
2
review process in lieu of the Planning Board and to conduct public hearings consistent with the
requirements of the Municipal Land Use Law (the MLUL) and Order granting the Builders
Remedy, and, thereafter, to make a recommendation to The Honorable Lisa Chrystal, J.S.C.
concerning the application.
By Order dated August 6, 2012, the Court also directed the Hearing Officer to make a
recommendation to the Court, based upon facts adduced at the site plan hearing(s), on the issue
of whether defendants, Township of Cranford, et al., should be required to take the necessary
formal actions that would permit CDA, at CDAs own expense, to regrade a stretch of
Birchwood Avenue to elevate it to a level one foot above the flood hazard area design elevation
in accordance with plans prepared by L2A Land Design, LLC, as part of its construction of the
proposed inclusionary development of the Property in order to obtain NJDEP approval of the
development.
A memorandum dated May 15, 2012 was circulated by Elizabeth C. McKenzie, AICP,
PP, the Court-Appointed Special Master (the Special Master) outlining the procedures to be
followed by the parties in submitting, reviewing and approving CDA'S site plan application.
THE APPLICATION
Consistent with the above-cited Orders and the procedural memorandum circulated by
the Special Master, CDA (the Applicant) submitted an application for Preliminary and Final
Site Plan Approval and requests for associated waivers and exceptions (the Application)
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
3/56
3
together with supporting reports, plans and other materials by letter of transmittal dated June 6,
2012 (collectively, the Application Materials), to permit development of the Property.
The Application Materials initially consisted of the following:
a. Preliminary and Final Site Plan and Application for Individual Flood Hazard AreaPermit, M.E. Dipple, June 4, 201225 sheets (Ex. A-4)
b. Architectural Plan, Lessard Design, June 5, 20128 sheets (Ex. A-5)c. Engineering Report, M.E. Dipple, Rev. June 4, 2012 (Ex. A-6)
Subsequently, CDA also submitted the following additional documents:
a. Traffic Impact Assessment, E. Dolan, June 14, 2012 (Ex. A-11)
b. Letter Report, Lessard Design, July 31, rev. August 1, 2012 (Ex A-8)
c. Code Analysis, Lessard Design, Aug. 1, 2012 (Ex. A-9)
d. Fire Code Analysis, Lessard Design, Aug. 1, 2012 (Ex. A-10)e. Letter Report, M.E. Dipple, July 31, 2012 (Ex. A-11)f. Letter Report, M.E. Dipple and C. Emerson, Aug. 6, 2012 (Ex. A-12)g. Sanitary Sewer Capacity Study, M.E. Dipple, January 2009 (Ex. A-17)h. Supplemental Traffic Report, E. Dolan, August 23, 2012 (Ex. A-24)
CDAs site plan showed the proposed regrading of Birchwood Avenue.
The application was reviewed by the Township prior to the Hearings. The Townships
review included not only reviews by the Townships own professionals but also by outside traffic
and engineering consultants retained by the Township in accordance with standard municipal
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
4/56
4
land use practice and paid for out of the escrow account established by CDA in accordance with
the MLUL, the Townships Ordinance and the recommended procedures of the Special Master.
In response to the Application, the Township of Cranford submitted the following review
reports:
a. Memorandum from Code Official R. Belluscio to P. Morin, 7-18-12 (Ex. D-1)
b. Letter from Traffic Consultant J. Staigar to P. Morin, 8-7-12 (Exs. D-2 and D-14)
c. Memorandum from Cranford Police Traffic Division to P. Morin, 7-15-12 (Ex. D-3)
d. Memorandum from Municipal Engineer R. Marsden to P. Morin, 7-20-12 (Ex. D-4)
e. Memorandum from Zoning Officer R. Hudak to P. Morin, 7-18-12 (not in
evidence)
f. Memorandum from Fire Chief L. Dolan to P. Morin, 7-18-12 (Ex. D-17)
On August 1, 2012, representatives of CDA, including its professional consultants, met
with representatives of Cranford Township, including its Municipal Attorney, Municipal
Engineer, Construction Code Official, Zoning Officer, and a representative of the Township
Police Department, to jointly review the Application.
THE HEARINGS
Pursuant to an Order entered by the Honorable Lisa Chrystal on August 6, 2012, Open
Public Hearings were held at the Union County Court House in Elizabeth, New Jersey, during
regular Court House hours. The Hearings took place on August 8, 2012, August 9, 2012, August
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
5/56
5
21, 2012, August 22, 2012, and August 23, 2012, before the Hearing Officer and in the presence
of the Special Master.
Although the Township of Cranford objected to the scope and sufficiency of the Notice
provided by the Applicant in a letter dated August 3, 2012, which letter is part of the record
before the Court, the Hearing Officer determined that the Applicant had provided adequate
Notice via proof of publication of the Notice in the Official Newspaper for Cranford Township,
as well as proof of service of Notice to all property owners within 200 feet of the Property as
shown on the certified list of property owners dated June 1, 2012, provided by Peter Barnett, Tax
Assessor for the Township of Cranford, on all utilities and cable television operators servicing
the Property or having facilities located within 200 feet of the Property, on any military facility
commander registered with the municipality, on the Union County Planning Board and on James
Simpson, New Jersey Department of Transportation Commissioner, all as provided by N.J.S.A.
40:55D-1, et seq. (Ex. A-1).
At the Hearings, the Applicant, represented by Stephen M. Eisdorfer, Esquire, of the firm
of Hill, Wallack, LLP, presented several witnesses, each of whom was then questioned by
counsel for the Township, Philip J. Morin, III, Esquire, of the firm of Florio, Perrucci, Steinhardt
and Fader, LLC, as well as by members of the public, including one attorney, Maria Anderson,
of 662 Trenton Avenue, Kenilworth, representing herself. The Applicant was permitted to
conduct a redirect examination, and the Township and members of the public were permitted to
ask questions limited to topics addressed in the redirect examination. Special Master Elizabeth
McKenzie and the Hearing Officer then asked questions. Finally, counsel for the Applicant and
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
6/56
6
the Township and members of the public were permitted to ask questions on topics addressed in
the responses to the questions of the Special Master and the Hearing Officer.
The Township then presented its own witnesses, following the same procedure.
Finally, members of the public were permitted to present testimony under oath.
The Applicant, the Township, and members of the public were permitted to offer
documents into evidence, which were marked, and by stipulation were all moved into evidence.
A list of the exhibits received into evidence is attached hereto as Appendix A.
CDA presented the testimony of the following witnesses:
a. Christian LessardArchitect (8/8 T. 31-160)
b. Elizabeth Dolan, P.E.Traffic Engineering (8/8 T. 161-230)
c. Michael Dipple, P.E.Engineering and Hydrology (8/9 T. 5-153 , 8/21 T. 7-173,
8/22 T. 5-129, 8/23 T. 101-103)
d. Peter HekemianApplicant (8/9 T. 154-160)
e. Clay Emerson, PhD.Engineering and Water Resource Engineering (8/23 T
144-195)
The Township presented the testimony of the following witnesses:
a. Richard MarsdenEngineering (8/22 T. 129-200, 8/23 T. 5-87)
b. Joseph StaigarTraffic Engineering (8/22 T. 105-129)
c. Leonard Dolanfire chief (8/23 T.103-143)
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
7/56
7
d. Thomas Creelmanengineering and hydrology (8/23 T. 87-100)
The following members of the public testified:
a. Laura Tarulli (8/23 T. 197-98)
b. Rita LaBrutto (8/23 T. 198-214)
c. Maria Anderson (8/23 T. 214-232)
d. Liz Sweeney (8/23 T. 232-238)
EXISTING CONDITIONS ON THE PROPERTY
The Application proposes the redevelopment of a 15.8-acre site consisting of two
separate but adjoining lots designated on the Cranford Township Tax Map as Block 291, Lot
15.01, and Block 292, Lot 2. The lots are located at 215 and 235 Birchwood Avenue in Cranford
Township. Site Plan (Ex. A-4).
The Property is currently developed with two office buildings and associated paved
parking areas. The remainder of the Property includes mature woods, a mixture of evergreen and
deciduous vegetation, and lawn. Casino Brook, a narrow stream that is a tributary of the Rahway
River (also known as Rahway River Branch 10-24) forms the western edge of the site. The
southeast corner of the site has another man-made ditch. Dipple, 8/8 T. 12-15; Site Plan, sht. C-
02 (Ex. A-4); Aerial Photo (Ex. A-8).
The Property contains regulated freshwater wetlands and wetlands transition areas, which
have been delineated by the NJDEP in a formal Letter of Interpretation. Letter from A. Clark,
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
8/56
8
Northeast Region Supervisor, Bureau of Inland Regulation, NJDEP, to Michael Rehman, July
20, 2009 (Ex. A-18); Site Plan sht. C-02 (Exs. A-4, A-14); Dipple, 8/9 T 13, 42-44. It also
contains areas within the regulated floodway and flood fringe area of Casino Brook. Site Plan
sht. C-02 (Exs. A-4); Dipple Engineering Report, Sheet FS-01, Dipple, 8/9T 13-14.
The surrounding uses include a health care facility to the east of the Property, an office
building to the west of the Property, and an office building owned by Verizon, Inc., and a
municipal composting and recycling center to the north of the Property on the other side of
Birchwood Avenue. The nearest existing residential uses are single family houses on
Wadsworth Terrace to the south of the Property, which homes have rear yards that back up to the
Property. Lessard, 8/8 T. 34-35; Dipple, 8/9 T. 10-11; Aerial photo (Ex. A-8).
As amended by Ordinance No. 2012-11, Cranford Townships Land Development
Ordinance locates the Property in the Inclusionary Multi-Family Residential (IMR) zone. This
zone was created by the Township in response to the Court's December 9, 2011, Order. The
lands to the west, north and east are located in the Low Density Office District (I-O) zone. The
lots to the south, along Wadsworth Terrace, are located in the R-4 Single Family Detached
Residential zone. Site Plan shts. C-O1,C-04 (Ex. A-4).
THE PROPOSED DEVELOPMENT/REDEVELOPMENT
As set forth in the Application, the Applicant proposes to redevelop the site with two
residential buildings, a garage structure, surface parking, walkways, lawns, open spaces,
preserved woods, wetlands, wetlands buffers, and recreational amenities. In accordance with the
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
9/56
9
Courts Order of December 9, 2011, CDA proposes to construct a total of 360 dwelling units,
including 54 low and moderate income rental units. Site Plan, sht. C04 (Ex. A-4, A-14); Lessard
8/8 T. 35-36; Dipple, 8/9 T. 16-17.
Proposed Building A fronts on Birchwood Avenue. It consists of a 58 space parking
level (parking podium) with three stories of residential units above it. It includes 60 residential
units. Proposed Building B fronts on Birchwood Avenue and wraps around Proposed Building C
(the parking structure). Building B is proposed to consist of four stories containing 300
residential units. Building C fronts on the internal driveway proposed along the east side of the
Property. It is a four-level parking structure containing 520 parking spaces. There are an
additional 89 surface parking spaces proposed along the internal drive. Lessard, 8/8 T. 36-37;
Site Plan, sht. C-04 (Ex. A-4, A-14); Architectural Plan, sht. 5 (Ex. A-5); Dipple, 8/9 T. 17-19,
22-23.
At its nearest point, Building A will be approximately 545 feet from the rear property
lines of the lots fronting on Wadsworth Terrace. Lessard, 8/8 T. 95. At its nearest point,
Building B will be approximately 205 feet from the rear property lines of the lots fronting on
Wadsworth Terrace and 70 feet from the side lot line of the health care facility to the east.
Lessard, 8/8 T. 50.
Building A will have a height of 55 feet above grade, measured to the midpoint of the
roof as mandated by Ordinance 2012-112(E)(6). Lessard, 8/8 T. 43; Architectural Plan, sht. 9
(Ex. A-5). Building B will have a height of 51.8 feet above grade, again measured to the
midpoint of the roof in accordance with the Township's Ordinance. Lessard, 8/8 T. 49;
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
10/56
10
Architectural Plan, sht. 9 (Ex. 5). The top level residential units in each building will each
include a loft level which will be open to the main level of the unit. These lofts will be within
the level of the roof and will not add to the height of the building. Architectural Plan, sht. 9 (Ex.
5); Lessard, 8/8 T. 41-42,45-46. The parking structure (Building C) will have four levels, of
which the top level will be open and unroofed. Lessard, 8/8 T. 93. The floor level of the fourth
parking level will be 38 feet above grade. Architectural Plan, sht. 9 (Ex. A-5). The building
heights are in conformance with the requirements of Cranford's Ordinance.
A two-way internal driveway will form a loop through the project, providing ingress and
egress onto Birchwood Avenue at two separate points. Site Plan, sht. C-04, Dipple, 8/9 T. 16. In
conformity with the Residential Site Improvement Standards, the width of the cartway of the
driveway will be at least 24 feet at all points. Site Plan, sht. C-04, Dipple, 8/9 T. 28.
Access by residents and guests to Building A will be from the building entrance facing
the internal driveway and from the ground floor podium parking area. Access by residents and
guests to Building B will be from each level of the parking structure (Building C) and from the
building entrance facing the internal driveway. Architectural Plans, shts. 1, 3 (Ex. A-5); Lessard,
8/8 T. 39-40.
As previously authorized by the Court in the December 9, 2011, Order, the project has
been designed with a ratio of 1.85 parking spaces per unit. While not strictly in compliance with
the RSIS, the exception had been approved by the Court based upon the testimony presented
during the Builder's Remedy trial as to the types and sizes of dwelling units proposed and the
potential availability of temporary on-street parking for visitors in Birchwood Avenue, weather
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
11/56
11
permitting. Architectural Plan, sheet 1 (Ex. A-5); Dipple, 8/21 T 156, 8/22 T. 52. The parking
spaces for residents versus guests have not been separately designated on the plans. If all of the
parking spaces in the podium level of Building A are occupied, residents and guests will be free
to park in the surface level spaces between Building A and Building B, in the parking structure
(Building C), or in the surface parking spaces to the east of Buildings B and C. Residents of
units in Building A and their guests will have direct access to the spaces in Building C through
the vehicular entrance and pedestrian walkway through Building B. Architectural Plan, sheet 1
(Ex. A-5). The parking spaces provided on the Property will include 14 designated handicapped
spaces, of which two will be handicapped van spaces as required by the Uniform Construction
Code. Lessard, 8/8 T. 64-65; Dipple, 8/9 T. 24-25, 123-124.
The drop off points for persons coming to the project would be inside the parking
structure for Building B and inside the podium parking area for Building A. For anyone not
wishing to go into the parking structure or the podium level of Building A, the drop off would be
along the eastern driveway by the entrance to the parking structure for Building B and along the
western driveway for Building A. Because there are no entrances into either of the buildings
along the building facades facing Birchwood Avenue, persons would not normally be dropped
off on Birchwood Avenue. Dipple, 8/9 T. 139 -40.
All parking spaces (except the handicapped and van spaces) will be 9 feet by 18 feet in
accordance with the Residential Site Improvement Standards. Dipple, 8/9 T. 122.
Loading areas will be provided adjacent to the internal driveway near the entrance to
Building A and near the entrance to the parking structure (Building C). Dipple, 8/9 T. 26.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
12/56
12
Residents will be able to move furniture and personal possessions into and out of their residential
units on carts using the elevator and proceeding through the parking structure or parking podium
to these loading areas. Elevators and doorways are designed to be wide enough to accommodate
such carts. Dipple, 8/22 T. 57-58.
Trash will be collected inside each building, stored inside the building, and taken outside
in carts by building staff members to the driveway for pickup. Lessard, 8/8 T. 41.
Of the residential units, 54 units (15 percent of the total) will be reserved for occupancy
by and will be affordable to low and moderate income households. Lessard, 8/8 T.35-36. In
conformity with the Rules of the New Jersey Council on Affordable Housing, the Applicant
proposes that 11 units will be three-bedroom units, 32 units will be two bedroom units and 11
units will be one bedroom or studio units. Lessard, 8/8 T. 141.
COMPLIANCE WITH STANDARDS IN ORDINANCE NO. 2012-11 AND THE COURTS
ORDER OF DECEMBER 9, 2011
The proposed structures comply with all the bulk standards set forth in Ordinance No.
2012-11 and the Courts order of December 9, 2011:
Required Proposed
Minimum tract area 15 acres 15.86 acres
Minimum lot frontage 750 feet 825.84 feet
Minimum front yard setback 25 feet 25 feet
Minimum average front year setback 30 feet 44.36
Minimum side yard setback 55 62.37
Minimum rear year setback 175 196.75
Maximum impervious coverage 31.21% (existing
impervious coverage)
31.1%
Maximum height 55 feet
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
13/56
13
Maximum heightBuilding A One parking level and
three residential levels
One parking level and
three residential levels
Maximum heightBuilding B Four residential levels Four residential levels
Minimum distance between multi-family
buildings
25 feet 57.71 feet
Minimum buffer to eastern lot line 10 feet 10 feet
Minimum buffer to rear lot line 175 feet 175 feet
Minimum parking spaces 666 667
Site plan, sht. C-04 (Ex. A-4); Dipple, 8/9 T. 19-21.
As presented, the proposed site plan contains an error. At the easternmost ingress/egress
driveway, the internal driveway is drawn too close the eastern lot line, leaving only an eight foot
buffer. Dipple, 8/9 T. 22; Site Plan, C-04 (Ex. A-4, Ex. A-14). The Applicant has agreed to
straighten the driveway and move it two feet to the west, which will eliminate that error and
bring the site plan into conformance with the bulk standards in Ordinance No. 2012-11 and the
Court Order. Dipple, 8/9 T. 22.
Subject to two requested waivers, and the correction of the above-described site plan
error, the Application conforms in all respects to the terms of Cranfords Land Development
Ordinance, as amended by Ordinance No. 2012-11, and the Court's Order of December 9, 2011.
Dipple, 8/9 T. 148.
Issues as to compliance of the proposed structures with the Uniform Construction Code
were raised in the report of Construction Code Official Belluscio. (Ex. D-1). These issues were
addressed in the testimony of the Applicant's Architect. Lessard 8/8 T. 50-69. The Township
did not present testimony by Belluscio or by any other witness on these issues. The Municipal
Engineer testified that certain issues had been resolved by the testimony of Lessard. Marsden,
8/22 T. 143, 186. Counsel for Cranford Township has requested that the Township have the
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
14/56
14
right to address any non-site plan issues of Construction Code compliance at the time the
Applicant applies for Construction Permits.
COMPLIANCE WITH RESIDENTIAL SITE IMPROVEMENT STANDARDS (RSIS)
Except for the parking ratio, which was previously addressed and specifically authorized
by the Court, the Applicant has designed the project to comply with the Residential Site Plan
Improvement Standards. Dipple, 8/9 T. 28, 121, 126, 8/21 T. 156, 8/22 T. 24, 98. The
Township has not identified any violations of the Residential Site Plan Improvement Standards.
INFRASTRUCTURE
According to the testimony of the Applicant's traffic expert, the additional traffic
generated by the project will not exceed the capacity of Birchwood Avenue. It will have only a
small impact on the intersections of Birchwood Avenue with Cranford Avenue and
Bloomingdale Avenue. Those intersections will continue to function at acceptable levels. The
Birchwood Avenue northbound approach to Orange Avenue will operate at Level ofService E
during the morning peak hour, which is a minimum level of acceptability. J. Staigar, 8/22 T.
111-112. No improvements were recommended, however, to enhance the Level of Service or
increase traffic safety. E. Dolan, 8/8 T. 161-230; J. Staigar, 8/22 T. 105-129; E. Dolan, Traffic
Impact Assessment (Ex. A-11); E. Dolan, Supplemental Traffic Impact Assessment (Ex. A-24);
Staigar, Letter to P. Morin (Exs. D-2 and D-14).
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
15/56
15
Fire Chief Leonard Dolan, who was offered and accepted as an expert in the field of fire
safety and design, expressed the following concerns about the layout of the site plan:
a. the angle at which the internal driveway meets Birchwood Avenue at the
easternmost ingress/egress may impede access by Cranfords fire equipment;
b. the turning radius of the internal driveway around the south end of Building B
may impede access by Cranfords largest fire truck; and
c. during any flood event that restricts access to the project through the westernmost
ingress/egress, the width of the internal driveway may be too narrow to accommodate Cranfords
largest truck plus permit access by other vehicles to Building A.
L. Dolan, 8/23 T. 107-125; L. Dolan Memorandum (Ex. D-17).
To address these issues, the Applicant has agreed to:
a. straighten the eastern ingress/egress;
b. increase the turning radius on the interior drive around the south end of Building
B to 30 feet;
c. provide mountable curbs along the internal drives; and
d. provide turnouts at various points along the internal driveway.
In this regard, the Applicant has agreed to submit a revised Site Plan to the Township and to the
Court evidencing compliance with all of these representations. Dipple, 8/9 T. 28-29, 125-126,
132; Truck Turning Diagram (Ex. A-15); Marsden, 8/22 T. 144-45; L. Dolan, 8/23 T. 130-131;
L. Dolan, 8/23 T. 122-25.
Chief Dolan also expressed concerns about the adequacy of access to the site under
severe flooding conditions that might make Birchwood Avenue impassable. He was particularly
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
16/56
16
concerned about the ability of emergency equipment to access the site during flooding conditions
given the depth of the Property and its relatively limited roadway frontage, especially at times
when the westerly driveway would be inaccessible. L. Dolan 8/23 T. 114-117. Elevation of
Birchwood Avenue to one foot above the flood hazard design elevation as shown on the Site
Plan (Site Plan, shts. C-04, C-19 (Ex. A-4)) would provide at least one point of access in a 100-
year flood event. L. Dolan, 8/23 T. 113. The elevation of Birchwood Avenue would satisfy the
NJDEP regulatory requirements. Dipple, 8/9 T. 127.
The Township did not embrace the testimony offered by the Applicant as to the public
safety efficacy of this solution, despite the fact that neither the Township nor Chief Dolan had
raised any objection when the Township was reviewing and approving a similarly situated
development known as the "Riverfront Redevelopment Project". That multifamily development
had been approved by the Township despite the fact that the development itself and all of the
surrounding streets lie within and remain below the elevation of the State-designated flood
hazard area. L. Dolan, 8/23 T. 136-39; L. Dolan Review Reports on Site Plan Application for
Riverfront Redevelopment Project (Ex. A-28); Dipple, 8/9 T. 86-89; Flood Hazard Area Permit
for Riverfront Redevelopment Project (Ex. A-22). In its attempt to justify this obvious
inconsistency, the Township argued that the Riverfront Redevelopment Project: a) is located
only one quarter mile from the Cranford Fire Station while the Applicants Property is over a
mile away; and b) the Riverfront Development has access from three public streets as compared
to the Applicants Project, which has frontage on only one street and on which the developable
area is exceptionally deep with limited exposure to the street frontage. L. Dolan 8/23 T. 142-
142, 116.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
17/56
17
Water for domestic consumption and fire suppression will be provided through
connection to Cranford Townships public water system. Dipple, 8/9 T 29-32. The parties were
in dispute at the Hearing as to whether the public water system will provide enough water to the
site for fire suppression. If the existing system were to be determined to provide an inadequate
supply of water for fire suppression purposes, possible solutions proposed by the Township
included: a) replacing the existing water main along Birchwood Avenue with a 12 inch pipe
extending from the hydrant at the east end of the Property to Bloomingdale Avenue and
increasing the size of the looped water line on the site to 12 inches; and b) providing a second
connection to the looped system on the Property from the adjacent nursing home property. L.
Dolan, 8/23 T. 128, 133-34; Dipple, 8/9 T. 32. Providing a fire pump at grade level would assure
sufficient water pressure for fire suppression at all levels in Buildings A, B and C. Lessard, 8/8
T. 86-87.
Sanitary sewage service is to be provided by connection to the Cranford Township
sanitary sewer system. Treatment for this system is provided by the Rahway Valley Sewage
Authority in Rahway, which has sufficient capacity. Dipple, 8/21 T. 172.
Cranfords sanitary sewage conveyance system is old. Most of the line that runs between
the Property and the Roselle Park border is 40 to 60 years old, and some stretches, constructed at
the same time as the Garden State Parkway or earlier, are at least 64 years old. Marsden, 8/23 T.
27-30. As a result, the system suffers from a serious problem of inflow - surface water entering
the system - and infiltration - groundwater entering the system. Marsden, 8/22 T. 158, 160. The
system has had relatively few failures - four lines breaks within the entire municipality over the
last eight years. Marsden, 8/23 T. 31-32. Two of these breaks, however, have occurred in the
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
18/56
18
past year in the stretch of line between the Garden State Parkway and the Roselle Park border,
which is part of the system that would serve the project. Marsden, 8/23 T. 30-34.
Based upon the Sanitary Sewer Capacity Study, the Existing Sanitary Sewer Map (Ex.
A-17) and measurement of existing flow through the pipes in the sanitary sewer system between
the Property and the Roselle Park border, the system has sufficient existing capacity to provide
service through simple gravity driven flow (open channel flow), except for three stretches of
pipe. As shown on the Existing Sanitary Sewer Map (Ex. A-17), each of these three stretches is
essentially flat; consequently, a mathematical analysis that assigns a value of zero to slope
under a simple gravity flow (open channel flow) model shows these stretches as having no
capacity. This "technical" lack of capacity is thus not a function of the sizes of the pipes but of
the lack of slope in certain areas. The Applicants Engineer testified that a field survey indicated
that one of these three stretches of pipe actually has adequate slope and functions properly and
safely using gravity flow under both average and peak flow conditions, although the data
supporting this conclusion were not presented at the Hearing. The two remaining stretches of
pipe operate properly and safely under average and peak flow conditions using pressurized flow -
described as surcharged flow (in which the pressure created by the effluent itself actually carries
the flow through the flat stretch of pipe). If the flow slows down, it backs up to a point that it
eventually creates the pressure needed to force it through the pipe. Dipple, 8/9 T. 35-40; 8/21 T.
103-105; 8/22 T. 37-40; Sanitary Sewer Capacity Study, Tables 1 and 2 (Ex. A-14).
Based upon the original Project design - for 422 units - 83,850 gallons per day would
have been added to the system, based on NJDEP design standards. Sanitary Sewer Capacity
Study, Table 3 (Ex. A-14). At 83,850 gallons per day, the system would operate properly and
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
19/56
19
safely under average and peak flow conditions. The currently proposed Project, for 360 units,
will generate lower flows than the original design would have generated. In the opinion of the
Applicants Engineer, all of the stretches that currently operate through simple gravity flow will
continue to do so properly and safely, and all of the stretches that operate through pressurized
flow (under surcharged conditions) will continue to do so properly and safely. Moreover, it is
the opinion of the Applicants Engineer that the additional flow from 360 units will not cause
any stretch of pipe to transition from simple gravity flow to pressurized flow. Dipple, 8/9 T. 35-
40; 8/21 T. 103-105; 8/22 T. 37-40, 91-93; Marsden, 8/23 T. 39.
The Applicants Engineer testified that under a more sophisticated evaluation - known as
a hydraulic grade line study -- it was determined that even where the system is currently
operating under surcharged or pressurized conditions, the level of flow does not rise above the
level of the pipes, i.e., it does not rise into the manholes above the pipes. Moreover, in the
opinion of the Applicants Engineer, due to the depth of the sewer pipes, the backups that
routinely occur in the stretches of sewer line that operate under surcharge or pressurized
conditions will not result in the effluent rising above the levels to which it currently rises and
into the manholes, even under peak conditions. Dipple, 8/22 T. 40-42, 91-93. It was the
conclusion of the Applicants Engineer that the existing sewerage system will operate safely and
effectively even with the additional flow. Dipple, 8/9 T. 137-38; 8/22 T. 37-42, 46, 91-93.
Cranfords Engineer, Richard Marsden, expressed "concerns" that, given the age of the
existing system, the additional flows from the project, which he characterized as substantial,
when combined with the existing flows and the existing (unremediated) inflow and infiltration
would create a potential risk of future line breaks, although he could not quantify the degree of
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
20/56
20
risk. Marsden, 8/22 T. 155-162; 8/23 T. 27. Marsden recommended that approximately 1,300
linear feet of off-tract sewer pipe be re-lined in order to reduce inflow and infiltration and to
increase the integrity of the existing pipe, reducing friction and enhancing flow-through. In
Marsdens opinion, such measures would decrease the incidence of pressurized or surcharge
flow. Marsden, 8/22 T. 161. Marsden opined that the Applicant would have substantial
responsibility for this off-tract improvement, but was unable to specify the magnitude of CDAs
pro-rata share of such an improvement. Marsden, 8/22 T. 161-172.
In light of the unresolved issue concerning the extent, if any, of the Applicants
responsibility for sanitary sewerage improvements under Section 136-27 of Cranfords Land
Development Ordinance, which addresses off-tract improvements, the Hearing Officer
recommended that the parties meet to attempt to resolve the issue and report back to the Court
and the Special Master as to whether or not the issue has been resolved.
COMPLIANCE WITH WETLAND, STORM WATER MANAGEMENT, AND FLOOD
HAZARD AREA STANDARDS
The Property includes areas of State-regulated freshwater wetlands and State-regulated
wetlands transition areas. Based upon the calculations provided by the Applicants experts, and
subject to NJDEP review and approval, the Project has been designed to avoid any infringement
on regulated freshwater wetlands. The Project will intrude into required freshwater wetlands
transition areas, and, in accordance with NJDEP regulations, the Applicant has applied to the
NJDEP for approval of a freshwater wetlands transition area averaging plan and will comply
with all NJDEP regulations concerning construction within and in the vicinity of a wetlands
transition area. Dipple, 8/9 T. 42-44, 46-47, 144-145.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
21/56
21
Notice of the applications for both the Flood Hazard Area Permit and Wetlands Permit
was provided as required by the NJDEP. Public Notices of CDA Application for Flood Hazard
Area Permit and Wetlands Permit (Ex. A-19).
The Townships Engineer (Marsden) suggested that construction of a short stretch of pipe
will require approval of a permit by the NJDEP. Marsden, 8/22 T. 156, 187. The Applicants
Engineer testified that if NJDEP determines that a general permit is required for that particular
stretch of pipe, such a permit is routinely available under NJDEPs regulatory standards for a
General Permit 2 and would be requested. Dipple, 8/9 T. 44-45, 135-136.
Township Engineer Marsden expressed a number of concerns as to the impact of the
Project on freshwater wetlands. All of these objections may appropriately be raised with the
NJDEP prior to final approval of the application by the NJDEP, and Cranford Township and
individual members of the public are entitled to voice any objections they may have to such
application. Dipple, 8/9 T. 47. Indeed, Cranford has already participated in the NJDEP review
process and has submitted its objections. Marsden, 8/23 T. 14-16; Letter from R. Marsden to
Engineering Supervisor for Union County, NJDEP, January 3, 2012 (Ex. A-26); Memorandum
from R. Marsden to V. Opara, NJDEP, August 2, 2012 (Ex. A-27).
As the Project will disturb more than one acre of land, it is subject to New Jerseys
Stormwater Management Regulations. Dipple, 8/9 T. 48. The NJDEP regulations are
incorporated by reference into the Residential Site Improvement Standards. Dipple, 8/9 T. 48.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
22/56
22
As part of its Flood Hazard Area Permit application, the Applicant has filed for NJDEP approval
of the stormwater management plan for the Project. Dipple, 8/9 T. 43.
The States Stormwater Management Regulations encompass four areas of regulation:
a. storm water quantity;
b. storm water quality;
c. infiltration to ground water; and
d. nonstructural strategies or best management practices.
The Applicant's Engineer testified that the Project is specifically designed to meet the applicable
standards within each of these areas to the extent applicable and subject to NJDEP approval of
the methodology and resulting calculations. Dipple, 8/9 T. 48.
The Applicant's Engineer testified that the NJDEP water quality standards do not apply to
the Project; the water quality standards only apply to projects that will increase the existing
impervious coverage. The Project will actually reduce impervious coverage from 31.21 percent
(existing) to 31.1 percent (proposed). Site plan, sht. C-04 (Ex. A-4); Dipple, 8/9 T. 19-21, 49.
The NJDEP groundwater recharge standards do not apply to sites within areas designated
on the State Plan as the Metropolitan Planning Area (PA-1). The Property is within PA-1, the
Metropolitan Planning Area. Dipple, 8/9 T. 49-50.
With respect to the stormwater quantity standard, the Project has been designed in
accordance with NJDEP regulations to reduce the peak rate of run-off below existing conditions
for the two-year, ten-year, and one-hundred-year storm events. The rate of run-off for the two-
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
23/56
23
year storm must be reduced by 50 percent, the ten-year storm by 25 percent, and the hundred-
year storm by 20 percent. The Project will satisfy these standards by providing for stormwater
storage in and controlled discharge from a large underground detention basin to be constructed
under the surface parking area on the east side of Buildings B and C. Dipple, 8/9 T. 51-52 and
8/21 T. 122-24; Site Plan sht. C-05 (Ex. A-4). The Applicants Engineertestified that, based on
the modeling that was undertaken in accordance with NJDEP standards, the Project will reduce
peak stormwater run-off (in cubic feet per second) as follows:
Storm event Existing
conditions peak
runoff rate
Proposed
conditions peak
runoff rate
Reduction Proposed rate
as percent of
existing rate
2 17.89 3.66 14.23 20%
10 24.59 11.86 12.73 48%
100 37.03 28.16 8.87 76%
Dipple, 8/9 T. 53-54 and 8/21 T. 117-118; Engineering Report, Table E-1 (Ex. A-6).
As required by the NJDEP, the rate of runoff for each storm was modeled taking into
account all existing conditions, including existing buildings, parking lots and drainage structures.
Dipple, 8/9 T. 56-57 and 127-28; Site Plan, sht. C0-2 (Ex. A-4).
Cranford Engineer Marsden raised various technical concerns about the stormwater
management plan and the calculations upon which it is based, claiming that CDAs Engineer
failed to properly account for existing drainage structures, improperly calculated the time of
concentration, and did not consider "tail water" effects. R. Marsden, 8/22 T. 134-137, 190-199;
Memorandum from R. Marsden to P. Morin, 7-20-12 (Ex. D-4).
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
24/56
24
These concerns were rebutted by CDAs experts, Dipple and Emerson, both of whom
stated that the drainage structures had been modeled in their existing condition. Dipple, 8/9 T.
56-57, 127-28, 145-47; 8/23 T. 101-103. According to Emerson, Marsdens critique of the time
of concentration analysis was based upon a methodology not used in CDAs study and not
permitted by NJDEP. Emerson, 8/23 T. 166-67. Further, under NJDEP regulations, "tail water"
effects must be dealt with by incorporating a mechanical backflow preventer in the detention
basin, which CDA has done. Emerson, 8/23 T. 168. Emerson acknowledged that he is not
licensed as a Professional Engineer in the State of New Jersey and that he had not viewed the
subject property during a storm event.
The NJDEP has jurisdiction over CDA's stormwater management plan in the context of
CDAs application for a flood hazard area permit, and objections to the Applicant's storm water
management plan (if any) can, and should, be directed to the NJDEP, which, in fact, Township
Engineer Marsden has already done on behalf of Cranford. Marsden, 8/23 T. 14-16 ; Letter from
R. Marsden to Engineering Supervisor for Union County, NJDEP, January 3, 2012 (Ex. A-26);
Memorandum from R. Marsden to V. Opara, NJDEP, August 2, 2012 (Ex. A-27).
The property includes areas within the state regulated floodway and the state regulated
flood fringe. Site Plan, sht. C-02; Dipple, 8/9 T. 58. Flooding conditions on the site are largely
due to stormwater flowing from developed areas north of the site and also due to stormwater
backing up from an undersized culvert under Wadsworth Terrace, which lies to the south of the
site. Dipple, 8/9 T. 58-59; Marsden, Flood Hazard Map (D-15).
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
25/56
25
As described by the Applicant's Engineer, the flood hazard area consists of the entire area
that would be flooded in a state-defined flood hazard area flood event - a 100-year storm plus
an additional flow rate of 25 percent. It is the area contiguous to the stream which lies below the
flood hazard area elevation - the maximum elevation of flood waters in a flood hazard area
flood event. The floodway is that portion of the flood hazard area which would actually carry
the downstream flow of water during a flood hazard area flood event. Its boundaries are
determined using a model approved by the NJDEP. The flood fringe is the remainder of the
flood hazard area and consists of areas of little or no velocity where storm water "ponds" and is
stored during a 100-year flood event; the flood fringe areas do not actually carry the downstream
flow. Dipple, 8/9 T. 65-68, 72; NJDEP Flood Hazard Area Diagram (Ex. A-20).
As part of its flood hazard area permit application, the Applicant's experts modeled
Branch 10-24, determined its flood hazard area elevation, and delineated its floodway boundary
and flood hazard area boundary based upon existing conditions on the site, all in accordance with
the NJDEP-approved methodology. Dipple, 8/9 T. 59-65, 72; Dipple Engineering Report, sht.
FS-01 (Ex. A-6); Site Plan, sht. C-02 (Ex. A-4). As required by the NJDEP-approved
methodology, the model included the existing office building and parking lot at 235 Birchwood
Avenue, both of which are located in the floodway. Dipple, 8/9 T. 64-65; Emerson, 8/23 T. 150-
151. The flood hazard area elevation is at a level of 78.6 feet (above the level of the base point).
Dipple, 8/9 T. 72. The floodway boundary and the flood hazard area boundary are shown on the
site plan. Site Plan sht. C-04 (Exs. A-4, A-14); Dipple, 8/9 T 13-14.
Cranford Engineer Marsden expressed concerns about the correctness of the methodology
used for determining the location of the floodway boundary, including that it did not follow
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
26/56
26
existing topographic contour lines, that it was improperly affected by the existing office building
at 235 Birchwood Avenue, and that it did not split the flow of flood waters coming from the
north side of Birchwood Avenue between stormwater piping under the street and surface flow
over the street. Marsden, 8/22 T. 138-140, 8/23 T. 61-72; Marsden Memo to P. Morin (Ex. D-4).
The NJDEP has sole and exclusive jurisdiction over the issuance of flood hazard area
permits and is thus the proper forum for these kinds of technical objections. Objections have
already been made in the form of letters from Engineer Marsden to the NJDEP on behalf of
Cranford Township. Marsden, 8/23 T.14-16, 72-75; Letter from R. Marsden to Engineering
Supervisor for Union County, NJDEP, January 3, 2012 (Ex. A-26); Memorandum from R.
Marsden to V. Opara, NJDEP, August 2, 2012 (Ex. A-27).
Notwithstanding the absence of any local jurisdiction over such matters, Marsden's
concerns were addressed and contradicted by CDAs experts, Engineer Dipple and Dr. Emerson,
both of whom testified that according to NJDEP standards the floodway boundary is required to
be determined utilizing existing conditions, including the existing structures, and cannot lawfully
be determined any other way. Further, since the determination of the floodway is based upon a
conceptual computer model of the area required for the flow of floodwaters, the floodway need
not, and typically does not, follow existing topographic contour lines. Finally, the computer
model expressly splits the flow between the storm water conduits under Birchwood Avenue and
surface flow. Dipple, 8/9 T. 129-130; Emerson, 8/23 T 147-157; Letter Report, M.E. Dipple and
C. Emerson, Aug. 6, 2012 (Ex. A-13).
Upon cross-examination by Mr. Eisdorfer, Marsden acknowledged that:
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
27/56
27
a. he had reviewed the floodway boundary determinations made by Dipple in the
summer of 2010;
b. he had an opportunity to request the underlying data from Dipple at that time;
c. he had testified on the floodway boundary issue at the Builder's Remedy trial;
d. he had reviewed the floodway boundary determination again in December, 2011,
in connection with CDAs flood hazard area permit application to the NJDEP;
e. he had filed objections to that application; and
f. while he had the knowledge and experience to run the standard computer model
himself to determine the floodway boundaries, he did not actually do so.
Marsden, 8/23 T. 6-18, 64. As a result, he could not testify that the floodway boundary as
determined by Dipple and Emerson was actually incorrect nor could he quantify the magnitude
of any alleged error. Marsden, 8/23 T. 18, 64. Finally, Marsden conceded that NJDEP
regulations require the floodway to be determined based on existing conditions at the time of
application and not based on proposed changes to those conditions. Marsden, 8/23 T. 82-83.
Consistent with NJDEP regulations, the Project does not involve any construction in the
floodway as determined by the Applicant's Engineer and delineated on the Site Plan. 8/21 T. 89;
Site Plan, sht. C-04 (Ex. A-4). Rather, the Applicant proposes to demolish and remove the
existing office building and parking lot currently located within the floodway. Dipple, 8/9 T. 65;
Site Plan, sht. C-03 (Ex. A-4). According to the Dr. Emerson, this will improve the functioning
of the floodway and actually reduce the area of flood flow. Emerson, 8/23 T. 151.
The Project, as proposed and as submitted to the NJDEP in connection with the flood
hazard area permit application, includes construction in the flood fringe area, including Building
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
28/56
28
A and a portion of the internal driveway adjacent to Building A. Buildings B and C and the
remainder of the internal driveway are entirely outside of the flood fringe area. Site Plan, sht. C-
04 (Exs. A-4, A-14).
Under NJDEP standards, construction is permitted in the flood fringe provided the State's
regulatory standards are met:
a. the project may not reduce the amount of flood storage in the flood fringe area;
b. all residential units within the flood fringe area must be at least one foot above the
flood hazard area design elevation;
c. to the extent possible, all required parking for residential units within the flood
fringe area must be at least one foot above the flood hazard area design elevation; and
d. for all public buildings within the flood fringe, the roadway must provide at least
one emergency exit route that is at least one foot above the flood hazard area design elevation.
Dipple, 8/9 T. 72.
The Applicant's Engineer testified that the project was designed to comply with NJDEP
standards for a flood hazard area permit. Dipple, 8/9 T. 72. The design includes a calculation of
the amount of flood storage within the flood fringe under existing conditions. Engineering
Report, sht. FS-1 (Ex. A-6). It also includes a grading plan designed to assure that the project
would not reduce the amount of flood storage within the flood fringe area during any of the
relevant potential flood events including the flood hazard area flood event. Dipple, 8/9 T. 70-71.
The plan includes providing for crawl spaces under Building A to provide additional flood
storage within the flood fringe area consistent with NJDEP regulations. Dipple, 8/9 T. 74-75;
Architectural Plans, sht. 9 (Ex. A-9). According to Dipple's calculations, the project will
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
29/56
29
increase the amount of flood storage during a 100-year storm event from 318,182.9 cubic feet
under existing conditions to 321,838 cubic feet under proposed conditions. Dipple, 8/21 T. 129-
130; Site Plan, shts. C-10, C-14.
The project design provides that all the residential units in Buildings A will be elevated to
a level at least 11 feet above the flood hazard elevation, thereby satisfying the requirement that
the units all be at least one foot above the flood hazard design elevation. Lessard, 8/8 T. 37, 45;
Architectural Plans, sht. 9 (Ex. A-5).
All of the parking is proposed to be elevated to a level at least one foot above the flood
hazard area design elevation. Lessard, 8/8 T. 44; Architectural Plans, sht. 9 (Ex. A-5).
Ingress/egress to and from the Property will is available even during a flood hazard area flood
event via the easternmost driveway, which is proposed to be elevated one foot above the flood
fringe area. Dipple, 8/9 T. 72; Site Plan, sht. C-03.
The Site Plan was submitted to the NJDEP as part of CDA's flood hazard area permit
application in December, 2011. NJDEP issued a deficiency notice on February 8, 2011,
requesting more information and changes in the design of the underground detention basin.
Dipple, 8/9 T. 76-77, 8/22 T. 94-97. The Applicant made the changes requested by the NJDEP
and submitted the revisions along with the required additional information. Dipple, 8/9 T. 76-77;
8/22 T. 94-97.
On March 8, 2012, NJDEP issued a new deficiency notice. Dipple, 8/9 T. 78-79; NJDEP
Deficiency Notice, March 8, 2012 (Ex. A-21). The new deficiency notice requested additional
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
30/56
30
documentation and also identified a substantive deficiency - a violation of N.J.A.C. 7: 13-11.5(h)
(Ex. A-23). It advised that the application, as submitted, would require a hardship waiver under
N.J.A.C. 7:13-9.8. Dipple, 8/9 T. 81-85.
Dipple reported that he had been informed via a telephone communication and a
subsequent meeting with NJDEP representatives that the deficiency was with respect to N.J.A.C.
7:13-11.5(h)(2), which provides in part:
(h) The Department shall issue an individual permit to construct or reconstruct a publicbuilding only if the following requirements are satisfied:....
2. For a new building in a fluvial flood hazard area, the applicant demonstratesthat the building is served by at least one roadway, the travel surface of which is
constructed at least one foot above the flood hazard area design flood elevation.
According to Dipple's testimony, NJDEP informed the Applicant that the deficiency lies
with the fact that Building A, which is a public building under the NJDEP regulations and is
located in the flood hazard area, lacks a roadway that is elevated "at least one foot" above the
flood hazard area design flood elevation. The NJDEP deems the portion of Birchwood Avenue
on which the Property fronts to be the roadway" to which this requirement applies, and both
driveways that serve Building A exit onto portions of Birchwood Avenue that lie at elevations
lower than the flood hazard area design flood elevation. Dipple, 8/9 T. 79-81, 84-85.
Dipple indicated that this determination was unexpected as it differed from the NJDEP's
historical interpretations as evidenced by its determinations in two other projects, including a
project constructed by the same developer in Englewood and another project in Cranford, the
Riverfront Redevelopment Project, for which the NJDEP had granted a flood hazard area permit
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
31/56
31
in February, 2010, while expressly noting in the permit that all of the surrounding streets are
located in the flood hazard area. Dipple, 8/9 T. 86-89; Flood Hazard Area Permit for Riverfront
Redevelopment Project (Ex. A-22).
Upon cross-examination, Dipple acknowledged that his knowledge of the Riverfront
Redevelopment Project was based on a review of file material and not from any direct
involvement with that project, and he also acknowledged that the permit for the Englewood
project had been a stream encroachment permit (the precursor to the flood hazard area permit)
that had been issued in 2003, prior to the adoption of the current NJDEP flood hazard area
regulations. Dipple, 8/21 T. 13-14. Further, Dipple admitted that he had not discussed this
aspect of the new regulations with NJDEP prior to submitting the flood hazard area permit
application for the CDA Project and that he had initially been of the opinion that a flood hazard
area permit would not even be required for the Project. Dipple, T. 16, 20-23.
According to Dipple, upon learning of NJDEP's position, the Applicant explored various
options for complying with N.J.A.C. 7:13-11.5(h)(2). The Applicant first considered extending
an emergency access from the back of the property onto North Union, but rejected this option
because the North Union access would likewise not be one foot above the flood hazard elevation
for its full length and, therefore, would also violate NJDEP regulations. Dipple, 8/9 T. 100-101.
Dipple indicated that the Applicant also attempted to secure the consent of the owner of the
health care facility to construct an access drive to that property, which access drive would have
been entirely outside of the flood hazard area, but that the owner had not responded to CDAs
repeated inquiries. Peter Hekemian, a principal of CDA, also testified as to the efforts to contact
the owner of the health care facility. Dipple, 8/9 T. 100; P. Hekemian, 8/9 T. 155, 156-157.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
32/56
32
According to Dipple, CDA concluded that the most promising means of complying with
N.J.A.C.:13-11.5(h)(2) and avoiding the necessity of seeking a hardship waiver (the approach
that had been recommended by the NJDEP), would be to elevate Birchwood Avenue in the
vicinity of the easternmost driveway of the project. Dipple, 8/9 T. 101.
As shown on the site plan application, CDA proposes to regrade a portion of Birchwood
Avenue at CDA's sole cost and expense so that it will be one foot above the flood hazard
elevation at the point the road crosses in front of the Projects easternmost driveway. This will
require the level of the roadway to be raised by 1.28 feet in that location. To effect a transition
between the proposed elevation at the easternmost driveway and the existing elevation of
Birchwood Avenue in the direction of Orange Avenue, about 300 linear feet of the roadway will
need to be included in the regrading. Dipple stated that, after the regrading, the road will run
gradually downhill toward Orange Avenue, as it does now, and opined that the resulting change
in elevation would be slight and probably unnoticeable. Dipple, 8/9 T. 90-93; 8/21 T. 86, 132-
133; Site Plan, shts. C-05, C-18, C-19 (Ex. A-4). The regrading will require the replacement of
driveway aprons at one of the driveways to the health care facility and at the driveway to the
municipal recycling facility; additionally, a portion of the sidewalk in front of the health care
facility would need to be replaced. All of these improvements would be undertaken within the
municipal right of way. Dipple, 8/9 T. 99; 8/22 T. 64. Dipple also stated that the scope of the
proposed improvements would include the addition of three new storm drains along Birchwood
Avenue, which could be expected to improve drainage for properties along Birchwood Avenue.
Dipple, 8/9 T. 96-97, 8/21 T. 134-36; Site Plan, pp.C-05 (Ex. A-4).
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
33/56
33
According to Dipple, the proposed regrading of Birchwood Avenue will add fill within
the flood fringe, thus requiring the Applicant to compensate for the loss of flood storage due to
the additional fill. Accordingly, the Project has been redesigned to provide the additional flood
storage elsewhere on the site in order to comply with NJDEP requirements. Dipple, 8/9 T. 93-
94.
Dipple testified that the proposed regrading will also cause the flood hazard area
boundary to be adjusted to a point west of the easternmost driveway. However, he determined
that this would not affect the flood hazard elevation, because any flood storage lost by the
regrading of Birchwood Avenue would be offset by newly created flood storage on the Property.
As a result, there will be no increased flooding on the upstream properties (to the north of
Birchwood Avenue) or on properties to the west along Birchwood Avenue that are in the flood
hazard area, and there will be no impact on properties to the east along Birchwood Avenue
(which will continue to be outside of the flood hazard area). Dipple also opined that the
regrading of Birchwood Avenue would not negatively affect drainage, because there would be no
increase in the amount of impervious coverage; in fact, drainage would be improved by virtue of
the additional storm drains proposed in Birchwood Avenue. Dipple and Dr. Emerson both
concluded that the proposed regrading of Birchwood Avenue would have no detrimental effect
on other properties or residents of Cranford. Dipple, 8/9 T. 84-100, 149-150; Emerson, 8/23 T.
163.
Dipple's conclusions as to the absence of any upstream impact were questioned by
Cranford Engineer Marsden and later by Cranford Consulting Engineer Creelman since the
Township had not been provided with any of the calculations or modeling upon which Dipple
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
34/56
34
presumably relied in reaching his conclusions. Marsden, 8/22 T. 145-152; Creelman 8/23 T. 90-
99. Marsden and Creelman were both concerned that moving the flood hazard boundary further
west on Birchwood Avenue would increase the flood hazard elevation and generally increase
flooding along Birchwood Avenue. Creelman opined that there were insufficient cross-sections
to enable a valid evaluation of the upstream impact. Creelman, 8/23 T. 90-98. Marsden agreed,
and noted that neither Dipple nor Emerson had accounted for the fact that floodwater flows into
the area north of Birchwood Avenue from Kenilworth to the northwest. As such, Marsden stated
his belief that flooding would increase on properties north of Birchwood Avenue. Marsden, 8/22
T. 145-154; Memorandum from R. Marsden to P. Morin, 7-20-12 (Ex. D-4); E-mail from P.
Morin to D. Cohen, 8-3-12 (Ex. D-9).
In light of NJDEP's sole and exclusive jurisdiction over the flood hazard area permit,
these objections must be adjudicated by the NJDEP. Marsden has, in fact, made Cranford's
objections known to the NJDEP by way of multiple letters objecting to the issuance of the flood
hazard area permit. Marsden, 8/23 T. 14-16 ; Letter from R. Marsden to Engineering Supervisor
for Union County, NJDEP, January 3, 2012 (Ex. A-26); Memorandum from R. Marsden to V.
Opara, NJDEP, August 2, 2012 (Ex. A-27).
In response, CDAs experts, Engineer Dipple and Dr. Emerson, both explained that, even
in a flood hazard area flood event, floodwater flows within the floodway. In their view, the
proposed change in the boundary of the flood hazard area (at a considerable distance from the
floodway, and involving a relatively small amount of fill) will have no effect on the overall flood
hazard area elevation. The entire flood fringe area is hydraulically interconnected and is
dominated by the effect of the undersized conduit under Wadsworth Terrace. Thus, the flood
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
35/56
35
fringe functions as a single lake. All of the floodwater throughout the entire flood fringe area
is stored at the same elevation. Floodwater that is temporarily unable to flow downstream
through the floodway is stored in the flood fringe area until it can, in due course, be released into
the floodway. Elevating the road will not change this. Since the geographic source of the
floodwater is immaterial to the function of the flood fringe area, there is no scientific justification
for a geographically divided analysis. Dipple, 8/9 T. 132-33; 8/21 T. 45-46, 49-50, 93-96, 142;
8/22 T. 88-89; Emerson, 8/23 T. 157-163, 165-68, 174-75, 180; Letter Report, M.E. Dipple and
C. Emerson, Aug. 6, 2012 (Ex. A-13). The Hearing Officer finds the analysis by CDA's experts
to be credible and accepts this testimony as valid.
As to fire safety, the Applicant did not provide any testimony from an expert of its own,
but, instead, relied on the conclusions of the Township's fire safety expert, Chief Dolan, that
elevating Birchwood Avenue at the eastern entrance to the Property will provide a safety benefit
because it will assure at least one point of access for fire fighting and other emergency vehicles
in the event of a flood hazard area flood event. L. Dolan, 23. T. 113; N.J.A.C. 7:13-11.5(h)(2).
Dipple acknowledged that if the proposed regrading of Birchwood Avenue were not
approved by Cranford and the Applicant is unable to obtain a hardship waiver from the NJDEP,
it will be impossible for CDA to build the proposed Project, due to its inability to obtain the
necessary flood hazard area permit from the NJDEP.1
Dipple, 8/9 T. 152-153; Dipple 8/21 T.
142-143.
______________________________________________________________________________
1It is the Township's position that the Applicant should seek the hardship waiver recommended by the NJDEP
before seeking permission to regrade Birchwood Avenue. The Township does not believe it has sufficient
information on which to base a decision to allow the grade of Birchwood Avenue to be altered nor does it accept
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
36/56
36
LANDSCAPING, TREE REPLACEMENT, REQUESTED WAIVER OF TREE REMOVAL
DESIGN STANDARD
The Site Plan includes a complete landscaping and tree replacement plan. Site Plan, sht.
C-07 (Ex. A-4,A-14). In accordance with the Court's Order of December 9, 2011, the Site Plan
provides for a 10 foot wide buffer between the driveway and the lot line for the health care
facility which will be landscaped with a dense row of deer-resistant arborvitae (or other suitable
deer-resistant species) in addition to the existing deciduous trees, which will remain. Also in
accordance with the terms of the Court December 9, 2011, Order, the Site Plan provides for a
dense buffer of evergreens to the south of the buildings between the development on the Property
and the single family homes along Wadsworth Terrace. Additional street trees will be planted
along Birchwood Avenue to supplement the existing street trees. There will foundation plantings
along the foundations of the buildings and ornamental trees in the court yards and near the
entrances. Dipple, 8/9 T. 102-3.
Existing trees in the wetlands areas, in the wooded areas at the south end of the site, in
the buffer along the eastern edge of the site, and on the street in front of the buildings will be left
in place. Many of these trees are mature trees having diameters of 16, 18, 24, and 36 inches and
heights ranging from 30 feet to as high as 79 feet. Dipple, 8/9 T. 104-107.
______________________________________________________________________________
that, in the context of a Builder's Remedy lawsuit, the site plan application is an appropriate forum for granting the
relief sought by the Applicant. Instead, it is the Township's position that this issue should be cause for
reconsideration of the award of the Builder's Remedy by the trial court. For reasons set forth in the Conclusions
section, the Hearing Officer disagrees with the Township's position and strongly recommends that the Court order
the regrading to be permitted to occur.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
37/56
37
Approximately 72 existing trees will have to be removed to make way for the proposed
structures. Dipple, 8/21 T. 160-61; Dipple, 8/22 T. 14-17; Site Plan, sht. C-07. Under the tree
replacement provisions of the Cranfords site plan regulations, the Applicant would have to
replace these 72 trees with 295 new trees. The Applicant proposes instead to plant 180 new trees
- 108 more trees than will be removed. Consequently, the Applicant seeks a design waiver from
the tree replacement standard in Cranford's Ordinance. Dipple, 8/9 T. 107-108; Site Plan, sht. C-
07.
As proposed, the landscaping plan provides for extensive landscaping on the property -
much more than the landscaping that exists there currently. The only open lawn area proposed is
in the floodway where the existing building and parking lot at 235 Birchwood are located now
and will be removed. The Applicant's Engineer testified that the planting of additional trees in
the floodway could potentially impede the flow of water through the floodway and trap branches
and other detritus that might build up and block the floodway. Dipple, 8/9 T. 108.
REQUEST FOR WAIVER OF BICYCLE RACK DESIGN STANDARD
The design standards of the Cranford site plan regulations require the installation of
bicycle racks based on a ratio that will require the Applicant to provide racks accommodating
394 bicycles. The Site Plan proposes to provide bicycle racks accommodating 40 bicycles out of
doors with additional bicycle storage to be provided on each level of the residential buildings or
in the parking structure (Building C). Dipple, 8/9 T. 109-110; Site Plan, sht. C-04. A design
waiver is sought from the Township's standard for the provision of bicycle racks on the grounds
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
38/56
38
that 394 bicycle rack spaces is an exorbitant requirement, far in excess of any likely usage.
Dipple, 8/9 T. 109-110.
Cranford has indicated its willingness to accept a reasonable deviation from the bicycle
rack requirement.
CONCLUSIONS
1. Subject to the granting of the two requested waivers, the proposed Project as
described in Exhibits A-4, A-5, and A-6 conforms in all respects to the terms of Cranfords Land
Development Ordinance as amended by Ordinance No. 2012-11 and the Courts Order of
December 9, 2011.
2. The Court need not determine whether the proposed project conforms to the storm
water management provisions of N.J.A.C. 5:21-7, et seq., and the Residential Site Improvement
Standards, since CDA has already filed an application for approval of its storm water
management plan with the NJDEP, and NJDEP will be reviewing that application for compliance
with applicable standards. With respect to all other site improvements, the Project conforms to
the requirements of the Residential Site Improvement Standards, except as to the reduced
parking requirement, which was approved as part of the Court's December 9, 2011, Order.
3. Development of the proposed project with fewer outdoor bicycle racks than
mandated by Cranford Ordinance 136-23(G)(5) will not create a substantial detriment to public
health or safety. Residents are more likely to store their bicycles within the building or Parking
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
39/56
39
Garage overnight, and provisions for this will need to be made in the design of the buildings and
Parking Garage. Granting a waiver for fewer outdoor bicycle racks than the number mandated
by the Ordinance will thus remove an unnecessary cost-generating requirement while better
addressing the needs of the residents of the Project. Subject to the conditions set forth below, a
waiver of Cranford Ordinance 136-23(G)(5) is justified in this particular case.
4. Likewise, the development of the Project with fewer trees than called for by the
tree replacement provisions of 136-23(L)(1)-(3) of Cranford's Ordinance will not create a
substantial detriment to public health or safety or to the appearance of the Property. The
Property is proposed to be well-landscaped in all areas that will be disturbed for development.
Other areas will be left in their existing natural state. Permitting the tree replacement
requirement to be reduced to a number that can comfortably be accommodated within the areas
slated for redevelopment will remove what would otherwise be an unnecessary cost generating
requirement, with no documented corresponding public benefit associated with requiring more
trees to be planted. The waiver sought from 136-23(L)(1)-(3) of Cranford's Ordinance to limit
the tree replacement requirement to only those trees shown on CDAs landscaping plan is,
therefore, justified.
5. Subject to conditions outlined in the next section of this Recommendation, the
Project as proposed will provide adequate ingress and egress to Birchwood Avenue, sanitary
sewer service and public water service.
6. Storm water management, flood control, and wetlands protection are matters that
are ultimately governed by the regulatory standards established by the NJDEP. CDA has filed
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
40/56
40
applications with the NJDEP for the approvals and permits needed in each of these areas and has
acknowledged that it cannot commence construction unless it receives all of these permits and
approvals. The Township of Cranford is permitted to participate in the proceedings before the
NJDEP and has elected to do so. Under these circumstances, and consistent with N.J.S.A.
40:55D-22(b), it is recommended that any approval granted by the Court be expressly
conditioned on CDAs securing all required permits and approvals from the NJDEP, or waivers
or exceptions therefrom, if available, as well as required permits and approvals from all other
outside agencies.
7. With respect to CDA's proposed regrading of Birchwood Avenue in order to
elevate the Project's easternmost entrance drive above the flood hazard elevation, it is duly noted
that the Township is opposed to the approval of this proposal in connection with the Court's
approval of the site plan. Nonetheless, this matter has been referred to the Hearing Officer for
consideration by the Court, and it is, therefore, appropriate for the Hearing Officer to make
findings and recommendations to the Court on this issue.
The Hearing Officer is satisfied, from both a legal and an engineering perspective, that
the proposed elevation of Birchwood Avenue should be ordered by the Court as a necessary
component of its grant of a Builder's Remedy to CDA, subject, of course, to whatever permits
and approvals are required by the appropriate governmental agencies and authorities. There is
simply no credible evidence to suggest any detriment will ensue, either from a planning,
environmental or flood protection perspective, if the regrading of Birchwood Avenue is
permitted to occur. Moreover, given the municipality's obligation to take such affirmative steps
as are reasonably necessary to facilitate and make realistically possible the construction of
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
41/56
41
affordable housing, there seems little reason for the Court to refrain from so ordering. In
addition to the lack of credible evidence that any detriment will ensue, there is sufficient credible
evidence that the regrading of a section of Birchwood Avenue as proposed by the Applicant will
promote public safety, ensure compliance with NJDEP's most recent interpretation of its
regulations, and ensure that a substantial amount of affordable housing can be built in the context
of the Project.
The Hearing Officer therefore unreservedly recommends to the Court that it authorize the
elevation of Birchwood Avenue to be performed by CDA, at its sole cost and expense, as an
integral component of the Builder's Remedy.
8. During the Hearings, the Township has proposed that CDA be required to
construct or contribute its pro rata share to the cost of constructing certain off-tract
improvements, as authorized by N.J.S.A. 40:55D-42. This provision of the Municipal Land Use
Law permits municipalities to adopt ordinances providing regulations by which developers may
be required to contribute their pro rata share of reasonable and necessary off-tract improvements
pertaining to street improvements, water, sewerage and drainage facilities, if such improvements
are necessitated or required by construction or improvements within the development. The Law
requires such ordinances to be based upon circulation and comprehensive utility service plans
prepared as part of the municipal Master Plan. It was not clear from the testimony offered by the
Township at the hearing whether such Ordinance, in fact, exists. If it does, the Township may
require the Applicant to contribute only its pro rata share of such improvements as have been
deemed necessary to the construction of the Project. If such an Ordinance does not exist, the
Township has no authority to require contributions for any off-tract improvements.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
42/56
42
The following off-tract improvement contributions were discussed at the Hearings:
a. increasing the size of the existing 8 inch water line between the Project and
Bloomingdale Avenue to 12 inches;
b. connecting the proposed water line in the easternmost driveway of the Project to
the water main in the service road of the adjacent health care facility; and
c. relining approximately 1,300 linear feet of sanitary sewer lines.
For reasons discussed in the next few paragraphs, only this last proposed off-tract improvement
contribution remains at issue.
9. As to water system improvements, Fire Chief Dolan had testified that a hydrant
water service level of 2,000 gallons per minute is desirable to assure sufficient water for fire
suppression at the Project. During the Hearings, the parties were in dispute as to whether
Cranfords existing public water system currently provides this level of service or if additional
water service needs to be created at the Property. Fire Chief Dolan had testified that, if a water
service level of 2,000 gallons per minute is not currently available at the Property, it could be
provided by replacing the existing 8 inch water main between the easternmost hydrant in front of
the Project and the water main in Bloomingdale Avenue with a 12 inch main. Furthermore, if
the water service level is insufficient at the hydrants served by the water main on Birchwood
Avenue in front the Project but is determined to be available elsewhere in the area, such as at the
water main in the service driveway of the health care facility just east of the Project, then
connecting the water line that will loop through the Project to another line with sufficient service
would be another way to create the additional water service level needed for the Project.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
43/56
43
There is no question that CDA is responsible for assuring that there is adequate water
service for the Project. Consequently, the Applicant offered to arrange for an independent test of
the water service level at the hydrants in front of the Project to be conducted either by the water
company or by another entity agreed upon by CDA and the Township, which test would be
undertaken in accordance with the relevant national standard, NFWA 291, and paid for by CDA.
If the test showed that the water service level at these hydrants is significantly below 2,000
gallons per minute, then CDA would either construct the 12 inch water line or elect to reimburse
Cranford for its pro rata share of the reasonable cost of the Townships performing this upgrade.
The second remedy proposed by Chief Dolan, which was the connection to the water main in the
driveway to the health care facility, would require an easement to be obtained from the health
care facility. Cranford has not offered to acquire such an easement through the exercise of its
powers of eminent domain. Consequently, approval of the Project cannot be conditioned on that
particular connection, although CDA agreed to make a good faith effort to attempt to secure the
property rights necessary to construct such a connection, if necessary.
Subsequent to the Hearings, on October 12, 2012, an independent test of the level of
water service available at the hydrants in front of the Property was conducted by New Jersey
American Water Company in the presence of representatives of both Cranford Township and the
Applicant. The results of the test indicate that, at a pressure of 20 pounds per square inch, the
flow at the two hydrants in front of the Property was 2,778 gallons per minute and 2,887 gallons
per minute, respectively. Since Fire Chief Dolan had indicated that an acceptable level of flow at
a pressure of 20 pounds per square inch is 2,000 gallons per minute, there is no need to upgrade
the 8 inch line in Birchwood Avenue between the easternmost hydrant in front of the Property
and Bloomingdale Avenue, as initially proposed by the Township.
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
44/56
44
Also subsequent to the Hearings, at a meeting held between the parties on September 28,
2012, the map of the municipal water system was reviewed and it was learned that the
Birchwood Avenue water main does not extend to Cranford Avenue; instead, it runs up
Birchwood Avenue to the driveway of the health care facility just east of the Property, runs down
that driveway, around the health care facility building and then out to Cranford Avenue.
Consequently, the water main in the health care facility driveway is not a separate water main, as
initially assumed, but is in fact the very same water main that serves the Property. Consequently,
there is no need to provide a second connection to the water main in the driveway to the health
care facility from the Property.
Accordingly, there is no reason to require any off-tract improvement contributions with
respect to the water system as a result of the Project.
10. As to the sewerage improvements, it is the position of Cranford Township that
even if the existing sanitary sewer system has the capacity to accept the additional flows from the
Project, such additional flows will increase the risk of future breaks in the system. To address
this potential problem, the Township has proposed that CDA be required to either re-line, or
contribute its pro rata share of the cost of re-lining, approximately 1,300 linear feet of sanitary
sewer lines at unspecified locations.
The parties both agree that the existing sewerage system is very old, suffers from serious
unremediated inflow and infiltration, and is already subject to breaks. There is substantial
disagreement, however, about whether and to what extent sewage flows from the Project will
increase the likelihood of additional breaks and the extent to which the Project should be
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
45/56
45
required to contribute toward necessary improvements to the sewerage system to correct existing
problems. This is an issue that may well need to be resolved by the Court, if the parties cannot
come to an agreement as to the need for improvements to the sewerage system and as to the need
for the Applicant to pay a pro rata share of the cost of such system improvements or what that
pro rata share should be.
Nothing herein is intended to suggest that the Township is precluded from making
whatever improvements to the system it believes are necessary and assessing each of the
beneficiaries of the improvement, including CDA, for a fair share of the costs, in the manner
provided by law.
RECOMMENDED CONDITIONS OF APPROVAL
During the course of the Hearings, the Applicant voluntarily agreed to a number of
conditions requested by the Townships experts, the Special Master and/or the Hearing Officer,
all of which conditions are recommended to be incorporated into any Preliminary and Final Site
Plan Approval ordered by the Court. There are also a number of other conditions, to which the
Applicant has not agreed, but are being recommended by the Hearing Officer (with the
concurrence of the Special Master) to be imposed by the Court as part of its approval of the Site
Plan for this Builder's Remedy Project.
THE HEARING OFFICER (WITH THE CONCURRENCE OF THE SPECIAL
MASTER) HEREBY RECOMMENDS THAT PRELIMINARY AND FINAL SITE PLAN
APPROVAL, ALONG WITH TWO WAIVERS OF TOWNSHIP DESIGN STANDARDS
-
7/30/2019 2012-11-10-Recommendations-Wolfson-Hearings of August 8, 9, 21, 22, 23, 2012
46/56
46
(ONE PERTAINING TO THE NUMBER OF TREES REQUIRED TO BE PLANTED TO
REPLACE TREES BEING REMOVED FOR DEVELOPMENT AND THE OTHER
PERTAINING TO THE NUMBER OF REQUI