20110205 Project Management
-
Upload
andy-dharma -
Category
Documents
-
view
220 -
download
0
Transcript of 20110205 Project Management
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 1/47
UNHAN
Artha Graha
Project Management
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 2/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 3/47
What is A Project ?What is A Project ?
Temporary
Progressive
Elaboration
Unique
Deliverable
A temporary endeavor undertaken to create
a unique product, service, or result
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 4/47
UNHAN Project vs. Program
Project
Usually a one-off, non-repetitive undertaking, temporary
nature with a definite beginning and end, a definableoutput typically specified in terms of cost, quality and
timing
Program
An ongoing process of change has no definable end point
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 5/47
UNHAN Laws of Project Management
1. No project is ever installed on time, within budget, or with the same staff thatstarted it
2. Projects progress quickly until they become 90% complete, then they remain at
90% complete for ever
3. When things are going well, something will go wrong. When things just cannotget any worse, they will. When things appear to be getting better, you haveoverlooked something
4. If the project content is allowed to change freely, the rate of change will exceedthe rate of progress
5. A carelessly planned project will take three time longer to complete thanexpected; a carefully planned project will take only twice as long
6. Project team detest progress reporting because it vividly manifests their lack of progress
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 6/47
By balancing competing demands for :
HowHow To Achieve Project SuccessTo Achieve Project Success ??
Cost
ScopeQuality
Time
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 7/47
UNHAN Project Management CSFs
Clearly Defined Goals: including the general project philosophy or generalmission of the project and a commitment to those goals on the part of theproject team members.
Competent Project Manager: a skilled project leader who has thenecessary interpersonal, technical and administrative skills.
Top-Management Support: top-management commitment for the projectthat has been communicated to all concerned parties.
Competent Project Team Members: the selection and training of projectteam members, who between them have the skills necessary to supportthe project.
Sufficient Resource Allocation: resources, in the form of money,
personnel, logistics, etc., which are available for the project in the requiredquantity.
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 8/47
UNHAN Project Management CSFs
Adequate Communications Channels: sufficient information is available onproject objectives, status, changes, organizational conditions and clients needs.
Control Mechanisms: the mechanisms which are in place to monitor actual
events and recognize deviations from plan.
Feedback Capabilities: all parties concerned with the project are able to reviewthe projects status and make suggestions and corrections.
Responsiveness To Clients: all potential users of the project are concerned with
and are kept up to date on the projects status.
Troubleshooting Mechanisms: a system or set of procedures which can tackleproblems when they arise, trace them back to their root cause and resolve them.
Project Staff Continuity: the continued involvement of key project personnel
through its life. Frequent turnover of staff can dissipate the teams acquiredlearning.
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 9/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 10/47
UNHAN Stages In Project Management
Understanding The
Project
Environment
Stage 1
Project Definition
Stage 2
Project PlanningStage 3
TechnicalExecution
Stage 4
Project Control
Stage 5
Changes
Corrective
action
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 11/47
UNHAN
Artha Graha
Understanding The ProjectEnvironment
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 12/47
UNHAN Project Environment
Stage 1 Understanding The Project Environment
Geo-Social Environment
Geographical Climate
Culture
Econo-Political
Environment Economic
Government
Regulation
Business Environment Industrial
Competition
Supply Network
Customer Expectation
Internal Environment Strategy
Culture
Resources
Constraints
The Pr ject E ir ent C nsists Of ll The F ct r s That Can ff ect The Pr ject
The r ject
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 13/47
UNHAN Project Stakeholders
People and organizations that are involved, affected or caninfluence the project. ± Who
± Their needs and influence
± Hidden agenda ± Risks
± Agreement on success factors with stakeholders
Key Stakeholder in Project :1. Project Manager 2. Project Sponsor
3. User / Customer
4. Project Team Member
5. Project Management Team
6. Performing Organization
7. Influencer 8. PMO
Stage 1 Understanding The Project Environment
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 14/47
UNHAN Stakeholder Power-Interest Grid
Stage 1 Understanding The Project Environment
Stakeholder
Power
Stakeholder Interest
Keep Satisfied Manage Closely
Monitor Keep Informed
Low High
Low
High
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 15/47
UNHAN
Artha Graha
Project Definition
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 16/47
UNHAN Project Objectives
Project Objectives ± Provide definition of an end point
± Used to monitor progress
± Identify success
Good Objectives ± Clear
± Measurable
± Quantifiable (preferably)
Clarifying Objectives Involves Breaking Down Project Objectives Into3 Categories: ± Purpose
± End Results : Identification of problems and recommendation of solutions
± Success Criteria
Stage 2 Project Definition
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 17/47
UNHAN Project Objectives Triangle
Stage 2 Project Definition
Quality
TimeCost
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 18/47
UNHAN Project Scope
Boundary setting exercise postulating what the project will
do and not do
Identifies work content and its products or outcomes
Often the scope can be in the form of legal boundaries or
at times articulated in a formal project specification
Stage 2 Project Definition
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 19/47
UNHAN Project Strategy
Define in a general way how the project is going to meet itsobjectives
± Defining the phases of the project
± Setting milestones and/or stagegates
Milestone is a passive term, which may herald the review of apart-complete project or mark the completion of a stage butdoes not necessarily have more significance than a measure of
achievement or progress
Stagegates are the decision points that allow the project tomove into the next phase by launching further activities andtherefore commits the project to additional costs, resources,
etc
Stage 2 Project Definition
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 20/47
UNHAN
Artha Graha
Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 21/47
UNHAN Project Planning
Fulfills Four Distinct Purposes1. Determines the costs and duration
2. Determines the level of resources which will be needed
3. Helps to allocate work and to monitor progress
4. Helps to assess the impact of any changes to the project
Planning is not a one-off process
Planning may be repeated several times during the projects life ascircumstances change
Replanning is not a sign of failure or mismanagement
Later stage planning means that more information is available andthe project becomes less uncertain
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 22/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 23/47
UNHAN Stages In The Planning Process
Stage 3 Project Planning
Identify the
activities in
the project
Estimate the
times and
resources foractivities
Identify the
relationships
and
dependenciesbetween the
activities
Identify time
and resources
sch
eduleconstraints
Fix the
schedule for
the time andresources
Adjust As Necessary
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 24/47
UNHAN Identify Activities
Most projects are too complex to be planned andcontrolled effectively unless they are first broken downinto manageable portions
This is achieved by structuring the project into a familytree which is further divided into smaller tasks until adefined manageable series of task called work package is
arrived
Each work package can be allocated with its ownobjectives of time, cost and quality and produce the work
breakdown structure
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 25/47
UNHAN
33
22
11
00
Work Breakdown Structure
Serve BreakfastIn Bed
Produce Glass
of Orange Juice
Prepare Juice Obtain Glass
Produce Boiled
Egg In Egg Cup
Produce BoiledEgg
Obtain EggFill Pan With
Water
Obtain Egg Cup
Produce
Buttered Toast
Produce Toast
Slice Bread
Obtain Butter
Arrange Tray
Obtain Plates &Cutlery
Obtain Tray
Stage 3 Project Planning
Purpose : Make breakfast in bed
End Result : Breakfast in bed of boiled egg, toast and orange juice
Success Criteria : Uses minimum staff resources (max 4), time (max 9 mins) and
product of high quality (warm and fresh)
Scope : Starts in kitchen at 6.00 am and finishes in bedroom using
normal kitchen equipment
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 26/47
UNHAN Estimate Time and Resources
Estimates are just a systematic best guess, not a perfec forecasts of reality
They must take into account the time of day and the state of operator / staff
The amount of uncertainty in a project has a major bearing on the level of confidencewhich can be placed on an estimate hence probabilistic curve may be used which is usuallypositively skewed
The greater the risk the greater the probability distribution
The natural tendency is to produce optimistic estimates
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 27/47
UNHAN Identify Relationships and Dependencies
All activities will have some relationships with one another that will depend on the logic of the project
Some activities will, by necessity, need to be executed in a particular order known asdependent or series relationship
Total activities takes 9 minutes. Some activities have spare time (float) that can be done atanytime provided that they are completed before the the final activity. Some activitieshave no float hence called critical path of the project
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 28/47
UNHAN Identify Schedule Constraints
Compare project requirements with available resources using two fundamentalapproaches: ± Resource Constraints
Only available resources are used in resource scheduling and are never exceeded
Project completion may slip
± Time Constraints The overriding priority is completion within a give time frame
Once normally available resources have been used up, alternative threshold resources are scheduled
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 29/47
UNHAN Fix The Schedule
Stage 3 Project Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 30/47
UNHAN Project Control
The essential link between planning and execution, andinvolves three sets of decisions:1. How to monitor the project in order to check its progress
What to monitor i.e expenditure, overtime, delays, technical changes,failures, missed milestones, etc
2. How to assess the performance of the project by comparing themonitored observations with the project plan
Actual versus plan, amount of tolerable deviations, etc
3. How to intervene in the project in order to make the changes that willbring it back to plan
Given the interconnected nature of projects a change in one partwill have knock-on effects elsewhere this means that interventionsoften require wide consultations and advice from all those affected
Stage 5 Project Control
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 31/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 32/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 33/47
UNHAN Critical Path Method
Each activity is represented by arrows with the tail as the start andthe head as the end
A circle called event, is a moment in time which occur at the start ofinish of an activity.
A sequence of activities are called paths
Each path will have a total duration which is the sum of all itsactivities
The path which has the longest sequence of activities is called thecritical path of the network (more than one critical path may exists)
Any delay along the critical path will delay the project
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 34/47
UNHAN Rules
Network Design
1. An event cannot be reached until all activities leading up to it are
complete
2. No activity can start until its tail event is reached
3. No two activities can have the same head and tail events; dummy
activities must be drawn
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 35/47
UNHAN Calculating Float
Earliest Event Time (EET) is the earliest the event couldpossibly occur if all preceding activities are completed as earlypossible
Latest Event Time (LET) is the latest time an event couldpossibly take place without delaying the whole project
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 36/47
UNHAN Activity On Node Networks
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 37/47
UNHANProgram Evaluation and Review
Technique (PERT)
This technique recognizes that activity durations and costs
in project management are not deterministic and that
probability theory can be applied to estimates
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 38/47
UNHANLongest Mean Time vs Greatest Time
Variance
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 39/47
UNHAN Introducing Resource Constraints
Network Planning
Non critical activities starts as soon as
possible
Loading not even with resource profiles
that varies from seven staffs to three staffs
If available staff is less than 7, project need
rescheduling
Activity B is delayed until activity A is
completed
Loading is more even with resource profiles
that varies from five staffs to four staffs
If available staff is less than 7, project need
rescheduling
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 40/47
UNHAN Crashing Networks
Crashing networks is the process of reducing time spans on critical pathactivities so that the project is completed in less time
Usually crashing activities incurs extra costs as a result of :
± Overtime working ± Additional resources
± Subcontracting
Network Planning
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 41/47
Project Life CycleProject Life Cycle
Inputs
Phases
Project
Management
Outputs
Project
Deliverable
Idea
Charter
Scope Statement
lan
Approval
rogress
Acceptance
Handover
INITIAL INTERMEDIATE FINAL
roject Team
RODUCT
Typical Sequence of
hases in a roject Life
Cycle
Baseline
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 42/47
INITIATING
PROCESSESCLOSING
PROCESSES
PLANNING
PROCESSES
EXECUTING
PROCESSES
Monitoring and
Controlling processes
Standard Project Management ProcessStandard Project Management ProcessGroupsGroups
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 43/47
UNHAN Project Management Process
Initiating Process : Define and authorizes the project
Planning Process : Define and refines objectives and
plans the course of action
Executing Process : Integrates peoples and other resources
Monitoring & Controlling Process : regularly measuresand monitors progress to identif y variances so thatcorrective action
C
losingP
rocess : Formalizes acceptance of theproduct, service or result
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 44/47
Overview V.3.0 Page 44
Project Management Knowledge AreaProject Management Knowledge Area
2. Project Scope Management
7. Project Communication Management
8. Project Risk Management
4. Project Cost Management
5. Project Quality Management
6. Project Human Resource Management
1. Project Integration Management
3. Project Time Management
9. Project Procurement Management
Project Management Body
of Knowledge (PMBOK)
dikeluarkan oleh PMI(Project Management
Institute) - USA
44
Knowledge Area &
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 45/47
UNHAN Project Management Mapping
Knowledge Area &
ProcessesInitiating Planning Executing Monitoring & Controlling Closing
Project Integration
Management
4.1 Develop
Project
Charter
4.2 Develop Project Management Plan 4,3 Direct & Manage Project Execution
4.4 Monitor & Control
Project Work
4.5 Perform Integrated
Change Control
4.6 Close
Project or
Phase
Project Scope
Management
5.1 Collect Requirements
5.2 Define Scope
5.3 Create WBS
5.4 Verify Scope
5.5 Control Scope
Project Time
Management
6.1 Define Activities
6.2 Sequence Activities
6.3 Estimate Activity Resources
6.4 Estimate Activity Duration
6.5 Develop Schedule
6.6 Control Schedule
Project Cost
Management
7.1 Estimate Costs
7.2 Determine Budget7.3 Control Cost
Project Quality
Management8.1 Plan Quality 8.2 Perform Quality Assurance 8.3 Perform Quality Control
Project HR
Management9.1 Develop HR Planning
9.2 Acquire Project Team
9.3 Develop Project Team
9.4 Manage Project Team
Project
Communication Mgt
10.1 Identify
Stakeholder 10.2 Plan Communication
10.3 Distribute Information
10.4 Manage Stakeholder Expectation10.5 Report Performance
Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risk
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.5 Plan Risk Responses
11.6 Monitor and Control
Risk
Project Procurement
Mgt.12.1 Plan Procurement 12.2 Conduct Procurement
12.3 Administer
Procurement
12.4 Close
Procurement
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 46/47
8/7/2019 20110205 Project Management
http://slidepdf.com/reader/full/20110205-project-management 47/47
TERIMA KASIH
Andy Dharma