Daedalus Projects, Inc.
112 South Street
Boston, Massachusetts
Franklin High SchoolFranklin, MA
Monthly Construction Management ReportNovember 30, 2011
-
8/3/2019 2011 11 FHS Monthly Report
2/9
OPM Activities (Reporting Period) Schematic design has been completed as of December 9, 2011. OPM activities include production of schematic costestimate, value engineering, reconciliation of cost estimates with those of the architect, project budget, schedule,drawing review and comment and participation in Building committee meetings.
Project Budget Status Appropriated through the Town Vote which is anticipated in March 2012.
Potential Issues None
Contract Summary Payment SummaryOriginal Contract Amount $196,781 Total Contract Amount $1,973,595
Contract Amendments (to Date) 2 Invoices Paid (to Date) $145,199
Value of Contract Amendments (to Date) $1,776,814 Invoices Received (Reporting Period) $18,000
Total Contract Amount $1,973,595 Contract Amount Remaining $1,810,396
Contract Amendments as Percentage of Original Contract Amount 903.0%
OPM Daedalus Projects Inc Progress Report as of Date 11/30/2011
District Name Franklin MSBA ID 200901010505
School Name Franklin High Project Name
OPM Firm Name Daedalus Projects Inc School Building Committee Representative Tom Mercer
Project Director Marks, Richard Total Project Budget (ProPay) $874,551
Designer Firm Name Ai3 Architects LLC Encumbered (Reporting Period) $0
Principal Encumbered (to Date) $1,086,545
General Contractor Firm Name Total Project Invoices Received (to Date) $818,611
General Contractor Contact Name Project Completion Percentage 10%
Daedalus Projects Inc Marks, Richard Progress Report as of Date 11/30/2011
RFIs and Submittals
RFIs Issued (Reporting Period) 0
Total RFIs Issued (to Date) 0
Remaining Open RFIs Past 30 Days 0
Notes
Remaining Open RFIs Past 60 Days 0
Contract Summary Payment Summary
Original Contract Amount $4,016,126 Total Contract Amount $4,058,368
Contract Amendments (to Date) 2 Invoices Paid (to Date) $29,867
Value of Contract Amendments (to Date) $42,242 Invoices Received (Reporting Period) $419,835Total Contract Amount $4,058,368 Contract Amount Remaining $3,608,666
Contract Amendments as Percentage of Original Contract Amount 1.0%
DESIGNER Ai3 Architects LLC Progress Report as of Date 11/30/2011
MBE/WBE Requirements
MBE Requirement 0%
MBE Actual 0%
WBE Requirement 0%
WBE Actual 0%
-
8/3/2019 2011 11 FHS Monthly Report
3/9
Designer Activities (Reporting Period) Schematic has been completed as of December 9, 2011 and submitted to MSBA. building committee meetingsand coordination meetings are being held. The complete Ai3 schematic design package has been assembled,reviewed by Daedalus and submitted to MSBA as of December 9, 2011. The cost estimates have beenreconciled and the complete MSBA 3011 budget submitted. At the December 8, 2011 building committeemeeting Ai3 reviewed proposed exterior elevations with the district and received feedback.
30 Day Look Ahead
Commissioning Agent
Commissioning Agent Status
Schedule Assessment
Notice to Proceed Date 1/1/0001 MBE Requirement
Physical Progress MBE Actual
Substantial Completion Date (Original) WBE Requirement
Substantial Completion Date (Revised) WBE ActualConstruction Progress (Reporting Period)
30 Day Look Ahead
Overall Schedule Assessment
Problems Identified (Schedule or Construction)
Quality Control
Safety Compliance
Number of Claims (to Date)
Value of Claims (to Date)
CommentsRecorded Manpower (Reporting Period)
Commissioning Agent
Commissioning Agent Status
Pending Change Orders
Change Order Status
Contract Summary Payment Summary
Original Contract Amount Total Contract Amount
Change Orders (to Date) Invoices Paid (to Date)
Value of Change Orders (to Date) Invoices Received (Reporting Period)
Total Contract Amount Contract Amount Remaining
Contract Type
Change Orders as Percentage of Original Contract Amount 0.0%
GENERAL CONTRACTOR Progress Report as of Date 11/30/2011
-
8/3/2019 2011 11 FHS Monthly Report
4/9
Report Submission (Hard Copy) will include the following attachments
Budget and Cost Report MSBA format
Projected Cash Flow
Project Schedule
Change Order Tracking Report
Progress Photos
The undersigned hereby certifies that, to the best of his/her knowledge, the information contained in this monthlyreport and attached hereto are true and accurate.
Project Director/Project Manager
______________________________________ Print Name
______________________________________ Signature
______________________________________ Date
Certification
-
8/3/2019 2011 11 FHS Monthly Report
5/9
Total Project Budget Template
Franklin High School, Franklin, MA 12/9/2011
TOTAL PROJECT BUDGET - ALL COSTS
ASSOCIATED WITH THE PROJECT ARE SUBJECT
TO 963 CMR 2.16(5) Estimated Budget
*Cost/Scope Items
Excluded from the
Total Facilities Grant *Ineligible CostsFeasibility Study AgreementOPM Feasibility Study $335,797A&E Feasibility Study $698,358
Env. & Site $51,890Other $500
Feasibility Study Agreement Subtotal $1,086,545 $0 $0Administration
Legal Fees $100,000 $100,000
Owner's Project ManagerDesign Development
Construction Contract Documents
Bidding $48,510
Construction Contract Administration $1,481,288Closeout
Extra Services
Reimbursable & Other Services $30,000Cost Estimates $78,000
Advertising $5,000Permitting
Owner's InsuranceOther Administrative Costs $7,500
Administration Subtotal $1,750,298 $0 $100,000Architecture and Engineering
Basic ServicesDesign Development $968,699Construction Contract Documents $1,115,877Bidding $127,914Construction Contract Administration $763,263Closeout $36,466Other Basic Services $164,127
Reimbursable ServicesConstruction testing
Printing (over minimum)
Other Reimbursable Costs
Hazardous Materials $131,460Geotech & Geo-Env. $167,650Site Survey
-
8/3/2019 2011 11 FHS Monthly Report
6/9
Total Project Budget Template
Franklin High School, Franklin, MA 12/9/2011
TOTAL PROJECT BUDGET - ALL COSTS
ASSOCIATED WITH THE PROJECT ARE SUBJECT
TO 963 CMR 2.16(5) Estimated Budget
*Cost/Scope Items
Excluded from the
Total Facilities Grant *Ineligible Costs
Construction Costs
SUBSTRUCTURE
Foundations $3,531,705Basement Construction $0
SHELLSuperStructure $9,251,663Exterior Closure $9,282,035Roofing $2,765,692
INTERIORSInterior Construction $9,586,888Staircases $379,275
Interior Finishes $4,056,512SERVICESConveying Systems $197,475Plumbing $3,065,430HVAC $8,276,661Fire Protection $1,226,172Electrical $8,835,206
EQUIPMENT & FURNISHINGSEquipment $1,624,098
Furnishings $1,868,804SPECIAL CONSTRUCTION & DEMOLITIONSpecial ConstructionExisting Building Demolition $1,465,200In-Bldg Hazardous Material Abatement $1,310,000 $561,000
Asbestos Cont'g Floor Mat'l AbatementOther Hazardous Material Abatement
BUILDING SITEWORK $8,923,906 $2,604,640
Site PreparationSite ImprovementsSite Civil/ Mechanical UtilitiesSite Electrical UtilitiesOther Site ConstructionScope Excluded Site Cost $0
C t ti T d S bt t l $
-
8/3/2019 2011 11 FHS Monthly Report
7/9
Total Project Budget Template
Franklin High School, Franklin, MA 12/9/2011
TOTAL PROJECT BUDGET - ALL COSTS
ASSOCIATED WITH THE PROJECT ARE SUBJECT
TO 963 CMR 2.16(5) Estimated Budget
*Cost/Scope Items
Excluded from the
Total Facilities Grant *Ineligible Costs
Overall Excluded Construction Cost
Construction Budget $87,914,728 $0 $3,679,028
Alternates
Alternates Subtotal $0 $0 $0
Const. Contingency $3,516,589Miscellaneous Project CostsUtility company Fees $150,000Testing Services $150,000Swing Space/Modulars
Other Project Costs (Mailing, printing & Moving) $200,000 $175,000
Misc. Project Costs Subtotal $500,000 $0 $175,000Furnishings and Equipment
Furnishings $2,640,000Equipment $0Computer Equipment $2,640,000Scope Excluded FFE Costs $1,320,000
FF&E Subtotal $5,280,000 $1,320,000 $0Owner's ContingencyOwner's Contingency $1,000,000Soft Costs that exceed 20% of Const'n Cost
Total Project Budget $104,537,266 $1,320,000 $3,954,028
Alternates $0
Ineligible cost $3,954,028Scope items excluded $1,320,000
Estimated Basis of Total Facilities Grant $99,263,238
Reimbursement Rate 57.94%
Estimated Total Maximum Facilities Grant $57,513,120
* NOTE: This template was prepared by the MSBA as a tool to assist Districts and their teams in the understanding of MSBA policies and practices and
their potential impact on the MSBAs calculation of a potential Basis of Total Facilities Grant and potential Total Maximum Facilities Grant. This template
does not contain a final, exhaustive list of all evaluations which the MSBA may use in determining whether items are eligible for reimbursement by the
-
8/3/2019 2011 11 FHS Monthly Report
8/9
-
8/3/2019 2011 11 FHS Monthly Report
9/9
ID Task Name Duration Start Finish
1 Town of Franklin 899 days? Wed 7/27/11 Mon 1/5/15
2 Franklin High School 899 days? Wed 7/27/11 Mon 1/5/15
3 MSBA Board Authorization 1 day? Wed 7/27/11 Wed 7/27/11
4 Invitiation to participate in the Model School Program 1 day? Wed 7/27/11 Wed 7/27/115 Model School Designer Selection 31 days Thu 8/11/11 Thu 9/22/11
6 Designer Invitation and Responses (District) 16 days Thu 8/11/11 Thu 9/1/11
7 Designer Interview and Selection (District) 5 days Fri 9/2/11 Thu 9/8/11
8 Designer Negotiation and Contract Execution (District) 10 days Fri 9/9/11 Thu 9/22/11
9 Project Scope & Budget Agreement/ PFA 132 days? Mon 9/26/11 Tue 3/27/12
10 Schematic Design Documents (District) 55 days Mon 9/26/11 Fri 12/9/11
11 Schematic Design Review (MSBA) 20 days Mon 12/12/11 Fri 1/6/12
12 Project Scope and Budget Conference (MSBA) 1 day? Mon 1/9/12 Mon 1/9/12
13 Board of Directors Vote on PSB (MSBA) 0 days Wed 1/25/12 Wed 1/25/12
14 Prepare/Distribute Project Scope and Budget Agreement (MSBA) 10 days Tue 1/10/12 Mon 1/23/12
15 Appropriation of Total Project Budget (District) (District must secure funds with 120 days of Board vote) 45 days Wed 1/25/12 Tue 3/27/12
16 Design Development & Construction Documents 174 days Mon 12/12/11 Thu 8/9/12
17 Prepare Design Development & Construction Documents (District) 174 days Mon 12/12/11 Thu 8/9/12
18 Prequalification of FSB 45 days Fri 6/8/12 Thu 8/9/12
19 Prequalification of GC 45 days Fri 6/8/12 Thu 8/9/12
20 Local permitting 50 days Mon 12/12/11 Fri 2/17/12
21 Conservation commission permitting 50 days Mon 12/12/11 Fri 2/17/12
22 Pre-Construction/Bid Process 42 days Fri 8/10/12 Mon 10/8/12
23 Bid Advertisment/bidding period 30 days Fri 8/10/12 Thu 9/20/12
24 Bid Award 10 days Fri 9/21/12 Thu 10/4/12
25 Notice to Proceed 2 days Fri 10/5/12 Mon 10/8/12
26 Construction 585 days Tue 10/9/12 Mon 1/5/15
27 New buildng 465 days Tue 10/9/12 Mon 7/21/1428 Abate and demolish existing building, final site phase 120 days Tue 7/22/14 Mon 1/5/15
1/25
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 42012 2013 2014
Franklin High SchoolModel School Schedule
Daedalus Projects, Inc. We