2014 GANIL/SPIRAL2 15TC
AGATA D.+PRISMA AGATA + VAMOS+ EXOGAM2
AGATA @ FRS
Total Eff.InFlight ~ 10% Total EffNominal. ~ 14% Total Eff.CloseConfig ~6%
AGATA@GANIL
E.Clément Novembre 2011
Gamma-ray spectroscopy of very neutron-rich nuclei populated in Deep Inelastic collisions or induced fission using VAMOS to identify the reaction products in Q, A and Z.
Spectroscopy of heavy elements towards SHE and N=Z nuclei populated by fusion –evaporation with VAMOS in gas-filled mode.
Spectroscopy of p-rich nuclei at the N=Z line using the N-wall
Spectroscopy using existing and new SPIRAL1 beams
GANIL physics cases
Ensuring these physics cases with the appropriate ancillaries detectors
The mechanical integration has to take into account this broad list of configurations
E.Clément Novembre 2011
Beam: 238U @ 5.5 MeV/u, (i ~ 2pnA) Target : 9Be, 12C,48Ca,70Zn, 198Pt … (1 mg/cm2) Full identification of the heavy
recoil in VAMOS
Shell evolution toward 54Ca (M. Rejmund et al) lifetime measurement with a plunger in n-rich nuclei beyond 68Ni (J Ljungvall et al; A Dijon et al, I. Celikovic et al) Delayed and prompt gamma spectroscopy around 68Ni (A Dijon et al) Transfer induced fission reactions (F. Farget et al, M. Rejmund et al. A. Görgen et al.) Spectroscopy of heavy element Os (J. Valient-Dobon et al)
EXOGAM coupled to VAMOS:Spectroscopy of n-rich nuclei
E.Clément Novembre 2011
Vacuum mode : 22Ne +197Au 214AcGas filled mode : 48Ca+198Pt 244Cf
VAMOS + EXOGAM+MUSETT Vamos at 0 degree used as separator Prompt spectroscopy after Recoil decay tagging (a-decay) in MUSETT
MU
SETT
arr
ayEXOGAM coupled to VAMOS+MUSETT:
Spectroscopy of SHE nuclei
Not yet fully funded and operationalFrench grant Agency for Research 2013 request (Saclay -GANIL)
a energy keV
g energy keV
E.Clément Novembre 2011 C. Schmitt et al NIM A 621 (2010) 558–565
VAMOS in gas-filled / Vacuum mode
Rejection > 1010
Measured in the 40Ca+150Sm reaction
Unique opportunity to couple AGATA -1p with a separator in fusion induced reaction
Prompt spectrocopy with p,a tagging at the focal plane (MUSETT)
Spectroscopy beyond Fm:the shell model towards SHE
E.Clément Novembre 2011
M. Sandzelius et al., Phys. Rev. Lett. 99, 022501 (2007).
VAMOS in gas-filled with AGATA and MUSETT (Island of a-emitter)
Onset of collectivity induced by np pairingnear N=Z and closed shells ?
Prompt spectroscopy of light Xe,Te,I isotopes a and p emitter
Gas filled mode : 54Fe+54Fe 106Te +2n (25 nb) 54Fe+58Ni 110Xe +2n (50 nb) 54Fe+58Ni 109I +p2n (10 mb)
Collectivity in N≈Z nuclei:Enhancement from T=0?
E.Clément Novembre 2011
J=9
Pd4646
92
J=9
J=7
J=7
92Pd, exp. 92Pd, SM0+ 0+
(2+ )
(4+ )
(6+ )
2+
4+
6+
8+
10+
0
874
1786
2536
0
878
1708
2466
3127
4072
A new Spin-aligned pairing phase in 92Pd
B Cederwall, et al, Nature 469, 68-71 (2011)
EXOGAM coupled to the NWallPrompt Spectroscopy of N=Z nuclei
E.Clément Novembre 2011
Charged particle array for transfer reaction MUST2/TIARA : (d,p) etc … program with SIB and RIB
Charged particle array for prompt tagging : DIAMANT Neutron detector (Nwall) Charged particle array for Recoil Decay Tagging : MUSETT
Scintillator : BaF2 array, LaBr3 Future detector : NEDA (n) , GASPARD ( ?), PARIS (LaBr3)
In G1 coupled to VAMOS (+ EXOGAM2): SIBs, RIBs
AGATA 1p at GANIL : Ancillary devices
At 0° as separator (vaccum/gas-filled)
Angles >10 deg for fission & MNT
Cryogenic target ? We ensure the coupling to AGATA through the VME AGAVA card
E.Clément Novembre 2011
E.Clément Novembre 2011
Design done by STFC Daresbury in close collaboration with GANIL An important work of integration is on-going Final design review 1st week of December Projection T1 -2013 9 months of construction estimated
On-going discussion with the IPHC workshop for the construction of the support
Workshop for the extended plateform not yet defined
E.Clément Novembre 2011
Which configuration for which physics ?
GANIL is designing a new target chamber, target holderand beam pipe to ensure most of the experiments (DIC,fission, fusion)
Nominal configuration
Compact configuration
E.Clément Novembre 2011
~150 k€
~17k€
Processing room 019Upgrade ~ 85k€
Detector lab infrastructure ~15 k€
Cryogenic upgrade, connection ~25 k€
Total investment cost ~360 k€
Optical fibers links ~70k€
E.Clément Novembre 2011
Collaboration :Local project manager : E.ClémentCampaign spokesperson announced : S. LenziCall for LOI sent : dead line 25th January 2013 1st workshop 18th to 20st of February organized at GANILFirst draft of the working together document sent to AMB
~ 4ETP are working in 2013 on the project ≈20 persons involved at GANIL
E.Clément Novembre 2011
Budget : Total cost investment ~300k€
237 k€ guaranteed by GANIL for 2013 to be completed in the 2014 request
IPHC requested 90k€ from IN2P3 AP for the mechanic
ANR (French Research Funding Agency) request for the gaz-filled mode to be submitted by the Saclay group (Ch. Theisen et al)
Loan of material from LNL & GSI (cooled cabinet, racks, water distribution, Optical link to be carefully evaluated)
E.Clément Novembre 2011
Schedule (assuming that material from GSI arrive on Jan-Feb 2014)
Gas-filled installation expected in mid-2015 GANISOL beam available for physics beginning of 2016
We request the host of AGATA until end of 2016 at least with ≥6 months beam time
T2-12 T3-12 T4-12 T1-13 T2-13 T3-13 T4-13 T1-14 T2-14 T3-14 T4-14 … T4-16
Mechanics STFC Design
GANIL Impl
IPHC construc
Mounting
Infrastructure det
GANIL Studies
Collecting items
Installation
LN2, AF
GANIL Studies Collecting items
Installation Test
DAQ Hardware
GANIL Studies
Collecting items
Installation Test
DAQ Software
Preparation
Test
Processing Room
Renov Aire Proj AGATA
infra
Detector
Mounting
Source & Commi
Expt …
E.Clément Novembre 2011
J. Ljungvall (CSNSM) for the AGATA collaboration - Preliminary
× ~ 1.25
× ~ 1.5
AGATA nominal 233 mmEXOGAM nominal 145 mm
Performance of the array
E.Clément Novembre 2011
b =12%
More than efficiency , AGATA provides higher sensitivity
× ~ 4.7
× ~ 12
gg performances under simulations
E.Clément Novembre 2011
E.Clément Novembre 2011
Performance simulations : on-going (final release expected February)Electronic coupling: on-going (several meeting already done or scheduled)Data flow, DAQ on-going (several meeting already done or scheduled)Mechanic design : on-going (final design review 1st week of Dec.)Optical link on-going (purchase order expected on April)Data analysis starting (first meeting on the first week of Dec.)AutoFill-cryogenic infra starting (meeting soon with Saclay crew)Infrastructure on-going (needs identified, final design review on going)
Local organization done (STP, BE, GAP,SPE, GVC already working)Task distribution doneGANIL project method: Set of spec delivered, management dvpt for ChristmasInstallation description for DIRC01 : 1st draft released to the QSE,
risk analysis beginning of 2013