2010 4-14 open house

24
Sound Transit Capitol Hill Station Construction Update Meeting April 14, 2010 6:30 p.m. 8:30 p.m. SCCC

description

 

Transcript of 2010 4-14 open house

Page 1: 2010 4-14 open house

Sound Transit

Capitol Hill Station

Construction Update Meeting

April 14, 2010

6:30 p.m. – 8:30 p.m.

SCCC

Page 2: 2010 4-14 open house

Agenda

6:30 p.m. – Open House

7:00 p.m. – Presentation

Project Update– Rhonda Dixon, CH Station Outreach Coordinator

Construction Activities – Jeff Munnoch, U-Link Community

Outreach

Construction Wall Art Program

Barbara Luecke, STart Manager

D.K. Pan, Lead Artist Capitol Hill construction wall

Q&A

8:00 p.m. – Return to Open House

Page 3: 2010 4-14 open house

Central Link• Westlake to SeaTac Airport

• 16 miles

• 13 stations

Page 4: 2010 4-14 open house

University Link• 3.15-mile light rail extension

– Capitol Hill Station

– UW Station

• Schedule

– Construction: 6.5 years

– Open for Service: 2016

• Adds 70,000 daily riders, 114,000 system wide (2030)

Page 5: 2010 4-14 open house

Capitol Hill Station

• Underground station with 3 entrances

• Staging area - station and tunnel excavation at site

• Ridership: 14,000 daily boardings

• Travel time:

– 3 minutes to downtown Seattle (University St.)

– 3 minutes to UW Station

Page 6: 2010 4-14 open house

Capitol Hill Construction Contracts1. Demolition (complete)

2. I-5 undercrossing (on-going)

3. Excavation / tunneling (2010 – 2013) 4. Station Construction (2013 – 2015)

Page 7: 2010 4-14 open house

I-5 Undercrossing Work2009 - 2010

• Preparing the ground

beneath I-5 for the

TBM’s

• Pike/Pine HOV off-

ramp will open in April

• Olive Way off-ramp

will open in May as

originally planned

Page 8: 2010 4-14 open house

Haul Route Pedestrian ImprovementsCompleted March, 2010

Page 9: 2010 4-14 open house

Restaurant, Retailing and

Social Media Seminars

• Restaurant Management

• Retail Management

• Social Media Applications (Facebook, Twitter, and other on-

line tools)

Page 10: 2010 4-14 open house

Construction Update

Page 11: 2010 4-14 open house

Current WorkApr-Jun 2010

• Construction wall

• Utility relocation

• Solider Piles

Soldier

piles

Utility relocation

Page 12: 2010 4-14 open house

Soldier Piles

• Steel beams support wood planks that keep the sides of the excavation stable

• 120 total piles

• 100 feet deep

Page 13: 2010 4-14 open house

Current WorkApr-Jun 2010

• Utility relocation

• Construction wall

• Solider Piles

• Jet grouting (north end of site)

• Sidewalk closedon John St.

Jet

grouting

Sidewalk closed

Soldier

piles

Utility relocation

Page 14: 2010 4-14 open house

Temporary sidewalk

• Steel containers incorporated into the wall

• No sidewalk detour necessary

• Potential viewing portals

Page 15: 2010 4-14 open house

ExcavationMay 2010

• Increased truck activity

(approx. 8 truck / hour)

• Daytime work

• Night work does not start

until tunneling begins

Page 16: 2010 4-14 open house

Excavation sequence

As dirt is removed, wooden

planks are inserted into the

I-beams to support the

sides of the excavation

Page 17: 2010 4-14 open house

Pine Street Jet Grouting

• Stabilize ground

where TBM will exit

• Sidewalk closure,

south side (4 weeks)

Sidewalk

closed

Page 18: 2010 4-14 open house

Construction Wall

• Surround the site on all sides

• 8 to 24 feet high, plywood construction

• Help contain noise, dust, and debris

8’ wall

12’ wall

16’ wall

24’ wall

KEY

Page 19: 2010 4-14 open house

STart ProgramConstruction Wall Art

Keep the sidewalk active

Mitigate impact with art

Continued Commitment to

placemaking

– STart On Broadway

– Oscillating Field

Page 20: 2010 4-14 open house

D.K. Pan, Lead Artist

Page 21: 2010 4-14 open house

Master Plan to integrate:•Art

•Project information

•Neighborhood promotion

CALL TO ARTISTS

Applications Due

Monday April 19

Page 22: 2010 4-14 open house

Next Steps

• Artist applications due – April 19

• Decision on noise variance published – April 22

• Finish site preparations, begin excavation – May

• North Link kick-off meeting - May

• Pine Street site preparation – Summer

• TBM assembly begins – early 2011

Page 23: 2010 4-14 open house

Questions?

Page 24: 2010 4-14 open house

Staying Informed

Quarterly Open Houses

Monthly electronic newsletters: www.soundtransit.org/subscribe

Sound Transit Website: www.soundtransit.org/u-link

Printed and electronic construction alerts

Full time outreach staff

24 hour construction hotline: 1-888-298-2395