2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2...

87
2010-11 CAPITAL WORKS PROGRAM June Outcome Report

Transcript of 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2...

Page 1: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

2010-11 CAPITAL WORKS PROGRAM June Outcome Report

Page 2: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

TABLE OF CONTENTS 1 INTRODUCTION ............................................................................................ 1

1.1 SUMMARY OF ACHIEVEMENTS FOR 2010-11 ............................................................ 1

2 2010-11 CAPITAL PROGRAM ......................................................................... 3

2.1 2010-11 PROGRAM OVERVIEW ............................................................................ 3 2.2 2010-11 PROGRAM EXPENDITURE AS AT 30 JUNE 2011 ........................................... 4

2.2.1 2010-11 Capital Upgrades Program ....................................................................... 5 2.3 ANALYSIS OF HISTORICAL YEAR-TO-DATE EXPENDITURE AS AT 30 JUNE 2011 ................ 7 2.4 NON-FINANCIAL (MILESTONE) OUTCOMES .............................................................. 8

2.4.1 Functional Briefs .................................................................................................. 8 2.4.2 Preliminary Sketch Plans ....................................................................................... 8 2.4.3 Development Applications .................................................................................... 9 2.4.4 Construction Commenced ..................................................................................... 9 2.4.5 Physically Completed Projects ............................................................................. 10

2.5 DELIVERY OF INFRASTRUCTURE FOR THE ACT COMMUNITY ........................................ 11 2.5.1 Land Release Program ........................................................................................ 11 2.5.2 Affordable and Social Housing ............................................................................. 12 2.5.3 Delivery of Roads and Paths Infrastructure ........................................................... 16 2.5.4 Community Safety, Corrections and Justice ........................................................... 23 2.5.5 Providing Education for All .................................................................................. 25 2.5.6 Improved Recreational and Lifestyle Opportunities ............................................... 30 2.5.7 The Arts, Culture and Historic Places .................................................................... 34 2.5.8 The Environment ................................................................................................ 37 2.5.9 Health ............................................................................................................... 40 2.5.10 Other Initiatives ................................................................................................. 43

ATTACHMENTS

A) 2010-11 CAPITAL WORKS EXPENDITURE BY AGENCY B) 2010-11 CAPITAL WORKS EXPENDITURE BY PROJECT C) VARIATIONS TO 2010-11 CAPITAL WORKS PROGRAM D) 2010-11 CAPITAL WORKS UNDERSPENDS E) CAPITAL WORKS PROGRAM 2010-11 END OF YEAR ACQUITTAL

FRONT COVER PHOTOS

TOP: RESTORATION OF THARWA BRIDGE

MIDDLE: MACARTHUR COMMUNITY PARK

SECOND MIDDLE: GUNGAHLIN PUBLIC LIBRARY

BOTTOM: NATION BUILDING AND JOBS PLAN – SOCIAL HOUSING – BRADDON DEVELOPMENT

Page 3: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 1

1 Introduction This report details the Government’s revised 2010-11 Capital Works Program, the achievements during the quarter and total program outcomes for specific projects for the year.

1.1 Summary of Achievements for 2010-11

Final expenditure for the 2010-11 Capital Works Program was $601.655 million – a record infrastructure delivery outcome. Details of the Capital Works Program outcomes by agency and individual project are outlined within Attachments A-D.

Achievements reported for 2010-11 include:

• expenditure for the June quarter of $168.146 million, taking full year expenditure to $601.655 million, improving on last financial year’s record final spend of $580.260 million;

• an end-of-year outcome of 113 functional briefs being lodged out of the required 115, highlighting the level of project planning and tender ready works undertaken;

• the physical completion of 113 projects during the June quarter, bringing the end of year total to 177 projects. A full list of projects completed is at Attachment E. Significant projects physically completed during 2010-11 include:

– the Baldwin Drive/Maribyrnong Avenue intersection upgrade at Lawson South;

– Lanyon Drive Upgrade – Stage 2, Hume;

– upgrade of the Emergency Services Agency – Jerrabomberra and Rivers Sheds;

– Gungahlin College precinct, including Gungahlin College, CIT Learning Centre, Public Library and Town Park;

– Namadgi P-10 School;

– Child and Family Centre at West Belconnen;

– 13 new public art pieces, with 2 installed during the June quarter at the Lake Ginninderra Foreshore and the corner of Benjamin and Belconnen Way;

– New Multistorey Car Park at the Canberra Hospital;

– the refurbished Early Morning Drop-in Centre in the City;

– Calwell High School Performing Arts Centre;

– the relocation of the Electrotechnology Program at Fyshwick CIT campus;

– expansion of the Woden Gymnastics Club;

– Stage 2 of the Southern Tablelands Ecosystem Park at the National Arboretum Canberra;

Page 4: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 2

– expansion of the Intensive Care Unit at Calvary Hospital;

– the program of works for the Establishment of Regional Community Facilities and Neighbourhood Halls;

– the refurbished Lyons Shopping Centre;

– completion of the extension of Braybrooke Street in Bruce;

– commissioning of the Cohen Street Extension and Replacement of Bus Interchange, Belconnen Town Centre;

– Bunda Street in the City refurbishments;

– construction of the Additional Jury Courtroom at the Magistrates Court;

– Harrison District Playing Fields;

– finalisation of upgrades to the Narrabundah Ball Park;

– Tuggeranong Town Park Outdoor Stage;

– the Surgical Assessment and Planning Unit and Neurosurgery Operating Theatre at the Canberra Hospital; and

– various upgrades to facilities at Exhibition Park.

• There have been a number of significant results against the Commonwealth Government’s Nation Building and Jobs Plan Stimulus initiatives:

– Building the Education Revolution – all projects under the Primary Schools for the 21st Century (P21) program and the National School Pride (NSP) program have been completed, with the Territory performing above the national average in delivering both the programs of work. The ACT was the first jurisdiction to complete all of its projects under the NSP program.

– Social Housing Program – Stage 1 of the program was completed in late 2010, with 57 new dwellings completed across the Territory. Stage 2 ($76 million) of this project will deliver a further 297 new social housing dwellings, with 288 properties completed as at 30 June 2011.

Page 5: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 3

2 2010-11 Capital Program 2.1 2010-11 Program Overview

The 2010-11 Budget committed to the most significant investment program for Capital Works across the Territory to date.

The original budgeted capital works program as published in the Budget Papers was $755.716 million. The program was amended to take account of rollovers and other opening financial year adjustments bringing it to $801.183 million. Details of rollovers and savings, including those identified post budget are provided at Attachment C and Attachment D.

A reconciliation of the 2010-11 capital works budget is shown in Table 1 below.

Table 1 2010-11 Original Budget Expenditure(a) $755.716 m Adjustments to Original Budget(b) ($0.274) m Net Unspent Appropriation from the 2009-10 program and accrued

expenditure ($8.193) m

2009-10 Section 16(b) Rollovers $53.934 m Total Funds Available for Expenditure 2010-11 $801.183 m Reconciliation of Total Funds Available for Expenditure for 2010-11 $801.183 m 2010-11 Program Variations(c) $0.000 m Phase 1 Re-profiling(d) -$33.549 m 2011-12 Budget Re-profiling(d) -$95.945 m Identified Savings(d) -$3.509 m Post Budget Rollovers / Anticipated Section 16(b) Rollovers -$66.525 m 2010-11 Capital Works Expenditure Outcome $601.655 m

(a) See 2010-11 Budget Paper 3 – page 189. (b) Original Budget has been amended for project transfers between agencies. The reduction of $0.274 million from the

original budget as published in the 2010-11 Budget Papers is due to projects with 2010-11 funding being accelerated and acquitted in 2009-10, offset by an additional rollover identified after budget.

(c) See Attachment C – Variations to the 2010-11 Capital Works Program. (d) See Attachment D – 2010-11 Capital Works Underspends.

Page 6: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 4

2.2 2010-11 Program Expenditure as at 30 June 2011

The expenditure outcome for the June 2011 quarter was $168.146 million which consisted of:

• New Works expenditure of $47.239 million; and

• Works in Progress expenditure of $120.907 million.

The final expenditure for 2010-11 was $601.655 million, which equates to 75.1 per cent of the total funds available for expenditure for 2010-11 of $801.183 million (or 90 per cent of the estimated outcome as shown in the 2011-12 Budget Papers of $668.110 million). This improves on last financial year’s record final expenditure of $580.260 million, which equated to 74 per cent of the total funds available of $785.384 million.

Table 2 below summarises the Capital Works Program expenditure as at 30 June 2011.

Table 2 – Capital Works Program Expenditure – As at 30 June 2011

Agency

2010-11 Estimated Outcome $’000(1,2)

Total 2010-11

Expenditure $’000

Percentage Spend

Against Estimated Outcome

Leg Assembly 297 264 88.9% TAMS 181,186 183,943 101.1% SSC 355 329 92.7% EDD 60,915 29,781 48.9% Treasury 5,345 3,112 58.2% Health 106,820 95,145 89.1% JACS 37,435 36,793 98.3% ESDD 14,646 6,110 41.7% ETD 186,957 176,950 94.7% CSD 21,316 18,292 85.8% Housing ACT 39,075 37,709 96.5% CIT 10,482 10,482 100.0% CFC 1,829 1,829 100.0% EPC 1,452 916 63.1%

TOTALS 668,110 601,655 90.1%

(1) 2010-11 Estimated Outcome = Total Funds Available for Expenditure – Rollovers (Phase 1 and 2).

(2) As a result of Administrative Arrangements 2011 (No. 1) which took effect on 17 May 2011, expenditure recorded for the financial year up until this date is shown against the receiving agency. The estimated outcome, however, has been updated at agency level to reflect the transfer of projects between agencies. Expenditure in excess of the Estimated Outcome for TAMS for example is attributed to the movement of the Sport and Recreation function from TAMS to EDD.

A breakdown of expenditure by agency is provided at Attachment A. Project by project financial data is provided at Attachment B.

Page 7: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 5

2.2.1 2010-11 Capital Upgrades Program

Capital upgrades are essential works that extend the useful life or improve the service delivery capacity for existing assets and do not include recurrent or ongoing expenditure for repairs and maintenance.

The 2010-11 Capital Upgrades Program final expenditure is $34.011 million, equating to 75.3 per cent, against the available budget of $45.160 million. In addition, 96.9 per cent of the prior year capital upgrades budget is now complete.

Table 3 – Capital Upgrades Program Expenditure – As at 30 June 2011

Agency New Capital Upgrades

2010-11 Budget

2010-11 Project

Savings / Variations

Total 2010-11

Exp % Spend

to Date $’000 $’000 $’000 Leg Assembly 222 -52 147 66.2% TAMS 18,351 -327 16,258 88.6% EDD 1,950 1 1,735 89.0% Health 4,281 -384 2,399 56.0% JACS 1,223 N/A 1,155 94.4% ETD 12,565 -2,823 6,349 50.5% ESDD 1,164 N/A 542 46.6% CSD 2,346 69 2,368 100.9% CIT 2,224 N/A 2,224 100.0% CFC 334 N/A 334 100.0% EPC 500 N/A 500 100.0% TOTAL 45,160 -3,516 34,011 75.3%

Upgrades completed at the Torrens Primary School

Page 8: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 6

Significant upgrade works completed during 2010-11 included:

• Health and Safety, Energy, and Building Improvements for the Canberra Institute of Technology (CIT).

• Various Upgrades at Exhibition Park, including Power and Workshop Improvements, Window Treatments and Tree Planting.

• Land Release Infrastructure Improvements including Roads, Paving, Fencing, Stormwater, Sewer, Water Supply and Landscaping.

• The Rehabilitation of Selected Failed Pavement Sections on Northbound Lanes of Northbourne Avenue.

• Stormwater Augmentation Program.

• Upgrades to Ageing Infrastructure at Dickson Aquatic Centre, Manuka Pool, and Kaleen Enclosed Oval.

Page 9: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 7

2.3 Analysis of Historical Year-to-Date Expenditure as at 30 June 2011

Table 4 and Graph 1 below show historical year-to-date expenditure. Expenditure to 30 June 2011 was at a record level, surpassing the expenditure for 2009-10 and more than doubling the expenditure for 2008-09.

Table 4 – Full Year Capital Works Expenditure Comparison (2003-04 to 2010-11)

Financial Year

Revised Budget $’000

Total 2010-11 Expenditure

$’000

Percentage of Expenditure

Against Revised Budget

2010-11 801,183 601,655 75.1%

2009-10 785,384 580,461 73.9%

2008-09 541,335 296,472 54.8%

2007-08 442,018 282,728 64.0%

2006-07 352,275 218,069 61.9%

2005-06 314,260 163,141 51.9%

2004-05 247,016 129,028 52.2%

2003-04 169,915 108,816 64.0%

Graph 1

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

900,000

2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

$'00

0

Year

Historical Capital Works Expenditure (2003-04 to 2010-11)

Revised Budget $'000 Total 2010-11 Expenditure $'000

Page 10: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 8

2.4 Non-Financial (Milestone) Outcomes

Delivery of the 2010-11 Capital Works Program is also measured against non-financial indicators, captured through monthly milestone updates. Project achievements are recorded by directorates against key milestones for the New Works Program, inclusive of the 2010-11 Capital Upgrades Program.

2.4.1 Functional Briefs

The lodgement of functional briefs is a key indicator of progress made during the project initiation phase of the new works program. There were 115 briefs required for delivery of the 2010-11 New Capital Works Program, of which 113 were completed at 30 June 2011. The Environment and Sustainable Development Directorate (ESDD) has recently completed interrelated studies associated with the Molonglo – East-West Arterial Road and Extension of John Gorton Drive to Molonglo River Feasibility Study. ESDD is also finalising the redesign for the North Weston/Molonglo Stormwater Harvesting Scheme, after the discovery of contamination at the pond site.

2.4.2 Preliminary Sketch Plans

A total of 67 preliminary sketch plans were completed in 2010-11, including for the following projects:

• Official Opening 2013 – National Arboretum Canberra.

• Red Hill Primary School Expansion.

• Forde – Horse Park and Gundaroo Drives Intersection Upgrade.

• Majura and Sutton Road Pavement Rehabilitation.

• Tidbinbilla Rural Fire Service Shed.

• Gungahlin – The Valley Ponds and Stormwater Harvesting Scheme.

• City West Infrastructure Stage 3.

• City Action Plan Stage 1 – Edinburgh Avenue Improvements.

• Transport for Canberra – Cotter Road Improvements.

• Transport for Canberra – Barry Drive and Clunies Ross Street Intersection Upgrade.

• Tuggeranong Health Centre Stage 2.

• Integrated Capital Region Cancer Centre – Phase 1.

• Enhanced Community Health Centre – Belconnen.

• Lake Ginninderra Community Path Lighting.

Page 11: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 9

2.4.3 Development Applications

As at 30 June 2011, 35 Development Applications had been lodged, including those for the following projects:

• Coombs Water Quality Control Ponds.

• Harrison – Well Station Drive Extension to Horse Park Drive.

• Enhanced Community Health Centre – Belconnen.

• New Gungahlin Health Centre.

• Integrated Capital Region Cancer Centre – Phase 1.

• Tuggeranong Health Centre – Stage 2.

• Bonner Primary School (design).

• Tidbinbilla Rural Fire Services Shed.

• Gungahlin – The Valley Ponds and Stormwater Harvesting Scheme.

• Transport for Canberra – Barry Drive and Clunies Ross Street Intersection Upgrade.

• Kings Highway Upgrade.

• North-South Arterial Road for Molonglo Suburbs.

• Strathnairn Homestead – Kitchen, Toilet and Verandah Improvements.

• Strathnairn Homestead – Additional Studio Space and Landscaping.

2.4.4 Construction Commenced

Construction had commenced on 125 projects as at 30 June 2011, including the following:

• Coombs – Water Quality Control Ponds.

• Gungahlin Wellbeing Precinct – Infrastructure Works.

• Harrison – Well Station Drive Extension to Horse Park Drive.

• Casey – Clarrie Hermes Drive Extension to the Barton Highway.

• Accelerating Replacing Stormwater Drains with Wetlands.

• Adult Acute Mental Health Inpatient Unit.

• Women and Children’s Hospital.

• New Gungahlin Health Centre.

• Refurbishment of Existing Health Centre – Tuggeranong Stage 1.

• New Forensic Medical Centre.

• Lawson – Ginninderra and Aikman Drives – Intersection Upgrade.

• Upgrades at the Red Hill Shopping Centre.

Page 12: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 10

2.4.5 Physically Completed Projects

A total of 177 projects were physically completed in 2010-11. Of these, 113 were completed during the June quarter. Key projects completed are shown below:

• Electrotechnology Program Relocation at the Canberra Institute of Technology.

• Upgrades and improvements at the CIT.

• National Partnership – Indigenous Early Childhood Development – Third Child and Family Centre.

• Establishment of Regional Community Facilities and Neighbourhood Halls.

• Various Public Art projects.

• Manuka Arts Centre Landscape Works.

• Manuka Oval Facilities Upgrades.

• Upgrades at Canberra Stadium including lighting and televisions.

• Upgrade and Expansion of the Woden Gymnastics Club.

• Harrison – District Playing Fields.

• Upgrades at Exhibition Park in Canberra including tree planting and re-wiring.

• Dickson and Kingston Master Plans.

• Nation Building and Jobs Plan – Building the Education Revolution.

• Gungahlin College.

• Namadgi P-10 School.

• Neurosurgery Operating Theatre and Surgical Assessment and Planning Unit at the Canberra Hospital.

• Intensive Care Unit at Calvary Hospital.

• New Multistorey Car Park at the Canberra Hospital.

• Refurbish Early Morning Drop-in Centre in the City.

• National Partnership – Social Housing.

• Emergency Services Agency – Jerrabomberra and Rivers Sheds.

• Narrabundah Ball Park Facility.

• Barry Drive Bus Lanes – Roads to Recovery Program.

• Gungahlin College – Offsite Works.

• Belconnen Town Centre – Cohen Street Extension and Bus Interchange.

• Park ‘n’ Ride and Bike ‘n’ Ride Facilities in Erindale and Mitchell.

• Upgrade of Bunda Street Paving.

• Glebe Park Pavement Replacement.

• Bruce – Braybrooke Street Extension.

Page 13: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 11

2.5 Delivery of Infrastructure for the ACT Community

2.5.1 Land Release Program

The annual land release program is an important part of the Government’s economic and social strategy. The program assists the Territory in delivering a range of affordable housing initiatives arising from the Affordable Housing Action Plan and supports the needs of a growing city, changing households and an expanding economy.

The land release program aims to maintain a level of land release to meet strong demand for residential housing, develop an inventory of serviced land and assist with housing affordability.

A total of 5,048 residential sites were released in 2010-11. These were largely situated in the high priority areas of Gungahlin and Molonglo, with more than 75 per cent of residential dwelling sites released from these two locations.

Land Release Significant Achievements for 2010-11

• The release of five sites for childcare use was announced on 29 April 2011. The sites in Macarthur, Holt, McKellar, Gungahlin and Giralang will assist in the provision of more affordable childcare places across Canberra.

• Eight multi-unit development sites were sold on Flemington Road in Franklin in between July 2010 and the end of March 2011. All sites are close to public transport, the Gungahlin Town Centre and Harrison Schools.

• Five commercial blocks zoned for bulky goods retailing, warehousing, vehicle sales, a transport depot and restaurants were sold in Fyshwick in February 2011.

• A mixed-use development site at the Kingston Foreshore was sold in February 2011. Once completed, the site will provide for medium density housing, offices, restaurants and shops.

• Four multi-unit sites were sold in the new Molonglo suburb of Wright between September and December 2010. Up to 231 dwellings will be constructed over the sites, including terrace dwellings, apartments and townhouses.

Several other related infrastructure projects are progressing to facilitate future land releases, including the Forde – Mulligans Flat Road Extension and Water Quality Control Pond, Casey – Clarrie Hermes Drive Extension to the Barton Highway, North-South Arterial Road for Molonglo Suburbs, Bonner – Western Distributor Road and Sewer, Lawson South – Road Intersections and Coombs – Water Quality Control Ponds.

Page 14: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 12

2.5.2 Affordable and Social Housing

A number of projects have been delivered under the Nation Building and Jobs Plan and other ACT/Commonwealth Government funded initiatives including the construction of new dwellings and repairs and maintenance to existing Housing ACT properties.

Affordable and Social Housing Significant Achievements for 2010-11

Two completed A Place to Call Home dwellings in Bonner

• Homelessness Initiative – A Place to Call Home – this initiative, jointly funded by the ACT/Commonwealth Government, provides for 20 dwellings for housing homeless families, 10 of which were delivered in 2009-10. Two properties in Bonner have been completed during the quarter, with another dwelling in the final stages and another at lock up stage. The remaining blocks of land have exchanged contracts and works will be commencing over the coming months.

Page 15: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 13

Completed social housing dwellings in Chapman (Nation Building and Jobs Plan)

• Stage 1 of the Nation Building and Jobs Plan – Social Housing project was completed in late 2010, with 57 new dwellings completed across the Territory. Stage 2 ($76 million) of this project will deliver a further 297 new social housing dwellings. To date, 288 properties have been completed. Works on all remaining sites are progressing well, with completions and handovers during June 2011 including 52 units in Conder, the first stage of a 70 unit complex in Rivett, and completion of further homes in Florey, Chapman and Hackett.

• Other social housing dwellings have been completed across Canberra in 2010-11 under the Nation Building and Jobs Plan, including in Curtin, O’Connor, Kambah and Bonython.

Curtin

Page 16: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 14

O’Connor

Kambah

Bonython

Page 17: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 15

• Under the Nation Building and Jobs Plan – Social Housing project, a 42 unit development in Braddon was officially opened on 21 April 2011, with 15 units made available for a new Youth Integrated Education and Accommodation Service, 18 units for public housing and 9 units for rebated renters. [see front cover photo]

Page 18: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 16

2.5.3 Delivery of Roads and Paths Infrastructure

Significant upgrades to the Territory’s roads, the construction of bus lanes to facilitate more efficient public transport, the improvement of safety measures at Black Spot locations and a number of new or upgraded car parks have been delivered in 2010-11. More than 702,000 square metres of road resurfacing has been completed across the Territory in 2010-11. These upgrades will result in better traffic conditions, congestion reduction and improved road safety across the Territory.

June Quarter Outcome

Timber and stainless steel trusses were installed on the Tharwa Bridge in

November 2010

The newly reopened Tharwa Bridge

[see front cover photo also]

Page 19: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 17

A number of significant milestones were achieved during the June quarter:

• The Tharwa Bridge has reopened. This follows the installation of eight new timber and stainless steel trusses on the bridge in November 2011. All works on the bridge are scheduled for completion by the end of 2011.

• Construction of the new signalised intersection at Baldwin Drive and Maribyrnong Avenue in Lawson South was completed in early May 2011. This project will better enable flow of traffic out of the Lawson land release and complements other intersection upgrades for the Lawson area at Ginninderra Drive and Allawoona Street and Ginninderra Drive and Aikman Drive.

• The Hume – Lanyon Drive Upgrade – Stage 2 is now complete and fully operational, with all roads and bridge lanes opened to traffic in April 2011. Minor landscaping along the duplication and creek protection works at Jerrabomberra Creek Bridge has recently been completed. The newly duplicated road has been constructed to improve travel times between Canberra and Queanbeyan and is a jointly Commonwealth, New South Wales and ACT Government funded initiative.

The bridge over Canberra Avenue will be strengthened and safety screens added as

part of the Monaro Highway Duplication

• Construction began on the Monaro Highway Duplication in April 2011. The initiative, funded through the Commonwealth Government’s Nation Building Program, will provide for a four lane divided road between Newcastle Street and Canberra Avenue adjacent to Fyshwick. The existing bridge over Canberra Avenue will be strengthened and new bridges will be constructed over Canberra Avenue and across the existing rail line to accommodate the dual carriageway.

• The first stage of the extension of Mulligans Flat Road from Jessie Street in Forde to the New South Wales border is complete, with more than 1.6 kilometres of the southern section of asphalt constructed. The second section of the road, towards the north, is expected to be completed by the end of 2011.

Page 20: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 18

Completed traffic signals, line marking and asphalt on the Western Distributor Road

• Road surfacing, traffic signals, street lighting, line marking and sewer works were completed on the new Western Distributor Road and Sewer at Bonner during the June quarter. The road will provide a connection between the suburbs of Bonner and Jacka, and a trunk sewer extension to service Jacka.

Other Significant Achievements for 2010-11

• Bruce – Braybrooke Street Extension – this project was completed in November 2010 and provides for a southern entrance to new residential estates in Bruce and facilitates safer traffic flows around the neighbouring Australian Institute of Sport.

Bulk earthworks being undertaken on the Kings Highway Upgrade

• Works continue on the upgrade of the Kings Highway including general earthwork operations, construction of structures and stormwater pipes. The upgrade will provide for the construction of a single carriageway deviation to the south of the existing highway, approximately 5 kilometres in length. The new road will improve travel times and traffic flow, resulting in safer travel between the ACT and both the Defence Headquarters Joint Operations Command (HQJOC) centre and the coastal region.

Page 21: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 19

Aerial shot of the North-South Arterial Road for Molonglo Suburbs to the northwest

including bridge works

New traffic lights at the intersection of Streeton Drive and Cotter Road

• Twin bridge work over Weston Creek to the northwest of Streeton Drive on the North-South Arterial Road for Molonglo Suburbs (John Gorton Drive) is substantially complete. The signalised intersection at Streeton Drive has been installed and stormwater works are in progress. Service roads to the new John Gorton Drive are also underway. Once finalised, the road will form the major access point for the Molonglo Valley development, stretching 3.5 kilometres to the northwest of the Cotter Road/Streeton Drive intersection.

Page 22: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 20

The Barton Highway bridge section of the GDE

Works on the road section between the Barton Highway and Aranda

• Significant works have been undertaken and completed on the Gungahlin Drive Extension (GDE) – Stage 2 during 2010-11, including:

– construction of all bridges required for the duplication, including the re-construction of the Barton Highway bridge;

– finalisation of works to the Glenloch interchange; and

– progress on the duplication of the road section between the Barton Highway and Aranda.

Page 23: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 21

• The duplicated road will become operational in both directions in the second quarter of 2011-12.

– Following the opening of the road, barriers and signage will be installed and landscaping will be finalised.

New bus platforms and shelters as part of the Belconnen Town Centre – Cohen

Street Extension and Replacement of Bus Interchange

• The Belconnen Town Centre – Cohen Street Extension and Replacement of Bus Interchange became fully operational in November 2010. Improvements to the interchange include six new bus platforms, an indoor waiting lounge and outdoor bus shelters.

• Refurbishments to Bunda Street in the City were completed in late 2010, providing for new pavement, improved street lighting and new furniture.

Construction of noise walls for Clarrie Hermes Drive in Nicholls

Page 24: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 22

• Works on the Clarrie Hermes Drive Extension to the Barton Highway at Casey are continuing. Earthworks and the construction of noise walls in Nicholls are progressing and asphalt works are being undertaken on the Barton Highway to accommodate the extension.

The widening of Horse Park Drive at the intersection of Well Station Drive

• Harrison – Well Station Drive Extension to Horse Park Drive – this project will provide for the extension of Well Station Drive, from Turtle Rock Street in Harrison to Horse Park Drive and will support land releases in Harrison 4 and Kenny. Works progressing on the extension include the widening of Horse Park Drive to accommodate the new road and construction of a new roundabout providing access to the first stage of the Harrison 4 estate.

Page 25: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 23

2.5.4 Community Safety, Corrections and Justice

June Quarter Outcome

The public entrance to the Forensic Medical Centre at Phillip

Office space inside the new centre

A number of milestones were achieved during the June quarter:

• The New Forensic Medical Centre in Phillip was nearing completion as at 30 June 2011 and has since become operational. The new centre replaces the 40 year old facility at Kingston.

• Jerrabomberra and Rivers Sheds projects were completed with the Rivers work completed in February 2011 and the Jerrabomberra component in May 2011. The upgraded sheds will ensure secure housing for emergency response vehicles and more appropriate office and training spaces.

Page 26: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 24

Other Significant Achievements for 2010-11

The new Jury Courtroom at the Magistrates Court

• Construction of the Additional Jury Courtroom and deliberation room at the Magistrates Court was completed during the December quarter, with the first hearing conducted on 8 November 2010. The new rooms provide supplementary capacity to run jury trials in addition to the two courtrooms located at the Supreme Court.

Page 27: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 25

2.5.5 Providing Education for All

June Quarter Outcome

• The Building the Education Revolution (BER) program was completed in May 2011. The Territory performed above the national average in delivering both programs of work – the Primary Schools for the 21st Century (P21) program and the National School Pride (NSP) program.

– All 84 projects across 82 public schools under the NSP program were completed by March 2010, with the ACT the first jurisdiction to complete all projects.

– The last project of the 68 P21 program was completed in May 2011 with the commissioning of a new Environment Centre at the Namadgi School.

– Some of the completed P21 projects are shown in the pictures below:

Most recently completed P21 project – Environment Centre at the Namadgi School

Arawang Primary School’s new multi-purpose hall

Page 28: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 26

Indoor performing arts space and sporting courts at Charles Conder Primary School

Enhanced library facilities at Hughes Primary School

Environmental Learning Room at Wanniassa Hills Primary School

Page 29: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 27

Gold Creek Primary School – new Environmental Centre

Interior of Sports Hall at Kaleen Primary School

Progress and achievements on other major education projects are shown below:

The courtyard at Gungahlin College

Page 30: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 28

Science laboratories at the Gungahlin College

• Gungahlin College and the CIT Learning Centre were officially opened on 21 May 2011. The school has been functional since the start of the 2011 school year providing opportunities in the areas of specialised science, visual and performing arts, sport science and fitness, design and technology, mechatronics and wood and metal studies for students.

Completed buildings and outdoor recreation area at the new Namadgi School

• The Namadgi P-10 School was officially opened on 4 June 2011. Stage 1 of the school includes preschool to year 7 buildings, administration offices, an assembly hall and library, which were all completed in time for the beginning of the 2011 school year. Stage 2 facilities, including years 8 to 10 buildings and the gymnasium have recently been commissioned. Currently, the school accommodates students enrolled from preschool to year 7, however, the school will grow to full capacity by adding a year level to enrolment every year until 2014.

Page 31: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 29

Other Significant Achievements for 2010-11

• Schools Infrastructure Program – the five year, $90 million program of works to improve facilities at older ACT public schools was completed in February 2011.

• Calwell High School Performing Arts Centre was officially opened in February 2011. The centre seats 350 people, has been designed for dance, music and theatre performances and is wheelchair accessible.

The completed Electrotechnology Building at CIT Fyshwick

• The Electrotechnology Building at the CIT Fyshwick Campus was completed in February 2011 and will provide up-to-date training facilities and equipment for fast developing trades. Electrotechnology students will have the opportunity to focus particularly on green technologies.

• The feasibility study for a new CIT Learning Centre at Tuggeranong was completed during 2010-11. The study explores the possibility of expanding the range of learning services that CIT provides to the Tuggeranong community, the functional and location requirements and the emerging planning concepts for flexible education delivery.

Stage 1 works at Harrison Secondary School are now complete

• Harrison Secondary School – stage 1 works providing for the middle school and gymnasium were completed during June 2011. The primary and pre-school component of Harrison School were completed in early 2008 and the secondary campus on the same site will cater for up to 800 students from years 6-10. The remaining works on the secondary school site are scheduled for completion prior to the start of the 2012 school year.

Page 32: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 30

2.5.6 Improved Recreational and Lifestyle Opportunities

The delivery of improved recreational and lifestyle areas and facilities across Canberra have provided upgrades to a number of sporting facilities, parks, urban open space and public places in 2010-11.

June Quarter Outcome

A new bird’s nest swing incorporated at the renewed Macarthur playground

[see front cover photo also]

A number of milestones were achieved during the June quarter:

• Construction commenced on the renewal of six play spaces across Canberra during the quarter, with five out of the six now complete. Playgrounds in Kaleen, Chapman, Curtin, Gowrie, Greenway and Macarthur have been upgraded to comply with Australian and ACT Standards and best practice contemporary play space design. Works to be completed include the play space renewal at Kaleen and the installation of some shade sails at existing playgrounds.

• New directional signs, bubblers and seats have been erected around the west basin of Lake Burley Griffin. A total of 37 signs have been installed around the 16 kilometre loop, with further signs to be installed around the central and eastern basin loops of Lake Burley Griffin, at Lake Ginninderra, Lake Tuggeranong and Yerrabi Pond. The signs include distances, walking and cycling times, maps and details of nearby attractions and heritage sites.

Page 33: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 31

The new Gungahlin Public Library is open and is part of the Gungahlin College

Precinct [see front cover photo also]

• The new Gungahlin Public Library was opened on 17 June 2011. The library is located adjacent to the Town Park and stocks 70,000 books, magazines and DVDs. A cafe and outdoor courtyard are part of the library facility, which also includes six meeting rooms available for general community use.

Entrance to the new Child and Family Centre at Kippax

• The third multi-purpose Child and Family Centre for the ACT was opened at Kippax on 2 May 2011. The centre, along with the already completed centres in Tuggeranong and Gungahlin, was built as part of the Indigenous Early Childhood Development National Partnership. The new centre at Kippax will provide children and families with access to early learning activities, play group and parental courses, maternal and child health, and outreach programs specifically designed for Aboriginal and Torres Strait Islander families.

Page 34: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 32

Other Significant Achievements for 2010-11

• The new Tuggeranong Town Park outdoor stage was completed in September 2010, providing a place for community performance and festival space capable of catering for up to 8,000 people.

• A pavilion, six football fields and cricket practice facilities were completed at the new Harrison District Playing Fields in October 2010. The new fields provide the appropriate infrastructure for the needs of the Gungahlin sporting community.

Gungahlin Town Park at the College Precinct

• The Gungahlin Town Park was completed in March 2011 as part of works associated with the Gungahlin College precinct. Among the facilities at the park is the A is for Alexander, B is for Bunyip, C is for Canberra piece of public Art. The park is irrigated by recycled stormwater, has drinking fountains, public toilets and a performance stage that is available for public bookings.

New seating and upgraded playing surface at the Narrabundah Ball Park – home of

the Canberra Cavalry

• The newly refurbished Narrabundah Ball Park was unveiled in November 2010. In support of the Canberra Cavalry competing in the Australia Baseball League, upgrades to the ball park include spectator seating, drought tolerant turf on the infield, a new irrigation system, electronic scoreboard, player safety padding, full-size dugouts and lighting to television broadcast standards.

Page 35: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 33

• The upgraded and expanded Woden Gymnastics Club was commissioned in January 2011, adding more than 400 square meters to the existing building and providing access to quality gymnastic facilities in the central south of Canberra.

The new national competition standard Belconnen Skate Park

• Works are progressing on the Belconnen Skate Park and Eastern Valley Way Inlet Upgrade. The skate park component is largely complete, with new elements of street skating introduced and new facilities capable of hosting national competitions.

Page 36: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 34

2.5.7 The Arts, Culture and Historic Places

A number of projects associated with Canberra’s arts, culture and historic places have been completed in 2010-11.

June Quarter Outcome

Winds of Light on the shores of Lake Ginninderra

• Winds of Light by artist Peter Blizzard was installed at the Lake Ginninderra foreshore on 26 May 2011. The work portrays the effect that the natural landscape has on the wellbeing of the human spirit.

Owl on the corner of Benjamin and Belconnen Way at Belconnen

• A sculpture honouring the largest owl species in Australasia, the Powerful Owl, was launched on 12 May on the corner of Benjamin Way and Belconnen Way, Belconnen. Owl by Bruce Armstrong has been portrayed as a totem overlooking its domain, as the species has a commanding presence when encountered in the wild.

Page 37: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 35

Other Significant Achievements for 2010-11

Life Cycle at the Petrie Plaza, Civic

• Public Art piece Life Cycle by Murrumbateman artist David Jensz was installed on a large granite plinth on Bunda Street, Civic in December 2010.

• The Restoration of Hobday’s Cottage and English Gardens at Weston Park was completed in March 2011. The heritage listed building is now home to more seating and increased exhibition space, improved lighting to the common car park and preserved gardens to provide a valuable learning centre for plant identification and culture.

dna sculpture situated in Yarralumla

• Purchased from the 2009 Bondi Sculpture by the Sea exhibition, dna by sculptor Jonathan Leahey was installed as a roadside artwork on Alexandrina Drive, Yarralumla in November 2010.

Page 38: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 36

Installation of Wide Brown Land at the National Arboretum Canberra

• Dorothea Mackellar’s poem My Country is reflected in the sculpture Wide Brown Land which was unveiled in July 2010 at the National Arboretum Canberra. The piece is three metres high and made of steel.

• Landscaping at the Strathnairn Arts Centre was completed in March 2011. Other works being undertaken at the homestead and arts centre include improvements to the kitchen, toilets and veranda, additional studio space and a bronze foundry workshop.

Page 39: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 37

2.5.8 The Environment

Works on a number of environmental/sustainability projects have progressed over the June quarter including those shown below:

June Quarter Outcome

A number of significant milestones were achieved during the June quarter:

• Several tree plantings took place in the Central Valley at the National Arboretum Canberra during the quarter. The Valley is reserved for plantings on behalf of Australian icons and international guests and has been enhanced by plantings as shown below:

Major General Michael Jeffrey (left) and The Honourable Julia Gillard MP, Prime Minister of Australia (right) (with former Chief Minister Jon Stanhope) planting a

eucalypt and a ghost gum at the National Arboretum Canberra

United States Ambassador Mr Jeffery Bleich (left) and President of the Republic of Cyprus Mr Demetris Christofias (right) (with Chief Minister Katy Gallagher) planted

trees in the Central Valley

Page 40: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 38

Other Significant Achievements for 2010-11

Gross Pollution Trap access and wall forms at one of the water quality control ponds

at Coombs

• Two ponds are being constructed in the new suburb of Coombs. The ponds will improve the water quality of runoff from new development areas in the Molonglo Valley and from Stromlo Forest Park and Village. Non-potable water will also be provided for irrigation. Works are being undertaken on fill, inlet towers, floodway reinforcement, bridge pier foundations, spillways and excavation.

Paths and new tree plantings at the Dickson wetlands

• Both wetland developments being delivered as part of the Accelerating Replacing Stormwater Drains with Wetlands project are approaching completion, with all civil works finalised at the Dickson site. Tree planting and landscape works have been engaged at the Dickson wetlands also. A large portion of civil works have been completed at the Lyneham pond, with the remaining works having begun recently after the successful testing of the replacement sewer. Both ponds are on target for completion by the end of 2011.

Page 41: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 39

• More than 1,600 street trees have been replanted across the ACT in 2010-11, to replace dangerous, dead or dying trees. The new trees are a mix of natives and deciduous trees and have been planted as part of the Government’s tree management program.

• Other significant milestones at the National Arboretum Canberra for 2010-11 include:

– The finalisation of Stage 2 of the Southern Tablelands Ecosystems Park garden in March 2011 including the planting of the understory species at the site to represent the grassy woodland ecosystem of the Southern Tablelands. Other significant works completed to date include construction of the dam, the earthworks for the Central Valley ceremonial gardens, upgrades to the road network and construction of the Events Terrace.

– Tree plantings by numerous politicians, musicians and sporting icons in the Central Valley: Federal Environment Protection Minister Peter Garrett, Governor-General Quentin Bryce AC, Prime Minister of Mongolia Mr Sukhbaatar Batbold MP, sporting icons Mal Meninga, Robert De Castella, Lauren Jackson and David Campese, the Right Honourable Malcolm Fraser and Jimmy Barnes.

Page 42: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 40

2.5.9 Health

Works continue on the redevelopment and reconfiguration of Canberra’s hospitals and healthcare facilities and the establishment of a sustainable and modern health system, to ensure the availability and ongoing viability of quality health care now and into the future.

June Quarter Outcome

A number of significant milestones were achieved during the June quarter:

• New Gungahlin Health Centre – the project manager was appointed on 28 April 2011, following the release of the preliminary sketch plans during March 2011. The new health centre will provide a range of health services including treatment, screening, counselling, therapy, community support, education services and group programs. A new enhanced community health centre will also be built in Belconnen and the existing community health centre in Tuggeranong will be extended and refurbished.

Other Significant Achievements for 2010-11

New facilities at the Neurosurgery Operating Theatre (left) and Surgical Assessment

Planning Unit (right)

• Neurosurgery Operating Theatre and Surgical Assessment and Planning Unit (SAPU) at the Canberra Hospital. The Neurosurgery component of this project was opened in September 2010. The new surgery facility includes an intra-operative medical resonance imaging suite and allows staff to conduct medical imaging during surgery. The new 16-bed SAPU was opened in October 2010 and provides diagnostic management planning services for surgical patients presenting to the hospital.

Page 43: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 41

New 24 hour Multistorey Car Park at the Canberra Hospital

• All eight levels of the new Multistorey Car Park at the Canberra Hospital are open and operational. The new facility provides 24 hour parking for staff, patients and visitors.

Upgraded facilities at the Intensive Care Unit – Calvary Hospital

• Intensive Care services at Calvary Hospital were enhanced during the March quarter, with the opening of the expanded Intensive Care Unit. The Intensive Care/High Dependency Unit and the Coronary Care Unit have both been refurbished to meet growing demand.

Page 44: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 42

The Adult Mental Health Inpatient Facility under construction

• Works are progressing on the Adult Mental Health Inpatient Facility with the majority of steel work completed and roofing, brick laying and roof cladding all advancing. Engineering services and internal fit-out has also been engaged. The project will provide for a 40 bed mental health facility at the Canberra Hospital.

Works are progressing on the Women and Children’s Hospital

• The new 146 bed Women and Children’s Hospital at the Canberra Hospital is well underway, with stage one works involving the extension of the existing maternity building progressing. Formwork, reinforcement and electrical services are engaged, trade packages are being procured and documentation for tendering packages continues.

Page 45: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Capital Works Program June Outcome Report

Page 43

2.5.10 Other Initiatives

June Quarter Outcome

• The expanded Baringa Childcare Centre was officially opened on 10 May 2011, with increased capacity for babies by an additional 24 places. The expansion, built in an adjacent former medical clinic, has created more childcare places in the same location for Spence residents.

• Design works are underway for a new Southern Cemetery and Memorial Park in Tuggeranong. Once built the cemetery will include a mix of burial and cremation services. Tree planting at the proposed site has been undertaken during the June quarter to prepare the site.

• Early Morning Drop-in Centre in the City – the refurbishment of the centre at Pilgrim House on Northbourne Avenue was completed in June 2011. The works undertaken have doubled the existing seating capacity for meals, provided a full commercial kitchen, administration and interview rooms, showers, toilets and laundry facilities.

• Upgrades to 87 bus stops across the ACT were completed in June 2011, improving accessibility for people with disabilities.

Other Significant Achievements for 2010-11

The Chifley Health and Wellbeing Hub was completed in February 2011

• The program of works for the Establishment of Regional Community Facilities and Neighbourhood Halls was completed in March 2011. Components of the program include neighbourhood halls and community hubs in Chifley, Griffith, Cook, Bonython, Weston, Kambah and Holt.

• Upgrades to the Lyons Shopping Centre were unveiled in March 2011. The shopping centre now has improved lighting, a shade area, bike racks, upgraded pavement and street furniture, community notice boards, new trees and drought tolerant shrubs.

Page 46: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT A

2010-11 Capital Works Program

June Quarter Expenditure

Summary

Page 47: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

CABINET IN CONFIDENCE Attachment A

Agency

Original Budget $'000(1)

Total Funds Available for Expenditure

$'000(2)

2010-11 Estimated Outcome (incl. Est.

Rollovers) $'000(3)

June Quarter Expenditure

$'000

Total2010-11

Expenditure $'000

Percentage Spend

Against Total Funds

Available for Expenditure

Legislative Assembly Secretariat 427 427 297 82 264 61.8%Territory and Municipal Services Directorate 165,720 174,006 181,186 59,200 183,943 105.7%Shared Services Centre 355 355 355 41 329 92.7%Economic Development Directorate 95,821 96,146 60,915 15,242 29,781 31.0%Treasury Directorate 7,420 8,705 5,345 2,206 3,112 35.7%Health Directorate 166,001 171,432 106,820 26,866 95,145 55.5%Justice and Community Safety Directorate 45,445 53,356 37,435 18,858 36,793 69.0%Environment and Sustainable Development Directorate 20,583 21,452 14,646 2,298 6,110 28.5%Education and Training Directorate 186,564 193,569 186,957 32,551 176,950 91.4%Community Services Directorate 25,305 27,289 21,316 7,122 18,292 67.0%Housing ACT 26,573 39,075 39,075 1,259 37,709 96.5%Canberra Institute of Technology 10,482 10,482 10,482 1,769 10,482 100.0%Cultural Facilities Corporation 1,686 1,829 1,829 349 1,829 100.0%Exhibition Park Corporation 3,060 3,060 1,452 303 916 29.9%

TOTALS 755,442 801,183 668,110 168,146 601,655 75.1%

Notes:

2) Total funds available includes opening balance adjustments, prior year underspends and indicative 2009-10 section 16(b) rollovers.3) 2010-11 Estimated Outcome (incl. est. Rollovers) = Total Funds Available for Expenditure - Rollovers (Phase 1 and 2).

2010-11 Capital Works Program - Expenditure Summary as at 30 June 2011

1) Original Budget has been amended for project transfers between agencies. The reduction of $0.274 million from the original budget as published in the 2010-11 Budget Papers is due to projects with 2010-11 funding being accelerated and acquitted in 2009-10, plus an additional rollover identified after budget.

Page 48: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT B

2010-11 Capital Works Expenditure by Project

Page 49: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

2010-11 Capital Upgrades Program

Building Fabric Restoration 145 40 0 0 145 40 0 0 0 39 40 39Building Plant Replacement 10 8 0 0 10 8 0 5 0 6 8 6Occupational Health and Safety 52 105 0 0 52 105 13 0 57 85 105 85Improved Environmental Measures 15 17 0 0 15 17 7 0 10 17 17 17

Sub-Total 222 170 0 0 222 170 20 5 67 147 170 147

Total New Works 222 170 0 0 222 170 20 5 67 147 170 147

WORKS IN PROGRESS

Lift Upgrade 285 211 97 97 185 114 0 0 0 114 211 211Improved Environmental Measures 78 54 51 51 20 3 0 0 -10 3 54 54

Sub-Total 363 265 148 148 205 117 0 0 -10 117 265 265

Total Works in Progress 363 265 148 148 205 117 0 0 -10 117 265 265

TOTAL CAPITAL WORKS PROGRAM 585 435 148 148 427 287 20 5 57 264 435 412

FOR THE PERIOD ENDED 30/06/2011LEGISLATIVE ASSEMBLY SECRETARIAT 2010-11 CAPITAL WORKS PROGRAM

Page 50: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

1

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Roads ACT and Road TransportTransport for Canberra – Walking and Cycling Infrastructure

1,000 1,000 0 0 1,000 1,000 260 202 124 730 1,000 730

Transport for Canberra – Parkes Way Widening 14,700 14,700 0 0 0 0 0 0 0 0 0 0Transport for Canberra – Phillip and Majura Avenues Intersection Upgrade

1,000 1,000 0 0 100 100 30 0 1 122 100 122

Transport for Canberra – Cotter Road Improvements 7,150 7,150 0 0 150 209 1 1 1 300 209 300

Transport for Canberra – City Path Lighting 1,500 1,500 0 0 500 500 17 49 292 501 500 501Transport for Canberra – Major Bus Stops Program 1,750 1,750 0 0 150 150 0 1 6 145 150 145

Transport for Canberra – Installation of Bus Shelters 1,000 1,000 0 0 500 111 2 0 4 89 111 89

Transport for Canberra – Canberra Avenue Bus Priority Measures

8,200 8,200 0 0 200 149 2 18 1 150 149 150

Transport for Canberra – Northbourne Avenue Bus Priority Measures and Dickson Major Bus Station

4,250 4,250 0 0 250 238 0 0 161 272 238 272

Transport for Canberra – Park and Ride Facilities 4,100 4,100 0 0 900 750 53 46 435 734 750 734Transport for Canberra – Improvements to City Bus Services and Facilities

2,000 2,000 0 0 100 100 0 0 95 98 100 98

Transport for Canberra – Gungahlin Town Centre Major Bus Station

1,675 1,675 0 0 175 108 0 -1 48 156 108 156

Transport for Canberra – Erindale Centre Major Bus Station

3,150 3,150 0 0 150 120 0 0 28 148 120 148

Transport for Canberra – Bike and Ride Facilities 700 700 0 0 250 190 46 51 115 238 190 238Transport for Canberra – Belconnen to City Transitway Stage 1 (Barry Drive and College Street Sectors)

7,300 7,300 0 0 700 417 2 127 2 418 417 418

Transport for Canberra – Barry Drive and Clunies Ross Street Intersection Upgrade

7,000 7,000 0 0 100 100 19 18 23 114 100 114

Transport for Canberra – Flemington Road Bus Priority Study (Design)

750 750 0 0 100 100 0 0 0 105 100 105

Transport for Canberra – ACT Road Safety Strategy (Design)

500 500 0 0 250 326 0 109 0 238 326 238

Transport for Canberra – Belconnen to City Bus Transitway Alignment (Feasibility)

200 200 0 0 200 100 0 0 0 0 100 0

Transport for Canberra – Barton Major Bus Station (Feasibility)

100 100 0 0 100 100 0 0 13 100 100 100

Bridge Strengthening on Commercial Routes 1,000 1,000 0 0 1,000 401 0 132 80 213 401 213Majura and Sutton Road Pavement Rehabilitation 2,250 2,250 0 0 250 250 2 1 103 224 250 224Page and Fyshwick Stormwater Augmentation 3,000 3,008 0 0 1,000 3,008 678 551 656 3,008 3,008 3,008Naas Road – Gudgenby Bridge (Design) 200 200 0 0 200 200 8 21 95 200 200 200Lake Ginninderra Community Path Lighting 1,000 1,000 0 0 1,000 898 85 22 328 657 898 657Drakeford Drive Pedestrian Link for Kambah P-10 School (Design)

240 240 0 0 240 240 0 50 67 175 240 175

Ashley Drive Upgrade (Feasibility) 150 150 0 0 150 150 0 8 -10 128 150 128Sub-Total 75,865 75,873 0 0 9,715 10,015 1,205 1,406 2,668 9,263 10,015 9,263

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 51: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

2

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Parks, Conservation and LandLake Ginninderra District Park Playground and Picnic Facilites

300 300 0 0 300 300 125 6 61 239 300 239

Strategic Bushfire Management Plan Version 23 3,798 3,798 0 0 925 560 0 15 116 479 560 479Belconnen Skate Park (Design) 200 2,200 0 0 200 1,400 388 222 1,021 1,798 1,400 1,798Jerrabomberra Wetlands Infrastructure Improvements

2,341 2,341 0 0 274 136 21 29 44 137 136 137

Sub-Total 6,639 8,639 0 0 1,699 2,396 534 272 1,242 2,653 2,396 2,653

Sports and RecreationNarrabundah Ball Park Facility Upgrade 1,050 1,050 0 0 1,050 1,050 48 -48 0 1,050 1,050 1,050

Sub-Total 1,050 1,050 0 0 1,050 1,050 48 -48 0 1,050 1,050 1,050

ACTIONACTION – Depot Upgrades (Feasibility) 151 151 0 0 151 151 24 0 0 151 151 151

Sub-Total 151 151 0 0 151 151 24 0 0 151 151 151

Land Release ProgramLawson – Ginninderra and Aikman Drives - Intersection Upgrade

2,500 3,500 0 0 1,800 3,500 250 1,236 1,186 3,140 3,500 3,140

Sub-Total 2,500 3,500 0 0 1,800 3,500 250 1,236 1,186 3,140 3,500 3,140

ACT NoWasteExtension of the Mugga Lane Resource Management Centre Landfill Cell

4,400 4,400 0 0 1,500 259 0 26 114 205 259 205

Mugga Lane Resource Management Centre – Future Options (Feasibility)

1,750 1,750 0 0 250 250 4 0 6 174 250 174

Sub-Total 6,150 6,150 0 0 1,750 509 4 26 120 379 509 379

Canberra ConnectGungahlin Canberra Connect Shopfront (Feasibility) 100 59 0 0 100 59 0 0 0 59 59 59

Sub-Total 100 59 0 0 100 59 0 0 0 59 59 59

PropertyConservation Management Plans for Heritage Buildings (Feasibility)

800 800 0 0 400 400 0 8 84 93 400 93

Remediation of Fuel Storage Facilities 1,000 1,000 0 0 500 500 108 23 40 204 500 204Sub-Total 1,800 1,800 0 0 900 900 108 31 124 297 900 297

2010-11 Capital Upgrades ProgramPavement Rehabilitation – Selected Failed Pavement Sections of Northbound Lanes of Northbourne Avenue

1,250 1,252 0 0 1,250 1,252 0 0 0 1,252 1,252 1,252

Road Barrier Improvements – Upgrading Selected High Priority Barriers and Bridge Railings at various locations along Belconnen Way and Hindmarsh Drive

164 165 0 0 164 165 0 0 0 165 165 165

Bridge Safety Fencing – Continue Implementation of Screens on Pedestrian and Selected Vehicle Bridges over Arterial Roads

615 615 0 0 615 615 0 303 183 615 615 615

Bridge Strengthening – Two Bridges in Mitchell and Two on Ginninderra Drive

538 538 0 0 538 538 24 248 205 538 538 538

Infill Lighting on Major Arterial Roads (Isabella Drive/Clive Steele Avenue Roundabout and Ginninderra Drive)

215 216 0 0 215 216 23 0 0 216 216 216

Page 52: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

3

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Road Safety Improvements Linked with the Road Safety Action Plan and Traffic Light Asset Management Plan – Work will take place at the Intersection of Hindmarsh and Melrose Drives

272 272 0 0 272 272 69 0 202 272 272 272

Traffic Light Upgrades – Corner of Hindmarsh and Melrose Drives

106 107 0 0 106 107 4 0 0 107 107 107

Design of Road Safety Measures in line with the New Road Safety Strategy and the Vision Zero Philosophy at various locations across the ACT Road Network

250 250 0 0 250 250 2 197 21 250 250 250

Stormwater Augmentation Program – Stormwater Improvements in Chapman and other Sites flooded during the December 2006 and February 2007 Major Storms

3,010 3,010 0 0 3,010 3,010 766 657 692 3,005 3,010 3,005

Stormwater Improvement Program – Upgrade Works at Sites selected from previous Studies in Duffy, Forrest and Chapman

451 451 0 0 451 451 182 5 0 451 451 451

Upgrade to Stormwater Infrastructure at Lake Ginninderra Foreshore

655 655 0 0 655 655 342 94 0 655 655 655

Footpath Improvements – Construction of High Priority Footpaths in Yarralumla, Narrabundah, Evatt, Curtin, Mawson, Lyneham, Hawker, Mitchell, and various Other Suburbs

379 379 0 0 379 379 96 156 0 379 379 379

Infill Lighting in Neighbourhood Developments, including Pathway Lighting in Macquarie and Upgrade of various Pedestrian Crossings in Lyneham

210 211 0 0 210 211 24 33 18 211 211 211

Installation of Energy Efficient Lighting in Kambah, Monash, Wanniassa, Rivett and Narrabundah to Reduce the Power Usage of the Street Light Network

513 513 0 0 513 513 -1 0 1 504 513 504

Replacement of Old Street Light Cables – Various Inner North and South Locations

379 379 0 0 379 379 67 62 15 379 379 379

Traffic Management Improvement at various Schools (Monash, North Ainslie and Turner Primary and Preschools, Campbell High School, St Thomas Mores Primary School, Majura and Forrest Primary Schools and the Blue Gum Community School)

210 210 0 0 210 210 70 57 0 210 210 210

Residential Street Improvements at various locations and investigation of Traffic Management Needs on Streeton Drive in Weston, Copland Drive in Belconnen and Sternberg Crescent in Wanniassa

159 159 0 0 159 159 38 10 94 159 159 159

Landscape Upgrade Works across Canberra, including Barbecues, Park and Street Furniture in Open Spaces and Shopping Centres, Shrub Beds, Bollards and Soil Stabilisation Works in various locations across Canberra including Belconnen, Weston, Woden and Tuggeranong

200 200 0 0 200 200 25 9 121 199 200 199

Landscape Upgrade Works at Oaks Estate including a Covered Barbeque Table, Barbeque and Playground Upgrade

100 100 0 0 100 100 0 17 22 39 100 39

Toilet Refurbishments at Molonglo Reach and Acton District Parks and the Hughes and Chisholm Shopping Centres

750 750 0 0 750 322 4 8 225 310 322 310

Page 53: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

4

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Playground Safety Program – Upgrade of Open Space Playground Assets in various Suburbs, including Gowrie, Weston, Chapman, Kaleen, Macarthur, Greenway, Florey, Belconnen and Chifley

1,228 1,128 0 0 1,228 1,018 381 258 119 863 1,018 863

Foreshore Upgrades from Sullivan’s Creek Bridge to the National Museum of Australia and from Dunrossil Drive to the English Garden in Weston Park

200 200 0 0 200 200 4 38 139 200 200 200

Landscaping Works within the Arboretum at the Former CIT School of Horticulture Site in Weston

50 50 0 0 50 50 1 0 38 42 50 42

Canberra Nara Peace Park – Naming and Wall Signage

28 29 0 0 28 29 0 0 0 29 29 29

Mulligans Flat Dam Restoration 100 200 0 0 100 200 0 0 0 0 200 0Tree Replacement Program – At various locations in the Inner North and South Regions

88 88 0 0 88 88 13 5 23 77 88 77

Mulligan’s Flat Restoration and Interpretation 150 150 0 0 150 150 12 8 0 22 150 22Facility Improvement Program – Upgrades to Ageing Infrastructure at Dickson Water Park, Manuka Pool and Kaleen Enclosed Oval

1,599 1,604 0 0 1,599 1,604 0 0 0 1,604 1,604 1,604

Territory Records Office – Installation of New Industrial De-humidifiers

20 20 0 0 20 20 0 0 0 20 20 20

Replacement of Shopfront and Contact Centre Equipment

25 25 0 0 25 25 0 15 0 15 25 15

OH&S Upgrades – Various Contact Centres and Shopfronts

30 30 0 0 30 30 1 10 0 30 30 30

Bus Stop Disability Improvements – Upgrade of Selected Bus Stops to meet Disability Standards, including provision of seating where appropriate. Works will be undertaken on Bus Routes in Gordon, Kambah, Greenway, Flynn, Charnwood, Scullin, Florey, Latham, and Fraser

379 381 0 0 379 381 128 55 55 381 381 381

West Belconnen Resource Management Centre – Decommissioning Program to achieve Sustainable Environmental and Hydrological Outcomes and Minimise Ongoing Costs

499 501 0 0 499 501 -40 80 40 501 501 501

Upgrades to Existing Recycling Drop Off-Centres in Belconnen Town Centre, West Belconnen, Mitchell, Phillip, Tuggeranong and Mugga Lane

150 150 0 0 150 150 102 48 0 150 150 150

Replacement of Ticket Machines on Buses 180 183 0 0 180 183 0 0 0 183 183 183Driver Seats – Upgrade and Replacement in Line with OH&S Requirements

150 150 0 0 150 150 1 0 31 150 150 150

Bus Engine Overhauls – Additional Engine Rebuilds 461 461 0 0 461 461 0 0 0 461 461 461

Canberra Stadium – Upgrade and Replacement of Infrastructure containing Asbestos

300 301 0 0 300 301 60 0 0 301 301 301

Wanniassa Business Park - Upgrade Works and Energy Efficiency Initiatives

158 158 0 0 158 158 0 0 42 70 158 70

Mitchell Depot - Sewerage Sleeving 200 200 0 0 200 200 0 0 43 43 200 43TAMS Visitors Centres - Condition Audit Upgrade Works and Studies

150 150 0 0 150 150 0 2 20 150 150 150

Mitchell Depot (Building 3) - Installation of Lift 400 400 0 0 400 400 0 0 0 0 400 0Mount Rogers Community Centre - Skylights and Audit Works

200 200 0 0 200 200 36 13 22 200 200 200

Magistrates Court - Condition Audit Upgrade Works 180 180 0 0 180 180 0 0 27 46 180 46

Dame Pattie Menzies House - Condition Audit Upgrade Works

250 100 0 0 250 100 17 16 39 72 100 72

Page 54: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

5

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Scollay St Offices - Condition Audit Upgrade Works 140 140 0 0 140 140 0 0 0 0 140 0

Phillip Business Park - Building Upgrades and Refurbishment

100 100 0 0 100 100 9 2 3 70 100 70

Smart Meter Installation and associated Electrical Works at Dickson Motor Vehicle Registry, 1 Moore Street Civic and North Building Civic

185 185 0 0 185 185 0 0 100 125 185 125

Fairfax Centre O'Connor - Demolition and Site Remediation

200 200 0 0 200 200 11 0 114 200 200 200

Upgrades to Hotel Kurrajong 125 125 0 0 125 125 0 0 73 115 125 115North Building HVAC Works 0 150 0 0 0 150 0 10 21 31 150 31Fire Services Upgrades 0 191 0 0 0 191 0 0 191 191 191 191

Sub-Total 18,351 18,562 0 0 18,351 18,024 2,471 2,416 2,940 16,258 18,024 16,258

TOTAL NEW CAPITAL WORKS PROGRAM 112,606 115,784 0 0 35,516 36,604 4,644 5,339 8,280 33,250 36,604 33,250

WORKS IN PROGRESSRoads ACT

Tharwa Bridge Foundation Works - Roads to Recovery Program

6,100 6,100 5,979 5,979 0 121 0 0 0 12 6,100 5,991

Flemington Road Bus Lanes - Roads to Recovery 2,900 3,665 1,916 1,566 400 1,749 -27 0 0 1,722 3,665 3,638Barry Drive Bus Lanes - Roads to Recovery Progam 4,500 4,500 4,142 3,291 0 358 0 0 0 358 4,500 4,500

Kings Highway Upgrade 20,000 10,500 1,714 1,658 7,000 2,774 560 2,051 -5 3,408 4,488 5,122Majura Ave/Phillip Av Traffic Lights 1,000 1,000 0 0 0 0 0 0 0 0 0 0Majura & Sutton Rd Pavement Rehabilitation 2,000 2,000 0 0 0 0 0 0 0 0 0 0West Belconnen Intersection Improvements 1,500 1,500 0 0 0 0 0 0 0 0 0 0Hume - Lanyon Drive Upgrade - Stage 2 11,000 11,000 5,591 7,575 3,200 3,867 1,373 276 509 5,291 9,458 10,882Cycling, Signage, Footpaths 9,200 9,200 3,078 3,035 2,100 1,922 265 577 412 2,414 5,000 5,492Gungahlin College Precinct - Offsite Works 8,530 8,530 2,340 2,314 5,797 6,190 38 -6 0 6,190 8,530 8,530Upgrade of Airport Roads - Majura Parkway 9,500 9,500 750 156 5,000 519 0 0 -10 -683 1,269 67Majura Road Pavement Improvements 2,000 2,000 2,000 2,000 0 0 0 0 0 2,000 2,000Monaro Hwy Duplication (Canberra Ave to Newcastle St)

18,500 18,500 3,000 3,000 5,000 5,663 1,288 2,943 2,087 9,291 8,663 12,291

Restoration of Tharwa Bridge 14,700 18,935 10,648 8,363 3,000 4,052 719 323 753 5,598 14,700 16,246Gungahlin Drive Extension - Stage 2 85,500 81,700 24,187 24,165 20,000 35,075 2,029 4,515 6,085 36,426 59,262 60,613Upgrade of Tharwa Drive - Stage 1 11,000 11,000 9,090 9,090 1,991 1,910 260 270 27 1,889 11,000 10,979North-South Arterial Road for Molonglo Suburbs 11,000 34,500 2,913 2,882 26,000 15,325 2,002 3 38 16,368 18,238 19,281North Weston Pond and Bridge 12,000 20,000 4,410 4,403 15,000 15,590 6 2,179 3,612 17,482 20,000 21,892Flemington Road Duplication 20,000 20,000 16,873 16,873 1,393 3,127 0 0 0 3,108 20,000 19,981Belconnen Town Centre - Cohen Street Extension and Replacement of Bus Interchange

16,500 23,205 16,588 16,581 5,962 6,617 0 0 0 6,607 23,205 23,195

Community Paths Program - Jerrabomberra Wetlands and Nature Reserve

900 900 837 837 0 63 0 0 0 1 900 838

Sub-Total 268,330 298,235 116,056 113,768 101,843 104,922 8,513 13,131 13,508 115,482 220,978 231,538

Page 55: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

6

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Transport Regulation and PlanningPark 'n' Ride and Bike 'n' Ride Facilities in Erindale and Mitchell

120 120 93 120 0 27 0 0 0 27 120 120

Sub-Total 1,000 120 93 120 0 27 0 0 0 27 120 120

Parks, Conservation and LandCare for Nature Reserves 950 950 204 142 375 371 185 78 94 370 575 574Covered Barbeques 100 100 92 2 0 8 0 0 0 7 100 99New Dog Park 250 250 230 99 0 20 0 0 19 19 250 249Mulligans Flat Signage and Paths 100 101 63 25 0 38 0 0 0 38 101 101Shopping Centre Upgrade Program - Red Hill and Lyons

8,000 8,000 0 0 1,400 1,400 59 0 15 975 1,400 975

Town and District Park Upgrades 6,000 6,000 946 880 1,361 1,008 25 10 248 443 1,954 1,389Drought Proofing Parks and Open Spaces 2,900 2,900 2,454 2,326 0 446 0 0 0 329 2,900 2,783Establishment of Regional Community Facilities and Neighbourhood Halls

2,000 2,404 2,256 1,435 0 148 0 0 0 148 2,404 2,404

Molonglo Corridor Tree Planting 400 400 63 63 0 337 0 0 161 302 400 365Upgrade of Bunda Street Paving 3,650 3,810 683 689 1,419 3,127 -445 396 72 2,932 3,810 3,615Lake Ginninderra Foreshore Stage 2 (Emu Inlet Upgrade)

3,200 6,095 881 672 2,077 865 3 277 334 1,082 1,746 1,963

Establishment of New Nature Reserves 948 948 664 649 271 284 8 90 47 246 948 910City West Infrastructure Stage 2 - Childers Street Precinct

3,000 3,000 2,595 2,578 395 405 15 70 4 242 3,000 2,837

The Sanctuary at Tidbinbilla - Stage 2 and Birrigai Outdoor School Development

2,200 2,200 451 444 1,730 253 10 14 14 76 704 527

Glebe Park Pavement Replacement 1,600 1,600 841 516 190 759 0 16 61 702 1,600 1,543Sub-Total 35,298 38,758 12,423 10,520 9,218 9,469 -140 951 1,069 7,911 21,892 20,334

ACT Planning and Land AuthorityBruce - Braybrooke Street Extension 4,550 4,550 3,835 3,817 0 715 0 0 0 692 4,550 4,527Coombs and Wright - Water Supply 2,000 1,400 466 458 400 934 0 55 5 859 1,400 1,325Forde - Mulligans Flat Road Extension and Water Quality Control Pond

13,500 13,500 3,579 2,991 6,000 9,921 6 -710 944 8,584 13,500 12,163

Bonner - Western Distributor Road and Sewer 11,000 9,000 4,505 3,750 3,500 3,920 5 487 -1 3,842 8,425 8,347Lawson South - Road Intersections 7,000 9,300 3,056 2,718 4,972 6,244 230 474 124 6,138 9,300 9,194Woden Town Centre - Wilbow and Easty Streets Infrastructure

3,500 3,502 2,961 2,961 0 541 0 0 0 541 3,502 3,502

Forde - Access Road and Trunk Sewer 1,700 1,630 1,501 1,501 121 129 0 0 0 129 1,630 1,630Sub-Total 43,250 42,882 19,903 18,196 14,993 22,404 241 306 1,072 20,785 42,307 40,688

Sports and RecreationThrosby District Playing Fields and Netball Centre 600 600 521 521 0 79 32 0 -2 79 600 600

Sub-Total 600 600 521 521 0 79 32 0 -2 79 600 600

Page 56: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

7

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

ACT No WasteMaster Plan for West Belconnen Landfill 120 120 80 74 0 40 6 0 7 17 120 97Remediation of West Belconnen Land Fill Borrow Pit 2,783 2,783 286 268 1,395 346 138 128 250 837 632 1,123

West Belconnen Landfill Sullage Pit Remediation 800 800 385 294 315 270 1 11 100 221 655 606Master Plan for Mugga Lane Resource Management Plan

120 120 119 13 0 1 0 0 0 0 120 119

New Landfill for the ACT 850 850 133 450 327 502 0 40 12 65 635 198Sub-Total 4,673 4,673 1,003 1,099 2,037 1,159 145 179 369 1,140 2,162 2,143

Local Initiatives Package/Pre-Election Budget UpdateBill Poster Silos to City and District Shopping Centres

400 400 345 282 0 55 0 0 0 55 400 400

Road Safety Message Signs 400 401 324 186 0 77 0 0 0 77 401 401Tuggeranong Town Park Stage 200 200 128 101 0 72 0 0 0 61 200 189

Sub-Total 1,000 1,001 797 569 0 204 0 0 0 193 1,001 990

Prior Year Capital UpgradesHeritage 50 52 47 50 0 5 0 0 0 5 52 52Canberra Stadium - Upgrade Handrails to Comply with New Building Codes

75 75 73 73 0 2 0 0 0 2 75 75

Urban Landscape and Built Asset Improvements 2,115 2,115 1,810 1,394 200 305 0 0 0 304 2,115 2,114Street and Park Trees Removal and Plantings 330 330 308 308 0 22 11 8 0 22 330 330Shopping Centre Improvements 3,250 3,250 2,701 2,245 79 549 29 -3 54 548 3,250 3,249Parks and Reserves - Improvements to Playgrounds, Recreational Amenities and Tracks

2,450 2,451 2,449 1,913 100 2 0 0 0 2 2,451 2,451

Urban Open Space 1,343 1,343 1,184 1,185 0 159 15 20 0 157 1,343 1,341Local Shopping Precincts Upgrades 1,370 1,370 1,292 1,156 0 78 1 -6 0 76 1,370 1,368City Centre Infrastructure Upgrades 330 331 290 250 0 41 0 0 0 41 331 331Urban Open Space - Upgrades 1,557 1,557 1,065 1,000 92 492 17 129 0 454 1,557 1,519Playground Safety Program - Upgrade of Open Space Playground Assets to Meet Current Australian Standards

910 914 601 174 0 313 1 103 0 313 914 914

Tree Replacement Program - Locations in the Inner North and Inner South Regions

150 152 67 61 55 85 0 0 0 85 152 152

Toilet Refurbishment 516 100 86 2 0 14 0 0 0 14 100 100Landscape Upgrade Works Across Canberra, including Barbecues, Park and Street Furniture in Open Space and Shopping Centres, Shrub Beds and Bollards

210 210 209 57 0 1 24 0 0 1 210 210

City Central Infrastructure Replacement, including Paving, Lighting and Street Furniture

1,000 488 240 232 51 248 0 0 0 248 488 488

Construction Projects - Upgrade of Lyons Local Shopping Centre

900 300 220 140 36 80 0 0 5 72 300 292

Facilities Improvements - Provides for Upgrades to Aging Infrastructure, Irrigation Systems, Pavilions and Toilets at Pools and Ovals/District Playing Fields

1,560 1,560 1,317 913 0 243 0 0 0 243 1,560 1,560

CCTV at Bus Interchanges - Continue Upgrade and Implementation Program

850 790 635 635 150 155 5 4 4 155 790 790

Radio System Upgrade 300 398 0 0 300 398 0 152 138 350 398 350Sub-Total 19,266 17,786 14,594 11,788 1,063 3,192 103 407 201 3,092 17,786 17,686

Page 57: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

8

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

TERRITORY AND MUNICIPAL SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

NurseryRestoration of Hobday's Cottage and English Gardens

200 273 194 194 0 79 0 0 0 79 273 273

Sub-Total 200 273 194 194 0 79 0 0 0 79 273 273

PropertyCivic Health Centre, Moore St - Carpet Replacement 285 285 103 108 0 182 10 27 66 182 285 285Climate Change Strategies - Installation of Solar Hot Water System (Dickson Motor Vehicle Registry), Water Collection and Reuse Systems (Fyshwick Depot) and Waterless Urinals at Government Owned Offices

600 600 134 93 0 466 0 0 14 370 600 504

Refurbishment of Albert Hall 2,723 3,223 1,633 1,709 400 1,590 511 7 163 1,223 3,223 2,856Upgrade of Callam Offices 811 811 2 2 650 809 0 0 54 130 811 132

Sub-Total 4,419 4,919 1,872 1,912 1,050 3,047 521 34 297 1,905 4,919 3,777

Total Works in Progress 378,036 409,247 167,456 158,687 130,204 144,582 9,415 15,008 16,514 150,693 312,038 318,149

TOTAL CAPITAL WORKS PROGRAM 490,642 525,031 167,456 158,687 165,720 181,186 14,059 20,347 24,794 183,943 348,642 351,399

Page 58: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW WORKS

Data Management Scoping Study – Current and Future Data Requirements (Feasibility) 250 250 0 0 250 250 0 0 41 250 250 250Sub-Total 250 250 0 0 250 250 0 0 41 250 250 250

Total New Works 250 250 0 0 250 250 0 0 41 250 250 250

WORKS IN PROGRESS

Record Services Mitchell Accommodation - Refurbishment 3,237 3,114 3,009 3,009 105 105 0 0 0 79 3,114 3,088Sub-Total 3,237 3,114 3,009 3,009 105 105 0 0 0 79 3,114 3,088

Total Works in Progress 3,237 3,114 3,009 3,009 105 105 0 0 0 79 3,114 3,088

TOTAL CAPITAL WORKS PROGRAM 3,487 3,364 3,009 3,009 355 355 0 0 41 329 3,364 3,338

SHARED SERVICES CENTRE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 59: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Financing

($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Official Opening 2013 – National Arboretum Canberra 22,620 22,620 0 0 7,710 7,710 1,171 1,486 2,996 7,370 7,710 7,370Transport for Canberra – Street Lighting in the City 2,000 2,000 0 0 1,000 1,000 129 70 2 214 1,000 214City West Infrastructure Stage 3 1,900 1,900 0 0 1,900 1,900 2 1 1 18 1,900 18City Action Plan Stage 1 – Edinburgh Avenue Improvements 2,500 2,500 0 0 200 200 2 1 2 19 200 19North Weston – Road Intersection Reconstruction 14,000 14,000 0 0 5,000 3,000 0 0 0 0 3,000 0Coombs – Water Quality Control Ponds 17,000 17,000 0 0 7,000 6,600 0 0 4,583 5,329 6,600 5,329Fyshwick – Intersection Upgrades – Gladstone Street, Section 26 4,000 4,000 0 0 3,500 1,300 0 0 784 784 1,300 784Barton – Intersection Upgrades – Darling Street, Section 22 1,000 1,000 0 0 1,000 650 0 0 0 0 650 0Forde – Horse Park and Gundaroo Drives Intersection Upgrade 4,000 4,000 0 0 4,000 2,850 0 0 0 0 2,850 0Watson – Stormwater Upgrade – Aspinall Street Block 2, Section 95 2,870 2,870 0 0 2,870 2,350 0 0 125 125 2,350 125Floriade – Upgrade to Commonwealth Park (Design) 300 300 0 0 300 300 0 61 0 296 300 296

Sports and RecreationGungahlin Leisure Centre (Design) 1,460 1,460 0 0 1,460 0 0 0 0 0 0 0Lyneham Precinct Redevelopment Stage 3 4,200 4,200 0 0 2,100 7 0 0 0 7 7 7Throsby Multisport Complex (Design) 500 500 0 0 500 90 0 0 0 0 90 0Gungahlin Wellbeing Precinct - Infratructure Works 6,500 6,500 0 0 0 0 0 0 0 0 0 0

Territory Venues and EventsManuka Oval Facilities Upgrades 407 407 0 0 407 407 11 60 267 407 407 407

Sub-Total 85,257 85,257 0 0 38,947 28,364 1,316 1,680 8,760 14,568 28,364 14,5682010-11 CAPITAL UPGRADES PROGRAM

City Central Infrastructure Replacement – including Paving, Lighting, Bubblers and Street Furniture in various locations throughout Canberra’s Central Business District such as City Walk and Mort Street

200 200 0 0 200 200 1 0 48 103 200 103

Water Demand Management Program – Irrigation System 1,000 1,000 0 0 1,000 1,000 195 -18 0 881 1,000 881Canberra Stadium – Upgrade of Spectator Lighting, Control System and Wiring

100 101 0 0 100 101 1 8 0 101 101 101

Canberra Stadium – Replacement of Analogue Televisions (to digital) in all Corporate and Public Areas

650 650 0 0 650 650 385 27 0 650 650 650

Sub-Total 1,950 1,951 0 0 1,950 1,951 582 17 48 1,735 1,951 1,735

Total New Works 87,207 87,208 0 0 40,897 30,315 1,897 1,697 8,808 16,303 30,315 16,303

ECONOMIC DEVELOPMENT DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 60: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Financing

($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

ECONOMIC DEVELOPMENT DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

WORKS IN PROGRESS

Temporary Surface Car Park - Southern Loop Commonwealth Avenue 1,000 900 0 0 900 0 0 0 0 0 0 0

Canberra CBD Upgrade Program 12,000 12,000 298 233 1,500 1,702 20 13 134 249 2,000 547Harrison - Well Station Drive Extension to Horse Park Drive 7,000 7,500 117 105 7,000 7,383 0 0 1,951 2,526 7,500 2,643Mitchell - Sandford Street Extension to the Federal Highway 9,000 14,000 505 502 7,000 395 0 0 0 200 900 705Casey - Clarrie Hermes Drive Extension to the Barton Highway 21,000 21,000 280 266 8,300 7,045 18 12 18 1,830 7,325 2,110Civic Revitalisation - Development of Civic Master Plan (Feasibility) 200 200 22 200 0 178 0 0 0 0 200 22Fitters Workshop Re-use - Design and Documentation 200 200 106 9 0 94 0 0 0 57 200 163Upgrade and Expand the Woden Gymnastics Club 550 550 162 158 300 388 0 0 0 388 550 550Mitchell Depot - Improved Disability Access - Installation of Lift in Building 3 215 24 24 215 0 0 0 0 0 0 24 24

National Arboretum Canberra 18,150 18,150 11,981 9,272 5,960 5,169 0 0 0 3,413 17,150 15,394Arts Organisation Relocation 600 600 571 571 0 29 0 0 0 29 600 600Government Office Accommodation and Relocation Fitout 5,270 7,170 26 270 6,900 444 0 0 0 0 470 26Government Office Accommodation Building Project 2,020 2,620 2,236 2,380 160 304 0 0 80 384 2,540 2,620

Sports and Recreation

Grant for Development of a New Basketball Centre and Player Amenities3,000 3,000 0 0 500 50 0 0 0 0 50 0

Gungahlin Enclosed Oval (Sports Complex) 6,000 6,000 36 33 1,000 811 0 12 216 238 847 274Gungahlin Leisure Centre 1,000 1,000 0 0 900 28 0 0 0 1 28 1Improvements to Griffith Oval 1,050 1,050 0 0 50 50 0 0 0 0 50 0Lyneham Precinct - Regional Tennis and Sports Centre - Stage 2 4,500 4,500 17 0 0 0 0 0 0 0 17 17Lyneham Precinct - Regional Tennis and Sports Centre - Stage 2 - GPO Funded

4,000 4,000 250 250 3,750 0 0 0 4 4 250 254

"Where Will we Play" Outdoor Facilities Water Reduction Strategies 8,000 16,000 1,456 1,448 3,507 1,070 23 0 0 65 2,526 1,521Enclosed Oval within Crinigan Circle, Gungahlin 400 400 179 179 0 121 30 0 0 60 300 239Harrison - District Playing Fields 4,250 5,250 4,883 5,092 400 367 0 0 100 310 5,250 5,193Lyneham Sports Precinct Development - Stage 1 - GPO & CI 8,600 8,600 2,743 2,743 5,974 4,357 115 0 0 3,305 7,100 6,048

Territory Venues and EventsMotorsport Funding - Capital 500 500 197 123 303 103 9 0 12 103 300 300Motorsport Funding - Investment Fund - GPO 1,500 1,500 0 0 500 500 21 21 21 306 500 306Stromlo Forest Park - Landscape and Amenity Planning 230 229 217 202 20 12 2 0 8 10 229 227

Sub-Total 120,235 136,943 26,306 24,251 54,924 30,600 238 58 2,544 13,478 56,906 39,784

Total Works in Progress 120,235 136,943 26,306 24,251 54,924 30,600 238 58 2,544 13,478 56,906 39,784

TOTAL CAPITAL WORKS PROGRAM 207,442 224,151 26,306 24,251 95,821 60,915 2,135 1,755 11,352 29,781 87,221 56,087

Page 61: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Financing

($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

ACT Government Office Project - Procurement Planning and Documentation 3,100 1,740 0 0 3,100 1,740 0 0 1,301 1,301 1,740 1,301Sub-Total 3,100 1,740 0 0 3,100 1,740 0 0 1,301 1,301 1,740 1,301

Total New Works 3,100 1,740 0 0 3,100 1,740 0 0 1,301 1,301 1,740 1,301

WORKS IN PROGRESS

Whole of Government - Capital Improvements Program 6,000 5,919 4,226 4,226 431 1,693 0 800 96 1,618 5,919 5,844Whole of Government - Asset Management and Capital Delivery Planning 5,000 5,548 959 959 2,639 1,639 0 4 8 96 2,598 1,055Government Office Building - Project Advice 2,300 2,111 4 25 1,250 259 0 0 -3 97 263 101

13,300 13,578 5,189 5,210 4,320 3,591 0 804 101 1,811 8,780 7,000

Total Works in Progress 13,300 13,578 5,189 5,210 4,320 3,591 0 804 101 1,811 8,780 7,000

TOTAL CAPITAL WORKS PROGRAM 16,400 15,318 5,189 5,210 7,420 5,331 0 804 1,402 3,112 10,520 8,301

FOR THE PERIOD ENDED 30/06/2011TREASURY DIRECTORATE 2010-11 CAPITAL WORKS PROGRAM

Page 62: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project

Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Clinical Services Redevelopment – Phase 2 15,000 9,800 0 0 15,000 400 0 0 293 295 400 295Tuggeranong Health Centre – Stage 2 14,000 14,000 0 0 0 0 0 0 4 4 0 4CADP Change Management and Communication Support 4,117 4,117 0 0 1,765 1,765 1 42 180 491 1,765 491National Health Reform 15,098 15,098 0 0 7,839 1,430 598 611 763 1,971 1,430 1,971Integrated Capital Region Cancer Centre – Phase 1 27,900 27,900 0 0 3,500 1,500 17 11 568 1,031 1,500 1,031

Sub-Total 76,115 70,915 0 0 28,104 5,095 616 664 1,807 3,793 5,095 3,793

2010-11 Capital Upgrades Program

Building Upgrades 556 556 0 0 556 556 30 31 195 556 556 556Installation of Energy Savings Equipment and Sustainability Upgrades 235 235 0 0 235 235 62 27 54 154 235 154Improvements to OH&S and Fire and Safety Systems 355 355 0 0 355 355 8 32 172 354 355 354Upgrade of Mechanical Systems 540 540 0 0 540 540 190 81 178 540 540 540Augmentation of Patient and Research Facilities 790 790 0 0 790 506 -4 103 -81 90 506 90Workplace Improvements 640 640 0 0 640 540 -1 52 -21 307 540 307Augmentation of Medical Offices 455 455 0 0 455 455 7 61 11 269 455 269Security Upgrades - Calvary 100 100 0 0 100 100 5 -5 0 44 100 44Fire Safety Upgrades - Calvary 300 300 0 0 300 300 6 16 21 84 300 84Residential Accommodation Refurbishment - Calvary 310 310 0 0 310 310 0 0 0 0 310 0

Sub-Total 4,281 4,281 0 0 4,281 3,897 303 397 528 2,399 3,897 2,399

Total New Works 80,396 75,196 0 0 32,385 8,992 920 1,061 2,335 6,191 8,992 6,191

WORKS IN PROGRESS

Capital Asset Development Plan

Enhanced Community Health Centre - Belconnen 51,344 51,344 0 0 6,369 1,400 -2 97 415 1,033 1,400 1,033Walk-in Centre - TCH 2,157 2,157 1,788 1,640 157 369 15 0 -65 304 2,157 2,092Mental Health Young Persons Unit 775 775 158 186 645 28 0 0 0 -37 186 121ACT Health Skills Development Centre 1,300 1,300 0 0 1,300 300 23 69 117 423 300 423Adult Acute Mental Health Inpatient Unit 23,630 23,630 0 3 15,934 10,003 1,431 2,580 1,521 9,186 10,003 9,186Adult Secure Mental Health Inpatient Unit - ON HOLD 11,160 0 0 0 1,000 0 0 0 0 0 0 0Mental Health Assessment Unit 2,010 2,010 1,356 1,244 0 654 0 30 24 243 2,010 1,599Women and Children's Hospital 90,000 107,560 2,061 1,553 25,939 17,939 2,119 1,499 3,341 16,633 20,000 18,694Neurosurgery Operating Theatre 5,500 10,500 8,473 7,394 960 2,027 -375 0 -35 1,993 10,500 10,466Surgical Assessment and Planning Unit 4,100 4,100 2,534 3,595 361 1,566 0 0 21 1,142 4,100 3,676New Gungahlin Health Centre 18,000 18,000 5 7 6,775 702 0 83 164 529 707 534Refurbishment of Existing Health Centre - Tuggeranong Stage 1 5,000 5,000 0 1 3,499 600 0 82 197 526 600 526Provision for Phase 1 CSR 57,000 26,630 9,279 9,006 10,604 7,321 -1,042 409 1,469 9,591 16,600 18,870Provision for Project Definition Planning 63,800 61,090 22,984 22,043 15,681 14,321 2,333 741 1,457 12,313 37,305 35,297Additional Beds 2,400 2,400 2,341 1,890 0 59 37 13 4 59 2,400 2,400Intensive Care Unit - Calvary 9,410 11,410 8,860 11,410 0 2,550 -200 0 0 2,550 11,410 11,410

Sub-Total 347,586 327,906 59,839 59,972 89,224 59,839 4,339 5,603 8,629 56,487 119,678 116,326

HEALTH DIRECTORATE 2010-11 CAPITAL WORKS PROGRAM

FOR THE PERIOD ENDED 30/06/2011

Page 63: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project

Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

HEALTH DIRECTORATE 2010-11 CAPITAL WORKS PROGRAM

FOR THE PERIOD ENDED 30/06/2011

Other Works in Progress Projects

Elective Surgery (Commonwealth Funding) 0 4,680 4,190 3,844 150 490 0 2 0 262 4,680 4,452Adult Acute Mental Health Inpatient Unit - Forward Design 2,290 2,290 1,667 1,680 573 623 0 -5 0 623 2,290 2,290Adult Secure Mental Health Inpatient Unit - Forward Design 1,200 1,200 344 389 827 856 0 0 0 141 1,200 485New Multistorey Car Park TCH 29,000 42,720 12,662 11,514 38,969 30,058 1,734 712 212 27,788 42,720 40,450Aboriginal Torres Strait Islander Residential Alcohol & Other Drug Rehabilitation Facility 0 5,883 621 621 2,583 200 6 -6 3 3 821 624Linear Accelerator Procurement and Replacement 18,700 17,700 14,245 15,187 0 3,080 64 5 365 1,069 17,325 15,314Fire Systems Upgrade (Phase 1) TCH 2,600 2,600 2,206 2,600 0 394 0 40 197 394 2,600 2,600

Sub-Total 53,790 77,073 35,934 35,835 43,102 35,702 1,804 748 776 30,281 71,636 66,215

Prior Years Capital Upgrades

Electrical, Plumbing, Floor Coverings and Air-Conditioning Upgrades (Stage 1) 225 225 45 45 0 180 1 92 0 180 225 225Energy Savings and Sustainability Works 305 305 191 192 0 114 0 51 0 114 305 305Safety Upgrades 325 325 269 213 0 56 2 7 0 55 325 324Refurbishment of Non-Clinical Accommodation at TCH 300 292 138 135 200 154 0 0 13 152 292 290Address Building Condition and Asbestos Audit Requirements 380 380 242 73 0 138 4 0 0 137 380 379TCH Upgrades to Ambulatory Areas, Intensive Care Facilities, Pathology Laboratories and ED 525 533 223 226 340 310 0 70 184 310 533 533Workplace Redesign to Meet Accommodation and OH&S Standards 290 290 96 99 0 194 131 13 40 194 290 290Improved Patient Amenity - Calvary 150 150 115 150 0 35 0 0 0 35 150 150Infrastructure Improvements (Various) - Calvary 230 230 62 230 0 168 0 0 0 168 230 230Occupational Health and Safety Upgrades (Various) - Calvary 312 312 69 312 0 243 38 0 0 243 312 312Equipment Loans Scheme Relocation 620 620 25 25 600 595 0 0 0 595 620 620TCH Discharge Lounge Relocation 150 150 0 0 150 100 0 2 2 4 100 4

Sub-Total 3,812 3,812 1,475 1,700 1,290 2,287 176 236 238 2,186 3,762 3,661

Total Works in Progress 405,188 408,791 97,248 97,507 133,616 97,828 6,319 6,587 9,644 88,954 195,076 186,202

TOTAL CAPITAL WORKS 485,584 483,987 97,248 97,507 166,001 106,820 7,239 7,648 11,979 95,145 204,068 192,393

Page 64: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Tidbinbilla Rural Fire Service Shed 1,644 1,644 0 0 1,644 282 -65 0 216 216 282 216Additional Jury Courtroom 450 450 0 0 450 450 0 0 30 447 450 447

Sub-Total 2,094 2,094 0 0 2,094 732 -65 0 246 663 732 663

2010-11 Capital Upgrades Program

Departmental Projects 723 723 0 0 723 723 122 78 267 656 723 656Emergency Services Agency Projects 278 278 0 0 278 278 21 0 159 277 278 277ACT Policing Facilities 222 222 0 0 222 222 0 0 222 222 222 222

Sub-Total 1,223 1,223 0 0 1,223 1,223 143 78 648 1,155 1,223 1,155

Total New Works 3,317 3,317 0 0 3,317 1,955 78 78 894 1,818 1,955 1,818

WORKS IN PROGRESS

New Supreme Court - Forward Design 4,000 4,000 0 0 4,000 200 -56 0 -8 30 200 30Emergency Services Agency - Jerrabomberra and Rivers Sheds 2,270 2,270 10 0 1,785 2,260 314 43 889 1,706 2,270 1,716Departmental Projects 706 706 480 424 200 226 0 0 208 211 706 691Emergency Services Agency Projects (ESA CUP 2009-10) 271 271 181 157 0 90 0 0 0 90 271 271Alexander Maconochie Centre - Chapel and Quiet Place 513 96 96 96 407 0 0 0 0 0 96 96New Forensic Medical Centre 4,770 5,570 339 276 5,247 4,231 989 608 1,875 4,146 4,570 4,485Emergency Services Agency - Stations Relocation Design 2,184 529 409 268 0 120 0 0 0 120 529 529Alexander Maconochie Centre - Transitional Costs (STRC Reconfiguration) 900 900 876 900 0 24 0 0 24 24 900 900Emergency Services Agency - Station Upgrades 831 831 709 718 52 122 43 0 29 122 831 831Upgrade Court Security and Facilities 1,904 1,904 1,519 1,227 0 385 0 0 303 342 1,904 1,861Disability Access and Accommodation Improvements 550 200 91 87 0 109 0 0 0 0 200 91Emergency Services Agency - New Headquarters 18,429 29,074 9,746 9,541 13,711 18,978 1,676 198 4,612 17,138 28,724 26,884Alexander Maconochie Centre 128,700 131,330 128,975 128,358 2,500 305 0 54 18 242 129,280 129,217New Belconnen Police Station - Construction 16,988 22,350 341 125 14,226 8,429 0 865 5,122 10,804 8,770 11,145

Sub-Total 183,016 200,031 143,771 142,177 42,128 35,480 2,967 1,768 13,073 34,975 179,251 178,746

Total Works in Progress 183,016 200,031 143,771 142,177 42,128 35,480 2,967 1,768 13,073 34,975 179,251 178,746

TOTAL CAPITAL WORKS PROGRAM 186,333 203,348 143,771 142,177 45,445 37,435 3,045 1,846 13,966 36,793 181,206 180,564

JUSTICE AND COMMUNITY SAFETY DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 65: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Financing

($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Lawson South – Relocation of Power Line (Design) 300 300 0 0 300 150 89 54 7 150 150 150Lawson South – Water Quality Control Pond (Design) 300 0 0 0 200 0 0 0 0 0 0 0Molonglo – Future Stormwater Management (Feasibility) 450 450 0 0 450 250 0 164 3 250 250 250Molonglo – East-West Arterial Road and Extension of John Gorton Drive to Molonglo River (Feasibility) 450 450 0 0

25020 0 0 0 14 20 14

Gungahlin Town Centre Roads (Feasibility) 300 300 0 0 300 300 0 91 89 180 300 180Scrivener Dam Upgrade (Feasibility) 350 350 0 0 350 350 0 58 0 58 350 58Woden Valley Stormwater Retardation Basins (Feasibility) 250 250 0 0 150 100 0 27 3 100 100 100Symonston – Arterial Road (Feasibility) 300 300 0 0 200 100 0 18 59 102 100 102John Gorton Drive Extension to Molonglo 2 and Group Centre 0 280 0 0 0 280 0 0 27 27 280 27Molonglo 2 Water Supply, Trunk Sewer and Stormwater Infrastructure 0 150 0 0 0 150 0 0 25 25 150 25North Weston/Molonglo Stormwater Harvesting Scheme 5,000 5,000 0 0 1,000 0 0 0 0 0 0 0Gungahlin - The Valley Ponds and Stormwater Harvesting Scheme 6,500 6,500 0 0 1,000 0 0 0 0 0 0 0

Sub-Total 14,200 14,330 0 0 4,200 1,700 89 412 213 906 1,700 906

2010-11 Capital Upgrades Program

Land Release Infrastructure Improvements - Roads, Paving, Fencing, Stormwater, Sewer, Water Supply and Landscaping

334 334 0 0 334 334 0 22 168 319 334 319

Robertson House, Oaks Estate Restoration and Interpretation 165 165 0 0 165 165 1 5 20 30 165 30Cargill's Dairy Cottage, Causeway Restoration and Interpretation 150 150 0 0 150 150 11 20 33 68 150 68Tralee Homestead Restoration and Interpretation 165 165 0 0 165 165 2 10 -4 11 165 11Heritage Signage including Aboriginal Campsite at Black Mountain Peninsula, Charnwood Homestead, Cricketers Arms Hotel, Emu Bank Homestead, George Henry Rottenberry’s Farmhouse, Kingston Guest House – Printers Quarters, Rosebud Apiary, Russell Hill Camp and Weetangera Homestead

100 100 0 0 100 100 0 0 24 49 100 49

Ginninderra Blacksmith’s Workshop Improvements 175 175 0 0 175 175 2 5 30 41 175 41Valley Homestead Ruins Upgrades 75 75 0 0 75 75 1 5 15 24 75 24

Sub-Total 1,164 1,164 0 0 1,164 1,164 17 67 286 542 1,164 542

Total New Works 15,364 15,494 0 0 5,364 2,864 106 479 499 1,448 2,864 1,448

WORKS IN PROGRESS

East Lake - Environmental Site Assessment Phase 2 & 3 400 400 323 324 0 77 0 0 18 62 400 385Canberra Integrated Urban Water Program 1,000 1,000 400 400 600 207 0 0 0 207 607 607Future Water Management Options - Molonglo River 500 500 242 242 200 258 0 0 0 258 500 500Urban Development Sequence for Affordable Housing - Molonglo and North Weston 650 650 497 500 150 153 0 0 2 153 650 650Urban Development Sequence for Affordable Housing - Environmental Impact Assessment Molonglo 550 550 399 395 155 91 0 0 15 77 490 476

Urban Development Sequence for Affordable Housing - Concept Plans Gungahlin 450 450 157 153 297 293 28 16 -3 280 450 437East Lake Sustainable Urban Renewal 1,720 1,720 1,207 1,241 360 363 0 78 229 1,570 1,436Dickson Master Plan 110 110 108 110 0 2 0 0 1 2 110 110Kingston Master Plan 200 200 197 200 0 3 0 0 1 3 200 200Horse Park Drive Extension from Amaroo to Moncrieff Group Centre 500 500 450 450 50 50 0 0 50 50 500 500Horse Park Drive Water Quality Control Pond 300 300 205 205 95 95 0 0 95 95 300 300Mirrabei Drive Extension to Horse Park Drive 300 300 205 205 95 95 0 0 95 95 300 300Kenny Water Quality Control Pond 300 300 220 220 80 80 0 0 77 80 300 300Accelerating Replacing Stormwater Drains with Wetlands 13,870 13,870 715 715 13,137 9,452 32 488 0 2,645 10,167 3,360Renewable Energy Technology Showcase - West Belconnen Child and Family Centre 417 417 0 0 0 417 0 24 157 285 417 285Renewable Energy Technology Showcase 583 583 583 583 0 0 0 0 0 0 583 583Heritage Signs 100 100 29 28 0 71 0 0 6 66 100 95Heritage Signage - Acton Precinct 50 50 2 2 0 48 0 0 34 48 50 50Heritage 150 150 123 103 0 27 0 0 0 27 150 150

Sub-Total 22,150 22,150 6,062 6,076 15,219 11,782 60 528 626 4,662 17,844 10,724

Total Works in Progress 22,150 22,150 6,062 6,076 15,219 11,782 60 528 626 4,662 17,844 10,724

TOTAL CAPITAL WORKS PROGRAM 37,514 37,644 6,062 6,076 20,583 14,646 166 1,007 1,125 6,110 20,708 12,172

FOR THE PERIOD ENDED 30/06/2011ENVIRONMENT AND SUSTAINABLE DEVELOPMENT DIRECTORATE 2010-11 CAPITAL WORKS PROGRAM

Page 66: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted

Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Harrison High School – Second Gymnasium Court 2,000 2,000 0 0 0 0 0 0 0 0 0 0Bonner Primary School (Design) 1,800 1,800 0 0 1,000 600 119 266 173 689 600 689Car Parks and Traffic Safety Program 1,250 1,250 0 0 250 250 0 1 71 112 250 112Molonglo Primary School (Design) 1,950 1,950 0 0 950 200 3 5 6 37 200 37Franklin Early Childhood School (Design) 1,400 1,400 0 0 800 600 131 118 8 301 600 301Red Hill Primary School Expansion 5,300 5,300 0 0 4,300 700 195 71 214 754 700 754

Sub-Total 13,700 13,700 0 0 7,300 2,350 448 461 472 1,893 2,350 1,893

2010-11 Capital Upgrades Program

Building Refurbishment and Upgrades 12,565 12,565 0 0 12,565 9,742 1,171 249 2,071 6,349 9,742 6,349Sub-Total 12,565 12,565 0 0 12,565 9,742 1,171 249 2,071 6,349 9,742 6,349

Total New Works 26,265 26,265 0 0 19,865 12,092 1,619 710 2,543 8,242 12,092 8,242WORKS IN PROGRESS

Harrison High School 43,500 43,500 1,875 1,869 28,000 24,125 3,541 5,143 3,781 22,031 26,000 23,906Canberra College (Woden Campus) Performing Arts Theatre 7,600 7,600 120 120 1,600 880 495 0 11 524 1,000 644Public Schools - Water Tanks 2,000 2,375 515 512 800 1,460 119 158 261 1,476 1,975 1,991Environment - Solar Schools 2,000 2,000 53 50 500 747 108 -103 63 298 800 351More Teachers, Lower Class Sizes 6,000 6,000 1,077 1,077 3,840 4,423 23 86 344 3,623 5,500 4,700Trade Training Centres 10,207 10,087 0 0 1,659 0 -4 -4 0 0 0 0National Partnership - Nation Building and Jobs Plan - Building the Education Revolution 143,024 150,523 86,550 82,906 57,812 63,973 959 286 1,327 63,973 150,523 150,523Transportable Classrooms 478 774 757 757 0 17 0 0 17 17 774 774Calwell High School Performing Arts Centre 5,000 5,000 1,715 1,712 3,000 3,285 0 -1,186 10 1,809 5,000 3,524Erindale Leisure Centre Redevelopment 3,000 3,000 2,886 2,886 0 114 3 87 0 99 3,000 2,985Schools Infrastructure Refurbishment 90,000 86,000 78,321 77,516 11,411 7,679 0 -6 -19 7,654 86,000 85,975Gungahlin College 60,700 71,407 36,494 36,479 35,077 34,913 1,035 2,094 1,898 33,377 71,407 69,871Kambah P-10 50,000 54,000 18,551 18,429 23,000 33,249 2,478 3,543 1,131 33,827 51,800 52,378

Sub-Total 423,509 442,266 228,914 224,313 166,699 174,865 8,757 10,098 8,824 168,708 403,779 397,622

Total Works in Progress 423,509 442,266 228,914 224,313 166,699 174,865 8,757 10,098 8,824 168,708 403,779 397,622

TOTAL CAPITAL WORKS PROGRAM 449,774 468,531 228,914 224,313 186,564 186,957 10,376 10,808 11,367 176,950 415,871 405,864

EDUCATION AND TRAINING DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Note: National Partnership - Nation Building and Jobs Plan - Building the Education Revolution - In addition to the Final Expenditure recorded ($150.523 million), the Directorate spent at further $1.625 million on this program of which $1.332 million related to interest and $0.293 million was sourced from cash.

Page 67: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Flynn Childcare Centre 4,000 4,000 0 0 3,000 1,000 0 65 601 699 1,000 699Regional Community Facilities Car Parks and Building Facades 3,162 3,162 0 0 1,939 1,939 0 0 22 1,863 1,939 1,863Replacement of Centre-Based Respite Houses (Feasibility) 250 250 0 0 250 250 0 0 110 162 250 162Expansion of the Baringa Childcare Centre 0 375 0 0 0 375 0 0 298 304 375 304Extension to the Street Theatre (Design) 150 150 0 0 150 120 1 0 -1 2 120 2Watson Arts Centre – Additional Studios and Residence 747 747 0 0 747 287 0 0 0 274 287 274Strathnairn Homestead – Kitchen, Toilet and Veranda Improvements 100 100 0 0 100 100 0 0 0 5 100 5Strathnairn Homestead – Additional Studio Space and Landscaping 100 100 0 0 100 10 0 0 0 0 10 0Kingston Arts Precinct Strategy 150 150 0 0 150 150 0 0 0 145 150 145

Sub-Total 8,659 9,034 0 0 6,436 4,231 1 65 1,030 3,454 4,231 3,454

2010-11 Capital Upgrades Program

Community Facilities 1,235 1,235 0 0 1,235 1,235 46 27 281 1,230 1,235 1,230Youth and Child Care Facilities 833 833 0 0 833 833 96 23 86 791 833 791External Painting at Arts Facilities 118 0 0 0 118 0 0 0 0 0 0 0Electrical Upgrades at Arts Facilities 60 0 0 0 60 0 0 0 0 0 0 0Upgrade of Fire Systems at Arts Facilities 100 0 0 0 100 0 0 0 0 0 0 0Gorman House - Installation of a compliant grease trap 0 20 0 0 0 20 0 0 5 20 20 20Watson Arts Centre - Construction of storm water drainage 0 25 0 0 0 25 0 0 25 25 25 25Ainslie Arts Centre - Critical repairs to hydraulics 0 70 0 0 0 70 57 0 13 70 70 70Asbestos Management at all facilities - Implementation of Management Plans 0 70 0 0 0 70 0 0 70 70 70 70Various Refurbishments and Upgrades 0 162 0 0 0 162 16 -12 108 162 162 162

Sub-Total 2,346 2,415 0 0 2,346 2,415 215 38 588 2,368 2,415 2,368

Total New Works 11,005 11,449 0 0 8,782 6,646 216 103 1,618 5,822 6,646 5,822

WORKS IN PROGRESS

Tuggeranong 55 Plus Club 1,500 1,500 0 0 1,500 1,000 6 0 0 46 1,000 46National Partnership - Indigenous Early Childhood Development - Third Child and Family Centre 4,200 4,230 673 690 3,157 3,557 6 2,939 320 3,268 4,230 3,941National Partnership - Pensioner Transport Concessions 31 31 4 0 0 27 0 0 0 27 31 31Forde Community Centre 352 352 0 0 352 0 0 0 0 0 0 0Establishment of Regional Community Facilities and Neighbourhood Halls 22,611 27,250 22,111 18,243 5,000 5,139 0 0 7 5,139 27,250 27,250Youth Detention Centre - Body Scanner 375 0 0 79 296 0 0 0 0 0 0 0Tuggeranong 55 Plus Club - Forward Design 200 200 137 137 0 63 0 0 0 63 200 200Additional Childcare Places - Forward Design 435 405 312 312 0 93 0 0 0 82 405 394ATSI Cultural Centre 2,025 2,025 1,944 2,025 0 81 54 0 12 78 2,025 2,022Strathnairn Arts Centre - Bronze Foundry Workshop 100 100 0 0 0 100 13 0 0 82 100 82Strathnairn Arts Centre - Landscaping 50 50 0 0 0 50 50 0 0 50 50 50Public Art 2,400 2,349 25 25 2,375 2,324 163 788 653 2,324 2,349 2,349artsACT 271 327 82 82 0 245 72 0 58 245 327 327Watson Arts Centre - Five Studios Forward Design 300 300 112 112 80 188 0 0 0 105 300 217Manuka Arts Centre Landscape Works 300 300 57 57 0 225 0 -38 16 203 282 260Belconnen Arts and Cultural Centre 9,000 8,141 7,829 7,907 0 312 0 -36 30 228 8,141 8,057Public Art Scheme 7,571 7,497 2,930 2,781 3,763 1,266 42 -651 -108 530 4,196 3,460

Sub-Total 51,721 55,057 36,216 32,450 16,523 14,670 406 3,002 988 12,470 50,886 48,686

Total Works in Progress 51,721 55,057 36,216 32,450 16,523 14,670 406 3,002 988 12,470 50,886 48,686

TOTAL CAPITAL WORKS PROGRAM 62,726 66,506 36,216 32,450 25,305 21,316 622 3,105 2,606 18,292 57,532 54,508

COMMUNITY SERVICES DIRECTORATE 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 68: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Homelessness Initiative – A Place to Call Home 2,500 2,500 0 0 1,000 1,000 238 0 0 1,000 1,000 1,000Refurbish Early Morning Drop-in Centre in the City 750 750 0 0 750 750 269 113 230 750 750 750

Total New Works 3,250 3,250 0 0 1,750 1,750 507 113 230 1,750 1,750 1,750

WORKS IN PROGRESS

National Partnership - Nation Building and Jobs Plan - Social Housing 96,323 87,079 50,964 63,256 23,823 36,115 911 0 -1,365 34,750 87,079 85,714National Partnership - Homelessness (A Place to Call Home) 5,000 5,000 2,000 2,000 1,000 1,000 570 238 55 1,000 3,000 3,000National Partnership - Social Housing 6,439 6,439 6,229 6,439 0 210 0 0 0 210 6,439 6,439

Total Works in Progress 107,762 98,518 59,193 71,695 24,823 37,325 1,481 238 -1,310 35,959 96,518 95,152

TOTAL CAPITAL WORKS PROGRAM 111,012 101,768 59,193 71,695 26,573 39,075 1,988 351 -1,080 37,709 98,268 96,902

FOR THE PERIOD ENDED 30/06/2011HOUSING ACT 2010-11 CAPITAL WORKS PROGRAM

Page 69: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

New CIT Learning Centre Tuggeranong (Feasibility Study) 250 250 0 0 250 250 36 39 31 250 250 250Bruce – Refurbishment of Canberra Raiders Training Facility (Design) 65 65 0 0 65 65 0 0 0 65 65 65

Sub-Total 315 315 0 0 315 315 36 39 31 315 315 315

2010-11 Capital Upgrades Program

Health and Safety Improvements 470 470 0 0 470 470 21 0 270 470 470 470Energy Management/Educational Improvements 880 880 0 0 880 880 0 0 0 880 880 880Building Improvements 874 874 0 0 874 874 27 0 126 874 874 874

Sub-Total 2,224 2,224 0 0 2,224 2,224 48 0 396 2,224 2,224 2,224

Total New Works 2,539 2,539 0 0 2,539 2,539 84 39 427 2,539 2,539 2,539

WORKS IN PROGRESS

Electrotechnology Program Relocation 9,943 9,943 2,000 2,000 7,943 7,943 1,216 347 -344 7,943 9,943 9,943Sub-Total 9,943 9,943 2,000 2,000 7,943 7,943 1,216 347 -344 7,943 9,943 9,943

Total Works in Progress 9,943 9,943 2,000 2,000 7,943 7,943 1,216 347 -344 7,943 9,943 9,943

TOTAL CAPITAL WORKS PROGRAM 12,482 12,482 2,000 2,000 10,482 10,482 1,300 386 83 10,482 12,482 12,482

CANBERRA INSTITUTE OF TECHNOLOGY 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 70: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Funding ($'000)

2010-11 Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

Canberra Theatre Centre – Heating Ventilation and Air Conditioning and Hydraulics Works 125 125 0 0 125 125 9 3 0 125 125 125Sub-Total 125 125 0 0 125 125 9 3 0 125 125 125

2010-11 Capital Upgrades Program

Canberra Theatre Centre 176 212 0 0 176 212 18 9 0 212 212 212ACT Museums and Galleries 120 81 0 0 120 81 33 0 -1 81 81 81Historic Places/Cultural Facilities Corporation 38 41 0 0 38 41 0 0 0 41 41 41

Sub-Total 334 334 0 0 334 334 51 9 -1 334 334 334

Total New Works 459 459 0 0 459 459 60 12 -1 459 459 459

WORKS IN PROGRESS

Historic Places Major Project 3,683 3,683 1,494 1,289 1,227 1,370 195 92 -9 1,370 2,864 2,864Total Works in Progress 3,683 3,683 1,494 1,289 1,227 1,370 195 92 -9 1,370 2,864 2,864

TOTAL CAPITAL WORKS PROGRAM 4,142 4,142 1,494 1,289 1,686 1,829 255 104 -10 1,829 3,323 3,323

CULTURAL FACILITIES CORPORATION 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 71: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Project

Original Project Value ($'000)

Revised Project Value ($'000)

Prior Yr Expenditure

($'000)

Prior Yr Financing

($'000)

2010-11 Budgeted Financing

($'000)

2010-11Estimated

Expenditure ($'000)

ActualApr

($'000)

ActualMay

($'000)

ActualJune

($'000)

YTD Exp ($'000)

Total Financing

to Date ($'000)

Total Exp

to Date ($'000)

NEW CAPITAL WORKS

2010-11 Capital Upgrades Program

Power Upgrade of Campground 30 30 0 0 30 30 0 0 0 30 30 30Budawang Building Internal Linings and Window Treatment 180 180 0 0 180 180 0 0 0 180 180 180Trade Waste Modifications Stage 3 100 100 0 0 100 100 0 53 18 100 100 100Re-Wiring of Arena Light Poles 50 50 0 0 50 50 0 0 0 50 50 50Upgrade to Workshop 20 20 0 0 20 20 0 0 0 20 20 20Tree Planting and Shade Cloth Installation 80 80 0 0 80 80 4 0 0 80 80 80Terrace Room Upgrade to Entry and Carpet Replacement 40 40 0 0 40 40 0 0 0 40 40 40

Sub-Total 500 500 0 0 500 500 4 53 18 500 500 500

Total New Works 500 500 0 0 500 500 4 53 18 500 500 500

WORKS IN PROGRESS

Use of Non-Potable Water for Irrigation of The EPC Venue 2,500 2,500 0 0 2,500 892 5 54 114 361 892 361Installation of Electronic Billboard 60 60 0 0 60 60 0 0 55 55 60 55

Sub-Total 2,560 2,560 0 0 2,560 952 5 54 169 416 952 416

Total Works in Progress 2,560 2,560 0 0 2,560 952 5 54 169 416 952 416

TOTAL CAPITAL WORKS PROGRAM 3,060 3,060 0 0 3,060 1,452 9 107 187 916 1,452 916

EXHIBITION PARK CORPORATION 2010-11 CAPITAL WORKS PROGRAMFOR THE PERIOD ENDED 30/06/2011

Page 72: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT C

Variations to 2010-11 Capital Works Program

Page 73: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Chief Minister and Cabinet Directorate (CMCD)

Projects Transferred from TAMSRobertson House, Oaks Estate Restoration and Interpretation 165Tralee Homestead Restoration and Interpretation 165Heritage Signage including Aboriginal Campsite at Black Mountain Peninsula, Charnwood Homestead, Cricketers Arms Hotel, Emu Bank Homestead, George Henry Rottenberry’s Farmhouse, Kingston Guest House – Printers Quarters, Rosebud Apiary, Russell Hill Camp and Weetangera Homestead

100

Ginninderra Blacksmith’s Workshop Improvements 175Valley Homestead Ruins Upgrades 75Heritage Signs 71Heritage Signage – Acton Precinct 48Heritage 27Cargill’s Dairy Cottage, Causeway Restoration and Interpretation 150

Variations between the Capital Upgrade ProgramExternal Painting (118)Electrical Upgrades (60)Fire Systems Upgrades (100)Gorman House – Installation of a compliant grease trap 20Watson Arts Centre – Construction of storm water drainage 25Ainslie Arts Centre – Critical repairs to hydraulics 70Asbestos Management – All facilities – implementation of Management Plans 70Various Refurbishments and Upgrades 93

AA Project Transfers – To CSDExtension to the Street Theatre (Design) (120)Watson Arts Centre – Additional Studios and Residence (287)Strathnairn Homestead – Kitchen, Toilet and Veranda Improvements (100)Strathnairn Homestead – Additional Studio Space and Landscaping (10)Kingston Arts Precinct Strategy (150)Strathnairn Arts Centre – Bronze Foundry Workshop (100)Strathnairn Arts Centre – Landscaping (50)Public Art (2,375)Watson Arts Centre – Five Studios Forward Design (188)Manuka Arts Centre Landscape Works (225)Belconnen Arts and Cultural Centre (312)Public Art Scheme (1,340)

AA Project Transfers – To CSD – Capital Upgrade Program

External Painting at Arts Facilities 0 Electrical Upgrades at Arts Facilities 0 Upgrade of Fire Systems at Arts Facilities 0 Gorman House – Installation of a compliant grease trap (20)Watson Arts Centre – Construction of storm water drainage (25)Ainslie Arts Centre – Critical repairs to hydraulics (70)Asbestos Management at all facilities – Implementation of Management Plans (70)Various Refurbishments and Upgrades (93)artsACT (Prior Year CUP) (189)

AA Project Transfers – To ESDDHeritage Signs (71)Heritage Signage – Acton Precinct (48)

AA Project Transfers – To ESDD – Capital Upgrade Program

Robertson House, Oaks Estate Restoration and Interpretation (165)Cargill's Dairy Cottage, Causeway Restoration and Interpretation (150)Tralee Homestead Restoration and Interpretation (165)Heritage Signage including Aboriginal Campsite at Black Mountain Peninsula, Charnwood Homestead, Cricketers Arms Hotel, Emu Bank Homestead, George Henry Rottenberry’s Farmhouse, Kingston Guest House – Printers Quarters, Rosebud Apiary, Russell Hill Camp and Weetangera Homestead

(100)

Ginninderra Blacksmith’s Workshop Improvements (175)Valley Homestead Ruins Upgrades (75)Heritage (Prior Year CUP) (27)

AA Project Transfers – To EDDFloriade – Upgrade to Commonwealth Park (Design) (300)

Total Variation (6,024)

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

Page 74: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

Territory and Municipal Services Directorate (TAMS)

Project VariationsBonner Western Distributor Road and Sewer (2,000)Belconnen Skate Park 2,000Belconnen Town Centre – Cohen Street Extension and Replacement of Bus Interchange (245)Lake Ginninderra Foreshore Stage 2 (Emu Inlet Upgrade) 245Forde – Access Road and Trunk Sewer (73)Restoration of Hobday's Cottage and English Gardens 73Kings Highway Upgrade (765)Kings Highway Upgrade1 (8,735)Tharwa Bridge Foundation Works – Roads to Recovery Program1 4,235Flemington Road Bus Lanes – Roads to Recovery Program 765West Belconnen Intersection Improvements1 1,500Phillip and Majura Avenue Traffic Lights1 1,000Majura and Sutton Road Pavement Rehabilitation1 2,000Gungahlin Drive Extension – Stage 2 (3,800)Lawson South – Road Intersections 2,300Lawson – Ginninderra and Aikman Drives – Intersection Upgrade 1,000

Projects Transferred to EDDNorth Weston – Road Intersection Reconstruction (5,000)Coombs – Water Quality Control Ponds (7,000)Fyshwick – Intersection Upgrades – Gladstone Street, Section 26 (3,500)Barton – Intersection Upgrades – Darling Street, Section 22 (1,000)Forde – Horse Park and Gundaroo Drives Intersection Upgrade (4,000)Watson – Stormwater Upgrade – Aspinall Street Block 2, Section 95 (2,870)Transport for Canberra – Street Lighting in the City (1,000)City Action Plan Stage 1 – Edinburgh Avenue Improvements (200)City West Infrastructure Stage 3 (1,900)City Central Infrastructure Replacement – including Paving, Lighting, Bubblers and Street Furniture in various locations throughout Canberra’s Central Business District such as City Walk and Mort Street

(200)

Temporary Surface Car Park – Southern Loop Commonwealth Avenue (900)Canberra CBD Upgrade Program (1,767)Harrison – Wells Station Drive Extension to Horse Park Drive (6,895)Mitchell – Sandford Street Extension to the Federal Highway (6,998)Casey – Clarrie Hermes Drive Extension to the Barton Highway (8,234)

Projects Transferred to CMCDRobertson House, Oaks Estate Restoration and Interpretation (165)Tralee Homestead Restoration and Interpretation (165)Heritage Signage including Aboriginal Campsite at Black Mountain Peninsula, Charnwood Homestead, Cricketers Arms Hotel, Emu Bank Homestead, George Henry Rottenberry’s Farmhouse, Kingston Guest House – Printers Quarters, Rosebud Apiary, Russell Hill Camp and Weetangera Homestead

(100)

Ginninderra Blacksmith’s Workshop Improvements (175)Valley Homestead Ruins Upgrades (75)Heritage Signs (71)Heritage Signage – Acton Precinct (48)Heritage (27)Cargill’s Dairy Cottage, Causeway Restoration and Interpretation (150)

Commonwealth Funding (Nation Building Program)Upgrade of Airport Roads (30,000)Monaro Highway Duplication (Canberra Avenue – Newcastle Street) 18,500Upgrade of Airport Roads – Majura Parkway 9,500Majura Road Pavement Improvements 2,000

AA Project Transfers – To EDDGungahlin Leisure Centre (Design) 0 Lyneham Precinct Redevelopment Stage 3 (7)Throsby Multisport Complex (Design) (90)Gungahlin Wellbeing Precinct – Infratructure Works 0 Manuka Oval Facilities Upgrades (407)Grant for Development of a New Basketball Centre and Player Amenities (50)Gungahlin Enclosed Oval (Sports Complex) (811)Gungahlin Leisure Centre (28)Improvements to Griffith Oval (50)Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 0 Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 – GPO Funded 0 "Where Will we Play" Outdoor Facilities Water Reduction Strategies (1,070)Enclosed Oval within Crinigan Circle, Gungahlin (121)Harrison – District Playing Fields (367)Lyneham Sports Precinct Development – Stage 1 – GPO & CI (4,357)

Page 75: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

Motorsport Funding – Capital (103)Motorsport Funding – Investment Fund – GPO (500)Stromlo Forest Park – Landscape and Amenity Planning (13)

AA Project Transfers – To EDD – Capital Upgrade Program

Water Demand Management Program – Irrigation System Replacement/Renewal and Couch Grass Conversions at Dickson District and Kambah District Playing Fields

(1,000)

Canberra Stadium – Upgrade of Spectator Lighting, Control System and Wiring (100)Canberra Stadium – Replacement of Analogue Televisions (to digital) in all Corporate and Public Areas

(650)

AA Project Transfers – From EDDConservation Management Plans for Heritage Buildings (Feasibility) 400Remediation of Fuel Storage Facilities 500Refurbishment of Albert Hall 1,590Upgrade of Callam Offices 809

AA Project Transfers – From EDD – Capital Upgrade Program

Wanniassa Business Park – Upgrade Works and Energy Efficiency Initiatives 158Mitchell Depot – Sewerage Sleeving 200TAMS Visitors Centres – Condition Audit Upgrade Works and Studies 150Mitchell Depot (Building 3) – Installation of Lift 400Mount Rogers Community Centre – Skylights and Audit Works 200Magistrates Court – Condition Audit Upgrade Works 180Dame Pattie Menzies House – Condition Audit Upgrade Works 100Scollay St Offices – Condition Audit Upgrade Works 140Phillip Business Park – Building Upgrades and Refurbishment 100Smart Meter Installation and associated Electrical Works at Dickson Motor Vehicle Registry, 1 Moore Street Civic and North Building Civic

185

Fairfax Centre O'Connor – Demolition and Site Remediation 200Upgrades to Hotel Kurrajong 125North Building HVAC Works 150Fire Services Upgrades 191Civic Health Centre, Moore St – Carpet Replacement and Toilet Upgrades (Prior Year CUP) 182Climate Change Strategies – Installation of Solar Hot Water System (Dickson Motor Vehicle Registry), Water Collection and Reuse Systems (Fyshwick Depot) and Waterless Urinals at Government Owned Offices (Prior Year CUP)

466

Total Variation (56,238)

Economic Development Directorate (EDD)

Projects Transferred from TAMSNorth Weston – Road Intersection Reconstruction 5,000Coombs – Water Quality Control Ponds 7,000Fyshwick – Intersection Upgrades – Gladstone Street, Section 26 3,500Barton – Intersection Upgrades – Darling Street, Section 22 1,000Forde – Horse Park and Gundaroo Drives Intersection Upgrade 4,000Watson – Stormwater Upgrade – Aspinall Street Block 2, Section 95 2,870Transport for Canberra – Street Lighting in the City 1,000City Action Plan Stage 1 – Edinburgh Avenue Improvements 200City West Infrastructure Stage 3 1,900City Central Infrastructure Replacement – including Paving, Lighting, Bubblers and Street Furniture in various locations throughout Canberra’s Central Business District such as City Walk and Mort Street

200

Temporary Surface Car Park – Southern Loop Commonwealth Avenue 900Canberra CBD Upgrade Program 1,767Harrison – Wells Station Drive Extension to Horse Park Drive 6,895Mitchell – Sandford Street Extension to the Federal Highway 6,998Casey – Clarrie Hermes Drive Extension to the Barton Highway 8,234

Variations between the Capital Upgrade ProgramDame Pattie Menzies House – Condition Audit Upgrade Works (150)North Building HVAC Works 150Mitchell Depot – Improved Disability Access – Installation of LIft in Building 3 (Prior Year CUP) (191)Fire Services Upgrades 191

AA Project Transfers – From CMCDFloriade – Upgrade to Commonwealth Park (Design) 300

Project VariationsHarrison – Wells Station Drive Extension to Horse Park Drive 500

Page 76: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

AA Project Transfers – To TAMSConservation Management Plans for Heritage Buildings (Feasibility) (400)Remediation of Fuel Storage Facilities (500)Refurbishment of Albert Hall (1,590)Upgrade of Callam Offices (809)

AA Project Transfers – To TAMS – Capital Upgrade Program

Wanniassa Business Park – Upgrade Works and Energy Efficiency Initiatives (158)Mitchell Depot – Sewerage Sleeving (200)TAMS Visitors Centres – Condition Audit Upgrade Works and Studies (150)Mitchell Depot (Building 3) – Installation of Lift (400)Mount Rogers Community Centre – Skylights and Audit Works (200)Magistrates Court – Condition Audit Upgrade Works (180)Dame Pattie Menzies House – Condition Audit Upgrade Works (100)Scollay St Offices – Condition Audit Upgrade Works (140)Phillip Business Park – Building Upgrades and Refurbishment (100)Smart Meter Installation and associated Electrical Works at Dickson Motor Vehicle Registry, 1 Moore Street Civic and North Building Civic

(185)

Fairfax Centre O'Connor – Demolition and Site Remediation (200)Upgrades to Hotel Kurrajong (125)North Building HVAC Works (150)Fire Services Upgrades (191)Civic Health Centre, Moore St – Carpet Replacement and Toilet Upgrades (Prioir Year CUP) (182)Climate Change Strategies – Installation of Solar Hot Water System (Dickson Motor Vehicle Registry), Water Collection and Reuse Systems (Fyshwick Depot) and Waterless Urinals at Government Owned Offices (Prior Year CUP)

(466)

AA Project Transfers – From TAMSGungahlin Leisure Centre (Design) 0 Lyneham Precinct Redevelopment Stage 3 7Throsby Multisport Complex (Design) 90Gungahlin Wellbeing Precinct – Infratructure Works 0 Manuka Oval Facilities Upgrades 407Grant for Development of a New Basketball Centre and Player Amenities 50Gungahlin Enclosed Oval (Sports Complex) 811Gungahlin Leisure Centre 28Improvements to Griffith Oval 50Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 0 Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 – GPO Funded 0 "Where Will we Play" Outdoor Facilities Water Reduction Strategies 1,070Enclosed Oval within Crinigan Circle, Gungahlin 121Harrison – District Playing Fields 367Lyneham Sports Precinct Development – Stage 1 – GPO & CI 4,357Motorsport Funding – Capital 103Motorsport Funding – Investment Fund – GPO 500Stromlo Forest Park – Landscape and Amenity Planning 13

AA Project Transfers – From TAMS – Capital Upgrade Water Demand Management Program – Irrigation System Replacement/Renewal and Couch Grass Conversions at Dickson District and Kambah District Playing Fields

1,000

Canberra Stadium – Upgrade of Spectator Lighting, Control System and Wiring 100Canberra Stadium – Replacement of Analogue Televisions (to digital) in all Corporate and Public Areas

650

Total Variation 55,562

Justice and Community Safety Directorate (JACS)

Project VariationsNew Belconnen Police Station – Construction2 5,362

Total Variation 5,362

ACT Planning and Land Authority (ACTPLA)

Project VariationsLawson South – Water Quality Control Pond (Design) (200)Canberra Integrated Urban Water Program (230)John Gorton Drive Extension to Molonglo 2 and Group Centre 280Molonglo 2 Water Supply, Trunk Sewer and Stormwater Infrastructure 150

Page 77: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

AA Project Transfers – To ESDDLawson South – Relocation of Power Line (Design) (150)Lawson South – Water Quality Control Pond (Design) 0 Molonglo – Future Stormwater Management (Feasibility) (250)Molonglo – East-West Arterial Road and Extension of John Gorton Drive to Molonglo River (Feasibility)

(20)

Gungahlin Town Centre Roads (Feasibility) (300)Scrivener Dam Upgrade (Feasibility) (350)Woden Valley Stormwater Retardation Basins (Feasibility) (100)Symonston – Arterial Road (Feasibility) (100)John Gorton Drive Extension to Molonglo 2 and Group Centre (280)Molonglo 2 Water Supply, Trunk Sewer and Stormwater Infrastructure (150)East Lake – Environmental Site Assessment Phase 2 & 3 (77)Canberra Integrated Urban Water Program (207)Future Water Management Options – Molonglo River (258)Urban Development Sequence for Affordable Housing – Molonglo and North Weston (153)Urban Development Sequence for Affordable Housing – Environmental Impact Assessment Molonglo

(91)

Urban Development Sequence for Affordable Housing – Concept Plans Gungahlin (293)East Lake Sustainable Urban Renewal (363)Dickson Master Plan (2)Kingston Master Plan (3)Horse Park Drive Extension from Amaroo to Moncrieff Group Centre (50)Horse Park Drive Water Quality Control Pond (95)Mirrabei Drive Extension to Horse Park Drive (95)Kenny Water Quality Control Pond (80)

AA Project Transfers – To ESDD – Capital Upgrade Land Release Infrastructure Improvements – Roads, Paving, Fencing, Stormwater, Sewer, Water Supply and Landscaping

(334)

Total Variation (3,801)

Department of Environment, Climate Change, Energy and Water (DECCEW)

AA Project Transfers – To ESDDNorth Weston/Molonglo Stormwater Harvesting Scheme 0 Gungahlin – The Valley Ponds and Stormwater Harvesting Scheme 0 Accelerating Replacing Stormwater Drains with Wetlands (9,452)Renewable Energy Technology Showcase – West Belconnen Child and Family Centre (417)Renewable Energy Technology Showcase 0

Total Variation (9,869)

Environment and Sustainable Development Directorate (ESDD)

AA Project Transfers – From ACTPLALawson South – Relocation of Power Line (Design) 150Lawson South – Water Quality Control Pond (Design) 0 Molonglo – Future Stormwater Management (Feasibility) 250Molonglo – East-West Arterial Road and Extension of John Gorton Drive to Molonglo River (Feasibility)

20

Gungahlin Town Centre Roads (Feasibility) 300Scrivener Dam Upgrade (Feasibility) 350Woden Valley Stormwater Retardation Basins (Feasibility) 100Symonston – Arterial Road (Feasibility) 100John Gorton Drive Extension to Molonglo 2 and Group Centre 280Molonglo 2 Water Supply, Trunk Sewer and Stormwater Infrastructure 150East Lake – Environmental Site Assessment Phase 2 & 3 77Canberra Integrated Urban Water Program 207Future Water Management Options – Molonglo River 258Urban Development Sequence for Affordable Housing – Molonglo and North Weston 153Urban Development Sequence for Affordable Housing – Environmental Impact Assessment Molonglo

91

Urban Development Sequence for Affordable Housing – Concept Plans Gungahlin 293East Lake Sustainable Urban Renewal 363Dickson Master Plan 2Kingston Master Plan 3Horse Park Drive Extension from Amaroo to Moncrieff Group Centre 50Horse Park Drive Water Quality Control Pond 95Mirrabei Drive Extension to Horse Park Drive 95Kenny Water Quality Control Pond 80

AA Project Transfers – From ACTPLA – Capital Upgrade Program

Land Release Infrastructure Improvements – Roads, Paving, Fencing, Stormwater, Sewer, Water Supply and Landscaping

334

Page 78: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

AA Project Transfers – From CMCDHeritage Signs 71Heritage Signage – Acton Precinct 48

AA Project Transfers – From CMCD – Capital Upgrade Program

Robertson House, Oaks Estate Restoration and Interpretation 165Cargill's Dairy Cottage, Causeway Restoration and Interpretation 150Tralee Homestead Restoration and Interpretation 165Heritage Signage including Aboriginal Campsite at Black Mountain Peninsula, Charnwood Homestead, Cricketers Arms Hotel, Emu Bank Homestead, George Henry Rottenberry’s Farmhouse, Kingston Guest House – Printers Quarters, Rosebud Apiary, Russell Hill Camp and Weetangera Homestead

100

Ginninderra Blacksmith’s Workshop Improvements 175Valley Homestead Ruins Upgrades 75Heritage (Prior Year CUP) 27

AA Project Transfers – From DECCEWNorth Weston/Molonglo Stormwater Harvesting Scheme 0 Gungahlin – The Valley Ponds and Stormwater Harvesting Scheme 0 Accelerating Replacing Stormwater Drains with Wetlands 9,452Renewable Energy Technology Showcase – West Belconnen Child and Family Centre 417Renewable Energy Technology Showcase 0

Total Variation 14,646

Legislative Assembly

Variations between the Capital Upgrade ProgramBuilding Fabric Restoration (53)Occupational Health and Safety 53

Total Variation 0

Community Services Directorate (CSD)

Project VariationsYouth Detention Centre – Body Scanner (375)Expansion of the Baringa Childcare Centre 375Additional Childcare Places – Forward Design (30)National Partnership – Indigenous Early Childhood Development – Third Child and Family Centre 30Public Art Scheme (74)Public Art (51)artsACT – Capital Upgrade Program 56Various Refurbishments and Upgrades – Capital Upgrade Program 69

AA Project Transfers – From CMCDExtension to the Street Theatre (Design) 120Watson Arts Centre – Additional Studios and Residence 287Strathnairn Homestead – Kitchen, Toilet and Veranda Improvements 100Strathnairn Homestead – Additional Studio Space and Landscaping 10Kingston Arts Precinct Strategy 150Strathnairn Arts Centre – Bronze Foundry Workshop 100Strathnairn Arts Centre – Landscaping 50Public Art 2,375Watson Arts Centre – Five Studios Forward Design 188Manuka Arts Centre Landscape Works 225Belconnen Arts and Cultural Centre 312Public Art Scheme 1,340

Page 79: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment C

Variations to 2010-11 Capital Works Program

Agency DescriptionFinancial

Impact ($'000)

AA Project Transfers – From CMCD – Capital Upgrade Program

External Painting at Arts Facilities 0 Electrical Upgrades at Arts Facilities 0 Upgrade of Fire Systems at Arts Facilities 0 Gorman House – Installation of a compliant grease trap 20Watson Arts Centre – Construction of storm water drainage 25Ainslie Arts Centre – Critical repairs to hydraulics 70Asbestos Management at all facilities – Implementation of Management Plans 70Various Refurbishments and Upgrades 93artsACT (Prior Year CUP) 189

Total Variation 5,724

Health Directorate

Project VariationsClinical Services Redevelopment – Phase 2 (5,200)Women and Children's Hospital – Additional Funding2 3,500Provision for Project Definition Planning (2,710)New Multistorey Car Park TCH (2,280)Women and Children's Hospital 10,190

Total Variation 3,500

Cultural Facilities Corporation (CFC)

Variations between the Capital Upgrade ProgramACT Museums and Galleries (39)Canberra Theatre Centre 36Historic Places/Cultural Facilities Corporation 3

Total Variation 0

TOTAL VARIATIONS TO CAPITAL WORKS PROGRAM 8,862

MINUS APPROPRIATION ADJUSTMENTS TO FUTURE YEARS 8,862

TOTAL VARIATIONS TO 2010-11 CAPITAL WORKS PROGRAM 0

Notes: 1. Appropriation transfers to occur in 2011-12.2. Additional appropriation to be provided in 2011-12.

Page 80: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT D

2010-11 Underspends

Page 81: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment D

Agency Budgeted Rollovers $'000

Savings Identified

$'000

Future Year Savings

Identified $'000

Total Underspends

$'000

Territory and Municipal Services Directorate (TAMS)

Transport for Canberra – Belconnen to City Transitway Stage 1 (Barry Drive and College Street 283 0 0 283Transport for Canberra – Installation of Bus Shelters 389 0 0 389Transport for Canberra – Canberra Avenue Bus Priority Measures 51 0 0 51Transport for Canberra – Northbourne Avenue Bus Priority Measures and Dickson 12 0 0 12Transport for Canberra – Park and Ride Facilities 150 0 0 150Transport for Canberra – Gungahlin Town Centre Major Bus Station 67 0 0 67Transport for Canberra – Erindale Centre Major Bus Station 30 0 0 30Transport for Canberra – Bike and Ride Facilities 60 0 0 60Transport for Canberra – Belconnen to City Bus Transitway Alignment (Feasibility) 100 0 0 100Belconnen Skate Park (Design) 800 0 0 800Jerrabomberra Wetlands Infrastructure Improvements 138 0 0 138Gungahlin Leisure Centre (Design) 1,460 0 0 1,460Throsby Multisport Complex (Design) 410 0 0 410Extension of the Mugga Lane Resource Management Centre Landfill Cell 1,241 0 0 1,241Toilet Refurbishments at Molonglo Reach and Acton District Parks and the Hughes and Chisholm Shopping Centres

428 0 0 428

Hume – Lanyon Drive Upgrade – Stage 2 1,542 0 0 1,542Kings Highway Upgrade 3,846 0 0 3,846Upgrade of Airport Roads 3,731 0 0 3,731North-South Arterial Road for Molonglo Suburbs 10,271 0 0 10,271Town and District Park Upgrades 46 0 0 46Lake Ginninderra Foreshore Stage 2 (Emu Inlet Upgrade) 1,335 0 0 1,335The Sanctuary at Tidbinbilla – Stage 2 and Birrigai Outdoor School Development 1,496 0 0 1,496Grant for Development of a New Basketball Centre and Player Amenities 450 0 0 450Gungahlin Leisure Centre 972 0 0 972Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 – GPO Funded 3,750 0 0 3,750"Where Will we Play" Outdoor Facilities Water Reduction Strategies 2,474 0 0 2,474Lyneham Sports Precinct Development – Stage 1 – GPO & CI 1,500 0 0 1,500Remediation of West Belconnen Land Fill Borrow Pit 929 0 0 929West Belconnen Landfill Sullage Pit Remediation 45 0 0 45New Landfill for the ACT 215 0 0 215Motorsport Funding 200 0 0 200Bridge Strengthening on Commercial Routes 599 0 0 599Lake Ginninderra Community Path Lighting 102 0 0 102Strategic Bushfire Management Plan Version 23 365 0 0 365Playground Safety Program – Upgrade of Open Space Playground Assets in various Suburbs, including Gowrie, Weston, Chapman, Kaleen, Macarthur, Greenway, Florey, Belconnen and Chifley

110 0 0 110

Lyneham Precinct Redevelopment Stage 3 2,093 0 0 2,093Gungahlin Enclosed Oval (Sports Complex) 153 0 0 153Enclosed Oval within Crinigan Oval, Gungahlin 100 0 0 100Gungahlin Canberra Connect Shopfront (Feasibility) 0 41 0 41

Sub Total 41,943 41 0 41,984

AccelerationsTransport for Canberra – Cotter Road Improvements (59) 0 0 (59)Transport for Canberra – ACT Road Safety Strategy (Design) (76) 0 0 (76)Page and Fyshwick Stormwater Augmentation (2,000) 0 0 (2,000)Lawson – Ginninderra and Aikman Drives – Intersection Upgrade (700) 0 0 (700)Restoration of Tharwa Bridge (1,700) 0 0 (1,700)Gungahlin Drive Extension – Stage 2 (20,309) 0 0 (20,309)Forde – Mulligans Flat Road Extension and Water Quality Control Pond (5,000) 0 0 (5,000)Bonner – Western Distributor Road and Sewer (2,925) 0 0 (2,925)Monaro Highway Duplication (Canberra Ave to Newcastle Street) (663) 0 0 (663)North Weston Pond and Bridge (2,479) 0 0 (2,479)Lyneham Precinct – Regional Tennis and Sports Centre – Stage 2 (17) 0 0 (17)

Sub Total (35,928) 0 0 (35,928)

Total 6,015 41 0 6,056

Economic Development Directorate (EDD)

Coombs – Water Quality Control Ponds 400 0 0 400Fyshwick – Intersection Upgrades – Gladstone Street, Section 26 2,200 0 0 2,200Barton – Intersection Upgrades – Darling Street, Section 22 350 0 0 350Mitchell – Sandford Street Extension to the Federal Highway 6,600 0 0 6,600Casey – Clarrie Hermes Drive Extension to the Barton Highway 1,175 0 0 1,175Government Office Accommodation and Relocation Fitout 6,700 0 0 6,700North Weston – Road Intersection Reconstruction 2,000 0 0 2,000Forde – Horse Park and Gundaroo Drives Intersection Upgrade 1,150 0 0 1,150Watson – Stomrwater Upgrade – Aspinall Street Block 2, Section 95 520 0 0 520Temporary Surface Car Park – Southern Loop Commonwealth Avenue 900 0 0 900

Total 21,995 0 0 21,995

Treasury Directorate

Whole of Government – Asset Management and Capital Delivery Planning 1,000 0 0 1,000Government Office Building – Project Advice 1,000 0 0 1,000ACT Government Office Project – Procurement Planning and Documentation 0 1,360 0 1,360

Total 2,000 1,360 0 3,360

2010-11 Capital Works Underspends

Page 82: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment D

Agency Budgeted Rollovers $'000

Savings Identified

$'000

Future Year Savings

Identified $'000

Total Underspends

$'000

2010-11 Capital Works Underspends

Health Directorate

Upgrade of Mechanical Systems 284 0 0 284Workplace Improvements 100 0 0 100TCH Discharge Lounge Relocation 50 0 0 50Clinical Services Redevelopment – Phase 2 14,600 0 0 14,600National Health Reform 9,204 562 2,795 12,561Integrated Capital Region Cancer Centre – Phase 1 2,000 0 0 2,000Enhanced Community Health Centre – Belconnen 4,969 0 0 4,969Mental Health Young Persons Unit 589 0 0 589ACT Health Skills Development Centre 1,000 0 0 1,000Adult Mental Health Inpatient Facility 5,931 0 0 5,931Women and Children's Hospital 9,613 0 0 9,613New Gungahlin Health Centre 6,073 0 0 6,073Refurbishment of Existing Health Centre – Tuggeranong 2,900 0 0 2,900Provision for Phase 1 CSR 3,000 0 0 3,000Aboriginal Torres Strait Islander Residential Alcohol & Other Drug Rehabilitation Facility 2,362 0 0 2,362Linear Accelerator Procurement and Replacement 375 0 0 375Secure Adult Mental Health Unit 0 1,000 10,160 11,160

Total 63,050 1,562 12,955 77,567

Justice and Community Safety Directorate (JACS)

Tidbinbilla Rural Fire Service Shed 1,362 0 0 1,362New Supreme Court – Forward Design 3,800 0 0 3,800Alexander Maconochie Centre – Chapel and Quiet Place 0 406 0 406New Forensic Medical Centre 1,000 0 0 1,000New Belconnen Police Station – Construction 6,953 0 0 6,953Emergency Services Agency – New Headquarters 350 0 0 350Alexander Maconochie Centre 2,050 0 0 2,050

Total 15,515 406 0 15,921

Environment and Sustainable Development Directorate (ESDD)

North Weston/Molonglo Stormwater Harvesting Scheme 1,000 0 0 1,000Gungahlin – The Valley Ponds and Stormwater Harvesting Scheme 1,000 0 0 1,000Accelerating Replacing Stormwater Drains with Wetlands 3,703 0 0 3,703Lawson South – Relocation of Power Line (Design) 150 0 0 150Lawson South – Water Quality Control Pond (Design) 0 0 100 100Molonglo – Future Stormwater Management (Feasibility) 200 0 0 200Molonglo – East-West Arterial Road and Extension of John Gorton Drive to Molonglo River 230 0 0 230Woden Valley Stormwater Retardation Basins (Feasibility) 50 0 0 50Canberra Integrated Urban Water Program 163 0 (230) (67)Symonston – Arterial Road (Feasibility) 100 0 0 100East Lake Sustainable Urban Renewal 150 0 0 150Urban Development Sequence for Affordable Housing – Environmental Impact Assessment Molonglo 60 0 0 60

Total 6,806 0 (130) 6,676

Education and Training Directorate (ETD)

Bonner Primary School (Design) 400 0 0 400Molonglo Primary School (Design) 750 0 0 750Franklin Early Childhood School (Design) 200 0 0 200Red Hill Primary School Expansion 3,600 0 0 3,600Building Refurbishment and Upgrades 2,823 0 0 2,823Harrison High School 3,500 0 0 3,500Canberra College (Woden Campus) Performing Arts Theatre 1,000 0 0 1,000Trade Training Centres 1,659 0 120 1,779

Sub Total 13,932 0 120 14,052

AccelerationsPublic Schools – Water Tanks (400) 0 0 (400)Kambah P-10 (7,000) 0 0 (7,000)

Sub Total (7,400) 0 0 (7,400)

Total 6,532 0 120 6,652

Community Services Directorate (CSD)

Flynn Childcare Centre 2,000 0 0 2,000Tuggeranong 55 Plus Club 500 0 0 500Forde Community Centre 352 0 0 352Watson Arts Centre – Additional Studios and Residence 460 0 0 460Strathnairn Homestead – Additional Studio Space and Landscaping 90 0 0 90Public Art Scheme 2,523 0 0 2,523Extension to the Street Theatre (Design) 30 0 0 30Manuka Arts Centre Landscape Works 18 0 0 18

Total 5,973 0 0 5,973

Page 83: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

Attachment D

Agency Budgeted Rollovers $'000

Savings Identified

$'000

Future Year Savings

Identified $'000

Total Underspends

$'000

2010-11 Capital Works Underspends

Exhibition Park Corporation (EPC)

Use of Non-Potable Water for Irrigation of the EPC Venue 1,608 0 0 1,608

Total 1,608 0 0 1,608

ACT Legislative Assembly

Lift Upgrade 0 74 0 74Improved Environmental Measures (CUP 2009-10) 0 14 0 14Building Fabric Restoration (CUP 2010-11) 0 52 0 52

Total 0 140 0 140

TOTAL CAPITAL WORKS UNDERSPENDS 129,494 3,509 12,945 145,948

Page 84: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT E

2010-11 End of Year Acquittals

Page 85: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT E

Approved Final SavingsBudget Expenditure Returned

2010-11$'000 $'000 $'000

Legislative Assembly

Building Fabric Restoration 2010-11 Capital Upgrades 40 39 1Building Plant Replacement 2010-11 Capital Upgrades 8 6 2Occupational Health and Safety 2010-11 Capital Upgrades 105 85 20Improved Environmental Measures 2010-11 Capital Upgrades 17 17 0Lift Upgrade Construction 211 211 0Improved Environmental Measures 2009-10 Capital Upgrades Program 54 54 0

Territory and Municipal Services Directorate

Transport for Canberra – Barton Major Bus Station (Feasibility) Feasibility 100 100 0Page and Fyshwick Stormwater Augmentation Construction 3,008 3,008 0Naas Road – Gugenby Bridge (Design) Forward Design 200 200 0Ashley Drive Upgrade (Feasibility) Feasibility 150 128 22Narrabundah Ball Park Facility Upgrade Construction 1,050 1,050 0ACTION – Depot Upgrades (Feasibility) Feasibility 151 151 0Gungahlin Canberra Connect Shopfront (Feasibility) Feasibility 59 59 0Pavement Rehabilitation – Selected Failed Pavement Sections of Northbound Lanes of Northbourne Avenue

2010-11 Capital Upgrades 1,252 1,252 0

Road Barrier Improvements – Upgrading Selected High Priority Barriers and Bridge Railings at various locations along Belconnen Way and Hindmarsh Drive

2010-11 Capital Upgrades 165 165 0

Infill Lighting on Major Arterial Roads (Isabella Drive/Clive Steele Avenue Roundabout and Ginninderra Drive)

2010-11 Capital Upgrades 216 216 0

Road Safety Improvements Linked with the Road Safety Action Plan and Traffic Light Asset Management Plan – Work will take place at the Intersection of Hindmarsh and Melrose Drives

2010-11 Capital Upgrades 272 272 0

Traffic Light Upgrades – Corner of Hindmarsh and Melrose Drives 2010-11 Capital Upgrades 107 107 0Design of Road Safety Measures in line with the New Road Safety Strategy and the Vision Zero Philosophy at various locations across the ACT Road Network

2010-11 Capital Upgrades 250 250 0

Stormwater Augmentation Program – Stormwater Improvements in Chapman and other Sites flooded during the December 2006 and February 2007 Major Storms

2010-11 Capital Upgrades 3,010 3,005 5

Stormwater Improvement Program – Upgrade Works at Sites selected from previous Studies in Duffy, Forrest and Chapman

2010-11 Capital Upgrades 451 451 0

Upgrade to Stormwater Infrastructure at Lake Ginninderra Foreshore 2010-11 Capital Upgrades 655 655 0Footpath Improvements – Construction of High Priority Footpaths in Yarralumla, Narrabundah, Evatt, Curtin, Mawson, Lyneham, Hawker, Mitchell, and various Other Suburbs

2010-11 Capital Upgrades 379 379 0

Infill Lighting in Neighbourhood Developments, including Pathway Lighting in Macquarie and Upgrade of various Pedestrian Crossings in Lyneham

2010-11 Capital Upgrades 211 211 0

Installation of Energy Efficient Lighting in Kambah, Monash, Wanniassa, Rivett and Narrabundah to Reduce the Power Usage of the Street Light Network

2010-11 Capital Upgrades 513 504 9

Replacement of Old Street Light Cables – Various Inner North and South Locations 2010-11 Capital Upgrades 379 379 0Traffic Management Improvement at various Schools (Monash, North Ainslie and Turner Primary and Preschools, Campbell High School, St Thomas Mores Primary School, Majura and Forrest Primary Schools and the Blue Gum Community School)

2010-11 Capital Upgrades 210 210 0

Residential Street Improvements at various locations and investigation of Traffic Management Needs on Streeton Drive in Weston, Copland Drive in Belconnen and Sternberg Crescent in Wanniassa

2010-11 Capital Upgrades 159 159 0

Foreshore Upgrades from Sullivan’s Creek Bridge to the National Museum of Australia and from Dunrossil

2010-11 Capital Upgrades 200 200 0

Canberra Nara Peace Park – Naming and Wall Signage 2010-11 Capital Upgrades 29 29 0Facility Improvement Program – Upgrades to Ageing Infrastructure at Dickson Water Park, Manuka Pool and Kaleen Enclosed Oval

2010-11 Capital Upgrades 1,604 1,604 0

Territory Records Office – Installation of New Industrial De-humidifiers 2010-11 Capital Upgrades 20 20 0Replacement of Shopfront and Contact Centre Equipment 2010-11 Capital Upgrades 25 15 10OH&S Upgrades – Various Contact Centres and Shopfronts 2010-11 Capital Upgrades 30 30 0Bus Stop Disability Improvements – Upgrade of Selected Bus Stops to meet Disability Standards, including provision of seating where appropriate. Works will be undertaken on Bus Routes in Gordon, Kambah, Greenway, Flynn, Charnwood, Scullin, Florey, Latham, and Fraser

2010-11 Capital Upgrades 381 381 0

West Belconnen Resource Management Centre – Decommissioning Program to achieve Sustainable Environmental and Hydrological Outcomes and Minimise Ongoing Costs

2010-11 Capital Upgrades 501 501 0

Upgrades to Existing Recycling Drop Off-Centres in Belconnen Town Centre, West Belconnen, Mitchell, Phillip, Tuggeranong and Mugga Lane

2010-11 Capital Upgrades 150 150 0

Replacement of Ticket Machines on Buses 2010-11 Capital Upgrades 183 183 0Driver Seats – Upgrade and Replacement in Line with OH&S Requirements 2010-11 Capital Upgrades 150 150 0Bus Engine Overhauls – Additional Engine Rebuilds 2010-11 Capital Upgrades 461 461 0Canberra Stadium – Upgrade and Replacement of Infrastructure containing Asbestos 2010-11 Capital Upgrades 301 301 0Flemington Road Bus Lanes – Roads to Recovery Construction 3,665 3,638 27Barry Drive Bus Lanes – Roads to Recovery Program Construction 4,500 4,500 0Gungahlin College Precinct – Offsite Works Construction 8,530 8,530 0Majura Road Pavement Improvements Construction 2,000 2,000 0Upgrade of Tharwa Drive – Stage 1 Construction 11,000 10,979 21Flemington Road Duplication Construction 20,000 19,981 19Belconnen Town Centre – Cohen Street Extension and Replacement of Bus Interchange Construction 23,205 23,195 10Community Paths Program – Jerrabomberra Wetlands and Nature Reserve Construction 900 838 62Park 'n' Ride and Bike 'n' Ride Facilities in Erindale and Mitchell Feasibility 120 120 0Covered Barbeques Construction 100 99 1New Dog Park Construction 250 249 1Mulligans Flat Signage and Paths Construction 101 101 0Establishment of Regional Community Facilities and Neighbourhood Halls Construction 2,404 2,404 0Establishment of New Nature Reserves Construction 948 910 38Glebe Park Pavement Replacement 2008-09 Local Initiatives Package 1,600 1,543 57Bruce – Braybrooke Street Extension Construction 4,550 4,527 23Woden Town Centre – Wilbow and Easty Streets Infrastructure Construction 3,502 3,502 0Forde – Access Road and Trunk Sewer Construction 1,630 1,630 0Master Plan for West Belconnen Landfill Feasibility 120 97 23Master Plan for Mugga Lane Resource Management Plan Feasibility 120 119 1Bill Poster Silos to City and District Shopping Centres 2008-09 Local Initiatives Package 400 400 0Road Safety Message Signs 2008-09 Local Initiatives Package 401 401 0Heritage 2008-09 Capital Upgrades 52 52 0Canberra Stadium – Upgrade Handrails to Comply with New Building Codes 2009-10 Capital Upgrades 75 75 0Urban Landscape and Built Asset Improvements 2007-08 Capital Upgrades 2,115 2,114 1

Project Type

Capital Works Program2010-11

End of Year Acquittal

Physically and Financially Completed Projects

Projects Physically and Financially Completed

Page 86: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT E

Approved Final SavingsBudget Expenditure Returned

2010-11$'000 $'000 $'000

Project Type

Capital Works Program2010-11

End of Year Acquittal

Physically and Financially Completed Projects

Projects Physically and Financially Completed

Street and Park Trees Removal and Plantings 2007-08 Capital Upgrades 330 330 0Shopping Centre Improvements 2007-08 Capital Upgrades 3,250 3,249 1Parks and Reserves – Improvements to Playgrounds, Recreational Amenities and Tracks 2007-08 Capital Upgrades 2,451 2,451 0Urban Open Space 2007-08 Capital Upgrades 1,343 1,341 2Local Shopping Precincts Upgrades 2008-09 Capital Upgrades 1,370 1,368 2City Centre Infrastructure Upgrades 2008-09 Capital Upgrades 331 331 0Playground Safety Program – Upgrade of Open Space Playground Assets to Meet Current Australian Standards

2009-10 Capital Upgrades 914 914 0

Tree Replacement Program – Locations in the Inner North and Inner South Regions 2009-10 Capital Upgrades 152 152 0Toilet Refurbishment 2009-10 Capital Upgrades 100 100 0Landscape Upgrade Works Across Canberra, including Barbecues, Park and Street Furniture in Open Space and Shopping Centres, Shrub Beds and Bollards

2009-10 Capital Upgrades 210 210 0

City Central Infrastructure Replacement, including Paving, Lighting and Street Furniture 2009-10 Capital Upgrades 488 488 0Construction Projects – Upgrade of Lyons Local Shopping Centre 2009-10 Capital Upgrades 300 292 8Facilities Improvements – Provides for Upgrades to Aging Infrastructure, Irrigation Systems, Pavilions and

2009-10 Capital Upgrades 1,560 1,560 0

CCTV at Bus Interchanges – Continue Upgrade and Implementation Program 2009-10 Capital Upgrades 790 790 0Restoration of Hobday's Cottage and English Gardens Construction 273 273 0

Economic Development Directorate

Floriade – Upgrade to Commonwealth Park (Design) Forward Design 300 296 4Manuka Oval Facilities Upgrades Construction 407 407 0Canberra Stadium – Upgrade of Spectator Lighting, Control System and Wiring 2010-11 Capital Upgrades 101 101 0Canberra Stadium – Replacement of Analogue Televisions (to digital) in all Corporate and Public Areas 2010-11 Capital Upgrades 650 650 0Upgrade and Expand the Woden Gymnastics Club Construction 550 550 0Mitchell Depot – Improved Disability Access – Installation of Lift in Building 3 2009-10 Capital Upgrades 24 24 0Arts Organisation Relocation Construction 600 600 0Stromlo Forest Park – Landscape and Amenity Planning Construction 229 227 2

Treasury Directorate

ACT Government Office Project – Procurement Planning and Documentation Feasibility 1,740 1,301 439

Health Directorate

Building Upgrades 2010-11 Capital Upgrades 556 556 0Improvements to OH&S and Fire and Safety Systems 2010-11 Capital Upgrades 355 354 1Upgrade of Mechanical Systems 2010-11 Capital Upgrades 540 540 0Additional Beds Construction 2,400 2,400 0Intensive Care Unit – Calvary Construction 11,410 11,410 0Adult Acute Mental Health Inpatient Unit – Forward Design Forward Design 2,290 2,290 0Fire Systems Upgrade (Phase 1) TCH Construction 2,600 2,600 0Electrical, Plumbing, Floor Coverings and Air-Conditioning Upgrades (Stage 1) 2009-10 Capital Upgrades 225 225 0Energy Savings and Sustainability Works 2009-10 Capital Upgrades 305 305 0Safety Upgrades 2009-10 Capital Upgrades 325 324 1Refurbishment of Non-Clinical Accommodation at TCH 2009-10 Capital Upgrades 292 290 2Address Building Condition and Asbestos Audit Requirements 2009-10 Capital Upgrades 380 379 1TCH Upgrades to Ambulatory Areas, Intensive Care Facilities, Pathology Laboratories and ED 2009-10 Capital Upgrades 533 533 0Workplace Redesign to Meet Accommodation and OH&S Standards 2009-10 Capital Upgrades 290 290 0Improved Patient Amenity – Calvary 2009-10 Capital Upgrades 150 150 0Infrastructure Improvements (Various) – Calvary 2009-10 Capital Upgrades 230 230 0Occupational Health and Safety Upgrades (Various) – Calvary 2009-10 Capital Upgrades 312 312 0Equipment Loans Scheme Relocation 2008-09 Capital Upgrades 620 620 0

Justice and Community Safety Directorate

Additional Jury Courtroom Construction 450 447 3ACT Policing Facilities 2010-11 Capital Upgrades 222 222 0Departmental Projects 2009-10 Capital Upgrades 706 691 15Emergency Services Agency Projects 2009-10 Capital Upgrades 271 271 0Alexander Maconochie Centre – Chapel and Quiet Place Construction 96 96 0Emergency Services Agency – Stations Relocation Design Forward Design 529 529 0Alexander Maconochie Centre – Transitional Costs (STRC Reconfiguration) Construction 900 900 0Emergency Services Agency – Station Upgrades Construction 831 831 0Disability Access and Accommodation Improvements Construction 200 91 109

Education and Training Directorate

National Partnership – Nation Building and Jobs Plan – Building the Education Revolution Construction 150,523 150,523 0Transportable Classrooms 2009-10 Capital Upgrades 774 774 0

Environment and Sustainable Development Directorate

Scrivener Dam Upgrade Feasibility 350 58 292Land Release Infrastructure Improvements – Roads, Paving, Fencing, Stormwater, Sewer, Water Supply and Landscaping

2010-11 Capital Upgrades 334 319 15

East Lake – Environmental Site Assessment Phase 2 & 3 Feasibility 400 385 15Future Water Management Options – Molonglo River Feasibility 500 500 0Urban Development Sequence for Affordable Housing – Molonglo and North Weston Feasibility 650 650 0Dickson Master Plan Feasibility 110 110 0Kingston Master Plan Feasibility 200 200 0Mirrabei Drive Extension to Horse Park Drive Forward Design 300 300 0Heritage Signage – Acton Precinct Construction 50 50 0Heritage 2008-09 Capital Upgrades 150 150 0Renewable Energy Technology Showcase Construction 583 583 0

Page 87: 2010-11 CAPITAL WORKS PROGRAM June Outcome Report › documents › 2010-11 Capital... · 2.4.2 Preliminary Sketch Plans ... – the Surgical Assessment and Planning Unit and Neurosurgery

ATTACHMENT E

Approved Final SavingsBudget Expenditure Returned

2010-11$'000 $'000 $'000

Project Type

Capital Works Program2010-11

End of Year Acquittal

Physically and Financially Completed Projects

Projects Physically and Financially Completed

Community Services Directorate

Expansion of the Baringa Childcare Centre Construction 375 304 71National Partnership – Pensioner Transport Concessions Construction 31 31 0Establishment of Regional Community Facilities and Neighbourhood Halls Construction 27,250 27,250 0Tuggeranong 55 Plus Club – Forward Design Forward Design 200 200 0Additional Childcare Places – Forward Design Forward Design 405 394 11Kingston Arts Precinct Strategy Construction 150 145 5Gorman House – Installation of a compliant grease trap 2010-11 Capital Upgrades 20 20 0Watson Arts Centre – Construction of storm water drainage 2010-11 Capital Upgrades 25 25 0Ainslie Arts Centre – Critical repairs to hydraulics 2010-11 Capital Upgrades 70 70 0Asbestos Management at all facilities – Implementation of Management Plans 2010-11 Capital Upgrades 70 70 0Various Refurbishments and Upgrades 2010-11 Capital Upgrades 162 162 0Strathnairn Arts Centre – Landscaping Construction 50 50 0Public Art Construction 2,349 2,349 0artsACT 2009-10 Capital Upgrades 327 327 0Belconnen Arts and Cultural Centre Construction 8,141 8,057 84

Housing ACT

Refurbish Early Morning Drop-in Centre in the City Construction 750 750 0National Partnership – Social Housing Construction 6,439 6,439 0

Canberra Institute of Technology

New CIT Learning Centre Tuggeranong Feasibility 250 250 0Bruce – Refurbishment of Canberra Raiders Training Facility Forward Design 65 65 0Health and Safety Improvements 2010-11 Capital Upgrades 470 470 0Energy Management/Educational Improvements 2010-11 Capital Upgrades 880 880 0Building Improvements 2010-11 Capital Upgrades 874 874 0Electrotechnology Program Relocation Construction 9,943 9,943 0

Cultural Facilities Corporation

Canberra Theatre Centre – Heating Ventilation and Air Conditioning and Hydraulics Works Construction 125 125 0Canberra Theatre Centre, ACT Museums and Galleries and Historic Places/Cultural Facilities Corporation 2010-11 Capital Upgrades 334 334 0

Exhibition Park Corporation

Power Upgrade of Campground 2010-11 Capital Upgrades 30 30 0Budawang Building Internal Linings and Window Treatment 2010-11 Capital Upgrades 180 180 0Trade Waste Modifications Stage 3 2010-11 Capital Upgrades 100 100 0Re-Wiring of Arena Light Poles 2010-11 Capital Upgrades 50 50 0Upgrade to Workshop 2010-11 Capital Upgrades 20 20 0Tree Planting and Shade Cloth Installation 2010-11 Capital Upgrades 80 80 0Terrace Room Upgrade to Entry and Carpet Replacement 2010-11 Capital Upgrades 40 40 0

Shared Services Centre

Data Management Scoping Study – Current and Future Data Requirements (Feasibility) Feasibility 250 250 0Record Services Mitchell Accommodation – Refurbishment Construction 3,114 3,088 26

TOTAL 374,729 373,267 1,462